Volume 2 Part 3
Volume 2 Part 3
TENDER DOCUMENTS
VOLUME 2 PART 3
PARTICULAR SPECIFICATIONS
EMPLOYER المـــالك
Roads Department إدارة الطرق
Roads & Transport Authority هـيئـة الطرق والمواصــالت
P.O. Box 118899 118899 :صندوق البريد
Dubai, U.A.E اإلمارات العربية المتحدة-دبي
TENDER DOCUMENTS
GENERAL INDEX
VOLUME 2 – PART 3
PARTICULAR SPECIFICATION
CONTENTS
-1-
SUB – SECTION DESCRIPTION PAGE
5/34 FASTENING FOR ALUMINIUM PARAPETS 5
5/35 PAINT & OTHER PROTECTIVE COATINGS 6
5/36 WATERPROOFING MEMBRANE FOR STRUCTURES 7
5/37 RUBBEERISED BITUMEN EMULSION 9
5/38 WATERSTOPS 9
5/39 PREFORMED JOINT FILLERS 10
5/40 COLD APPLIED JOINT SEALANT 10
5/41 BRIDGE DECK EXPANSION JOINT 10
5/42 LOCKABLE MEDIAN BOLLARD 11
5/43 SPECIAL COATING SYSTEM FOR THE PROTECTION 11
OF EXPOSED CONCRETE SURFACES
5/44 BRIDGE BEARING (NEW CLAUSE) 13
5/45 BEDDING MORTAR (NEW CLAUSE) 26
5/46 GRP KIOSK 27
5/48 REINFORCED FILL RETAINING WALL 28
5/57 PARTICULAR SPECIFICATIONS FOR HIGH DURABLE
ROADMARKING/ RED COATING 34
5/58 FLEXIBLE RUBBER BOLLARD 37
5/59 HYDRAULIC PRESSED (WET MIX)
TILES FOR CYCLE TRACK 38
5/60 METALWORK AND GLAZING 40
-2-
SUB – SECTION DESCRIPTION PAGE
8/11 DRILLING FLUID 8
8/12 PLACING CONCRETE 10
8/13 EXTRACTION OF CASING 12
8/14 TEMPORARY BACKFILLING 14
8/15 DISPOSAL OF EXCAVATED MATERIAL 14
8/16 CUTTING OFF PILE HEADS 14
8/17 INTEGRITY TESTING OF PILES 14
8/18 LOADING TESTS 15
8/19 FAILURE OF PILE 16
8/20 RECTIFICATION OF FAILURE 17
8/21 PROTECTION OF PILING FROM CHEMICAL ATTACK 17
8/22 CLEARANCE OF WORKS 17
-3-
SUB – SECTION DESCRIPTION PAGE
12/8 WORKMANSHIP STANDARDS FOR THE SURFACE
PREPARATION OF COATED STEEL WORK BY BLAST
CLEANING, ABRADING, GRINDING AND CLEANING 14
12/9 PAINTS AND SIMILAR PROTECTIVE COATING 15
12/10 TESTINF OF PAINTS 16
12/11 METAL COATING 17
12/12 TESTING OF METAL SPRAY COATING 18
12/13 STORAGE REQUIREMENTS AND KEEPING PERIODS
FOR PAINTS 19
12/14 APPLICATION OF PAINT 20
12/15 STORAGE AND TRANSPORT OF STEEL AND
FABRICATED STEEL WORK 23
12/16 SURFACE IN CONTRACT WITH CONCRETE 23
12/17 REQUIREMENTS FOR APPROVAL 24
12/18 ACCESS AND LIGHTING 24
12/19 ANTI – SLIP SURFACE DRESSING 24
-4-
SUB – SECTION DESCRIPTION PAGE
-5-
SUB – SECTION DESCRIPTION PAGE
14/2.21 WATER FLOW SWITCHES 17
14/2.22 SPRINKLER AND STANDPIPE VALVE
SUPERVISORY SWITCHES 17
14/2.23 COLOR TOUCHSCREEN REMOTE LCD
ANNUNCIATOR 18
14/2.24 CAUTION AND ADVISORY SIGN 18
14/2.25 SYSTEM AND CONTROL WIRING 18
14/3 PART 3 – TESTING AND DOCUMENTS 19
14/3.1 SYSTEM INSPECTION AND CHECK OUT 19
14/3.2 TRAINING REQUIREMENTS 19
14/3.3 OPERATION AND MAINTENANCE 20
14/3.4 AS-BUILT DRAWINGS 20
14/3.5 ACCEPTANCE TESTS 20
14/3.6 SYSTEM INSPECTIONS 21
SECTION 15 – AC SYSTEM
PLEASE REFER TO APPENDIX A
-6-
SUB – SECTION DESCRIPTION PAGE
-7-
SUB – SECTION DESCRIPTION PAGE
-8-
SECTION 4 CONCRETE WORKS
Section 4
Concrete Works
-1-
SECTION 4 CONCRETE WORKS
-2-
SECTION 4 CONCRETE WORKS
PS 4.14 ADMIXTURES
4.14 The following paragraphs are additional to the requirements of Section 4/14 of the
General Specifications:
2. Plasticizers and super plasticizers shall not contain substance, which adversely
affect the durability and performance of the concrete
3. If two or more admixtures are used simultaneously in the same concrete mix,
data including manufacturer’s certificate shall be provided to assess their
interaction and ensure their compatibility.
4/15.1 Concrete shall be as shown in the table of 4.5. The number of mixes may require to be
increased.
The criteria given in the table are designed to produce concrete of the required strength
and durability.
If the maximum aggregate size is 10mm then the cement content stipulated for the class
of concrete given in table 4.5 shall be increase by 40kg / m3.
-3-
SECTION 4 CONCRETE WORKS
TABLE 4.5
TABLE OF MIXES
The CCSs are for concrete which has been cured at a temperature of 23 degrees C ± 2
degrees C, and are the values below which no more than 5% of the test result full. The 7
– days strength shall be used only as a guide.
4/15.2 Concrete shall comply with BS 8110 except where be is 8007 or this specification differs.
Sampling for test purposes shall comply with BS 1881 part 101 (on site) & part 125 (in
laboratory).
If air – entertainment is specified the average air content at the time of placing measured
in accordance with be is 1881 part 106 shall be:
Concrete for water – retaining shall be water type and shall complied with the
recommendation of BS 8007.
Concrete for paving or precast unit shall be tested to BS 1881 part 118 and shall have
minimum flexural beam strength of 3.5N/mm2 at 28 days. If the concrete has a specified
CCS of 40N/mm2 or greater, then the minimum flexural strength shall be 4N/mm2.
If the concrete specimens are recurred at the highest temperatures or longer failures. Then
BS 1881 part 111 requires, the adjusted CCS shall be calculated as follows:
-4-
SECTION 4 CONCRETE WORKS
= adjusted CCS
f = specified CCS
T = curing temperature
D = age at testing in days
A&B = are coefficient given in the following table
Before placing concrete the contractor shall obtain approval of mixes propose for each
class of concrete and the average target strengths. The mixes shall be design to achieve
the minimum workability for the Contactor to place and compact the concrete with the
equipment proposed for use.
The mean strength shall exceed the CCS by a margin of 1.64 times the standard division
expected from the concreting plan, except that no standard division less than 3.5N/mm 2
shall be use as a basis for designing a mix. Unless otherwise approved standard division
of 7N/mm2 shall be use for initial mixes.
4/15.3 The ultimate compressive strength of the concrete shall be determined on test specimens
obtained and prepared in accordance with B.S. 1881. Part 108.
4/15.4 Mixes for structural concrete shall be designed by the Contractor. The class of concrete
(shown on the drawings) is denoted by the 28 days characteristic cube strength and the
maximum size of aggregate.
4/15.5 the chloride and sulphate levels in the concrete mix shall comply with the following
requirements:
-5-
SECTION 4 CONCRETE WORKS
Note: The OPC and MSRPC cements can also contain chlorides , the relevant standard
BS 12 allows up to 0.1%. Therefore any chlorides content in the cement has to be
taken into account while computing total Cl in the mix. In case the cement
contains the maximum limit of 0.1% Cl, then aggregates, water and admixtures
used for prestressed concrete or heat cured reinforced concrete should be
absolutely free of chlorides.
Where concrete for the present contract is to be obtained from a batching plant for other
sites, the requirements for trial mixes may, with the approval of the Engineer, not be
required subject to the following:
(a) The concrete mix is currently approved at the source Site, and
(b) Trial mix procedures have been undertaken and approved.
Documentation of trial mix procedures, approvals and all cube strength results must be
provided. The cubes strength results from the source site must be used in assessing
compliance with Clause 4/17.3
No concrete shall be sourced from another site where the mix has not met with
the specification requirements of that site until further notice from the Engineer.
i) The average strength determined at the age of 28 days from the sample of three
or more cube test result exceed the specificities CCS by 0.5 times the current
margin or,
-6-
SECTION 4 CONCRETE WORKS
ii) No individual result of the sample is less than that (Specified CCS minus 3
N/mm2), or
iii) Number of individual results in the sample below specified CCS is not more than
one.
If the above criteria are not satisfied, the unit represented by the sample is questionable
and the following actions may be instructed as appropriate:
If the range of individual cube strengths made from the same sample exceeds 15% of the
mean, then the method of making, curing and testing cube shall be checked. In the event
of the sample having a range exceed 20%, then the result shall be unacceptable and the
Engineer may order any of the following actions:
n the event of cutting and testing of cores are required, the Contractor shall cut cores
from approved locations and test them to BS 1881 as modified by BS 6089.
4/31.1 Any one set of 6 cubes for each class of concrete and for each particular application
represents a maximum quantity of concrete as shown in Table 4.6. The point of sampling
of fresh concrete shall be at delivery into the construction unless otherwise directed by
the Engineer. Each set of cubes shall be made from a separate batch.
4/31.2 Portland Cement: One 2 kg sample for quality test shall be taken from each 1.700 bags or
equivalent weight in accordance with BS EN 196-7.
4/31.3 Water: One 1 gallon sample shall be obtained prior to use from each source and at least
once every week for quality testing.
-7-
SECTION 4 CONCRETE WORKS
TABLE 4.6
SAMPLING RATES
SAMPLING TO
TYPE OF STRUCTURE REPRESENT A
VOLUME OF M3
1. Critical structures
e.g. masts, cantilevers, columns 10
2. Intermediate structures
e.g. beams, slabs, bridge decks 50
-8-
SECTION 5 ANCILLARY WORKS
Section 5
Ancillary Works
-1-
SECTION 5 ANCILLARY WORKS
-2-
SECTION 5 ANCILLARY WORKS
5/21.2 Steelwork shall be mild steel Grade 43A to BS 4350, and shall be hot-dip
galvanized after fabricating in accordance with BS 729 to the thickness
shown on the Drawings.
5/21.3 Fencing shall be erected to the dimensions and tolerances shown on the
drawings to produce a flowing alignment. The Contractor shall adjust the
elevation of any rail as required.
5/21.4 The rail section shall be such that when freely supported over a 3 m clear
span, with the road face uppermost, and centrally loaded with a point load
of 1000 Kg, the deflection measured at the centre of the span shall not
exceed 40 mm.
5/21.5 Adjacent rails shall be connected by bolted lap of joints made in the relevant
direction to prevent vehicles striking rail ends.
5/21.6 Guardrail posts may be driven into the ground as detail on the drawings
provided that:
-3-
SECTION 5 ANCILLARY WORKS
iii. Driven posts shall have a protective coating of bituminous paint over
the length which is to penetrate the ground and extend 75mm above
the finished ground level. The bituminous paint shall be of high
quality with excellent adhesion properties. A sample of the paint
together with the manufacturer’s specifications shall be submitted
to the Engineer for approval prior to use.
5/21.7 The ends of safety fences shall terminate with a mitered end rail and
anchorage flared away from the line of fence.
5/21.8 Site drilling or cutting of beams and posts not be permitted without
approval. Flame cutting shall not be permitted.
5/21.10 The horizontal alignment of fences shall not depart from the road alignment
by more than 30 mm overall, and the relative deviation shall not be more
than 10 mm in any two successive rail lengths.
5/21.11 The height of the uppermost edge of the rail shall not depart from the
dimensions shown on the drawing by more than 30 mm, nor shall the
relative deviation from this line be more than 5 mm in any two successive
rail lengths.
5/32.1 Steel for the fabrication of bridge parapets and sign gantries shall comply
with the requirements of BS 4, Part 1, BS 5400, BS 4360 and BS 4848 as
appropriate.
5/32.2 Fixing bolts and accessories complying with BS 5400, BS 4190 and BS
4320 2S appropriate.
5/33.1 Extruded sections shall conform to the following requirements. Posts Alloy
6082 TE to BS 1474 Other Locations Alloy 6082 TF to BS 1474
-4-
SECTION 5 ANCILLARY WORKS
5/34.2 Aluminum parapets in contact with concrete shall have bearing pads of
rubber/fabric, new and un vulcanized.
5/34.3 All other fastening shall be of stainless steel 315S 16 quality to BS 970 Part 4.
5/35.1 All paints forming any one painting system shall be obtained from one
manufacturer and, unless otherwise agreed by the Engineer, the source
of supply shall not be changed after the Engineer's approval has been
given. Paint snail be supplied in sealed containers of not more than 5
liters capacity and these shall be used in strict order of delivery.
5/35.2 The Contractor shall obtain from the paint manufacturer paint ready for
the use specified under the contract. The paints shall be adequate in all
respects for the purpose intended.
5/35.3 The system of protection for all non-galvanized steel work shall be as
follows;
Prime Coat: Inter zinc QHA 027/028 (or equivalent) minimum dry film
thickness 65 microns.
Second Coat: Intergard EBA 070/EBA 100 JB (or equivalent) natural
M.I.O. minimum dry filter thickness 100 microns.
Third Coat: Intergard EBA 070/EBA 100 JB (or equivalent) silver grey
M.I.O. minimum dry film thickness 100 microns.
Fourth Coat: Intergard EFK 724 (or equivalent) epoxy finish
Grey minimum dry film thickness 50 microns.
Total dry film thickness - 315 microns (minimum).
The coating shall have a minimum adherence to the steel work of 2.5 MPa
when tested with an adhesive tester.
5/35.4 Prior to painting the steel work shall be grit blasted to SA 2-1/2 Swedish
Standard 055900 or by other approved method to equivalent standard.
Before the steel surface shows signs of flash rusting the first coat of zinc
primer shall be applied. If the steel does flash rust then the cleaning
process is to be repeated.
-5-
SECTION 5 ANCILLARY WORKS
For Testing of Guard Rails, Nuts, Bolts & Washers (Thickness of Coating)
shall be checked with DCL as per BS EN ISO 1461: 1999.
Water Proofing Membrane: The following test shall be checked with Dubai
Central Laboratory.
GENERAL - TYPE 1
5/36.1 Deck waterproofing shall be composed of a proprietary membrane of a
polyester reinforced, SBS (Styrene-Butadiene Styrene) polymer modified
bitumen sheet prayed or torched applied to primed concrete deck as
detailed on the drawings.
MATERIALS
5/36.2 Membranes shall comply with the requirements of Technical
Memorandum BE 27 (Bridges) Waterproofing and Surfacing of Bridge
Decks and the system shall be certified by the British Board of
Agreement. Materials shall have the following physical properties.
REPARATION OF SURFACE
5/36.3 All concrete surfaces to be waterproofed shall be smooth and free from
projections or holes which might cause puncture of the membrane. The
surface shall be dry and immediately before the application of primer or
membrane, the surface shall be thoroughly cleaned oil dust and loose
materials.
5/36.4 Immediately after cleaning and drying of surface, priming should be applied
in strict compliance with manufacturer’s instructions. Primer coat shall be
allowed to cure completely before membrane application. Membrane shall
be laid parallel to traffic direction and tangent to the bridge curve in such a
manner that overlaps are never less than the specified width. In all cases
waterproofing shall begin at the low point of the surface to be waterproofed.
End laps should be staggered one meter so that at no point are there more
than three thickness of membrane. It shall be installed with 100 mm side
laps and 150 mm staggered endlaps.
APPLICATION DETAILS
3/36.5 At the edges of the membrane and at any point where it is punctured by
appurtenances such as drains or pipes, suitable provision shall be made to
prevent water from getting between the waterproofing and the waterproofed
surface, as recommended by the manufacturer.
5/36.7 The bituminous wearing course should be laid as soon as possible after a
minimum period of four hours has elapsed from completion of the
membrane.
GENERAL
5/36.8 Type 2 deck waterproofing membrane shall consist of a two part rapid
curing liquid applied system based on methacrylate resins. The complete
system shall comprise of a primer to ensure good adhesion to the substrate,
the membrane and a tack coat to ensure good adhesion to the bituminous
road surfacing. The system must be suitable for use in Dubai. The
temperature of the bituminous surfacing at the time of laying onto the
waterproofing membrane must be according to Clause 3/33.
CERTIFICATION
5/36.9 The Type 2 waterproofing membrane system must hold a British Board of
Agreement Certificate.
-7-
SECTION 5 ANCILLARY WORKS
APPLICATION
5/36.10 Application shall be strictly in accordance with the manufacturer's
instructions.
5/37.2 The Contractor shall submit to the Engineer for approval three samples in
one liter containers of the rubber bitumen emulsion. The Contractor shall
also submit to the Engineer certificates that the material complies with
requirements of the Specification, and is suitable for the intended purpose.
5/38 WATERSTOPS
5/38.1 Alternatives from those indicated on the drawings will be accepted only if
the Engineer is satisfied that their material and their performance are not
inferior. The waterstop, used must be installed strictly in accordance with
the manufacturer instructions.
For rubber waterstops the rubber compound shall comply with U.S. Fed.
Spec. 22R-601 a except ASTlv1 D 395-52 for compression and ASTM
D2240-75 for hardness.
5/38.3 No splices will be permitted in straight strips. Strips and special connection
pieces shall be well cured in a manner such that cross section shall be dense,
homogeneous and free from all porosity, All junctions in the special
connection pieces shall be full moulded. During welding or vulcanizing
periods the joints shall be securely held by Suitable clamps. The materials
at the splices shall be dense and homogeneous throughout the cross section.
-8-
SECTION 5 ANCILLARY WORKS
5/38.4 If after placing concrete, waterstops are materially out of position or shape
or if voids are found, the surrounding concrete shall be removed, the
waterstop reset, and the concrete replaced, all at the Contractor's expense.
5/39.1 Joint fillers in expansion joints for structures shall consist of a compressive
non-extruding board manufactured from bitumen impregnated fibers.
5/39.1 The Physical properties of the material shall conform to the requirement of
ASTM D-1751.
5/40.1 Cold applied joint sealant shall be a multi-component, gun applied material
a grade suitable for the hot climate with a service temperature of up to 70
degrees centigrade and high resistance to ultraviolet exposure.
5/40.2 The compound shall comply with the priority of latest edition of standard
shall be as follows:-
5/40.3 The sealant must be suitable for the application whether the joint to be
sealed is horizontal or vertical and with the ability to accommodate and
movement at the joint without rupturing or losing adhesion.
5/40.4 The hardness of the joint sealant shall be no less than 20 on the "Shore A”
scale.
5/40.5 The Contractor shall supply samples together with the manufacturers
literature relevant to any sealant for any application for the Engineers
approval prior to use. Only high quality products with demonstrable
resilience to the local climate conditions shall be approved. If a
Polysulphide based sealant is proposed for locations exposed to biological
attack or wet conditions then, it should have a minimum 40% polymer
content. All polysulphide based sealant must utilize a manganese dioxide
curing system.
5/40.6 The mixing application and curing of the approved sealant shall be in
accordance with the manufacturer’s recommendations.
5/40.7 The approved sealant shall be delivered to site in sealed containers showing
date of manufacture, batch number and shelf life.
-9-
SECTION 5 ANCILLARY WORKS
5/41.1 GENERAL
Expansion joint assembly shall be as shown on the drawing.
The Contractor shall submit the detailed shop drawings and obtain 'the
Engineer's approval before manufacture is commenced.
5/41.2 All anchoring steel plates, bolts and socket shall be protected against
corrosion.
5/42.3 Post sleeve shall be 4 mm thick PVC pipe encased with concrete as
approved by the Engineer.
- 10 -
SECTION 5 ANCILLARY WORKS
GENERAL
5/43.1 The coating system shall be an elastomeric system of single component
products, a weather resistant top coat used in conjunction with a penetrating
primer. The Coating shall have the ability to provide in-depth protection for
reinforced concrete structures against corrosion associated with the ingress
of chloride and sulphate ions, carbon dioxide and other air-borne acid gases,
and shall have 'the ability to allow water vapour to escape from the structure.
PRIMER
5/43.2 The primer shall be a low viscosity reactive silane-siloxane/acrylic blend
dissolved in a penetrating organic carrier. The primer shall have the
capability to penetrate and produce a chemically bound Hydrophobic
barrier to prevent the passage of chloride and sulphate ions, The primer
should also be film forming to condition and stabilize the substrate prior to
the application of the topcoat. The primer should be applied in full
accordance with the manufacturer Instructions.
TOPCOAT
5/43.3 The top coat shall be a fibre reinforced pure aliphatic acrylic resin,
decorative, high performance water based, pigmented coating. It shall have
resistance to water, carbon dioxide and other air-borne acids and have the
ability to allow the passage of water vapour from within the structure.
5/43.4 The top coat shall have elastomeric and flexural capabilities and should be
applied in strict accordance with the manufacturer's instructions. Approved
make DURA GARD HY-BUILD, FOSROC or MBT or equal approved
5/43.5 The system will, during trials, display the following properties when applied
in accordance with the manufacturer’s specification to samples obtained
from concrete Made without additives.
TRIAL PANELS
5/43.6 Prior to applying the system in the works, trial applications shall be carried
out on trial panels made by the Contractor under Clause 4/33. The trials will
demonstrate the method proposed for applying the system, coverage,
coating thickness, colour and final appearance of the coating.
Representatives of the coating manufacturers shall be present at the trials
and the surface preparation and application of the coating shall be carried
out under their direction. The Contractor shall at his own expense surface
coat as many panels as required by the Engineer until a trial panel has been
accepted by the Engineer as satisfactory. The coated panel, when accepted
will form the standard against which the corresponding coating in the works
will be judged. No application of the coating in the works shall be
undertaken until trials have been completed to the Engineer's satisfaction.
INSPECTION OF CONCRETE
5/43.7 The Contractor shall not proceed with the surface finish or making good of
concrete surfaces until he has received the Engineer's Representative's
permission to do so and he shall not apply cement slurry or mortar or any
other coating to the concrete surfaces from which the shuttering has been
struck until the concrete has been inspected and approved by the Engineer's
Representative.
- 12 -
SECTION 5 ANCILLARY WORKS
5/44.1 The bearings shall be guaranteed for 10 years and the Contractor shall
provide the guarantee from the bearing manufacturer.
5/44.3 Well in advance of their scheduled inclusions in the works, the Contractor
shall supply written details of the bearings and method of installation that
the Contractor proposes to use. The information supplied should include
documentation from the bridge-bearing supplier of successful usage in
similar environmental conditions to those experienced in Dubai.
5/44.4 Materials use and tolerances in bridge bearings shall comply with BS 5400:
Part 9.2.
5/44.6 The bearings shall be designed in accordance with BS 5400 Part 9.1 with
the additional analysis required hereunder.
5/44.6 The Contractor shall submit for the approval of the Engineer detailed
designed calculations in support of the sizes and quality of each component
of the bearing.
5/44.7 The Contractor shall submit, for the approval of the Engineer, shop
drawings and maintenance manual for the bearings.
5/44.8 The Contractor shall submit of a method of statement for the approval of
the Engineer. The method statement shall include the specification of all
materials, including bedding mortar, the corrosion protective system and the
method of handling, transportation, storage and installation. It shall also
include the replacement scheme of the bearing.
5/44.9 Bridge bearings, including bearing which are not required to provide lateral
restraint, shall be attached to the structure by mechanical fixings. The
friction between the bearing and the superstructure shall not be considered
to assist in resisting horizontal forces.
5/44.10 In addition to the normal material and load test certificates supplied by the
bearing manufacturer, all bearing materials shall be tested for specification
compliance.
5/44.11 Metal bearings shall be test for vertical load equal to one and a half (1.5)
times the specified working load. The test load shall be applied in five
equal increments and the test load held for 1 hour or until deformation
ceases, whichever is the greater.
- 13 -
SECTION 5 ANCILLARY WORKS
The load shall then be removed in equal decrements as the load increment.
A second cycle of load increment and decrement shall be applied with the
maximum test load bearing held for 30 minutes. The load deformation graph
shall be plotted for both load cycles and the ‘set’ exceeds a value deemed
to be excessive by the Engineer, the Engineer may require all bearings to be
pre-loaded before installation. At the end of the vertical load test, the
bearing shall be dismantled and the bearing surfaces examined.
5/44.12 Friction test for sliding surfaces shall be performed at constant vertical load
of 50 and 80 percent of the specified load. The horizontal load shall be
applied to obtain a steady rate of movement of one 1 mm per minute to
reach a total movement of 300mm or as directed by the Engineer.
5/44.13 Guide test shall be carried out at constant vertical loads 50 and 100 percent
of the specified load. The horizontal load shall be applied in ten equal
increments to a maximum of a specified guide capacity and held for thirty
30 minutes. The load decrement shall be the same as load increment. Two
load cycles for each test shall be performed. The load deformation graph
shall be plotted for both load cycles. At the end of the guide test, the bearing
shall be dismantled and the bearing surfaces examined.
5/44.14 All testing, including load testing of prototype bearings, shall be carried out
at an approved independent laboratory and will form the basis for approved
of the bearings. The Engineer or his nominated representative one or all of
the test. The Contractor shall arrange the dates and times of test to enable
the Engineer or his representative to attend the tests, the Contractor shall, at
his own cost, arrange of an independent observer approved by the Engineer,
to witness the test.
5/44.16 Unless otherwise described in the Contract the surface preparation and
corrosion protection of bearing shall comply with BS 5400 Part 9.2 and BS
5493. The environment should be considered to be exterior, exposed, non-
polluted, coastal atmosphere, and typical time for first maintenance 10 to
20 years.
5/44.18 PTFE Cold Flow Test - Testing of bearing PTFE for the cold flow test shall
be done under minimum temperature of 60 Deg. C, in addition to the
requirement specified in Volume 1 Part 1of the standard specifications.
- 14 -
SECTION 5 ANCILLARY WORKS
1. General - The Contractor shall furnish and install Spherical type, guided
expansion and fixed bridge bearings at the locations shown on the
Drawings. The bearing assemblies shall be complete and ready for
Installation. The design of spherical bearings shall comply with either
AASHTO LRFD or BS EN 1337 (and applicable European Norms for
requirements for individual components).
- 15 -
SECTION 5 ANCILLARY WORKS
3. Materials
General
b) PTFE
For PTFE applicable requirements included in design code and in the
relevant section of the General Specifications for Pot Bearings should
be referred.
Face of the stainless steel in contact with the sliding material: bright
annealed mirror (No.8) finish (less than 0.2 µm RMS).
- 17 -
SECTION 5 ANCILLARY WORKS
Metal to metal contact surfaces within bearings (inclusive of the top and
bottom adapter plates) shall be prepared either by machining or fine
grinding. Machining shall always be carried out after welding has been
finished.
The type and country of origin of the structural steel utilized in the
manufacture of the bearings shall be subject to the Engineer’s approval.
- 18 -
SECTION 5 ANCILLARY WORKS
g) Adhesive Material
• The adhesive material used for bonding the sliding material onto the
steel substrate shall be an epoxy resin satisfying the requirements of
ASTM C 881/C 881M, FEP film or equal, as approved by the
engineer.
• It shall be stable from -40°C to 125°C.
• Care shall be taken to ensure that the adhesive is applied uniformly
over the entire surface of the sliding material so as not to cause an
uneven sliding surface that premature could lead to premature wear.
- 19 -
SECTION 5 ANCILLARY WORKS
1. The design should be such that bearings will not suffer damage which
would affect their correct functioning or incur excessive maintenance
costs during their intended life.
2. The minimum vertical load on any bearing shall not be less than 20%
of the maximum vertical design load at the serviceability limit state.
3. The outer plates of bearings should be so proportioned that
concentrated loads are sufficiently distributed to ensure that the
permissible stresses on the adjacent bridge structure are not exceeded,
4. Top and bottom adapter plates shall be provided to allow for simple
bearing replacement.
5. Bearings shall be designed strictly in accordance with the material
manufacture’s specifications and recommendations. Limiting stresses
on the material shall be in accordance with the material manufacture’s
specifications.
6. SSM or any other PTFE replacement materials proposed by the bearing
supplier shall be demonstrated by tests from approved internationally
recognized laboratories to perform at least equal to or better than PTFE
in all aspects of bearing design requirements. All such materials not
covered by design standards shall have ETA certificate at the
applicable temperatures in Dubai (see point 8 below).
7. The performance of the replacement materials shall be demonstrated
with the use of lubricants such as silicone grease and in the absence of
lubricants. Actual friction values shall be considered for the design of
bridge elements.
8. The designer shall account for the high effective bearings temperatures
existing in Dubai in his design of the sliding materials, particularly the
effects of high temperatures on the characteristic compressive strength
and stiffness of the sliding materials. The bearing manufacturer shall
provide experimental evidence of the performance of proposed sliding
materials for temperatures in the range of 30°C to 70°C.
9. The coefficient of friction shall be established using friction tests in
accordance with EN 1337-2 for lubricated and unlubricated sliding
materials. The results of the tests carried out on unlubricated sliding
materials shall be obtained for information only. If an alternative
sliding material is proposed, an ETA shall be submitted to describe the
friction properties and the combination of sliding materials.
10. Bearing manufacturers shall also provide to the engineer the expected
maximum coefficient of friction for bearings which have undergone
extensive wear during the life of the structure.
11. The concave and convex spherical element will be machined from a
solid block of structural and non-corrosive steel respectively.
12. The minimum center thickness of the concave spherical element and
the minimum edge thickness of the convex spherical element shall be
at least 20 mm.
- 20 -
SECTION 5 ANCILLARY WORKS
13. Unseating of the curved spherical surfaces relative to each other shall
be prevented by transferring horizontal forces through specifically
designed restraints or by control of the spherical radius.
14. If design performed to EN/ETA, Service temperature of bearings shall
be considered as +70° C for the calculation of special sliding material
design stress values.
- 21 -
SECTION 5 ANCILLARY WORKS
If all tests performed on the selected bearing in a given load range meet
specified requirements, all bearings within that load range will be
acceptable. In the event that any test on a bearing in a given load range
does not meet specified requirements, the tested bearings and all other
bearings in that same load range will be rejected unless each individual
bearing is satisfactorily tested and approved by the Engineer.
d) Proof Load Test - A test bearing shall be loaded to 150 percent of the
bearings rated design capacity and simultaneously subjected to a
rotation range of 0.02 radian (1.146°) or design rotation, whichever is
greater, for a period of one (1) hour. Design rotations are defined as
bearing tolerance required by the design standard (AASHTO LRFD)
plus the maximum strength limit state rotations from the applicable
design loads.
The bearing will be visually examined both during the test and upon
disassembly after the test. Any resultant visual defects, such as
extruded or deformed elastomer, polyether urethan or TFE, damaged
seals or limited rangs, or cracked steel, shall be cause for rejection of
the lot.
- 22 -
SECTION 5 ANCILLARY WORKS
Bearing grout pads shall be placed as shown on the Drawings and as herein
before specified for “Grout Pads” using an epoxy and quartz sand grout as
recommended by the bearing manufacturer. The top surfaces of the epoxy
grout pads shall be perfectly level and any perceptible deviations from a
straightedge shall be ground level or filled with epoxy mortar and ground
until a true level surface is obtained.
- 23 -
SECTION 5 ANCILLARY WORKS
The bearings shall be placed at the time of superstructure form erection and
all temporary restraints shall be removed as directed by the bearing
manufacturer.
The bearings shall be set on the exact alignment as shown on the Drawings
for each location and shall be oriented in the proper direction. Extreme care
shall be exercised in aligning both the base and the upper part of the guided
expansion bearing parallel to the expansion axis of the structure to avoid a
wedging action in the bearing during movements of the superstructure. The
location of the upper part of the bearing shall be adjusted relative to the base
to allow for temperature at the time of erection.
If for any reason the bearings are disa6sembled, reassembly shall be only
permitted in the presence and guidance of the skilled representative of the
bearing manufacturer.
8. Approvals
- 24 -
SECTION 5 ANCILLARY WORKS
9. Shop Drawings
The Contractor shall submit shop drawings to the engineer for approval
which shall include, but not limited to, the following information:
- 25 -
SECTION 5 ANCILLARY WORKS
5/45.1 Bedding mortar under base plates and bearings shall be a high performance,
dual shrinkage compensated, cementitious high-performance grout
conforming to the requirements of U.S. Corps of Engineers specification for
non-shrinkage grout CRD-C621-82A and ASTM C1107-91 (Type C).
5/45.4 The cementitious free flow grout shall requirements: conform to the
following
5/45.5 All material storage, mixing, application and curing shall be carried out in
strict in accordance with the manufacturer’s instructions.
5/45.6 all contact surfaces must be free from oil, grease, free standing water and
any loosely adherent material. All dust must be removed and bolt holes and
fixing pockets blown and clean from any dirt or debris.
5/45.7 Adequate form work shall be provided in accordance with the relevant
codes of practice. This shall be surely fixed to withstand the hydraulic
pressures of the grout without distortion or movement during placement.
5/45.8 The formwork shall be watertight at all joints between panels and between
the formwork and the existing concrete surface so as to prevent grout
leakage.
- 26 -
SECTION 5 ANCILLARY WORKS
5/45.10 Formwork surfaces that are to be in contact with the grout shall be treated
with a suitable mould release agent. This shall be used in accordance with
the manufacturer’s recommendations.
5/45.13 Where necessary, provision shall be made for controllable bleed points to
prevent air entrapment and enable the flow of the grout to be assessed.
i. The clear space between the front of the control panel and the kiosk
shall not be less than 1500 mm and minimum of 750 mm clear space
on remaining three sides the panel. The GRP kiosk shall be provided
with stainless steel installation skid.
ii. The kiosk shall be supplied with sufficient number of 36,000 BTU/hr.
floor standing split air conditioner with drip trap, supports and
drainpipe, 4 no. 36 W limit switch operated fluorescent lights and
hygrostat operated 2 no. tubular heaters.
iii. The kiosk to have an single lead emergency door with push bar on the
opposite site of the main entrance.
vi. The kiosk should have provision for fixing split AC unit, anti-
condensation heater, junction box, smoke detector, beacon, fire
extinguisher, fire alarm etc.
PS 5/48.1 General
The Contractor shall provide a maintenance manual for the Reinforced Fill
System.
The specifications are presented to the Engineer shall also state any
requirements for additional thickness of reinforcing strips and/or limitations
on the backfill used in the structure to insure the des1gn life. The final
thickness shall be subject to the approval of the Engineer.
- 28 -
SECTION 5 ANCILLARY WORKS
The following standards and codes in their latest edition shall be particularly
applied to works covered by this Specification where applicable, together
with any further standards or codes as described within the approved
Specifications for the approved wall system.
BS5400
ASTM
Pressed and Forged Steel Shapes, Plates Bars and Strips A 153 Zinc Coating
(Hot Dip) on Iron and Steel Hardware
A 325 High Strength Bolts for Structural Steel Joints including suitable
Nuts and Plain Hardened Washers
A 570 Hot Rolled Carbon Steel Sheet and Strip, Structural Quality
D 1752 Performed Sponge Rubber and Cord Expansion Joint Fillers for
Concrete Paying and Structural Construction
BS 1377: Part 2: Test S Determining the Plastic Limit and Plasticity Index
of Soils
PS 5/48.4 Materials
b) Concrete Finish - The concrete surface pattern and finish for the exposed
faces shall conform to the plans. The rear face of the panel shall be
roughly screened to eliminate open pockets of aggregate and surface
distortions in excess of 6.5mm. The Color and texture of the finish shall
be approved by the Engineer based on three trial panels rovided by the
Contractor prior to producing the final panels.
g) Handling, storage and shipping - All units shall be handled, stored and
shipped in such manner as to eliminate the danger of chipping, cracks,
fractures and excessive bending stresses. Panels in storage shall be
supported on firm blocking located immediately adjacent to tie strips or
toggles to avoid damage to these tie strips and toggles. Any panels,
including fastening hardware, damaged during handling, storage or
shipping shal] be rejected by the Engineer.
- 30 -
SECTION 5 ANCILLARY WORKS
4. Steel Reinforcing and Tie Strips - Tie strips shall be shop fabricated of
hot rolled steel confirming to the minimum requirements of ASTM A-
570, Grade 36 or equivalent. Guaranteed anti-corrosion measures are to
be applied and are to be effective throughout the specified design life.
The tie strips and reinforcing strips shall be cut to length and tolerance
shown on the Drawings and the holes for bolts shall be punched in the
locations shown. All reinforcing and tie strips shall be carefully
inspected to ensure they are true to size and free from defects that may
impair their strength and durability. The Contractor shall furnish the
Engineer with a Certificate of Compliance certifying that these
materials comply with the application specifications.
Reinforcing strips shall be fixed to the facing panels using stainless steel
or embedded polyethylene coated polyester fiber strips and glass fiber
toggles, unless otherwise noted on the approved shop drawings and in
accordance with approved samples. The Contractor shall furnish the
Engineer with a Certificate of compliance certifying that these materials
comply with the applicable specifications.
a) Piller for vertical joints between panels shall be flexible open cell
polyethylene foam strips, unless otherwise noted on the approved shop
drawings.
b) Filler for horizontal joints between panels shall be resin bonded cork
filler conforming to ASTM D 1752 (Type II) unless otherwise noted on
the approved drawings.
- 31 -
SECTION 5 ANCILLARY WORKS
- 32 -
SECTION 5 ANCILLARY WORKS
When concrete face panels are specified, at each panel foundation level
a concrete levelling footing shall be provided as shown on the plans.
The footing shall be cured a minimum of 48 hours before placement of
wall panel.
- 33 -
SECTION 5 ANCILLARY WORKS
- 34 -
SECTION 5 ANCILLARY WORKS
PS 5/57.3 Storage:
Store in tightly closed original containers in a dry, well-ventilated room
at temperatures between +5 °C and +30 °C (41 °F – 86 °F), not directly
on the floor and not in the vicinity of heating radiators. Please note that
the material can show a tendency towards sedimentation during
transportation and storage. In this case, the Contractor shall keep the
material stir until it is homogenous, and it will be ready for use again.
PS 5/57.4 The Application
a. Preparation of Road Surface
The paint shall be applied only on a surface which is clean and dry. It
shall not be laid over loose detritus, mud or similar extraneous matter
or over a thermoplastic marking or over an old paint marking which is
faulty or incompatible with the paint being applied.
Depending on the amount of flux oils contained in new bituminous
surfaces, these may need to be weathered up to 8 weeks before final
application. Especially on hot days sweating of flux oils from fresh
bitumen occurs often. If cold plastic material is applied too early on
fresh asphalts the cured marking can be pealed off. In case of doubt it
is recommend applying a test stripe and try to peel it off after curing (30
min). If peeling off is possible then, hot ambient temperatures should
be avoided and or the road surface needs additional time to be
weathered. A special precationaries to be applied for bitumen-poor
asphalt pavements based on the manufacturerer’s recommendation.
If a primer or undercoat is necessary to ensure proper adhesion of the
marking paint to the road surface without bleeding or discolouration,
the primer or undercoat shall be fully compatible with the marking paint
and the road surface, and shall be applied only if, and at the rate of
application approved by the Engineer.
- 35 -
SECTION 5 ANCILLARY WORKS
b. Preparation of Paint
All cold-applied paint shall be thoroughly field mixed before applying in
order to keep the pigments in uniform suspension. The use of thinner
or other additives shall not be permitted unless otherwise agreed to by
the Engineer.
c. Laying of Paint
Markings shall be applied by brush, spray, hand-propelled or self-
propelled machine according to the marking configuration and the type
of paint approved for use or as directed by the Engineer. The rate of
application of paint for each coat shall be that recommended by the
manufacturer and shall produce a minimum total cover rate of
unthinned paint of 0.5 litre per square metre, unless otherwise directed
by the Engineer. Where a spray machine is to be used the Contractor
shall not proceed with the marking work until the equipment, method of
application, and rate of application, as established by a test section,
have been approved by the Engineer. When more than one coat is
used, the succeeding coat shall not be applied until the previous coat
has fully set. The work shall be carried out very carefully to a regular
alignment in accordance with the Drawings. Straight edges and
templates shall be used if required by the Engineer. Where applicable
the Ballotini (glass beads) shall be applied to the surface of the paint
immediately application is complete and shall be applied in a controlled
manner by use of a spreading device which will permit an even spread
from a fixed height of between 300mm and 400mm or otherwise as the
Manufacturer may recommend. (A wheel mounted, variable width,
funnel applicator may be suitable). The loss of glass beads after 3
weeks traffic shall not exceed 10 percent of the total applied.
d. Protection of Paint Markings
All markings shall be protected from traffic until they have dried
sufficiently.
PS 5/57.5 Post Application:
After application, quality control shall be made according to EN 1436
and acceptance procedures shall be implemented.
PS 5/57.6 Defective Materials of Workmanship
Materials which are defective or have been applied in an unsatisfactory
manner or to incorrect dimensions or in a wrong location shall be removed,
the road pavement made good and the materials replaced, reconstructed
and/or properly located, all at the Contractor’s expense and to the
satisfaction of the Engineer/ RTA.
- 36 -
SECTION 5 ANCILLARY WORKS
- 37 -
SECTION 5 ANCILLARY WORKS
PS 5/59.1 Introduction
Cycle track tiles is Hydraulic Pressed (Wet Mix) tiles full bodied (Single
Mix) to avoid delamination.
PLANT
1 No. Single Station - Motherwell Bridge, UK - 400 Ton Press - Simplex.
3 Nos. Three Station- Forest Press Hydraulics, UK - 400 Ton Press -
Duplex.
RAW MATERIALS
Raw materials, coarse & fine aggregates are transported to the plant by
trailors and stockpiled. Moisture sensitive materials like cement are stored
in silos.
MIXING
Raw materials, both fine and coarse aggregates are conveyed to the
collection bucket, which introduces the material so collected into the main
mixing plant. Here, the aggregates are mixed along with cement.
BATCHING
After the completion of dry mixing time directly as present according to
the requirement controlled by the automatic hydrometer, water is added.
The mixture is allowed to mix with water for about 25-40 seconds, which
is characterized as the wet mixing time.
MOULDING
The wet mix is delivered to dispenser through moving bucket, which is
measured by volumetric basis from dispenser to mould. The mix easily
runs and fills the mould without any need for vibration and paper or filter
cloth is attached to the die head to prevent the escape of fines. The
concrete when required in the dispenser unit is dropped to mould. At
- 38 -
SECTION 5 ANCILLARY WORKS
this stage, the mould table moves to hydraulically press with an applied
pressure of 400 tons, this is assisted by a vacuumed top drainage system.
The pressing duration ranges from 10 to 15 seconds depends on the
characteristics of aggregates and sizes. After completion of the press, the
mould detracts.
CUBING
When the ejector is raised, the product becomes clear of the mould and
contacts the vacuum plate achieving vacuum. The ejector is then lowered
and the carriage traverses over the Pallet conveyor.
STACKING
The roller conveyor supports the pallets during the stacking operation.
After a product has been stacked on the pallet, the conveyor indexes
forward a distance which is controlled by an adjustable timer set by the
Operator to correspond to approximately the thickness of one product.
When the pallet is full, it is moved down the powered conveyor, ready to
be taken away by the fork-lift truck and off-loaded at the curing area.
CURING
All finished materials are kept at the curing area are cured in kraft curing
chamber for 24 hours. After 24 hours they are removed and dry stacked
in open area for dispatch to sites.
SURFACE FINISHING
Shot blasted: Finished products will be cured sufficiently and then taken
to M/s.Schindler, Germany, automatic blasting machine for surface
blasting with steel shots to get the desired finish.
Curling: After shot blasting the same will be curled in automatic M/s.
Schindler, Germany, curling machine to get the desired finish & effect.
- 39 -
SECTION 5 ANCILLARY WORKS
PS 5/60.1 GENERAL
The Contractor is required to employ approved specialists to supply, or supply and erect all
metalwork items. Working drawings are to be prepared and issued to the Engineer in
quadruplicate for approval in good time to afford no delay to the project and in no case less
than eight weeks before work needs to be put in hand. No work at site or fabrication in
factory shall commence prior to any approval by the Engineer.
PS 5/60.2 STANDARDS
Materials used in this Section shall comply with British Standards, the British Codes of
Practice, DIN Standards, American Standards and American Society for Testing and
Materials, or Local Authority Standards and Codes whichever are the more stringent.
Applicable provision of the following British Standards shall apply to these works as
follows:‑
1) Mild Steel shall comply with BS 4360, sections generally shall comply with BS 4:
Part 1, hollow sections with BS 4848: Part 2 and angles with BS 4848: Part 4. Steel
plate and sheet shall comply with BS 1449: Part 1 and steel tubes to BS 1775.
2) Stainless Steel Tubes shall comply with BS 3014, and stainless steel plate with BS
1449: Part 2.
3) Aluminum alloy extruded sections shall comply with BS 1161 or BS 1474 and
aluminum alloy drawn tube with BS 1471. Anodizing process when applicable to
comply with BS 3987.
4) Brass work as indicated on the drawings shall comply with the various appropriate
Standards.
5) Fastenings unless otherwise specified shall be of the same metal as the item being
fixed, with matching coating or finish. Wood screws shall comply with BS 1210.
Bolts, Screws and nuts to BS 4190, machine screws and nuts to BS 4138 and
self‑tapping screws to BS 4174.
6) Plugs shall be proprietary fibre plastics or other approved type.
7) Bitumen solution for cold application shall comply with BS 3416, Type 1.
1) General
The finished coating shall be as stated on the Drawings and applied strictly in
accordance with the manufacturer's instructions.
The colour of the coating shall be selected from available ranges if not stated
elsewhere in these Documents. The Contractor shall offer samples for approval
prior to the final selection and the manufacturer of these elements.
2) Anodised coating
The aluminium anodising shall comply with BS 3987 and be integral color hardcoat
anodising 550kp/mm² hardness, minimum 25 microns thick.
- 40 -
SECTION 5 ANCILLARY WORKS
All aluminium sections that are to receive a polyester powder coating shall be given
a caustic etch followed by an anodix oxide treatment to obtain an architectural class
1 anodic coating. Anodisation should be not less than 20 micron thickness.
Unless otherwise stated mild steel shall be spray coated with Epoxy based paint to
be factory applied in two layers, primer coat 0.3 mils dry film thickness and finished
colour coat minimum 1.0 mils dry film thickness, minimum overall thickness of 1.3
mils dry film thickness. Inside corners, channels and the like shall be visually
covered to the extent possible. The Engineer shall select the colour from the range
available.
The coating shall be applied to properly cleaned and pre‑treated galvanised steel
sections. Application shall be by approved applicators and the Contractor shall
provide certified details of same. The pretreatment and application of the coating
shall conform to all ASTM, BS, DIN Standards and the like as stated in the
Supplier's printed Specifications.
5) Coating thickness
As and when instructed by the Engineer, the Contractor shall provide certificates
from independent laboratories that the minimum thickness as stated in these
Documents has been applied to all sections. Failure to provide such information
shall result in the complete installation being rejected and replaced at the
Contractor's expense.
6) Dissimilar materials
All aluminium surfaces that are to be in contact with cured concrete, mortar, steel
and other metals shall have the contact surfaces protected wherever they may entrap
moisture or corrosive elements. Metals that are to be in contact with mortar or
concrete shall be protected with a two coat bituminous coating.
Prime paint steel parts of anchors, anchor inserts, reinforcement, supports, and all
parts after field welding or bolting with zinc chromate. Minimum dry film thickness
of 1 mil for zinc chromate.
- 41 -
SECTION 5 ANCILLARY WORKS
PS 5/60.4 ALUMINIUM
(i) Generally
All aluminum elements i.e doors, windows, frames, transoms, mullions, etc, where
shown on the drawing shall be manufactured of extruded section of aluminum alloy
to B.S. 1474. Heat treatable free from defects type, 11.9. They shall be supplied by
a manufacturer approved by the Engineer. Fittings shall be aluminum alloy in
accordance with B.S. 1473.
All exposed surfaces shall be light etched and anodised in a satin or matt finish to
the colour indicated on the drawings. The thickness of anodising shall be guaranteed
to be 20 microns (.020 mm) by the manufacturer and shall be polished to a mirror-
like surface.
Aluminum coated materials shall not be permitted in lieu of the aluminum items
specified herein. Samples of the anodized finish must be offered for approval before
proceeding.
All aluminum sections shall present clear, straight and shapely defined lines and
shall be free from defects and imperfections that may impair their strength.
The Contractor shall be responsible for the protection of all aluminum work until
the completion of the Works, and only units in perfect working order and in perfect
condition will be accepted. All hardware, screws, bolts and other necessary
accessories shall be of aluminum or other non- corrodible material and shall match
in colour and consistency the finish of the anodised aluminum.
Where aluminum is in contact with wood, the wood shall be treated with
pentachlorophenol or equal and approved, 5% minimum concentration, followed
with the protective measures described for aluminum in contact with wood or other
absorptive materials.
The aluminum work shall be fabricated and anchored so that work will not be
distorted nor the fasteners overstressed from the expansion and contraction of the
metal.
(ii) Protection
Before shipment from the factory, aluminum surfaces requiring protection shall be
given a coating which will protect the metal during construction. In areas where
appearance of the finish on aluminum items is important a coating of methacrylate
lacquer shall be applied.
weight) muriatic acid for a period of six hours at 70 degree F and the action of
atmospheric weathering for a period of 12 months. Alternatively a thick adhesive tape
may be used. The coating or tape shall be applied in the manufacturers plant to the
exposed surfaces of all aluminum components subject to staining from alkaline
mortar and plaster abrasion and other construction abuses.
(iii) Workmanship
The Contractor shall furnish all aluminium units as indicated on the drawings.
The Contractor shall furnish all labour materials and equipment to complete the
aluminium work indicated on the drawings or specified herein to the satisfaction of
the Engineer.
Work shall include all parts and accessories for all variations of fabrication
techniques required for a complete installation, caulking, priming and back coating
and shop drawings.
All aluminium work shall be performed in a shop where grade of metal work is of
recognised quality acceptable to the Engineer. All items shall be installed plumb,
straight, square, level and in proper elevation, plane, location and alignment with
other work. All work shall be fabricateded for adjustment to field variations, fitted
with proper joints and intersections and adequately anchored in place.
All workmanship and finishes shall be first class, strictly in accordance with the best
practice. All work shall be complete in every detail. Finished work shall be
approved by the Engineer before the job will be accepted.
Where aluminium surfaces come into contact with metals other than stainless steel,
zinc, white bronze or small areas of other metal compactable with aluminium, they
shall be kept from direct contact with such parts by painting the dissimilar metal with
a primer, followed by one or two coats of aluminium metal and masonry paint of
other approved suitable protective coating, excluding those containing lead
pigments, or a non-absorptive tape or gasket shall be placed between aluminium and
dissimilar metals. Steel anchors and connecting members shall be hot dip galvanized
or zinc plated after fabrication.
Aluminium in contact with wood or other absorptive materials which may become
repeatedly wet shall be painted with two coats of aluminium metal and monsonary
paint or a coat at heavy bodied bituminous paint. Alternatively paint the wood or
other absorptive material with two coats of aluminium house paint and seal joints
with a good caulking compound.
Upon completion, the Contractor shall clean all aluminium work as required by
removing protective tape and other coating, using mild soap or detergent and clear
- 43 -
SECTION 5 ANCILLARY WORKS
petroleum spirits. Acid, caustics and abrasives shall not be used. Where cleaners are
used to remove excess sealing compounds care shall be taken to prevent damage to
seal or staining or damage to adjacent work.
1) General
All frames should be made to fit the actual openings with a 5mm clearance
all round. Discrepancies in overall width or height exceeding 5mm will not
be allowed and the frames will be rejected in such cases. Any small
discrepancies shall have the gaps suitably backed and then filled with
gun‑applied water repellant mastic sealant.
All nuts, bolts, washers and screws used for assembly and fixing shall be of
adequate strength for their purpose within the and shall be stainless steel
grade 18/8.
All sealants used in the assembly of, and in the fixing of cladding and
window framing, shall be non‑setting to allow thermal movement without
detriment to those joint sealants used for peripheral caulking and shall be one
part silicone sealant and shall conform to BS 4245. All spliced joints between
mullions will be sealed with an approved silicone product, compatible with
other sealants and packings used.
All ironmongery shall have the same finish as the frames and shall be
approved by the Engineer.
At all opening windows and doors and where there are louvred screens and
doors, a flyscreen shall be provided to the approval of the Engineer,
constructed following the prinicples and specifications as described
elsewhere in this specification.
Glazing sections shall be set in special heat resisting PVC and of channel
type. Separate glazing sections on each side of the glass will not be
permitted.
- 44 -
SECTION 5 ANCILLARY WORKS
All materials shall be stored in protected areas on site and shall be fully
protected against the effects of weather.
All materials shall be carefully handled and stored under cover in a manner
to prevent deformation and damage to the materials and to shop finishes,
and to prevent rusting and the accumulation of mud, dirt or other foreign
matter on the metal work. All such damage and accumulation shall be
corrected prior to erection.
PS 5/60.6 MATERIALS
All materials shall be new stock, free from defects, impairing strength,
durability or appearance and of best commercial quality for each intended
purpose.
Provide all anchors, bolts, sleeves, spigots and other parts required for
securing each item of work of this Section to the construction, including
furnishing to concrete workers all required inserts and sleeves for use in
concrete and furnishing to masons of all anchors, bolts, and other items
required to be built‑in masonry.
All exposed fastenings shall be of the same material finish as the metal to
which applied, unless otherwise noted.
Bolts and nuts where used, shall be in accordance with B.S. 1400 or 1769.
- 45 -
SECTION 5 ANCILLARY WORKS
Bolts shall be of sufficient length to show at least one full thread beyond
the nut after tightening. Bolted joints subject to vibration shall be securely
locked.
The cramps for fixing wood frames to walls shall be 200mm long 30mm
wide and 3mm thick and shall have one end bent and twice countersunk
drilled for screwing to the frame and the other end fishtailed for setting into
walling.
All fixing cramps, wall tiles, anchors etc., shall be galvanised mild steel
proprietary type such as Pepcon International (Al Tayer), Harris and Edgar
or equal and approved. The Contractor is responsible for submitting
suitable samples to Engineer for approval.
Shop paint for ungalvanised ferrous surfaces shall be a high quality, lead
free, rust‑inhibitive primer, as approved by the Engineer.
Shop paint for galvanised metal shall be high quality, zinc rich, metal
primer especially formulated for use on galvanised metal, as approved by
the Engineer.
Galvanising
a) All ferrous metal under this Section for exterior use in addition to
any other interior items specifically so specified, shall be of hot
dip galvanized, including all bolts,
Shop Painting
e) After erection, sand smooth and retouch all portions of the shop
coats chipped or damaged during erection, and coat all field welds
and connections with the same paint used for all the shop coat.
PS 5/60.9 WORKMANSHIP
7) When assembled all moving parts must move freely and without
binding.
12) Apply metal coatings after fabrication is complete and all fixing
holes have been drilled, unless otherwise, specified. Before
applying coating remove all welding slag, weld spatter, anti‑spatter
compounds, paints, grease, flux, rust, burrs, and sharp arrises and
make good all defects which would show after application of
coating and finish surfaces smooth.
15) Position metalwork accurately, plumb, level and true to line. Fix
securely to prevent pulling away, deflection, or other movement
during use. Do not distort when tightening fastenings and the like.
PS 5/60.10 INSTALLATION
4) All works are to be fully protected for the duration of the contract
from damage by other trades. The Engineer shall approve the
method of protection.
- 50 -
SECTION 5 ANCILLARY WORKS
PS 5/60.11 SAMPLES
2) Unless specifically called for, size and form of each sample shall be
as directed by the Engineer.
The Contractor shall ensure that joints are dry and remove all loose material,
dust and grease.
When using backing strips, the Contractor shall not leave gaps and shall not
reduce depth of joint for sealant to less than the minimum recommended by
the manufacturer.
Cavities shall be filled and jointed with sealant in accordance with the
manufacturer's recommendations. Sealant shall be tooled to form a smooth
flat bead.
- 51 -
SECTION 8 CONCRETE PILE FOUNDATIONS
Section 8
Concrete Pile Foundations
-1-
SECTION 8 CONCRETE PILE FOUNDATIONS
8/1 DESCRIPTION 3
8/2 MATERIALS 3
8/4 TOLERANCES 3
-2-
SECTION 8 CONCRETE PILE FOUNDATIONS
8/1 DESCRIPTION
8.1.1 All pile foundations shall be bored cast-in-place concrete piles and shall be
constructed as indicated on the drawings and in compliance with these
specifications.
8/2 MATERIALS
8.2.1 The materials for the manufacture of the reinforced concrete shall be in
accordance with Section 4 - "Concrete Works".
8.2.2 The temporary steel casings and the permanent casings or liners shall be
cylindrical, of the diameter indicated on the Drawings and shall be of sufficient
strength to maintain shape and location during boring and placement of concrete.
The Casings shall be sufficiently watertight to exclude ground water during
placing of concrete.
8/2.3 In case drilling mud is used, bentonite, as supplied to the site and prior to mixing
shall be in accordance with Specification DFCP 4 of the Oil Companies Materials
Association.
8/3.1 Factual information and reports on site investigation for the works will be
provided to tenderers. However, in the event that a full report is given including
interpretations, opinions or conclusions, no responsibility is accepted by the
Employer, 8/3.2 The Contractor shall report immediately to the Engineer any
circumstances which indicates that in the Contractor's opinion the ground
conditions differ from those reported in or which could have been inferred from
the site investigation reports or trial pile results.
8/4 TOLERANCES
8/4.2 VERTICALITY
At the commencement of installation, the equipment governing the alignment of
the bored pile, shall be made vertical to a tolerance of within 1 to 100. The
maximum permitted deviation of the finished pill from the vertical is 1 in 75.
-3-
SECTION 8 CONCRETE PILE FOUNDATIONS
8/4.3 RAKE
The equipment governing the direction and angle of rake shall be set to give the
correct alignment of the pile within a tolerance of 1 In 50. The piling rig shall be
set and maintained to attain the required rake. The maximum permitted deviation
of the finished pile from the specified rake is 1 in 25 for piles raking up to 1:6 and
1 in 15 for piles raking more than 1:6.
8/5.1 The Contractor shall supply for approval all relevant details of the method of
piling and the plant he proposes to use. Any alternative method to that specified
shall be subject to approval.
8/5.2 The Contractor shall inform the Engineer each day of the intended programme of
piling for the following day and shall give adequate notice of his intention to work
outside normal hours and Public Holidays.
8/5.3 The Contractor shall submit to the Engineer his proposed sequence and timing for
boring piles, having regard to the avoidance of damage to adjacent piles.
8/5.4 Any proposals by the Contractor for ground treatment of any nature or for
temporary lowering of the water table by well pointing or any other method shall
be subject to the approval of the Engineer. The Contractor shall however remain
fully responsible for any effects of such ground treatment or control of the level of
water tables upon the existing roads, building and structures in the vicinity of
works.
8/5.5 Any proposals by the Contractor for underpinning, needling and shoring of
existing structures in the vicinity of the works shall be carefully designed by the
Contractor and be subject to approval of the Engineer.
8/6.1 The Contractor shall keep records as follows the installation of each pile
and shall submit two signed copies of these records to the Engineer not later than
noon of the next working day after the pile was installed. The signed record will
form a record of the work.Any unexpected boring conditions shall be noted in the
records.
Data to be recorded
i. Contract
-4-
SECTION 8 CONCRETE PILE FOUNDATIONS
8/7.1 If damage will be, or is likely to be, caused to mains, services adjacent structures,
the Contractor shall submit to the Engineer his proposals for making surveys,
monitoring movements or vibrations, and minimizing avoiding such damage.
8/7.2 The Contractor shall carry out the work in such a manner and such times so as to
minimize noise and disturbance.
8/8.1 Concrete for piles shall be Class 30 or as shown on the drawings and shall be in
accordance with Section 4 of the Specification and the following requirements.
8/8.2 When a designed mix is specified the Contractor shall be responsible for selecting
the mix proportions to achieve the required strength and workability, but the
Engineer will be responsible for specifying the minimum cement content and any
other properties required to ensure durability.
8/8.3 The Concrete shall have sufficient workability to enable it to be placed and
compacted by the methods used in forming the piles.
-5-
SECTION 8 CONCRETE PILE FOUNDATIONS
8/8.5 The cement content in any mix shall not be less than 360 kg/CU.m. Where
concrete is to be placed under water or drilling mud by tremie the cement content
shall be not less than 380 kg/CU.m., or where the pile will be exposed to sea
water 400 kg/CU.m.
8/8.6 All concrete aggregates, cement and water shall be sampled and tested as
frequently as deemed necessary by the Engineer as detailed under the relevant
clauses in section 4 concrete. work. All test samples shall be supplied by the
Contractor at his own expense.
8/8.7 Trial mixes shall be prepared for concrete in accordance with BS 5328, showing
that the proposed mix proportions and manufacture will produce a concrete of the
strength and quality required, having adequate workability for compaction by the
method to be used in placing. 8/8.8 The Contractor shall keep a detailed record of
the results of all tests on concrete and concrete materials. Each test shall be
clearly identified with the piles to which it relates.
8/9.1 The reinforcement for the piles shall conform to the requirement of
SECTION 4 of the specification.
