Answers Assignment - DMBA206 - MBA 2 - Set 1 and 2 - Feb-March 2024
Answers Assignment - DMBA206 - MBA 2 - Set 1 and 2 - Feb-March 2024
Usually, the first two types of organisational structures are found in military form of
organisations and conventional business houses respectively, where joint family system of
business exists. They are inappropriate for the modern multinational organisations and also
do not fit in to the bill for any project environment. Thus the discussion will be confined to
the remaining two types of organisation structures in this section namely functional structures
and project/matrix structures.
1. Functional-type organisation
The functional type structure organises teams of employees based upon the specific jobs
within the organisation. The employees work in departments based on what they have to
do such as marketing department, purchasing department, maintenance department, HR
department and finance department.
Examples of functional-type organisation
Car manufacturing companies
Electronics manufacturing units
Brick kilns
Hospitals
Hospitality units
2. Project-type organisation
3. Matrix-type organisation
Activities and events are used to construct network diagram An activity is a specific task, job,
or function to be carried out in a project. For example, 'prepare dinner' (see above Figure) is
an activity. An activity is symbolised by an arrow. The head of the arrow depicts the
completion of the activity and the tail of the arrow depicts its beginning. (There is no
significance of length and 'compass' direction of the arrow.) The event is a specific point in
time Representing the beginning or end of one or more activities. It stands for a milestone
and does not consume time or resources. It is essential to detail all the activities of the project
because activities are the basic building blocks of a network diagram. For this reason, it is
useful to break the project into some steps. The number of steps in a project depends upon its
magnitude and complexity. For industrial projects, usually, a two-step procedure is sufficient.
In the primary step, there is identification of major parts of the project and in the next step the
activities of each major part are defined. Activities must be so defined that they are distinct,
logically uniform tasks for which time and resource requirement can be estimated.
Illustration
A building project consists of the following activities:
A = Lay foundation
B = Erect framework
C= Install millwork
D = Install wiring
E = Install plumbing
F = Plaster walls
G = Install siding
H= Decorate the interior
I = Finish the exterior
The interrelationship among these activities is as follows:
A should precede B.
B should precede C, D, E, F, and G.
C, D, E, and F should precede H.
G should precede I
Given the above interrelationship the network diagram for the project is developed in several
steps using the forward method as shown in figure given above.
Benefits of Scheduling
One biggest benefit of scheduling is predictability. A scheduling system makes everyone’s job
easier by adding predictability to the AIS environment. To your superiors, it provides a means
of holding down costs through better use of personnel and equipment. Other possible benefits
of scheduling areas are:
Process change-over reduction
Inventory reduction, levelling
Reduced scheduling effort
Increased production efficiency
Labour load levelling
Accurate delivery date quotes
Real-time information
Assists with tracking, reporting, and communicating progress
Ensures everyone is on the same page with tasks, dependencies, and deadlines
Highlights issues and concerns, such as a lack of resources
Identifies task relationships
Monitors progress and identify issues early
Assignment Set- 2