8/9.2 Reinforcement in the form of a cage shall be assembled with additional support
such as spreader forks and lacing, necessary to form a cage which can be lifted
and placed without permanent distortion. Intersecting bars shall be fixed together
by approved means. Hoops, links or helical reinforcement shall fit closely around
the main longitudinal bars and be bound to them by approved wire, the ends of
which shall be turned into the interior of the pile. Reinforcement shall be placed
and maintained in position to specified projection of reinforcement above the final
cut-off level.
8/9.3 The cover to all reinforcement in cast-n-place piles shall be not less than 75mm
unless otherwise approved by the Engineer. Spacers shall be designed and
manufactured using durable material which will not lead to corrosion ot the
reinforcement or spalling of the concrete cover.
8/9.4 The number of laps in longitudinal steel bars shall be kept to a minimum. Joints in
reinforcement shall be such that the full strength of each bar is effective across the
joint and shall be made so that there is no detrimental displacement of the
reinforcement during the construction of the pile.
-6-
SECTION 8 CONCRETE PILE FOUNDATIONS
8/10.1 Prior to boring the Contractor shall check the casing position for each pile during
and immediately after placing the casing, and agree it with the Engineer.
8/10.2 Where the open bore is unstable, temporary casing or bentonites us pension may
be used to support the wall of the bore prior to concreting.
8/10.3 Piles shall not be bored so close to other piles which have recently been cast and
which contain workable or unset concrete that a flow of concrete could be
induced from or damage caused to any of the piles.8/10.4 The Contractor shall
carry out the work in such a manner and at such times as to minimize noise and
disturbance.
8/10.5 Any proposals by the Contractor for ground treatment of any nature or for
temporary lowering of the water table by well pointing or any other method shall
be subject to the approval of the Engineer. The Contractor shall however remain
fully responsible for any effects of such ground treatment or control of the level of
water tables upon the existing roads, buildings and structures In the vicinity of the
Works.
8/10.6 Any proposals by the Contractor for underpinning, needling, and shoring
structures in the vicinity of the works shall be carefully designed by the
Contractor and be subject to the approval of the Engineer.
8/10.7 Temporary casings shall be free from significant distortion. They shall be of
uniform cross-section throughout each continuous length. During concreting they
shall be free from internal projections and encrusted concrete which might
adversely affect the proper formation or piles.
8/10.8 Where piles are bored under water or bentonite suspension in an unlined state, the
insertion of a full-length loosely fitting casing to the bottom of the bore prior to
placing concrete will not be permitted.
8/10.9 Where boring takes place through unstable water bearing strata, the process of
excavation and the depth of temporary casing employed shall be such that soil
from outside the area of the pile is not drawn into the pile section and cavities are
not created outside the temporary casing as it is advanced.
8/10.10 Where the use of drilling fluid is specified or approved for maintaining the
stability of a bore, an adequate temporary casing of all shall be used in
conjunction with the method so as to ensure stability of the strata near ground
level until concrete has .been placed. During construction the level of drilling
fluid in the pile excavation shall be maintained within the cased or stable bore so
that it is not less than1.0m above the level of external standing groundwater at all
times In the event of rapid loss of drilling fluid from a pile excavation, the bore
-7-
SECTION 8 CONCRETE PILE FOUNDATIONS
shall be backfilled without delay and the instruction of 'the Engineer shall be
obtained before boring at that location is resumed.
8/10.11 All reasonable steps shall be taken to prevent the spillage of bentonite suspension
on the Site in areas outside the immediate vicinity of boring. Discarded bentonite
shall be removed from the Site without undue delay. Any disposal of the bentonite
shall comply with the regulations of the RTA / Roads Department.
8/10.12 Pumping from pile bores shall not be permitted unless the bore has been sealed
against further water entry by casing or unless the soil is stable and will allow
pumping to take place without ground disturbance below or around the pile.
8/10.13 For a pile constructed in a stable cohesive soil without the use of temporary
casing or other form of support, the pile shall be bored and concrete shall be
placed without such delay as would lead to significant impairment of the soil
strength.
8/10.14 Each pile bore which does not contain standing water or drilling fluid shall be
inspected directly or indirectly prior to concrete being placed in it. This inspection
shall be carried out from the ground surface in the case of piles of less than
750mm diameter. Torches or other approved means of lighting, measuring tapes,
and a means of measuring vertically shall be provided. For piles of 750mm
diameter or larger, equipment shall be provided by the Contractor to enable his
representative and the Engineer to descend into the bore for the purpose of
inspection, Any method of, descent and the equipment used shall comply with the
requirements of BS 5573.
8/10.15 Completion of boring and where inspection of a dry pile bore indicates the
necessity, loose disturbed or softened soil shall be removed from the bore. Where
pile bores contain water or drilling fluid, a cleaning process shall be employed
before concrete is placed. Large debris/or accumulated sediment shall be removed
using appropriate approved methods, which shall be designed to clean while at the
same time minimizing ground disturbance below the pile bases. Water or drilling
fluid shall be maintained at such levels throughout and following the cleaning
operation that stability of the bore is preserved,
8/11.1 Bentonite, as supplied to the Site and Prior to mixing, shall be in accordance with
Specification DFCP 4 of the Oil Companies Materials Association.
-8-
SECTION 8 CONCRETE PILE FOUNDATIONS
8/11.3 Bentonite shall be mixed thoroughly with clean fresh water to make a suspension
which will maintain the stability of the pile bore for the period necessary to place
concrete and complete construction, The temperature of the water used in mixing
the bentonite suspension and of the suspension when supplied to the borehole,
shall be not lower than 5 deg. C.
8/11.5 The frequency of testing drilling fluid and the method and procedure of sampling
shall be proposed by the Contractor for approval prior to the commencement of
the work. The frequency may subsequently be varied as required, depending an
the consistency of the results obtained, subject to approval.
Control tests shall be carried out on the bentonite suspension, using suitable
apparatus. The density of freshly mixed bentonite suspension shall be measured
daily as a check on the quality of suspension being formed. The measuring device
shall be calibrated to read to within 5g/L. Tests to determine density, viscosity,
shear strength and pH value shall be applied to bentonite supplied to the pile bore.
For average soilconditions the results shall generally be within the ranges in Table
1.
The tests shall be carried out until consistent working pattern has been
established, account being taken at the mixing process, any blending of freshly
mixed bentonite suspension and previously used bentonite suspension. When the
results show consistent behavior, the tests for shear strength and pH value may be
discontinued, and tests to determine density and, viscosity shall be carried out as
agreed with the Engineer. In the event of a change in the established working
pattern, tests for shear strength and pH value shall be reintroduced for a period if
required.
TABLE 1
Property to be Range of results at Test methods
measured 20 deg. C
-9-
SECTION 8 CONCRETE PILE FOUNDATIONS
Where the Fann Viscometer is specified, the fluid sample should be screened by a
number 52 sieve (300 u) prior to testing.
8/12.1 The method of placing and workability of the concrete shall be such that a
continuous monolithic concrete shaft of the full cross-section is formed.
8/12.2 The concrete shall be placed without such interruption as would allow the
previously placed batch to have hardened. The method of placing shall be
approved.
8/12.3 The Contractor shall take all precautions in the design of the mix and placing of
concrete to avoid arching of the concrete in temporary casing. No soil liquid or
other foreign matter which would adversely affect the performance of the piles
shall be permitted to contaminate the concrete.
8/12.4 Slump measured at the time of discharge into the pile bore shall be in accordance
with the standards shown in table 2.The concrete shall be of the workability
approved when in its finial position and shall remain sufficiently workable for all
pile construction procedures to be safely completed.
TABLE 2
- 10 -
SECTION 8 CONCRETE PILE FOUNDATIONS
8/12.6 Approved measures shall be taken to ensure that the structural strength of
concrete placed in all piles is not impaired through grout loss, segregation or
bleeding. Concrete shall be directed vertically into the centre of each vertical pile
so that grout is not lost from the initial discharge.
8/12.7 Before placing concrete, measures shall be taken to ensure that there is to
accumulation of silt or other material at the base of the baring, and the Contractor
shall ensure that heavily contaminated bentonite suspension, which could impair
the free flow of concrete from the temie pipe, has not accumulated in the bottom
of the hole.
8/12.8 Concrete to be places under water or drilling fluid shall be placed by tremie and
shall not into the water or drilling fluid. Pumping of concrete may be approved
where appropriate.
8/12.9 A sample of the bentonite suspension shall be taken from the base of the boring
using an approved sampling device. If the specific gravity of the suspension
exceeds 1.20 the placing of concrete shall not proceed. In this event the
Contractor shall modify or replace the bentonite as approved to meet the
Specification.
8/12.10 The concrete shall be a rich coherent mix of high workability and cement in
accordance with Subsection 8/8.5 and mix C. Table 2. The concrete shall be
placed in such a manner that segregation does not occur.
8/12.11 The hopper and pipe of the tremie shall be clean and watertight throughout. The
pipe shall extend to the base of the bore and a sliding plug or barrier shall be
placed in the pipe to prevent direct contact between the first charge of concrete in
the tremie and the water or drilling fluid. The pipe shall at all times penetrate the
concrete which has previously been placed and shall not be withdrawn from the
concrete until completion of concreting. A sufficient quantity of concrete shall be
maintained within the pipe to ensure that the pressure from it exceeds that from
the water drilling fluid. The internal diameter of the pipe of the tremie shall be
mot less than 150 mm for concrete made with 20mm aggregate. It shall be so
designed that external projections are minimized, allowing the tremie to pass
within reinforcing cages without causing damage. The internal face of the pipe of
the tremie shall be free from projections.
8/12.12 No concrete shall be placed until all driving within a radius of 4.5 meters has been
completed, nor until all the shells for any one cluster have been completely
driven. If this cannot be done, all driving within above limits shall be
discontinued until the concrete in the last pile cast, has been set for at least seven
days.
8/12.13 Unless designated as basement piles all piles shall be placed with their tops at
least 1 metre above pile cut-off level in their respective pile caps. All boreholes
- 11 -
SECTION 8 CONCRETE PILE FOUNDATIONS
except for basement piles or unless otherwise specified, shall be filled with
concrete to the top of the hole so that the Engineer can be assured that all the
bentonite has been displaced by the concrete.
8/13.1 Temporary casings shall be extracted while the concrete within them remains
sufficiently workable to ensure that the concrete is not lifted. During extraction
the motion of the casing shall be maintained in an axial direction relative to the
pile.
8/13.2 When the casing is being extracted, a sufficient quantity of concrete shall be
maintained within it to ensure that pressure from external water. Drilling fluid or
soil is exceeded and that the pile is neither reduced in section nor contaminated.
8/13.3 The concrete level within a temporary casing shail be topped up where necessary
during the course of casing extraction in such a way that the case of the casing is
always below the concrete surface under the casting of the pile has been
completed.
8/13.4 Adequate precautions shall be taken an all cases where excess heads of water or
drilling fluid could occur as the casing is withdrawn because of the displacement
of water or fluid by the concrete as it flows into its final position against the walls
of the pile bore. Where two or more discontinuous lengths of casing (double
casing) are used in the construction the proposed method of working shall be
approved by the Engineer.
8/13.5 For piles cast in dry bores using temporary casing and without the use of a
permanent lining, pile heads shall be cast to a level above the specified cut-off so
that, after trimming, a sound concrete connection with the pile can be made. The
casing level shall be within the tolerance above the cut-off level shown in Table 3
but shall not be above the commencing surface level. No pile shall be cast with its
head below standing water level unless approved measures are taken to prevent
inflow of water causing segregation of the concrete as temporary Casing is
extracted; and where applicable, the standing water level for each pile shall be
agreed with the Engineer, and this level is to be treated as the cut-off level for the
purpose of calculating tolerance.
8/13.6 For piles Cast in dry bores within the permanent lining tubes or
permanent casings, or where their cut-off levels are in stable ground
below the base of any casing used, pile heads shall be cast to a level
above the specified cut-off so that, after trimming, a sound concrete
connection with the pile can be made. The Casting level shall be within the
tolerance above the cut-off level shown in Table 4, but shall not be above the
commencing surface level.
8/13.7 For piles cast under water or drilling fluid, the pile heads shall be cast to a level
above the specified cut-off so that, after trimming to remove all debris and
- 12 -
SECTION 8 CONCRETE PILE FOUNDATIONS
contaminated concrete, a sound concrete connection with the pile can be made.
The casing level shall be within the tolerance above the cut-off level shown in
Table 5, but shall not be above the commencing surface level. Cut-off levels may
be specified below the standing groundwater level, and where this condition
applies the borehole fluid level shall not be reduced below the standing ground
water level until the concrete has set.
8/13.8 Where the cut-off level of piles lies at depths greater than 10m below the
commencing surface, than the tolerances given in Tables 3 - 5 will be varied after
discussion with the Contractor and before commencement of the piling to take
account of the special conditions which apply.
8/13.9 During extraction of temporary casings, where circumstances are such that newly
placed unset concrete is brought into contact with external groundwater,
precautions shall be taken to ensure that the internal concrete pressure at all levels
within the pile exceeds the external ground water pressure.
TABLE 3. Casting tolerance above cut-off level for piles cast in dry bore using temporary
casing and without the use of a permanent lining.
0.3+H/12+C/8
0.15 – 10.00 where C=length of temporary casing
below the commencing surface *
TABLE 4. Casting tolerance above cut-off level for piles cast in dry bores within permanent
lining tubes or pelmanent casings, or where their cut-off levels are in stable
ground below the base of any casing used.
- 13 -
SECTION 8 CONCRETE PILE FOUNDATIONS
TABLE5. Casting tolerance above Cut-off level for piles cast under water or drilling fluid*.
1.0+H/12+C/8
0.15 – 10.00 where C=length of
temporary casing below the
commencing surface
in cases where a pile is cast so that the cut-off is within 2 permanent lining
tube, the appropriate tolerance is giver, by deletion of the casing term C/8 in
the table.
8/14.1 After each pile has been cast, any empty bore remaining shall be protected and
shall be carefully backfilled as soon as possible with the approved materials.
8/15.1 Disposal of excavated material shall be carried out by the Contractor as necessary
to facilitate the works and to the satisfaction of the Engineer.
8/16.1 When cutting off and trimming piles to the specified cut-off level, the Contractor
shall take care to avoid shattering or otherwise damaging the rest of the pile. Any
cracked or defective concrete shall be cut away and the pile repaired in an
approved manner to provide 2 full and sound section at the cut-off level.
8/17.1 Where integrity-testing is called for but the method is not specified, the method to
be adopted shall be approved by the Engineer and shall be one of the following.
i. Sonic Method
ii. Vibration Method
iii. Sonic Logging
8/17.2 Other methods may be adapted to the approval of the Engineer and subject to
satisfactory evidence of performance.
8/17.3 In the cast-in-place concrete piles, integrity tests shall not be carried out until 7
days or more have elapsed since pile-casting unless otherwise approved.
- 14 -
SECTION 8 CONCRETE PILE FOUNDATIONS
8/17.4 Where the method of testing requires the positioning of sensing equipment on the
pile head, the head shall be clean, free from water, laitence, loose concrete,
overspilled concrete and blinding concrete, and readily accessible for the purpose
of testing.
8/17.6 The interpretation, of tests shall be carried out by competent persons and the full
test results and findings shall normally be given to the engineer within 10 days of
the completion of each phase of testing. Full details of the ground conditions and
construction method shall be made available to the specialist firm when required
in order to facilitate interpretation of the tests.
8/18.1 Each test pile and working pile to be tested shall be loaded axially to 2.0 times
and 1.5 times the working load respectively as specified on the Drawings. The
tests shall not be commenced until the concrete has reached 90% of its testing
strength and shall be maintained on the pile as aforementioned or for such further
period as the Engineer may direct,
8/18.2 Loading tests shall be carried out at the date ordered on individual piles selected
by the Engineer.
i. The test load shall be applied by a method approved by the Engineer and
shall be measured within an accuracy of 2 percent. Settlements shall be
measured within an accuracy of 0.25mm.
ii. The test load and unloading shall be applied in suitable increments and as
smoothly and expeditiously as possible.
iii. The load after each increment shall be kept constant until the rate of
settlement does not exceed 0.25 mm per hour.
iv. The amount of settlement shall be recorded before the next load
increment.
v. The full test load shall be maintained for 48 hours and the total settlement
recorded. The load after each reduction shall be kept constant until the rate
of recovery does not exceed 0.25 mm per hour.
vi. The load after each reduction shall be kept constant until the rate of
recovery does not exceed 0.25mm per hour.
vii. The amount of recovery shall be recorded before the next load reduction.
viii. The Contractor shall, within 24 hours of the completion of the test, submit
to the Engineer for each pile tested graphs showing.
- Load and settlement plotted above and below a common
base line of time.
- Settlement and recovery plotted vertically against a base
line of time.
- 15 -
SECTION 8 CONCRETE PILE FOUNDATIONS
ix. The settlement of the pile under the test load and the recovery
of the pile after its subsequent removal shall be within the limits
agreed with the Engineer.
8/18.4 The temporary caps will be cut away and the debris removed by the Contractor.
8/18.5 The Contractor shall keep detailed records in collaboration with the Engineer of
the settlement and recovery of the pile as the increment of load are applied and
removed respectively.
8/18.6 The Contractor shall provide the Engineer with two copies of his records of each
test.
8/18.7 If the tests indicate that, in the opinion of the Engineer, the piles are unsatisfactory
for the working load, the Contractor shall at his own expense replace the tested
pile in a suitable position and if necessary support to be given to the structure to
be carried.
8/18.8 The Contractor shall bear the cost of any additional work made necessary as a
result of the unsatisfactory pile or piles. The Contractor shall also satisfy the
Engineer that any piles constructed prior and subsequent to the results of the tests
being known are capable of carrying the specified working load. Further tests
shall be carried out, if required by the engineer, and any piles deemed to be
unsatisfactory by the Engineer shall be replaced or augmented by further piles. No
extra cost will be accepted, or extension of time granted in connection with the
foregoing work.
8/18.9 The Contractor shall state in his proposals the measures he intends to take if the
ultimate load of any pile falls to reach the required value under the loading test,
with regard to lengthening, rendering and retesting of the test pile, and also to the
provision of additional piling to augment or replace the tested pile. No extra cost
will be accepted, or extension of time granted in connection with the foregoing
work.
8/18.11 Dynamic (High strain dynamic) pile load test in compression can be carried out
alternatively if any constrains to static pile load test. Subjected to the Client and the
Engineer's approval. The test shall be conducted based on ASTM D4945 method.
Dynamic pile load test shall be carried out a minimum of 5% of total number of
piles.
- 16 -
SECTION 8 CONCRETE PILE FOUNDATIONS
8/19.1 A pile shall be considered to have failed when any of the following conditions
apply:
- On completion of a load test, the residual settlement after rebound
- exceeds 6 mm.
- The test load as specified in the contract shall not have been
achieved.
- The maximum settlement exceeds 10 % of the least lateral
dimension of the pile under ultimate load.
8/20.1 In the event of a pile falling a load test, notwithstanding any contrary proposals by
the Contractor the Engineer may insist on the following methods of rectification
(as a minimum).
- When a trial pile - an additional trial pile shall be driven as directed
by the Engineer and tested. If this second trial pile fails, the
Engineer shall order such changes in the design of the pile as he
considers necessary.
- When part of the main piling operation - a further pile in the same
group shall be tested. If this second test pile fails, the Engineer
shall order such changes in the design of the pile/pile group as he
considers necessary.
8/20.2 In the case of the first pile of the main piling operation failing a test load, but
subsequent piles passing the load test, a new pile shall be driven to replace the
defective pile in a position agreed by the Engineer at the expense of the
Contractor.
8/20.3 In the event of additional works being carried out as a result of new piles being
required under this Clause, the cost of this additional work will be at the expense
of the Contractor.
8/21.1 All Piles shall have protective sleeve for a minimum, depth of 3 m below the cut-
off level of the pile. This sleeve shall be plastic or metal bedded in mastic to form
a fully water-proofed seal to the concrete.
8/22.1 Upon the completion of the works the Contractor shall clear away and remove
from the Site all constructional plant, equipment, surplus materials, rubbish, etc.,
and leave the whole of the Site and Works clean and in perfect condition to the
satisfaction of the Engineer.
- 17 -
SECTION 11 STRUCTURAL STEEL WORK
Section 11
Structural Steel Work
-1-
SECTION 11 STRUCTURAL STEEL WORK
11/1 GENERAL 3
-2-
SECTION 11 STRUCTURAL STEEL WORK
11/1 GENERAL
Contents
Page l
Table 2A Insert additional table title as follows: “2A Preliminary tightening of
nuts”.
-3-
SECTION 11 STRUCTURAL STEEL WORK
(i) For a thickness up to and including 25mm, by more than 4% below the
minimum thickness, and
(ii) For a thickness over 25mm, by more than that 4% below the nominal
thickness,
Otherwise allowed by Clauses 19.3, 20.3, 21.4 and 21.5 of BS 4360 and, if
appropriate, BS4: Part 1, BS 4848: Part 4 (with a minimum removal of 3mm) (see
also 10.4)
The procedure for the correction of the defects given in BS4360 Clause 10.4.1
shall not be permitted, and the procedure given in Clause 10.4.2 shall only be
carried out with the prior approval of the Engineer.
3.1.2., line 9
“The maximum carbon equivalent value for weather resistant steel shall be 0.54%
3.1.4.1, line 10
Delete ‘DD21’, insert “BS5996”.
3.1.4.2, line 3
Delete ‘DD21’, insert “BS 5996”.
“The chemical composition of bolts and nuts for weather resistant steel shall
comply with ASTM A3 25 TYPE 3Grade A or equivalent “.
Page 3
-4-
SECTION 11 STRUCTURAL STEEL WORK
“The chemical composition of washers for weather resistant steel shall comply
with ASTM A 325 Type 3 Grade A or equivalent”.
Unless otherwise described in the Contract, Stainless steel bolts and nests shall
comply with steel Grade A4 and property class 80 to BS 6105 and washers to BS
1449: Part 2 in the softened condition, grade 316 S 31. The dimensions and
tolerances shall comply with:
Insert additional paragraphs and table as follows:- “For weather resistant steel,
load indicating bolt heads or washers shall not be used.
Where bolt and nuts in compliance with BS 4395: Part 1 are tightened by the ‘part
turn’ method, the value of bedding torque for the preliminary tightening shall be
as in table 2A
Where bolt or washers with load indicating devices are described in the Contract
or approved by the Engineer, the range of the final average gap for each batch (as
defined in BS 4395) shall be established by testing a minimum of three bolt, nut
and washers assemblies in a bolt load meter, and agreed by the Engineer. The bolt
shall be tightened in two stages, and in sequence and pattern as agreed with the
Engineer, the range of the average gap after initial tightening shall be as agreed by
the Engineer. On final tightening of each bolt and nut, the average gap under the
bolt head or washer shall be within the agreed final range.”
-5-
SECTION 11 STRUCTURAL STEEL WORK
4.4.6 Para 1
Delete the second sentence (Lines 3 – 5)
4.7.1 Para 2, line 4
Delete Clause 23 of BS 5135 1974
Insert “BS 5135”
Page 5
4.7.1, after Para 6
Insert additional paragraphs as follows:-
“Unless otherwise described in the Contract, all butt weld shall be complete
penetration welds made between prepared fusions faces.
In the fabrication of built-up assemblies, all butt welds in each component part
shall be completed, whenever possible, before final assembly.
“Unless otherwise described in the Contract, all butt welds shall be complete
penetration welds made between prepared fusion faces.
-6-
SECTION 11 STRUCTURAL STEEL WORK
In the fabrication of built-up assemblies, all butts welds in each components part
shall be completed, whenever possible, before the final assembly.
“for welding trials, where galvanizing or other metal coating of the material is to
be applied to a part to a part which is to be subsequently welded in the shop or on
site, the same coating shall be applied to the sample material the procedure trials
are made.
For flame cutting, trials on materials 20mm thick shall be deemed to cover all
4.16, line 3
First sentence, after ‘BS 4360’ insert the following additional wording:-
All surfaces shall be maintained free from concrete, mortar, asphalt, paint, oil,
grease and any other debris or contaminants, and where specified, shall be blast
cleaned to assist the formation of a uniform coating. The quality of surface finish
shall be clean steel 2nd quality medium profile in compliance with Clause 10/7.
Faying surfaces of high strength friction grip joints shall be blast cleaned to clean
steel quality medium profile in compliance with Clause 10/7 and so maintained
until assembly.
Concrete piers, abutments and other specified areas shall be protected against rust
staining during construction”.
Page 6
5.2.2, line 2
Delete ‘DD21’, insert ‘BS 5996”
-7-
SECTION 11 STRUCTURAL STEEL WORK
Insert additional clause 5.2.3 as follows “5.2.3 Testing of bolts, nuts and washers
including HSFG
The frequency of sampling and testing of high strength friction grip bolts, nuts
and washers shall be in compliance with the appropriate part of BS 4395.
The frequency of sampling and testing of structural steel and stainless steel, bolts,
nuts and washers shall be as defined in BS 4395: Part”.
Page 7
5.5.2. Para 3, line 3
Delete ‘box girder’, insert box girder”.
5.5.2, after Para 3
Insert additional Para as follows:-
“Unless otherwise agreed by the Engineer, weld defect acceptance levels shall be
in compliance with table 5 of BS 4870: Part 1”
Page 9
6.3.1
7.1
Delete clause
7.2
Delete clause.
Page 15
-8-
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
Section12
Protection of Steel Work
Against Corrosion
1
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/1 General 1
2
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/1 General
12/2.1 Before Blast cleaning or abrading steel surfaces or before over coating painted or
galvanized surfaces, contamination by oil or grease shall be removed by wet
cleaning the affected surfaces as described in Clause 12/3.9. Solvents shall not be
used unless otherwise described in the Contract.
12/2.2 Clean water which does not leave harmful residues on the surface shall be used
for cleaning and rinsing.
12/2.3 Weld spatter shall be removed from accessible areas which are to be galvanized
or protected by metal spray or paint. Firmly adhering weld spatter in the heat
affected zone shall be removed before blast cleaning.
12/2.4 After dry surface preparation of internal surfaces and before any wet cleaning all
dust and debris shall be removed from accessible areas by sweeping and vacuum
cleaning.
12/2.5 Immediately before application of each coat of paint, the Contractor shall ensure
that the surfaces:
12/2.6 Joints, plies and fasteners shall be sealed in accordance with Clauses 12/4.27 and
12/4.28.
12/2.7 Coats of paints shall be free from embedded metallic or other foreign particles
including metallic dust. Deposits of adherent matter on metallic coatings or
painted surfaces shall be cleaned off immediately they occur. Coatings damage in
the process shall be restored.
12/2.8 Unless otherwise described in the Contract, the final shop coats on external
surfaces shall be wet cleaned on site.
3
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/3 Surface Preparation – Materials and Methods Dry Blast Cleaning in Shop
12/3.1 Unless otherwise described in the Contract chilled cast iron grit abrasive
complying with BS 2451 or steel of not less than 40 Hardness Rockwell C and
complying with the size requirements of BS 2451 shall be used.
12/3.2 Particle size of any abrasive in plant or equipment shall not exceed the maximum
for the relevant grade as specified above.
12/3.3 Before the start of blast cleaning and during blast cleaning the Contractor shall
ensure that the abrasive is free from matter which could leave detrimental
contamination, as defined in clause 12/7.7 on the surfaces to be treated.
12/3.4 Any encrusted foreign matter or paint which may be difficult to remove by
abrading alone shall with the Engineers approval be dislodged by scraping, aided
by hand or power wire brushing. This work shall be completed before abrading
the areas so affected.
12/3.5 Abrading shall be carried out using abrasive paper or other material or flexible
abrasive disc mounted on a power driven flexible pad, or a power driven arbor or
spindle-mounted flexible abrasive flap wheel. Abrading tools may be used to
remove weld spatter. Subject to the Engineer’s approval, wet abrading may be
employed for the preparation of finishes over sound undercoats, over unsound
systems over galvanizing, or galvanizing.
12/3.6 All equipment including tools, abrasive sheets, abrasive discs and abrasive wheels
shall be of a type, capacity and in a condition, approved by the Engineer. The
speed of revolution shall be as approved by the Engineer.
12/3.7 A burnished appearance cause by polishing in of paint, rust or dirt will not be
acceptable.
12/3.8 Areas of previously corroded steel ro unsound metal coatings, except galvanizing,
which have been prepared by abrading down to bright steel or bright metal
coating, and blast cleaned where appropriate, shall be protected by the primer and
next two coats of paint before any cleaning down or preparation of adjacent
surfaces.
4
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/3.9 Wet cleaning shall be carried out by scrubbing with stiff-bristled brush using
water and a cleaning agent. Immediately after cleaning, the surfaces shall be
thoroughly rinsed.
12/3.13 Within 60 minutes of wet blast cleaning, the whole of the cleaned surface shall be
thoroughly washed using the blast cleaning equipment with air and water. Any
further deposits of abrasive on already rinsed surfaces shall be removed in a
similar manner also within 60 minutes of being deposited. AH accumulated
deposits of abrasive and debris on other parts of the structure shall be removed by
the method before the end of the working day. After washing, the surfaces shall
be free from all particles of dust and debris. Test for freedom from detrimental
contamination shall be made after the washing.
12/3.15 The specified standard of surface preparation shall have been achieved in full
initially by wet blast cleaning and washing, before any later dry blast cleaning of
the same areas to remove flush rusting or to restore the required standard of
surface preparation.
5
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
Other Requirements
12/3.16 When surface preparation is to be carried out by dry blast cleaning and, on
adjacent surfaces, by wet cleaning and or abrading, then unless otherwise agreed
or required by the Engineer, the wet cleaning and any abrading shall be carried
out first.
When combined wet/dry blast cleaning has been specified instead of dry blast
cleaning only. The above sequence may be reversed. On completion of the wet
blast cleaning part of the process, the areas to be abraded shall be cleaned in
compliance with sub-clause 9 of this clause except that for rinsing, the wet blast
cleaning part of the process, and dry abrading shall be carried out after any wet
abrading required and final rinsing. Any prepared dry metal surface shall be
protected from the effects of any further wet method of surface preparation by the
application of the next two coats of paint including stripe coats.
12/4.3 Metal coatings on surfaces or fasteners which are to be painted shall be:
(i) Free from all traces of or grease and then washed with a mordant solution
or
(ii) Treated at the same time as the parent material where fasteners are already
assembled in compliance with sub-Clause 24 of this clause.
Fasteners excluding those in (ii)above shall be pressure rinsed with water and
allowed to dry before assembly or packing for delivery at least one hour and more
than four hours after satisfactory application of a mordant solution.
12/4.4 Fasteners which have become difficult to tighten because of corrosion shall be
replaced or treated as instructed by the Engineer
6
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/4.5 The standard of initial blast cleaning of joint material and parent material in joints
shall be at least equal to that for the parent material. Before a joint is made on site,
contact surfaces shall be restored to clean steel, 2nd Quality or to sound coating.
The blast primer applied to the parent material shall be taken 10mm to 15mm
inside the perimeter of the joints. The outer surfaces and edges of site joint
material may, at the opinion of the Contractor, also be given a coat of the blast
primer.
Unless otherwise described in the Contract, the metal spray shall be applied to the
contact surfaces of the joints and to the outer surfaces and edges of joint material.
The metal spray on the contact surfaces of the parent material shall be taken
10mm outside the perimeter of the joints. The blast primer applied to the parent
material shall be taken 10mm to 15mm inside the perimeter of the joints. The
metal spray on the outer surfaces and edges of site joint material shall be given a
coat of sealer.
12/4.8 In steelwork metal sprayed overall and sealed only or painted overall:
Unless otherwise described in the Contract, the metal spray shall be applied to the
contact surfaces of the joints and to the outer surfaces and edges of joint material.
The sealer applied to the parent material shall be taken 10mm to 15mm inside the
perimeter of the joints. The metal spray on outer surfaces and edges of site joint
material shall also be given a coat of sealer.
All material at joints shall be galvanized when a mordant solution and a first
undercoat are applied before a joint is made they shall be taken 10mm to 15mm
inside the perimeter of the joint, these coats shall also be applied to edges and
outer surfaces of the joint material.
12/4.10 The thickness of a protective paint coat applied to the outer surfaces of joint
material prior to assembly of any HSFG bolted joint shall not exceed 20mm dry
film thickness (dft).
At Non-Friction-Bolted Joints
7
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/4.11 At shop joints in all steelwork other than in galvanized steelwork the blast primer
alone or metal spray plus sealer shall be applied initially to parent and joint
material. Immediately before assembly of a joint which is to be painted the first
undercoat shall be applied to the contact surfaces and the joint made while the
paint is wet.
12/412 At site joints in all steelwork other than in galvanized steelwork unless otherwise
described in the Contract, all surfaces except those of fasteners, shall receive in
the shop protective system which is applied to the parent material.
12.4/13 At shop and site joints in galvanized steelwork mordant solution and shop coats
may be applied to the joint material before or after shop joints are made. When
galvanized steelwork is painted on site mordant solution and paint shall be applied
to joint material after the joint has been made.
At Welded Joints
12/4.14 At shop and site joints in all steelwork surfaces to be welded shall be restored to
clean steel, 2nd Quality or to bright steel and shall be free of any protective or
other coating immediately prior to welding.
12/4.15 The paint coats with the exception of the primer or first coat of paint shall be
stepped back at 30mm intervals commencing 10mm from the perimeter of the
joints.
At Non-Friction-Bolted Joints
12/4.16 Unless otherwise described in the Contract, shop paint coats are not required to be
stepped back.
At Welded Joints
12/4.17 Metal spray coating shall be kept clear of the weld by a distance of at least 15
times the thickness of the steel in the area to be welded, with a maximum of
300mm from the joint. The restricted area shall be masked during metal spraying.
Galvanizing shall be removed 5mm back from the edges of weld areas. Paint
coats shall be stepped back at 30mm intervals commencing at least 100mm from
the joint, or from the edge of the metal spray starting with the 2nd coat of paint
8
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
At Completed Joints
12/4.18 within 14 days, or such lesser time as directed by the Engineer, of a completed
joint having been passed by the Engineer, exposed surfaces of parent and joint
material shall be prepared in compliance with sub-Clause 19 to 23 of this Clause
and fasteners in compliance with sub-Clause 24 to 26 of this Clause.
At Bolted Joints
12/4.19 In steelwork painted only overall, blast cleaned only or primed surfaces shall be
prepared by dry blast cleaning or as otherwise agreed by the Engineer to restore or
provide the standard of surface preparation, for shop or site work as appropriate,
described in the Contract.
12/4.20 In steelwork metal sprayed at joints only, and painted overall, primed or sealed
metal sprayed coatings shall be prepared by dry blast cleaning or as otherwise
agreed by the Engineer to restore the surfaces to the standard described in the
Contract.
12/4.21 In steelwork metal sprayed overall, and sealed only or painted overall, metal spray
coatings shall be prepared as described in sub-Clause 20 of this Clause.
12/4.22 In steelwork galvanized only galvanized and painted overall the surfaces shall be
free from contamination detrimental to pain coats by wet cleaning.
At Welded Joints
12/4.23 In all steelwork, unless otherwise agreed by the Engineer, welds shall be prepared
by the methods and to the standards described in the Contract for shop ort sire
works as appropriate. Surfaces of areas adjacent to the weld shall be similarly
prepared.
Surface of Fasteners
12/4.24 Uncoated and temporarily coated fasteners shall be free from all but traces of oil
and grease and blast cleaned to clean steel, 2nd Quality, medium profile, before
painting.
12/4.25 Metal coated fasteners have been treated with mordant solution before assembly
shall be dry cleaned after final surface preparation of the joint and then painted.
12/4.26 Fasteners which are to be metal sprayed after assembly shall be blast cleaned to
clean steel, 1st Quality, medium profile, with chilled cast iron grit.
9
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/4.27 Bolted joints or built up sections shall be free from any water which has
penetrated the plies.
When drying out has been completed to the satisfaction of the Engineer or when
surfaces are dry after surface preparation, fine gaps around the perimeter of joints
or along plies shall be sealed by successive application of undercoat paint. AH
wider gaps shall be sealed with a proprietary sealant compatible with the primer
or undercoats and approved by the Engineer.
12/4.28 Unless otherwise agreed by the Engineer these gaps shall be sealed by brush
application of primer and successive undercoats, of the types on adjacent areas.
12/5.1 Score marks and indentations in the surface of a steel substrate or of a metal
coating shall be treated by abrading or grinding to bright steel or bright metal
coating, to produce a surface without sharp edges or abrupt change in contour.
Damage to unprepared surfaces shall be treated before blast cleaning. Unless
otherwise required by the Engineer, a blast cleaning profile shall be restored on
areas to be metal sprayed but not necessarily areas to be painted only. Other
surface defects in the steel substrate, including fissures caused by the removal of
‘hackles’ or inclusions described in Clause 12/7.3, shall be similarly treated
subject to the approval of the Engineer.
12/5.2 In the case of damage to pain coatings only, surface preparation shall be by
abrading or other method agreed with the Engineer. The paint coatings shall then
be restored.
12/5.3 Single pack blast primers may be omitted when an oleo-resinous system is being
restored over a steel substrate.
12/5.5 In the shops, a damaged metal spray coating, together with any damaged sealer or
paint coats, shall be restored.
12/5.6 On site, with the exception of small areas permitted under sub-Clause 7 of this
Clause, a damaged metal spray coating, together with any damaged sealer or paint
coats shall be restored but with a minimum thickness of 150urn of metal spray.
10
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/5.7 On site, small areas of isolated damage, as agreed with the Engineer, in as metal
spray coating plus paint system, need not be restored; after surface preparation in
compliance with sub-Clause 1 of this clause, the metal spray shall be replaced by
100mm of the first undercoats, omitting the sealer. Adjacent paint coats,
excluding the sealer shall then be restored over the repaired area.
12/5.8 In the shops, in the case of galvanizing only, small isolated areas of in to 40mm²
may, after surface preparation, be repaired with low melting point zinc alloy.
Isolated areas of damage larger than 40mm² in galvanizing which is to be painted
later or which has already been painted may be repaired with low melting point
zinc alloy after surface preparation. Alternatively the whole of the affected area
including exposed steel substrate shall, after surface preparation, be given a coat
of mordant solution which, when wet cleaned in accordance with Clause 10/3.9
and finally dry, shall be over coated with two coats of MIO Epoxy Primer,
medium gray, 2 pack, to a total minimum dft (mdft) of 150urn. The mordant
solution and Epoxy paint shall not be applied over existing paints.
All repair work shall only be undertaken when agreed by the Engineer and shall
be to his approval, otherwise the component shall be regalvanised.
12/5.9 On site, galvanized components found to have minor damage, as agreed with the
Engineer, may be repaired as described in sub-clause 8 of this Clause, otherwise
the components shall regalvanised.
12/5.10 In all cases where paint coats only are to be restored, or metal spray coals
replaced or restored, or galvanizing is to be replaced by paint, the edges of paint
coatings or metal coating adjacent to the affected area shall be beveled back into
sound paint or metal coating. This work shall be carried out before any final blast
cleaning described in sub-Clause 4 of this Clause.
12/5.11 Unless otherwise agreed by the Engineer, mordant solution applied outside the
agreed areas shall be removed immediately by wet cleaning.
12/5.12 In the shops exposure and over coating times shall not exceed those specified in
Clauses.
On site, unless otherwise agreed by the Engineer, over coating shall be carted
immediately after surface preparation of the affected area and continued as soon
as each coat is dry enough for over coating.
12/6.1 In the shops failed paint coatings and failed metal spray coatings shall be restored.
Abrading down to sound paint only is permissible. If a metal spray coating is
damaged or reduced to less than 80% of the specified minimum thickness during
abrading, it shall be restored.
11
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/6.2 On site failed paint coatings and metal spray coatings shall be restored except that
abrading down to sound paint or to bright steel and blast cleaning to clean steel,
2nd quality are permissible methods of surface preparation when restoring paint
systems over steel substrate.
12/6.3 In the shops, and on site unless otherwise agreed by the Engineer, galvanized
components showing signs of failure of the coating shall be regalvanised. On site,
in exceptional circumstances agreed by the Engineer, defective galvanizing may
be replaced by sealed aluminum metal spray.
12/6.4 In the shops and on site. Failed paint coatings over galvanizing shall be restored.
Unless otherwise agreed by the Engineer, surface preparation shall be by
abrading. Areas of sound galvanizing exposed through a paint system shall be
abraded only as necessary to ensure satisfactory application of mordant solution
and paint. If the galvanizing is damaged or reduced to less than 80% of the
specified minimum thickness during abrading, the component shall be
regalvanised.
12/6.5 In all cases of local failure, the extent of the failure and the required surface
preparation shall be agreed with the Engineer. Restoration of protective coatings
shall not be started until the standard of surface preparation, including the
cleanliness of the surface, has been passes as satisfactory by the Engineer.
12/7.1 The surface profile to be achieved by blast cleaning, either Tine “Medium” or
“Coarse”, as described in the Contract, shall be within the limits set by the
Surface Profile Comparator for the Assessment of Abrasive blast Cleaned
Surfaces, conforming to International Standard 8503 Part 1.
12/7.2. Blast cleaned surfaces shall be virtually free from sharp spikes of parent metal
defined as ‘rogue peaks’ formed by the impact of abrasive particles and which
project above the blast cleaning profile. Any “rogue peaks’ which in the opinion
of the Engineer would be detrimental to the protective system shall be removed.
12/7.3 “Hackles” and inclusions caused by the rolling process, visible after blast
cleaning, which in the opinion of the Engineer would be detrimental to the
protective system, shall be removed. Affected surfaces shall be prepared by
grinding or abrading to bright steel in compliance with Clause 10/5.1 where
appropriate. Sharp edges shall be rounded. If metal spray is to be applied the
surfaces shall then be blast cleaned.
12
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/7.4 Steel surfaces to be prepared by any of the methods described in the Contract
shall be such that after surface preparation the surfaces shall be free from
detrimental contamination.
10/7.5 Surface preparation by blast cleaning shall be to one or more of the following
standards of visual cleanliness:
There shall be a blast cleaning pattern overall. The surface profile shall be free
from mill scale, rust and foreign matter when viewed through an X10 illuminated
magnifying glass of a type approved by the Engineer.
Appearance:
There shall be a blast cleaning pattern overall. The surface profile shall be free
from mill scale, rust and foreign matter when viewed by normal vision.
Appearance:
The surface shall be free from all rust scale, loose rust and loose mill scale.
12/7.6 After surface preparation by blast cleaning to 1st or 2nd Quality the surface profile
shall be virtually free from embedded abrasive particles when viewed through an
X10 illuminated magnifying glass of a type approved by the Engineer. Surfaces
assessed as unsatisfactory in this respect by the Engineer shall be blast cleaned
again with fresh abrasive. Other abrasive complying with the specification may be
used.
13
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
(i) Any visible gloss which may, in the opinion of the Engineer, prevent
adequate adhesion of the next coat.
12/8.2 Definition of terms used in describing the above standards of workmanship are as
follows:
(iv) Bright metal coating resulting from abrading: The surfaces shall be free
from all corrosion products and of bright appearance overall
14
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
(vi) “Sound metal coating”, a metal coating which complies with Clause
12/11.2 including such a metal coating which has been blast cleaned but
which has a reduced thickness in accordance with Clause 12/6.1
12/8.3 Definitions of terms used in Clause 12/4, 12/5 and 12/6 are as follows:
When “clean steel” is exposed through a metal spray coating during remedial
surface preparation, remnants of sound aluminum metal spray coaling may,
subject to the agreement of the engineer, be retained in a blast cleaning profile;
also, subject to the agreement of the engineer, traces of zinc metal may remain
occluded within the surface of a blast cleaning profile after removal of a zinc
metal spray coating.
12/9.1 The team paint in this Specification shall be deemed to refer also to similar
protective coatings including specialist coatings such as grease paints.
15
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/9.2 All paint proposed shall be supported by technical data including, but not
limited to the following:
12/9.3 All paints shall be supplied in sealed containers of not more than 5 liters capacity
and these shall be used in order of delivery. Each container shall be clearly
marked on the side to show the mane of the manufacturer registered description of
the material (including purpose, e.g whether primer, undercoat or finish), color,
paint manufacturer’s reference number, batch number and date of manufacture.
12/9.4 The contractor shall ensure that the properties of the paints he has selected are
suitable for the conditions in the shops and on site, including temperature and
humidity, and that he is able to apply the paints satisfactorily to all parts of the
structure in these conditions.
12/9.5 Unless otherwise described in the Contract all paints forming any one protective
system or overlapping systems, shall be obtained from the same manufacturer, as
named in the proposed system submitted by the Contractor. Unless the source of
supply is rejected by the Engineer it shall not be changed once the proposed
system has been submitted for approval.
Provision of Samples
The contractor shall supply 500ml samples, for application control purposes.
The Contractor shall supply 500ml samples of paints for application control
purposes samples when instructed by the Engineer, and only under his
supervision. The samples shall be taken from painter’s kettles or from nozzles of
airless spray guns directly into clean, new 500mm tins which shall be filled and
then sealed and handed to the Engineer. On return of the samples to the
Contractor, the Contractor shall dispatch them immediately to the testing
authority in accordance with the Engineer’s instructions.
16
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
(i) Inhibited hydrochloric acid with a strength not exceeding 14% and
within a temperature range of 15° to 25° or inhibited sulphuric acid
with a strength not exceeding 14% and within a temperature range
of 60° C to 80° shall be used for pickling.
(ii) Components shall not be immersed in the pickling acid longer than
is necessary for cleaning the surfaces prior to galvanizing.
(iii) The surfaces of components to be galvanized shall be dried before
immersion in the molten zinc.
(iv) When an aqueous flux is to be used all traces of acid shall be
washed off immediately after pickling.
(v) Galvanized coatings shall be virtually free from imperfections,
including porosity, to the satisfaction of the Engineer.
(vi) Detrimental surface contamination of galvanized coating which are
to be painted shall be removed by wet cleaning in compliance with
Clause 12/3.9. Te surface shall not receive chromate passivation
treatment.
(vii) Vent holes drilled in hollow section prior to galvanizing shall be
plugged to the satisfaction of the Engineer.
Sprayed metal coatings shall, unless otherwise in the Contract, comply with
BS2569: Part 1 Sprayed Metal Coating (protection of iron and steel by aluminum
and zinc against atmosphere corrosion) and with the following:
(i) Aluminum coating shall be material GIB with composition in accordance with
BS 1475 Wrought aluminum and aluminum alloys for general engineering
purposes wire, and zinc coating shall be material Zn 3 with composition in
accordance with BS 8436 Ingot zinc
(ii) The thickness of either coating shall be not less than 100mm
(iii) The strength of adhesion of metal spray coatings shall not be less than the
following:
Aluminum 50 kgf/cm2
Zinc 80 kgf/cm2
17
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
(iv) Metal spray coatings shall be applied continuously over each 0.5m2 per gun or
the area of the component whichever is the lesser until; the specified thickness
has been achieved
(v) The procedure for applying metal spray is separate layers described in the
NOTE in Clause 4 and Clause 7 of BS2569 is no permitted.
(vi) All surfaces to be metal spayed, including that of the reference panel
described in Appendix A to BS 2569, shall be blast cleaned with chilled cast
iron grit, and the standard shall be clean steel, 1st Quality medium profile.
Sheradised coatings shall, unless otherwise described in the contract, comply with
Class 1 table 1 of BS 4921. Sherardised coating on iron and steel articles
Other Requirements
12/11.5 Before proceeding with the galvanizing process the Contractor shall provide full
details of the surface preparation and coating methods he proposed to adopt and
shall not put the work in hand until the Engineer’s permission has been received.
Such permission shall not relieve the Contractor of his responsibilities under the
Contract. When instructed by the engineer, similar requirements shall apply in the
case of other metal coating.
12/12.1 At the start of the Contract, and later at intervals specified by the Engineer (with
the exception of coating on steel in bearings, curved surfaces, repairs to
mechanical damage, local failure of metal spray at site joints or areas restored on
site) the Contractor shall demonstrate by means of a pull off test, of a type
approved by Engineer, that the minimum adhesion required is being attained. In
the excepted areas the Contractor shall demonstrate to the satisfaction of the
engineer that the adhesion is satisfactory when tested in accordance with BS
2569. Areas affected by the test shall be restored.
18
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/12.2 The pull of test shall be carried out initially on panels 150mm x 150mm x 6mm
which are of the same grade of steel as the parent material and which before glass
cleaning had the same surface condition. The panels shall be blast cleaned and
metal sprayed together with the parent material to the same standard and using the
same techniques.
12/12.3 The Contractor shall make arrangements for the Engineer to witness the
preparation of the panels and all testing. When instructed by the engineer, the
Contractor shall carry out further tests on similarly prepared and metal – sprayed
panels.
12/12.4 If the adhesion requirement on any test panel is not met, the Contractor shall carry
out a farther test on the parent material adjacent to the panel position. In the case
of adhesion failure on the steelwork itself by other method of test, the metal spray
shall be restored top an extent specified by the Engineer and the tests repeated.
12/12.5 If more than two local areas of faulty adhesion occur on any one component, he
whole of the metal spray coating on the component shall be considered as having
failed, and it shall be restored. Clause 12/8.4 is not applicable in the case of
adhesion failure
12/13.1 On delivery to the shop or site, paint shall be unloaded directly into one or more
secure paints stores. Unless otherwise agreed by the Engineer, paint shall be
stored within 100 meters of the painting area. Insulation and means of ventilating
shall be provided as necessary to maintain the temperature of paint stores between
5o C and 27o C.
If at any time or place paint in tins, painters kettles or airless spray containers is
allowed to reach temperature outside the 5% and 27o limits, the paint shall be
discarded and not used for the works. The Contractor shall also implement any
conditional storage restriction recommended by the paint manufacturer.
12/13.2 Unless accepted in sub – Clause 4 of this Clause, paint which has not been used
within the shelf life recommended by the manufacturer or within 12 months of the
date of manufacture, whichever is the lesser, shall be discarded and not used in
the work.
12/13.3 Chemically or moisture cured paints shall not be used after the expiry of the pot
life stipulated by the paint manufacturer. They shall be discarded on expiry of the
pot life or at the end of each working day / night whichever is the less. All other
paints in opened tins or open containers including painters’ kettles shall be
returned to store and keep in sealed containers which not more than 10% ullage.
19
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
cured Epoxy paints may have their keeping period extended to 24 months
provided that the Contractor returns the paints to the paint manufacturer and
reconstitute the paints as necessary so that such paints are equal in all respect to
the paints described in the Contract.
12/13.5 Each tin of reconstituted paint returned to the shops or sites by the manufacturer
shall have an additional label affixed extended keeping period to (date) the
previous date marking shall remain and not be obscured. Agreement by the
Engineer to extended keeping periods for certain paints does not relieve the
Contractor of his responsibilities as described in the Clause 12/9. Testing in
compliance with Clause 12/10 shall apply to reconstituted paints.
12/14.1 Paint shall be supplied from the Contractor’s paint store to the painter ready for
application, the adjustment of formulation permitted being as described in the
Clause 1915.4. Any additional of solvent shall be made in the store in the
presence of the Engineer, and shall not exceed 5% by volume on the paint.
12/14.2 Paint shall be applied only in the surface which have been prepared and cleaned
as described in this Section.
12/14.3 Unless otherwise described in the Contract a coat of paint in the system shall be
applied by one of the following method:
(i) brush
(ii) airless spray
(iii) air pressure spray
12/14.5 All shop painting of steel work shall be carried out in the fully enclosed workshop
unless otherwise agreed by the Engineer.
12/14.6 Before starting the application of coats and as required by the Engineer, the
Contractor shall furnish the Engineer with details of the overall wet film thickness
for each coat he proposes to apply. He shall also provide information as to the
total amount of paint he expects to use for each coat of each system during any
contract for which [procedure trials are required. The calculation of the amount of
20
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
the amount of paint to be used shall be based on the volume solids phis an
allowance for waste.
12/14.10 When required by the engineer, the degree of gloss of the finishing coat
shall be agreed before application. A painted tinplate reference panel,
150mm x 100mm, shall be provided by the Contractor for this purpose.
12/14.11 All successive coats in a system including the stripe coats shall be in
contrasting colors to aid identification.
12/14.12 Two pack chemically cured paints shall not be applied when the steel or
ambient temperatures are below those advised by the paint manufacturer,
nor shall such paints be applied when the temearture is likely to fall below
the advised temperatures during the curing period.
Stripe Coats
12/14.13 Unless otherwise described in the Contract two stripe coats shall be applied to all
welds and all fasteners including washers and to external comers except those of
RHS sections. The first stripe coat, in second undercoat paint shall be applied
21
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
over the primer, sealer or mordant solution the second stripe coat, in second and
third undercoat paint, shall be applied before the last undercoat of the complete
system in the shop or on site as appropriate. The first stripe coat on fasteners
treated with mordant solution shall apply by brush; other stripe coat may be
applied by brush or airless spray appropriate
12/14.14 Square solid infill bars shall, after the second undercoat has been applied, be
given an extra coat of first undercoat in lieu of stripe coats.
12/14.15 clean steel prepared by dry blast cleaning or bright steel prepared by abrading or
by grinding shall be primed within 4 hours.
12/4.16 clean steel prepared by wet blast cleaning only, shall be primed within 4 hours of
being dry enough for painting.
12/4.17 Clean steel prepared by combined wet/dry blast cleaning shall be primed within 4
hours of dry blast cleaning.
12/4.18 Steel or steelwork blast primed at the mills or in the shops shall be overcoated
within 18 weeks. The primed surfaces shall only be exposed outside for a
maximum of 2 weeks of the 8-week period. Prepared surfaces affected by
detrimental contamination or corrosion which in the opinion of the Engineer will
reduce the required durability of the protective system shall be restored when
directed by the Engineer.
12/4.19 Steelwork which has been metal sprayed in the shops shall be primed or sealed
within 4 hours. The next coat shall be applied within 72 hours.
12/14.20 Prepared steel surfaces, unsealed metal spray coatings and undercoats, excepting
final shop undercoat, shall not be exposed outside the shops.
12/14.21 All surfaces treated with mordant solution, except those of fasteners which have
been treated in compliance with Clause 12/4.3, shall, after initial drying, be wet
cleaned in compliance with Clause 12/3.9 and allowed to dry before overcoating.
The first coat of paint shall be applied within 48 hours of surfaces treated with
mordant solution being first dry enough for painting over.
12/14.22 When galvanized steel is to be protected by a paint system, mordant solution shall
be applied not later than 14 days after delivery to site unless otherwise agreed by
the Engineer.
12/14.23 A first shop undercoat shall be overcoated within 72 hours. Unless otherwise
agreed with the Engineer, further shop coats shall be applies within 72 hour
interval per coat.
22
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/14.24 the application of sealant in gaps in compliance with Clause 12/4.27, may be
carried out either before or after application, as appropriate, of the first coat of
paint to be applied to the completed joints or assembled plies.
12/14.25 Prepared steel surfaces and sprayed metal coatings which have been restored, also
paint coats and galvanizing which have been prepared after surface damage or
deterioration shall be overcoated with the primer or first undercoat as appropriate
before the surfaces have been affected by moisture and in any case within 4 hours.
12/14.26 Steel surfaces and metal spray coatings which have been primed or sealed on site
shall have the following coat applied with 7 days the next coat shall be applied
within a further 14 days, or such lesser time recommended by the paint
manufacturer.
12/15.1 Steel awaiting fabrication for the Contract and over coated steelwork shall be
adequately protected from contaminants liable heavy rusting and possibly pitting
of the surface.
12/15.2 Steelwork shall not be loaded for transport until the paint system is sufficiently
hard for handling.
12/15.3 During storage, steelwork shall be kept clear of loose ground and shall be laid out
or stacked so as to prevent water or dirt accumulating on or against any of the
surfaces. Suitable packing shall be placed between layers of stacked steelwork.
When cover is provided it shall be ventilated sufficiently to keep condensation to
a minimum.
12/15.4 Components weighing less than one ton shall be kept in a storage area away from
then-erection point in order to minimize damage to protective coatings.
12/15.5 Lengths of parapet and the like shall be supported on timber, and precautions
taken to prevent damage to their protective coatings and ingress of water. They
shall only be positioned adjacent to their erection point immediately before
erection. If the planned erection time is delayed by more than 72 hours the
components shall be returned to the storage area.
12/16.1 Unless otherwise described in the Contract, metal spray coatings and all shop
paint coats shall be returned 25mm into the concrete steelwork contact area.
23
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
12/16.2 Where aluminum metal spray, which has been sealed only, is returned into the
contact area, it shall be given a 40mm mdft coat of Zinc Phosphate Epoxy Ester
Undercoat, not later than 48 hours before concreting; application of the paint
outside the contact area shall be prevented, by masking if necessary.
12/16.3 Galvanised coatings shall be applied overall. Unless otherwise described in the
Contract concrete may come into direct contact with the galvanized surfaces.
12/17.1 As soon as the Contract has been let the Contractor shall submit for approval full
details of the paint system to be used, including documentation of usage in similar
environmental conditions to those in Dubai.
12/18.2 Manual surface preparation and coaling application work shall not be carried out
when natural light intensity at the workface is less than 500 lux. When the light
intensity falls below this level the Contractor shall install and maintain temporary
lighting which shall provide a minimum light intensity of 500 lux over at least
1.0m² at the workface during the work and also for inspection when required by
the Engineer.
12/19.1 Where indicated on the Contract Drawings, these areas shall be finished with a
3.5mm thick, heavy duty flow applied tar modified epoxy resin based lightweight,
anti-slip surface dressing with the following physical properties:
24
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
The tar modified epoxy resin slurry shall be a multi-component system, surface
dressed with an inert, hard-wearing aggregate. The system shall provide a
lightweight, flexible, spark resistant, chemical and abrasion resistant surface
treatment.
The surface dressing system shall have proven successful track record of us in
similar applications under local ambient conditions.
12/19.2 The tar modified epoxy resin surface dressing shall be applied to the prepared and
primed susbstrate to a thickness of no less than 3.5mm. A wet film gauge shall be
used to ensure that the minimum thickness is achieved. The surface dressing
aggregate shall be immediately applied by blinding the slurry coat to saturations.
All surface preparation, priming, mixing and application of the surface dressing
system shall be carried out in s strict accordance with the manufacturer’s
instructions by a specialized applicator approved and recommended by the system
manufacturer.
Note: Epoxy micaceous iron ore, with a minimum of 80% MIO pigment as a percentage of the
overall pigment weight.
25
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
26
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
27
SECTION 12 PROTECTION OF STEEL WORK AGAINST CORROSION
Schedule 12/1/3
Bridge steelwork
Area C: Paved area of deck and
treads and risers of stairs
28
Section 13
Deck and Staircase
SECTION 13 DECK AND STAIRCASE
SUB-
SECTION DESCRIPTION PAGE
13/1.0 GENERAL 2
13/2.0 CABLES 6
13/3.0 EARTHING 16
-1-
SECTION 13 DECK AND STAIRCASE
13/1.1 GENERAL
13/1.2.1 General
A. Provide a method statement that explains the strategy for the planning
and Execution of the Works on receipt of approved material submittal
stage.
B. The method statement shall include, but not be limited to, programs,
proposals for temporary work and installation sequence plans.
C. Method statements shall include work certified reports verifying
compliance with specified materials and systems.
-2-
SECTION 13 DECK AND STAIRCASE
13/1.3 Warranties
13/1.3.1 General
13/1.4.1 General
-3-
SECTION 13 DECK AND STAIRCASE
i. Luminaires
ii. LV and Control Cables
iii. Lighting Cabinets /Distribution Boards
iv. The Scope of Inspection Shall Include Type Tests, Document
Control & Routine Test And Inspections.
A. Prepare test schedules and test record forms for the tests requested in
each chapter, and as specified in the project specification as applicable
to the works. Schedules shall be issued for review prior to the
execution of testing.
B. Provide RTA with details of each testing agent for acceptance.
C. Test procedure and all related forms/documents should be submitted
for approval by the Engineer/Employer.
A. Prepare test schedules, test record forms and submit to RTA for
acceptance prior to testing. the test should follow the engineer
test/inspection with result confirming material compliance to
specifications and contract requirements.
B. Provide calibrated test apparatus, including calibration certificates and
conduct the following tests as a minimum:
i. Polarity.
ii. Load balancing of phases.
iii. Verification of phase, neutral and earth identifications.
iv. Verification of labeling, and wire and terminal numbering.
v. Continuity.
vi. Insulation (phase-phase; phase-neutral; phase-earth; neutral-
earth with a 1000V insulation tester).
vii. Insulation shall exceed 10 mega ohm per metre cable length.
viii. Effectiveness of individual electrodes.
ix. Checking of voltages at transformer, switchboards and each
luminaire, and setting of appropriate tappings on control gear.
x. Lighting Measurements.
-4-
SECTION 13 DECK AND STAIRCASE
13/1.4.6 Commissioning
B. Reference Standards
ii. All Standards and Codes referred to shall be the latest issue at the time
of invitation to Tender.
E. The Following Are The General Conditions Under Which The Cable
Shall Operate:-
13/2.0 CABLES
A. All cables accessories and materials shall be of the best quality and
most suitable for local climatic conditions and shall be such that the
cable shall withstand without damage, any conditions arising from
short circuits, switching operations and sudden variations of load and
voltage as may be met under normal working conditions. The cable
shall be suitable to be buried directly in saline soil. The Contractor
shall submit for approval a sample cut-piece of each type of cable and
one metre length of any cable size with the required embossment. The
materials are to be accompanied by manufacturers’ installation
instructions. This specification provides for manufacturing, testing of
four core power stranded copper conductor XLPE/SWA/MDPE cable,
rated service voltage 600/1000 volts.
A. Cables between sub stations and MDBs shall comply with the
following minimum requirements. Project specific requirements shall
be identified and tabulated for each installation condition:
B. Cable Buildup: Cu/XLPE/PVC/ SWA/ MDPE (ST-7).
C. Voltage rating: 600/ 1000 Volts.
D. Core: 4 cores 50 mm2 and above.
E. Insulation type/ thickness: XLPE.
-6-
SECTION 13 DECK AND STAIRCASE
13/2.1.3 DB to luminaires
Earthing cables shall comply with the following minimum requirements. Project
specific requirements shall be identified and tabulated for each installation condition.
-7-
SECTION 13 DECK AND STAIRCASE
F. The earthing cable shall run all the way from the source electrical
control cubicle to the last luminaire on each circuit.
i. First Line:
a. “ROADS AND TRANSPORT AUTHORITY LIGHTING
600/1000 VOLT”.
ii. Second line
a. The second line legend shall be aligned with the first line
along the circumference.
b. The second line shall include the cable manufacturer, year
of manufacture, country, number of cores x conductor cross
section, type and metering length marked at regular
intervals on the sheath, as per the following example:
-8-
SECTION 13 DECK AND STAIRCASE
13/2.2.1 Material
A. Submit manufacturer's test data confirming that the cables meet the
requirement of the Specification.
B. Submit copy of deck /staircase lighting Shop Drawings/Design and
BOQ.
13/2.3.1 General
-9-
SECTION 13 DECK AND STAIRCASE
13/2.3.4 Construction
A. Conductors
i. The conductors shall be stranded plain annealed copper in
accordance with IEC Publication 228: Conductors of Insulated
Cables or BS EN 60228:05.
ii. The conductors shall comply with the test requirements
mentioned at Clause 9 of BS EN 60228:05 and test certificates
from independent authorities / labs. shall be submitted.
B. Insulation
C. Bedding
- 10 -
SECTION 13 DECK AND STAIRCASE
E. Wire Armour
F. Armour Tests
G. Oversheath
H. Testing of Cables
i. Conductor
a. The conductors shall be stranded plain annealed copper in accordance
with IEC Publication 228: Conductors of Insulation Cables or BS EN
60228:05.
b. The conductor shall comply with the test requirements mentioned at
Clause 9 of BS EN 60228:05 and test certificates from independent
authorities / laboratories shall be submitted.
ii. Insulation
- 11 -
SECTION 13 DECK AND STAIRCASE
b. Second Line:
1. “XXXX 19XX UAE 4 x XX MM CU 3955 M”
2. This shall be equally spaced with the first line along the
circumference. An identification of the manufacturer, year,
country, number of cores x conductor cross section, type and
metering length shall be marked at regular intervals on the sheath.
This shall not affect the spacing between repetitions of the legend
for the voltage designation.
i. Before dispatch, the manufacturer shall cap the ends of all cables so as
to form a seal to prevent the ingress of water during transportation.
ii. All cables shall be delivered to site with the manufacturer's seals,
labels or other proof of origin intact. The labels and seals shall be
retained for inspection by the Engineer.
iii. Each drum length of cable shall be allotted a distinctive and separate
reference number. This number shall appear on the Test Sheets
covering the respective length of cable and shall also be clearly marked
on the cable drum. All cables shall be capped on the drum to prevent
the ingress of water.
- 12 -
SECTION 13 DECK AND STAIRCASE
13/2.5.1 General
- 13 -
SECTION 13 DECK AND STAIRCASE
A. Conduits shall be uPVC and comply with BS 4607, be suitable for the
climatic conditions. Conduit joints shall be cemented. During
construction conduits shall be protected to prevent movement, ingress
of moisture and dirt, and damage. Any open ends shall be capped to
keep out dirt and moisture. Conduits shall be installed in straight runs,
level, and parallel or perpendicular to the structure, and to avoid the
spread of fire and ingress of moisture. Conduits shall be installed with
all requisite accessories. Internal burrs shall be removed from the
conduit ends.
C. Where cables cross under roads and paved areas they shall be drawn
into uPVC ducts provided complete with temporary tapering uPVC
end caps of suitable diameter to prevent the ingress of soil into the
ducts.
i. The removal of temporary plugs, rodding and cleaning of the ducts
shall be carried out by the Contractor. The ducts shall be sealed with
foam or other suitable sealing material after the cables have been
drawn through.
B. Runs shall be neat and free from kinks, care being taken in the routing
to avoid risk of damage to or interference with other equipment.
- 14 -
SECTION 13 DECK AND STAIRCASE
- 15 -
SECTION 13 DECK AND STAIRCASE
Any cable sizes shown on the tender drawing are indicative and for
tender purposes only, it will be the responsibility of the Contractor to
check and size the cables for acceptance by the Engineer as necessary.
R. Where cable runs, conduit and trunking pass through fire barrier walls
and partitions, they shall be sealed against smoke and fire by a
proprietary material having third party verification of performance.
Cable trunking shall also be sealed inside at the point where it passes
through the barrier with the same material.
S. Adequate allowance for expansion shall be made in all conduits,
trunking and tray-work runs, where they cross building expansion
joints or are subject to wide fluctuations in ambient temperature.
13/3.0 EARTHING
- 16 -
SECTION 13 DECK AND STAIRCASE
A. This test will be applied to each section of cables and will comprise
of:-
i. Phase to phase insulation resistance.
ii. Phase to neutral insulation resistance.
iii. Phase to earth insulation resistance.
iv. Neutral to earth insulation resistance.
B. The resultant insulation resistance for any of the above measurements
shall not be less than 10 mega ohm per metre cable length and
measured with 1000 volt.
C. For these tests, a voltage not less than 2.5 times the normal voltage of
the supply shall be applied for the measurement of insulation
resistance.
- 17 -
SECTION 13 DECK AND STAIRCASE
to the main earth electrode shall not exceed 1 ohm, and the resistance
to earth at this termination shall not exceed 0.5 ohm.
B. Inspection certificates, completed by the Contractor shall be generally
in accordance with IET regulations.
C. Brand type and calibration report of test equipment used for testing the
electrical installation by the Contractor shall be subject to the approval
of the Engineer.
D. These calibration reports are to be submitted to the Roads & Transport
Authority Street Lighting Section and Maintenance Section along with
the test results prior to the commencement of the maintenance period.
E. Owing to the highly corrosive nature of the sub-soil at certain locations
the Dubai Electricity and Water Authority shall be consulted regarding
the metal to be used for the earth termination.
F. Earth and Insulation test to be witnessed by the Engineer/RTA.
Environmental Conditions
Corrosion
Deflections
A. The works shall not deflect under loading in any way that is
detrimental to any element of the works.
- 18 -
SECTION 13 DECK AND STAIRCASE
Movements
A. The works shall resist applied static and dynamic loads likely to be
encountered without causing permanent deformation of components or
the failure of systems, materials or seals and shall transmit such loads
safely to the points of support.
Seismic Performance
Thermal Performance
Moisture Resistance
A. The works shall not suffer temporary or permanent deformation nor
any reduction in performance due to changes in the moisture content of
nents, resulting from variations in the moisture content of the air.
Fire Performance
- 19 -
SECTION 13 DECK AND STAIRCASE
A. The contractor shall submit along with the offer 5 sets of luminaires of
each type to equip 5 mast for examination and photometrical test on
site.
B. The materials to be accompanied by manufacturer's assembling and
erection instruction.
C. The contractor shall carry out site testing after installation work is
completed for photometric performance in accordance with the
contract specification requirements. All the test shall be carried out in
the presence of the Engineer. The luminance measuring device shall be
provided by the Engineer.
D. The final acceptance of any submitted offer shall be strictly depending
on the photometric and electrical performance test on site.
E. Standards:
13/6.1 General
- 21 -
SECTION 13 DECK AND STAIRCASE
- 22 -
SECTION 13 DECK AND STAIRCASE
A. The light source shall be LED package chip with single Diode, high
brightness white light emitting Diodes (LEDs) at 4000K/3000K
arranged in arrays to provide the required lighting output. The colour
temperature can vary as per RTA request and project requirement.
B. The LEDs shall be from a reputed manufacturer of LEDs with proven
past performance in accordance with ANSI/NEMA/ANSLG C78.377-
2008 – (American National Standard for Chromaticity of Solid State
Lighting Products) or similar approved International Standard.
C. At least 15 years experiences delivering HP LED chips to outdoor
applications
D. Chips shall only be from Macadam Ellipse max. Steps 5 Bins.
Therefore, 4000K +/- the defined ranges for step five by
ANSI/NEMA/ANSLG C78.377- 2009.
E. The CRI ≥70.
- 24 -
SECTION 13 DECK AND STAIRCASE
- 25 -
SECTION 13 DECK AND STAIRCASE
- 26 -
SECTION 13 DECK AND STAIRCASE
A. Photometric performance:
- 27 -
SECTION 13 DECK AND STAIRCASE
- 28 -
SECTION 13 DECK AND STAIRCASE
ii. Warranty:
a) Comprehensive 10 years warranty and 5 years warranty
for deck and strip lighting respectively shall be given for
the whole system including but not limited to LED
modules, Driver, wiring connections, Housing, glass
cover, hardware’s, painting, corrosion, etc.
13/7.1 Description
A. The work of this Section is integral with the whole of the Contract
Documents and is not intended to be interpreted outside that context.
B. Coordinate the work with all other services affecting the work of this
Section.
A. This Section shall include all labour, materials and accessories for the
complete performance of all distribution boards in accordance with the
Specifications and Drawings.
- 29 -
SECTION 13 DECK AND STAIRCASE
13/7.5 Submittals
13/7.6 General
- 30 -
SECTION 13 DECK AND STAIRCASE
13/7.7 Busbars
- 31 -
SECTION 13 DECK AND STAIRCASE
13/7.11 Contactors
A. Lighting Contactors
i. The contactors shall be single coil, electrically operated,
mechanically held (latch type) and shall be rated for Tungsten,
LED,Fluorescent or discharge lighting load.
ii. Contactors rating and number of poles: as indicated in the
Schedule of Points.
iii. Operating coil: suitable for 220 V, 50 Hz. supply. Continuous
rating without overheating or noise
iv. Main Contacts: double break silver-to-silver type protected by
arcing contacts.
v. Contacts: self-aligning, renewable from the front panel.
vi. Solenoids: shaded pole pattern of such construction that
lamination noise is eliminated.
vii. Control of contactor: by remote push switches, as indicated. A
manual operating never shall also be included.
viii. Lighting contactor’s controlling lighting circuits of distribution
boards shall be mounted in the board enclosure.
13/7.12 Installation
13/7.13 MCBs
- 32 -
SECTION 13 DECK AND STAIRCASE
E. Selector switch:
- 33 -
SECTION 13 DECK AND STAIRCASE
b) ON
c) OFF
ii. A selector switch for connecting the traffic signal out-going MCBs
to selected phase shall be provided.
- 34 -
Section 14
FM 200 System
Specification
SECTION 14 FM 200 SYSTEM SPECIFICATION
SUB-
SECTION DESCRIPTION PAGE
14/1.1 REQUIREMENTS 1
14/1.2 EXCLUSIONS 1
14/1.3 GENERALS 1
-2-
SECTION 14 FM 200 SYSTEM SPECIFICATION
This specification outlines the requirements for a “Total Flood” Clean Agent Fire
Suppression System with automatic detection and control. The work described in this
specification includes all engineering, labor, materials, equipment and services
necessary, and items required to complete and test the fire suppression system.
The design, equipment, installation, testing, and maintenance of the Clean Agent Fire
Suppression System shall be in accordance with the applicable requirements set forth
in the latest edition of the following codes and standards:
• National Fire Protection Agency (NFPA) No. 2001 – Clean Agent Fire
Extinguishing Systems
• NFPA No. 70 – National Electrical Code
• NFPA No. 72 – National Fire Alarm Code
• Factory Mutual Approval Guide
• UL Listings
• Requirements of the Authority Having Jurisdiction (AHJ)
The standards listed, as well as all other applicable codes, standards, and good
engineering practices, shall be used as “minimum” design standards.
14/1.1 REQUIREMENTS
The suppression system installation shall be made in accordance with the drawings,
specifications, and applicable standards. Should a conflict occur between the drawings
and specifications, the specifications shall prevail.
14/1.2 EXCLUSIONS
The work listed below shall be provided by others or under other sections of this
specification:
120 VAC or 220 VAC power supply to the system control panel.
Interlock wiring and conduit for shutdown of HVAC, dampers, and/or electric power
supplies, relays, or shunt trip breakers.
14/1.3 GENERAL
14/1.3.1 MANUFACTURER
The manufacturer of the suppression system hardware and detection components shall
have approval in DCD
All devices, components, and equipment shall be the products of the same
manufacturer.
All devices, components, and equipment shall be new, standard products of the
manufacturer’s latest design and suitable to perform the functions intended.
14/1.3.2 INSTALLER
The contractor shall have enough experience to install, test, and maintain fire
suppression systems.
When possible, the installing contractor shall employ a NICET certified special
hazard designer, Level II or above, who will be responsible for this project.
The installing contractor must have a minimum of 5 years experience in the design,
installation, and testing of Clean Agent, or similar fire suppression systems. A list of
systems of a similar nature and scope shall be provided on request.
The installing contractor shall show evidence that his company carries a minimum $2
million liability and complete operations insurance policy. These limits shall
supersede limits required in the general conditions of the specifications.
The installing contractor shall maintain, or have access to, a clean agent recharging
station. The installing contractor shall provide proof of his ability to recharge the
largest Clean Agent system within 24 hours after a discharge. Include the amount of
bulk agent storage available.
14/1.3.3 SUBMITTALS
The installing contractor shall submit the following design information and drawings
for approval prior to starting work on this project:
Field installation layout drawings having a scale of not less than 1/8 in. (3 mm) = 1 ft
0 in. (0.3 m) or 1:100 detailing the location of all agent storage containers, nozzles,
pipe runs including pipe sizes and lengths, control panel(s), detectors, manual pull
stations, abort stations, audible and visual alarms, etc.
-2-
SECTION 14 FM 200 SYSTEM SPECIFICATION
Auxiliary details and information such as maintenance panels, door holders, special
sealing requirements, and equipment shutdown.
Separate layouts or drawings shall be provided for each level, (i.e. room, under floor,
and above ceiling) and for mechanical and electrical work.
A separate layout or drawing shall show isometric details of agent storage containers,
mounting details, proposed pipe runs and sizes, and symbol legend.
Electrical layout drawings shall show the location of all devices, and include point-to-
point conduit runs, and a description of the method(s) used for detector mounting.
Provide an internal control panel wiring diagram, which shall include power supply
requirements and field wiring termination points.
Provide calculations for the battery stand-by power supply taking into consideration
the power requirements of all alarms, initiating devices, and auxiliary components
under full load conditions.
Submit drawings, calculations, and system component data sheets for approval to the
local fire prevention agency, owner’s insurance underwriter, and all other authorities
having jurisdiction before starting installation. Submit approved plans to the Architect
Engineer for record.
The system shall be a Total Flood FM-200 Fire Suppression System shall be from an
approved supplied Manufacturer
The system shall provide the FM-200 fire extinguishant minimum design
concentration of 6.7% (UL) or 7.17% (FM) by volume for Class A hazards and a
minimum of 8.97% by volume for Class B hazards, in all areas and/or protected
spaces, at the minimum anticipated temperature within the protected area.
-3-
SECTION 14 FM 200 SYSTEM SPECIFICATION
For Class C hazards, a minimum design concentration of 7.2% (UL) or 8.1% (FM) by
volume shall be provided. System design shall not exceed 10.5% for normally
occupied spaces, adjusted for maximum space temperature anticipated, with
provisions for room evacuation before agent release.
The system shall be complete in all ways. It shall include all mechanical and electrical
installation, all detection and control equipment, agent storage containers, FM-200
agent, discharge nozzles, pipe and fittings, manual release and abort stations, audible
and visual alarm devices, auxiliary devices and controls, shutdowns, alarm interface,
caution/advisory signs, functional checkout and testing, training and all other
operations necessary for a functional, UL Listed and FM Approved FM-200 Clean
Agent Fire Suppression System.
Provide 2 inspections during the first year of service. Inspections shall be made at 6
month intervals commencing when the system is first placed into normal service.
The general contractor shall be responsible for sealing and securing the protected
spaces against agent loss and/or leakage during the “hold” period, which is a
minimum period of 10 minutes or a time period sufficient to allow for response by
trained personnel.
The FM-200 system shall be automatically actuated by either counting zone detection
or cross-zoned detection methodology. Smoke sensors / detectors shall utilize
photoelectric technology and/or Aspiration Smoke Detectors (ASD) for very early
warning smoke detection. Smoke detectors and ASD sample points shall be installed
at no more than 250 ft2 (23.2 m2) of coverage per detector. When using analog
addressable sensors or ASD detectors offering pre-alarm thresholds, further system
design consideration is suggested for providing very early warning detection which
can offer extended investigation time prior to suppression agent release. In all cases,
the compatibility listings of the detectors for use with the control unit should be
observed. The system shall require two detectors in alarm prior to automatic agent
release.
Both Photoelectric and ASD type smoke detectors can be combined in the releasing
process, using one of following methods:
-4-
SECTION 14 FM 200 SYSTEM SPECIFICATION
Double action manual releasing stations shall be provided at each exit of the protected
area, and shall, when activated, release the FM-200 agent and cause all audible /
visual alarms to activate. In addition, activation of the manual releasing stations shall
cause immediate shutdown of air and power circuits.
Abort station shall be provided at each exit of the protected area, and shall, when
operated, interrupt the pre-discharge time delay of the FM-200 agent and emergency
power-off functions. The abort station shall be momentary devices (dead-man)
requiring constant pressure to maintain contact closure.
Note: Manual Releasing Station activation shall override any abort station. Abort
station operation shall be per IRI and FM guidelines.
The FM-200 Clean Agent System materials and equipment shall be standard products
of the supplier’s latest design and suitable to perform the functions intended. When
one or more pieces of equipment must perform the same function(s), they shall be
duplicates produced by one manufacturer.
The system design can be modular, central storage, or a combination of both design
criteria.
-5-
SECTION 14 FM 200 SYSTEM SPECIFICATION
Each supply shall be located within the hazard area, or as near as possible, to reduce
the amount of pipe and fittings required to install the system.
Each container shall have a pressure gauge and low pressure switch to provide visual
and electrical supervision of the container pressure. The low-pressure switch shall be
wired to the control panel to provide an audible and visual “Trouble” alarms in the
event
the container pressure drops below 290 psi to 294 psi (19.9 psi to 20.3 bar). The
pressure gauge shall be color coded to provide an easy, visual indication of container
pressure.
Each container shall have a pressure relief provision that automatically operates
before the internal pressure exceeds 774.5 psi (53.4 bar) ± 5%.
Nozzles shall be available in 3/8 in. through 2 in. pipe sizes. Each size shall be
available in 180° and 360° distribution patterns.
Ceiling plates can be used with the nozzles to conceal pipe entry holes through ceiling
tiles.
Before assembly, all piping shall be reamed, blown clear, and swabbed with suitable
solvents to remove burrs, mill varnish, and cutting oils.
All pipe threads shall be sealed with Teflon tape pipe sealant applied to the male
thread only.
All control systems shall be UL Listed and FM Approved, and shall be utilized with
listed or approved compatible operating devices, and shall be capable of the following
features:
-6-
SECTION 14 FM 200 SYSTEM SPECIFICATION
• Battery standby
• 4.3” color touchscreen LCD operator interface and LED indicating lamps
• Key lock steel enclosure
• Programmable time delay
• Programmable detection logic
• Microprocessor based logic
• History buffer
The Fire Alarm Control Panel (FACP) shall be an AUTOPULSE Z-20 control panel
with the capability of protecting up to 20 hazards. The panel shall contain a Central
Processing Unit (CPU) with integral 8 amp power supply which is rated to provide 8
amp for “Special Application” appliances including suppression release peripherals
such as horns, strobes and horn/strobes and rated to 6 amp for “regulated 24 VDC”
appliance power. The CPU shall communicate with and control the following types of
equipment used to make up the system: addressable and conventional initiating
devices, addressable modules, annunciators, and other system controlled devices.
The control panel shall provide up to a 250 addressable point capacity with the
capability of expansion to 3 loops.
The system shall include 4 Class B programmable notification appliance circuits rated
at 3 A each.
The control panel and remote annunciator (optional) shall include a full featured,
intuitive color touch screen display capable of supporting up to two languages. The
menu-driven interface shall provide color coded system status LEDs, allow for direct
control of the fire alarm system and also allow for quick access to more detailed
system information.
The real time clock may also be used to control non-fire functions at programmed
time-of-day, day-of-week, and day-of-year.
The microprocessor unit shall communicate with, monitor, and control all external
interfaces with the control panel. It shall include system program storage in non-
volatile memory for building-specific program storage, and a "watch dog" timer
circuit to detect and report microprocessor failure.
The microprocessor unit shall contain and execute all control-by-event programs for
specific action to be taken if an alarm condition is detected by the system. Such
control- by-event programs shall be held in non-volatile programmable memory and
shall not be lost even if system primary and secondary power failure occurs.
The microprocessor unit shall also provide a real-time clock for time annotation of
system displays and history file.
14/2.5.2 Display
The touch screen display shall provide all the controls and indicators used by the
system operator.
The display shall include status information and custom alphanumeric labels for all
addressable and conventional detectors, addressable modules, and software zones.
The SLC interface called an IDNet+ circuit, shall provide power to and communicate
with up to 250 addressable points which can include Photoelectric or Thermal
detectors along with all monitoring and control points. This can be accomplished
over one to three SLC loops and shall be capable of NFPA 72 Class A or B wiring.
The loop interface board(s) shall receive and process information from all detectors to
determine whether normal, alarm, supervisory or trouble conditions exist for each
detector. The software shall automatically maintain the detector's desired sensitivity
level by adjusting for the effects of environmental factors, including the accumulation
of dust in each detector. The information shall also be used for automatic detector
-8-
SECTION 14 FM 200 SYSTEM SPECIFICATION
The detector software shall meet NFPA 72, requirements and be certified by UL as a
calibrated sensitivity test instrument.
Enclosures:
The control panel shall be housed in a UL listed cabinet suitable for surface or semi-
flush mounting. Cabinet and front shall be corrosion protected, given a rust-resistant
prime coat, and manufacturer's standard finish.
The door shall provide a key lock and include a glass or other transparent opening for
viewing of all indicators.
All interfaces and associated equipment are to be protected so they will not be
affected by voltage surges or line transients consistent with UL standard 864.
Optional modules shall be available for NFPA 72 supervising station and public
emergency alarm reporting systems. The control panel shall have the ability to meet
the latest requirements of UL 864 for delayed AC fail reporting.
The power supply shall operate on 120 or 240 VAC, 50/60 Hz, and shall provide all
necessary power for the control panel. The power supply shall have a 6 A output
rating which provides current for special application devices, IDNet devices, module
currents and auxiliary output currents. When NACs are controlling regulated 24 DC
appliances, total NAC current available shall be 3 A.
It shall provide a battery charger for 24 hours of standby using dual-rate charging
techniques for fast battery recharge.
It shall provide an earth detection circuit capable of detecting earth faults on I/O
modules field wired circuits connected to power supply.
For ease of service, all panel I/O wiring terminal blocks shall have sufficient capacity
for 18 to 12 AWG wire.
-9-
SECTION 14 FM 200 SYSTEM SPECIFICATION
The programming function shall be enabled with a password that may be defined
specifically for the system when it is installed. Three levels of password protection
shall be provided in addition to a key-lock cabinet. One level is used for status level
changes such as zone disable or manual on/off commands. A third level (higher-level)
is used for actual change of program information.
A special program check function shall be provided to detect common operator errors.
Smoke Detector Sensitivity Adjust: Means shall be provided for adjusting the
sensitivity of any or all analog intelligent smoke detectors in the system from the
system keypad. Sensitivity range shall be within the allowed UL window.
Point Disable: Any device in the system may be Enabled or Disabled through the
system keypad.
Point Read: The system shall be able to display or print the following point status
diagnostic functions:
• Device status.
• Device type.
• Custom device label.
• View analog detector values.
• Device zone assignments.
• All program parameters.
System Status Reports: Upon command from a system operator, a status report will be
generated and printed listing all system status provided an optional RS232 card is
installed. The report must also be exportable to a USB device on the Z-20 USB port.
System History Recording and Reporting: The control panel shall contain a history
buffer that will be capable of storing up to 2000 events (1000 alarm and 1000
trouble). Each of these activations will be stored and time-and-date stamped with the
actual time of the activation. The contents of the history buffer may be manually
reviewed, one event at a time, exported to a USB device or printed (if optional RS232
module is provided) in its entirety.
The history buffer shall use non-volatile memory. Systems that use volatile memory
for history storage are not acceptable.
- 10 -
SECTION 14 FM 200 SYSTEM SPECIFICATION
If any intelligent smoke detector in the system responds with a reading that is below
or above normal limits, the system will enter the trouble mode and the particular
detector will be annunciated on the system display. This feature shall in no way
inhibit the receipt of alarm conditions in the system nor shall it require any special
hardware, special tools or computer expertise to perform.
Pre-Alarm Function: The system shall provide 2 levels of pre-alarm warning to give
advance notice of a possible fire situation. Both pre-alarm levels shall be fully field
adjustable. The first level shall give an audible indication at the panel. The second
level shall give an audible indication and may also activate control relays. The system
shall also have the ability to activate local detector sounder bases at the pre-alarm
level to assist in avoiding nuisance alarms.
Software Zones: The control panel shall provide 512 programmable software zones.
All addressable devices may be field programmed to be grouped into these zones for
control activation and annunciation purposes.
14/2.5.8 Batteries
Batteries shall have sufficient capacity to power the fire alarm system for not less than
24 hours in standby plus 5 minutes of alarm upon a normal AC power failure.
Batteries are to be completely maintenance free. No liquids are required. Fluid level
checks, refilling, spills and leakage shall not be accepted.
Electronic sounders shall be field programmable without the use of special tools to
choose 1 of 8 tones with an output sound level of at least 90 dBA measured at 10 ft
(3.0 m) from the device.
Strobe lights shall meet the requirements of the ADA as defined in UL standard 1971
and shall meet the following criteria:
- 11 -
SECTION 14 FM 200 SYSTEM SPECIFICATION
The strobe intensity shall meet the requirements of UL 1971 and devices shall be
multi-candela 15 cd – 110cd and higher intensity if required by the plans.
The appliance shall be placed 80 in.(to the bottom of the appliance) to 96 in. (to the
top of the appliance) above the finished floor within the space.
Audible/visual combination devices shall meet the requirements of Section 3.6 (listed
above) for visibility.
Detectors shall be intelligent and addressable, and shall connect with 2 wires to the
fire alarm/release control panel signaling line circuits.
Addressable smoke and thermal detectors shall provide dual alarm and power LEDs.
Both LEDs shall flash under normal conditions indicating that the detector is
operational and in regular communication with the control panel. Both LEDs shall be
placed into steady illumination by the control panel indicating that an alarm condition
has been detected. If required, the flashing mode operation of the detector LEDs shall
be optional through the system field program. An output connection shall also be
provided in the base to connect an external remote alarm LED.
Smoke detector sensitivity shall be set through the control panel and shall be
adjustable in the field through the field programming of the system. Sensitivity may
be automatically adjusted by the panel on a time-of-day basis.
Using software in the control panel, detectors shall automatically compensate for dust
accumulation and other slow environmental changes that may affect their
performance. The detectors shall be listed by UL as meeting the calibrated sensitivity
test requirements of NFPA Standard 72.
The detectors shall be ceiling-mount and shall include a separate twist-lock base with
tamper-proof feature. An optional base shall be available with a built-in (local)
sounder rated at 85 dBA minimum.
The detectors shall provide a test means whereby they will simulate an alarm
condition and report that condition to the control panel. Such a test may be initiated at
the detector itself (by activating a magnetic switch) or initiated remotely on command
from the control panel.
Detectors shall also store an internal identifying type code that the control panel shall
use to identify the type of device (PHOTO or THERMAL).
- 12 -
SECTION 14 FM 200 SYSTEM SPECIFICATION
Addressable manual pull station shall, on command from the control panel, send data
to the panel representing the state of the manual switch. They shall use a key operated
test-reset lock and shall be designed so that after actual emergency operation, they
cannot be restored to normal use except by the use of a key.
All operated stations shall have a positive, visual indication of operation and utilize a
key-type reset.
Manual stations shall be clearly visible operating instructions provided on the cover.
The word AGENT shall appear on the front and both sides of the stations.
The detectors shall use the photoelectric (light-scattering) principle to measure smoke
density and shall, on command from the control panel, send data to the panel
representing the analog level of smoke density.
Heat detectors shall be analog addressable devices rated at 135 °F (57 °C) and have a
rate-of-rise element rated at 15 °F (9.4 °C) per minute. It shall connect via 2 wires to
the control panel signaling line circuit. Up to 159 intelligent heat detectors may
connect to one SLC loop.
The detectors shall use an electronic sensor to measure thermal conditions caused by a
fire and shall, on command from the control panel, send data to the panel representing
the analog level of such thermal measurements.
An optional, intelligent heat detector shall be available for applications which do not
require a rate- of-rise element.
When sufficient smoke is sensed, an alarm signal is initiated at the control panel and
appropriate action is taken to change over air handling systems to help prevent the
rapid distribution of toxic smoke and fire gases throughout the areas served by the
duct system.
- 13 -
SECTION 14 FM 200 SYSTEM SPECIFICATION
Addressable monitor modules shall be provided to connect one supervised IDC zone
of conventional alarm initiating devices (any N.O. dry contact device) to one of the
control panel SLC loops.
The monitor module shall mount in a 4 in. (102 mm) square, 2 1/8 in. (54 mm) deep
electrical box.
The IDC zone may be wired for Style D or Style B operation. An LED shall be
provided that shall flash under normal conditions indicating that the monitor module
is operational and in regular communication with the control panel.
For difficult to reach areas, the monitor module shall be available in a miniature
package and shall be no larger than 2-3/4 in. x 1-1/4 in. x ½ in. (69.9 mm x 31.8 mm x
12.7 mm). This version need not include Style D or an LED.
Addressable monitor modules shall be provided to connect one supervised IDC zone
of conventional two-wire smoke detectors or alarm initiating devices (any N.O. dry
contact device).
The two-wire monitor module shall mount in a 4 in. (102 mm) square, 2 1/8 in. (54
mm) deep electrical box or with an optional surface back box.
The IDC zone may be wired for Class A or B (Style D or Style B) operation. An LED
shall be provided that shall flash under normal conditions indicating that the monitor
module is operational and in regular communication with the control panel.
Each detector shall include a visual status indicator, provide remote LED output, and
include a built-in test capability.
The detector cover and screen shall be easily removable for field cleaning.
A special vandal-resistant locking screw shall be provided to lock the head to the
base.
Photoelectric-type smoke detector shall be light reflective type and compatible with
the AUTOPULSE control system. The detector shall have an LED in its base which is
illuminated in a steady-on mode when in alarm and pulse mode when in standby.
Reset of the detector shall be performed by the control unit reset switch.
The design of the photoelectric detector compensating circuits shall provide stable
operation with regard to minor changes in temperature, humidity and atmospheric
conditions.
Photoelectric-type smoke detector with heat detector shall be light reflective type and
compatible with the AUTOPULSE control system. The detector shall have an LED in
its base which is illuminated in a steady-on mode when in alarm and pulse mode
when in standby. Reset of the detector shall be performed by the control unit reset
switch.
Addressable control modules shall be provided to supervise and control the operation
of one conventional Notification Appliance Circuit (NAC) of compatible, 24 VDC
powered, polarized audio/visual notification appliances. For fan shutdown and other
auxiliary control functions, the control module may be set to operate as a dry contract
relay.
The control module shall mount in a standard 4 in. (102 mm) square, 2 1/8 in. (54
mm) deep electrical box, or to a surface mounted back box.
The control module NAC circuit may be wired for Style Z or Style Y (Class A/B)
with up to 1 amp of inductive A/V signal, or 2 amps of resistive A/V signal operation,
or as a dry contact (Form C) relay.
The relay coil shall be magnetically latched to reduce wiring connection requirements
and to insure that 100% of all auxiliary relay or NACs may be energized at the same
time on the same pair of wires.
Audio/visual power shall be provided by a separate supervised power loop from the
main control panel or from a supervised, UL listed remote power supply.
The control module shall provide address-setting means using decimal switches and
shall also store an internal identifying code that the control panel shall use to identify
the type of device. An LED shall be provided that shall flash under normal conditions
indicating that the control module is operational and is in regular communication with
the control panel.
A magnetic test switch shall be provided to test the module without opening or
shorting its NAC wiring.
The control module shall be suitable for pilot duty applications and rated for a
minimum of 0.6 amps at 30 VDC.
- 15 -
SECTION 14 FM 200 SYSTEM SPECIFICATION
The isolator module shall not require any address-setting and its operations shall be
totally automatic. It shall not be necessary to replace or reset an isolator module after
its normal operation.
The isolator module shall mount in a standard 4 in. (102 mm) deep electrical box or in
a surface mounted back box.
It shall provide a single LED that shall flash to indicate that the isolator is operational
and shall illuminate steadily to indicate that a short circuit condition has been detected
and isolated.
The abort switch shall be used where an investigative delay is desired between
detection and actuation of the fire suppression system.
This switch shall be a momentary contact "dead-man" type switch requiring constant
pressure to transfer one set of contacts. Clear operating instructions shall be provided
at the abort switch.
The maintenance lock-out switch shall be used where it is desired to disable the fire
suppression system during routine maintenance.
This switch shall be key operated allowing removal of the key only in "Normal"
position. A red indicator lamp shall be included on the switch assembly to be
illuminated when in the "Lock-Out" position. The control unit is used to indicate a
supervisory condition when in the "Lock-Out" position.
The switch shall include 1 set of normally open and 1 set of normally closed control
contacts rated for 2 A resistive @ 30 VDC.
- 16 -
SECTION 14 FM 200 SYSTEM SPECIFICATION
This switch shall be key operated allowing removal of the key in either the "Main" or
"Reserve" position.
This switch shall be rated at 28 VDC @ 1.1 amp make/break or 6 amp continuous
carry.
Flow switches shall have an alarm transmission time delay that is conveniently
adjustable from 0 to 60 seconds. Initial settings shall be 30 or 45 seconds.
Flow switches shall be located a minimum of 1 ft (0.3 m) from a fitting that changes
the direction of the flow and a minimum of 3 ft (0.9 m) from a valve.
Each sprinkler system water supply control valve riser, or zone control valve, and
each standpipe system riser control valve shall be equipped with a supervisory switch.
Standpipe hose valves, and test and drain valves shall not be equipped with
supervisory switches.
Each Post Indicator Valve (PIV) or main gate valve shall be equipped with a
supervisory switch.
The switch shall be mounted so as not to interfere with the normal operation of the
valve and adjusted to operate within 2 revolutions toward the closed position of the
valve control, or when the stem has moved no more than one-fifth of the distance
from its normal position.
The entire installed assembly shall be tamper proof and arranged to cause switch
operation if the housing cover is removed or if the unit is removed from its mounting.
Valve supervisory switches shall be provided and connected under this section and
installed by mechanical contractor.
- 17 -
SECTION 14 FM 200 SYSTEM SPECIFICATION
The remote annunciator shall provide a 4.3” color touchscreen LCD display that is
identical to the control panel user interface. The annunciator shall be capable of
displaying a custom background image when the system status is normal.
The annunciator shall provide; a local sounder; discrete status LEDs for Alarm,
Priority 2, Supervisory, Trouble, Alarm Silenced and AC power indications; and three
programmable LEDs with associated control switches with provisions for custom
labels. A lamp test feature shall be available from the display menu.
The remote annunciator shall provide access to all system status information, controls,
diagnostics, and reports that are available on the control unit user interface. Protected
access shall be provided to the following operator control functions and diagnostics;
Alarm, Priority 2, Supervisory and Trouble Acknowledge; Alarm Silence; and System
Reset; Hardware Reset; Point Disable/Enable; Annunciator Sounder Silence, Clear
History Logs; Panel Setup; and System Diagnostics. Protection against unauthorized
use shall be provided via a passcode, keyswitch, or both.
The annunciator shall have the capability to support up to two languages with the
ability to toggle between languages using one of the programmable control switches
on the annunciator.
The annunciator shall connect to a two-wire Remote Unit Interface (RUI). The two-
wire RUI connection shall be capable of distances of up to 2,500 feet (762 meters).
Signs shall be provided to comply with NFPA 2001 and the recommendations of the
FM- 200 agent equipment supplier:
Flashing light sign: 1 required at each flashing light over each exit from a protected
space.
All wiring shall be installed in electrical metallic tubing (EMT or conduit) and must
be installed and kept separate from all other building wiring.
All system components shall be securely supported independent of the wiring. Runs
of conduit and wiring shall be straight, neatly arranged, properly supported, and
installed parallel and perpendicular to walls and partitions.
- 18 -
SECTION 14 FM 200 SYSTEM SPECIFICATION
The sizes of the conductors shall be those specified by the manufacturer. Color-coded
wire shall be used. All wires shall be tagged at all junction points, and shall be free
from shorts, earth connections (unless so noted on the system drawings), and crosses
between conductors.
Final terminations between the control panel and the system field wiring shall be
made under the direct supervision of a factory-trained representative.
Wiring installation shall meet all local, state, province, and/or country codes.
The complete system electrical installation and all auxiliary components shall be
connected to earth ground in accordance with the National Electrical Code.
After the system installation has been completed, the entire system shall be checked
out, inspected, and functionally tested by qualified, trained personnel, in accordance
with the manufacturer’s recommended procedures and NFPA standards:
All containers and distribution piping shall be checked for proper mounting and
installation.
All electrical wiring shall be tested for proper connection, continuity, and resistance to
earth.
The complete system shall be functionally tested in the presence of the owner or his
representative, and all functions, including system and equipment interlocks, must be
operational at least 5 days prior to the final acceptance tests:
All system and equipment interlocks, such as door release devices, audible and visual
devices, equipment shutdowns, local and remote alarms, etc. shall function as
required and designed.
Each control panel circuit shall be tested for trouble by inducing a trouble condition
into the system.
Prior to final acceptance, the installing contractor shall provide operational training to
each shift of the owners personnel. Each training session shall include control panel
operation, manual and (optional) abort functions, trouble procedures, supervisory
procedures, auxiliary functions, and emergency procedures.
- 19 -
SECTION 14 FM 200 SYSTEM SPECIFICATION
Prior to final acceptance, the installing contractor shall provide complete operation
and maintenance instruction manuals, Four copies of the instruction manuals shall be
provided for each system to the owner. All aspects of system operation and
maintenance shall be detailed, including piping isometrics, wiring diagrams of all
circuits, a written description of the system design, sequence of operation and
drawing(s) illustrating control logic, and equipment used in the system. Checklists
and procedures for emergency situations, troubleshooting techniques, maintenance
operations and procedures shall be included in the manual.
Upon completion of each system, the installing contractor shall provide 4 copies of
system “As-Built” drawings to the owner. The drawings shall show actual installation
details, including all equipment locations (i.e.: control panel(s), agent container(s),
detectors, alarms, manuals, and aborts, etc.) as well as piping and conduit routing
details. The drawings shall show all room or facilities modifications, including door
and/or damper installations completed. One copy of reproducible engineering
drawings shall be provided reflecting all actual installation details.
The tests shall demonstrate that the entire control system functions as designed and
intended.
All circuits shall be tested: automatic actuation, solenoid and manual actuation,
HVAC and power shutdowns, audible and visual alarm devices, and manual override
of abort functions. Supervision of all panel circuits, including AC power and battery
power supplies, shall be tested and qualified.
If room pressurization testing indicates that openings exist, which would result in
leakage and/ or loss of the extinguishing agent, the installing contractor shall be
responsible for coordinating the proper sealing of the protected space(s) by the
general contractor, or his sub-contractor, or agent.
- 20 -
SECTION 14 FM 200 SYSTEM SPECIFICATION
The general contractor shall be responsible for adequately sealing all protected
space(s) against agent loss or leakage. The installing contractor shall inspect all work
to ascertain that the protected space(s) have been adequately and properly sealed.
The installing contractor shall provide 2 inspections of each system, installed under
this contract, during the one-year warranty period. The first inspection shall be at the
6 month interval, and the second inspection at the 12 month interval after system
acceptance.
- 21 -
Section 16
Fire Alarm &
Extinguishing System
SECTION 16 FIRE ALARM & EXTINGUISHING SYSTEM
SUB-
SECTION DESCRIPTION PAGE
16/1 GENERAL 1
16/9 INSTALLATION 4
16/12.1 GENERAL 6
16/12.4 ARRANGEMENTS 6
-1-
SECTION 16 FIRE ALARM & EXTINGUISHING SYSTEM
16/1 GENERAL
The Contractor shall arrange for an approved Sub-Contractor who shall be on the list
of Approved Contractors, to supply, install, wire and commission the complete
manual/automatic fire alarm system comprising manual fire alarm call points, alarm
bells and sounders, smoke and heat detectors and control panels as indicated on the
drawings.
The fire alarm system equipment shall be selected from equipment approved by the
Fire Department. The system shall be installed and maintained in accordance with the
recommendations of an approved international standard. The wiring shall be 1.5 mm2
MICC/PVC for bell and battery circuits.
Manual fire alarm call points shall consist of a die cast plastic cover locked in position
with screws. The enclosure shall house a micro switch. The micro switch plunger
shall bear onto an inset break glass panel fixed into the cover. The call point shall be
arranged for surface mounting. The cover and the enclosure shall be self coloured red.
The words “BREAK GLASS FOR ALARM” shall be printed on the frangible glass.
A testing facility using a special key shall be provided to enable the call point to be
tested without breaking the glass and the frangible glass shall be covered with plastic
film to prevent injury when the glass is broken. The mounting height shall be 1500
mm above finished floor level.
The switching unit contacts shall be gold or silver plated or an alloyed metal which
will not corrode when left unattended in a highly polluted environment. Contact
blades and other metal parts of the switching unit shall also be constructed from
plated or alloyed metal which will not corrode when left unattended. Contacts shall be
normally open or normally closed to suit the alarm monitoring system. The voltage
and current rating of the contacts shall be marked within the enclosure.
The call point shall comply with an approved international standard Specification for
manual call points.
The call point shall be resistant to the ingress of dust and water and shall be suitable
for operation in the environmental conditions at the site of installation.
Optical smoke detectors shall comply with an approved international standard and
approved by Dubai Civil Defence.
An operation indicator lamp of the light emitting diode type and a time delay unit to
override spurious alarms shall be fitted to the base.
-1-
SECTION 16 FIRE ALARM & EXTINGUISHING SYSTEM
The fire alarm panel shall be wall mounted adjacent to the motor control centre. The
fire alarm system shall protect risk areas within the premises by giving warning of a
fire condition relayed by an automatic detector or by the operation of a break glass
callpoint.
Operation of an individual detector is to be displayed by an indicator fitted into the
base of the detector. This indicator will illuminate when its detector goes into alarm.
Fixed temperature heat detectors will not have this local indication facility. Upon
receipt of an alarm, the control units shall perform the following actions:
Reset of the controller, after the fire incident has been investigated, will be achieved
by operation of the “Reset” switch.
The enclosures of the panels shall be fabricated from sheet steel, minimum thickness
1.5 mm and shall be provided with a hinged lockable door. Protection to an approved
international standard shall be provided.
The control unit should be designed to comply with the compulsory requirements of
an approved international standard, relating to “Automatic fire alarm systems in
buildings, control and indicating equipment”.
b) DC supply on indicator
j) Voltage free normally closed circuits which shall open in the event of an alarm
to shutdown ventilation and air conditioning equipment in the immediate
vicinity.
Alarm indicators shall be of the light emitting diode type. Indicators shall be provided
in pairs for each function.
Alarm panels shall continuously monitor all alarm circuits, including wiring and
control devices. When a fault monitoring circuit has been energized it shall not reset
until the fault condition is cleared.
Batteries shall be of the sealed lead acid type and shall have a capacity capable of
maintaining the system in normal working condition for at least 24 hours without
recharging and subsequently to operate in the alarm condition for at least one hour.
Monitoring circuits shall utilise solid state components. Output relay contacts shall be
gold or silver plated and shall be rated for the circuit conditions into which they
operate.
Alarm bells shall be of the gong type with a minimum diameter of 200 mm. They
shall be continuously rated and be mounted 2200 mm above finished floor level.
2.5kg hand held CO2 operated for extinguishers and 4.5 kg hand held dry powder
type fire extinguisher, suitable for Class A, B and C fire risks, flammable liquid, and
fires from electrical sources. The extinguisher shall comprise a light alloy or steel
cylinder finished in blue epoxy resin fitted with a controllable brass valve with
pressure gauge or aluminum head cap for CO2 operated cylinders. Valves to be fitted
with safety pin lever.
All equipment supplied shall be suitable for the high temperatures, humidities, and
dusty atmospheres experienced in Dubai, with a minimum jet range of 5-7m
discharging in approximately 15 secs.
All equipment supplied under this section shall be obtained from a company regularly
-3-
SECTION 16 FIRE ALARM & EXTINGUISHING SYSTEM
Fire extinguishing devices shall be clearly and indelibly labelled with clear
instructions for their use in English, Arabic and pictorial form.
All equipment and devices shall be wired and connected by fire retardant cables of
minimum cross sectional area of 1.5mm² for detector circuits and 2.5mm²for bell and
battery circuits. The cable outer sheath shall be flame retardant.
All cables shall be installed on cable trays or conduits and fastened suitably. All fire
alarm wiring shall be completely segregated from all other wiring in the plant.
16/9 Installation
b) Install manual station with operating handle 1.4m above finished floor
level.
c) Install audible and visual signal devices 2.3m above finished floor
level.
-4-
SECTION 16 FIRE ALARM & EXTINGUISHING SYSTEM
e) Mount outlet box for electric door holder to withstand 40kg pulling
force.
A 2.5 KVA UPS system shall be installed within the MDB in a separate compartment
together with its battery bank. A distribution board to receive and distribute the power
to critical equipment shall also be included either within the UPS or outside the UPS
in the control room. Batteries shall be sized to provide an autonomy of 3 hours.
Batteries shall be stationary and sealed, maintenance free, Ni-Cd type installed in a
separate rack/cabinet.
The basic AC-UPS system shall be composed but not limited to the following
components:
• rectifier/charger
• 1 battery bank;
• inverter
• static bypass switch.
• manual bypass switch
• distribution section
16/12.1 General
The design of the AC-UPS shall be based on achieving the following minimum
lifetimes.
Capacitors of the electrolyte type shall maintain their capacity within the specified
tolerances for at least 10 years.
• The equipment shall be of a standard, well set and proven design which
ensures maximum safety to personal, maximum service reliability and
economic operation for an operational lifetime of at least 20 years.
• All equipment and parts shall be brand new and unused, of current
manufacturers, of modern design and of the highest industrial grade, free from
all defects that might effect the performance of the unit.
• Capacitors of the electrolyte type shall be non-toxic and free from any PCB's.
The input voltage of the AC-UPS, with rectifier disconnected, will be sinusoidal
according to IEC 60146. The input voltage is 230 Volt, 1 phase, 50 Hz, which will not
exceed the following values:
• static ± 10 %
• dynamic + 16 % ; - 20 %
• spikes 2 kV
• frequency ± 5 %
• Output Voltage 230V, 1phase, 50HZ
16/12.4 Arrangements
The equipment shall comprise but not limited to the following items:
-6-
SECTION 16 FIRE ALARM & EXTINGUISHING SYSTEM
The output of the rectifier shall supply the power requirement of the load via the
inverter and at the same time maintaining the battery in the float-mode.
If there is an AC-supply failure the battery will take over the power requirement of
the load via the inverter for not less than the specified time.
If the AC-supply is restored, the rectifier will then recharge the battery and at the
same time supply the power requirement of the load. The rate of recharging the
battery shall be sufficient to restore it to a capacity that is capable to fulfill the power
requirement of the load in case again an AC-supply failure may occur. The recharging
has to take place within a specific time limit mentioned in the data sheet.
The inverter converts the input DC voltage into an AC output voltage. The output
voltage to the requirements is 230 V, 1 phase, 50 Hz.
The dynamic output voltage variations shall not exceed ± 10 % of the rated output
voltage in case of an instantaneous load variation of 100 %. The steady state output
voltage variation shall not exceed ± 5 % of the rated output voltage in case of a load
variation of 100 %, the steady state output voltage shall be restored within 0.1 sec.
The waveform of the output voltage shall be sinusoidal according to IEC 60146 with a
relative harmonic content not exceeding 5% under linear load conditions and 10%
under non-linear load conditions.
The variations in the output frequency shall not exceed the rated output frequency by
± 2%. It is recommended that the inverter is of the pulse width modulation (PWM)
type regarding the low harmonic distortion level in the supply output of the inverter.
(Valid for switching frequencies over 700 Hz).
A no-break static transfer switch, programmable for sense and transfer time and return
transfer time delayed, shall be incorporated as part of the AC-UPS.
It will provide automatic bypass to the alternate supply system in case of inverter
malfunction or system overload. The total sense and switch transfer time shall not be
-7-
SECTION 16 FIRE ALARM & EXTINGUISHING SYSTEM
more than ¼ cycle. When the load and inverter return to the normal operating range,
the static transfer switch shall automatically retransfer the load back to the inverter.
A continuity monitor shall be provided which will test that the switching devices in
each pole of the static switch control.
If the test fails it shall signal the control circuit to transfer the load to the alternate
position. If neither the inverters nor the alternate source is available, it shall
disconnect the load thereby further protecting the load from being burned up due to
the possible application of half wave AC.
The Contractor should ensure that the functioning of the switch shall not affect the
normal functioning of the control system.
It will be so arranged as to isolate the UPS from the load, permitting maintenance and
testing to proceed on the UPS, without disturbance to the load.
HMI shall be 15” TFT color screen with high resolution and pre-programmed to
provide a basic graphical display of the process. Real-time numeric display of process
variables and alarm messages shall be available. All process control functions shall be
accessible for the operator from the HMI. The application program shall be stored in
Non-volatile Memory.
Each HMI shall provide as minimum facilities with the following functions:
• Real-time operation.
• Direct memory access.
• Real-time clock.
• ‘Watchdog’ timer.
• Memory protection.
• Error checking in all data transfers
• Trends & storage
• Alarms History
• Alarm banner
-8-
Section 17
Security CCTV
Performance Requirements
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
SUB-
SECTION DESCRIPTION PAGE
17/1.1 INTRODUCTION 2
17/3.1 WARRANTY 19
17/3.2 MAINTENANCE 20
-1-
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
17.1.1 INTRODUCTION
The following sections of this document provide the minimum performance requirements
that the Contractor must adhere to when designing and implementing the Foot bridges
CCTV security systems.
All CCTV security systems installed under this contract must be operated and controlled
by an appropriate and approved Management Control System. The RTA reserves the right
to demand the use of an alternative Management Control System, where they identify that
the Contractor’s proposed system does not meet all RTA requirements.
The Contractor must also demonstrate that systems commissioned during the
implementation stage of the project achieve all of these minimum performance
requirements.
17.1.3.1 Conops
The Contractor must submit a surveillance coverage matrix for Footbridges RTA
infrastructure as part of the design process and submit this for approval by RTA corporate
security& control section.
-2-
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
The Concept of Operations (CONOPs) for Video Surveillance will be based upon three
core functions of Monitoring, Assessment and Investigation as identified below.
Video surveillance will be used extensively for pro-active monitoring of Footbridges RTA
infrastructure by RTA corporate security& control. The Contractor must therefore ensure
that the extent of coverage, imaging performance, quality of live viewing and ease of
navigation between cameras, are suitable for this role.
The second function of the Video Surveillance System will be to provide an Assessment
capability following an alarm trigger from another sub-system, or from video analytics-
based detection. As identified earlier, it will be the Contractor’s responsibility to ensure
that, to the fullest extent possible, the Footbridges integrated CCTV security system is
‘Event-Driven’ in order to minimise the requirement for manual operator monitoring.
Therefore, it will be necessary to ensure that all potential areas where an alarm event could
occur, have the appropriate level of surveillance coverage to allow an immediate
assessment to be made.
Furthermore, the system should provide automatic image switching and display to the point
of alarm, as well as pre- and post-alarm recording at full frame rate and resolution.
The third core function of the system will be that of Video Investigation, whereby recorded
video will be utilised to establish the cause of security incidents that have already occurred,
identify potential suspects, facilitate post-incident analysis and provide evidential material
in support of subsequent prosecution.
In order to achieve the required capability, the Contractor must provide both high quality
recorded imagery, as well as the intelligent video search and synopsis capabilities
necessary to provide an efficient means of analysis. Furthermore, the system must be able
to output and manage evidential material to the required local (Dubai Police) and
International standards.
The above functions will primarily be achieved via the use of fixed camera surveillance
coverage of the Footbridges and supporting infrastructure; PTZ cameras may be used in a
supporting secondary role where additional coverage is required to fulfil the Performance
Requirements identified below.
-3-
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
Every camera that will be used for Footbridges will have a clear Operational Requirement
that identifies the specific function and purpose of the device and video output.
The contractor will be responsible for documenting and maintaining these operational
requirements, which are set out in the following table (examples in Italics).
Referencing various Target Image Heights defined as 1.6 meter (i.e. the percentage of the
vertical screen that a human-sized target occupies within the image) provides a useful
means to help ensure that the video surveillance system provides video images capable of
achieving various operational requirements.
This is particularly important for Video Assessment capability given that the operator may
not have time to take advantage of digital zoom or playback. The concept of Target Image
Height is illustrated in the following diagram:
-4-
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
The camera acceptance test must be conduct be using a standard target like the rotiken.
The following table identifies the Target Image Height reference levels that must be utilised
in video surveillance design for Footbridges CCTV system, along with corresponding
Operational Requirements and example applications.
Target
Image Pixels Per Example
Category Operational Requirement
Height Meter Applications
-5-
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
The above table also includes an equivalent target resolution in Pixels Per Meter (PPM).1
This can be used as an alternative reference for High Definition or Megapixel Video
Cameras, where the additional resolution may allow the same Operational Requirements
to be achieved using a smaller Target Image Height; due to the cameras ability to capture
significantly more detail (pixels) within the scene, which subsequently allows areas of the
image to be enlarged within the monitoring application, without compromising image
quality (This is typically referred to as a ‘Digital Zoom’ function and is in contrast with an
Optical Zoom whereby a motorised lens is used to zoom in on a subject).
The use of smaller Target Image Heights than those outlined in the above table may be
acceptable for a small number of cameras under the following circumstances:
1. Cameras images are used primarily in a Video Investigation role where digital
zoom can be applied to achieve the same level of detail at lower Target Image
Heights.
2. Images are used in circumstances where the operator has time to digitally zoom in
to the live image whilst the target is still within the field of view – for example
whilst subjects are in a queue or similar static position.
The Video Surveillance System must provide the following minimum frame rates based on
the PAL video standard:
1. Live Video: 25 frames per second (FPS) for all live video transmitted to the local
monitoring station.
2. Recorded Video: 12 FPS for all standard recorded video (non-alarm conditions).
3. Alarm Video: 25 FPS for all recorded alarm video, including 2 minute pre-alarm
and 15 minutes post alarm.
1
PPM is calculated by dividing the horizontal camera resolution in pixels by the width of the video scene
in meters.
-6-
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
The system must be capable of outputting separate live and recorded video streams, either
directly from the camera of via the Video Management System. In addition it must be
possible to output a third stream to the OCC at a range of user-selected frame rates from 1
to 25 FPS, as instructed by the RTA based upon available backhaul bandwidth.
All video images may be required for use in a Video Investigation role and therefore must
be recorded in sufficient resolution for use as investigative and evidential material. this is
considered to be a minimum of 1080p resolution.
Recorded video will be retained on live/fast storage for a period of 31 days and
subsequently moved to slow/archived storage for a minimum retention period of 3 months
before being overwritten, with the exception of Video Alarm Data, which will be retained
for a minimum of 1 year. The Contractor must implement redundant / failover video storage
via one of the following methods:
The Contractor must provide automatic synchronisation between failover servers, either
via use of a separate synchronisation server, or via virtualisation.
The Video Surveillance System for Footbridges must provide the following capabilities in
order to allow the secure control and export of evidential material:
The Video Management System provided by the contractor must be capable of the
following minimum functions:
-7-
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
2. Local recording and playback (via NVR application) and central recording and
playback at the EC3 & RTAHQ CSC. Video downloads must be strictly controlled
by a nominated person within the OCC only.
3. Integration of alarm event data from other local sub-systems including Video
Analytics, Intrusion Detection, Access Control, Public Address, and Fire Systems.
4. Provide a central alarm stack such that all main sub-system alarms can be monitored
from within the VMS application.
5. Provide automatic image switching and display of cameras associated with alarm
locations.
6. Provide the capability to automatically increase recording frame rate and resolution
in response to alarm events.
7. Provide a Graphical User Interface (GUI) with embedded Footbridges maps that is
capable of displaying interactive sensor icons with activate / deactivate controls,
alarm events and device tags.
8. Support Integration with the existing/new VMS and PSIM systems deployed at
theEC3 & RTAHQ CSC.
1. Captures the frontal area of the face with a maximum operational tolerance of +/-
15 degrees yaw or pitch and 20 degrees roll. The height of the camera and distance
to the person at the target capture point will determine whether or not this is
achieved, as shown below:
-8-
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
3. Use Camera/Lens Field of View (FoV) combinations that provide images with a
minimum of 100 pixels between the pupils of a subject standing at the capture point.
4. Provide the ability to stream live and recorded images at 25 fps.
5. Provide ONVIF compliance for integration of video feeds into third party facial
recognition server applications.
17.1.5.1 Conops
In addition to traditional electronic sensors used to generate alarms, Video Analytics will
be used in selective areas of Footbridges RTA infrastructure in order to further reduce the
requirement for manual monitoring of video surveillance systems and aid security
personnel in detecting and investigating potential security breaches. There will be three
primary categories of video analytics utilised as part of the security function, as identified
below.
1. Intrusion Detection: this will consist of various rules capable of alerting operators
to potential intrusions into restricted areas.
2. Behavioural Analytics: this will include more complex cognitive rules that alert
operators to suspicious behaviour in public areas of the station.
3. Investigative Analytics: this will include tools for the intelligent searching of
recorded video, via the application of metadata to create an automated visual
database of events.
The use of video analytics for Footbridges CCTV system will initially be focused towards
high-risk areas and associated critical assets rather than on all camera feeds.
The following section identifies the specific type of analytic rules and performance
requirements that the contractor must deliver.
The contractor will provide a Video Analytics solution that can perform the following
intrusion detection functions on selected camera video images:
1. Tripwire Detection – creation of a virtual tripwire within the video scene, which
generates an alarm when crossed by a target object such as a person or vehicle.
2. Area Detection – creation of a virtual detection zone within a three-dimensional
space, which generates an alarm when a target object enters.
-9-
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
The contractor’s video analytics solution for the above intrusion detection functions must
provide a minimum of 95% Probability of Detection (PoD) against all types of intrusion,
with a maximum Nuisance Alarm Rate (NAR) of 1 per camera per 48 hours.
The contractor will provide a Video Analytics solution that can perform the following
behavioural detection functions on selected camera video images:
The contractor’s video analytics solution for the above behavioural detection functions
must provide a minimum of 90% Probability of Detection (PoD) against all types of
incidents, with a maximum Nuisance Alarm Rate (NAR) of 1 per camera per 24 hours.
The contractor will provide a Video Analytics solution that can perform the following
investigative functions in relation to recorded video images from all cameras:
1. Define areas of interest and areas of exclusion within the video scene.
2. Define and search by objects of interest, including attributes of colour, size,
direction and speed.
3. Provide a video synopsis function where original video duration is automatically
reduced by applying attribute filters.
4. Allow objects of interest to be tagged and annotated.
5. Provide case management and user access control.
6. Provide secure export of original video footage.
The investigative analytics solution must be integrated with the Video Management System
to provide a seamless operator interface.
- 10 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
All Video Analytics solutions provided by the Contractor must have the following alarm
filter options as a minimum:
1. Time of Day/Week/Month
2. Direction of Travel
3. Object Size/Type
4. Object Speed
The contractor will be required to configure all video analytics rules in such a manner as
to ensure that all of the above performance requirements have been met in full, and in
compliance with RTAs requirements, which may only be defined in full during the
commissioning process. The contractor must also provide full training to RTA staff to
allow the video analytics to be set up by RTA staff in future. Additional support or training
must be provided by the Contractor as necessary throughout the maintenance period.
Video traffic demands high bandwidth and should be isolated from other traffic physically.
Security network should be totally isolated from the operation network and dedicated only
for the security application.
The contractor will be required to consider the following aspects during the network
design:
• The ability to prioritize data packets for services that are more time-critical, such
as achieved with the Quality of Service (QoS).
• Avoidance of the cascade type of CCTV failure that could lead to undesired
bandwidth saturation.
• Ensuring that switching of networks must not interrupt the recording of CCTV data
for more than one second.
- 11 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
Steps must be taken to ensure the physical security and integrity of the system’s recording
device. Placement of the recording device in a restricted-access location, such as a locked
cabinet or room. Note that proper environmental controls must be implemented according
to the manufacturer’s specifications. For example, NVRs and hard drives require adequate
airflow to prevent overheating.
- 12 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
- 13 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
- 14 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
• 3D DNR/Defog/EIS/HLC/BLC
• IP67, IK10
• License plate recognition
• Support vehicle speed under 120km/h (74.6mi/h)
• Up to 10000 whitelist and blacklist
• Reliability Test.
These tests are to be performed at the Contractor's factory, or other approved locations,
before any equipment is shipped to Dubai.
The tests are intended to demonstrate that the hardware and software comprising the system
are in compliance with the Specifications and function together as an integrated system.
The environmental conditions to be tested are identified in Section 1.8 of these Particular
Specifications and all the Outstation equipment are subject to this requirement.
- 15 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
The System Design Document shall identify the test laboratory or laboratories proposed to
be used. The test laboratories shall be subject to the approval of the Client, as shall the test
procedures used by the independent testing laboratory.
The Contractor shall provide the Client with certified copies of test results for all tests
conducted at Independent Laboratories as part of Factory Acceptance Tests.
These tests cover all Outstation and In-station system components being provided as part
of this project, in their installed locations, including all materials furnished and installed.
Complete functionality shall be tested as defined in the System Design Document and as
specified in the Particular Specifications.
Following the successful completion of the Integration Tests, a 12-week Reliability Test
shall be conducted. During this period the complete system shall operate with the specified
level of functionality and reliability and shall operate to the satisfaction of the Client
without unresolved, intermittent or sporadic failures.
RTA reserves the right to terminate the Reliability Test, in the event that major faults are
identified with the deployed system, or RTA is not able to utilize the system to the required
functionality. The Reliability Test Period of 12 weeks will restart from zero after
rectification of the major fault.
All defects detected during or subsequent to the Reliability Test shall have been rectified
and successfully passed their tests prior to the issuance of the Taking-Over Certificate.
The Tenderer shall thoroughly describe his approach to each phase of acceptance testing
in his Proposal.
Detailed FAT and SAT test procedures and schedules shall be finalized by the Contractor
following the System Design Document stage of the Contract. The final test procedures
shall follow the scope and intent of the tests defined herein but shall be expanded in detail
and grouping to conform better to the Contractor's equipment and in-house test procedures.
The Contractor shall not alter the basic testing sequence of Factory and Site Acceptance
Tests.
The Contractor shall submit detailed test procedures to the Client for approval at least four
(1) weeks prior to the scheduled test date. Tests shall not commence without written
approval from the Client for the proposed test procedures.
- 16 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
The Contractor shall provide all equipment and materials necessary to conduct all tests,
including all test equipment.
The Tenderer shall indicate in the Proposal the estimated time required for each test phase
specified herein. The Tenderer shall also describe in his Proposal any additional acceptance
tests considered necessary and shall indicate an estimate of the time required for any
proposed additional tests.
The manufacturer's standard documentation shall be provided for all items of standard, off-
the-shelf hardware and software supplied for the system.
Standard System Documentation shall be submitted at the time of installation on-site of the
appropriate equipment.
The proposal shall include provision of resources to produce documentation throughout the
Contract. Sections issued during the Contract will be regarded as in draft form.
The issuance of Project Documentation is required throughout the Contract to fully inform
the Client of the system being implemented, even if several revisions are necessary for
particular documents.
- 17 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
Project Documentation shall be prepared in a form suitable for inclusion in the relevant
final manuals. This method will save effort and maintain familiarity of the Client's staff
with the information presented.
All Project Documentation shall contain a complete subject index with appropriate cross-
references to other manuals.
The Contractor shall conduct training courses for the RTA's staff. Training courses shall
be designed to ensure that the RTA's staff achieves a full knowledge and appreciation of
the design, operation and maintenance of the equipment and software being supplied as
part of this project.
Training sessions shall be completed to the satisfaction of the Client prior to the issuance
of the Taking-over Certificate.
The Contractor shall be responsible for the provision of suitable training facility, training
documentation, appropriate System equipment and teaching staff.
The Contractor shall be responsible for providing all necessary meals during any
continuous training sessions extending from morning until late afternoon. All trainings
shall take place in Dubai.
The courses shall be a combination of lectures and demonstrations and shall provide
practical (hands-on) training and experience, as appropriate to the specific training course.
The Contractor shall provide a detailed program of training and a syllabus for each course
for the approval of the Client within the System Design Document period of the Contract.
The information shall include tentative dates for courses, locations, an outline of topics and
names of instructors.
Upon completion of Final Acceptance Test activities to the satisfaction of the Client and
upon compliance with all other specified requirements, the Taking-Over Certificate will be
issued.
- 18 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
Upon issuance of this certificate, the Defects Liability Period of the Contract and First Year
of Maintenance shall commence.
- 19 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
17.3.1 WARRANTY
The Contractor shall provide a comprehensive warranty of all components and system,
including software provided under this contract. The scope of the warranty shall provide a
comprehensive on-site warranty, which covers materials and workmanship, such that
equipment and systems continue to meet their performance measures as set out in the
contract.
The intent of these warranty requirements is to influence design of equipment and services
to provide the Client with a system with a minimum design life of fifteen years. Given the
functional nature of these system specifications and the system design latitude permitted
to encourage the application of state-of-the-art advances, these guarantees are considered
minimum assurance that sound design practices shall be used.
The Contractor shall guarantee that all articles of equipment, including all parts thereof,
are of first quality throughout and comply in all respects or are fully equal to standards
called for in the specifications. The Contractor shall further guarantee all equipment, and
all parts thereof, against any defects of workmanship, construction, and materials and shall
guarantee to repair or replace, without cost to the Client, any article that has become
defective, and not proven to have been caused by negligence on the part of the user.
The Warranty Period of one year shall begin upon commencement of the Defect Liability
Period and continue until issuance of the Defect Liability Certificate.
The Contractor shall be responsible for repairing and/or replacing all hardware and systems
supplied under the Contract. The Contractor shall also bear the total cost of delivery and
transportation costs related to the repair of the supplied equipment during the terms of the
guarantee as detailed in this section. The Client shall reserve the sole right to determine
unsuitability of the supplied equipment within the warranty period.
The Contractor shall determine appropriate failure rates and repair times for all equipment
supplied under this Contract. Based on these rates, the Contractor shall provide the
necessary spare materials, components, and/or parts to ensure the continued proper
operation of the CCTV System. These materials and components shall form the basis for
the spares-holding requirement and shall include both local repairs and repairs that may
require shipment to the factory.
- 20 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
In the event of failure on the part of the Contractor to replace or put in first-class condition
any such equipment/sub-assemblies within thirty (30) calendar days from the date of
notice, the Client may have the work done by others and charge the cost to money due, or
that may become due to the Contractor, or if there be no money due, the Contractor shall
agree to pay such costs.
17.3.2 MAINTENANCE
It is required that the various equipment and components making up the CCTV system be
maintained to a high level of operational integrity by the Contractor for a period of three
(3) years following the successful completion of the Reliability Test and Issuance of Taking
Over Certificate. This section describes the required functions and performance standards
expected for maintenance of the CCTV system.
In addition to maintenance during the three-year period specified above, the Contractor
shall be fully responsible for all maintenance activities for the period between installation
of equipment and issuance of the Taking-Over Certificate. All costs incurred by the
Contractor for maintenance prior to the Taking-Over Certificate shall be considered to be
included in the costs for the associated components.
Following completion of the specified three-year maintenance period, the Client may
request the Contractor to provide maintenance services for additional years. Annual
increases in rates for maintenance beyond the third year shall be limited to a maximum of
five (5) percent per year.
A complete program of weekly, monthly and quarterly routine preventive maintenance and
repair functions must be provided to maintain the system components in proper operations.
Maintenance and repairs shall include all such instances that require such activities
including ordinary equipment and/or hardware failures and damages caused by outside
agencies. These maintenance and repair functions are considered a part of the general
responsibility of the Contractor and will not be a separate rate pay item.
Certain items and/or components, however, may be subject to damage and/or destruction
by forces outside the Contractor's direct control. Cabinets, poles and support structures and
other items that cannot be effectively protected from outside interference must be properly
restored to their original condition by the Contractor, even when damaged by forces outside
his control. Under such circumstances, the Client will reimburse the Contractor for the
costs involved from the agency and/or person responsible for such damages.
- 21 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
In order to ensure the maximum utilization of the system and its components, the
Contractor shall undertake a program of preventive maintenance. This program requires
the periodic inspection, cleaning, lubricating or other recommended preventive
maintenance activities regarding each component of the CCTV System.
The Contractor shall maintain a log of all preventive maintenance activities undertaken. A
copy of the log shall be provided to the Client at monthly intervals.
The Tenderer shall submit with his Proposal a detailed outline of the anticipated periodic
maintenance activities and schedule (frequency) for the CCTV System.
System elements are divided into a number of categories, in order to describe response
and repair requirements, as follows:
The Tenderer, in his response, shall identify his “critical” and “noncritical” components.
Critical components shall be those components that impact the ability for staff to monitor
and operate the CCTV system.
The Contractor shall make available adequate levels of personnel, equipment, test facilities
and repair facilities, including necessary transportation and mobile workshops, to achieve
the minimum response and repair time requirements.
The response and maximum continuous outage times indicated in this table include normal
periods (0600-2200) as well as night response times. Fridays and official holidays will use
right response times.
- 22 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
The Tenderer should indicate any suggested changes to these response times and
procedures in his Proposal, along with any explanatory information that is required.
Exhibit 6.1
Minimum Maintenance Response and Repair Requirements
Response Time Maximum Continuous Outage
Normal Night Factor Normal Availability
Item Night (Hrs)
(Hrs) (Hrs) (%) (Hrs) Ratio
Critical Instation
1 6 95 3 12 99
Equipment
Non-critical Instation
2 12 90 24 48 98
Equipment
CCTV Equipment 2 12 95 6 36 99
Outstation Equipment 2 12 90 24 36 99
Communications
1 6 95 24 36 99
Network
Applications Software 1 6 95 3 12 99
Night - “Night” encompasses the period between 22:00 and 6:00 daily. Response times for
Night also apply all day on Fridays and on official national holidays.
Response Time - The time allowed from notification of a fault until a Contractor's
representative is at the scene of the fault.
Factor (%) - The percentage of times that the Contractor is expected to conform to the
Stipulated Response Time for each specific fault category.
Availability Ratio - A ratio relating the serviceable time for an equipment item to the
serviceable plus out-of-service time.
The Contractor shall make available the necessary personnel, equipment and spare
components to effect repairs to any system component on an emergency basis. Traffic
accidents and other extraordinary events that demolish or otherwise render inoperable
- 23 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
system components, including poles and support structure, are considered to fall under this
category. The Tenderer shall identify in his proposal the magnitude and nature of such
events that he anticipates and plans for.
The Contractor shall maintain an adequate level of spare equipment and components in
Dubai to meet the specified maintenance requirements at all times. The minimum amount
of spares holdings shall be determined by a combination of the MTBF for the individual
component, the number of units in the system and the anticipated order and delivery time
for replacement units.
The Tenderer shall include in his Proposal a list of all equipment items to be included in
the system down to the circuit board level. The MTBF rates for each of these items shall
be indicated, along with the number of units in use. At a minimum, the Contractor is
required to maintain spare component assemblies equal to a four-week supply at the
indicated MTBF rates and the number of units in use. The Tenderer shall provide a
complete listing of the anticipated spares holdings in his Proposal.
Components below the circuit board or assembly level must be maintained at a level equal
to the anticipated number of failures during the order and delivery time of the components.
The Contractor shall submit an updated list of proposed spare equipment and components
to the Client for approval. This list shall be submitted a minimum of 4 weeks before
commencement of the Defect Liability Period.
The Contractor shall establish and maintain the necessary physical facilities to allow the
timely completion of the required maintenance duties. This shall include, but will not be
limited to, the following: office and working space, test equipment, tools, rolling stock,
mobile workshops and spare components and assemblies.
Test equipment shall be provided by the Contractor to allow the complete testing and
diagnosing of problems relating to CCTV equipment. Test equipment shall also be
provided to allow the testing and diagnosing of electronic circuit problems on the
component circuit boards contained within the devices of the system.
All test equipment used by the Contractor shall have current calibration certification
available for inspection by the Client.
The Contractor shall keep an accurate and detailed record of all maintenance activities.
Standard forms shall be developed to serve as a basis for the recording system.
- 24 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
Data items, which should be included in the forms for the various maintenance activities,
are listed below. Additional information felt to be necessary should also be included. The
forms shall be subject to approval of the Client.
Daily Maintenance
• date;
• time and source of notification of a fault;
• fault reported;
• time of arrival at location of reported fault;
• fault discovered;
• disposition of fault;
• identification of equipment and components replaced;
• time spent on the fault;
• identification of further action required; and
• personnel conducting maintenance.
- 25 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
When a shipment of components, assemblies etc. is received, the inventory records shall
be updated to reflect the items received.
An inventory record shall also be maintained that indicates the date each item was ordered
and when it was received.
The Contractor shall submit to the Client a detailed monthly report of all maintenance
activities and a summary of updated MTBF rates for all items maintained on inventory. An
annual report shall also be provided. These reports shall include; but will not be limited to,
the following;
These reports should also include any suggestions and/or recommendations for
improvements to the maintenance procedures and programs.
The Contractor shall be responsible for coordinating with the Client on the format and
content of all Maintenance Reports.
The reports shall be given as per the Client’s system using a performance indicator
technique to show the Contractor’s performance. These indicators include:
• Response Time
• Outage Type
• Time to Repair
• Availability Ratio
All maintenance activity records and inventory records shall be stored in a computerized
database at the Contractor's maintenance facility. A copy of these records shall be
transmitted electronically to the Client as they are updated, in a format approved by the
Client.
The Contractor shall provide an electronic mechanism to access the CCTV system data in
order to ascertain operational and failure status, and shall provide RTA staff with on-
demand access to maintain reports, as well as the ability to issue work orders to the
Contractor.
- 26 -
SECTION 17 SECURITY CCTV PERFORMANCE
REQUIREMENTS
The format and content of the maintenance database shall be subject to the approval of the
Client.
The maintenance database shall be the property of the Client, who shall have the right to
use it for any other purposes or to continue using it, if CCTV maintenance activities are
subsequently performed by other contractors.
The Contractor shall provide training, documentation, source code, and a licensed copy of
the maintenance database software to the Client for the Client’s use.
- 27 -
Section 18
Metal Works
SECTION 18 – METAL WORKS
TABLE OF CONTENTS
-1-
SECTION 18 – METAL WORKS
1 MATERIALS
1.2 Steel
(i) Where the terms "steel" or "mild steel" are used it shall mean steel to BS 4: 1, BS 1449,
BS 4360 or BS 4848 and shall be Grade 43a unless specified otherwise.
(ii) Stainless steels shall be austenitic non – magnetic steel unless specified otherwise and
shall be in accordance with BS 1449; Part 2 and BS 3100: 18/10/3 Chromium – nickel
– molunclenum group (BS Type 316) and finish shall be as specified. (e.g. Dull Polish,
Mirror Polish etc).
1.3 Aluminium
(i) The term "aluminium" shall mean `wrought aluminum alloys for general engineering
purposes' in accordance with the BS 1470 - 1475 series and `cast aluminum' shall be
aluminum cast by permanent mould or gravity die techniques to BS 1490 using LM6
alloy.
(ii) Fittings shall be aluminum alloy in accordance with BS 4951 the latest edition.
(iii) All exposed surfaces shall be polished to a mirror – like surface, free from defects, and
shall be light etched and anodized in a satin or a Matt champagne or silver or bronze or
brown finish as shown on drawings and as directed in writing by the Engineer.
(iv) Aluminum shall be treated to comply with BS 1615, and BS 3987, to provide an
anodization not less than 20 microns thickness.
(v) All aluminum sections shall present clear straight and sharply defined lines and shall
be free from defects and imperfections that may impair their strength.
(vi) All screws, bolts and other necessary accessories shall be of aluminum or other non-
corrodable material and shall match in color and consistency the finish of the anodized
aluminum.
(vii) Aluminum elastic glazing beads shall be provided to all windows and doors, which are
assembled by pressure to fit with the relevant groove in the profile.
(viii) The glazing bars shall be threaded or interlaced at points of intersections and machine
tenoned to frame.
(ix) The Contractor shall submit samples of components to the Engineer for approval
together with test certificates which show that the components possess the following
characteristics.
Mechanical Properties :
Cupping test to DIN 53156 9 mm
Bend test to DIN 53152 Less than 5 mm
Reverse impact to ASTM 27944-69 100-150 cm/kg
-2-
Indentation hardness to DIN 53153 More than 100
Pencil hardness 2H
Cross cut test to DIN 53151 Gt.0
Chemical Resistance :
Humidity test to DIN 50017 on zinc phosphated No change after 500 hours.
steel sheet
Salt spray test to ASTM B 117 on zinc No loss of adhesion after 20
phosphated steel sheet rounds
Weathering in Florida (USA) and industrial
Excell
ent results climate
(ii) Mill finish aluminum will not be accepted unless specified or to the Engineer's written
approval or to be subsequently decorated.
-3-
Plain washers shall be made of galvanized steel. Taper or other specially shaped washers shall be
made of steel or malleable cast iron and shall conform to the requirements of BS 4230, Metal
washers for general engineering purposes.
(v) As far as possible the assembled units as a whole shall be coated to avoid joint heat
build-up, scratches, touching up joints, etc. Powder coating shall be carried out in a well
established factory fully equipped for such works and shall be subject to the approval of
the Engineer.
(e) Painting
When described on the drawings/schedules painting of metalwork shall be in accordance
with Section N of this specification.
2 COMPONENTS
-4-
as they are applicable to the specific component, and where a British Standard exists for
that component it shall also be complied with.
(iii) The shop drawings referred to in 2.1 (i) above shall conform to the design, dimensions and
general descriptions as shown on the drawings/schedules and as specified.
(iv) After finalization of all details, prepare control samples as requested and obtain approval of
appearance before proceeding with manufacture.
(v) All fixings shall be of materials compatible with the component being fixed and where
dissimilar metals are used adequate precautions, such as coating or sleeving, shall be taken
to prevent electrolytic corrosion.
(vi) All nuts and bolts shall be adequately protected from corrosion and all exposed bolts
including Carpenters and Joiners metalwork are to be capped with an approved dome
headed nut.
2.3 Substrate
The flexible substrate is a durable, flexible, translucent, dimensionally stable material consisting of a
polyester scrim embedded between two layers of white pigmented vinyl specially formulated to accept
the decorative graphics material.
The flexible substrate manufacturer must give written approval of compatibility of the substrate with
the decorative material used, and must warranty against failure of the substrate due to chemical
incompatibility with the graphic material and the materials used to transfer the graphics onto the
substrate.
Typical characteristics of the flexible substrate are :
-5-
Property English Units Metric Units
Light Transmission 28 % ± 2 %
28 % ± 2 % (Opacity)
Support combustion U. L.
Recognized
CIELAB L*=-90.20
-6-
SECTION 18 METAL WORKS
2.4 Workmanship
2.4.1 General
(i) All metalwork shall be undertaken in accordance with sound engineering and smithy
practice and as much metalwork as possible shall be undertaken in properly equipped
workshops with site work restricted to fixing and other operations that cannot be
undertaken prior to delivery to site.
(ii) All finished components shall be wrapped, taped or otherwise protected with non-
absorbent coverings and delivered to site at a time to eliminate or reduce to a minimum,
storage on site prior to fixing.
(iii) Protective coverings shall be sufficiently removed for jointing, assembly and fixing
purposes and afterwards replaced.
(iv) After erection all metalwork with applied finishes shall be adequately protected from
any damage and any such work which is scratched, marked or damaged in any way shall
be suitably repaired if appropriate, to the Engineer's approval or, if so instructed by the
engineer, replaced at the Contractor's expense.
(v) The Contractor shall submit to the Engineer evidence that the thickness of
protective/decorative coatings are not less than as specified and in cases of doubt the
Engineer may instruct the Contractor to send sample pieces to independent testing
laboratories and the cost of all such testing shall be borne by the Contractor.
(vi) All window, door, screen, and other like frames shall be made to allow a 5 mm
tolerance all round the opening in the structure and junctions shall be finished off by
applying an approved sealant onto a closed cell polystyrene foam backing strip or as
otherwise shown on drawings or specified.
(vii) Discrepancies in overall width or height exceeding 5 mm will not be allowed and where
such discrepancies occur the frame will be rejected.
(viii) Welding shall be undertaken in accordance with the appropriate British Standard for the
type of metal being joined.
(ix) Aluminium fixed against or into cementitious materials or stone/brickwork shall be
adequately protected by plastic spacers/sheeting or two coats bituminous paint applied
to the fixed face of the component.
All steel members in contact with the soil shall be painted with two (2) coats of protective asphalt
paint. All doors, frames, staircases, etc. shall be given at least one (1) coat of approved rust inhibiting
primer before delivery to site.
Frames for doors and windows shall be provided with not less than (3) adjustable type anchors on each
jamb, minimum distance between anchors shall be eight hundred (800) mm.
All joints shall be machined to a close fit and all pins and screws shall be countersunk and dressed
flush after assembly.
-7-
SECTION 18 METAL WORKS
Forging shall be sharp and true. Curves, intersections and members of the same size shall be halved
together.The plain surfaces shall be smooth, free from warp or buckle. Moulded members and mitres
shall be clean, cut straight and true. Construction joints shall be welded their full length and cleaned
off flush on exposed surfaces.
All work shall be erected plumb and true to lines and rigidly secured to walls, floors or ceilings as
shown on drawings and to the satisfaction of the Engineer.
Ironmongery for steel doors, etc. shall be as specified under “CARPENTRY & JOINERY”
2.4.3 Aluminium
The Contractor shall furnish and install all aluminium units as indicated on the drawings.
Workmanship and installation shall be in accordance with recommended standards of first class
aluminium manufacturers.
All aluminium work shall be performed in a shop where the grade of metal work is of recognized
quality acceptable to the Engineer. All items shall be installed plum, straight, square, level and in
proper elevation, plane location and alignment with other work. All work shall be designed for
adjustment to field variations, fitted with proper joints and intersections, adequately anchored in
place, strictly in accordance with best practice.
Aluminium for arches shall be extruded from soft aluminium sections to achieve the required radius
as stipulated and detailed in the drawings. Tenderers are contractually required to submit, for
Engineer‟s approval, a sample of the proposed section together with all relevant and necessary data.
Where aluminium surfaces come in contact with metals other than stainless steel, zinc, white bronze
or small areas of other metals compatible with aluminium surfaces, they shall be kept from direct
contact with such parts by painting the dissimilar metal with a prime coat of zinc chromate primer or
other suitable primer, followed by one or two coats of aluminium metal and masonry paint or other
suitable protective coating, excluding those containing lead pigments, or a non-absorptive tape or
gasket shall be placed between aluminium and dissilar metals. Steel anchors and connecting members
shall be hot dip galvanized or zinc plated after fabrication.
Aluminium surfaces in contact with lime mortar, concrete, plaster or other masonry materials, shall
be painted with alkaline- resistant coatings such as heavy – bodied bituminous paint or water – white
methacrylate lacquer.
Aluminium in contact with wood or absorptive materials which may become repeatedly wet shall be
painted with two coats of aluminium metal and masonry paint or a coat of heavy – bodied bituminous
paint. Alternatively paint the wood or other absorptive material with two coats of alumiuium house
paint and seal joints with a good quality of caulking compound.
Where aluminium is in contact with treated wood, wood shall be treated with pentachlorophenol, 5%
minimum concentration or approved equal, followed with the protective measures described for
aluminium in contact with wood or other absorptive materials.
The aluminium work shall be designed and anchored so that the work will not be distorted nor the
fasteners overstressed from the expansion and contraction of the metal.
Before shipment from factory, aluminium surfaces requiring protection shall be given a coating
which will protect the metal during construction. In areas where appearance of the finish on
aluminium items is important, a coating of methacrylate type lacquer shall be applied as specified
hereinafter.
Apply two sprayed coats of water – white methacrylate lacquer having a total minimum thickness of 0.015
mm, which when applied to the aluminium surface shall be capable of withstanding the action of lime
mortar for a period of at least one week in an atmosphere of 100% relative humidity at 40 degree
-8-
SECTION 18 METAL WORKS
centigrade, the action of 10% (by weight) muriatic acid for a period of six hours at 20 degree centigrade,
and the action of atmospheric weathering for a period of 12 months.
The coating shall be applied in the manufacturer‟s plant to the exposed surfaces of all aluminium
components subject to staining from alkaline mortar and plaster, abrasion and other construction
abuses. Before application of lacquer, the manufacturer shall remove all fabrication compounds,
moisture, dirt, accumulations and other foreign materials to ensure proper lacquer adhesion.
Upon completion, the Contractor shall clean all aluminium work as required by removing protective
tape orther coating, using mild soap or detergents and clear petroleum spirits.
Acids caustics and abrasives shall not be used. Where cleaners are used to remove excess sealing
compounds care shall be exercised to prevent damage to seals or staining or damage to adjacent
work.
The Contractor shall be responsible for the protection of all aluminium work until the completion of
the works, and only units in perfect working order and in perfect condition shall be accepted.
3 STEELWORK
(i) All steelwork shall be provided and fixed complete with all plates, cleats, bolts, etc., cut
to lengths and sizes and drilled as shown on the Drawings. Steelwork generally shall
comply with BS 4 part 1, BS 2994 or BS 4848 Part 4.
(ii) Rag bolts and nuts shall be mild steel to BS 1494 Part 2. Black bolts shall comply with
BS 4933 and washers to BS 4320.
-9-
SECTION 18 METAL WORKS
(iii) The steel sections where specified to be factory rustproofed shall be rust-proofed by hot
dip galvanizing, metalizing or sheradizing process. The rust – proofing shall be sufficient
to withstand the 72 hours salt – spray test as provided for in BS 5466 : If the rustproof
coating suffers any damage during the progress of work, the damaged part shall be re-
coated to a minimum of the original thickness to the satisfaction of the Engineer.
3.1 Fabrication
(i) All fabrication and welding shall comply with BS 449 Part 2.
(ii) Welding shall be carried out by skilled operatives with proven qualifications and
experience in using the same electrode, class and welding positions which will be required
in the work and shall comply with BS 1856. The competence of all welders shall be tested
in accordance with the relevant BS.
3.2 Priming
All steel items which are not galvanized or zinc coated are to be primed with a coat of
approved rust- proofing primer. Items which have been primed before delivery to site should
immediately be touched up with similar primer and every effort made to protect the members
from damage during fixing. All structural steelwork is to be adequately protected from the
effects of the weather before fixing.
3.4 Welding
(i) All welding at works shall be carried out in accordance with BS requirements. All
welding operatives employed shall be tested and qualified welders in accordance with
BS recommendations and the Contractor shall submit to the Engineer, if required,
evidence of qualification.
(ii) All welded connections shall be accurately made and the joint faces formed in
accordance with BS for metal type and thickness as appropriate and any necessary pre-
treatment due to metal thickness or type shall be undertaken. All welding electrodes shall
- 10 -
SECTION 18 METAL WORKS
3.5 Inspection
The Engineer may employ, to act on his behalf, an Independent Weld Inspection Company
to carry out regular inspections and nondestructive, and visual examinations, whilst the
fabrication and erection are in progress to ensure compliance with the Specification and BS
requirements and an adequate standard of workmanship and supervision for the works.
The Contractor is to allow unrestricted access and facilities at his works or those of his sub-
contractors or on site for authorized personnel to carry out inspection procedures on behalf
of the Engineer, in respect of the fabrication, erection and or welding of the Steelwork.
3.6 Stability
All erected steelwork shall be true to line, level and plumb, and securely bolted and fixed
with temporary bracing to resist safely all loads from erection procedures and or all
accidental and natural forces which may occur. All connections shall be permanently
bolted when the members are fixed true to line, level and plumb.
3.8 Protection
(i) The Contractor will be responsible for all preliminary cleaning and priming at works
prior to delivery and all making good of the initial protective film on site due to damage
in transit or during erection prior to handing over of the steelwork.
(ii) In addition all site bolted or welded joints shall after erection be painted as the remainder
of the steelwork. Where load indicating washers are used with HSFG bolts particular
care is to be taken to fill and seal the gap between the washer and the fittings created by
the indicating nibs.
(iii) All types of paint of protective medium are to be used and applied to the steelwork in
accordance with the appropriate section of BS and CP requirements and the
manufacturer's recommendations and instructions for the type of paint or material being
employed and also the type and workmanship for cleaning and preliminary protection.
All steelwork after fabrication is to be cleaned by picking and subsequently hot dip galvanized in
accordance with the BS to give a minimum coating thickness of 100 micron.
3.10 Design
- 11 -
SECTION 18 METAL WORKS
(i) The Engineer will supply the Contractor with the information and drawings he requires
preparing and completing his shop drawings. The Contractor shall,unless otherwise
specified, prepare and check shop drawings incorporating sufficient information for the
proper fabrication of the steelwork.
(ii) In the event of any contradiction or ambiguity in the information or drawings supplied by
the Engineer becoming apparent the Contractor shall immediately inform the Engineer
and obtain from him written clarification.
(iii) The Contractor shall check dimensions and prepare shop drawings for the steelwork. The
Contractor shall be responsible, unless otherwise specified, for the design and sufficiency
of the structural steelwork. Where certain sections of the work have been designed by the
Engineer, the Contractor shall check and verify the sufficiency of the design and take full
responsibility for it.
(iv) Before commencing fabrication the Contractor shall obtain the approval of the Engineer
in writing for all shop drawings. This approval will signify verification of the correct
interpretation by the Contractor of the Engineer's requirements but shall not signify
approval of the dimensions. Notwithstanding such approval the Contractor shall be
entirely responsible for the accuracy of the shop drawings, the correctness of detail and
the proper design of connections and joints. The Contractor shall supply the Engineer with
complete sets of working drawings.
(v) Structural metalwork items included in this project are entirely the design responsibility
of the sub-contractor.
(vi) All structural steelwork shall be designed in accordance with the requirements of BS 449,
"The use of structural steelwork in building" and other standards specified therein. The
Contractor shall carry out his design calculations accordingly and shall submit such
calculations for checking by the Engineer if requested to do so.
- 12 -
APPENDICES
Appendix A
Mechanical and Electrical
Design Guidelines and
Specifications
R1117 Improvement of Al
Mustaqbal Street
Mechanical and Electrical
Design Guidelines and
Specifications
Submitted to:
May 2024
Revision 0
Mechanical and Electrical Design Guidelines and Specifications
Page 1 of 417
Mechanical and Electrical Design Guidelines and Specifications
1.1 General
Please note that the Employer Requirements is the main document to meet
the Project Requirement. The Guidelines and Specification in this document is
only to provide guidance on the minimum requirements to the Project. The
Contractor shall include for the design, supply, installation, testing and
commissioning of the Mechanical and Electrical Services detailed in the Contract
Documents.
The Contractor shall include for Client staff training in the operation and
maintenance of the works.
The Contractor shall include for promptly rectifying defects during the
maintenance period.
Any item in any section of the specification shall apply equally and wherever
appropriate to any item in any other section.
1.2 Responsibilities
No claims for additional money or time will be entertained by the Engineer after
award of the Contract.
The Contractor shall be responsible for ensuring that the works are completed
in accordance with the Employer Requirement, contract documents and the
construction program. He shall be responsible for ensuring that all working
drawings, materials and labor are in place, to complete the works to the
specified quality and on time.
The Contractor shall be responsible for design and final verification of the
works to ensure that the works meet the project objective.
The Contractor shall be responsible for providing all required design calculation
and reports, which will include concept, preliminary and detail design stage. It
is the responsibility of the Contractor to timely incorporate/substantiate the
comments raised by the Engineer and the Employer in each stage of the
design before moving to the next stage of the project.
Page 2 of 417
Mechanical and Electrical Design Guidelines and Specifications
The Contractor shall be responsible for liaison with the local statutory
authorities to ensure that electricity, water, fire, drainage, cooling etc.
interfaces are incorporated in the works.
The Contractor shall obtain all necessary local authority completion certificates
prior to the practical completion certificate being issued.
1.3 Coordination
The Contractor shall ensure that all plant offered is of latest models, suitable
for its purpose and that it can be accommodated and supported in the
positions shown.
The Contractor shall bring to the Engineers attention, prior to submitting his
tender, in writing, any discrepancies between the Contract Documents and the
above, no claims for money or extension of time shall be entertained for such
discrepancies after award of Contract.
Page 3 of 417
Mechanical and Electrical Design Guidelines and Specifications
The Contractor shall be responsible for all health and safety issues relating to
the works.
The Contractor shall submit for approval by the Engineer, a Health and Safety
plan. The plan shall cover:
The approved health and safety plan shall be displayed on the Contractors
notice board at all times.
The Contractor shall train his staff in the use of fire extinguishers, first aid, safe
use of ladders and scaffolds.The Contractor shall ensure that his staff and
official visitors to the site are provided with:
• Safety Helmets
• Safety Shoes
• Eye Protection
• Ear Protection
• Safety Harnesses
• As indicated by the work situation.
The Contractor shall use 110 volt tools and lamps, unless otherwise approved
by the Engineer.
Contractor shall insure and achieve suitable air quality during construction and
prior of occupant as required in DM green building regulations item
401.02 and 401.06, including the certification and tests.
1.7 Materials
All materials and equipment shall be new and shall be manufactured under ISO
9000, or equivalent. At any time materials which are identified as of inferior
design or make, or which are considered as unsuitable for the proposed
application shall be rejected by the Engineer, and such items shall be at once
removed from the site and correct materials shall be provided entirely at the
Contractors expense.
Page 4 of 417
Mechanical and Electrical Design Guidelines and Specifications
All materials shall be selected using the following criteria: Local availability of
spare parts and after sales service for 15 years after Defect Liability Period.
Local availability of technical support- (Must have Manufacturer’s Authorized
Technical Representative with proven record of relevant Training and
experience)
The Contractor shall include in the tender for the provision of materials and
equipment, etc. as specified herein. The Engineer may reject any items with
which he is not satisfied, and his decision shall be final and binding.
All materials shall be transported to site and stored on site in accordance with
the manufacturer’s instructions. All critical equipment which are prone to
damage due to local ambient conditions must be stored in in-site air-
conditioned stores.
1.8 Workmanship
The Engineer shall reject any part of the installation which, in his opinion, is not
properly erected or installed by reason of poor workmanship and such parts
shall be made good to the best accepted standards, entirely at the Contractors’
expense.
The Contractor shall submit to the Engineer for approval, all drawings detailing
the works including, Concept Design, Preliminary Design and Detail Design.
All drawings lists must be approved by consultant and must be submitted with
the project closure hand over documents.
Page 5 of 417
Mechanical and Electrical Design Guidelines and Specifications
The working drawing numbering system and title block shall be submitted to
the Engineer for approval prior to submission of any shop drawing.
Within two (2) weeks of award of contract, the Contractor shall submit to the
Engineer for approval a drawing schedule, the schedule shall detail the
following:
Within two (2) weeks of award of contract the Contractor shall submit to the
Engineer for approval a material approval schedule, the schedule shall detail
the following:
The Contractor shall submit four (4) copies of the material submittal to the
Engineer for approval; the submittal shall be accompanied by an approved
approval form.
The Contractor shall test and commission the works to the approval of the
Engineer. The mechanical works shall be tested and commissioned in
accordance with the BSRIA and NFPA, ASME, NEC commissioning codes to
the satisfaction of the Engineer. Fire pumps shall be tested to NFPA 20
Page 6 of 417
Mechanical and Electrical Design Guidelines and Specifications
• Drainage pumps
• Fire pumps
• Fire Protection System
• HVAC Balancing
The Mechanical services Subcontractor shall record the results of all checks
and measurements during commissioning and hand a copy to the Engineer as
part of the “hand-over” information. The Test Report format shall be submitted
to the Engineer and Client for approval, prior to starting of any tests.
The Mechanical and Services Sub-contractor shall allow adequate time in his
program of works for both his commissioning activity and for the Engineers
acceptance tests.
Under no circumstances will the Engineer allow the Contractor to use his own
staff for the following Mechanical Services instead Contractor has to use
qualified third party consultants:
The Contractor shall submit to the Engineer for approval his “close-down”
program for the works. The program shall address the following as a minimum:
The Contractor shall submit the Engineer for approval, a detailed method
statement for each testing and commissioning activity.
Page 7 of 417
Mechanical and Electrical Design Guidelines and Specifications
The Contractor shall ensure that he gives the Engineer at least two (2) working
days written notice of any tests requiring witnessing.
Successful test records shall be counter signed by the Engineer and bound into
the Operation and Maintenance Manual.
The Contractor shall maintain, on site, a paper print copy of each approved
“Construction Issue” working drawing. The drawing shall be marked up by the
Contractor with any site changes. The drawing shall form the basis of the
projects record drawings.
Each record drawing shall be marked “As built” as well as the completion date.
The manuals shall be submitted to the Engineer for approval, draft manuals
shall be submitted before the Practical completion of the project. The Testing
and Commissioning results may be subsequently added to the draft manual.
The draft manuals shall be retained on site until the final manuals are approved
by the Engineer.
Four copies of the manuals shall be required from the Contractor. The manuals
shall be bound into A4 size plastic ring binders with front covers providing the
necessary information in the following format:
Page 8 of 417
Mechanical and Electrical Design Guidelines and Specifications
Startup instructions for each system Shut down instruction for each
system
Schedules of plant / equipment with reference to drawing number
(e) As Built Drawing – Schematic valve charts for each plant room and service
shaft. These are to show valve identification and isolation sequence, one
copy is also to be located in each plant area.
The Contractor shall hand over the following spares and tools:
Manufacturers recommended spares and tools for all equipment’s and diesel
driven plant for two year operation unless otherwise specified.
Four (4) number manhole keys Two (2) sets of valve keys
One (1) spare belt for each belt driven item.
One (1) set of bearings for each type of pump and fan.
One (1) year supply of chemical for water treatment systems
One (1) set of spare sprinkler heads and tools in a lockable box in accordance
with LPC regulations
2 DESIGN DESCRIPTION
The Contract Documents have been prepared using the following design criteria.
Page 9 of 417
Mechanical and Electrical Design Guidelines and Specifications
The declared electric supply for the project is 400 volts, 3 phase, 50 Hz all
equipment incorporated in the works shall be suitable for this voltage.
Service Name
The equipment installation and construct shall be as per fire and life safety
code 2011 and its latest edition and Dubai civil defense regulations, contractor
to provide all design, equipment, material with fully comply with Dubai civil
defense regulations.
Note: The Contractor shall visit the site, survey thoroughly all the existing
installations to confirm that all existing services re-routing/re-location/interface
with existing services are included in this contract and bring to the notice of the
Engineer during tender if any discrepancy. No claims shall be entertained later.
Page 10 of 417
Mechanical and Electrical Design Guidelines and Specifications
2.6.2 Drainage
Soil and waste connections will be taken from within the building to the DM
gravity collection system .
Rain water outlets shall be taken to DM storm water drain for the Building.
Hot and Cold water supply system including storage tanks, Sandwich Panel
construction room, and accessories, domestic water booster pumps and
controls, and distribution services to sanitary fittings and other utilities to
Ancillary Buildings. Hot water supply system including hot water heaters and
distribution services to sanitary fittings and other utilities to the Ancillary
Buildings.
Distribute chilled water from the nearest District Cooling Network located in the
vicinity of the project.
From the pump room located in the Stake Holders Building sites a pipe work
distribution network to supply wet fire standpipe system shall be provided
Fire Fighting Wet Stand Pipe will be installed on both sides within the sidewalk.
The exact location shall be decided on site and approved by the Civil Defense
Department. A water connection shall be taken from the Fire water pump
station which is to be located near the nearby Building. This Fire Water pump
station shall have its own Fire Water storage tank. The Fire water storage tank
shall be sized to be suitable to supply water for fire fighting for one hour. The
water supply to the Fire water storage tank shall be from nearest Irrigation
water or DEWA Water main, subject to the approval. The continuous pressure
required in the wet standpipe shall be 100 PSI (6.9 bar) at each fire hose. Both
the Main fire water pumps shall be electric motor driven.
The Electric supply shall have a Diesel Generator back up, to provide power in
case of DEWA Mains failure. A jockey pump will maintain the system under
pressure at all time. The 6.9 bar pressure shall be maintained at the farthest
point of the fire fighting system. Fire water pipe shall be of HDPE and Hot Dip
Galvanized internally and externally and painted with Epoxy powder Red color
from outside, with UL approval. The complete fire water system shall be
designed as per NFPA 502 Regulations, NFPA 14 Regulations and as per
Dubai civil Defense requirements.
Page 11 of 417
Mechanical and Electrical Design Guidelines and Specifications
Whenever available pressure would exceed 100 PSI, a pressure reducing valve
shall be installed on the connection line. A pressure gauge shall also be
provided at each FHC to indicate the available pressure.
Two Fire Department Siamese connections will be located at each end of the
pedestrian bridge.
Provide all necessary piping, valves, Air release valves, drain valves, tees, and
connections from the Fire water pump station to the fire hose cabinets, within
the Ancillary Buildings .
3.1 General
This section is not intended to delegate functions nor to delegate work and
supply to any specific trade, but rather to generally designate a basic unit of
work.
3.2 Definitions
The Contractor shall furnish all labor, material, equipment, and services to
complete the works of all mechanical systems.
As mentioned elsewhere.
3.5 Measurements
Page 12 of 417
Mechanical and Electrical Design Guidelines and Specifications
The Contractor shall maintain at the site, at all times, qualified personnel and
supporting staff, with proven experience in erecting, supervising, testing, and
adjusting projects of comparable nature and complexity.
The supervising personnel and their qualifications are subject to the approval of
the Engineer.
The Contractor shall supply and erect any special structure required for
installation of equipment supplied under this section. Structures shall be
adequate to support the weight of equipment involved without sagging or
bowing.
The Contractor shall supply anchors and bolts, templates and/or accurate
dimensions, as well as equipment to be built in or measurements to allow for
same, as and when required. Sleeves shall be set, and services installed
promptly in advance of concrete pouring or similar work.
The Contractor shall ensure the products and installation meet the
requirements and specification of latest recognized published standards, as
noted herein. Unless otherwise specified, the Contractor shall comply fully with
requirements of the approved international standards.
3.10 Drawings
Each mechanical shop drawing submitted shall carry the following information
as applicable:
(a) Manufacturer’s name and model number.
(b) Supplier’s name.
(c) Shipping and working weight.
(d) Performance characteristics.
(e) Dimensions.
(f) Materials used in manufacture.
(g) Subcontractor’s approval stamp.
(h) Contractor’s approval stamp.
(i) Project number.
(j) Specification section and clause number and title.
Page 13 of 417
Mechanical and Electrical Design Guidelines and Specifications
Should the above requirements not be complied with, shop drawings will be
rejected without further consideration.
The Contractor shall bind one complete set of corrected shop drawings in each
operating and maintenance instruction manual.
The Contractor shall submit product factory test reports when requested for
review, or a minimum of four weeks prior to installation of the product.
The Contractor shall inform the Engineer at least 15 days prior to a product
factory test being performed. The Engineer shall be given the opportunity to
witness the tests at his discretion.
3.12 Certificates
The Contractor shall apply for, obtain, and pay for all permits, licenses,
inspections, examinations, and fees required.
The Contractor shall arrange for inspection of all work by the authorities having
jurisdiction over the work. On completion of the work, the Contractor shall
present to the Engineer the final unconditional certificate of approval of the
authorities.
Before starting any work, the Contractor shall submit the required number of
copies of drawings and specifications to the authorities for their approval and
comments. The Contractor shall comply with any changes requested as part of
the Contract, but notify the Engineer immediately of such changes, for proper
processing of these requirements. The Contractor shall prepare and furnish any
additional drawings, details, or information as may be required.
These letters shall state the names of persons present at the time of testing,
the methods used, a list of functions performed and the location and room
number where applicable.
Page 14 of 417
Mechanical and Electrical Design Guidelines and Specifications
The drawings shall indicate exact locations of services left for future work, if
any, and show dimensions to any work embedded in the structure. They shall
also indicate the exact locations of access panels and junction points.
The Contractor shall submit for approval, installation, interference, and setting
drawings, dimensioned and in the correct scale as may be required or
requested to make clear the work intended or to show its relation to adjacent
work or the work of other trades. The Contractor shall not proceed with work in
new areas until approval of such drawings has been obtained.
The Contractor shall obtain, in writing from the Engineer, a list of the
Department’s representatives qualified to receive instructions and then instruct
the Department’s representatives in the operation and maintenance of all the
systems and equipment.
The Contractor shall arrange and pay for services of service consultants and
other manufacturers’ representatives required for instruction on specialized
portions of the installation.
The Contractor shall submit to the Engineer, at the time of final inspection, a
complete list of systems stating the following for each system:
The Department has the privilege of trial usage of mechanical systems or parts
thereof, as soon as the Contractor agrees that said work is completed, for the
purpose of testing and learning operational procedures.
The Contractor shall carry out the trial usage over a length of time deemed
Page 15 of 417
Mechanical and Electrical Design Guidelines and Specifications
One copy of the manual shall be submitted to the Engineer for review, and
three final copies shall be submitted to the Department during the instruction
period. The Contractor shall allow four weeks prior to the instruction period to
review and process the final copies of the manuals.
3.19 Workmanship
The Contractor shall obtain general arrangement details from the Drawings and
dimensions of finished work from dimensioned Drawings showing the actual
location of services and equipment in areas where space is critical.
Page 16 of 417
Mechanical and Electrical Design Guidelines and Specifications
The Engineer may reject proposed equipment when, in his opinion, service of
the equipment and availability of necessary spare parts would not be
satisfactory.
All major mechanical system products shall have the size, rating, or class, and
manufacturer’s name clearly marked on a securely fastened nameplate.
The Contractor shall conduct performance and operating tests for each system
or equipment unit, in the presence of the Engineer and a representative of any
agencies having jurisdiction.
Works to be concealed shall remain uncovered until the required tests and
inspections have been completed, but if the construction schedule requires it,
the Contractor shall arrange for tests on parts of the system.
The Contractor shall give written notice in ample time to all concerned of the
date when tests will be conducted, and inspection is required.
The Contractor shall ensure that suitable access is provided when required at
any stage of construction, into and within the building, for the unloading and
maneuvering of equipment to the final location. The Contractor shall ensure
that, on completion of the installation work, suitable access is provided to all
equipment and devices with freedom from interferences caused by other
equipment provided or installed.
The Contractor shall be careful not to spill, drop, or store oil on the floor surface
at any time. Operations requiring the use of oil, such as pipe cutting and
threading or machining, are to be performed so that floors are protected by the
use of oil-drip panels under machines, plywood sheets placed on floors, and/or
plywood partitions erected around machines to avoid splashing on floors and
walls.
(a) General.
The Contractor shall maintain in full working order and service all electrical
Page 17 of 417
Mechanical and Electrical Design Guidelines and Specifications
and mechanical equipment supplied and installed under the Contract for the
time period as stated in the Contract, beginning from the preliminary
handing over date until final handing over of the project.
The items to be maintained and serviced shall include, but not limited to, all
equipment associated with the standby power systems, electrical and
lighting systems, elevator system, air-conditioning and ventilation system,
fire fighting and fire protection system, water services, drainage services,
irrigation system, and fountains with all necessary components furnished
and installed under this Contract.
4 PIPEWORK INSTALLATIONS
Steel pipes shall be supplied with either screwed or plain ends for welding as
required, if galvanized it should be hot dipped, be complete with plastic end
caps and shall be marked with identification colour bands indicating the grade
of pipe.
Page 18 of 417
Mechanical and Electrical Design Guidelines and Specifications
The Engineer shall reject any pipe lengths that in his opinion are rusty.
All copper tube shall be suitably treated for the removal of carbon deposit left
by the drawing lubricant.
All tubes and fittings shall bear an appropriate mark to indicate that it has been
manufactured in accordance with the provisions of the specified BS.
Above ground uPVC soil pipe and fittings shall be manufactured to BS 4514 :
2001.
Butt welding fittings shall have a wall thickness the same as the pipe.
Capillary fittings for use with copper pipe shall be manufactured to BS 864: Part
2: 1983 and the joints shall be made in accordance with the manufacturers
instructions with regard to cleaning, tinning, flux and application of heat.
Page 19 of 417
Mechanical and Electrical Design Guidelines and Specifications
All necessary copper to iron adaptors for connections to valves and other
equipment shall be provided.
Chromium Plating
Where chromium plated pipe is specified all valves, fittings, clips etc. shall also
be chromium plated.
All chromium plated equipment shall be properly stored and protected, and
damage to such equipment no matter how slight will result in such equipment
being rejected by the Engineer.
Pipe jointing shall be carried out by suitably skilled and experienced personnel
in accordance with the best practices and the manufacturers recommendations.
The Contractor shall verify that all pipe joints specified in subsequent sections
and jointing methods and systems adopted are suitable for the operating
pressures, surge pressures and test pressures applying to each system.
The Contractor shall allow for all supports, anchor guides etc., over and above
those specified or detailed that may be additionally necessary to suit a
particular jointing methods or system.
Screwed joints for steel pipes shall be made in accordance with BS 21: 1985.
Screwed joints for copper pipes shall, unless otherwise specified, be made in
BS 21: 1985.
The joints shall be lean threaded, pulled up tightly and made with P.T.F.E.
(polytetrafluoroethylene) tape applied with care in the manner specified by the
Page 20 of 417
Mechanical and Electrical Design Guidelines and Specifications
manufacturer.
When for the purpose of threading, pipes are held in a vice, care shall be taken
to ensure that the pipe surface is not damaged. Any pipework so damaged
shall not be incorporated in the works.
For galvanized tube care shall be taken to ensure that threads are carefully cut
so that the number of exposed threads is minimized. Exposed threads shall
receive a coat of protective red oxide paint after each joint has been made.
If the bead of a fitting is damaged during the installation the fitting shall be
replaced.
Pipework for welding shall be supplied with plain ends and the bores at the end
of adjacent pipes are to be matched on site and beveled to an 80 degree
included angle or bevel, except for pipe sizes 12 to 50 mm which shall be
square ends for butt welding.
All welded joints are to be stamped in a suitable position adjacent to the weld,
to enable the identity of the welder to be established. The identification coding
shall be made available to the Engineer prior to the commencement of
installation. The Engineer shall have the authority to request that 2% of all
welds be cut out for routine examination and testing, such test will be applied to
any welded joint at the discretion of the Engineer. Where specific defects are
suspected the 2% limit will not apply.
The Engineer or his representative shall be present when welds are to be cut
out and to witness such tests that may be considered necessary to ensure that
the full bore of the pipe is maintained at each welded joint.
Bending tests, micro-etching tests and any other methods of testing may also
be requested if considered necessary by the Engineer and will be carried out in
accordance with BS EN (1320:97&910:96). The entire cost of cutting out,
Page 21 of 417
Mechanical and Electrical Design Guidelines and Specifications
If any such weld is found to be inferior and not up to the standard required, two
further welds by the same welder shall be similarly tested and if these also are
found to be unsatisfactory then the welder shall be taken off the pipeline and all
welds made by him shall be cut and remade: the entire cost of the cutting out,
reinstatement, testing and painting shall be at the Contractor’s own expense.
All flanges for use with steel pipes shall be manufactured from mild steel in
accordance with BS EN 1514:97 and to the Table appropriate for the system
pressure, but never less than Table E.
Flanges for use with copper pipes shall be manufactured from bronze or
gunmetal to BS EN 1092:02 and to the Table appropriate for the pressure
specified.
Flanges for welding shall be plain faced slip on back type flanges.
All flanges joints shall be flush and truly aligned and shall employ full faced
corrugated metal rings coated on both sides with an approved jointing
compound.
Flanges other than mating flanges for certain specialized equipment shall be
drilled to the appropriate Table for the service concerned and secured with the
necessary bolts, nuts and washers.
All bolts and nuts shall be hexagonal headed bright steel in accordance with BS
4882 : 1990, no more than two threads shall project beyond the nut.
For the purpose of cold-draw for expansion compensators, high tensile steel
bolts shall be used.
Sleeves shall be provided where pipes pass through walls, floors, beams,
fittings and waterproof membranes.
Split sleeves shall not be used, the sleeves shall be of the same material as the
pipe passing through or rigid PVC which may be used when the operating
temperature of the pipe is below 100ºC. The internal diameter of the sleeve
shall not be less than 13 mm and not more than 25 mm larger than the external
diameter of the pipe. Where pipe sleeves pass through walls or floors which
form a fire barrier, the sleeve shall be of the same material as the pipe and the
space between the sleeve and the pipe passing through the sleeve shall be fire
stopped with an approved fire-resistant packing.
Sleeves through bearing walls and footings shall be packed with flexible foam
and the ends sealed with bitumen.
Page 22 of 417
Mechanical and Electrical Design Guidelines and Specifications
All sleeves shall protrude not less than 2 mm and not more than 3 mm proud of
the finished floor or wall surface.
The shield shall be sealed to the pipe with waterproof material and mastic
compound.
Where pipes pass through floors and ceilings they shall, unless otherwise
specified, be provided with chromium plates, rolled steel, hinged floor plates of
the set-screw pattern.
Where possible, pipes shall be spaced to accommodate the entire floor plates,
but where the available spacing is inadequate and necessitates the cutting of
the plates to prevent overlap, and then each plate shall be cut by an equal
amount to give a symmetric appearance.
All pipework shall be erected to present a neat and tidy appearance; arranged
to follow the contour of walls and other structural members of the building. It
shall give maximum headroom and avoid the obstruction of windows and
doorways. Pipework shall be installed with the consideration for the location of
other services with which its arrangement shall be coordinated; allowance
should also be made during its erection for the thickness of insulation thereon.
Service Gradient
Page 23 of 417
Mechanical and Electrical Design Guidelines and Specifications
All bends required for expansion purposes and all swan necks, offsets and
springs are to be formed by the use of a suitable bending machine or by heat
treatment. Heat treatment shall not be employed for galvanized pipe. Bends,
springs and offsets for copper tube may be formed using bending springs.
Pipework shall generally be set around all piers and columns, around steelwork
and other projections beyond the face of walls and partitions, and where walls
reduce in thickness; whether so indicated on the drawings or not and no extras
shall be allowed.
The center line radius of bends, sets, springs etc., shall not be less than three
times the nominal bore of the pipe for pipes up to and including 160 mm
diameter, and three and a half times the bore larger than 160 mm diameter.
Where two or more pipes change direction together, the pipes shall be installed
at a constant spacing before and after the bend.
All pipework valves, fittings etc., shall be free from corrosion and internal
obstruction and the ends of all lengths, and cuts from standard lengths, shall be
trimmed square and reamed to the full bore of the pipe to remove burrs; the
swarf shall be cleared from the pipe.
Joints will not be permitted within the thickness of walls, floors, ceilings or other
equally inaccessible positions. All pipework, valves, fittings and equipment
forming the general installation shall be erected in a manner that will permit
easy dismantling and convenient accessibility for future repairs and
replacements for items of plant. Flanged or union connections shall be provided
at valves and at suitable intervals to facilitate erection of the pipework.
Particular attention is drawn to welded pipework where sufficient flanged joints
shall be provided to limit the length of pipe sections for convenient handling.
Bends and tees shall be of easy sweep or pitcher pattern wherever possible,
appropriate, and convenient. The use of bushes and hexagonal eccentric
reducing nipples are not to be used unless authorized by the Engineer or his
representative. Square tees and round elbows shall be used for thermometer,
thermostat, gauge and drain connections and air vents. Round elbows may be
used where pipework is exposed in rooms and where the use of an easy sweep
bend would throw the center of the pipe beyond an acceptable distance from
the wall. No elbows will be allowed on fire service systems where all changes of
direction shall be by means of standard bend springs or long radius bends.
Flat seated unions shall not be used; unions shall have bronze conical seats
ground in. All pipe systems shall be thoroughly flushed out when the installation
Page 24 of 417
Mechanical and Electrical Design Guidelines and Specifications
All steel pipework in small channels which are to be provided with permanent
floor covering, and pipework where encased or otherwise make inaccessible
within the building structure, shall be performed with welded joints.
All internal pipework and supports, other than galvanized or copper shall be
cleaned and painted one coat of red oxide paint to afford protection during the
course of erection. The paint shall be applied immediately after the pipework
has been installed.
All pipework in channels which are to be sealed shall be covered in dry sand
unless otherwise specified.
Special care is to be observed to prevent dirt and rubbish entering the open
ends of pipes during erection, and the open ends are to be temporarily fitted
with plastic or metal caps, plugs or blank flanges during the progress of the
work.
In the event of failure to comply with this instruction the Engineer shall order
pipework to be dismantled and cleaned internally to the extent which he may
consider necessary; at no cost to the Client.
All pipework not insulated shall be painted one coat of red oxide paint and two
coats of grey gloss paint.
Vertical pipework shall be fixed at each floor level and at least one intermediate
point between floors with either cast in holderbats or floor clamps. Horizontal
Page 25 of 417
Mechanical and Electrical Design Guidelines and Specifications
pipework shall be fixed at not less than 1000 mm centers with Holderbats or
pipe hangers of mild steel drilled and fixed into concrete soffits or otherwise to
an approved detail. All drainage pipework where appropriate shall be supported
on either cantilever or gallows brackets constructed from a minimum of 40 mm
x 40 mm x 6 mm mild steel angle screwed and bolted to the structure with at
least 2 x 12 mm pre-drilled fixings. Connections to traps are to be made with
approved disconnecting unions.
ABS pipes are to be supported with either ABS saddle clips, or two piece ring
clips at the following spacing:
32 – 38 mm 0.5 m 1.2 m
40 – 50 mm 0.5 m 1.2 m
NOTE: These figures are the maximum spacing and it is the Contractor’s
responsibility to ensure that pipes are properly and securely fixed.
ABS tubes passing through floors or walls are to be sleeved with a pipe
generally of the next layout size. Joints between ABS and uPVC are to be
made with an appropriate approved connector.
Main soil and waste pipes are to be fixed to give a constant gradient.
Soil and waste pipes shall be swept in the direction of flow to enter the main
horizontal or vertical soil or waste pipe at a minimum angle of 92.1/2% and a
maximum of 135º.
All pipes where used with bends or machine pulled bends shall be free from
throating, flattening or rippling and the bore and thickness shall be maintained
throughout.
Pipes passing through flat roofs are to have vent pipe roof connections with
raising pieces to give a maximum height above roof level of 450 mm.
All vents shall be fitted with either uPVC or copper wire balloons.
Vent pipes shall be carried out in full bore and terminate 450 mm above roof
levels, or not less than 900 mm above the head of any window opening,
ventilated roof light or HVAC air inlet with 5, 000 m horizontal distance.
Access shall be provided at the foot of each stack and at various points
throughout the system to enable adequate maintenance to be carried out.
The Contractor shall ensure that all necessary access points are provided and
that builders work access doors are correctly located in relation to pipe access
points in order that maintenance may be efficiently and adequately carried out.
Pipe and junction access doors shall be positioned on top of horizontal pipes
Page 26 of 417
Mechanical and Electrical Design Guidelines and Specifications
Cleaning eyes shall be of circular pattern of brass with screwed cap and fibre
washers. All cleaning eyes shall be eased and well greased before being
tightened.
All copper traps and wastes where exposed to view shall be chromium plated.
Use fixtures and chrome fittings of the same range and manufacture in any one
group, to ensure matching of profiles, colour etc. All fixtures supplied shall be
certified FIRST QUALITY products of the manufacturer. These shall be free of
defects like warping, cracks, chipping, discoloration, etc. All fixtures supplied
shall have true roughing in dimensions, as in published catalogues. All copper
alloys used in the manufacture of chrome fittings shall be dezincification
resistant types.
Submit product data, samples and roughing in details in accordance with the
provisions of relevant Section. Submit colour schemes and samples in
coordination with the tiling works.
All necessary brackets, clips, hangers, and other pipe supports including
necessary bolts, nuts, washers, backing plates, screws and plugs which shall
be provided for the fixing and alignment of pipework and shall be approved by
the Engineer.
All chilled water, water service and hose reel pipework shall be supported at the
maximum centers given in the schedule included in Table B15.3 of the CIBSE
Guide.
In the event of two or more pipes being carried by a single support the spacing
shall be selected shall be selected for the shorter interval. Under no
circumstances shall one pipe be supported from another pipe. All supports for
steel pipes shall be of ferrous material and shall be galvanized where used with
galvanized pipe.
Page 27 of 417
Mechanical and Electrical Design Guidelines and Specifications
Spacing of pipe supports on fire service pipework shall conform with the LPC
regulations.
All supports for copper pipes shall be of polished brass where exposed to view;
elsewhere, they shall be of either cast brass or galvanized with rubber insert.
Within room all wall brackets supporting pipework shall be of school board
pattern.
All supports shall be adequate, firmly and duly fixed and shall not promote
vibration.
Where pipework is connected to vibrating plant the pipe supports shall where
necessary be of the spring or vibration isolated type for a given distance away
from the connection commensurate with the natural dampening effect of the
pipe. The deflection of the anti-vibration support shall be adequately allowed for
such that no undue load is imposed on other supports or connections.
All supports shall be selected and fabricated to allow for thermal movement of
their associated pipe and where applicable vapour sealed insulation system.
All brackets shall be painted with a primer coat and tow coats of red oxide on
steel and galvanized iron.
4.23 Expansion
Page 28 of 417
Mechanical and Electrical Design Guidelines and Specifications
The selection of compensators, loops, offsets and the like shall take due
account of the system pressures and their arrangements relative to anchor
points shall take account of the thrust forces exerted by pipe expansion and
contraction and the effects of such forces on the anchor points and the
structure to which it is fixed.
To prevent undue stressing of flanges due to cold draw, long flange bolts shall
be used initially and shall be pulled up in pairs diametrically opposed until the
joint is finally made when the bolts may be replaced one at a time by one of the
correct length.
4.25 Headers
The stools shall be of sufficient length to clear the thickness of any insulation
thereon and permit the insertion of flange bolts. All spare outlets which may be
specified shall be provided with valves appropriate to the service concerned
and such spare valves shall be blanked off with plugs or blank flanges as may
be appropriate.
Services laid in the ground shall be installed with care and in such a manner
that pipework and fittings shall not be damaged due to ground movement.
Consideration shall be given, particularly for non-metallic pipes, to the depth at
which the pipe shall be laid, depending upon the size of the pipe, the location,
width of trench and the class of bedding upon which the pipe will lie.
Page 29 of 417
Mechanical and Electrical Design Guidelines and Specifications
Steel pipes shall receive a coat of primer and two coats of red oxide protective
paint, and all metal pipes shall be wrapped with Denso tape prior to back-filling.
Buried cold water pipes shall be not less than 900 mm below finished ground
surface level.
Where pipes pass under roadways carrying vehicles, they shall be located
within sleeves or conduit. After the pressure test, concrete anchor and thrust
blocks are to be poured and the size and position of all block shall be adequate
and suitable to prevent pipe movement.
All detachable and flanged joints shall be protected with thick bitumen, special
care being taken to apply a liberal coating to screwed ends and exposed
portions of bolts.
All drains shall be installed in accordance with BS EN 752 parts 1-4 at even
gradients, in straight lines within preformed trenches trimmed to the depths and
falls as indicated on the drawings.
Pipe trenches for plastic drain pipes shall be as narrow as possible at pipe
crown level, but never less than the outside diameter of the pipe plus 300 mm.
In wide trenches, a narrow sub trench shall be formed to achieve this condition.
Where the crown of the pipe is less than 150 mm from the underside of the
concrete slabs, the pipe shall be surrounded in concrete.
Where drains are run under roadways or under areas where vehicles can be
expected to pass over them, they shall be laid such that their crown is at least
900 mm below ground level. Where the depth of cover indicated is less than
900 mm, drains shall be encased in concrete with a minimum thickness in any
direction of 150 mm. Where flexible jointing is used on drainage systems the
concrete encasement shall be sectionalized to match the drain jointing with a
20 mm minimum thickness of a compressible material used as a permanent
shutter between sections to permit movement at joints.
In all cases the pipes shall be laid direct on the bedding and the use of bricks,
blocks, battens or the like to bring the pipeline to gradient will not be permitted.
Side filling for flexible pipes shall be of the same material as used for the
bedding and shall be placed and compacted in layers of 100 mm to a minimum
height of 100 mm above the crown of the pipe.
Page 30 of 417
Mechanical and Electrical Design Guidelines and Specifications
Side filling for rigid pipes except as otherwise stated shall be of selected
excavated material with stones of over 25 mm size removed. The side fill shall
be placed and compacted in layers of 150 mm to a minimum depth of 300 mm
above crown.
Concrete surrounds and back filling shall not be carried out until the drain has
been inspected, tested and approved by the Engineer. Any defects after testing
shall be made good and retested at the Contractors expense.
The Contractor shall ensure that prior to backfilling all timber, metallic or
concrete temporary supports are removed.
The Contractor shall inform the Engineer when initial side filling of jointed pipes
is complete to allow him opportunity to inspect, carry out random checks and to
observe tests.
All jointing shall be carried out at its final position in dry conditions; any ground
water in the trench shall have been pumped away. No joint shall be made
under water.
When drain pipes enter manholes below the ground water level the pipe shall
be complete with integral puddle flange.
Drains shall be inspected and tested in accordance with BS EN 752 parts 1-4
and any additional testing which may be required by the Local Authority.
Manholes and inspection chambers shall be to BS EN 752 parts 1-4 of the size
and type indicated elsewhere. Blockwork manholes shall be constructed of 200
mm thick solid loadbearing concrete blocks of sulphate resisting quality and
jointed in cement mortar (1:4) on a bed of sulphate resisting cement.
Page 31 of 417
Mechanical and Electrical Design Guidelines and Specifications
even surface true to radius, line and level and shall be kept well watered for
ten days after laying.
Branch inverts shall be at the center line of the main channel. In the case of
manholes where level inverts are required as shown on the drawings, channels
and channel bends and junctions shall be as shown on the drawings.
Galvanized malleable steel step irons for use in manholes shall comply with BS
1247:1990. Manhole covers and frames shall comply with BS 497:1994 Part 1.
Particular attention shall be paid to the requirements of the Local Fire Authority
and the LPC regulations with respect to the provision of drain taps on fire
service pipework systems.
All cylinders, coils and pumps together with all low points of pipework within
plantrooms shall be provided with drain cocks.
Drain taps shall also be provided on the flow and return of all sub-circuits
provided with isolating facilities and shall be located on the isolated side of the
valves.
The Contractor shall be responsible for the design and positioning of all drain
points.
The valve shall have an ABS inner body and UPVC outer body. The internal
rubber seal diaphragm shall be in accordance with BS 2494:1990 and a
corrosion resistant spring to BS EN 10270-1:2001.
Page 32 of 417
Mechanical and Electrical Design Guidelines and Specifications
Air vents shall be provided at all high points in the pipework, whether indicated
on the drawings or not. Large diameter automatic air vents shall be provided at
all primary venting position, such as plantrooms and at the head of vertical
risers.
Air bottles shall be provided at all venting points. Heating and cooling coils on
air handling units, fan coils and ductwork systems, in addition to all high points
of pipework which require venting, shall be provided with 6 mm diameter air
cocks unless some other form of venting is specified or has been indicated on
the drawings.
For coils and similar cased appliances, the air cock shall be located for
convenient operation external to the outer casing.
Air bottles shall be formed from pipe of equal bore to the pipe being vented and
of length equal to the bore plus 150 mm. Each air bottle shall be provided with
a 6 mm vent pipe welded into the top and terminating in a conveniently
accessible position, approximately 1,600 mm above floor level, with a 6 mm
lockshield needle valve.
The needle valve shall be provided with a 6 mm tailpiece with mitred end.
Each automatic air vent shall be preceded by a lockshield pattern stop valve,
and the discharge from the air vent shall be 12 mm copper pipe terminating
with an open discharge in a position to be agreed over a conveniently located
drain, gulley or sump.
The Contractor shall be responsible for the design and positioning of all air
vents.
Equilibrium Type (For Panel type GRP Water Tanks): Bronze construction,
angle pattern, equilibrium type float valve with flanged inlet; complete with
brass/stainless steel float rod and copper float.
For fire water supply break tank provide a float valve, which maintains a
constant level in the tank by admitting flow into the tank in direct proportion to
the flow out of the tank.
The main valve installed in the supply line and a float operated pilot control
installed at the high liquid level in the tank. Provide connection between the float
control and the valve with suitable tubing as per manufacturer’s
recommendation. The main valve shall be single seated hydraulically operated
diaphragm type valve. The pilot control is a direct acting float valve, which
closes when the float rises.
Page 33 of 417
Mechanical and Electrical Design Guidelines and Specifications
Valves and cocks shall be provided where indicated on the drawings and of the
sizes given. They shall be in accordance with the types specified.
All valves and cocks shall be located in an accessible position for operational
and maintenance purposes.
Valves and cocks for use on hot and cold water services shall comply with the
regulations and requirements of the Local Water Authority, no extras shall be
allowed for any charges for testing and stamping of valves and cocks which
may be required.
All flanged valves and cocks shall be provided with the necessary counter
flanges drilled to suit, complete with corrugated jointing rings and bolts.
Generally all principal circuits and sub-circuits of each system (other than open
circuit system) together with elements such as heating and cooling coils shall
have gate valve on the flow and a double regulating valve on the return, located
such that complete isolation is obtainable. In certain instances, as shown on
drawings flow regulation is required.
The valves used for this purpose shall be as indicated on the drawings and shall
include for visual indication of shut off or lockshield type with dust cover. All
other valves shall be of the hand wheel pattern.
The types of isolating pressure systems such as cold water service the isolating
valves shall be stopcocks. DN 65 mm and over isolating devices on open circuit
systems shall be sluice valves.
Automatic Air Valves shall have a bronze body with bolted cover and a 9 mm
top outlet. They shall each incorporate a suitable float mounted on a stainless-
steel spindle terminating in a needle valve for closure against a stainless steel
seating at the outlet.
For low pressure systems the valve shall be provided with a test cock and a
brazed float, but for medium and high pressure systems the float shall be of
stainless steel.
Page 34 of 417
Mechanical and Electrical Design Guidelines and Specifications
Automatic air valves for low pressure systems shall incorporate an internal ball
check valve at the inlet to prevent air entry to the system.
Automatic air valves for the cold water services shall be to the approval of the
Local Water Authority complete with lock bronze shield valve and screwed in
accordance with BS21.
Globe valves shall be in accordance with either BS 5154: 1991 (Bronze valves)
or BS 5150 : 1990 (Cast Iron valves).
Globe valves shall have spherical metal disk, outside screw rising stem,
screwed-in bonnet, ventilated hand wheel and repackable non-asbestos gland
packing.
The valve opening position shall be locked with an Alan key and rendered
tamper proof by means of a wire seal.
The valve body shall be fitted with two double seal pressure test cocks to
enable the pressure drop across the valve to be measured.
(a) Brass to BS 2872 CZ132 will be for use in an aggressive environment and
not subject to dezincification
(b) Bronze to BS 1400 LG2
(c) Cast Iron to BS 1452 grade 220
(d) Stainless steel to BS 970316 S11/S13
Ball valves for feed and expansion tanks and storage tanks up to 230 litres
actual shall be of the “Portsmouth” type with nylon seats conforming with BS
1212 Part 1: 1990 or Part 2: 1990 Diaphragm type (brass body)”, floats shall be
copper, with brazed seams to BS 2456 : 1990.
For storage tanks exceeding 230 litres actual capacity ballvalves shall be of the
equilibrium type with bronze body and screwed connections up to and including
Page 35 of 417
Mechanical and Electrical Design Guidelines and Specifications
50mm bore.
Equilibrium type ballvalves shall have gunmetal faced valve and seating, with
the valve mounted on a forged bronze spindle and sliding freely in a gunmetal
lined cylinder guide, floats shall be copper, with brazed seams to BS 2456 :
1990.
4.37 Bib-taps
They shall be provided with hose union nosepiece and hand wheel operated.
Check valves shall be in accordance with either BS 5154: 1991 (Bronze valves)
or BS 13789: 2002 (Cast Iron Valves).
Check valves shall be complete with a corrosion resistant return spring, making
them suitable for horizontal or vertical installation.
Plug valves shall be glandless of the lubricated parallel type with limit stops and
with rectangular ports. Each valve shall be provided with an indicating plate and
quadrant. Plug valves 150mm diameter and over shall be operated by means of
a Capstan wheel worm gearing and mitre gearing to suit the position of the
valve. All other plug valves shall be provided with a malleable iron standard
wrench set screwed to the plug stem. Plug valves shall be screwed or flanged
whichever is specified for the pipe size concerned. Cast Iron to BS 1452 grade
220 and shall comply with BS 5417.
Double regulating valves shall be Y-pattern, double regulating globe valve type,
with characterized throttling disk.
The valve opening position shall be locked with an Alan key and rendered
tamperproof by means of a wire seal.
(a) Brass to BS 2872 CZ132 will be for use in an aggressive environment and
not subject to dezincification.
(b) Bronze to BS 1400 LG2
(c) Cast Iron t BS 1452 grade 220
(d) Stainless steel to BS 970316 S11/S13
Page 36 of 417
Mechanical and Electrical Design Guidelines and Specifications
The valve body shall be fitted with two double seal pressure test cocks to
enable the pressure drop across the valve to be measured.
Pressure differential regulator shall be of the spring loaded diaphragm type with
piston plug and double-seated valve. Refer elsewhere in the specification for
temperature/pressure rating, material and connection requirements.
These shall be suitable for use on the service to which they are applied.
(a) Brass to BS 2872 CZ132 will be for use in an aggressive environment and
not subject to dezincification.
(b) Bronze to BS 1400 LG2
(c) Cast Iron t BS 1452 grade 220
(d) Stainless steel to BS 970316 S11/S13
Gate valves shall be in accordance with either BS 5154: 1991 (Bronze valves)
or BS EN 1171:02 (Cast Iron valves).
Gate valves shall have solid wedge disks, non-rising stem, screwed-in bonnet,
ventilated hand wheel and repackable non-asbestos gland packing.
Where applicable the valves can be resilient seated with disc fully encapsulated
in EDPM rubber.
Gland cocks shall be of gunmetal with solid taper plug and two bolt oval gland,
and where used for emptying or drain purposes, they shall, unless situated on
permanent drain or emptying pipes, be provided with serrated hose union
tailpieces. These shall comply with the requirements of BS 2879.
Fixed orifice double regulating valves shall comprise matched double regulating
valve and metering station orifice.
The Contractor shall ensure that they are installed with the manufacturer’s
recommended straight length of up and downstream pipe.These shall be in
accordance with the requirements of BS 4504.
Relief valves shall be of the full bore, bronze body, PN20, enclosed spring
Page 37 of 417
Mechanical and Electrical Design Guidelines and Specifications
loaded, with padlocked rotateable easing lever, with a discharge pipe to a point
agreed with the Engineer.
Cast iron sluice valves shall be in accordance with BS 5163: 2004. They shall
have open and shut indications, a bronze non-rising spindle, a solid wedge with
renewable gunmetal rings on valve and seat and lubricated hemp gland
packing.
4.47 Stopcocks
Stopcocks for water services shall be in accordance with BS 1010: 1973 Part
2. They shall have screwed or capillary ends to suit the associated pipework
and unless otherwise specified, shall have crutch handles. Stopcocks for wash-
down or similar services exposed to unauthorized interference shall be provided
with lockshield and loose keys and where stopcocks are located beneath
ground level they shall have square spindle caps for extended keys.
Stopcocks situated at the base of rising mains services to roof shall be of the
combination or brazier type incorporating a drain tap.
Three way gland cocks on common relied pipes shall be heavy pattern,
gunmetal closed bottom type with solid taper plug and T ports and with two bolt
oval glands. They shall be suitable for the service and size concerned. These
shall comply with the requirements of BS 2879.
Pressure reducing valves shall be of the variable input constant output pressure
type and capable of complete closure in a no flow condition to prevent pressure
equalization.
All pressure reducing valves shall have cast iron bodies and gunmetal internal
valves, guides, rings, piston rings and piston rings and junk rings, bronze liners,
leather cups and face rings and stainless steel indicator rods with all other
components of suitable non-corroding materials.
The relay system shall comprise bronze body, diaphragm guide, support and
piston, stainless steel spindle nylon valve face, synthetic reinforced rubber
diaphragm and steel spring.
The relay system shall have isolating cocks, bronze bodied orifice/strainer units
and copper strainers. All pressure reducing valves shall be flanged to the
appropriate Table in accordance with BS 10, and sized as appropriate to their
Page 38 of 417
Mechanical and Electrical Design Guidelines and Specifications
duty.
4.50 Strainers
Above DN 50 strainers shall be manufactured from cast iron and shall be for the
‘Y’ type bolted cap or basket type, PN 16 temperature/pressure rating and shall
be complete with drilled and tapped caps complete with drain cocks.
Strainers shall be provided with a medium grade screen sized such that in their
clean condition the maximum pressure drop at the design flow rate shall not
exceed 6 kPa. For chilled water the mesh shall be stainless steel and for water
services the mesh shall be copper.
(a) Resistive type level transmitter housed in custom fabricated, 100mm (4 in.)
diameter PVC pipe housing with 50mm (2 inch) diameter flanged side
connections at the top and bottom of the tank side. The transmitter
assembly shall be threaded onto a blank flange at the top of the housing,
drilled and tapped to size.
1 Water level indication (dial shall be calibrated in cu. meter and imperial
gallons).
2 High / low water audio-visual alarms at the indicator panel.
3 High water audible alarm at the tanker fill point.
4 Low water cut out of filtration transfer sets.
5 On site adjustment of alarm set points.
6 Indication of power supply availability to the panel.
7 Provision for hook up with the Building Automation System for critical
alarms.
Page 39 of 417
Mechanical and Electrical Design Guidelines and Specifications
(a) Chrome plated brass, atmospheric type with flat pipette type, rubber discs
and hose thread outlet.
(b) Bronze body, pressure type with heat resistant disc opening to atmosphere
at less than 12mm (1/2-inch} mercury vacuum.
(c) Install vacuum relief valves at inlet to all central water heaters (install in line
check valves at inlet of wall mounted water heaters).
1. Bronze body, stainless steel spring and trim, with pipette type manual
actuator lever. The unit shall be preset and sealed at the factory. The
label shall contain the manufacturer's name, serial no., maximum
working pressure and set pressure.
1. Bronze body, stainless steel spring and trim, one ceramic coated
temperature sensing element and pipette type manual actuator lever.
The unit shall be rated for relieving the maximum heat input to the water
heater and preset and sealed at the factory. The label shall contain the
manufacturers name, serial no., maximum working pressure and
temperature, set pressure and temperature and relieving capacity in
BTU/hr.
(c) Provide automatic pressure and temperature relief valves on all central
electric water heaters.
(d) Provide pressure relief valves on unit electric water heaters.
(e) Provide bypass type pressure relief valves between discharge and suction
manifolds of pressure controlled booster sets.
(f) Pipe the discharge of water heater relief valves to safe locations, to prevent
injury to personnel.
Page 40 of 417
Mechanical and Electrical Design Guidelines and Specifications
(a) Bronze body with non-ferrous float and internal working parts. Construction
shall be “take apart” type, for easy maintenance. Outlet shall be tapped for
connection to drain line.
(b) Provide automatic air vents on top of all central electric water heaters, as
detailed.
(c) Provide automatic air vents at system high points, as indicated on drawings.
(a) Air chambers: Fabricated from copper pipes of line size (minimum 25mm (1
inch diameter) and 300mm to 450mm (12 to 18 inches) long.
(b) Provide air chambers at the topmost junction of all cold water, hot water and
hot water return risers, connected to pressurized systems.
(a) Hose bibs: Chrome plated brass, globe type with integral vacuum breaker
with 12mm (1/2 inch) male threaded inlet and 19mm (3/4 inch) hose thread
outlet. The valve operation shall be by loose keys where required. The inlet
shall be of male thread with wall flange.
(b) Hydrants: Hose bibs as above in cast brass housing suitable for recessed
installation. The door of the housing shall be lockable with the same key as
the hose bib.
(c) Wash Down Stations: Bronze body, piston operated valve with stainless
steel trim; complete with stainless steel hose rack and 15 meters long (50
feet) high pressure hose and trigger controlled, two position jet and spray)
nozzle. The assembly shall be suitable for 1034Kpa (150-psig) working
water pressure.
(d) Provide hose bibs with operating handles or with loose operating keys as
appropriate.
All pipework shall be tested hydraulically after assembly on site and before any
insulation is applied or pipework made inaccessible by building cladding, to a
pressure equal to twice the working pressure. If the working pressure is greater
than 600kpa the test pressure may be one and a half times the working
Page 41 of 417
Mechanical and Electrical Design Guidelines and Specifications
pressure.
The minimum test pressure for water pipes shall be 700 kpa.
Hydraulic pressure tests shall be carried out by means of a purpose made test
pump, which shall be locked after the desired pressure is obtained.
The test pressure shall be registered at the lowest part of the system being
tested and maintained for a period of two hours during which time all parts must
remain completely watertight and no pressure loss is indicated on the test
guage. In the case of Fire Mains wet rises and Hosereel supplies, the pressure
test shall be maintained for 24 hours. Any leakage must at once be made good
and the pressure test repeated until the desired test conditions are maintained.
During this period all welds on steel pipe shall be well hammered. Any defects
shall be made good and the relevant section shall be re-tested all at the
Contractor’s expense.
Boilers, Chillers, Pumps and any other ancillary items of equipment which may
be liable to damage by the test pressure, shall be isolated or suitably protected
during the test, and all necessary precautions shall be taken. Any damaged
equipment shall be replaced.
In order not to delay the building operations sections of the pipework may be
pressure tested independently as the work progresses. All necessary plugs,
caps or blank flanges shall be provided for testing and these shall be removed
after the pressure tests have been approved.
A test certificate shall be issued for each section of the pipwork satisfactorily.
An air test shall be applied at a pressure equal to 380 pa and shall system
pressure shall remain constant for a period of not less than three minutes. The
water seals of all sanitary appliances which are installed shall be fully charged
and a test plug shall be inserted into the open ends of the pipework to be
tested, each plug being sealed with a small quantity of water.
In addition to a test for air or water tightness, every discharge pipe installation
shall be tested for stability of the trap seals on the system. When subjected to
the appropriate discharge tests every trap must retain not less than 25 mm
water seal. Each test shall be repeated three times, traps being recharged
before each test and the maximum loss of seal in any one test should be taken
as the significant result.
Page 42 of 417
Mechanical and Electrical Design Guidelines and Specifications
Testing and inspection shall be in accordance with the procedures set down in
BS EN 752. All items of the drainage system shall be inspected and tested
including gravity drains, ancillary works, drainage pumping mains and
apparatus.
First stage testing, immediately before the work is covered up although in the
case of pressure mains after anchors have been formed and pipework
adequately weighted between joints.
Hydraulic tests on gravity systems shall comprise a minimum head of 1.5 kPa
at the high end and a maximum of 4.0 kPa at the low end sustained for a
period of 30 minutes whereby the loss of water shall not exceed the
acceptance criteria stated in BS EN 752 parts 1-4.
All work shall be tested as specified and to the satisfaction of the Engineer
before refilling of excavation is commenced.
The Contractor shall provide clean water and all assistance and appliances for
testing during the progress of the work and for the independent final tests.
The Contractor shall locate and remedy all defects before further pipe laying
proceeds, and shall repeat the test until a satisfactory result is obtained. Where
a length of pipe under test terminates at a manhole, the restriction on further
Page 43 of 417
Mechanical and Electrical Design Guidelines and Specifications
The Contractor shall provide and fix testing branches and bends as required
and shall seal off or remove them as described by the Engineer.
At completion of the work all rubbish and superfluous materials shall be cleared
away and the whole of the apparatus shall be left clean and in working order.
All pipe, fittings, valves and other items of equipment are to be clean and any
grease, dirt, metal cuttings, sludge etc., which may have accumulated during
the work shall be removed. Any discolouration or other damage to parts of the
building, its finishes or furnishings shall be made good without additional cost to
the Employer. All pipework, fittings, valves, plant etc., or insulation applied shall
be painted, other than where specifically stated to the contrary.
4.66 Water Treatment and Sterilization of Hot and Cold Water Systems
Hot and cold water service pipework systems shall be disinfected in accordance
with BS 6700 : 1997, clause 13.9.
After disaffection the Contractor shall obtain samples and submit them to be
analyzed and cultured. The Contractor shall submit duplicate copies of
certificates of acceptance as hot and cold water.
The systems, shall be repeatedly flushed with clean water before final analysis
to remove all traces of free chlorine. The acceptance certificate must state
residual chlorine content.
All valves controlling mains and sub-circuits for all services shall be labeled
before the works are commissioned in accordance with a schedule of valves
which shall correspond with valves indicated upon the final as-installed
drawings and any circuit control diagrams considered necessary.
The labels shall be stamped or engraved with letters and numbers not smaller
than 10mm high. Each label shall indicate the type of service and the valve
reference number which shall agree with a schedule of valves which shall be
prepared for each service. The schedule shall comprise the valve reference
number, the function of the valve and its location. In addition to the schedule a
Page 44 of 417
Mechanical and Electrical Design Guidelines and Specifications
schematic diagram of each service shall be prepare indicating the position and
reference number of each valve. The schematic diagram shall clearly indicate
the location of each valve in the building.
The schedules and schematic diagrams shall be framed and glazed and hung in
the relevant plant room; an alternative method may be submitted to the
Engineer for approval. Duplicate copies of the schedules and schematic
diagrams shall be submitted to the Engineer for approval.
Motors, starters and switchgear shall have labels of “Traffolyte” with white
lettering on black background. The labels are to be screwed to the front of
starters and isolators and shall indicate the service.
Similar labels shall be affixed below each instrument on the instrument panel
and shall indicate the purpose of the instrument and the respective boiler, tank
or other appliance to which its recordings are applicable. Each fan, pump or any
item of plant shall bear a metal label giving the maker’s name, date of
manufacture and serial number, test and working pressures, duty, horsepower,
phasing, number of cycles per second, speeds, BS number for the standard to
which the item of plant conforms, and all relevant performance data as
appropriate to the item of plant to enable easy identification at a later date.
An engraved label shall be fixed to each filter stating the maximum permissible
pressure drop. In addition to the maker’s label each item of plant shall be fitted
with a further label identifying the equipment in relation to the Schedules of
Plant in the Operating and Maintenance Instructions.
All exposed driving belts, shafts, pulleys and other moving parts shall be
provided with suitable guards constructed from stout woven wire mesh of
suitable gauge, adequately braced and firmly fixed in a manner to allow for
ease of removal and freedom from vibration. Guards shall be provided with
75 mm diameter openings with removable covers opposite rotating shaft
centers for the purpose of tachometer readings. Guards and supports shall be
galvanized or suitably protected.
5 PLUMBING
Page 45 of 417
Mechanical and Electrical Design Guidelines and Specifications
(a) The procurement and installation of the water supply line from DEWA valve
chamber to the water storage tank.
(b) Cold water supply system including storage tanks and accessories,
domestic water booster pumps and controls, and distribution services to
sanitary fittings and other utilities.
(c. Hot water supply system including hot water heaters and distribution
services to sanitary fittings and other utilities.
(d) Soil and waste systems inside toilet rooms which discharge from sanitary
fittings and other utilities and floor drains, etc., into the under slab sanitary
discharge system.
(e) Stormwater system inside the bridge levels that discharges from floor
drains, through pipe fittings.
(f) Vacuum breakers, trap primers, hydrants etc. shall be tested and certified
for conformity with the requirements of relevant standards.
(g) Water hammer arrestors shall be tested and certified for conformity with
relevant standards.
(h) Pressure relief valves and pressure and temperature relief valves shall be
tested and certified for conformity with the requirements of relevant
standards.
(i) The construction of the specialties shall be of corrosion resistant materials
like cast iron, stainless steel or dezincification resistant copper alloys
(bronze, brass).
(j) All castings used in the construction of the drainage specialties shall be of
good quality, without blow holes or inclusions and shall be finished smooth,
by sand or shot blasting. All these castings shall be given appropriate
coatings, internally and externally, at the factory.
(k) Flashing clamps, where used, shall be non-puncturing type and shall be
fixed by corrosion resistant fasteners. Drainage flanges shall have seepage
holes to conduct away the water collected.
(l) As far as practicable, items of similar nature shall be products of the same
manufacturer.
(m) Use heavy duty gratings / covers in areas subjected to vehicular traffic.
(n) Testing of the above systems, equipment with controls and other devices, to
demonstrate that the entire installation is in perfect working order.
(o) Preparation of all design and shop drawings, material submittals, reports,
and O & M manuals as necessary.
(p) Submit product data, samples and installation details under provisions of
relevant Section.
(q) Submit selection criteria and ordering schedule, listing types against use
and location.
All equipment and materials shall be new, bearing stamped ratings as required,
and must be approved by the Engineer prior to installation.
Page 46 of 417
Mechanical and Electrical Design Guidelines and Specifications
carried out by others, under Section VII, Water Works, of the Standard
Specifications. The Contractor shall include for all necessary coordination with
the responsible parties.
(b) System piping shall be Stainless Steel 316 with welded joints. Manifold
ends shall be flanged.
(c) Valves: All Cast Iron Butterfly valves with SS 316 disc at suction and
discharge of each pump and stainless 316 wafer type self-closing (non-
slam) check valve at discharge of each pump.
(d) Base frame: Fabricated stainless steel 304, with resilient mounting for
pumps, where required.
(e) Relief valve: Provide suitable bypass pressure relief valve from discharge to
suction manifolds, to prevent pump operation at shutoff head.
(f) Accessories: Compound gauge at suction manifold and pressure gauge at
discharge manifold, flexible connections at suction and discharge
connections.
(g) Pump motor and control panel: See relevant Section for details.
(i) Finishing: The assembly shall be given two coats of primer and one coat of
gloss enamel at the factory.
The pumps shall be supplied complete with all necessary pipework, valves,
control panel, controls, wiring, etc., so as to require only inlet and outlet piping
connections and electrical supply. Storage tank for the booster pumpset
package to be of polyethylene construction, complete with accessories.
Pipe work supplied with the unit shall be copper complying with BS 2871, Table
X.
All other components and materials shall comply with the relevant section of
this specification.
Page 47 of 417
Mechanical and Electrical Design Guidelines and Specifications
A low-level cut out shall be provided in the reservoir, set to cut out the pumps
when the water level drops to 150 mm above the pump-suction line.
The membrane pressure vessel shall be sized as shown on the Drawings. The
vessel shall incorporate a manhole, a drain valve, a relief valve, a sight gauge,
and all necessary air and water connections. Capacity to be suitable for limiting
number of pump starts to 15 per hour.
The control panel shall be manufactured to comply with IP45 standard and shall
include for each pump: power-on lights, run and trip lights, HAO selector
switches, duty selector switches, an isolator, and line and control circuit fuses.
The panel shall incorporate audio and visual alarms for high and low water
levels and overflow of the domestic water reservoirs, together with an alarm
silencing button. A common repeater alarm shall be installed in the control
room.
All pumps shall be “on line” and the lead/lag sequence of the pumps shall
change for each operation.
5.4 Potable Water Roof Storage Tanks
The tank assembly shall be complete with structural steel base, ladders, level
indicator, vents (two no. per compartment), hinged and lockable access
manhole, overflow and drain fittings etc. Suitable GRP shed shall be provided
for the Potable water tanks. The joints shall be sealed with non-toxic, age proof
gasketting and the tank assembly shall be capable of withstanding a deflection
Page 48 of 417
Mechanical and Electrical Design Guidelines and Specifications
Suction Strainers
Suction strainers shall be installed on all supply connections from water storage
tanks, with bend down elbows in low-level connections. Bronze/fabricated
copper suction strainers shall be used for copper piping. Cast iron suction
strainers shall be used for steel piping.
The Contractor shall coordinate with the building works and ensure the
sufficiency of dimensions of the reinforced concrete structural base, to suit the
requirements of the tank manufacturer. Necessary information in respect of the
allowable deflections of the tank base shall be furnished, to check the integrity
of the reinforced concrete base, to suit the tank.
The inside of the tank shall be thoroughly cleaned of all dirt, washed down with
water and drained. The tank(s) shall be disinfected along with the disinfections
and flushing of the water supply piping. Water samples shall be analysed and
results submitted to the Engineer, prior to Handing Over.
Floor drain FD-1 shall have a cast-iron body with an integral trap and flashing
collar and 150-mm by 150-mm square nickel-bronze top strainer grate, equal to
J. R. Smith.
The parking garage floor drain shall have an epoxy Duco coated cast iron body
and flashing collar with a 300-mm by 300-mm square heavy-duty tractor
ductile-iron grate and sediment bucket with lift bar equal to J. R. Smith.
A scupper drains with a cast-iron body, flashing clamp, and loose-set grate
shall be provided. The outlet shall be at an angle of 45° and the grate shall be
the angle type, equal to J. R. Smith.
Page 49 of 417
Mechanical and Electrical Design Guidelines and Specifications
between supplies to irrigation or fountains and the potable water lines to isolate
from potable water. The unit shall contain two check valves and a pressure-
differential relief valve. It shall also have two 1/4-turn, full-port, resilient-seated,
bronze ball-valve shut offs, one before and one after the device with a strainer
and ball type test cocks.
Where cleanouts are provided on buried pipework, a 45° cleanout branch shall
be used which shall be extended up to the floor/ground level and a cover
provided.
Floor cleanout covers shall be manufactured from Duco-coated cast iron. The
cover shall be adjustable, utilizing a Speedi-set gasket. The closure plug shall
be from ABS plastic and be complete with a gasket to form a gas-tight seal. Set
screws shall be from stainless steel.
In unfinished (parking) areas, the cover top shall be round with a scoriated finish
and be of the nontilt tractor type. This type of cleanout cover shall be equal to J.
R. Smith). In tiled areas, the cover top shall be manufactured from nickel-bronze
alloy and shall be square with recess suitable to receive a floor tile. This type of
cleanout cover shall be equal to J. R. Smith. In terrazzo tiled areas, the cover
shall be manufactured from nickel-bronze alloy and shall be square with a
recess suitable to receive a terrazzo tile. This type of cleanout cover shall be
equal to J. R. Smith.
The rainwater inlet shall be a promenade deck drain with 14-inch diameter duco
cast-iron body, perforated stainless-steel extension and flashing clamp, equal to
J. R. Smith.
Duco-coated cast-iron body and flashing collar with cast iron dome and
stainless steel mesh screen, similar to J. R. Smith.
Page 50 of 417
Mechanical and Electrical Design Guidelines and Specifications
The hose bib shall be a 20 mm (3/4”) bronze, angle, hose, and gate valve, with
a rubber composite disc similar to Crane No. 58.
Electric water heaters shall be provided in accordance with the sizes and
capacities shown on the drawings. Water heaters shall be of the glass-lined,
horizontal type suitable for mounting above a suspended ceiling.
They shall incorporate magnesium rods for cathodic protection. The inlet to
each water heater shall incorporate a combination isolating valve, non return
valve, pressure and temperature relief valve, and drain, piped to the nearest
floor drain.
The Contractor shall provide and install tank overflow pipes for each cold water
storage tank, which shall terminate at the nearest sump as indicated on the
drawings.
The Contractor shall provide for each overflow pipe, a stainless- steel insect
screen at the termination point.
The water meter shall be provided in accordance, Water Works of the Standard
Specifications.
(a) Type: Ceramic cartridge with activated carbon fill for removal of taste, dirt,
bacteria, odour and sub-micron filtration of dirt and bacteria.
(b) Construction: Moulded clear plastic body and opaque plastic cover with
threaded connection and threaded inlet and outlet ports.
Page 51 of 417
Mechanical and Electrical Design Guidelines and Specifications
(c) Accessories: Mounting bracket, chrome plated brass wall unions at inlet and
outlet; outlet piping concealed in the wall; ball type isolating valve at the
inlet and a bib tap above the deck for outlet.
(d) Installation: Under counter with concealed discharge piping and outlet valve
above deck.
5.21 Valves
(a) General
All valves from 1/4” to 2” shall be bronze valves and valves 2 1/2” or larger
shall be cast iron as per the following specification.
(b) Gate Valves. All bronze gate valves shall comply with BS 5154, PN20,
Series B, and have a screwed bonnet, and a non rising stem. Ends shall be
screwed with BS 21 taper thread (ISO R7). Valve-pressure rating shall be a
minimum of 20 bar (at between -10 °C and 100 °C) and shall be equal to
Crane.
All cast-iron gate valves shall comply with BS 5150, PN16 with an inside
screw, a non rising stem, and zinc-free bronze trim. Ends shall in be flanged
in compliance with BS 4504, Table 17.11 and shall be equal to Crane.
(c) Globe Valves. All bronze globe valves shall comply with BS 5154, PN20,
Series B, and have a screwed bonnet. Ends shall be screwed with BS 21
taper thread (ISO R7). The valve-pressure rating shall be a minimum of 20
bar (at between -10 °C and 100 °C) and shall be equal to Crane.
All cast-iron globe valves shall comply with BS 5152, Class 125, and have
an outside screw and yoke, a rising stem, and zinc-free bronze trim. Ends
shall be flanged in compliance with BS 1560, Section 3.2 and shall be equal
to Crane.
Page 52 of 417
Mechanical and Electrical Design Guidelines and Specifications
(d) Ball Valves. All bronze ball valves shall comply with BS 5750, Part 1, PN25,
with lever operation, bronze body P.T.F.E. (polytetrafloruoethylene) seat
and packing and bronze or DZR (dezincification-resistant) brass ball. Ends
shall be screwed BS 21 taper thread (ISO R7). Valve-pressure rating shall
be a minimum of 25 bar (at between -10 °C and 100 °C) and shall be equal
to Crane.
(e) Butterfly Valves. All cast-iron butterfly valves shall comply with BS 5155,
PN16, with flangeless, wafer type, gearbox/handwheel. Valves shall be SG
iron body and disk with black high-nitrile rubber body lining, 17/2 Cr/Ni
stainless-steel shaft and shall be equal to Crane.
(f) Check Valves. All bronze check valves shall be of the swing type and shall
comply with BS 5154, PN25, and Series B with screwed bonnet suitable for
horizontal and vertical mounting. Ends shall be screwed BS 21 taper thread
(ISO R7). Valve-pressure rating shall be a minimum of 25 bar (at between -
10 °C and 100 °C), and shall be equal to Crane.
Cast-iron valves shall be swing type in compliance with BS 5153, PN16,
with bolted bonnet, and zinc-free bronze trim, suitable for horizontal or
vertical mountings. Ends shall be flanged to BS 4505 PN6. Valve pressure
rating shall be minimum of 6 bar (at between –10 °C and 120 °C), and shall
be equal to Crane.
(g) Strainers. All bronze strainers shall be Y-type, PN32, series B, with screwed
cover, 17.8 stainless-steel screen, 26 s.w.g. (steel wire gauge) with 0.8-mm
perforations. Ends shall be screwed BS 21 taper thread (ISO R7). Valve-
pressure rating shall be a minimum of 32 bar (at between -10
°C and 100 °C) and shall be equal to Crane.
All cast-iron strainers shall be Y-pattern, PN16, with bolted cover, 17.8
stainless-steel screen with 1.6-mm perforations. Ends shall be flanged in
compliance with BS 10, Table F, but drilled in compliance with BS 4504
Table 17.11. Pressure rating shall be a minimum of 14 bar (at between - 60
°C to 65 °C) and be equal to Crane.
(h) Float Valves. Float valves shall be full-bore, bronze, equilibrium type,
incorporating a copper ball float. The connection shall be flanged in
compliance with BS 4504, Table 17.21 or in compliance with BS 10, Table
E. Pressure rating shall be a minimum of 10.3 bar (at 71 °C).
The Contractor shall install cold water main from DEWA Street main to storage
tank.
The Contractor shall install all piping promptly, temporarily capping or plugging
open ends as work progresses and in a manner to conserve space for other
work.
The Contractor shall inspect each piece of pipe, tubing, fittings and equipment
for defects and obstructions, and promptly remove all defective material from
job site.
Page 53 of 417
Mechanical and Electrical Design Guidelines and Specifications
Dissimilar metals shall be separated from direct contact with each other by
gaskets and dielectric couplings. Metal screws and clamps shall be of same
metal and finish as materials supported.
Drain valves shall be installed at low points and air vents at high points on all
piping.
(a) Select all pump motors for the maximum loading of the selected impeller.
(b) Select all pumps, with operating points within 20% on either side of the
maximum efficiency point.
(c) In so far as possible, do not select the maximum and minimum impeller
sizes for unit pumps.
(d) Use coded colours for finishing equipment of different services.
Equipment shall be accurately set, plumbed, and leveled; and shall be installed,
positioned, and located to allow proper and sufficient space for service,
maintenance, and adjustment.
Ensure that the doorways and other accesses to technical areas are amply
sized, to allow for the movement of equipment. Provide hooks, rails or other
provisions, to allow for hoisting or movement of equipment. Furnish data on
heat loss to surroundings from equipment located in air conditioned areas, to
HVAC trade. Furnish data on required power supply to electrical trade.
5.25 Testing
Prior to covering over, furring in, or placement of insulation, the Contractor shall
test all pipework using the air test as described in BS 5572. All pressure-
sensitive devices shall be removed prior to tests.
All water piping shall be flushed with water at a flow rate sufficient to produce a
velocity of 2.0 metres per second to 2.5 metres per second. The flow rate shall
Page 54 of 417
Mechanical and Electrical Design Guidelines and Specifications
The Contractor shall furnish all material, labour, and equipment necessary to
perform the work to comply with the required DEWA standards for chlorine
residual and bacteriological tests.
A residual of chlorine of not less than 10 ppm will be required in the water after
24 hours, unless otherwise directed by DEWA.
The Contractor shall test the initial and residual chlorine concentrations and
submit a report, providing test results, to the Engineer for his approval.
When the required chlorine residual is obtained, the system shall be flushed as
described above until all excess chlorine is removed. Flushing shall continue
until the chlorine content is equal to that of the water being used for flushing.
The Contractor shall obtain water samples for bacteriological testing. These
samples shall be sent to a recognized laboratory for testing and the results shall
be submitted to the Engineer and DEWA for approval.
Piping shall not be put into service until the results are acceptable to the DEWA.
(a) Fixtures and fittings shall be placed in final position and connected
complete.
(b) Ensure that all the fixtures are located in a manner that enhances the usage
of each fixture. Unless otherwise stated, allow for the following minimum
spacing between fixtures.
1. Centre line of wash basin to centre line of bidet / watercloset - 60 cm.
2. Centre line of bidet to centre line of watercloset - 60 cm.
3. Centre line of bidet / watercloset to wall -40 cm.
4. Centre line of wash basin to wall -45 cm.
(c) Locate the supply angle valve, hose bibs, fixture traps etc. at wall tile lines.
Install these symmetrically on the fixture centre line.
(d) Recess shower edges into the wall finish. Tiling must start over the edge of
these fixtures.
(e) All fixtures shall be fixed firmly to the floor / wall with accessories supplied
by the manufacturer. Use chrome plated brass cap nuts for fixing screws.
Page 55 of 417
Mechanical and Electrical Design Guidelines and Specifications
(f) All ferrous accessories used for the installation of sanitary fixtures shall
have factory applied anti-rust treatment.
(g) Provide chrome plated brass escutcheon plates on chrome fittings fixed on
the wall.
(h) Refer to schedules on drawings for roughing-in details.
(i) Mount fixtures at the following heights above FFL, unless otherwise dictated
by selection.
1. Water closet. 38 cm to top of bowl rim.
2. Bidet. 38 cm to top of bowl rim.
3. Urinal. 55 cm to top of bowl rim.
4. Washbasin. 78 cm to top of bowl rim.
5. Flush valves. 28 cm above top of bowl rim.
6. Shower fixing valves. 90 cm above FFL.
Cleanouts shall be installed on fixture drains of sinks such that the fixture drain
is no more than 6.0 m from a cleanout.
Every cleanout shall be made with a barrett-type fitting that has a bolted cover
plate and gasket, a fitting that has a threaded plug, or a cleanout ferrule that is
installed on a Y.
Cleanouts shall be equal in diameter to all pipes less than 100-mm diameter
and at least 100-mm diameter for pipe sizes larger than 100 mm.
Cleanouts shall be located such that the opening is readily accessible and has
sufficient clearance for effective rodding and cleaning.
Cleanout covers shall match the floor or wall finish in which they are installed.
All vent pipes shall be installed without depressions in which moisture can
collect and shall be graded and connected such that moisture can drain back to
the drainage system.
All vent pipes shall be connected directly from their lower ends to outside air.
Vent pipes shall be installed vertically unless approved otherwise by the
Page 56 of 417
Mechanical and Electrical Design Guidelines and Specifications
Engineer.
Where a vent pipe is to be connected to another vent pipe, the connection shall
be located at least 80 mm above the floor-level rim of any fixture that is served
by either vent pipe.
Connections between a yoke vent and vent stack or branch vent shall be
located at least 80 mm above the flood level rim of every fixture in the storey in
which the connection is made.
The upper ends of all vent pipes that do not terminate in open air shall be
connected to a vent pipe or venting system that does terminate in open air.
The upper end of every vent pipe that is terminated in open air shall be
extended through a roof.
Where a vent pipe is terminated in open air, the terminal shall be located as
follows:
(a) At least 915 mm above or 3.7 m in any direction from any air inlet, window,
or door.
(b) At least 2.1 m above or 3.7 m in any direction from a roof that is used for
other than weather protection.
(c) Except for a fresh air inlet, at least 2.1 m above the ground.
Where a vent pipe passes through a roof, it shall be terminated at least 915 mm
above the roof.
Every fixture supplied with separate hot and cold water controls shall have the
hot water control on the left side and the cold on the right.
Piping shall be graded such that any part of the system can be drained. If it is
not practical to avoid a trap or a sag in a pipe, provision shall be made to drain
it.
5.32 Measurement and Payment
Measurement and payment for various plumbing works included in the Bills of
Quantities will be at the rate per unit included therein for the respective item,
which rate shall be considered as full compensation for the materials, labour,
tools, equipment, and appurtenances required to furnish and install the
respective item.
Each item in the Bills of Quantities shall also include price for all items
mentioned in Section “Mechanical General Requirements” and, “Mechanical
Basic Material and Methods” of the Standard Specifications for Parking
Structures, whether such items are specifically mentioned in the Bills of
Quantities or not.
Page 57 of 417
Mechanical and Electrical Design Guidelines and Specifications
For all plant or equipment requiring an electrical supply, the provision and
installation of wiring or cabling, (including terminations) from the local isolator to
the equipment shall be included as part of the rate for the equipment in the
mechanical Bills of Quantities. The isolator and incoming cabling shall be
included as part of the electrical Bills of Quantities. All wiring shall comply fully
with the electrical specification and local regulations, as applicable.
Payment for the domestic booster-pump set shall include for the complete
packaged set with anti-vibration mountings, flexible connections, control panel,
repeater panel, piping, valves, strainers, pressurization tank, and
instrumentation. Any remote control items such as repeater panel and
pressurestat with wiring shall also be included in the rate.
Payment for the drainage pumps shall include the complete pump set with
flexible connections, control panel, repeater panel, piping, valves, level
switches, interconnecting wiring between panels, and instrumentation.
Payment for hot water heaters shall include flexible connections, all associated
valves, relief-valve piping, and any access panels required for maintenance
access.
Payment for copper pipework shall include for all fittings such as bends, tee,
outlets and unions, all supports and anchors, insulation and finishes, all
connections to equipment, outlets and valves (including flanges and unions), all
chromium plating (where required), chrome-plated stopcocks, air vents, drain
cocks, dirt pockets, puddle flanges, and any other appurtenances required to
form a complete installation. Mainline valves have been measured separately,
the rate for which shall include supports, insulation, and any access panels
required in the building fabric.
Payment for float valves shall include the strainers immediately preceeding the
valve.
Payment for polyethylene pipework with PVC sleeve shall include all fittings
such as bends, tees, unions, connectors, flanges, all supports and anchors,
puddle flanges and any other appurtenances required to form a complete
installation.
Payment for floor drains, planter drains, trench drains, rainwater inlets, and floor
cleanouts shall include all flashing collars, screens, gratings, sediment buckets,
sumps, and pipe connectors to form a complete installation to manufacturer’s
recommendations, where applicable.
Payment for drainage pipework shall include all joints, fittings such as bends,
tees, branches, all supports, line cleanouts, sealing rings, ‘O’ rings, and/or
adhesive to form a complete installation.
Payment for cleanouts shall include any access panels required in the building
fabric.
Payment for UPVC pipework shall include all fittings such as bends, tees,
unions, connectors, flanges, all supports and anchors, connections to
Page 58 of 417
Mechanical and Electrical Design Guidelines and Specifications
equipment, air vents, drain cocks, dirt pockets, puddle flanges, and any other
appurtenances required to form a complete installation. Valves are measured
separately.
Payment for hose bibs shall include connection to piping system and fixing to
the building fabric.
6 DUCTWORK
Galvanized steel ductwork shall be constructed from strip mill cold reduced
sheet steel continuously hot dip galvanized to BS 2989 : 1982, Grade Z2
Coating Type G275, and shall be fabricated in accordance with the
recommendations in the HVCA Specifications issued by the Heating and
Ventilating Contractors Association, ESCA House, 32/34 Palace Court,
Bayswater, London W2 4JG.
Page 59 of 417
Mechanical and Electrical Design Guidelines and Specifications
The fabrication of all ductwork and fittings shall be executed in a neat and
competent manner by a manufacturer experienced in this class of work. It shall
be true to size and free from sharp edges and projections both internally and
externally.
All items shall be suitable in every way for the design velocity and pressure
conditions and shall comply with all specified tests. Ductwork dimensions
shown on the drawings represent the net free internal sizes, exclusive of all
excrescence’s or linings and shall be provided as such. Due allowance shall be
made to maintain the free area where insulation is to be provided internally.
All ductwork and connections shall be adequately braced and stiffened where
necessary to prevent sagging, drumming and vibration.
The air leakage limits set down in DW143 Table 2 shall not be exceeded and
aggregate total leakage from any whole system shall not exceed 5% of the
total design airflow volume.
All stiffeners and angle frames for steel ductwork shall be manufactured from
galvanized sections, and where cut shall be cold galvanized after manufacture.
For external ductwork, including ducts situated on a roof, steel ducts shall be
not less than 1.6 mm thick.
All longitudinal seams for metal ductwork shall be of an approved type and
shall be grooved and sealed at not more than 60 mm centers. Joints in
rectangular metal ducts with the longest side equal t or greater than 600 mm
shall be angle flanged with bolts at 150 mm centers, and with the duct ends
swaged into the angle joints which shall be sealed with a suitable gasket or
sealant.
Page 60 of 417
Mechanical and Electrical Design Guidelines and Specifications
The duct shall be riveted to the flange with rivet spacing not more than 60 mm
centers. Additional flanged joints shall be provided where necessary to
facilitate erection of the ductwork and disconnection for maintenance purposes.
All site joints for metal ductwork, other than flanged joints, shall be properly
swaged plain slip type with the inside lap in the direction air flow and shall be
riveted or jointed with self-tapping screws at not more than 60mm centers. All
such joints shall be sealed and rendered airtight with a suitable sealant.
Metal duct connections to masonry shafts and other builders work openings
shall be made with angle flanges screwed to a hardwood frame fixed to
grounds set in the masonry, and with the duct extended to form a tailed entry.
In the case of fire damper connection to fire barrier walls or floors, the flanged
connection shall be made to a metal companion flange provided with a suitable
sealing gasket.
Where a metal duct passes through a wall, roof or other building structure, it
shall be isolated from the structure by a layer of bituminous felt over which
shall be superimposed a 25 mm thick layer of mineral wool flexible slab to
which the opening shall be made good.
This does not apply to fire dampers which shall be built in.
All screws, bolts and nuts used for erection of the ductwork shall be sheradized
or similarly protected.
All cut edges and other exposed metal shall be painted two coats of red oxide
or zinc chromate paint before erection; and after erection, unless special
protection is specified for the service concerned, all rivets, bolts and nuts and
other exposed metal shall receive two coats of the same protective paint.
All necessary ductwork supports shall be provided and fixed to the building
structure and all necessary bolts, nuts, washers, screws, plugs shall also be
provided.
Page 61 of 417
Mechanical and Electrical Design Guidelines and Specifications
All mild steel sections used for the construction of duckwork supports shall be
galvanized and painted with suitable zinc rustproofer. Welded work to be
galvanized after manufacture shall be zinc sprayed or otherwise rustproofed in
a suitable manner.
Flexible joints shall be provided on the inlet and outlet connection to each fan,
on ducts crossing building expansion joints and elsewhere in the ductwork if so
indicated on the drawings or where necessary to meet the requirements of the
noise and vibration control.
Flexible joints shall consist of, or be protected by, a material having a fire
protection period of at least 15 minutes when tested in accordance with BS.
476 Part 8 : 1972.
The material shall be of glass fibre cloth type; canvas will not be accepted, and
the length of the joints from metal to metal edge shall not be greater than 250
mm or less than 150 mm.
The ductwork shall not impose any load of the flexible joint.
6.8 Non Metallic Flexible Ducts
Page 62 of 417
Mechanical and Electrical Design Guidelines and Specifications
galvanized spring steel wire helix between the liner and cover, and an outer
helix of glass fibre cord or equal bonded to the cover.
Access openings shall be provided in the ductwork at suitable positions for the
purpose of inspection and servicing of the plant and equipment.
Access panels shall be of 1.2 mm thick galvanized sheet steel with a 25mm x
6mm thick approved sealing gasket fixed around the edge with a suitable
adhesive to form an airtight seating against the duct frame. They shall be
provided with a central handle and shall be provided with a central handle and
shall be secured with turn buckles at not more than 150mm centers.
Page 63 of 417
Mechanical and Electrical Design Guidelines and Specifications
Access doors for sprays, humidifiers and cooling coils shall incorporate a 6 mm
clear glass panel 200 mm wide by 400 mm high mounted in a frame with a
waterproof rubber seal.
Where ducts are to be thermally insulated, the frame of access doors or panels
shall be extended beyond the face of the duct using a hardwood timber frame
or other approved means by a measurement equal to the finished thickness of
insulation and arranged so that the insulation can be dressed into the frame.
The insulation finish and any vapour seal shall be carried over the timber frame
and sealed. Access covers in such applications shall be dished to contain the
required insulation thickness and vapour sealed overall.
Access doors on insulated ductwork shall be of the double skin insulated type.
Test holes shall be provided where necessary in main ducts and in all branch
ducts having the diameter or larger dimension greater than 300mm. Test holes
shall be 25mm diameter and shall be provided as near as possible to the
junction of the branch. Locations of these points shall be confirmed to the
engineer by the contractors commissioning engineer with the work shop
drawings. Hinged plug caps shall be provided and all holes shall be sealed at
the completion of the testing and commissioning.
All medium and high pressure ductwork systems as defined by DW 143 shall
be tested for air leakage.
The Engineer reserves the right to require up to 25% of the low pressure
ductwork systems of his selection to be tested for air leakage. Should any one
of the low pressure system tests indicate an air leakage above the prescribed
limit the Engineer will call for all low pressure systems to be so tested and no
Page 64 of 417
Mechanical and Electrical Design Guidelines and Specifications
If a first test produces leakage in excess of the permitted maximum, the section
shall be released and retested until a satisfactory result is achieved. If at the
time of witnessing the test it is apparent that excessive additional sealing of
seams or joints has been done in order to meet the required leakage level, the
section of ductwork under test shall not be counted as part of the tested
ductwork except where the whole of the ductwork is required to be tested.
Seven days clear notice of any test shall be given to the Engineer in writing so
that, where he deems necessary, the Engineer or his representative shall
witness the test. The test rig and all necessary blanks for the purpose of
sealing the ductwork under test shall be provided, and blanks shall be removed
after the test has been approved for each section of the ductwork.
A test certificate shall be issue for each section of the ductwork satisfactorily
tested. Standard test certificates shall be issued by the Engineer’s and each
certificate submitted shall clearly state the information required on the
certificate. Constant air volume boxes or any other ancillary items of equipment
which may be liable to damage by the test pressure shall be isolated during the
test and all necessary precautions shall be taken. Any damaged equipment
shall be replaced.
7 INSULATION
The Insulation shall be as per UAE fire and life safety code 2018 chapter 10
and DM Green building regulations.
7.2 Workmanship
Before insulation is applied pipework and ductwork shall be clean, free from
rust and erected in accordance with good practice with proper clearance to
permit the application of insulation. All pipes and ducts shall be insulated
independently and no two shall be lagged together. Wherever possible the
space between finished surfaces shall not be less than 25 mm. All the required
heat test, pressure tests, and air leakage test shall have been satisfactorily
carried out and approved, and existing pipework and plant shall be suitably
protected, before insulation work may commence.
In order not to delay building operations where pipework or ductwork will
eventually be encased or made inaccessible within the building structure, if
necessary, sections of the installation shall be insulated independently as the
work proceeds.
Skilled labour only shall be used and the materials and workmanship shall be
Page 65 of 417
Mechanical and Electrical Design Guidelines and Specifications
7.3 Scope
Thermal insulation shall be applied to, but not limited to, the following systems:-
Return and extract air ductwork other than ductwork which due to the nature of
the systems can only under all circumstances convey air at the same
temperature as the surrounding ambient
All thermal insulation shall be applied where specified and in accordance with
the Schedule of Insulation in a careful and efficient manner to give a smooth,
homogenous and cleanable surface and to present a neat and symmetrical
appearance. Rigid sections shall be concentric and accurately matched for
thicknesses. Damaged ends will not be accepted and any irregular or badly
finished surfaces shall be stripped and re-lagged to the satisfaction of the
Engineer.
At bends, tees etc, the sectional insulation shall be formed into neat segments.
The sections of insulation shall be carefully butted together to ensure the
absence of gaps in the insulation and to prevent voids forming between the
insulation and the pipework.
All insulation shall be fixed with a suitable adhesive applied over the whole of
the surface to which the insulation is to be applied.
On all sizes of pipework where a vapour seal and insulation are specified, the
pipe applied insulation shall terminate at a load bearing insulant of the same
type as specified for pipe support points and the vapour seal and insulation
Page 66 of 417
Mechanical and Electrical Design Guidelines and Specifications
finish shall be dressed down to the bare pipe 50 mm either side of valves or
flanges.
An aluminum or stainless steel box shall be fitted over valves and flanges. The
box shall include as an integral part, sleeves of the same material as the box
which shall overlap the vapour sealed load bearing insulant on the adjoining
pipework on each side and fit closely about it. The space between the sleeve
and the overlapped insulation and its finish shall be filled with an approved
sealant. The sleeved valve/flanged box shall be lined with aluminum foil, the
whole space between the uninsulated pipe, valve/flange shall then be filled with
a closed cell polymer injected foam insulant suitable for a temperature range of
-20º C to +110º C. The foamed insulation shall terminate at the top of the valve
bonnet and any surplus foam shall be wiped clean. Care shall be taken to
ensure that the injected foam does not impede the valve operation. Valve
spindles, handwheels and the like shall be contained in a removable section of
the valve box permitting access to handwheels. The handwheels and spindles
shall be wrapped with an adhesive closed cell insulating tape as a primary
precaution. A loose mattress of insulation shall then be inserted in the cavity
between the removable valve box section and hand wheel/spindle and a
vapour barrier of aluminum foil shall be applied over the loose insulation
mattress.
The vapour barrier shall be extended to the pipe surface every 4.0 m on
vertical risers, so that any failure in the vapour barrier can be easily identified.
Where foamed plastic pipe insulation is specified it shall generally be of the slit
type. All joints shall be closed and sealed with adhesive as recommended by
the manufacturer of the insulation after its application and the butt joint shall
receive a final seal of pressure sensitive self adhesive tape.
Page 67 of 417
Mechanical and Electrical Design Guidelines and Specifications
The insulation shall be of rigid slab type cut to fit such that top and bottom
pieces overlap the sides. The insulation shall be bonded to the ductwork with
an approved adhesive applied in 150 mm wide bonds at no greater than 300
mm intervals. The fixing of side and underside insulation sections shall be
reinforced by means of spot welded nails or self adhesive nails secured with
spring loaded washers at appropriate intervals.
All ductwork insulation exposed to view in plantrooms, risers, and like areas
shall have its corners reinforced by stiff cardboard angles fixed firmly to the
insulation by adhesive.
The insulation shall then be covered by glass scrim cloth treated against fungal
attack and securely fixed by means of a suitable adhesive.
Flexible connections shall not normally be insulated. Where test holes are
provided the insulation shall be beveled to form a neat access hole 75 mm in
diameter around the test hole.
Access doors is insulated ducts shall be of the double skin insulated type.
Where a vapour seal has been specified for the insulation the vapour seal shall
be continued around the termination of the insulation in order to preserve the
integrity of the vapour seal. Furthermore, the ductwork supports shall not be
connected to the ductwork stiffening or flanges but shall incorporate an
insulator to which the insulation and vapour barrier shall abut and maintain the
continuity of the vapour barrier.
Thermal insulation when delivered to site and prior to installation the Engineer
may request the following tests:-
Page 68 of 417
Mechanical and Electrical Design Guidelines and Specifications
No insulation shall vary from the specified thickness by more than 10%.
To verify that the correct thickness has been installed the Contractor shall cut
out up to 5 sections of each type and thickness of insulation specified on each
service as directed by the Engineer. The Contractor shall allow for the cost of
cutting out and making good in his tender. Should such cutting out shown that
the insulation is in anyway inadequate further test sections shall be cut out as
directed by the Engineer. In the event of this insulation being inadequate or
unacceptable to the Engineer the whole of the insulation or such parts as the
Engineer shall identify shall be cut out and all such sections re-insulated to this
approval.
After a 24 hour period two further coats of a vinyl vapour barrier with a water
vapour transmission of 0.04 perm at 0.38 mm dry film thickness shall be
applied in accordance with the manufacturer’s recommendations. The vapour
barrier shall be continued around end termination of insulation including where
the normal insulant terminates at valve and flange boxes, pipe and duct
supports and the like to preserve the integrity of the integrity of the barrier and
to provide sectional barriers to prevent any condensation that may for any
reason form in a section of insulation from spreading unduly.
The vapour seal shall be continued over flanges and at any point where the
vapour seal will be interrupted by such as thermostats an approved sealant
material shall be applied to provide a flashing around the projection through the
insulation. This also applies to valves and the flashing shall be provided at the
top of the valve bonnet.
All paint shall comply with the appropriate BS and each type shall be selected
for its use and position.
The choice and use of paints, or other materials, shall comply in all respects to
the manufacturer’s printed instructions.
Page 69 of 417
Mechanical and Electrical Design Guidelines and Specifications
(a) Where installed internally all brackets; once free from rust and scale, are to
be painted with one coat of red primer before erection (a works primer coat
is accepted in lieu if touched up where cut or damaged), and on completion
of the work, but before the lagging is put on, the following shall also be
painted one coat of black heat resisting paint:
(b) Where installed internally the following, once free from rust, scale and
lagging waste, are to be pained with a primer coat (red oxide on steel and
galvanized iron, and Chromate primer on copper and gunmetal) and two
coats of inspection quality and colour heat of inspection quality and colour
neat resisting paint:
2. All un-insulated services and plant in ducts, walkway ducts, voids and
ceiling voids. This also applies to ducts that run externally to buildings.
3. All un-insulated services and plant in rooms (which include service
spaces and tank rooms).
All pipes whether insulated or not shall be identified by code indication colour
bands in accordance with BS 1710: 1984.
Colour bands shall not be provided on pipes which are to be painted to match
internal decorations.
In addition to the identification band coding all services shall be legibly and
neatly marked with black letters a light background is used and white letters
where a dark background is used and appropriately coloured triangles to
indicate the direction of flow as follows:
Page 70 of 417
Mechanical and Electrical Design Guidelines and Specifications
Aluminum protective cladding shall be formed from either 0.6 mm stucco finish
or 0.8 mm thick plain aluminum sheet with overlap joint secured with pop rivets.
Care shall be taken to ensure that no damage to the insulation surface or its
outer finishes occur in this process. Where pipework is located in a particularly
vulnerable position or so as to obstruct normal man access such that it may be
climbed 1.0 mm stainless steel cladding shall be provided in lieu of the
specified aluminum for the entire section.
Where flanges, valves, unions, etc., have to be insulated the cladding shall
take the form of demountable casings fabricated from 0.6 mm stucco finish or
0.8 mm aluminum sheeting.
Unless otherwise indicated, all thermal insulating materials used within any
building shall, when tested in accordance with BS 476 Part 4, be classified
non-combustible. Alternatively, all thermal insulating materials used within any
building shall be non-combustible with a facing of combustible material
providing the facing is no more than 0.8 mm thick and it has a Class 1 Surface
Spread of Flame when tested in accordance with BS 476 Part 7. Thermal
insulating materials used within any building shall be free from substances
which in the event of a fire would generate appreciable quantities of smoke,
noxious or toxic fumes. When requested by the Engineer, evidence of fire
classification, obtained from an approved testing laboratory, shall be provided
by the Contractor in order to certify that materials comply with this clause.
Glass fibre insulation shall have a maximum thermal conductivity of 0.04 W/mº
C, approximate density 65 kg/cum and shall be in accordance with the
provisions of BS 3958.
Glass fibre insulation in the form of rigid slabs shall be resin bonded.
Glass fibre insulation for pipes including fittings, shall be applied as rigid
preformed sections factory covered with strong glass scrim cloth with 50 mm
end and side overlaps which shall be neatly fastened down with a suitable
Page 71 of 417
Mechanical and Electrical Design Guidelines and Specifications
Mineral wool insulation shall be manufacturer from rock drawn out in long fine
fiber’s and made up to the form required. Rockwool mineral insulation shall
have a maximum thermal conductivity of 0.05 W/m/C and shall be in
accordance with the appropriate parts of BS 3958.
All air handling units shall be of the double skin casing type with 50 mm of
incombustible mineral wool insulation having a density not less than 50 kg/m3
contained between to give the same coefficient of heat transmission as the
insulation specified for the adjoining ductwork.
In general the manufacturer’s standard insulation type and finish will ordinarily
suffice subject to the approval of the Engineer and its compliance with the
general terms of the insulation specification.
Insulation Schedule
Service Insulation Insulation Insulation Finish
Service Location
s Size Type Thickness
Chilled water PIC foam Vapor barrier and
External 15 to 40 30
sections Aluminum cladding
Chilled water PIC foam Vapor barrier and
External 50 to 80 38
sections Aluminum cladding
Chilled water PIC foam Vapor barrier and
External >80 45
sections Aluminum cladding
Chilled water Conceale PIC foam
15 to 40 25 Vapor barrier
d sections
internally
Chilled water Conceale PIC foam
> 40 32 Vapor barrier
d sections
internally
Chilled water PIC foam Vapor barrier and
Plantroom 15 to 40 25
sections Aluminum cladding
Page 72 of 417
Mechanical and Electrical Design Guidelines and Specifications
Insulation Schedule
Service Insulation Insulation Insulation Finish
Service Location
s Size Type Thickness
Chilled water PIC foam Vapor barrier and
Plantroom > 40 32
sections Aluminum cladding
Condensate Taped, sealed and
External All Foam plastic 10
drains weather finish
Condensate Concealed
All Foam plastic 10 Taped and sealed
drains internally
Condensate Taped, sealed and
Plantroom All Foam plastic 10
drains Aluminum cladding
Cold water
All All None - -
service
Fire protection
All All None - -
Concealed
Hot water All Fiber glass 25 Wear coating
internally
service rigid
sections
Hot water Fiber glass
Plantroom All 25 Aluminum cladding
service rigid section
Supply, return
and exhaust air Fiber glass Vapor barrier and
External All 25
dusts sections Aluminum cladding
Supply, return
and exhaust air Concealed Fiber glass
All 25 Vapor barrier
dusts internally sections
Supply, return
Rigid fiber
and exhaust air Vapor Aluminum
Plantroom All glass 25
dusts barrier and cladding
Supply, return
and exhaust air Concealed Fiber glass
All 25 Vapor barrier
dusts internally sections
Supply, return
and exhaust air Vapor Aluminum
Plantroom All Rigid fiber 25
dusts barrier and cladding
glass
Subsequent clauses of the section detail general requirements for noise and
vibration control, refer to the particular specification for project specific
requirements.
Page 73 of 417
Mechanical and Electrical Design Guidelines and Specifications
The Contractor shall allow for lining all ducts including builders work ducts
where necessary to provide additional attenuation or to prevent the formation
of standing waves and the like.
8.3 Attenuators
Attenuators shall be cased in galvanized mild steel of at least the same gauge
as the adjoining ductwork and otherwise as necessary to suit their purpose.
They shall be provided with mating flanges which shall be riveted to the
ductwork at intervals not exceeding 60mm centers. The duct ends shall be
swaged into the joint which shall be sealed with a suitable gasket or sealant.
Flanges shall be bolted together at not more than 150mm intervals.
Acoustic lining of ductwork, including builders work ducts and plenums shall be
applied, where necessary to achieve the required acoustic performance.
Acoustic lining shall be vermin proof, rot proof and noncombustible tested to
BS 476 Part 4: 1970 and shall be fixed to ductwork in an approved manner. It
shall be contained behind a suitable scrim or liner to prevent airborne fibre
entrainment.
The Contractor shall provide all means necessary to isolate all vibrating plant,
Page 74 of 417
Mechanical and Electrical Design Guidelines and Specifications
All vibration control components and its selection shall be based on ASHRAE
handbook and related ASHRAE code and standard latest edition.
The Contractor shall allow for the design, selection and provision of, necessary
(and regardless of whether indicated on the drawings or not):
Antivibration mountings, floating floors, plinths, inertia blocks, etc. Flexible pipe
and ductwork connections and couplings spring mounted pipe and duct
hangers and supports. Ductwork stiffeners and bracing. Water hammer/shock
arrestors and all such items as may be necessary.
The Contractor shall take due regard in his selection of all related factors likely
to affect the performance of his proposed antivibration items including the
behavior of the supporting structure under the appropriate forcing frequency,
the compound effect of series coupled anti-vibration mounts, near synchronous
beat frequencies, harmonic affects and the like.
All HVAC systems shall be as per DM green building regulations and ASHRAE
90.1 - Energy Standard for Buildings Except Low - Rise Residential Buildings.
This section covers all the prime air movement apparatus in relation to the
types of air-conditioning and ventilation systems.
Units shall comply with ARI Standard 210. The unit’s efficiency shall be a
minimum of 9.5 EER using the T1-ARI 210/240 test procedure or 6.6 EER using
T3-ISO 5151 test procedure, ASHRAE 90 latest and DM green building
regulation. Units shall have the specified design capacities. The evaporator
units shall be completely matched with the condensing units. cooling capacity
shall be based on actual capacity not nominal.
Page 75 of 417
Mechanical and Electrical Design Guidelines and Specifications
All acoustic and thermal insulation including facings and adhesive shall be fire-
resistant and conform to the requirements of the local authorities.
The noise output of the units shall not cause the specified noise levels within
the conditioned spaces to be exceeded.
The casing shall make the units fully weatherproof for outdoor installation and
shall be suitable for saline and marine conditions.
The electrical supply to each unit shall be from the local distribution panel in
compliance with the requirements of DEWA. The unit shall be factory wired and
incorporate starters and a control circuit to permit remote starting.
Gauges of sheet metal specified herein, refer to U.S. standard gauges and are
the minimum permissible thicknesses.
Units and components within shall be bonded for grounding, to meet the safety
standards for servicing required by UL and NEC. Unit shall be suitable for fresh
air as mention in drawings.
Assembly
Split system air conditioning units shall be provided complete with house
keeping pads for outdoor condensing unit, vibration isolators, mounting brackets
and bolts, support for indoor unit, refrigeration and condensate drain piping and
controls. The condensing unit shall be mounted as shown on the Project
Drawings or approved by the Engineer. The units shall operate on 400V, 3
phase 50 Hz system.
Cabinets shall be constructed from galvanised steel with epoxy coat finish.
Indoor section of the cabinet shall be lined with fibreglass insulation. Indoor
coil drain pan shall be constructed from heavy gauge galvanised steel.
Electrical cable inlets shall be furnished in cabinet for wiring entry with sealant
and proofing.
Both indoor and outdoor coils shall be constructed of aluminum fins, machine
fitted to copper tubes and tested under pressure to ensure leak proof
construction. The coil assembly shall be provided with a corrosion resistant
baked-on coating applied at the manufacturer's works so as to provide
increased resistance to attack by saline and marine atmosphere.
Page 80 of 417
Mechanical and Electrical Design Guidelines and Specifications
25mm frame filters with washable or vacuum cleanable polyurethane shall be
provided. Contractor shall provide one set of spare filters for each indoor unit.
The contractor shall provide all necessary refrigeration copper tubing for
interconnecting piping between indoor and outdoor units. The sizes of
refrigerant liquid and suction lines shall be as recommended by AC unit
manufacturer having connection sizes matching the unit connections.
Refrigeration tubing shall have continuous thermal insulation closed-cell type of
minimum thickness 15mm designed for temperature range –200C to +800C.
The condensate drain piping shall be minimum 25mm uPVC, draining each
indoor unit cooling coil to sanitary sewer. An emergency overflow drain pipe
shall be provided under units mounted in MCC (motor control centres) rooms.
The pan shall be piped to the nearest drain outside the MCC room.
The fan coil units shall be selected to satisfy the design conditions when
operating at medium speed. A condensate drain and running trap shall be
provided from each fan coil unit, with the minimum seal depth of the trap equal
to the pressure generated by the fan.
Equipment Coating
Coating of Cabinets and Other Components: For the cabinet, frame, motors,
compressors, tubing, etc., all surfaces are to be cleaned as above and any rust,
welding flux or residue of any kind shall be removed by light sand- blasting. The
surface of the factory-applied enamel is to be treated to remove gloss with a
prep solution made for the purpose.
Page 81 of 417
Mechanical and Electrical Design Guidelines and Specifications
Controls
A complete control system for the air conditioning system shall be furnished
and installed. The controls shall be the manufacturer's standard control
package for the specified unit.
All AC units shall be operated as duty and standby with change over control
panel.
Installation
Room mounted fan coil units shall be mounted in the positions as directed by
the Engineer. These units may be tiered if necessary, not more than two units
being allocated to any one tier. Air cooled, outdoor condensing units shall be
mounted around the periphery of the building, in the positions as directed by
the Engineer. All necessary epoxy/poweder coated mounting brackets and
supports to be supplied.
9.5 Refrigerant
The Contractor shall leave the refrigeration systems with full charges of
refrigerant and shall be responsible for the maintenance of a full charge of
refrigerant in the systems for a period of 2 (two) years from date of Substantial
Completion. Should any leaks in the refrigeration system occur during the
guarantee period, Contractor shall eliminate such leaks and recharge system
to a full charge of refrigerant at no cost to the Client.
Page 82 of 417
Mechanical and Electrical Design Guidelines and Specifications
Service
Contractor shall provide a written service contract to the Client which shall
provide monthly service inspection and maintenance for the air conditioning
systems, for 2 (two) years from the date of Substantial Completion and final
acceptance of the air conditioning in the Contract. If, during this time interval,
replacement of any parts, cleaning, oiling or maintenance of the various pieces
of equipment is necessary for proper and continued functioning of this system,
this service will be provided at no charge to the Client. Full charges of
refrigerant shall be maintained, and any leaks which might occur during this
time shall be repaired.
Monthly service shall include checking and adjusting all drives, lubrication of
equipment as required, changing/cleaning air filters, checking general operation
of the entire air conditioning system, and making adjustments as required for
proper system operation. Checking all drain pans and drain lines from air units
and clean as required. Storage of extra filters and installation as required above.
Each unit shall comprise fan, and filter enclosed in a heavy gauge galvanised
sheet steel casing with manufacturer's standard finish. The casing shall
incorporate supply duct spigot and return air plenum or where appropriate,
supply and return air grilles, together with insulated drain tray. The free
standing units will be finished in baked enamel or similar standard finish.
Filters shall have a minimum efficiency of 92% when tested to BS 2831 using
Test Dust No.2.
Each unit shall be provided with a trapped condensate drain connected into a
common drain and run to a discharge point as indicated on the drawings.
Fans shall be of the forward curved centrifugal DIDW type direct driven by an
internally mounted motor wound for a 220/240 volts single phase 50 Hz.
electric supply, and with sealed-for-life bearings.
Provide and install extract fans as indicated on the drawings with the
scheduled duties.
Page 83 of 417
Mechanical and Electrical Design Guidelines and Specifications
Extract from toilets shall be by means of twin fan cabinet units. Each unit shall
consist of a casing constructed from galvanised or plastic coated steel sheet
enclosing twin centrifugal fans direct or belt driven by separate electric motors.
Motors for direct driven fans shall be suitable for a 220/240 volt single phase
50 Hz. supply and for belt driven fans shall be suitable for a 400/415 volts three
phase 50 Hz. supply. Motors shall have sealed for life bearings.. All units shall
incorporate back- draught shutters.
All scheduled fan duties are based on air quantities required at the room
outlets and due allowance must be make in fan selections for duct leakage.
The external fan resistance shall be calculated by the Contractor taking into
account the resistance of ductwork. attenuators, grilles etc.
9.8 Attenuators
All materials used shall comply with the relevant parts of BS 476.
Attenuator casings shall be constructed to the same pressure classification as
the adjacent ductwork.
Roof mounted extract units shall be installed in the locations shown on the
Contract Documents
For ducted systems they shall comprise direct drive mixed flow fans mounted
in low contour weatherproof housings arranged for curb or purlin mounting as
appropriate.
The housings shall be constructed from heavy gauge aluminium alloy finished
in polyester powder paint or molded in fire retardant glass-fibre reinforced
resin.
The assembly shall conform in all respects with the testing to BS 848 and BS
3638. Matched silencers shall be provided subject to confirmation of noise
levels by the contractor.
The fans shall be single inlet high performance mixed flow type manufactured
Page 84 of 417
Mechanical and Electrical Design Guidelines and Specifications
Motors shall directly drive the fans and shall have sealed for life bearings.
Electrical supply shall be single phase.
Twin fan units on toilet and kitchen extract systems shall incorporate duty and
standby fans within the same housing.
All fans shall be heavy duty type suitable for marine weather and continue
operation.
Local wall mounted fans shall be installed in the locations shown on the
Contract Documents. Wall and window mounted extract fans shall be capable
of the duty as shown in the Contract Documents.
The fan unit shall consist of a propeller fan housing, back draught shutters and
discharge grille. Construction shall be of high quality moulded plastic.
Fan motors shall be totally enclosed in aluminum alloy case and shall be
protected by a thermal overload cut-out.
Motor bearings shall be self-aligning oil impregnated porous bushes with ample
oil reservoir.
Page 85 of 417
Mechanical and Electrical Design Guidelines and Specifications
Units shall comply with ARI Standard 210. The unit’s efficiency shall be as per
ASHRAE 90 latest and DM green building regulation.
Units shall have the specified design capacities. cooling capacity shall be based
on actual capacity not nominal.
The safety controls shall protect the unit from, low suction pressure and high
condenser pressure.
The units shall be provided with direct driven, propeller type fans arranged for
vertical discharge. All acoustic and thermal insulation including facings and
adhesive shall be fire-resistant and conform to the requirements of the local
authorities.
The noise output of the units shall not cause the specified noise levels within
the conditioned spaces to be exceeded. The casing shall make the units fully
weatherproof for outdoor installation and shall be suitable for saline and marine
conditions.
The electrical supply to each unit shall be from the local distribution panel in
compliance with the requirements of DEWA. The unit shall be factory wired and
incorporate starters and a control circuit to permit remote starting.
Units and components within shall be bonded for grounding, to meet the safety
standards for servicing required by UL and NEC.
9.19 Assembly
The air conditioning units shall be provided complete with house keeping pad,
refrigeration and condensate drain piping and controls. The unit shall be
mounted on a concrete pad suitably located, as approved by the Engineer.
The units shall operate on 400V, 3 phase 50 Hz system.
Cabinets shall be constructed from 18 gauge (1.20 mm) galvanised steel with
epoxy coat finish. Evaporator section of the cabinet shall be lined with fibreglass
insulation. Indoor coil drain pan shall be constructed from heavy gauge
galvanised steel. Electrical cable inlets shall be furnished in cabinet for wiring
entry with sealant and proofing.
Page 86 of 417
Mechanical and Electrical Design Guidelines and Specifications
Package units shall have spring and neoprene vibration isolators, secured by a
isolator with minimum deflection under load, unless internally isolated. In this
case provide neoprene pads of required thickness between the unit and
mounting platform or housekeeping pads.
The condensate drain piping shall be minimum 25mm uPVC, draining each unit
cooling coil to sanitary sewer..
The units fan shall be self-contained, with temperature control, cleanable filter,
cooling coil and operated by a room thermostat. A fan speed control selector
with 'off' position shall be located with the room
Page 87 of 417
Mechanical and Electrical Design Guidelines and Specifications
thermostat. The units shall incorporate all necessary protection devices, the
electrical supply shall be arranged to be from the distribution board. The units
shall be selected to satisfy the design conditions when operating at medium
speed. A condensate drain and running trap shall be provided from each fan
coil unit, with the minimum seal depth of the trap equal to the pressure
generated by the fan. Anti-vibration mountings and flexible connections shall be
provided for each unit.
Coating of Cabinets and Other Components: For the cabinet, frame, motors,
compressors, tubing, etc., all surfaces are to be cleaned as above and any rust,
welding flux or residue of any kind shall be removed by light sand- blasting. The
surface of the factory-applied enamel is to be treated to remove gloss with a
prep solution made for the purpose. A wash primer is to be applied to all bare
metal surfaces (including galvanised surfaces). All surfaces (excepting fin, fan
blade and plastics) are to be coated with urethane, to a minimum thickness of 6
mils.
9.21 Controls
A complete control system for the air conditioning system shall be furnished
and installed. The controls shall be the manufacturer's standard control
package for the specified unit.
Page 88 of 417
Mechanical and Electrical Design Guidelines and Specifications
9.22 Installation
The installation shall be carried out in a neat and workmanlike manner and
shall be unobtrusive, whilst remaining readily accessible for maintenance.
9.23 Refrigerant
The Contractor shall leave the refrigeration systems with full charges of
refrigerant and shall be responsible for the maintenance of a full charge of
refrigerant and oil in the systems for a period of 2 (two) years from date of
Substantial Completion. Should any leaks in the refrigeration system occur
during the guarantee period, Contractor shall eliminate such leaks and
recharge system to a full charge of refrigerant at no cost to the client.
9.24 Service
Contractor shall provide a written service contract to the client which shall
provide monthly service inspection and maintenance for the air conditioning
systems, for 2 (two) years from the date of Substantial Completion and final
acceptance of the air conditioning in the Contract. If, during this time interval,
replacement of any parts, cleaning, oiling or maintenance of the various pieces
of equipment is necessary for proper and continued functioning of this system,
this service will be provided at no charge to the Cliet. Full charges of
refrigerant shall be maintained, and any leaks which might occur during this
time shall be repaired.
Monthly service shall include checking and adjusting all drives, lubrication of
equipment as required, changing air filters, checking general operation of the
entire air conditioning system, and making adjustments as required for proper
system operation. Checking all drain pans and drain lines from air units and
clean as required. Storage of extra filters and installation as required above.
All ductwork and distribution accessories delivered to Site shall be new and
indelibly stamped to identify different grades, materials and manufacturers.
Galvanized steel ductwork shall be constructed from strip mill cold reduced
sheet steel continuously hot dip galvanized Grade Z2 Coating Type G275, and
shall be fabricated in accordance with the recommendations in the HVCA
Page 89 of 417
Mechanical and Electrical Design Guidelines and Specifications
HVAC, DW/144: Specification for Sheet Metal Ductwork, Low, Medium and
High Pressure/Velocity Air Systems.
The ducts that are used for normal air conditioning and ventilation system are
termed non-fire rated ducts.
The zinc coating shall not be damaged during fabrication and installation. The
construction shall comply with SMACNA. Bends and branch vanes, dampers
etc. shall be of the same material as used for the ducts.
All duct sections shall be joined as per DW/144 and SMACNA requirements. All
nuts, bolts and washers shall be galvanized. Duct sizes shall be selected on the
basis of maximum pressure drop of 1.25 Pa/m of duct. The recommended
maximum velocity in ducts is 7m/s in public area.
All air ductwork passing through walls, floors or ceilings shall be sleeved. All air
conditioning ductwork shall be insulated to control condensation.
The ducts shall be properly and correctly constructed with all necessary
accessories to minimize waste of energy and pressure losses due to eddies,
vortices etc. and shall not create, amplify or transmit any noise or vibration.
Internal roughness and obstructions to air flow (other than dampers, splitters,
vanes etc.) shall not be accepted for ductwork constructed from sheet materials.
Sharp edges or corners on the outside of ductwork, fittings and supports shall
not be accepted.
Steel metal duct sizes shown on the Drawings are clear internal dimensions and
allowance shall be made for insulation where applicable.
Provide splitter dampers, complete with adjusting handle or similar device to all
branches of the supply air ducts to regulate air flows along the main duct and
the branch ducts, whether they are specifically shown on the Drawings or not.
Provide opposed blade type volume control dampers to all branch ducts.
Provide fire dampers as require by the fire strategy plan. Fire damper
Page 90 of 417
Mechanical and Electrical Design Guidelines and Specifications
construction shall comply with the requirements of NFPA and local authorities.
Installation
Provide complete ductwork systems and ensure that the installation can be
adjusted to the designed flow rates.
Check all the Drawings provided in regard to structural requirements and other
finishes before detailing the ducting system. Allowance shall be made for the
detailed development and on-site coordination.
Duct sizes given on the Drawings are clear internal dimensions and allowance
shall be made for insulation where applicable.
Install dampers and splitters in a manner so that they can be adjusted at any
time after completion of the work.
Internal roughness, sharp edges or obstructions to air flow shall not be allowed.
External edges and corners formed from cleated joints shall be neatly dressed
down with air tight joints.
Supports shall be located close to all dampers, diffusers and other in duct
equipment.
During construction the duct openings shall be temporarily closed with covers to
avoid debris entering ducts.
Access Doors
Access doors shall be installed at every air chamber, filter section, fire damper,
automatic damper, valves, temperature control equipment, filters, fan bearings,
entering side of cooling coils, to permit inspection operation and maintenance.
Page 91 of 417
Mechanical and Electrical Design Guidelines and Specifications
All doors shall be hinged with two hinges, and two latches shall be used on
doors over 200 mm x 200 mm or larger.
THERMAL INSULATION
Thermal insulation shall be provided for all air conditioning ductwork. Thermal
insulation shall comply with the requirements of BS 476.
Flammability – BS 476 Part 6 - Method of test for fire propagation for products
BS 476 Part 7 - Method of test to determine the classification of the surface
spread of flame of products criteria, Class 1.
Insulation materials and finishes shall be inherently proof against rotting, mould
and fungal growth and attack by vermin and in all respects be suitable for
continuous use throughout the range of operating temperatures and for the
environment conditions.
Insulated pipes and ducts shall be supported on the outside of the insulation,
with load spreading metal plates of suitable size and thickness between the
insulation and supports to prevent the insulation being crushed. The insulation
at the support points shall be of heavy density load bearing form in pre-formed
or slab sections made to the same thickness and external finish as the adjacent
pipe or duct insulation. At all points of support, both insulation and outer
covering shall be continuous and shall not be punctured or fouled by the
supports. The insulation at supports shall be material of sufficient compressive
strength to take the loads transmitted to the supports. The load-bearing
insulation shall be extended on each side of the supports.
Page 92 of 417
Mechanical and Electrical Design Guidelines and Specifications
Acoustic duct internal lining shall be provided after the machine inlet for 3
meters. The material used for acoustic duct internal lining shall be
incombustible, non-hygroscopic, vermin proof and moisture proof. It shall be
25mm thick with 48kg/cum density.
The lining shall comply with BS 476 Part 6 and the requirements of DCD,
including the associated fasteners, adhesives, tapes etc.
The duct internal lining shall be fixed to the duct with 100 % coverage of fire-
resistant adhesive. The liner shall also be additionally secured with mechanical
fasteners on maximum 400 mm centres on all sides.
For duct bends installed with internal lining, the lining shall be a minimum of 25
mm thick, 48 kg/m3 fiberglass with protecting surfaces.
The duct lining shall extend for at least 3 m on both arms of the elbow.
All motor operated dampers shall be suitable for installation in either a vertical
plane or a horizontal plane as shown on the Drawings.
Fire Damper
Fire dampers used singly or in combination shall have an overall fire rating not
less than that as required and, in no circumstances, not less than that for the
wall or floor slab in which they are located. Fire dampers shall be constructed of
either a corrosion resistant material be galvanized or otherwise treated to
Page 90 of 417
Mechanical and Electrical Design Guidelines and Specifications
Fire Dampers shall be supplied with all necessary fixing frame work for their
installation.
Each fire damper casing shall be clearly marked with a permanent indication of
the correct fixing attitude of the damper, the direction of air flow and the side at
which the access/maintenance opening is located.
Gravity operated multi-bladed fire dampers shall not be used in vertical ducts.
Gravity operated single bladed dampers may be used for horizontal ducts.
Means shall be provided to ensure reliable and positive closure when operating
in maximum air flow rate conditions.
Unless otherwise specified, each fire damper shall be held in the open position
by a corrosion resistant retaining device, incorporated a fusible element, which
shall operate at temperature of 74 °C. The fusible link shall be arranged in an
exposed position and upstream of the damper.
Fire damper casings shall be flanged to suit the ductwork which they are fitted
and the cross-sectional area shall not be less than that of the ductwork.
Blades and fusible links shall be accessible for servicing through air-tight
inspection doors placed upstream or downstream of the air path, whichever
provides the better access. Proprietary fire dampers shall be DCD approved.
All grilles and diffusers shall be of dry powder coated aluminium unless
otherwise specified.
All supply, return and exhaust diffusers shall be complete with opposed blade
dampers, suitable for mounting with appropriate diffuser and shall be fitted with
concealed adjustment devices.
Each supply air grille shall be complete with an opposed blade damper.
The drawings show provisional locations of diffusers and grilles but in each
instance, outlets shall be installed in accordance with the final detail drawings
and reflected ceiling plans.
Velocities, net airways and distribution patterns shall give satisfactory air
distribution and temperature equalization, be free of draughts, stratification or
noise nuisance. Make final adjustments to air patterns when balancing.
Supply and Return Air Grilles
Double deflection supply air grilles/registers shall be tapped from side or bottom
of ducts with provision for tamper-proof adjustment of air pattern spread along
Page 91 of 417
Mechanical and Electrical Design Guidelines and Specifications
Grilles and registers shall be factory assembled with opposed blade volume
control dampers operable through the grille face. The adjustment shall be by a
key through the face of the register and the volume control damper shall be
group-operated or opposed blade type. The operating mechanism shall not
project through any part of the register face.
All grille cores shall be capable of being removed easily from the ductwork for
access to dampers.
All edges exposed to view shall be rolled or otherwise stiffened and rounded. All
edges shall be equipped with airtight, sealing strips to prevent leakage. The
register rings or frames shall be compatible with the ceiling construction in
which they are installed.
Aluminium Cladding
Aluminium protective cladding shall be formed from either 0.6 mm stucco finish
or 0.8mm thick plain aluminium sheet with overlap joint secured with rivets.
Care shall be taken to ensure that no damage to insulation surface or its outer
finishes occur in this process.
Vibration Isolators:
The Contractors shall provide all means necessary to isolate all vibrating plant,
equipment, associated system components and the like to the minimum
standards set down in the schedule of isolation Efficiencies or as otherwise
necessary.
The contractor shall allow for selection and provision of necessary antivibration
mounting, floating floors, plinths, inertia blocks etc. Vibration pads shall be
provided to all AC Equipment’s for isolating Vibration.
Flexible duct work connections, duct hangers and supports shall be provided for
isolation of Vibration from Equipment to the Duct System.
10.1 General
Subsequent clauses of the section detail general requirements for chilled water
system.
Page 92 of 417
Mechanical and Electrical Design Guidelines and Specifications
All chilled water pipework, fittings and valves shall conform with the clauses in
“PIPEWORK INSTALLATIONS”.
All pipework of above 150 mm nominal bore and above shall be to BS 3601. All
steel pipework of 65 mm bore and above and all sizes of steel pipework in
ceiling voids and concealed locations shall be welded with butt welded fittings.
All other steel pipework in the range 15 mm to 50 mm nominal bore shall have
screwed malleable iron fittings.
All circulating pumps shall be of the centrifugal, single stage, direct coupled
type, conforming to DIN 24255. The pumps and the dive motors shall be
suitable for Variable Speed drive with isolated bearings. The circulating pumps
shall be on duty/standby basis.
The pump volute, back pull out bearing housing and gland box shall be
constructed from cast iron to BS 1452 GR260. Vertical Inline pumps are also
acceptable.
The impeller shall be constructed from gunmetal to BS 1400. The drive shaft
shall be constructed from high tensile steel.
The drive shaft sleeve shall be constructed from stainless steel to BS 970.
The bearings shall be of the heavy duty, deep grooved ball type and shall be
sealed for life.
The gland seals shall be mechanical, self adjusting bellows with a long life
ceramic seat. The volute shall be fitted with replaceable wear rings.
The casing shall be designed to allow for the removal of the impeller without
disturbing the pipework.
The pump and drive motor shall be mounted on a common base plate.
Unless otherwise indicated the drive motor shall be totally enclosed fan cooled,
IP 54, Class “F”, 1450 rpm.
They shall be sized to cater for expansion and contraction of the chilled water
system, whilst ensuring that the systems are always sealed and pressurized.
Page 93 of 417
Mechanical and Electrical Design Guidelines and Specifications
Units shall be of the pre-charged spill tank type system.
The unit shall be of the packaged type, consisting of chassis, pumps (Duty and
Standby), pressure vessel, spill tank, valves, pipework, fully integral controls,
with steel cubicle with rigid doors. The whole unit shall be delivered to site pre-
charged and fully assembled.
The pumps shall be of the single stage or vertical multi-stage centrifugal type
with close coupled TEFC induction motors running at 2,900 rpm. Pump bodies
shall be cast iron or stainless steel with internals of stainless steel and bronze,
fitted with mechanical seals.
After flushing, the chemical treatment shall immediately be applied and shall
comprise control agents against algae, fungi, bacteria, corrosion, scale and
organic fouling. The Contractor shall provide sufficient chemicals for the entire
12 months defects liability period.
The Contractor will note that the optimum level of 0.7 +/- 0.5 pH is the
acceptable datum to aim for any other reading will be rejected and the
treatment will be repeated.
The pot shall be equipped with conical funnel, non-return valve, air release
cock and drain valve.
Conductivity meter for measurement of the water and initiation of the dosing
equipment.
50 litre capacity polythene chemical dosing tank complete with suitable dosing
pump and low level chemical shut-off switch.
Upon completion of the chemical cleaning the Contractor shall take a sample
of the chilled water and have it tested by an independent laboratory for free
iron and suspended solids. If the results of the analysis indicate the presence
of free iron and suspended solids the chemical cleaning shall be redone at the
Contractors expense.
Page 94 of 417
Mechanical and Electrical Design Guidelines and Specifications
The Contractor shall include in his tender for the complete design, supply ,
installation, testing and commissioning of the systems to the standard and
approval of local Civil Defense. The MEP Sub-contractor shall include for all
labor, materials, tools and tackle, complete with all supports and fixings back
to approve building structural members.
The Contractor shall be responsible for all dimensions and location of other
services, and the correct setting out of the installation.
All fire fighting equipments shall be UL listed and / or FM approved and shall
be approved from Dubai Civil Defense.
All fire fighting equipments shall be installed and tested by approved Dubai
Civil Defense specialist company.
Fire Water Pump Station including but not limited to the following:
(a) Main Fire pump complete with its Electrical Panel and Controllers,
(b) Jockey Pump complete with its electrical panel and controller,
(c) Fire Water Tank- with two partitions.
(d) Inlet and Outlet valves, PRVs, Air Release valves, Drain Valves.
(e) Submersible Pump, Controller, piping, valves, etc. for the Underground Fire
Water Pump station.
(f) Pressure Switches, Level Switches, Flow meters, Valve Position switches
for remote monitoring, all associated cables, instruments, supports, etc. to
fully meet NFPA 20 regulation requirements.
The following standards will be applicable for this specification and contractor
scope of work:
Page 95 of 417
Mechanical and Electrical Design Guidelines and Specifications
11.3 Pipework
HDPE High Density Polyethylene (HDPE) pipes and fittings to ISO 4427 type
PE 100.
A 25 mm diameter automatic air valve shall be fitted at all high nodes of the
system.
All pipes to be selected according the expected pressure and temperature. All pipes
shall be UL/FM approved and shall carry the UL/FM stamp on the materials.
Fire cabinets shall be provide where shown on the drawings in accordance with
this specification.
The fire hose cabinet shall be made of 1.5mm stainless steel mirror type 316L
grade 7 sheet, the color of the mirror shall be decided upon the approval of the
consultant. The cabinet shall be either wall-mounted type or recessed type as
shown on the drawings.
The hose reel drum shall be installed in a cabinet made of stainless steel 316,
mirror type supported with reinforced support arm, which shall be chrome
plated and swing through 180 degrees. Welding of any part on cabinet front
Page 96 of 417
Mechanical and Electrical Design Guidelines and Specifications
shall not be allowed. The hose shall be made up of red, seamless reinforced
with double synthetic textile yarn layer. The working pressure of the hose shall
be 20 bar minimum and bursting pressure shall be 50 bar. The hose reel shall
be in accordance with BS EN 671:01 and AS 1221; the hose shall be wound
on a fabricated steeldrum with circular side plates. The hose reel shall turn on
automatically when 1.5 to 1.8 meters of hose is withdrawn from the reel/drum.
Each hose reel shall be installed and tested to BS EN 671:01 and shall deliver
not less than 0.4 l/s when the two topmost reels are in use simultaneously
providing a jet of approximately 6m in length. Pressure reducing devices shall
be provided whenever necessary to limit the pressure to 6.9 bar.
The reels shall incorporate a valve that automatically turns on the water supply
when more than approximately 3m of hose is unreeled, and shuts off again
when the hose is re-wound onto the reel. A manual shut-off valve of the wheel
type shall also be installed on the service pipe at each hose reel.
An inspection plate shall be supplied with each reel indicating the method of
use in English and Arabic.
The hose reels shall be of a make, approved by the Ministry of the Interior Civil
Defense Department, and shall be supplied through an authorized agent.
Hose reels shall comply with BS 5306 and have an effective arc of operation of
not less than 30m. The hose should be of 25mm internal diameter rubber fire
hose reinforced with double braiding and 30m long. The nozzle shall be of high
impact plastics, jet spray/shut off.
Cabinet type hose reels shall be of the automatic swinging type mounted 1.5m
from floor level and provided with a local isolating valve. Where cabinet
mounted hose reels shall also be suitable for recessed fitting.
Surface type hose reels shall be automatic non-swing pedestal type complete
with local isolation valve, double concave roller hose guide.
The hose reels shall be suitable for working pressures up to 6.9 bar (100 PSI)
and shall be installed in accordance with the manufacturer’s instructions.
Page 97 of 417
Mechanical and Electrical Design Guidelines and Specifications
Landing Valves
Landing valves shall be installed on the standpipe system for the use of Fire
brigade as shown on the drawings. Landing valves shall be oblique pattern
brass chrome plated globe valves, high pressure type to BS 5041 with 65mm,
diameter, bore fitted with 65mm. Instantaneous female coupling to conform to
BS 336 and a brass chrome plated blank cap secured by a suitable length of
chain. The landing valve shall have 65mm Dia. Flanged inlet for attachment to
the dry riser. The valve shall be equipped with spindle not less than 22.2 mm
diameter and fitted with a brass chrome plated hand wheel of about 150mm.
Diameter. Marked with OPEN and CLOSED directions. Opening shall be anti-
clockwise. The whole valve fittings shall be sound construction and
hydraulically tested to a pressure of 20.7 bar.
The breeching piece shall be equipped with a 25mm drain valve to drain the
riser. Al enclosed in an approved stainless steel (AS 304) flush box with wired
glass glazed front panel and:
The box shall be built into the structure with a fall of one in 12, from the rear of
the base to the front of the base.
The physical dimensions of the extinguishers shall be such that they housed
within the cabinet if necessary.
Page 98 of 417
Mechanical and Electrical Design Guidelines and Specifications
The cylinder shall be seamless and extruded of high graded steel to withstand
a test pressure of 250 bar. The extinguisher shall comply with BS EN 3 1-6:96.
The temperature range for safety operation shall range from – 20 to 60 degree.
Fire extinguishers shall be to the approval of the Ministry of the interior, Civil
Defense Department and shall be purchased through an authorized agent.
The Contractor shall provide and install a complete pressure boosting system,
comprising electrically driven main pump, stand-by pump, and an electrically
driven Jockey pump. The pumps shall be of the type indicated in the
Equipment Schedule and shall have a characteristic as defined by NFPA-20
regulations for the hazard being protected.
(a) The Jockey pump should start due to pressure drop in the system through
pressure switch. In case the water demand exceeds the supply capacity of
Jockey pump the main pump should start through the pressure switch to
meet the water demand.
(c) Construction
The pump casing shall be of extra heavy cast iron, with minimum tensile
strength of 30,000 lbs and shall be split parallel to the shaft. Bearing
housing supports, suction and discharge flanges shall be cast, bored and
machined integrally with the lower half casing. Upper and lower half casings
shall be dowelled and bolted together. Removable upper half casing must
permit inspection or removal of the entire rotating assembly without
distributing the piping. Flanges shall be No. 125 ASA Flat Face Suction and
No.250 ASA Flat Face Discharge.
The impeller shall be of Bronze enclosed single opposed suction type both
statically and hydraulically balanced. The impeller shall be keyed to a steel
Page 99 of 417
Mechanical and Electrical Design Guidelines and Specifications
The pump shall be equipped with Bronze renewable throat bushings, casing
rings, and interstage channel ring to reduce casing wear and maintenance
costs. The casing rings and channel rings shall be held by antirotational
pins to permit easy re-installation and reduce down time. Impeller wear
rings are optional and will be of Bronze material. The rotating element shall
be mounted in grease lubricated ball bearings (when temperatures rise
above 225 deg F, Water jackets shall be added). Heavy cast split glands
shall be furnished on each stuffing box design for easy removal for packing
inspection and maintenance. Various mechanical seals can also be
installed. Heavy fabricated steel base (with drip lip) to mount the pump and
driver shall be furnished. Flexible shaft coupling shall be furnished to
connect the driver pump. Coupling shall be enclosed in (standard) coupling
guard.
ii. Flow meter unit shall be provided on the discharge line in order to check
the capacity of the pump set for details of the flowmeter see Section PS
10/26.
The pump bearings shall have an L-10 rating of not less than 50000 hours
based on load ratings and fatigue life. The shaft shall be sealed with a
stuffing box and packing with external water-seal piping. The stuffing box
glands shall exert uniform pressure on the packing.
(e) Engine
The engine shall be equipped with an engine “Hot Start”, battery charger,
dual battery contactors capable of mechanical operation to energize the
starting motor in the event of control circuit failure, and an emergency
manual fuel solenoid valve.
(f) Controller
All relay contacts shall be gold flashed and rated for 10 amps. A vibrating alarm
bell with a 6-inch gong shall be provided.
A Y-strainer shall be provided after the pressure switch connection and before
the drain valve solenoid.
The controller enclosure shall be constructed in accordance with NEMA 12
requirements.
(h) Motor
Comply with PS 10
The MEP Sub-contractor shall supply and install inspectors test valves in
accordance with the NFPA 20 requirements.
Tubes and all items of equipment shall be delivered, stored and maintained in
storage with their open ends effectively plugged, capped or sealed. All fittings,
valves and sundry items shall be stored in clean bins or bagged and stowed in
suitable racks. All such items shall be maintained under weatherproofed cover
to be supplied by the MEP sub-contractor until they are ready for incorporation
in the works. Particular care shall be taken to ensure that electrical equipment
and components are kept clean and dry.
Before installations are handed over or subjected to the inspection and tests
and entire installation shall be thoroughly cleaned, both internally and
externally.
All fire protection installations shall be flushed out with clean water. During the
flushing out provision shall be made to exclude any items of plant, which could
be damaged by the cleaning operation. The entire operation shall be carried out
to the satisfaction of the Engineer. The fire protection system shall be tested in
accordance with the NFPA codes and the relevant standards, with particular
reference to the following:
All testing shall be performed under the work of his section. All services
required for testing shall be a responsibility of the work of this section. The MEP
subcontractor shall notify the Engineer of all tests, 48 hours prior to testing.
The Fire Protection Piping System shall be tested hydrostatically for not less
than 2 hours and at one time the system pressure without any leaks, as
directed by the Local Fire Department.
If the systems are tested in sections, the connection to the previously tested
section shall be included.
All tests that may be required by the local fire authorities shall be performed
under the work of this section in the presence of their representative if so
required.
All leaks shall be corrected and the system re-tested until no leaks are found,
at no cost to the Client. Functional tests of all water flow alarms are a
responsibility of the works of this Section.
When the various systems are completed, operation tests shall be run on all
equipment to demonstrate proper operating conditions. These tests shall be
run under the observation of the Inspector and the Client’s Operating Engineer.
The Client’s Operators shall be instructed during this period. Operation tests
shall be performed under the work of this Section.
General
The Computer Room, Telecommunications Room and electrical Room or as
indicated by DCD shall all be protected with a Clean Agent Fire Extinguishing
System.
The clean agent fire extinguishing system shall comply with the latest edition of
the following standards:
11.13.2 Submittals
The specialist installer shall prepare detailed installation drawings for each
area indicating the agent storage tanks , location of all plant and equipment,
pipe runs including sizes and lengths, controls panels including terminal writing
ports, detectors, conduit runs, manuals all stations, abort stations, audible and
visual alarms, etc.
The specialist installer shall provide auxiliary details and information such as
hydraulic flow calculations from a UL listed computer program, maintenance
panels, door holders special sealing requirements, operation and control
documentation, damper operation, alarm devices, shutdown functions, remote
signaling and agent discharge times.
The system shall provide a clean agent agas (FM 200) concentration of 7% by
volume, minimum.
• After completion of the time delay sequence the agent shall be discharged
and the following shall occur:
3 Audible circuits
Diagnostic LED’s for easy trouble shooting
Solid state filed programmable time delay 0 to 60 seconds. Protective covers
over high voltage terminals
Connections to power a remote annunciation Agent cylinder isolating switch
Cross-zone principle of agent discharge.
This is a dual action device for manual discharge of the agent. The manual
actuation shall by pass the time delay and abort functions, shall cause the
system discharge and shall initiate all the alarm and shut down functions.
An abort stations hall be located next to each manual release switch and shall
be monitored by the control panel. Upon activation of the abort switch a signal
shall be generated at the main control panel producing a visual indication.
Provide 150mm diameter bell, alarm horn and visual alarm strobe lamp with
label attached to strobe lens.
Provide, in Arabic and English, signs are required to comply with NFPA and
Local Civil Defense recommendations at each entrance to the protected areas,
for all manual discharge stations and for each strobe light.
Provide automatic self-closing fire doors at all exits to the protected area. Each
door leaf shall be provided with an electrically actuated magnetic door holder
and door return device.
The exit doors shall close automatically upon receiving a signal from the
control panel. Each door shall also close manually.
Seal all openings in walls, floors and ceilings within each protected area with 2
hours service for all fire protection equipment and devices.
Pipes shall comply with NFPA 2001, section 2-2.3, seamless mild steel
schedule 40 to ASTM (A53) Grd. B, Non-metallic pipes shall not be allowed.
Pipe’s fittings shall comply with NFPA 2001, section 2-2.3, malleable iron rated
at 20 bar to ASTM A-197. All fittings shall be threaded.
Provide for each protected area a separate cylinder bank as required complete
with independent discharge pipework arrangements.
Provide and install gray anodized aluminium agent discharge nozzles providing
a full 3600 discharge pattern. The specialist shall determine the number of
nozzles required.
Provide and install suitable smoke detectors as detailed earlier in this section.
Fire-detection cabling shall be red PVC sheathed MICC and shall be run
surface clipped as recommended by the manufacturer.
All inter-communication and control cable shall be run in fire rated cable and
conduit system.
Each protected area shall be provided with a dedicated control panel providing
the functions as outlined above.
Each panel shall be wall mounted and constructed from 18 gauge sheet steel
with epoxy paint finish. The cabinet shall be suitable for electrical circuits
complete with all safety features as described in the electrical specification.
Tubes and all items of equipment shall be delivered, stored and maintained in
storage with their open ends effectively plugged, capped or sealed. All fittings,
valves and sundry items shall be stored in clean bins or bagged and stowed in
suitable racks. All such items shall be maintained under weatherproofed cover
to be supplied by the MEP sub-contractor until they are ready for incorporation
in the works.
Before installations are handed over or subjected to the inspection and tests
and entire installation shall be thoroughly cleaned, both internally and
externally.
All fire protection installations shall be flushed out with clean water. During the
flushing out provision shall be made to exclude any items of plant, which could
be damaged by the cleaning operation. The entire operation shall be carried out
to the satisfaction of the Engineer. The fire protection system shall be tested in
accordance with the NFPA codes and the relevant standards, with particular
reference to the following:
All testing shall be performed under the work of his section. All services
required for testing shall be a responsibility of the work of this section. The MEP
subcontractor shall notify the Engineer of all tests, 48 hours prior to testing.
The Fire Protection Piping System shall be tested hydrostatically for not less
than 2 hours and at one time the system pressure without any leaks, as
directed by the Local Fire Department. If the systems are tested in sections, the
connection to the previously tested section shall be included.
All tests that may be required by the local fire authorities shall be performed
under the work of this section in the presence of their representative if so
required.
All leaks shall be corrected and the system re-tested until no leaks are found,
at no cost to the Client. Functional tests of all water flow alarms are a
responsibility of the works of this Section.
When the various systems are completed, operation tests shall be run on all
equipment to demonstrate proper operating conditions. These tests shall be
run under the observation of the Inspector and the Client’s Operating Engineer.
The Client’s Operators shall be instructed during this period. Operation tests
shall be performed under the work of this Section.
General
The contract includes for the design, supply and installation, commissioning
and testing of a complete Wet Pipe Automatic Sprinkler System as shown on
the drawings.
The sprinkler system shall comply in every respect with the Rules for Automatic
Sprinkler installation issued by the National Fire Protection Association (NFPA-
13) or the approved Ruling Organizations. The system shall also comply with
the requirements of the local Fire Authority, together with any particular
requirements of U.A.E. Civil Defense Department.
The installation shall be complete with all necessary valves, pressure gauges,
alarms, proving equipment, etc, as required by NFPA-13 Standards.
All zone or sectional valves hall be provided with monitor switches to indicate
closure. The switches shall be inter-connected with the fire alarm panel.
Zoning of the sprinklers shall be similar to that of the fire alarm system.
The sprinkler heads shall be of the spray pattern installed in an upright position
or pendent as may be required. Sprinkler in false ceilings shall be concealed to
ceiling and to architects approval.
The Design Criteria for all sprinklers such as K-factor, type and operating
Shall be flush, low profile, fusible solder automatic sprinklers designed for
installation along with a wall or lintel, supplied along with a clamp on
escutcheon plate finished in a color to architect’s approval. The sprinklers
and lines shall not be spaced too close together in order to prevent an
operating sprinkler form wetting and hereby delaying operation of adjacent
sprinklers.
Sprinkler head guards hall be fitted to all sprinklers. The guards shall be
constructed form metal and shall be of a pattern approved by the Fire Insures.
A control valve set shall be provided for each sprinkler system zone and shall
comprise:
Alarm valve fixed above the main stop valve, on the main supply pipe and
before any connection is taken off.
Alarm devices, including water motor alarm gong, pressure switch. Facilities for
Dial pressure gauges suitable for the water pressures above and below the
alarm valve shall be fitted to the alarm valve set. Each gauge shall be so
arranged that it can be easily removed for testing and checking without shutting
down the water supply.
All stop valves fitted to the installation shall be so constructed that in order to
shut the vale the spindle must turn clockwise. The hand wheels of all stop
valves shall be clearly marked to indicate which direction the wheel is to be
turned to close the valve.
An indication shall also be provided which shows whether the valve is open or
shut.
Each main stop valves shall be secured open by a padlock or riveted strap.
All stop valves shall confirm to |BS 1218, NFPA, or equivalent International
Standard.
The sprinkler system shall be fitted with an approved water motor alarm, which
shall be located at a distance not exceeding 25m from the alarm valve, and at
a height not to exceed 6m above the alarm valve.
The pipe work and fittings used shall be galvanized and to the sizes
determined by the NFPA-13. The pipe work shall be arranged to drain through
a fitting having an orifice not exceeding 3mm in diameter.
The orifice plate may form an integral part of the fitting but shall be
manufactured from a non-ferrous material to prevent the hole from becoming
blocked by corrosion or foreign matter.
Electric alarm pressure switches shall be installed in the system and they shall
be mounted on a vertical branch pie at least 300mm long.
The pressure switch may be of the diaphram bellows or bourdon tube operated
type, and shall be sufficiently sensitive to operate when only on sprinkler is
discharging. The pressure switch shall be provided with volt free contracts to
facilitate monitoring by a Building Management System, ad wired to the main
fire alarm panel. The pressure switches shall be of a type that is approved by
the NFPA.
Pressure gauges shall be fitted to meet the requirements of the LPC. Pressure
gauges shall confirm to BS 1780 or equivalent International Standard. The
maximum reading of the scale shall be 150% of the maximum system pressure
and each scale shall have divisions not exceeding 0.2 bar.
A Fire Service Inlet shall be fitted to the sprinkler systems in accordance with
MFPA regulations or as directed by the Local Fire Authority.
The MEP sub-contractor shall provide and fix in an approved position a plan of
the risk upon which shall be clearly indicated the location of the main stop
valves.
Location plates shall also be fixed on the outside of the Tank Room walls
adjacent to the sprinkler chamber. The location plate shall bear the following
words in raised letters:
11.15.14 Sprinkler
The location plate shall be of cast iron constructed with raised figures and
letters. The figures and letters shall be painted white on a flame red
background. The alarm valve shall be suitably identified.
The MEP sub-contractor shall label each stop valve. The number shall relate to
a framed glass covered valves chart to be supplied and installed in each
sprinkler chamber. The charts shall indicate the function of the valves and shall
be to the FSD and Engineers approval.
All drain lines from test valves, drain down points etc. shall discharge over
suitable and proper drain vent. Each drain vent shall be connected to a 50mm
galvanized mild steel heavy quality drain line which shall discharge over a
suitable gully.
All drain vents, pipe fittings, and support clips used for the drain lines shall be
galvanized.
The MEP Sub-contractor shall provide and install a complete pressure boosting
system, comprising electrically driven main pump, diesel driven stand-by pump
and electrically driven Jockey pump. The pumps shall be of the type indicated
in the Particular Specification and shall have a characteristic as defined by
NFPA-20 regulations for the hazard being protected.
The MEP Sub-contractor shall supply and install inspectors test valves in
accordance with the NFPA 13 requirements.
The MEP sub-contractor shall provide a dedicated sprinkler indication panel for
the complete sprinkler installation which shall have the following facilities:
Schematic diagram showing locations of all major items of plant, i.e. pumps,
control valves, sectionalisation valves, electric alarm pressure switches, etc.
Each item shall be clearly engraved in the National Language and English.
Each electric alarm pressure switch shall have the following indications:- i
Amber Lamp : For fault alarm
ii Red Lamp : For fire alarm
All fault and fire alarm signals shall be sent to the main fire alarm panel and / or
Central Building Management System as required.
Water storage facilities shall be provided to suit the given hazard rating which
shall be calculated on the maximum water flow and time at this flow rate as
indicated by NFPA-20 regulations.
Water tanks shall be provided with a deep suction pit to prevent pump
cavitations and to make full use of the stored volume.
The MEP Sub-contractor shall supply and install inspectors test valves in
accordance with the NFPA requirements.
The MEP sub-contractor shall provide a dedicated indication panel for the
complete fire fighting installation which shall have the following facilities:
Schematic diagram showing locations of all major items of plant, i.e. pumps,
control valves, sectionalisation valves, electric alarm pressure switches, etc.
Each item shall be clearly engraved in the National Language and English.
Each control alarm pressure switch shall have the following indications:
i Green Lamp : For valve open
ii Amber Lamp : For fault alarm, valve
Each electric alarm pressure switch shall have the following indications:-
i Amber Lamp : For fault alarm
ii Red Lamp : For fire alarm
All fault and fire alarm signals shall be sent to the main fire alarm panel and / or
Central Building Management System as required.
Provide and install a complete Fire Pump Set, which shall serve the wet riser
system, comprising electrically driven main pump, diesel driven stand-by pump
and jockey pumps. The main and stand-by pump shall be of end suction
centrifugal type, capable of delivering the scheduled duties. The appropriate
flow rate for engine and pump cooling shall be added to the net duties given.
Each pump shall be fitted with automatic air release valve, discharge pressure
gauge + valve and suction compound pressure/vacuum gauge + valve.
The jockey pump shall be capable of a duty of scheduled duties. Each pump
shall be of the high efficiency vertical multi-stage type direct driven by a 2900
rpm totally enclosed electric motor with class “F” installation and wound for a
400 volts 3 phase 50 Hz. Power supply.
All fire pump used shall be approved from Dubai Civil Defense, the pumping
unit shall be listed by Underwriters Laboratories and FM approved shall meet
all requirements of the National Fire protection Association, Pamphlet No. 20.
The pump shall be given a complete performance test at the factory with
positive suction pressure as per NFPA 20 requirements.
11.15.24 Controls
The Diesel, Electric and Jockey pumps shall be controlled individually with
each having a pressure switch connected to the fire main header via a 15mm
diameter tube.
All pressure switch pipeworks shall be arranged with a test valve and an
upstream drain valve assembly.
The Diesel and Electric pumps shall also be fitted with a back flow by pass and
non-return valve to allow either or both pumps to operate even if the test valve
is inadvertently left isolated.
Each pump set shall have its own individual control panel complying with
requirements of the relevant LPC documents.
The installation shall be complete with all necessary valves, pressure gauges,
alarms, proving equipment, etc, as required by the NFPA-20 rules
All zone or sectional valves shall be provided with monitor switches to indicate
closure. The switches shall be inter-connected with the Fire alarm panel.
11.15.26 Approval
Upon completion of the systems, the specialist contactor and MEP contractor
shall furnish the client a certificate of approval from legally constituted
authorities having jurisdiction, or in lieu thereof, a certified copy of the same.
Upon completion and approval of the systems, the MEP sub-contractor shall
provide an experienced Engineer to instruct the client’s operators in all details
of operating and maintaining the system.
The MEP sub-contractor shall provide three (3) sets of type written operation
instruction, parts list and service manuals for all equipment, wiring diagrams,
control diagrams and test reports, suitably bound. SIGNAGE
Drain valves, test valves, control valves, shall be fitted with approved enameled
signs indicating their use.
The MEP sub-contractor shall hand over prior to the completion of the
works the record drawings and manuals in accordance with contract
specifications and requirements.
12.1 Description
The overall system shall be connected and generate the below I/O for RTA
remote monitoring system :
Water chillers shall operate under the dictates of their own controls to
maintain the specified leaving water temperature. Chiller controls shall be
interlocked with water flow detectors and the chilled water pump panel to
inhibit operation in case of low water flow volume.
(c) Chilled Water Pressurization Unit. The chilled water pressurization set shall
be equipped with its own integral control panel for control of duty/standby
pumps in accordance with line pressure. A duty selector switch shall be
provided along with pump fail indication, high water pressure alarm and low
water pressure alarm.
(d) Fan Coil Units. Chilled water fan coil units shall be provided with a
combined wall mounted thermostat and 3-speed controller with “off” switch.
The thermostat shall operate a two position, electrically operated 3-way
valve on the chilled water return line. A regulating valve shall be provided in
the bypass line to ensure chilled water flow volumes remain constant with
the control valve in either the full flow or bypass positions.
(e) Air Handling Units. Air handling units shall be provided with a local control
and starter panel. Separate sections of the panel shall house controls and
motor starter equipment. The panel shall be a wall mounted steel enclosure
to IP-54 standard, finished with epoxy powder coating and fully labelled.
Fan motor shall be provided with an on/off/auto selector switch on the face
of the panel. In the auto position, the fan shall start under the dictates of a 7
day, 24 hour, electronic, programmable time clock provided within the
panel. Run and trip lamps shall be provided on the panel along with an ‘air
flow fail’ lamp to be activated via a pressure differential switch located
between the fan inlet and outlet ducts. The panel shall be provided with
power on lamp and door interlocked isolator.
Control wiring shall be fully coded and identified and installed in conduit
to the standards of the electrical specification requirement.
1. Air-Flow Switches. Each supply fan and each extract fan shall be
equipped with an air-flow switch which shall indicate to the ventilation
control panel. If fans are required to start either manually or
automatically and air flow is not confirmed within 60 seconds of the
starter closing an alarm shall be initiated and air-flow fail lamp
illuminated for the fan concerned.
initiated.
• Open motorized damper. A limit switch indicates to the MCC that
damper is 100 percent open, and allows fan to start.
• If air flow not confirmed within 60 seconds, initiate alarm (visual
and audible) at the VCIP.
All valves up to 40mm Nominal Diameter to be of the threaded type, with gun
metal bodies. Plug and spindles to be made from stainless steel. A neck to be
provided for fitting of the actuator to the valve via a threaded coupling. A
Specifications
All valves over 40mm (inclusive) to be of the flanged type with cast iron bodies.
Spindles to be from stainless steel and the bodies to be from GG.20 cast iron or
equivalent. The parabolic control plug to be made from brass or gun metal. All
valves to be fitted to the main system with counter flanges and gaskets. All
valves used for chilled water systems are to be protected against corrosion
from condensation by means of two layers of paint and suitable lagging. Valves
to be suitable for mounting in any orientation except upside down.
Specifications
Nominal stroke: 20mm for up to DN 80 40mm for DN 100 – 150
All valves up to 40mm nominal diameter to be fitted with electric actuators with
spring returns of equal percentage or linear flow characteristic. Actuators to be
maintenance free with reversible motors and with stroke indication. If fitted, the
gear train to be of blocking-proof design which can be easily disengaged. A
facility on the housing to provide selector plug for linear or equal percentage
flow characteristic.
Specifications
Specifications
12.17 Sensors
Where indicated room temperature sensors are to be provided for input to the
terminal equipment controllers. Each sensor will incorporate a thermistor
element, and a connection for a plug-in-portable operator’s terminal, for access
to the controller.
Deliver the selected set point or as position signal. The output range to
correspond to the setting range.
Specifications
Operating voltage: 24 V A.C. ± 20% Input signal: 0 – 10 V D.C.
Output signal: 0 – 10 V D.C.
Specifications
Operating voltage: 24V A.C. ± 20% Output signal: 0 – 10 V D.C.
Static pressure range: As required
Medium temperature: 50º C Max.
Permissible operating temp: - 25 to 65º C
Vibration and corrosion resistant, for wall, immersion, or duct mounting as
required:
Platinum.
Mounting to be via a mounting flange which may be adjustable and all terminal
connections to be inside the housing. Cable entry to be via a purpose made
gland.
Flood sensor shall be provided in elevator pit and interfaced with RTA
monitoring system , the sensor shall be of 316LSS / plastic for wetted parts.
(a) This Section specifies the requirements for manufacture and installation of
Submersible Pumps as per equipment schedule.
13.2 Submittals
All seal materials shall be compatible with and resistant to the fluid being
handled. There shall be two back-to-back mechanical seals provided to seal off
the motor from the pump. The upper seal shall be oil lubricated, its rotating
component shall be of carbon whilst its fixed component, like both parts of the
lower seal, shall be made from tungsten carbide or silicon.
The Pump shaft and motor shaft shall be the same unit. Couplings shall not be
acceptable.
Bearings shall be capable of taking the static weight of the rotating parts and
any thrust produced by the operation of the pump. Bearings shall be of the
antifriction type designed for B10 life of 50 000 hours per NFBMA test
procedures. The bearing between the motor rotor and the impeller shall be
lubricated by an internal oil supply, which shall also serve to cool shaft seals.
Replaceable wear rings shall be provided for the casing and/or impeller as per
Engineer’s approval. Wear rings shall be constructed of suitable wear resistant
material of minimum 300 Brinell hardness.
sump without first undoing nuts and bolts or any other fixing arrangement. The
pump shall be automatically coupled to the delivery pipework, by its own
weight, during the lowering operation.
The pump motor shall be rated for a minimum margin on absorbed power of
10% based on maximum absorbed power at maximum design discharge and
suitably de-rated for continuous operation in a 55 deg. C ambient temperature.
Motor shall be squirrel cage, induction, and shall have permanently lubricated
bearings and mechanical seal. Motor shall have lower ball bearing for thrust
that shall be capable of taking drive shaft-weights where necessary and upper
sleeve bearing for radial loads.
Power and signal cables shall be connected to the motor through a watertight
terminal box, sealed from the motor. Cables shall be brought out directly from
the well in un-jointed run. Cables shall be securely anchored to the wellhead so
as to avoid any stress, the anchor being capable of ready release.
If required, due to the longer distance between the pump-motor and motor
control cubicle a junction box shall be provided out side the well, for splicing the
motor cables with the circuit cable.
13.10 Examination
(a) Verify that dimensions are as illustrated by the manufacturer.
(b) Verify that proper power supply is available.
13.11 Installation
(a) Install in accordance with the manufacturers’ instructions.
(b) Co-ordinate installation of components of the pump, gauges valves and
appurtenances.
13.12 Demonstration
(a) Specifications Contract Closeout, Starting of Systems. Demonstrating
installed work.
(b) Submit integrated step-by-step test procedure for approval 30 days prior to
start of demonstration.
1. Arrange meeting prior to demonstration with representatives of the
Owner and Engineer.
2. Perform visual inspection and overall review of system installed.
(a) Furnish Employer with the following extra parts for each pump:
1. one complete set of bearings
2. one complete set of mechanical seal
3. one set of wear rings
(b) Furnish Employer with the following extra parts for each pump type:
14.1 General
The Air Conditioning Contractor shall supply, deliver, install, set to work and
commission the VRF Variable Refrigerant Flow systems or VRV system and
equipment as detailed in this section of the specification, as shown on the
Tender drawings and listed in the Schedule at the end of this section.
The VRF system will control flow of refrigerant through the fan coil units, by
means of an electronic expansion valve fitted in each indoor unit.
The VRF system will have the ability to sustain refrigerant piping lengths with a
level difference as shown in the drawings, between fan coil units and
condensing unit if the outdoor unit is located above the highest level indoor
unit. An option shall be available to increase the level difference of the pipe
work between fan coil units and condensing unit if the outdoor unit is located
above the lowest level indoor unit.
The VRF system shall operate with Refrigerant R410A or other environmental
friendly refrigerator as per DM green building regulations.
All equipment shall be run tested in accordance with the following procedures
prior to leaving place of manufacture.
The unit casing shall be manufactured from polyester powder coated baked
enamel finish sheet steel in order to have a high corrosion resistance and to
protect against salt laden environment close to where the units may be
installed. The air outlet shall have plastic coated wire guards.
Prior to delivery to site, each condensing unit shall be clearly identified with
nameplate, securely attach on each condensing unit showing manufacturer
name, serial and model number.
Condensing unit noise level shall not exceed 70dBa. Condensing unit shall be
tested as per AHRI standard.
The outdoor units shall have inverter driven compressor (Variable Frequency
Drive Compressors Scroll Compressors), electronically controlled and capable
of changing speed linearly to follow the variation in cooling requirements.
The unit shall offer EER of 3.5 and above as per ASHRAE ambient conditions,
DM green building regulations, and comply with Emirates Authority for
standardization& metallurgy.
removable panels.
The outside unit shall be connected to max allowed indoor units as per
manufacturer recommendations, the total cooling load shall be suitable to total
connected fan coil unit capacity with safety factor, selection shall according to
manufacturer’s software, the software shall be certified.
High capacity units shall have two scroll compressors, and will be capable of
operating on one compressor under emergency condition in case the one
compressor fails.
The lubrication oil of the compressor shall be fed through the centre of the
crankshaft and then across the complete area of the scrolls from the centre
outwards to ensure the complete contact area is positively lubricated
maximizing compressor efficiency and minimizing wear and tear.
Condensing unit oil control shall be through oil separators and oil return control
logic.
The outdoor unit fan motor shall be hi efficiency BLDC motor of insulation class
B and shall operate electronically by sensing operational temperatures,
pressures and ambient temperature and monitoring the dictates of the indoor
units.
The condensing unit fan shall be propeller type. The fan will be capable of
overcoming of external static pressure. The units shall be capable of being
combined to provide multi systems using combinations of two or three outdoor
units connected to give the capability of higher capacities.
Condensing unit casing thickness shall be min 0.8 mm. The outdoor unit casing
shall be weatherproof with epoxy coated galvanized steel. The cabinet shall be
exterior enamel paint finish and weather resistant. The fins shall be coated with
hydrophilic coating to avoid corrosion and marine weather.
All refrigerant connections both internal within the unit and the external
connections to the indoor units shall be brazed.
The unit shall be capable of carrying out automatically the calculated required
additional refrigerant charge necessary to operate the system within its
optimum efficiency. This cycle shall be completely automatic and provide a
warning to the service technician to indicate when charging has been
completed or the charging cylinder is empty.
The refrigerant cycle shall not rely upon float valves, level switches or weighed
input of the refrigerant.
capable of being used at any time during the life of the system for any
alterations or service operations which may be required.
The condensing unit coil shall be pressurized 38 bar for a period of 24hours, all
the condensing units shall be factory tested.
Indoor FCU shall comprising of filter, cooling coil and fan assemblies capable
of required duties when running at a fan speed to meet the acoustic
requirements of this specification. Acoustic figures for each unit shall be
provided to the engineer before the units are ordered.
Unit shall be selected to meet required duty and noise levels when operating
on medium speed, all the FCU’s shall be factory tested. FCU testing shall be
tested as per AHRI standard.
The ducted fan coil unit, its fan external static pressure should be suitable to
calculated pressure at highest speed. However, the unit static pressure can be
adjusted (at various speeds) to match the static pressure of the duct connected
to that unit.
Where required a condensate lift pump shall be provided within the unit and
shall be capable of discharging above the drain outlet.
The unit casing shall be manufactured from galvanized steel plate and shall be
fully insulated. All insulated shall be as per UAE fire and life safety code latest.
. Facility shall be provided for duct connection for introduction of fresh air to the
unit and branch ductwork from the unit. The return air to the unit shall be
through the back of the unit as standard.
The heat exchanger coils will be manufactured from copper tubes and
aluminum fins. It shall have electronic expansion valve to control refrigerant
flow rate in response to the load variation in the conditioned space. The
expansion valve shall be controlled by an integral computerized PID control
system to maintain correct room temperature.
The unit casing shall be manufactured from heat resistant plastic. The casing
color shall be White. The back plate and the support frames shall be
manufactured from galvanized steel plate.
The fan shall be multi blade cross flow type, statically and dynamically
balanced to ensure low noise and vibration free operation.
The heat exchanger coils will be manufactured from copper tubes and
aluminum fins. It shall have electronic expansion valve to control refrigerant
flow rate in response to the load variation in the conditioned space.
The air filters shall be incorporated within the unit and shall be washable resin
net type.
The unit casing shall be manufactured from galvanized steel plate with internal
insulation. The fresh air shall be introduced through the back of the unit as
standard.
The fan shall be centrifugal fans with the dual suction multi blade type,
statically and dynamically balanced to ensure low noise and vibration free
operation.
The motor shall be three speed BLDC motor with insulation class E.
The heat exchanger coils will be manufactured from copper tubes and
aluminium fins. The coil shall be 3 row coil with fin pitch of 2.0 mm.
The copper tubing shall be suitably selected with a wall thickness capable of
withstanding the system operating pressures on Refrigerant R410A, all as
described within the outdoor unit’s installation manual.
Pipework shall be supported and not secured at regular intervals not exceeding
1.5m.
Due care and attention shall be taken at all times to allow pipework to freely
expand and contract naturally.
Copper pipe joints shall be silver brazed connection made under nitrogen flow
while brazing. The copper pipe shall be pressurized to 38 bar for a period of
24hours.
All the copper pipes shall be pressure tested at 1.5 times of working pressure.
The VRF control system will analyze the data from VRF equipment
continuously and in most of cases will alert before the equipment actually
breaks down. In this way, most of the failures can be predicted and possible
down time reduced to an absolute minimum.
The system will continuously check the cleanliness of the system filters and
heat exchangers. Furthermore, it has to manage a wide range of data (like
pressures, temperatures, running hours, etc.) in order to let VRF equipment run
as efficiently and trouble free as possible. This will also prevent equipment
from consuming too much energy.
15 ELEVATORS
15.1 General
The contractor shall supply, install, test and commission and hand over the
complete elevator installation as specified
The elevator system shall be equipped with gearless traction machinery with
permanent magnetic synchronous motor, elevator cars, solid state control
systems and all other equipment and accessories required to provide a
complete, modern, durable and efficient vertical transport system.
All the electrical equipment shall be compatible with the available electrical
system of the building, as specified under electrical section.
The contractor shall also give notice that any fault notified will receive
immediate attention on the day of the notification.
The elevator shall be equipped with variable voltage and variable frequency
controlled gearless permanent magnetic synchronous motor, having smooth
speed time characteristics.
All rotating parts shall be statically and dynamically balanced to ensure smooth
running.
All the rotating electrical machinery shall be fitted with microtherms, to provide
overload protection.
The winding insulation levels of the motors shall be of insulation class ‘b’.
The variable voltage, variable frequency motor drive vvvf unit will control the
motor speed using a microprocessor.
The VVVF system will be provided with a converter which performs ac-to-dc
conversion and an inverter which is designed to invert dc to three-phase
variable voltage variable frequency ac. The inverter will give an output of
sinusoidal current with zero [0] through fifty [50] hertz by application of pulse
width modulation technology.
The inverter will control voltage and frequency continuously and accurately in
accordance with speed command signal which is performed by a
microprocessor in the elevator controller.
Protective devices will ensure to open the main circuit between the VVVF unit
and the motor of the traction machine to stop the elevator when one of the
following conditions occurs:
The control system will consist of the VVVF motor drive unit and a
computerized controller. a computer-controlled regulator will control the car
speed by comparing the actual car speed detected by a pulse-rotary encoder
with an ideal speed pattern generated by a microprocessor.
While the car is accelerating, the ideal accelerating pattern will be generated by
the microprocessor to obtain the smooth and optimum acceleration.
While the car is decelerating, the microprocessor will calculate and provide the
ideal speed pattern to obtain the comfortable and stable riding performance.
The control system shall have provision to capture all the regenerative power
including braking power. The control system should be suitable to recover all
the possible energy recovery, thereby reducing the energy consumption.
A) GUIDE RAILS
For smooth running of the counter weight and the elevator car, guide rails with
steel tee sections shall be installed, covering the entire height of the elevator
shaft. the rails shall rest on the hoistway pit to prevent exerting any physical
forces on hoist way ceiling or walls of the building.
B) Hoisting Ropes
Bright steel wire ropes with fibre cores of adequate cross-section manufactured
or steel wire ropes with adequate cross-section, manufactured.
C) Governor Rope
These shall be manufactured similar to hoisting ropes. the two ends shall be
securely linked to the car and attached to the safety gear operating level. The
governor ropes shall be tensioned by a weight-loaded device located in the pit.
D) Counterweight
Cast iron blocks enclosed in a steel framework shall be provided to balance the
weight of the car and the specified capacity.
The travelling cables shall be 450V/750V grade multi-core with stranded high
conductivity copper conductors, especially designed for elevator duty. these
cables shall be properly supported by retaining straps and individual cable
clamps.
The gradual type safety system, comprising of a close loop roping system,
over-speed centrifugal governor, safety gear equipment etc. shall be provided.
The operation of the system shall be such that if the car over speed in the
downward direction, the governor jaws shall trip, operating the safety gear. it
shall, in sequence, cut off the motor power supply, apply normal brakes and
engage the safety gear gibes when the safety gear gibes engage with the car
guides. it shall apply a constant retarding force to bring the car to a gradual and
A) Over Travel
Over travel limit switches shall be provided at the top and bottom of the
terminal landings to disconnect the power supply and apply brakes to bring the
car to safe stop position in the event of an over travel in either direction.
When the fireman's switch activated during a fire, all calls are cancelled and the
designated car returns immediately to a specified floor. to facilitate rescue
afterwards, the car responds only to car calls
The car operating panel of each elevator shall contain the following:
Operating buttons numbered to correspond to the landing served with
acknowledge light for each button.
- Emergency call button.
- Door open and door close buttons.
- Intercom station.
- Overload indicating lamp with buzzer.
- VOIP Communication
- Braille Type Control Buttons
15.10 Electrical Installation of Elevators
Distribution equipment shall contain all protection equipment for motors and
circuits. these shall include overload protection, short-circuit protection, single
phasing protection, etc. as appropriate.
A. Main Specifications
Type : Electric Elevator (Machine Room Less)
Standard : EN 81-20, EN 81-50 and IBC
No. of Stops 2
No. of Opening : 2 (Same/Opposite line as per site condition)
Floor designation : 1M / sec.
Drive Controls : VVVF (Variable Voltage Variable Frequency) Inverter
Operation : Full Selective Collective Arrangements.
Total Travel : As per site condition
T. Cabin:
U. Doors:
i. Car Doors
Type : 2 Panel center Opening
Finish : Tempered Glass.
Door safety : Infrared light beam for full length of door to detect
passenger or object
Operating type : VVVF (Variable Voltage Variable Frequency) inverter
control
X. Jambs:
16.1 GENERAL
The objectives and key features of the telemetry system will be as follows:
B. To provide operational data for both normal and fault conditions including the
initiation of alarms in order to minimize the frequency of visits and to provide a
prompt response to faults.
C. To collect, store and process operational data for management purposes The
system shall make use of the public telephone network, if available or through
GPRS.
The Contractor will be provided with outline requirements for the system and
will be required to then offer detailed proposals and specifications for the plant
and equipment to be supplied.
The specifications, plant and equipment etc. shall be subject to the approval of
both the Employer and the Engineer. During the commissioning/start up period
of the system it will be necessary to provide appropriate training and instruction
in the operation and maintenance of the system for the Employer's operations
staff.
16.2.1 GENERAL
The remote terminal units shall be of modular construction and housed in wall
or floor mounting cabinets dust and damp proof to IP 54. The cabinets shall
house the local UPS or battery backup supply and marshalling terminal section
for interfacing and connection with the master station, communication links and
field equipment. Where transducer remote electronic equipment is provided eg
ultrasonic level measuring devices may be incorporated within the remote
terminal unit cabinet. Cabinet and panel arrangements shall be submitted for
approval by the Engineer.
Each remote terminal unit shall be able to accept at least two or more I/O
modules of each type without requiring replacement of the original equipment.
16.2.3 HARDWARE
The remote terminal units shall be intelligent devices that can collect data,
generate alarms, perform process and control functions. The microprocessor
based remote terminal unit will be the main device used to control loops in
each process or plant area. The remote terminal units shall be able to receive
analogue and digital inputs from the filed, perform processing and alarm
checking, perform the algorithms controls and output to various equipments.
Each remote terminal units shall be sized for controlling the required
inputs/outputs and future expansion.
The program and data held within the memory shall remain intact and error free
if all external power is removed from the remote terminal unit for a minimum
period of two weeks.
The Contactor shall supply UPS and/or batteries for each RTU with enough
capacity to maintain full power to the RTU for 4 hours after a power failure. The
UPS system shall be integral to the RTU. The batteries shall be of a sealed
maintenance free type.
All field connections shall be made in terminal blocks located for easy access.
They shall be clearly marked and identified. Terminals carrying voltages in
excess of 24V shall be fully shrouded. All terminals shall be of the flip up
isolator type with test points.
The connection to other devices will use modules ASCII or remote terminal
units protocols as standard, however details of other protocols available are to
be included within the tender, Each remote terminal unit shall support peer to
peer communications, either directly or via the Master Station System.
LED’s indicating status of input and output digital signals shall be provided on
the input/output modules.
RTU’s shall be configured such that a single RTU or RTU module failure will
not interrupt or degrade plant monitoring and control functions.
The RTU shall be capable of processing locally input plant information before
transmitting it to the master station.
The software programs shall be written such that they facilitate easy alterations
and additions. Structured programming techniques shall be followed and
accompanied by flow diagrams.
Total internal scan time interval for all inputs and outputs in an RTU shall not
exceed 1sec.
The RTU shall operate on a report by exception basis. The RTU’s shall have
sophisticated in built control facilities to permit control loop configuration using
simple building blocks. These blocks shall sequence control, three term control
and other control routine components as required.
The RTU’s shall be standalone capability able to continue monitoring plant and
executing control loops if the communication link to the master station fails. In
the event of such a failure the RTU shall log all alarms and required analogues
until all the tool memory is filled. When the communication link is restored the
RTU will automatically upload the logged data to the archiving system.
The RTU’s shall have a watchdog function and full self-diagnostics capable of
detecting and reporting faults to the master station and displayed locally. The
Contractor shall program the RTU’S fully under this Contract. It shall be
possible to modify the programs remotely by downloading from the master
station.
The data transfer system shall be self monitoring such that any equipment or
line failure shall be displayed at both ends. The protocol used shall safeguard
against false data transmission, allow for error detection, recovery, failure
detection and initiate switchover the redundant data highway. A diagnostic
routine shall be included to monitor the highway performance. Data protocol
and diagnostics shall be fully documented.
Within the confines of the pump station site a hard wired serial communications
link shall be utilized.
16.4.1.1 Inputs/Outputs
General
All process I/O and plant interface boards shall comply with the following:
b) Hot removal of I/O modules shall be possible without special tools. Digitals
inputs shall meet the following requirements:
(1) Alarms: in the healthy condition the contracts shall be closed with
the relay coil energized: in the alarm condition the contacts shall
be opened with the relay energized.
(2) States: contacts shall be open with relay coil de-energised in the
off condition and closed in the on condition.
(3) Two bit digital eg valve position: One contact shall close when the
plant is in one state and a second contact shall close when the
plant is in the opposite state.
Input impedance shall be greater than 1 M for voltage inputs. ADC conversion
at ten times per second shall be 12 bit, system accuracy + 0.2% of span.
All digital outputs shall be optically isolated and matched to the new and
existing plant requirements.
In general all analogue outputs shall be 4-20 mA or 1-5 V dc., selectable and
drive a maximum loop impedance of 60 for current outputs and 2000 for
voltage outputs.
The signal earth shall be separate from the system main earth. DAC
conversion shall be of 12 bit, system accuracy + 0.2% of span.
16.6.1 General
Before dispatch from the manufacturers’ work each item of hardware software
and related components shall be tested in accordance with the relevant British
Standard or Code of Practice. In the absence of British Standard or Code of
Practice these shall be performed in a manner subject to the approval of the
Engineers and witnessed and approved by the Engineer or his representative.
A test plant shall be produced by the Contractor which shall indicate a logical
step by step schedule comprising step, action and reaction.
The means of fault detection and diagnostic provided by the system software
shall be validated. This will involves making provision for including a sufficient
variety of faults and out- of-range conditions in the system to ensure the
detection processes are adequately tested.
16.7 IMPLEMENTATION
16.1 Installation
The Employer will use their best endeavors to allow the Contractor an
uninterrupted installation and commissioning programme. However, they
reserve the right at all items to take full control of the Site where necessary.
The Contractor shall include for the supply of all spanners, keys, special tools,
gauges and all other electronic and calibration tools required for the efficient
installation testing, commissioning and operation of the plant.
16.2 Training
A. Introduction
The entire cost of the complete training program, except per diem expenses for
Employers personnel to attend the training program, shall be responsibility of
The system specialist shall submit information on the training program for
approval prior to shipment of the equipment. This submittal shall include course
outline, time required, courses schedule, sample coursebook and instructor
qualification information for each level. The system specialist shall provide a
coursebook on each course available to every person taking the courses listed
herein. The coursebook shall be of sufficient detail to enable trainees at a later
date review in detail the major topics of the course.
The maintenance training program shall be developed for personnel that have
some electronics maintenance and repair experience and a general knowledge
of computer systems, but shall not assume any familiarity with the specific
hardware furnished. The following subjects shall be covred as a minimum.
The operation training program shall include the following topics as a minimum.
The Client & Engineer or their representative shall attend the inspection and
tests before setting of work.
These tests shall be carried out after commissioning and be a repeat of the
functional tests performed at the system specialist premises. This shall include
operating the equipment in a variety of modes and sequences determined by
the site inspection and testing documents.
After commissioning and site inspection and testing the equipment shall be set
to work by the Contractor in agreement with the Engineer. Setting to work
includes connecting to the master station and operating the plant but not
repeating the site acceptance tests.
17.1.1 SUMMARY
(a) This section specifies the requirements in general for supply and
installation of electrical equipment, items, accessories etc. for a
complete operational system as a part of the Project.
17.1.2 REFERENCES
(a) All supplies and services offered in response to this specification shall
conform to the latest standards.
(b) The design, equipment and installation requirements shall comply with
the latest editions of standards and recommendations laid down by
the following:
(d) The Scope of Work under this project shall include the following major
elements of work.
all respects. This shall also include all the cable trays, conduits,
GRP/ uPVC ducts, concrete pull pits, cable support systems,
trenches, etc. required for proper installation of all the cables.
17.1.4 APPLICABILITY
(a) The Dubai Electricity and Water Authority (DEWA) will provide the
electricity supply unless it is specified to be connected from the
existing sources in the project area. The exact characteristics,
including fault levels, shall be obtained from the Department and
suitably rated equipment shall be provided in full compliance with their
specific requirements. For bidding purposes, the supply characteristics
shall be taken as follows: -
(a) The climate in Dubai in the summer months is hot and humid and a
humidity of 100 percent at 50 degree Celsius has been recorded.
(b) Climate
1. violent sand and dust storms of several hours duration occur and
even on comparatively still days, fine dust is carried in suspension
in the atmosphere.
2. all apparatus and equipment shall, therefore, be so designed and
constructed that they operate satisfactorily and without any
deleterious effect for prolonged and continuous periods in the
(c) The equipment shall be designed and installed in accordance with the
16th Edition of the IEE Regulations.
(d) A front clearance of minimum 900mm shall be provided between the
MCC panel largest door opened at right angle and any wall or
immovable structure.
(a) Kilowatt-hour meters for loads less than 50kW (100Amp) shall be
directly connected. For loads more than 50kW the kilowatt-hour
meters shall be connected through current transformers (CT). The
technical specification shall be similar to those as required by Dubai
Electricity and Water Authority (DEWA). The current transformer ratio
shall be from one of the following, depending on the connected load:
1. 2000/5
2. 1000/5
3. 300/5
4. 200/5
(b) Indicating Ammeters and Voltmeters shall have full-scale deflection to
240 degree.
(c) Phase failure protection shall be provided in the Incoming circuit.
(d) Test switches shall be provided for indicating lamps.
(e) Regulated battery chargers shall be included at RTU and PLC
locations.
(f) A Beacon Alarm lamp (outside the plant room or external kiosk) shall
be provided at plant location to indicate emergency situation.
(g) Secondary/integral Distribution Boards shall be provided with fixed
type busbars and not combed type.
(h) Automatic transfer switch and Main transfer switch (ATS/MTS) shall
be installed inside generator control cubicle.
(i) Grounding resistance for lightning protection system shall not exceed
10 ohms.
(j) An over all power factor correction capacitor bank shall be provided
for smaller inductive loads, instead of individual load. The capacitor
bank shall be connected on the load side of the incomer circuit
breaker and prior to the plant protection equipment. Over all correction
shall not be less than 0.93.
(k) No less than 60cm space shall be provided behind and on sides of
floor mounted monitoring and control panels.
(l) All outdoor switches and outlets shall be metallic, dust and water-
proof; ingress protection minimum to IP 65.
(m) Emergency push-buttons for installation inside wet well, shall be
water-proof and protected to IP 68.
(n) The finished paint color for plants and equipment shall be in
accordance with 18 E 51 of BS 4800.
(o) All outdoor equipment and panels shall be provided with sunshade as
per the requirement of the manufacturer.
(a) Motor
Motor output ratings as indicated on the drawing or elsewhere are
approximate. Motor rating shall cover the full operating range of the
pump without being overloaded at any stage. Motors shall be rated
according to pump shaft power requirement as per the pump
manufacturer, derated for ambient condition, shall have 1.15 service
factor, 10 percent spare capacity and other requirements as per this
section. Protection and control equipment shall be rated accordingly.
(c) Power Connection
The Contractor shall take into account of all the civil/mechanical works
associated with installation of MCC panels, indoor and outdoor cabling
works, entry ducts, relocation/refurbishment of MCC panels or cable
trench modification in the project sites including removal of existing
facilities, if any.
Provide split type air conditioning for cooling of the MCC panel as
required. The design shall provide effective cooling to all the
controllers and efficient air-circulation ensuring temperature and
humidity as specified in mechanical equipment specifications.
(i) When specified, GRP kiosk to house the MCC panel for outdoor
installations, provide FCU inside the housing and place the
(j) The cooling requirement shall be based on the heat developed by the
speed controllers, installed equipment and as recommended by the
panel manufacturer.
(k) Provide proper sealing to the exiting pipes suitable for the IP
requirements as specified.
(a) All electrical equipment shall meet the overall project requirements.
(a) All electrical equipment shall match the overall project performance
requirements.
17.1.12 WORKMANSHIP
(a) The entire work provided in this specification shall be constructed and
finished in every respect in a workmanlike and substantial manner.
The Contractor shall provide the system in accordance with the best
trade practice and to the satisfaction of the Engineer.
(b) Keep others fully informed as to the shape, size and position of all
openings required for apparatus and give full information sufficiently in
advance of the work so that all openings may be built in advance.
Provide and install all sleeves, supports, etc., hereinafter specified or
required.
(c) Obtain detailed information from the manufacturers of apparatus as to
the proper method of installing and connecting same. Obtain all
information from others, which may be necessary to facilitate work and
the completion of the whole Project.
(d) Provide the services of an experienced foreman, who shall be
continuously in charge of the erection of the electrical work, together
with all necessary skilled workmen, helpers and laborers, required to
properly unload, transfer, erect and connect up, adjust, start, operate
and test the system.
(e) Before installing any work, verify that it does not interfere with
clearance required for other work. Notice of adverse conditions shall
be forwarded in writing to the Engineer before any work in question is
installed. If notification is not made, and work installed causes
interference with the contemplated design, make such changes in his
work as directed by the Engineer to permit the installation of all work
of the Project, at no additional cost to the Client.
(f) Raceways shall be run as straight and direct as possible in general
forming right angles with or parallel with walls or piping and neatly
spaced, with risers erected plumb and true, maintain a clearance of at
least 25 mm between finished coverings and adjoining work.
Approved ceiling height shall be obtained from Architectural Drawings.
(g) All equipment and accessories shall operate without objectionable
noise or vibration. Should operation of any of the equipment or
systems produce noise or vibration which is, in the opinion of the
Engineer objectionable, make change in equipment and do all work
necessary to eliminate the objectionable noise or vibration at no
additional cost to the Client.
(a) The contractor is deemed to have visited and inspected the site to
familiarize himself with the existing site conditions and services at
tender stage.
(b) The contractor shall obtain the existing services record drawings from
DEWA and various utility services departments (i.e. Etisalat, Town
Planning Services Department, etc).
(c) Co-ordination between Design and Shop drawings, work on site and
existing services shall be carried out by the Contractor.
(d) The Contractor shall be fully responsible for any damages to the
existing services including repairs, and penalties imposed by the
concerned parties etc and for removing any site obstacles such as
underground cables, pipes, civil works etc. which is obstructing his
work on site.
(e) The Contractor shall also be responsible for liaison with DEWA and
Etisalat and all other government utility departments to disconnect the
existing services supply to the existing site prior to demolishing.
(a) The indication and/or description of any item on the Drawings or in the
Specification, unless otherwise specifically stated, imply an instruction
to supply and fix such items.
(b) Notes on Drawings referring to individual items of work take
precedence over the Specification.
(c) Drawings show the general run of cables, raceways, etc. and the
approximate location of equipment and utilities; symbols and
schematic diagrams are of no dimensional significance. Obtain from
the Engineer dimensions not shown on, or which cannot be
determined from Drawings. Do not scale drawings to obtain locations.
(d) Notify the Engineer of conflicting requirements. Where departures
from the drawings are deemed necessary, details of such departure
and reasons thereupon shall be submitted to the Engineer for
approval.
(e) No such departure shall be made without prior written approval of the
Engineer.
(a) The term 'shop drawings' includes fabrication, erection, layout and
setting out drawings; manufacturer's standard drawings, schedules;
descriptive literature, illustrations, catalogues and brochures;
performance and test data; wiring and control diagrams and other
drawings and descriptive data pertaining to materials, equipment,
raceway systems, control systems and methods of construction as
required to show that materials, equipment and systems and position
thereof, conform to the Contract Documents. The term 'manufactured'
applies to standard units usually mass-produced. The term
'fabricated' means items specifically assembled or made out of
selected materials to meet individual design requirements.
(b) Shop drawings shall establish actual detail of all manufactured or
fabricated items, indicate proper relation to adjoining work, amplify
design details of electrical equipment in proper relation to physical
spaces in the structure, and incorporate minor changes of design or
construction to suit actual conditions.
(c) The Contractor shall submit for approval, and obtain in due time to
conform to the Contract Program, all shop and installation drawings
based on the design drawings approved by the DEWA and all other
relevant Municipality and Government Authorities.
(d) The Contractor, after being awarded the Contract, shall prepare and
submit shop drawings submittal schedule within 30 days of Contract
Award. Shop drawings shall be submitted with such promptness as to
cause no delay in his own work or to any other Contractor. No
extensions of time will be granted because of failure to have shop
drawings submitted in ample time to allow for processing, in
accordance with the submittal schedule.
(e) Provide shop drawings, to a scale not smaller than the corresponding
layout drawings, showing the following and obtain approval before
commencing work:
1. exact runs and sizes of conduits, ducts, cables, cable trays and
trunking.
2. layout drawings for each separate electrical installation showing
the actual locations of points, suitably identified, the locations of
switchgear, switchboards, motor control centers and distribution
boards, details and types of fittings.
3. plans showing the equipment assembly, space requirements,
clearances and locations for cable entrances and anchor bolts.
4. elevations showing all parts, devices, components and
nameplates, positions and arrangements of the equipment. Show
as many elevations as necessary to clearly depict component and
device arrangements.
5. schematic diagram indicating load schedule, e.g., power splited to
(f) Drawings shall be ISO standard size A1. Shop drawings and samples
shall be properly identified with the name of the Project, the
Contractor, the Sub-Contractor and the date, and signed by
Contractors Authorized Engineers.
(g) Final co-ordination of electrical works with mechanical, structural and
architectural work shall be carried out from complete shop drawings
and sufficient time shall be allowed for co-ordination and checking of
shop drawings and calculations after shop drawings are submitted.
(h) Individual shop drawings shall be submitted following the distribution
of the co-ordination drawings and shall bear a stamp indicating that
the work has been coordinated with other trades.
(i) The Engineer's review and approval of shop drawings submitted by
and approved by the Contractor is for general conformance with the
design concept and information given in the Contract Documents
and shall not relieve the Contractor from responsibility for any
deviations from the requirements of the Contract Documents. The
Engineer's review and approval shall not be construed as a
complete check nor shall it relieve the Contractor from responsibility
for error of any sort in shop drawings or schedules, or from the
necessity of furnishing any work required by the Contract
Documents which may have been omitted on the shop drawings.
The Engineer's review and approval of a component item shall not
indicate review and approval of the complete assembly in which it
functions.
(a) Provide and keep on the job at all times, one complete and separate
set of blackline prints of the electrical work on which shall be clearly,
neatly and accurately noted, promptly as the work progresses, all
architectural and electrical changes, revisions and additions to the
work. Whatever work is installed otherwise than as shown on the
Contract Drawings, such changes shall be noted.
(b) Indicate daily progress on these prints by coloring in the various
conduits, ducts, trunking, cable trays, fixtures, and apparatus and
associated installation works erected.
(a) The contractor shall provide the as built drawings, as approved by the
engineers, in DXF format or Micro-station DGN format, in CD-ROM.
The drawings shall be submitted not later than 2 months after
completion of the Project, or putting into operation, whichever is
earlier. An additional, 5 sets of hard copy of all relevant drawings,
which will be required for operation and maintenance, shall be
supplied in bound book forms immediately after the commissioning of
the Project.
(a) Provide operating data for all equipment specified in all Sections of
PS10 specifications.
1. Comply with submittals requirement in this section and in General
Conditions of Contract.
a. Submit four sets prior to final inspection.
specified.
1. General Requirements
2. The Contractor’s Quality Plan shall designate all Quality Control
Procedures, Method Statements (Work Instructions), Inspection &
Test Plans, Inspection & Test Records, Laboratory Procedures
and/or other Quality Documents necessary to ensure compliance
with all aspects of the contract documents.
3. As a minimum, the QP must include the following:
Engineer’s approval.
Any damaged equipment deemed unsuitable for repair by the
Engineer shall be removed from site and replaced at the Contractor’s
expense.
17.1.25 SEQUENCING
(a) General
1. The Contractor shall co-ordinate construction activities included
under various Sections of these Specification, to ensure efficient
and orderly installation of each part of the Works.
2. The Contractor shall coordinate construction operations included
under different Sections of the Specifications that are dependent
upon each other for proper installation, connection and operation.
(b) Scheduling
a. Such activities include, but are not limited to, the following:
(c) Drawings
1. Prepare and submit shop drawings where close and careful co-
ordination is required for:
i Installation of products
ii Materials fabricated off-site by separate entities
iii Where limited available space necessitates maximum
utilization of space for efficient installation of different
components.
(e) Specifications
(c) Provide complete listing of all consumable stores and spare parts
used by the Contractor during the maintenance period.
17.1.30 PROGRAMS
(a) The Contractor shall produce a work program based on CPM or Bar-
chart form indicating the time required for various operations to
complete the Project in time. The following points shall be highlighted
in the program:
1. mobilization
2. drawings/submittals
3. approvals
4. equipment deliveries including delivery periods from supply
sources external to the UAE
5. first fix
6. cabling
17.1.32 SUBSTITUTIONS
become apparent.
17.1.33 PROTECTION
(a) The Contractor shall be responsible for his work and equipment until
finally inspected, tested and accepted. Materials and equipment,
which are not immediately installed after delivery to site, shall be
stored carefully. Close open ends of work with temporary covers or
plugs during construction to prevent entry of obstructing material.
(b) Protect work and material of other trades from damage that might be
caused by his work or workmen and make good damage thus caused.
(c) Protect exposed live equipment during construction for personnel
safety.
(d) Shield and mark live parts "LIVE 220 VOLTS" or with appropriate
voltage in English and Arabic.
(e) Arrange for installation of temporary doors for room containing
electrical distribution equipment. Keep these doors locked except
when under direct supervision of an electrician.
17.1.36 SAMPLES
(a) Power ratings shown for the proposed equipment are in accordance
with the best information available to the Engineer and are to be
considered as minimum ratings. In the event equipment items
proposed by the Contractor should require motors with different power
rating than shown, it shall be the Contractor’s responsibility to furnish
circuit breaker, starting equipment, feeder and branch circuits,
conduits, and accessories etc. as required to comply with the electrical
code and prevent excessive voltage drop without added cost to the
Client.
(b) Where equipment to be furnished is installed in an existing enclosure
or adjacent to existing equipment, the Contractor shall field check the
dimensions of existing equipment, location of conduits, etc., and shall
familiarize himself with all existing conditions and difficulties to be
encountered in performing such work.
(c) Degree of protection for all electrical equipment, unless indicated
otherwise, shall be as follows:
1. IP 54, enclosure for indoor equipment
2. IP 55, enclosure for outdoor equipment
3. IP 65, for outdoor push buttons and switches
4. IP 67, push buttons in the dry well
5. IP 68, submersible equipment
(b) All raceways shall be kept clear of other services except where
intentionally earthed or bonded. Generally, raceways shall be kept
150 mm away from and above hot water and 75 mm away from other
services.
(c) Unless specifically indicated otherwise, normal, emergency, low
voltage cables and wiring shall be segregated throughout the
installation generally in the following manner:
1. armored and sheathed cables: Where more than one tray has
been specified or is necessary to accommodate the number of
cables on a run, where practical, segregation shall be achieved by
dedicating each tray to either normal or emergency services.
Where normal and emergency cables have to run together in
trays, ducts or trenches, they shall be formed in two groups, one
normal and one emergency. Divider on cable trays shall be
provided. Power, control and signal cables shall be laid separate.
2. insulated conductors: Insulated conductor circuits shall, where
possible, be segregated throughout by enclosing in separate
conduits, trunking or trunking compartments.
(a) The polarity of all apparatus used for the Works specified shall be
arranged as follows when apparatus is viewed from the front:
1. for two pole apparatus the phase or “live” pole at the top (or left
hand side) and the '“neutral or earthed” pole at the bottom (or right
hand side). On plug and socket outlets.
2. the polarity shall conform to BS 196, BS 546, or BS 1363 as
appropriate.
3. for three or four pole apparatus the phases in order red, yellow,
blue and neutral reading from top to bottom or left to right in the
case of vertical and horizontal layouts respectively.
live cores shall be red, yellow, blue, as appropriate, and fittings and
switch accessories shall be permanently labeled and segregated in
accordance with I.E.E. Regulations.
Dubai region.
xi. Fully automated report generation- the scanning device shall
generate its own reports, which shall be attached with the main
reports.
xii. Facility for direct connection to a PC.
(a) Establish from Architectural Drawings where fire and smoke barriers
exist, and make adequate provision of fire and smoke barriers in and
around trunking, conduits, cables, etc., where they pass through floors
and fire rated walls, and where protection systems are installed pack
space between wiring and sleeve full with Fire Retardant Material and
seal with caulking.
(b) The Contractor shall ensure that this work is carried out such that the
integrity of any such fire barrier is properly maintained where pierced
by electrical services.
(c) The contractor shall put the notice for electrical shock treatment in
details with sketches and instructions as per standard procedures.
The notice shall comply with the requirement of the DEWA in content
and format. However, this should include the following as a minimum:
ACT IMMEDIATELY
• safeguard yourself.
• switch off current or break electric circuit.
• use or stand on some dry non-conducting material to remove the
CASUALTY from cable or source of electricity.
(d) Locks for interlocking purposes shall be of the figure lock type.
(e) No spare or master key shall be provided, unless specified.
(f) Device items are to be arranged to ensure that there is no danger of
interchange with existing locks on other units.
(a) General:
1. provide sufficient spare parts as follows. Submit to the Engineer a
list of all spare parts to be required for a further two years
operation from the date of issue of the Maintenance Certificate.
2. spare parts required include but not necessarily limited to those
listed below, provided specified in the Project Documentation or
where quantities for each item or equipment is recommended by
the manufacturer.
3. spare parts to be delivered to central stores.
(h) The tenderer shall submit with his offer detail prices of the spare parts
he is required to provide, as specified above, under the Contract
indicating the quantity and the unit rate of each item. The tenderer
Notify the Engineer that a part of the Works or Works is ready for the
Taking-Over inspection.
6. Notify the Engineer that a part of the Works or Works is ready for
the final inspection.
• Include the itemised list of deviations and non-conformances in
the notification letter.
(a) The Client reserves the right to videotape and audiotape the
instruction with no extra cost to Client.
(b) Size of the class shall not exceed 15 people.
(c) The Contractor shall develop individual training courses for each
system identified on the Contract Process and Instrumentation
Drawings (P&ID’s).
1. Separate training sessions shall be provided for operations,
maintenance and electrical/instrumentation personnel.
(d) The Contractor shall develop and submit the curriculum to the
Engineer for approval.
1. Establish curriculum level for high school graduates with trades
qualifications.
2. Perform a task and skills analysis, identifying the requirements for
proper operation, maintenance and repair of the system and of all
its components.
3. Perform a training analysis identifying:
i Tasks requiring training.
ii Logical order of presentation.
iii Objectives of each training segment.
iv Methods for measuring achievement of objectives for each
segment.
v Include tests with at least 15 questions on each outline topic.
(e) Prepare an instructor’s manual, including notes to the instructor, for
each training session.
1. The manual shall address:
i Session objectives.
ii Session outline.
iii Session application.
iv Instructor qualification and knowledge requirements.
v List of tools and supplies required for instruction.
vi. Include safety and standby equipment.
vii Student and course evaluation forms.
viii Audio/visual resources or reproductions.
ix. Session tests and a grading guide.
• References to the source of answers shall be provided in
the course material.
x. Additional notes such as references, review questions,
demonstration techniques, class exercises, coordination with
other sessions and achievement measurements.
17.2.1 SUMMARY
(a) This section specifies the low voltage circuit breakers including air
circuit breaker (ACB), moulded case circuit breaker (MCCB), miniature
circuit breaker (MCB) and earth leakage circuit breaker (ELCB) to be
used in motor control center panel, factory built assembly panel,
17.2.2 REFERENCES
(a) All supplies and services offered in response to this specification shall
conform to the latest standards.
(b) The design, equipment and installation requirements shall comply with
the standards and recommendations laid down by the following:
(a) All low voltage circuit breakers shall be housed in control boards,
which comply with the requirements of 17.21 and 17.20 and provided
with cable boxes complete with glands of suitable size for the
accommodation of the incoming and outgoing cables entering from
below.
(b) Circuit breakers of 600-amp rating and above shall be horizontally
isolated, horizontal draw-out pattern, air break type (ACB). The closing
and tripping mechanism shall be as detailed in the relevant clauses or
schedules. The circuit breaker closing mechanism shall be provided
with a handspring charging. Circuit breakers below 600 amps. shall be
of the moulded case pattern except where otherwise shown on the
drawing.
(c) Circuit breakers shall be designed and constructed such that
inspection maintenance and replacement of the main fixed and
moving contacts shall be easily possible on site. Manufacturer's
detailed instructions shall be incorporated in the maintenance
manuals. Breakers requiring their complete return to the
manufacturers for service will not be acceptable.
(d) All circuit breakers shall be provided with interlocks to ensure that: -
17.2.4 SUBMITTALS
(a) Deliver, store, protect and handle products to site under provisions of
Section 17.1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1.
(a) Air Circuit Breakers shall conform to EN 60947-2 and shall have
breaking capacity of 50 kA symmetrical for 3 seconds at 380 Volts.
Utilization category A as per EN 60947-2 (AC3 as per IEC 947-4-1).
(b) The Air Circuit Breakers (the conventional type and not moulded case
circuit breaker) shall be 500 V, 50 Hz, triple pole with neutral link for
incoming and outgoing ACB; or four poles for incoming (where earth
leakage protection is specified on both incomers) and bus tie ACB as
shown on the Drawings. They shall be air break, trip free, draw-out
type with mechanical and electrical ON/OFF indicators.
motor failure.
(d) The air circuit breaker shall be provided with over current, short circuit
and earth fault protection having the following characteristics:
(e) The circuit breaker shall have three position on the draw-out
mechanism, namely service position where all main and auxiliary
contacts are made, test position where main contacts are open but
auxiliary contacts are closed and isolated position where all contacts
are open. An indicator shall clearly show these positions and
provisions shall be made for locking the breakers in any position.
ON/OFF indicator shall be provided.
(h) The moving contacts comprising the main and arcing contacts shall be
of the spring loaded, self-aligning type. The arc contacts shall be
arranged to make before and break after the main contacts.
(i) Each ACB shall be included but not limited with following components
and accessories:
1. Auxiliary Contacts
2. Arc Chutes
3. Folding Extension Rail
4. Charging Handle
5. Open and Close Push-buttons
6. Over Current Trip Indicator
7. Key lock on Trip Button
8. Spring charge motor when required
9. Spring Charge Condition Indicator
10. Breaker Position Indicator
11. Making Current Release
12. Automatic Shutters for the B/B Terminal
13. Carriage for every size of ACB exceeding 25 KG in Weight
14. Operation Counter
(j) The Main Incoming Circuit Breakers shall be provided with cable
terminal boxes to suit the incoming cables from the transformer/source
supply.
(l) Type test certificate for each size of circuit breakers and MCCB from
an internationally recognised testing authority acceptable to the
Engineer shall be provided.
(a) MCCB’s shall be of the type, four pole for incoming from DEWA with
DG set and triple pole with neutral link for incoming and triple pole for
outgoing operation or as indicated. Utilization category A as per EN
60947-2 (AC3 as per IEC 947-4-1).
(b) MCCB Shall have a combination of thermal and magnetic tripping
giving an inverse time delay protection against sustained overloads
and instantaneous tripping under heavy overloads and short circuits.
Unless otherwise stated in the particular specification or drawings,
MCCB shall have a minimum short circuit rating of 25 kA.
(c) Tripping due to overload or short circuits shall be clearly indicated by
the handle assuming a position mid-way between the manual ON and
OFF position.
(d) Breakers shall have a quick make, quick break over-center switching
mechanism that is mechanically trip free from the handle so that
contacts cannot be held closed against short circuits and abnormal
current.
(e) Latch surfaces shall be polished.
(f) Poles shall be constructed to open, close and trip simultaneously.
(g) Ampere ratings shall be clearly visible.
(h) Breakers shall be completely enclosed in a moulded case to IEC No.
157 - 1A, suitable for installation inside switchboards.
(i) Non-interchangeable trip breakers shall have the trip unit sealed.
(j) Breakers with earth leakage relay protection shall be provided with
shunt trips.
(k) Frame sizes shall be as per manufacturer’s standard size and as
approved by the Engineer.
(l) Each MCCB shall be complete with 2 N/O and 2 N/C spare auxiliary
contacts (10A, 240v rating) in addition to those required for the
contract
(m) Shunt trip mechanism when required for emergency or manual
opening operation
(a) These shall be suitable for the type of load they feed. MCBs shall
17.2.16 MCB/ELCB
(a) Current operated earth leakage circuit breakers shall provide accident
protection by interrupting dangerous contact with voltage which may
be present in faulty electrical equipment as a result of frame faults,
insufficient insulation or misuse.
(b) The ELCB shall also provide a high degree of protection against earth
leakage, fires and electric shock and can withstand at least 9 kA or as
indicated in the Project drawings. The breakers shall generally
comply with BS 4293, 1983 and the recommended specification CEE
227 of the IEC on Rules for the approval of electrical equipment.
(c) The breaker shall consist of a core balance transformer, a tripping coil
with contact assembly, main supply contacts, ON/OFF switch, a test
button and a trip free mechanism all enclosed in a robust body of all
insulated material.
(d) Degree of Protection against earth leakage throughout the electrical
installation shall be as indicated on the Drawings. Unless otherwise
indicated, ELCB shall have 30 mA trip settings.
(e) The breaker protecting external lighting and power outlet circuits shall
be mounted inside the panel board enclosure.
(a) Provide testing and analysis under this section - General Equipment
Provisions.
(b) All circuit breakers shall be subject to the following witness tests to EN
60947 or other approved equivalent standard for voltages up to and
including 1000 Volts:
1. Routine tests including H.V. pressure test, Milli-volt drop tests and
mechanical tests.
2. Operation of D.C. closing coil and satisfactory closing of the circuit
breaker with the voltage on the coil between 85 per cent of it’s
rated voltage and 110 per cent of it’s rated voltage.
3. Satisfactory shunt opening release of the circuit breaker with the
trip coil energized to between 50 per cent and 110 per cent of its
rated voltage.
4. Interchangeability of identically equipped withdrawable circuit
breakers and checking of all mechanical and electrical interlocks.
5. Type Test Certificates giving records of performance for identical
circuit breakers shall be made available.
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
17.2.20 PREPARATION
17.2.21 INSTALLATION
(a) Conduct field inspection and testing under provisions of Section 17.1.
17.2.24 DEMONSTRATION
17.2.25 TRAINING
17.2.26 MAINTENANCE
17.3.1 SUMMARY
(a) This section specifies the fuse switches to be used in motor control
center panel, factory built assembly panel, distribution board etc. This
shall be read in conjunction with other related sections of the
specification and contract drawings.
17.3.2 REFERENCES
(a) All supplies and services offered in response to this specification shall
conform to the latest standards.
(b) The design, equipment and installation requirements shall comply with
the standards and recommendations laid down by the following:
17.3.3 SUBMITTALS
(c) Prior to the despatch from the factory, the Contractor shall notify the
Engineer, in sufficient time to allow the Engineer or his representatives
to inspect and test the equipment or witness the test, if so desired.
(a) Deliver, store, protect and handle products to site under provisions of
this section.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under this section.
(c) Equipment and materials shall be delivered, handled and stored
according to the recommendation of the manufacturer along with the
following provision.
(a) Fuse switches shall comprise flush mounted heavy duty composite air
break switches and fuse units complying with BS EN 60947– 3 and
fitted with fuses to BS 88/BS EN 60269 and shall be rated and
equipped as per the requirement of the equipment to protect.
Switches shall be suitable for AC23–B utilization category conforming
to IEC 947– 4–1. Composite units shall be contained within an
17.3.10 FUSES
1. NEMA Class M
2. NEMA Class J time delay
3. IEC 269
4. BS 88
(g) Small Power Branch and Control Circuits:
Conforming to one of the following as recommended by the equipment
manufacturer and to meet Dubai Electricity and Water Authority
(DEWA) regulations:
1. NEMA Class G
2. IEC 269
3. BS 88
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
17.3.14 PREPARATION
17.3.15 INSTALLATION
(a) Conduct field inspection and testing under provisions of Section 17.1.
17.3.18 DEMONSTRATION
17.3.19 TRAINING
17.3.20 MAINTENANCE
17.4.1 SUMMARY
(a) This section includes specification for motor starters in general and as
required to be supplied for the project.
(b) The motor starters as required, are to form part of a Motor Control
Center and as such circuit connections, protection devices and the like
shall be provided in the scope of starters as specified in this Section.
17.4.2 REFERENCES
(a) BS EN 60439 -
Specifications for low voltage
switchgear and control gear
assemblies.
(b) BS EN 60947-4 - Contactors and motor starters.
(c) Approved equal American Standards.
(a) The starter as required are to form part of a motor control center
(MCC) and as such circuit connections, protection devices and the like
shall comply with BS EN 60439. The starters shall comply with BS EN
60947-4. The cubicles shall be easily accessible for maintenance
purposes and shall be damp-proof and dust-proof.
(b) The starter manufacturer shall coordinate with the motor control center
manufacturer to ensure provision of adequate space, ventilation
requirements etc. for trouble free operation of the starters.
17.4.4 SUBMITTALS
(a) The following shall be included in the submittals:
1. Shop drawings, product data and samples.
2. Complete description, specifications, drawings and descriptive
literature on the equipment.
3. Make and model of each component.
4. Number of sizing electrical and control wires and power
requirements.
5. Complete wiring and equipment installation diagram.
6. List of spare Parts to be provided.
7. Recommended procedure for protection of equipment against
damage, prior to installation.
8. Complete system diagram showing required components, routing
through in-plant duct bank system.
(b) The submittals shall be subject to approval by the Engineer. The
Contractor shall submit the final documentation based on the
Engineer’s comments.
(c) Manufacturer's Certificate: Certify that products meet or exceed
specified requirements.
17.4.7 QUALIFICATIONS
(a) Deliver, store, protect and handle products to site under provisions of
Section 17.1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1 – Provisions
for Electrical Requirements.
(a) General
The motor starter shall be of rating to carry the full load current of its
rated duty at its most severe load conditions. All starters shall be
capable of at least 20 starts per hour at 100 percent full load torque.
2. motors bigger than 2.2kW (3 HP) and up to 37kW (50 HP) shall
have their starting current restricted to 4 times FLC and shall use
2. Auto Transformer
(b) Accessories:
1. contactors shall be selected for AC3 duty. The duty current shall
be at the mid point of the operating range of the contactor.
2. motors will be required to operate in a predetermined sequence
and starters shall include suitably rated auxiliary contacts/relays.
3. components of the starter shall have been type tested and ASTA
certified to achieve Type 2 co-ordination in accordance with IEC
947.
4. volt-free changeover contacts shall be wired down to outgoing
terminals for remote indication of the plant status information
specified. As a minimum requirement running/stopped,
healthy/fault indications shall be provided for each motor drive.
5. analogue signals specified shall be wired down to outgoing
terminals. Analogue signals for such indication shall be 4-20mA,
fully floating, and capable of driving into a load of up to 500 ohm.
6. outgoing terminals for remote indication and control shall be
continued to telemetry cubicle if provided, or otherwise they shall
be located in the common control cubicle.
1. one triple pole MCCB externally operated and interlocked with the
cubicle door. There shall be provision for padlocking in the OFF
position.
2. one Starter as below.
i. overcurrent
ii. unbalance
iii. single phase
iv. earth fault
(b) For motors 11 kW and above, the relay shall be electronic and provide
display indication of:
1. relay settings
2. percent of FLC that the motor is taking
3. continuous monitoring of thermal capacity of motor
4. thermal capacity used during start of motor
5. if tripped, how much time before restart to take place
6. stall or short circuit trip
7. earth fault trip
8. starting
provide overload relay having current/time characteristic at its
setting (hot/cold for the thermal overload) to match with the motor
manufacturers thermal stability time/current characteristic curve.
Consideration must be given to the required method of starting
(DOL, auto transformer etc.).
(a) All the starters and main Incomer breakers shall have electronic solid
state, multifunction, microprocessor based relays with communication
capabilities. These relays shall perform all the functions such as
Status Indications, Motor parameter monitoring, allow for local and
remote control, protective functions, and shall provide diagnostic
information about the motor and the relay itself. All Intelligent MCCs
and LV switchboards shall be time synchronized with the SCADA.
SCADA will be the master clock.
b. Commands from the operator station and from the Starter Module.
1. .Start / Stop Command.
2. Fault Reset at Starter module, at the System Engineer’s station
and Electrical Engineer’s station.
c. Monitoring Functions: -
Following parameters shall be available for monitoring at the Operator
workstation and Electrical Engineer’s station.
1. Phase Currents,
2. Average Current,
3. Full Load Current.
4. Current Imbalance percent.
5. Percent Thermal capacity utilized / available.
6. Power Factor,
7. Voltage,
8. Running Hours.
9. Trends, Graphic Displays for monitored parameters
d. Protective Functions:-
e. Diagnostic Information: -
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
17.4.17 INSTALLATION
(a) Conduct field inspection and testing under provisions of Section 17.1.
17.4.20 DEMONSTRATION
17.4.21 TRAINING
17.4.22 MAINTENANCE
17.5.1 SUMMARY
(a) This section provides specification requirements for the “Soft Starter”
for a standard three-phase squirrel cage motor.
(b) The Starter and associated control equipment including the power
factor correction items shall be housed within a cubicle forming a part
17.5.2 REFERENCES
(a) The starter as required are to form part of a motor control center
(MCC) and as such circuit connections, protection devices and the like
shall comply with BS EN 60439. The starters shall comply with BS EN
60947-4. The cubicles shall be easily accessible for maintenance
purposes and shall be damp-proof and dust-proof.
(b) The starter manufacture shall coordinate with the motor control center
manufacturer to ensure provision of adequate space, ventilation
requirements etc. for trouble free operation of the starters.
17.5.4 SUBMITTALS
Engineer’s comments.
(c) Manufacturer's Certificate: Certify that products meet or exceed
specified requirements.
17.5.7 QUALIFICATIONS
17.5.9 WARRANTY
(a) Deliver, store, protect and handle products to site under provisions of
Section 17.1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1.
17.5.13 RATINGS
(a) Rated input system is 380 volts ± 10%, 3 phase, 4 wire, 50 Hz ± 5%.
(b) The starter for specified motor shall be rated to work in the shaded
ambient temperature of 50o C. having relative humidity of 95% (non-
condensing).
(c) The starter shall be rated for the continuous maximum rating of the
motor and not its running load.
(d) The soft starters shall be derated for operation at 500C ambient
temperatures. Soft starter shall be suitable for starting and stopping of
3-phase asynchronous squirrel cage motor.
(e) Power factor correction capacitor shall be provided to keep the power
factor of the system within 0.93 lagging to unity over the entire
operating range.
(a) General
(a) All the dialogue functions shall be accessible on the front panel of the
unit via:
(a) All dialogue functions, display units, remote functions, terminal blocks,
configuration switches shall be accessible on the front of the control
module without any exposure to control circuit boards and electrical
power devices during routine adjustments.
(b) The starter shall be preset to the following for normal operation,
unless specified otherwise:
(c) Digital display unit shall indicate the following minimum conditions,
(d) Keypad shall provide the facility to configure the following operating
parameters:
17.5.18 PROTECTIONS
(a) The soft starter shall be designed for TYPE 2 protection co-ordination.
(c) The soft start shall provide phase loss, phase reversal, under load,
stall, and jam protection.
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
17.5.21 INSTALLATION
(a) Conduct field inspection and testing under provisions of Section 17.1.
17.5.24 DEMONSTRATION
17.5.25 TRAINING
17.5.26 MAINTENANCE
17.6.1 SUMMARY
17.6.2 REFERENCES
17.6.4 SUBMITTALS
17.6.7 QUALIFICATIONS
(a) Deliver, store, protect and handle products to site under provisions of
Section 17.1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1.
1. Motors 0.37kW (0.50 HP) and larger shall be 400 volts, 3 phase,
50 Hertz unless otherwise indicated.
2. Motors smaller than 0.37kW (0.50 HP) shall be 220 volts, 1 phase,
50 Hertz unless otherwise indicated.
Motor rating
1. Motors with the following minimum power factors, at full load, shall
be provided:
1. Open and TEFC motors of rating 187kW (250 HP) and less and
vertical motors shall be provided with service factor 1.14. All
horizontal motors larger than 187kW (250 HP) shall have a 1.0
service factor.
1. The maximum locked rotor KVA/HP code letter for motors smaller
than 11kW (15 HP) shall not exceed the requirements for NEMA
Design B motors as indicated in NEMA MG 1-1.15.1.2. The
maximum locked rotor KVA/HP code letter shall be Code G for
motors 11kW (15 HP) through 187kW (250 HP) unless otherwise
indicated. The maximum locked rotor KVA/HP code letter shall be
Code F for motors 224kW (300 HP) and higher as indicated in
NEMA MG 1-10.37.2.
(h) Insulation
(i) Windings
(k) Bearings
1. The motors shall run in ball and/or roller bearings and the weight
of the motor shall be carried by thrust bearings incorporated in the
motor body.
2. Bearings shall be grease lubricated using hydraulic type nipples,
which are freely accessible without any dismantling, or otherwise
piped out to a readily accessible location.
3. “Sealed for Life” bearings shall not be used except for small
motors.
4. The motors shall be commercially silent in operation and run
free from vibration and the rotors shall be perfectly balanced
both statically and dynamically and shall be tested and adjusted
for dynamic balance in an approved manner.
5. Additional temperature sensors shall be provided for bearing
temperature monitoring for motors rated 30kW and above.
(m) Duty
1. Motors shall be rated for S1 duty on full rated capacity. All motors
shall be capable of starting 10 times per hour. The stalled motor
current shall not exceed 6 times full load current.
(o) The maximum continuous rating (MCR) of each motor shall be as set
out in Table 1 and shall be rated and designed to suit the site climatic
data as specified. This reserve power requirement shall be added to
the calculated power prior to any other adjustments e.g. high ambient
temperatures at Site.
TABLE 1
Maximum Continuous Ratings (MCR)
Application Up to 75 kW drive Above 75 kW drive
All pump motors 10% above that 5% above that
(excluding positive required under all required under all
displacement type) conditions of conditions of
operation operation
Positive displacement 25% above max. duty 12.5% above max.
pumps and compressors requirements duty requirements
(p) Motors shall be selected from the following to satisfy the Contract's
performance requirements and comply with the Utility Company
(DEWA) starting current restrictions: -
3. Motors larger than 37 kW (50 hp) shall have their starting current
restricted to 1.5 x FLC and shall use one of the following starting
methods as shown on contract drawings:-
(q) Centrifugal pumps on unscreened sewage shall give at least 100% full
load torque on starting and therefore only squirrel cage rotor machines
utilizing direct-on-line (DOL) starting or slip ring wound rotor machines
with rotor resistance starting will be acceptable for these drives.
(r) Motors shall be suitable and certified for the zone hazard in which they
are to be installed. Motors for use in all categories of potentially
explosive atmospheres as defined in BS 5345 or equivalent shall have
the appropriate BASEEFA/CENELEC or other similar National Testing
Organization Certificate. Copies of the certificates shall be submitted.
(b) Motors shall be squirrel cage, induction type, totally sealed, suitable
for the maximum immersion depth likely to be encountered. Motor
shall be capable of start up and operation in the event of completely
flooded well to the maximum level.
(c) Motor shall be air filled. Degree of protection against ingress shall be
IP 68 complying with EN 60529.
(d) Motor insulation shall be Class F (maximum working temperature 155
degree Celsius), limited to a Class B temperature rise (maximum 80
degree Celsius rise) complying with specification standard EN 50017.
(e) Motor temperature shall be monitored using a thermistor, one in each
phase of the winding, set to stop the motor when the monitored
absolute temperature reaches 130 °C.
(f) Motor shall be suitable for class S1 duty, even when it is not
submerged. Motor shall be capable of starting up to 10 times per hour
(minimum).
(g) The motor shall be capable of operating continuously in a totally dry
condition (non-submersed) of 50 degree Celsius ambient temperature
under full load without damage.
(h) Power and signal cables shall be connected to the motor through a
watertight terminal box, sealed off completely from the surrounding
liquid and the motor windings.
(i) Leak detector shall be provided for each motor for detecting liquid leak
into sealing/motor casing, for connection in motor control circuit for
tripping.
(a) Enclosures for induction motors shall be approved for the installation
and as indicated. The enclosure types shall be one of the following as
outlined in the driven equipment specifications unless otherwise
indicated.
(c) Motor enclosures shall be suitable and certified for the zone of hazard
in which they are to be installed.
(d) All motors mounted outdoors shall be fitted with appropriate sunshade
to maintain motor environment at ambient temperature.
(e) Housing, end brackets and all outside components shall be cast iron
except WP II or open drip-proof enclosures, which may be, fabricated
steel.
(f) A condensate drain hole shall be provided on all non-explosion-proof
enclosed motors. The drain hole shall be provided in each end
bracket on horizontal motors. A single drain hole shall be provided in
(a) Terminal boxes shall be provided with glands suitable for XLPE or
PVC armored cable. The motor stool base where appropriate shall be
drilled at works vertically below the terminal box gland for the passage
of the cables and the edges of the hole slightly countersunk or the
hole bushed.
(b) Terminal boxes shall be cast iron and shall be designed to accept the
cables as detailed by the contract. On non-submersible motors,
terminal boxes shall be mounted on the right hand side when viewed
from the driving end of the motor, unless otherwise required by the
contract.
(c) All three phase motors, rated 2.2 kW and higher, shall have six
winding leads brought out into the terminal box to allow connection for
star-delta type reduced voltage starting.
(d) Terminals shall be stud-type, substantially designed, anchored to a
carrier terminal block and insulated from the motor frame. Terminals
shall be identified in accordance with BS 4999 Part 108 or equivalent.
A separate earth stud shall be included on each terminal box. Heater
terminals shall be shrouded.
(e) Adequate space and glanding arrangements shall be provided,
particularly on smaller motors requiring glanding and termination of
steel wire armored cable for star/delta starting, anti-condensation
heating and thermistor winding protection devices.
(f) Where a common terminal box is used for main, heater and thermistor
cable terminations, a permanent warning label shall be fixed to the
terminal box cover. In addition, heater and thermistor cable
terminations shall be clearly marked to identify their separate functions
and operating voltages.
(g) Terminal box covers shall be gasketted to provide a degree of
protection equivalent to or better than that of the motor.
17.6.14 NAMEPLATE
(a) Provide stainless steel fasteners and nameplate of ample size with
clear numerals and letters.
(b) Nameplate shall indicate the manufacturer, serial number, model
number, type, horsepower, phase, hertz, volts, design, full load
amperes, locked rotor code letter, service factor, speed, insulation,
class, temperature rating, information required by NEMA MG 1-10.38
and other essential data.
(c) Nameplate data shall be in the English language and metric units.
(d) Nameplate shall be secured to the motor frame with corrosion
resisting pins in accessible locations.
17.6.15 ACCESSORIES
(a) Additional accessories for motors 75 kW (100 HP) and larger shall
include the following:
(c) All of the above accessories, except the surge capacitors, shall have
wires brought out in a terminal box or boxes other than the main motor
power terminal box.
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
17.6.18 INSTALLATION
(a) Conduct field inspection and testing under provisions of Section 17.1.
17.6.21 DEMONSTRATION
17.6.22 TRAINING
17.6.23 MAINTENANCE
17.7.1 SUMMARY
(a) This section specifies the equipment, accessories and materials for
lighting and small power requirements.
(b) This shall be read in conjunction with other related sections of the
specification and contract drawings.
17.7.2 REFERENCES
17.7.3 GENERAL
17.7.4 SUBMITTALS
17.7.7 QUALIFICATIONS
(a) Deliver, store, protect and handle products to site under provisions of
Section 17.1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1 – Provisions
for Electrical Requirements.
(a) General – LED moisture proof Luminaire for plant room areas shall
be ceiling mounted surface type. Number of the luminaires and the
locations for the installation shall be as indicated on the Drawings.
Mounting height shall be 2.5 meter measured from the bottom of the
luminaire to the floor directly beneath it.
(b) Suspension type luminaires shall be provided complete with all
accessories similar to Whitecroft hibay type B1150S/HBSR or
equivalent and protected to minimum IP42 having one 150 watt SON
lamp per luminaire
(c) Construction Details - Luminaire housing including guard shall be
made of diecast aluminum. Reflector material shall be of galvanized
steel roll-formed with white enameled finish. Luminaire shall have
diffusers with crystal glass of optical texture. Luminaire housing color
shall be white unless otherwise directed by the Engineer.
(d) LED luminaries used for plant room lighting shall meet the relevant
BS requirements. Degree
(a) LED luminaires installed in the control room shall provide shadow
less illumination. The LEDs shall have a color rendering index of
greater than 70 at a corrected color temperature of 4000 K or higher.
(b) Provide recessed type LED luminaires complete with all accessories
and control gear as shown on drawings.
(c) Lighting for control room shall be designed for maximum flexibility to
permit flicker-free variation of illumination levels above each group of
operator stations. Luminaires shall be installed to minimize reflections
and glare at operating screens.
(d) Manual switches located at the entrance of every room shall control
(a) General
2. The operation of the system shall be such that on loss of one or all
phases of the main electricity supply, a set of central batteries or
individual battery packs shall provide power for 3 hours to
illuminate emergency luminaires throughout the building. On
restoration of the mains supply the batteries shall be charged by
an integral charger such that the system supplies not less than
85 % of its rated voltage after a period of 12 hours.
(b) Self Contained Emergency Battery Packs
(a) Low voltage luminaires shall be provided with its integral step down
transformers, unless indicated otherwise.
1. to BS 1363
2. 3 rectangular pin (2P+E) shuttered, with combined switch, rated
13A, 250 V
3. to be supplied with plug complete with fuse
1. to BS 546
2. 3 round pin (2 P + E) shuttered switched pattern complete with
plugs.
3. Neon indicator lamp, unless specified otherwise in the Project
Documentation.
17.7.19 SWITCHES
(a) Internally mounted switches shall be of the "multiple phase" type with
the switches arranged in multigang boxes where possible.
(b) Special care shall be taken to ensure that all switches are securely
fixed truly vertical and that flush mounted switches are flush with the
wall finish so that the overlapping cover plates seat onto the rims of
the boxes.
(c) Light Switches
1. to BS 3676
2. to be rated 10, 15 or 20 amps depending on connected load, as
stipulated in the DEWA regulations
3. recessed with concealed conduit, surface pattern elsewhere
4. quick make and break type
5. single pole, double pole, one way, two way or intermediate as
indicated
6. surface mounted switches to be either poly-carbonate, or metallic
and as indicated in the Project Documentation
7. flush mounted switches to be of the grid fixing type with finish as
noted in the Project document.
8. switches shall be certified for AC-23A duty
(d) Waterproof Switches:
1. the double pole switches shall be with neon indication lamps and
shall be rated 20, 30 or 45 Amps. as indicated on the drawings
2. the faceplate shall be of matt chrome, unless specified otherwise
in the Project Documentation and shall be engraved ‘WATER
HEATER’, ‘WATER COOLER’ etc. as required.
3. switches shall be certified for AC-23A duty.
17.7.21 TIMER
1. 10 ....................200 seconds
2. 0.10 .................. 20 seconds
1. delay on energization or
2. delay on de- energization type, as per the application requirements
3. Upon supply of rated voltage to the input terminals, the timer shall
start, the output relay remains in rest position. After the set
time, the output relay pulls in.
4. The relay resets after the input supply has been cut-off.
(a) Time clocks to control circuits depended on time and hours of the day,
may be either
(c) Output contacts shall be suitable for both AC and DC control circuits.
The contacts shall be suitable for duty of AC-2 or DC-3 utilization
category. The rating of output contacts shall be co-coordinated with
the application requirements.
(d) The no. of output contacts and the duration of contact closing shall be
decided as per the application requirements.
(e) Time clocks shall be provided with a time dial setting for 24 hours and
7 days program.
(f) Each time clock shall be provided with a minimum running reserve
energy for 1 day.
(g) Accuracy of clocks shall be better than 1 second per day.
17.7.23 WIRING
(a) Wiring for lighting in Ancillary Buildings shall be carried out in PVC
cable to BS 6004 or equivalent enclosed in high impact PVC conduit
or steel conduit as specified or indicated on drawings.
(b) Wiring may also be carried out where required in high impact PVC or
Metal trunking to BS 4678 with prior approval from the Engineer.
(c) The minimum copper conductor size used shall meet current Dubai
Electricity and Water Authority (DEWA) requirements.
(d) The use of junction boxes between fittings shall be kept to a minimum
and where practicable all connections shall be made at the fitting.
(e) Where used junction boxes shall be rectangular pattern and where
possible their position shall be hidden from immediate view but not
made inaccessible.
(f) Circuit wiring shall not be connected directly onto the terminals of
lighting fittings but shall be made off in point boxes consisting of a
standard box containing shrouded pinch screw connectors to which
connections shall be made to the light fitting by heat resistant flexible
cables.
(g) Through wiring for luminiares using luminiares are not acceptable.
(h) .
(a) The Junction Box shall be completed with a terminal block suitable for
connecting up to 10mm2 copper conductor (phase, neutral and earth)
and an all insulated moulded white cover plate with removal covers.
(b) The cover plate shall be raised for connecting outgoing cable.
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
17.7.26 INSTALLATION
(a) Conduct field inspection and testing under provisions of Section 17.1.
(b) Arrange and carry out such witnessed and unwitnessed tests and
inspections as may be required by the Dubai Electricity and Water
Authority (DEWA) and obtain and handover to the Engineer their
certificate of approval of the complete electrical installation.
17.7.29 DEMONSTRATION
17.7.31 MAINTENANCE
17.8 CABLES
17.8.1 SUMMARY
(a) This section includes specification for cables to used in this project
work.
(b) This shall be read in conjunction with other related sections of the
specification and contract drawings.
17.8.2 REFERENCES
1. Fault level.
2. Conditions of ambient temperature relevant to method of laying.
3. Voltage drop.
4. Voltage drops in motor circuits due to starting.
5. Over-current settings of circuit breakers.
(e) Cable ratings shall be calculated in accordance with BS 7671 and for
direct buried cables ERA publication 69-30.
(f) The Contractor shall submit details of the cable sizing calculations for
the Engineer's approval before ordering.
(g) The Contractor shall be responsible for measuring the length of cable
required.
(h) Each cable shall be supplied in a suitable length and be continuous
through its run. Through joints will not be permitted without written
permission from the Engineer.
(i) The earthing conductor shall be of adequate cross sectional area and
shall either be one core of a multicore cable or a separately run single
core cable. The use of conduit, water or other service pipes in any part
of the earth continuity conductor is not permitted.
(j) The Contractor shall supply and install all necessary cable glands and
sealing boxes required to complete the installation. All materials used
in the manufacture of the glands etc. shall have no deleterious effect
on the cable core or armoring and shall not be susceptible to
corrosion.
(k) The cores of each cable shall be taken direct to the terminals of the
equipment to be connected. Cable ends shall be sealed in suitable
chambers bolted to terminal boxes. Compression glands with armor
clamps where required are to be supplied as an integral part of
switchboards, distribution boards, switches, motor starters and similar
equipment, unless otherwise stated.
(l) The general routing of cables may be indicated on the Drawings but
the final routes and duct locations shall be agreed with the Engineer
before any work in connection with the cable installation is
commenced. All cables shall be installed in strict accordance with the
requirements of this Specification.
(m) All cables used shall bear the manufacturer's original guarantee and
all cables shall be delivered to Site in their original wrappings. The
Contractor shall obtain the permission of the Engineer before any
wrappings removed or cables are installed.
(n) The Contractor shall ensure that no more than one phase will occur at
switch lighting or power outlets where these outlets are less than 2.5m
apart unless guarded by a wall partition or other barrier. If this is
impracticable the Contractor shall obtain the advice of the Engineer
before proceeding.
(o) The scheme of wiring shall conform to the color code requirements of
BS 7671.
(p) A minimum length of 250 mm tails shall be left on all cables at outlet
positions for connection of the lighting fittings or other apparatus fed
by the outlet.
(q) The installation of multi-core and single core cables or bunching of
cables in conduit is to be carried out on the assumption that such
17.8.4 SUBMITTALS
17.8.6 QUALIFICATIONS
(a) Deliver, store, protect and handle products to site under provisions of
Section 17.1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1- Provisions
for Electrical Requirements.
(a) PVC insulated wiring cables shall comply with BS 6004 or BS 6346
and shall be 600/1000 V grade. The cable used shall not be less than
1.5mm2 cross-sectional area.
follows: -
(a) Cables for direct buried application shall have outer sheath suitable for
installation of cables in ground having highly corrosive chemicals. An
additional HDPE jacket shall be provided for locations where cable is
expected to remain under water continuously for long period.
(a) All optical fiber cables shall be suitable for industrial communication
networks and shall meet the following requirements:
(a) Joints
1. malleable cast iron boxes for joints in all power cables shall be
compound filled and of adequate size. The boxes shall be fitted
with suitable armouring clamps and glands. The armoring of the
cables shall be terminated at the armouring clamps and the inner
sheath shall pass through the gland. Self amalgamating tapes
shall be applied to give fully screening insulation reinstatement
where the insulation is screened
2. the box and compound shall be at the correct temperature before
the compound is poured to allow total adhesion between the
compound and the box. The compound shall then be allowed to
cool and topped up before the box is closed. No air locks shall be
formed within the box
3. with the consent of the Engineer, plastic shells fitted with suitably
sized armour bond and filled with an approved type of cold pouring
encapsulating compound to BS 6910 may be used as an
alternative to the compound filled cast iron joint boxes for jointing
PVC-insulated power cables. In such cases, the complete jointing
kit, including plastic shell, compound, insulating tape etc. shall be
from the same proprietary manufacturer who is specialised in
manufacturing products for this purpose. The jointing methods
and procedures, as laid down by the manufacturer, shall be
followed in strict accordance
4. ferrules, compression connectors and bare portions of cable core
resulting from a jointing or terminating process shall be insulated
with an approved type of insulating tape or heat shrinkable tubing
after completion of process. Such insulating tape or heat
shrinkable tubing shall have equal or better electrical and
mechanical properties than those of the original insulation
removed, and shall be adhered to the cores etc. securely and
permanently. The final thickness shall be in smooth contour
throughout the whole length
5. every compression joint shall be of a type which has been the
subject of a test certificate as described in BS 4579. When a
compression joint is made, the appropriate tools specified by the
manufacturer of the joint connectors shall be used.
6. a circuit protective conductor having adequate cross sectional area
and of same material as the phase conductors shall be installed
and connected to maintain the effectiveness of the earth continuity
across every cable joint
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
17.8.21 INSTALLATION
(a) Conduct field inspection and testing under provisions of Section 17.1.
(b) Inform the Engineer prior to the testing of the cables and be
responsible for liaising with any other contractor to whose equipment
the cables may be terminated to ensure that all parties concerned are
aware of the impending tests, to guarantee the safety of personnel
and that the isolation of any equipment has been completed. Any
special isolation or preparation required to be carried out before cable
testing can be completed, will be carried out by the Contractor
responsible for that equipment. All tests shall be carried out by the
Contractor but shall be supervised by the Engineer.
(c) Provide D.C. test equipment and apply (after isolation) in the presence
of the Engineer, the following D.C. test voltages on all cables between
cores, cores and sheath and cores and armor: -
1. PVC SWA PVC and XLPE SWA PVC 1,000 volt grade cable
between cores 3,500 volt
between core and armor 7,000 volt
(a) Manufacturer shall provide factory routine test reports for all the
cables being supplied.
(b) OTDR testing shall be carried out for all the fiber optic cables at site.
(c) The Contractor shall provide all special tools, testing instruments,
connectors, etc. for carrying out tests on fiber optic cables at site.
(d) Fiber optic cables shall be tested immediately after laying, before
connection and also after complete installation of the entire network.
(a) The work of this section is integral with the whole of the Project
Documentation and is not intended to be interpreted outside that
context.
(b) Co-ordinate the work with all other services affecting the work of this
section.
17.9.2 REFERENCES
17.9.3 DESCRIPTION
17.9.4 SUBMISSIONS
(a) Samples:
1. Cut-away samples of all sizes of conduits, conduit boxes and
fittings of each type shall be fixed to a board and submitted to the
Engineer.
(a) Standards:
1. Conduit and fittings shall comply with BS 4607: Part 1 and CEE
Publication 26. In addition, conduit and fittings shall comply with
this specification where requirements are more stringent.
2. Conduit diameters shall comply with DEWA regulations.
(a) Flexible conduit shall be of low smoke & zero halogen material as per
NFPA-502.
(a) Conduits used inside pedestrian bridge shall be fire resistant, low
smoke & halogen free GRP conduits.
(b) Exposed GRP conduits shall be extra heavy duty with minimum 0.25
inch wall thickness.
(c) GRP conduits shall meet requirements of following standards
- BS 476 Part 7, ISO 4589, NFPA-502 & IEC 695-2-1.
17.9.10 PREPARATION
(a) General
1. Run conduit in square, symmetrical lines, parallel to or at right
angles to walls and in accordance with the accepted practice.
2. Conduit system shall be mechanically continuous and watertight
after installation. All conduit system shall be arranged wherever
possible to be self draining.
3. Conduit runs between draw-in positions shall conform to DEWA
Regulations regarding no. of bends and lengths of straight run
4. Installation shall permit easy drawing in of cables.
5. Keep conduits at least 100mm from pipes and other non-electrical
services.
6. Where conduit runs are to be concealed in the structure or are to
17.9.13 CLEANING
(a) The conduit outlets when installed and before wiring shall be
temporarily closed by means of well fitting wooden plugs, and
immediately before cables are drawn in, conduit systems shall be
thoroughly swabbed out until they are dry and clean.
17.10.1 SUMMARY
(a) This section includes specification for works related to cabling in the
project area in general
(b) This shall be read in conjunction with other related sections of the
specification and contract drawings
17.10.2 REFERENCES
(a) Every cable shall be installed in accordance with the relevant codes of
practice and shall be neatly run in all situations.
(b) All cables shall be run on trays or brackets either secured to walls,
ceilings and building structures or run in ducts and trenches.
(c) Every cable whether in or out of sight shall be neatly run vertically,
horizontally or parallel to adjacent walls, beams or other structural
members.
(d) Spacing of clips, saddles and cleats shall be such to prevent sagging
of the cable at all times during their installed life
(e) All cable hangers, cleats, saddles, brackets and similar supporting
devices shall be of an approved type and of adequate strength for the
cables they are supporting. They shall be treated to withstand site
conditions without corroding.
17.10.4 SUBMITTALS
17.10.6 QUALIFICATIONS
(a) Installer: All cable work shall be installed by personnel trade tested
and approved by Dubai Electricity and Water Authority (DEWA).
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
6. When pulling by winch or the like, fit a suitable tension gauge into
the haulage line between winch and cable. Pulling tension shall
not exceed the limit recommended by the cable manufacturer
7. Do not allow cable to twist or rotate about its longitudinal axis
8. Lay 3 phase groups of single core cables in trefoil formation. If
this is not possible obtain instructions from Engineer.
9. Install cables to allow any one cable to be subsequently removed
without disturbing the remainder.
(d) Identification
(e) Sealing
minutes.
v. self-supporting, non-setting and removable.
vi. accommodates movement due to settling, subsidence or
vibration.
vii. vermin proof.
(g) All cables shall be delivered on robust cable drums with cable ends
treated to form an effective seal. When a cable is cut from a drum the
cable end left on the drum shall be immediately sealed in an approved
manner to prevent the ingress of moisture.
(a) The contractor shall carry out the excavation and backfilling of cable
trench work.
(b) The contractor shall supply and lay the sand bedding, cables, sand
blinding, cable cover tiles and marking tape. He shall also supply and
lay cable route marker posts after the backfilling and compaction, has
been carried out.
(c) The sanding and laying of all cables shall satisfy the following
requirements:
(d) The contractor shall provide cable route markers to the approval of the
TABLE A
Distance over which parallelism Minimum Segregation Distance
exists between signal and power Requirement in mm
cables in meters Power cable
Instrumentation Signal Classification
Category to BS 6739 or equivalent
Cat. 2 Cat. 3
Maximum current 0 - <3 50 50
10 amps at any 3 - <10 100 100
phase voltage up 10 - <25 100 150
to 250 volts a.c. 25 - <100 150 200
or d.c. 100 - <250 200 250
250 - < 500 250 300
(a) Conduct field inspection and testing under provisions of Section 17.1.
17.11 TRUNKING
(a) The work of this section is integral with the whole of the Project
Documentation and is not intended to be interpreted outside that
context.
(b) Co-ordinate the work with all other services affecting the work of
this Section.
17.11.2 REFERENCES
(a) The Contractor shall supply and install the complete trunking
system as indicated on the Drawings and specified in this Section.
17.11.4 SUBMISSIONS
(a) General:
(a) The work of this section is integral with the whole of the Project
Documentation and is not intended to be interpreted outside that
context.
(b) Co-ordinate the work with all other services affecting the work of this
section.
(c) .
17.12.2 REFERENCES
17.12.3 DESCRIPTION
17.12.5 SUBMITTALS
17.12.7 CO-ORDINATION
(a) The work of this Section shall be completely co-ordinated with the
work of other services.
(a) The cable tray system shall be of one manufacturer and shall include
factory-made trays, tray fittings, connectors and necessary
accessories and supports to form a complete cable support system.
(b) The cable tray system shall include the following factory-made tray
elements:
1. Straight cable trays and ladders.
2. Fittings as horizontal and vertical bends of various angles,
crosses, tees, wyes, reducers, vertical riser elements.
3. Connectors.
4. All necessary fixing accessories.
ventilation. Cable tray shall be raised 15cm from finished floor level.
17.12.9 MATERIALS
(a) Drilling, machining or cutting shall not be carried out after application
of protective coat, unless previously agreed by the Engineer. If
cutting or drilling is necessary, edges shall be cleaned up and painted
with zinc based paint before erection.
(b) Installation of vertical runs of tray along the line of vertical expansion
joints in structure of the facility shall not be allowed.
(c) Cables shall be fixed to the trays by means of PVC covered saddles
17.12.11 ERECTION
(a) Cable trays arranged one above the other shall have spacing in
relation to their width not exceeding a ratio of 1:2 with a minimum
distance of 150mm.
(b) Supports:
1. Install fixings and supports.
i. At 3 metre centres or as shown on drawings
ii.150mm from bends, tees, intersections and risers
iii.As close as practicable to joints
iv.Each side of expansion joints.
2. Supports shall be selected from the following types, to suit the site
conditions:
i. M12 steel threaded drop rods fixed to ceilings complete with GI
channels or brackets
ii. Wall support brackets
iii. Cantilever arms
iv. Steel channels.
(c) The cable trays shall be fixed in accordance with site conditions and
manufacturer’s recommendations.
(d) Join cable tray and accessories with hardware per manufacturer’s
recommendations.
(e) Avoid mid-span joints.
(f) The Contractor shall submit, as required, all calculations relating to
tray work and tray supports, demonstrating acceptable mechanical
stresses and sag.
(g) Cable trays installed on roofs shall be supported using GI brackets or
concrete blocks. Removable cable tray cover shall be fitted.
(h) Access shall be available at all times to remove or replace cables with
a minimum of 400mm between trays and physical obstructions, A/C
ductwork etc.
(i) Provide adequate ventilation while tray installation is in progress.
17.12.12 EARTHING
(a) Provide all type test reports of cable trays for Engineer’s review before
order placement.
(b) Provide routine factory test reports of cable trays for Engineer’s
approval before despatch of trays.
17.13.1 Scope
17.13.2 References
17.13.4 Submittals
(a) Submit full technical details and conductor size calculations of each
type of cable or wire proposed
(b) Submit exact route of each cable or wire proposed.
(a) Generally:
1. Products used in the lightning protection system shall be copper or
an approved copper alloy, unless otherwise specified, specifically
manufactured for the purpose.
17.13.7 Testing
17.13.1 SUMMARY
(a) This section includes specification for steel cabinets for motor control
centers and distribution boards. This section also includes the
specification for GRP enclosure cabinets for motor control centers and
distribution boards for outdoor installation.
(b) This shall be read in conjunction with other related sections of the
specification and contract drawings.
17.13.2 REFERENCES
(b) In the case of conflict the Dubai Electricity and Water Authority
(DEWA) requirements shall take precedence.
(a) Deliver, store, protect and handle products to site under provisions of
Section 17.1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1.
(a) Boxes: Galvanized steel or stainless steel of grade 316 with minimum
sheet steel thickness of 2mm with panel fronts of thickness 2.0mm
minimum.
(b) Box Size: To suit equipment requirements.
(c) Backboard: Provide interior metal panel for mounting terminal blocks
and electrical components; finish with white enamel.
(d) Fronts: Lift-off hinge, held closed by lockable car type handles. Doors
shall close on to neoprene or soft rubber sealing strips held in place
mechanically.
(e) Knockouts: To suit conduit and circuiting arrangements.
(f) Provide metal barriers to form separate compartments wiring of
different systems and voltages.
(g) Provide accessory feet for free-standing equipment.
(h) Finish: In accordance with epoxy powder coated.
(i) Protection: Dust and vermin proof. Environmental protection to IP 54.
(a) General
1. Provide split type unit air conditioning for the enclosures with
MCC. The condensing unit shall be installed outside the enclosure
on concrete floor or separate foundation. Piping from the
enclosure shall be properly sealed to ensure the integrity of
protection IP classification.
2. Controlling of the unit shall be provided by internally installed
thermostat.
3. The doors shall be properly sealed with gaskets to prevent
leakage of cool air from inside the cabinet.
(e) Installation
(f) Cabling
i. Cables shall enter the cabinet below the ground via pre-cast
ducts within the plinth.
ii. All ducts entering the cabinet shall be sealed to the approval of
the Engineer. All ground areas shall be reinstated.
(g) Foundation/plinth
“STATION NAME”
DANGER
400-VOLT ELECTRICAL APPARATUS
17.13.14 ACCESSORIES
17.13.15 STANCHIONS
(a) Stanchions shall be provided for mounting local isolators for extract
fans, which are installed on the roof and local emergency control of
pump motors. The support structures for the stanchions shall be made
of stainless steel of grade 315. The structure shall be extended to
support the control isolators and switches at an approximate height of
0.5 meter from fixing level. The cables shall be top or bottom entry, as
per application arrangement.
(b) Stanchions for emergency stop push buttons, control devices etc.,
shall be mounted on a plinth and or bolted through roof structures or
directly to the floor. Provide canopy on the top of the switch assembly.
(c) Structures and equipment shall be weatherproof to IP 65.
(d) Heights of stanchions and mounting position of control devices shall
be uniform within same or similar areas. Where mounting height is not
shown or specified, instructions shall be obtained from the Engineer.
(e) All support structures, in general, for electrical fittings shall be made of
stainless steel grade 315. Fastenings shall be of the same material as
the support structures.
(c) Install enclosures and boxes plumb. Anchor securely to wall and
structural supports at each corner under the provisions of Section
17.1.
(d) Install cabinet fronts plumb.
17.13.18 CLEANING
17.14.1 SUMMARY
(a) This section includes the specification for the grounding system and
provision for bonding all the conducting parts to the grounding system.
(b) A new grounding system shall be provided for the facilities being
constructed under this contract and shall incorporate the features as
described in this section. The grounding system shall provide
protection and safety to personnel against electric shock and
protection of equipment against damage due to ground fault in the
electrical system.
17.14.2 REFERENCES
(a) Shall be the ground rod electrode type, unless impracticable to drive
deep into the particular soil.
(b) Ground rod electrodes: 20mm diameter comprising a Solid Copper rod
with hardened tips and threaded top ends.
(c) Shall be 3.6m long, in 1.2m sections coupled by strong bronze
couplers.
(d) Ground electrodes shall be solid copper or steel cored copper with a
metallic bonded outer surface. Electrodes shall be provided with
special hardened tips and caps to avoid distortion being driven into the
ground. Approved non-ferrous clamps for connecting the electrodes
to the copper strips leading to the disconnecting links shall be
provided.
(a) Shall be either Copper; or Cast iron where artificial treatment of soil is
necessary because of high soil resistivity.
(b) Description: Metallic-salt-filled tube electrode.
(c) Shape: Straight or as specified.
(d) Length: 2400 mm or as specified.
(e) Connector: U-bolt pressure plate.
(a) Main grounding conductors shall comprise tinned copper tapes of hard
drawn, high conductivity copper strip or stranded copper conductor.
(b) Sized to meet requirements of latest edition of BS 7671 and to meet
DEWA regulations.
(c) Grounding conductors shall be adequately sized for the maximum
fault current and in no case shall be smaller than:
1. 38mm x 4mm for Low Voltage equipment.
17.14.17 INSTALLATION
(d) Bonding
(g) Interface with lightning protection system installed for buildings under
Section 17.1.
17.15.1 SUMMARY
17.15.2 REFERENCES
17.15.3 SUBMITTALS
(b) Products:
17.15.6 STANCHIONS
(a) Stanchions shall be provided for mounting local isolators for extract
fans, which are installed on the roof and local emergency control of
pump motors. The support structures for the stanchions shall be made
of stainless steel of grade 315. The structure shall be extended to
support the control isolators and switches at an approximate height of
0.5 meter from fixing level. The cables shall be top or bottom entry, as
per application arrangement.
(b) Stanchions for emergency stop push buttons, control devices etc.,
shall be mounted on a plinth and or bolted through roof structures or
directly to the floor. Provide canopy on the top of the switch assembly
(c) Structures and equipment shall be weatherproof to IP 65.
(d) Heights of stanchions and mounting position of control devices shall
be uniform within same or similar areas. Where mounting height is not
shown or specified, instructions shall be obtained from the Engineer.
(e) All support structures, in general, for electrical fittings shall be made of
stainless steel grade 315. Fastenings shall be of the same material as
the support structures
17.16.1 SUMMARY
17.16.2 REFERENCES
17.16.3 SUBMITTALS
markers.
(a) Nameplates:
1. External labels: Clear perspex back engraved in Arabic and
English with chamfered edges fixed with chrome plated nuts and
bolts with slotted holes to allow for expansion of the label.
2. Internal labels: Multi-layered plastic to an approved design
engraved in Arabic and English, and fixed with chrome plated nuts
and bolts or a permanent adhesive.
3. Adhesive labels will not be acceptable for internal components and
fuses.
4. Labels for internal components and Fuses shall have circuit
designations, which can be correlated with the drawings.
5. Labels shall not be attached to trunking covers or other readily
removable items.
(b) Locations:
17.16.10 APPLICATION
17.17.1 SUMMARY
(a) This specification section covers the supply and installation of power
factor correction equipment operating on electrical power systems up
to 600-volt ac 50 Hz.
(b) Coordinate the work with other relevant items as specified in the
related sections below.
17.17.2 SCOPE
17.17.3 REFERENCES
17.17.8 QUALIFICATIONS
(a) Deliver, store, protect and handle products to site under provisions of
17.1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1 – Provisions
for Electrical Requirements.
(a) Capacitors shall comply with BS 1650 and shall be of a dry metalised
film construction, containing no liquid and must have low losses
(typically 0.5 Watts/kVAr).
(b) Each capacitor shall be housed in a sealed container and be fitted
with a fail-safe, pressure sensitive disconnect device.
(c) Each capacitor shall be equipped with suitable discharge resistors to
reduce the voltage to less than 50V in one minute, or less, after supply
disconnection.
(d) The capacitors shall be housed in a metal enclosure, forming part of
the motor control centers. The enclosure size should allow enough
space and cabling etc., for at least one additional capacitor unit to be
fitted at a later date.
(e) Provision shall be made to ensure that a connection point is available
for a series connected, de-tuning reactor in case of problems with
harmonics.
(f) The equipment must comply with BS 800 with respect to electrical
interference.
(g) The capacitors shall be protected by a fused switch-disconnector or
circuit breaker on the LV motor control center.
(h) The capacitor manufacturer must recommend the maximum fuse or
circuit breaker that will ensure the protection of each capacitor bank.
(i) All power and control cables used within the capacitor bank enclosure
must be in accordance with BS 6231 Type BK.
(j) Capacity: Approved kVAR at rated voltage and frequency to meet
Dubai Electricity and Water Authority (DEWA) requirements.
(k) Operating Temperature Limits: 110 percent rated voltage in ambient
air temperature between 0 degrees C and 55 degrees C.
17.19 FUSES
17.19.1 SUMMARY
circuits.
(b) This shall be read in conjunction with other related sections of the
specification and contract drawings.
17.19.2 REFERENCES
17.19.3 SUBMITTALS
17.19.5 QUALIFICATIONS
(a) Deliver, store, protect and handle products to site under provisions of
Section 17.1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1 – Provisions
for Electrical Requirements.
17.20.1 SUMMARY
(a) This section includes specification for switchboards which are factory
built and supplied as assembled item.
(b) This shall be read in conjunction with other related sections of the
specification and contract drawings.
(c) This section shall be applicable to all LV Switchgear and Main LV
Distribution Boards (MDBs) being supplied for this project.
17.20.2 REFERENCES
purposes.
(n) EN 60529 - Specification for degrees of
protection provided by enclosures
(IP Code).
(o) BS 159 - Specification for high voltage
busbars and busbar connections.
(p) EN 60073 - Specification for coding of indicating
devices and actuators by colors and
supplementary means.
(q) BS 7625 - Specification for voltage
transformers.
(r) BS 921 - Rubber mats for electrical purposes.
(s) EN 60903 - Specification for gloves and mitts of
insulating material for live working.
(a) All FBA's shall consist of a number of cubicles of equal height and
depth mounted side by side to form a composite board of uniform
appearance.
(b) Assemblies shall be front access only, unless specified otherwise;
constructed such that doors and covers are flush with one another and
aligned to a common vertical plane; manufactured from mild steel
having the following minimum thickness:
(c) All except mounting plates shall be stove enameled to BS 4800 shade
18E51, 0.075mm enamel thickness minimum.
(e) All assemblies shall be vermin proof, and dust and damp protected to
BS EN 60529 (IEC 529) Type IP54
17.20.6 SUBMITTALS
17.20.10 QUALIFICATIONS
(a) Deliver, store, protect and handle products to site under provisions of
section PS-10/1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under section PS-10/1.
(a) Provide equipment suitable for climate specified under this section.
(b) Mounting
1. Floor
3. Post/Column
(c) Cubicles
(a) General
(b) Construction
(c) Labels
2. All labels shall be engraved in both Arabic and English and shall
be approved by the Engineer.
(g) Annunciation
Audible and visual annunciation for each panel shall be provided. The
audible annunciation for minor fault and major fault shall be
differentiated by separate tones.
Each panel shall be provided with lamp testing switch and re-setting
facility.
4. The air circuit breaker shall be provided with over current, short
circuit and earth fault protection having the following
characteristics:
i Adjustable long time delay current setting (50% - 150%) with
varied tripping time.
ii Adjustable short time delay current setting (400% - 1000%)
with variable tripping time.
iii Instantaneous tripping for heavier over current adjustable from
400% - 1600% of base current.
iv Adjustable earth fault trip current setting (20% - 60%) with
variable tripping time.
shall be of the spring loaded, self aligning type. The arc contacts
shall be arranged to make before and break after the main
contacts.
10. The Main Incoming Circuit Breakers shall be provided with cable
boxes to suit the incoming cables from the transformers which are
supplied and installed by the Dubai Electricity & Water Authority
(DEWA).
11. Circuit breakers shall be tropicalized to operate continuously in an
ambient temperature of 55°C and high relative humidity.
12. Type test certificate for each size of circuit breakers and MCCB’s
from an internationally recognized testing authority acceptable to
the Engineer shall be provided.
(n) Instruments.
withstand twice the rated full scale voltage for 1.0 minute without
damage.
7. Three Ammeters or a single ammeter with selector switch shall be
provided to read the current of each phase, as indicated on the
Drawings.
8. The voltmeter selector switch shall be of the rotary type with cam
operated contactor and shall have (7) positions off, R-Y, Y-B, R-N,
Y-N, B-N.
9. Single and poly phase power factor meters with associated current
and potential transformers shall be provided as required and
specified herein.
Current Transformers:
1. Current transformers shall be of the bar primary type, air cooled
and suitably insulated. The current transformers shall be of Class
C accuracy for indication and Class CM accuracy for metering
purposes.
2. Current transformers shall be rated not less than 5 VA and shall
have thermal and mechanical rating at least equal to those of the
main circuit breakers.
KWH Meters:
17.20.17 MATERIALS
(a) Busbars
shall be easily accessible from the front or top of the board and
shall have a lockable cover. Provision for storing the links nuts
and bolts shall be made in the switchboard.
(b) Labels
(c) Fuses
1. Types
2. Terminations
i. All wiring shall have crimped terminations, only one wire being
held by any one crimp. Crimped lugs shall be of the insulated
type without conductor exposure between the crimp and wire
insulation.
ii. The type of crimp used shall be appropriate for the type of
terminal to which it connects.
iii. Terminations shall be neatly arranged leaving adequate length
for one termination.
iv. All terminal blocks for the connection of small wiring shall
comprise shrouded anti-tracking moulding of melamine
phenolic or comparable material with provision for securing
conductors either by high tensile screws and clamps or
alternatively in the case of small telephone type conductors by
solder tag connection.
v. Terminal blocks shall be arranged to facilitate easy access to
both terminals and wiring ends. Connections for outgoing
circuits to auxiliary pilot cables shall be provided with test links.
vi. Removable rail terminals shall be provided for all wiring,
mounted at an angle to provide ease of access.
Disconnecting- link type terminals shall be provided for
analogue signal circuits, external control devices and all
alarm/telemetry signals. Sufficient, suitably sized earth
terminals and end stops shall also be provided.
vii. The gap between gland plates and associated terminals shall
be such that conductors can be safely manipulated and
connected without damage. Terminals shall face the door of a
cubicle for ease of connection.
viii. Barriers shall be provided on all terminal banks, to group
terminals into logical divisions. Power terminals of different
phases shall be barriered from each other and separated from
control terminals.
ix. In all cases care shall be taken to ensure that terminals are
easily accessible after all wiring and plant cabling has been
installed and terminated. All connections shall be made on the
front of terminal blocks.
x. No more than two conductors shall be connected to one side
3. Manner of Installation
1. Indicating Lamps
2. Pushbuttons
(k) Instruments
(o) Interlocking
master clock.
The details of the functions are as follows. Signals /Information to
be provided for each breaker
ii. Commands from the operator station and from the Breaker
Module.
• Open / Close Command.
• Fault Reset at Breaker module, at the System Engineer’s
station and Electrical Engineer’s station.
v. Diagnostic Information: -
Following information shall be provided at the Electrical
Engineer’s station and Operator workstation.
17.20.18 ACCESSORIES
(a) For each switchboard the Contractor shall supply the following
equipment:
been approved by the Engineer and written permission given for their
dispatch to site.
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
17.20.21 INSTALLATION
(b) Conduct field inspection and testing under provisions of section PS-
10/1.
(c) Each control panel shall be tested to demonstrate correct operation of
relaying, fault protection and control equipment. All isolators, fuse
switches, oil and air circuit breakers shall be tested for correct
operation and fault operation. All associated cabling shall be tested for
correct phase connection and insulation resistance.
17.20.24 DEMONSTRATION
17.20.25 TRAINING
17.20.26 MAINTENANCE
17.21.1 SUMMARY
(a) This section includes specification for motor control centers including
their controls and accessories.
(b) This shall be read in conjunction with other related sections of the
specification and contract drawings.
(a) Furnish, install and test the intelligent type, communications capable
motor control centers as shown in the drawings in accordance with
these specifications.
(b) Motor control centers shall be sized to include all equipment, spares
and future provisions as shown in the drawing.
(c) Commissioning of the Motor Control Center shall be by the
manufacturer.
17.21.3 REFERENCES
17.21.4 SUBMITTALS
(a) Perform Work in accordance with NEMA ICS 2.3 or ISO 9002 or other
standards as directed by the Engineer.
(b) Maintain one copy of each document on site.
17.21.7 MANUFACTURERS
(a) Deliver, store, protect and handle products to site under provisions of
Section 17.1.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1.
(c) Deliver in 1.2m maximum width shipping splits, individually wrapped
for protection, and mounted on shipping skids.
(d) Store in a clean, dry space. Maintain factory wrapping or provide an
additional heavy canvas or heavy plastic cover to protect units from
dirt, water, construction debris, and traffic.
(e) Handle in accordance with NEMA ICS 2.3 or other approved standard.
Lift only with lugs provided for the purpose. Handle carefully to avoid
damage to motor control center components, enclosure, and finish.
(a) Multi-cubicle suite, free standing floor mount type motor control
centers shall be provided according to BS EN 60439 for factory built
assemblies consisting of units for incoming feeder, outgoing feeders,
variable frequency drives, motor starters, integral distribution boards,
PLC/SCADA interfaces and VDU etc. and other associated items.
(b) Single cubicle panel up to 1200 mm high by 900 mm wide shall be
designed for wall mount for indoor installations. Bigger cubicles shall
be free standing floor mount type.
(c) Ratings and references: BS EN 60439 (IEC 439).
(d) Incoming circuit isolation: Circuit breaker.
(e) Voltage Rating: 400 volts three phase, four wire, 50 Hz or as specified
for other voltages.
(f) Integrated Equipment Short Circuit Rating: 31 MVA (43 KA) at 400
volts for 1 second duration.
(g) Horizontal Bus: Copper, with a continuous current rating of specified
amperes. Include copper ground bus entire length of control center.
(h) Vertical Bus: Copper.
(i) Configuration: Units front mounting only, accessible from the front.
(j) Feeder Tap Units: Circuit breakers or Fusible switches as indicated.
(a) The distribution board shall be an integral part of the motor control
center as specified in this section and as shown in the drawing. A
separate compartment in the cubicle shall be assigned for the
purpose.
(b) The distribution boards shall be provided with fixed cover and a
hinged door with padlock, which can be, opened without any
obstruction about 120 Degree and conduit knockouts from the top and
bottom. The hinged door with a lock and key shall be integral part of
the fixed cover.
(c) The cabinet shall be constructed so that it is necessary to open the
door to operate Miniature Circuit Breakers (MCB) or ELCB.
(d) A circuit label shall be provided to indicate the circuit served by each
MCB.
(e) Ratings:
(a) All signal transfer between the MCCs and the central control system
(SCADA) shall be through communication bus using high speed
communication protocol. All the starters and main Incomer breakers
shall have electronic solid state, multifunction, microprocessor based
relays with communication capabilities. These relays shall perform all
the functions such as Status Indications, Motor parameter monitoring,
allow for local and remote control, protective functions, and shall
provide diagnostic information about the motor and the relay itself.
2. Commands from the operator station and from the Starter Module.
i Start / Stop Command.
ii Fault Reset at Starter module, at the System Engineer’s
station and Electrical Engineer’s station.
3. Monitoring Functions: -
Following parameters shall be available for monitoring at the
Operator workstation and Electrical Engineer’s station.
i Phase Currents,
ii Average Current,
iii Full Load Current.
iv Current Imbalance percent.
v Percent Thermal capacity utilized / available.
vi Power Factor,
vii Voltage,
viii Running Hours.
ix Trends, Graphic Displays for monitored parameters
4. Protective Functions:-
Station.
i Thermal Overload- Trip Class adjustment.
ii Under load,
iii Jam protection,
iv Stall Protection,
v Current Imbalance,
vi Phase Loss,
vii Zero Sequence ground fault,
viii Start Limitation,
ix Under voltage Protection,
x PTC Thermister input,
(b) Also comply with the requirements specified under Control and
Instrument section.
1. Diagnostic Information: -
Following information shall be provided at the Electrical Engineer’s
station and Operator workstation.
i Motor Controller Real Time status,
ii Warning Status,
iii Time to Reset,
iv Trip Status,
v Time to overload trip,
vi History and Cause of previous trips (minimum 5)
vii Communication failure.
(c) Also comply with requirements specified under Control and Instrument
section.
17.21.19 CONSTRUCTION
(a) General
6. operation of the MCC shall be from the front with all switches
being accessible from floor level.
7. shipment shall be made in sections to facilitate field handling, and
the shipped sections shall be joined together to form a complete
back-to-wall or back-to-back unit assembly as indicated on the
Contract Drawings.
8. transit sections of the MCC shall be fitted with removable lifting
lugs.
9. at one end of each MCC, an empty panel shall be provided, of the
wardrobe type, suitable for mounting electronic control equipment,
PLC. etc. Where necessary, (e.g. to allow extension), the busbars
shall be carried through the enclosure in a purpose made steel
plate trunking. This panel shall be provided in addition to any
panels required for an intelligent motor control center.
10. MCC frames, covers, doors and mounting plates shall be
fabricated from a minimum 2 mm thickness mild steel pressed or
rolled to shape and neatly finished and free from any joints or
sharp edges. The MCC plinth/bed frame shall have a 3 mm
thickness minimum.
11. MCC shall have a minimum protection rating of IP54 to BS EN
60529 unless otherwise indicated. The MCC shall be vermin-proof.
12. individual starter shall be housed in separate
compartment/section.. All full voltage starter units for sizes up to
and including 100 kW shall be of the drawout type (unless
indicated or specified otherwise). Draw-out provisions shall include
a positive guide rail system and stab shrouds to absolutely ensure
alignment of stabs with the vertical bus. Draw-out units shall have
a tin-plated stab assembly for connection to the vertical bus. No
wiring to these stabs shall extend into the bus compartment. The
MCC shall include a set of main copper busbars and the required
number of dropper busbars to suit the columns of starters. Interior
of all units shall be painted white for increased visibility. Units shall
be equipped with side-mounted, positive latch pull-apart type
control terminal blocks rated 600-volts. All drawout units shall be
secured by a spring-loaded quarter turn indicating type fastening
device located at the top front of the unit. Each unit compartment
shall be provided with an individual front door.
13. an arrangement shall be incorporated which will ensure that, when
the starter is withdrawn, the aperture can be padlocked to prevent
unauthorized insertion of starters.
14. arrangements of starters in the MCC shall be organized to suit the
most practicable arrangement with regard to temperature rise and
location of Duty 1 and Duty 2 starters.
15. main busbar ratings above 200A, the busbar arrangement shall be
third party certified by an independent testing authority (e.g.
ASTA). Busbar arrangements for 200A and below need not be
certified.
(b) Mounting
1. Floor
Fixing shall be by not less than four holding down bolts per
assembly section, located around the periphery of the section.
The fixing shall not be visible from outside the section, but shall be
readily accessible from within.
2. Wall
At least four lugs shall be provided for bolting to the wall. Fixing
holes shall not be provided inside the assembly, which shall stand
at least 10mm off the wall surface.
earthed.
9. cableways shall be provided as necessary to ensure that apart
from inter-connections no cable routed to one cubicle shall pass
through any other cubicle.
(i) Labels
17.21.20 BUSBARS
(a) All busbars shall extend through the length of the board with same
cross section throughout unless indicated otherwise.
(b) A Copper Earth Busbar sized at least 50% of the phase busbars shall
be provided along the full length of the board.
(c) Busbars shall be adequately supported by porcelain or moulded
insulators spaced on suitable centers so that the complete assembly
can withstand the maximum mechanical stresses to which it may be
subjected to under fault conditions.
1. wiring shall have crimped terminations, only one wire being held
by any one crimp. Crimped lugs shall be of the insulated type
without conductor exposure between the crimp and wire insulation.
2. type of crimp used shall be appropriate for the type of terminal to
which it connects.
3. terminations shall be nearly arranged leaving adequate length for
one re-termination.
(a) The MCC shall contain incoming and outgoing circuit breakers and
fuse switches, as indicated on the Contract Drawings as specified in
Section 17.2 and Section 17.3.
(b) Main circuit breaker shall be externally operated and interlocked with
the cubicle door. The unit shall also be capable of being padlocked in
the ”OFF” position.
(c) Fuse switches used in MCCs shall comply with BS EN 60947-3, be of
the double-break design and meet utilization category AC23.
17.21.23 DISCONNECTS
17.21.28 INSTRUMENTATION
(b) Power Monitoring Unit: The unit shall be microprocessor based and
shall be capable of measuring and indicating incomer currents on
each phase, voltages between phases and phase to neutral, active
and reactive powers, power factor and total energy consumed. The
kWH meter reading shall be stored in password protected non-volatile
memory. The unit shall be mounted on the incomer cubicle at a height
not above 1.6 meter from floor level. The backlit display unit shall be
high contrast type, having light emitting characters of height not less
than 15 mm. The unit shall work on the system voltage without the
need for any separate auxiliary power. The function of power
monitoring unit for remote indication and alarm shall be included.
1. Overcurrent unbalance
2. Single phase
3. Earth fault
(d) Solid-state electronic protection relays shall be used for motors rated
1. Overload
2. Overcurrent
3. Single phase
4. Earth fault
5. Under voltage
6. Over voltage
(f) All motor overload relays shall include a manual resetting facility.
(a) All the starters and main Incomer breakers shall have electronic solid
state, multifunction, microprocessor based relays with communication
capabilities. These relays shall perform all the functions such as
Status Indications, Motor parameter monitoring, allow for local and
remote control, protective functions, and shall provide diagnostic
information about the motor and the relay itself. All Intelligent MCCs
and LV switchboards shall be time synchronized with the SCADA.
SCADA will be the master clock.
(b) Commands from the operator station and from the Starter Module.
1. Start / Stop Command.
2. Fault Reset at Starter module, at the System Engineer’s station
and Electrical Engineer’s station.
(c) The CMU shall pass data to a PLC from the starters, controllers and
overload relays. The master or the host network's baud rate (speed of
upper network passing data to PLC) shall be independent of the
CMU's subnetwork baud rate. The master or host network's baud rate
shall be established via the PONI communications module while the
CMU's sub-network baud rate shall be switch selectable at CMU.
(d) The program directing the functions or the CMU shall be permanently
stored in the CMU. The addresses, types of devices and descriptions
shall be stored in memory during the learn mode and shall also be
retained throughout a power loss. Unless there has been a change, it
shall not be necessary to re-enter the learn mode after a power loss.
(e) CMU shall have an 8-digit alphanumeric display to monitor active
data, trip data or set points, which are available from the individual
Motor Control devices. CMU shall have separate LEDs to indicate
which group of data is being displayed, as selected through
membrane-type alphanumeric pushbuttons by the user. CMU shall
have alphanumeric display to indicate the address of the control
device for which data is being displayed. CMU shall have membrane
type push buttons to allow the user to step up or down to select the
control device to be displayed. CMU shall have separate LEDs to
indicate “operational status” of CMU and "alarm" status on any one of
(a) Each motor control center shall contain power factor correction
capacitors to improve the overall power factor to between 0.93 logging
to unity. Provide reactors in series, as per the DEWA requirement.
(b) Where there is a large number of smaller drives, up to and including
11kW, a single power connection unit shall be used to improve the
power factor, as indicated on the Drawings. A minimum of four
connection stages shall be provided for common MCC capacitors.
(c) For motors above 11kW, individual power factor correction equipment
shall be provided to improve the power factor to between 0.93 lagging
and unity when the drive is operating at its duty point.
(d) Each motor shall be provided with a three-phase capacitor. Capacitors
shall be mounted in the motor control center either within the starter
compartment or in an adjacent and fully interlocked compartment.
(e) The rating of the capacitor must not exceed 60% of the magnetizing
KVAR of the motor. A separate contactor shall be provided. Dual
speed, pole change, PAM and reversing motors shall also have
separate contactors to switch the capacitors out of circuit
independently of the motor. Additional capacitors and contactors may
also be required by some of these drives to correct the power factor
throughout the speed variation.
(f) Capacitors shall be connected after the line contactor but before the
motor protection. All capacitor connections shall be fused at the take-
off point.
(g) Capacitors shall comply with BS 1650 and shall be of the dry
metalised film construction type, as specified in Section 17.18,
complete with discharge resistances. A metal enclosed terminal box
with screw fixed cover and cable entry sealing shall be provided.
(h) A label shall be provided warning that discharge resistances are fitted.
(i) Capacitors containing polychlorinated biphenyls or askarels will not be
acceptable.
17.21.33 ACCESSORIES
17.21.35 PREPARATION
17.21.36 INSTALLATION
(h) Provide sufficient space to allow for doors to open fully without fouling
with other items of equipment or other open doors.
17.21.37 COMMISSIONING
17.21.39 TRAINING
17.22.1 Summary
17.22.3 References
17.22.4 Submittals
(a) The variable speed drives shall be of the electronic, pulse width
modulating (PWM), variable frequency type with an output suitable for
controlling standard industrial squirrel cage motors, with a
synchronous speed as specified in the pump section.
(d) The contractor shall provide certified test results to confirm that the
controller has been tested to substantiate the designs according to
applicable standards. The test shall verify not only the performance of
the unit and integrated assembly, but also the suitability of the
enclosure venting, rigidity and bus bracing. In addition, the unit shall
(g) The AC Drive shall be submitted to a Hi-Pot test with all enclosed
devices mounted and wired, prior to shipment
17.22.9 Rating
17.22.10 Enclosure
(a) Deliver, store, protect and handle products to site under provisions of
Section 17.1 - Material and Equipment.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under Section 17.1 – Provisions
for Electrical Requirements.
(a) Provide the following spare parts for each type and size drive
specified for each pump station (cost included in the drive price):
1. printed circuit board – one of each type
2. power diode – two
3. power transistor – one pair
4. fuse of each type and rating – 100 percent (power and control)
Spares shall be packaged for long-term storage. Identify each item
with manufacturer name, description and part number on the exterior
of the package. Include description of drive reference to which the
spares belong.
Conduct field test to measure the harmonics with all the drives
(excluding dedicated standby unit), regardless of whether filters,
chokes etc., are installed or not, running at 100 percent and 50
percent loads, for at least 3 hours duration under each loading
condition. If drives do not meet the specified performance, Contractor
shall provide an acceptable solution at no additional cost to the owner.
17.22.16 Warranty
(a) The AC Drive shall convert the input ac mains power to an adjustable
frequency and voltage as defined in the following sections.
(b) The input power section shall utilize a full wave bridge design
incorporating diode rectifiers. The diode rectifiers shall convert fixed
voltage and frequency, ac line power to fixed dc voltage. This power
section shall be insensitive to phase rotation of the ac input line.
(c) The output power section shall change fixed dc voltage to adjustable
frequency ac voltage. This section shall preferably utilize 3rd
generation insulated gate bipolar transistors (IGBT) or intelligent
power modules (IPM) with current source design as required by the
current rating of the motor.
(d) A DC link choke smoothing reactor shall be included to limit fault
throughput
(e) The AC drive shall be designed for both manual and automatic speed
control. The manual speed control shall be by means of a hand-
adjusted potentiometer.
(f) The starting arrangement shall include a ramp for speed control so
that the starting current remains within the limit of normal rated current
of the motor.
(g) The drive shall incorporate facility to allow the connection of an
Emergency Stop Push Button to ensure effective direct stopping of the
drive, if dangerous situations arise. The means provided shall include
an air-break on-load contactor suitable to open directly by operation of
the emergency push button. The arrangement shall not:
1. inhibit any in-built deceleration provided by the controller
2. produce additional safety hazards
3. cause damage to the controller
17.22.18 Protection
(a) Upon power-up the AC Drive shall automatically test for valid
operation of memory, option module, loss of analog reference input,
loss of communication, dynamic brake failure, dc to dc power supply,
control power and the pre-charge circuit.
The AC Drive shall have solid-state I²t protection that is UL Listed and
meets UL 508 C as a Class-10 overload protection and meets IEC
60947.
The protection shall be provided for TYPE 2 co-ordination.
For a fault condition other than a ground fault, short circuit or internal
fault, an auto restart function will provide programmable restart
attempts. The programmable time delay before restart attempts shall
be adjustable from 10 second to 10 minutes.
(a) The AC Drive shall self-configure to the main operating supply voltage
and frequency.
(b) Upon power-up, the AC Drive shall send a signal to the connected
motor and store the resulting electro-mechanical resistance data into
memory. The inductance data will be measured during no-load
operation when operating at a frequency equal to power frequency.
The AC Drive shall automatically optimize the operating
characteristics according to the stored data.
(c) The AC Drive will be factory pre-set for the application
(d) A choice of three types of acceleration and deceleration ramps will be
available in the AC Drive software; linear, S curve and U curve.
(e) The acceleration and deceleration ramp times shall be adjustable from
.1 to 500 seconds.
(f) The memory shall retain and record run status and fault type of the
past 8 faults (minimum).
(g) Slip compensation shall be a software-enabled function.
(h) The starter shall have a PID control system integrated as standard to
accept the external signals coming from sensors and transducers in
the pumping application.
(i) Following configurable inputs and outputs, as minimum, shall be
provided which can be used to interface the drive with the control
system for remote applications:
(j) Provide communication interface and facility for control to integrate the
operation of the system. The facility shall be compatible with the
arrangement for other equipment in the MCC and suitable for
operation of the drive with PLC through RS485 serial interface.
(k) The drive controller shall incorporate a user friendly programmer
keypad having LCD panel in “Plain Language Text in English” with
help feature to enable easy setting up of parameters, and running the
drive diagnostic program with out referring to the instruction manual.
Parameter setting shall be password protected. The man/machine
interface facility for parameter setting shall include:
1. menu selection
2. parameter setting
3. speed potentiometer
(l) The display will be a high resolution, LCD backlit screen capable of
displaying graphics such as bar graphs as well as alphanumeric
characters, simultaneously. The display panel shall be used to monitor
the electrical metering parameters by menu driven selection.
This shall include:
1. input/output currents
2. input/output voltages
3. Input/output frequencies
4. kilowatt
5. running hours
(m) The following operator devices, either door mounted or unit mounted
but accessible without opening the door, shall be included:
1. start
2. stop
3. emergency stop
4. fault reset
5. local/remote selector
6. hand/off/auto selector
7. heater on/off
(n) The AC Drive shall have LEDs mounted on the front panel to indicate
functional status
This shall include:
1. green LED – system healthy
2. red LED – drive faulty
3. red LED – motor faulty (Thermal)
4. white LED – motor running
5. amber LED – overload alarm
6. red LED – emergency stop
17.22.20 Control
The control power for the digital inputs and outputs shall be rated for
24 VDC.
The internal power supply unit shall incorporate automatic current fold-
back protection facility to protect it, if incorrectly connected or shorted.
The transistor logic outputs shall be current limited and shall be
protected, if shorted or excess current is pulled.
17.22.21 Cables
(a) Cables between the drive and motor shall be sized and insulation
grade selected based on the manufacturer recommendation for the
particular installation considering the distance between them. Multi-
core power cables shall be armored and XLPE insulated. The armor of
the cable shall be cross-bonded to earth. All signal and control cables
shall be shielded.
Any restriction on the length of the cable shall be taken into care and if
required, output reactors shall be provided with suitable compensation
for output torque.
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
17.22.24 Installation
(a) Conduct field inspection and testing under provisions of Section 17.1 -
Quality Control.
(b) Conduct field inspection and testing under provisions of Section 17.1 -
Provisions for Electrical Requirements.
(a) Prepare and start systems under provisions of Section 17.1 - Quality
Control.
(b) Prepare and start systems under provisions of this section - General
Equipment Provisions.
(c) The manufacturer’s trained service test technician shall perform start-
up and commissioning of the VFD. He shall perform all the adjustment
and settings as per the field requirements.
17.22.27 Demonstration
17.22.28 Training
17.22.29 Maintenance
17.23.1 Summary
17.23.2 Scope
(a) Provide Two independent UPS systems, site rated for maximum site
ambient temperature of ratings as indicated on the drawings.
(b) Provide factory-assembled and pre-wired equipment consisting of
rectifier, inverter, battery charger, battery, control equipment, static
switches etc. to provide an uninterruptible power supply system.
(c) Provide all labor, materials, equipment, services and accessories
necessary to furnish and install the work of this Section, complete and
functional, as indicated in the Contract Documents and as specified
herein.
17.23.3 References
(a) The static uninterruptible power supply (UPS) system shall provide
high quality sinusoidal AC power required for loads such as
1. Emergency lighting
2. CCTV System
3. Control & Instruments
4. SCADA System
(b) The UPS system shall provide true uninterrupted supply against
17.23.8 Qualifications
(a) Deliver, store, protect and handle products to site to meet site ambient
requirements specified elsewhere.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under this section - General
Equipment Provisions.
(a) The UPS system shall comprise of rectifier, battery charger and
inverter modules.
1. The UPS system shall be designed in such a way that any spare
part, printed circuit board, sub-assembly or component, can be
replaced without any adjustment.
2. It shall supply clean, uninterrupted power to the critical loads and
meet the following specifications.
3. Transformers shall be manufactured using vacuum pressure
impregnated insulation.
(b) During normal operation, shall be powered from the mains through the
rectifier and the inverter. The rectifier shall also supply current to
charge and maintain the battery in a fully charged state.
(c) When the mains is outside the operation limits or has failed, the
battery supplies the inverter, which in turns supplies the load. On
restoration of normal condition of the mains supply, the UPS shall
automatically return to its normal mode of operation
(d) A static switching arrangement shall be included to bypass the UPS
system for maintenance or outage, and supply power to load from
mains without power break.
(e) The UPS cabinet shall be designed such that all components are
removable from the front, cable entry by floor mounted gland plates.
(e) Include communication interface to connect to the existing SCADA
17.23.14 Rectifier/Charger
Input systems
Voltage 400 volts +/- 10%
Wiring 3-phase, 4-wire + Earth
Frequency 45 to 55 Hz
Grounding systemTNS
17.23.15 Battery
(a) The battery shall be of sealed lead acid maintenance free type and
sized for the pre-selected time with the UPS operating at rated load.
The battery set shall be installed in similar cabinet finish as the UPS
unit.
(b) The battery system shall be sized to maintain full load for a period of
30 (thirty) minutes. However, it shall be possible to supply 50% load
for two hours.
17.23.16 Inverter
(a) The inverter shall be of transistorized PWM type, rated power at 0.8
p.f.
Output
Rated Voltage 220/400 volts (+/- 1%), 50Hz (+/-0.25 Hz).
Wiring 3-phase, 4 wire + Earth
Transient voltage and Regulation:
Voltage transients shall not exceed +/- 5% for a 100% load step
change and the return to steady state value shall be in less than 20
milliseconds.
Harmonic distortion: Less than 4% THD
Efficiency: For 100% to 50% load > 90%
Audible noise: 65 dBA @ 1.5m
(a) The static switch shall have anti-parallel connected thyristor bank for
instantaneous load transfer between the inverter and the reserve
mains supply.
Manual bypass switch system of full UPS shall be integrated into the
UPS so that load can be transferred to mains supply WITHOUT break
for maintenance of UPS. Procedure for transfer to maintenance
bypass and back to UPS shall be controlled by the bypass menu of
the UPS, thus eliminating possibility of causing disturbance of load by
operator who may be unaware of correct procedures.
(a) Monitors
The following status information shall be monitored by indicating lights
on the front panel of the UPS
rectifier-charger on
load on inverter
load on Mains bypass
alarm
inverter shutdown imminent
boost charge
battery high temp. alarm
(b) Alarms
An audible alarm shall warn the user of faults or operating problems.
The system shall be equipped with an alarm off button. Metering
values displayed on an alpha-numeric display.
(c) Meter
The following measurements shall be available:
inverter output voltage (L-L)
inverter output frequency
inverter output currents
voltage across battery terminals
battery current (charge/discharge)
mains input voltages (L-L)
rectifier/charger input currents.
(b) The UPS shall include protection against input over voltages, load
short-circuits, external or internal over temperature, vibration and
impacts during transport, etc. The UPS shall stop automatically if the
DC voltage drops below a preset minimum value.
(c) Controls shall be micro processor based and the following main
controls shall be possible:
rectifier/charger on/off
inverter on/off
forced shutdown
forced transfer upon forced shutdown of inverter when the bypass
power supply (mains 2) is outside tolerances
self-test
(a) Install the UPS system including battery cabinet at location in the UPS
room of Ancillary Buildings as decided by the engineer at site.
Provide minimum clearance as per manufacturer’s recommendation
and DEWA regulations.
(b) Submit method statement for commissioning of the UPS system and
transferring load from the mains to the UPS system.
(b) The Contractor shall provide a record of all tests carried out including
records of abortive tests.
(a) Before the positioning/bolting down into the final UPS location at site a
visual inspection shall be carried out.
(b) Tests shall be carried out utilizing the plant wiring and voltage source.
(c) The UPS manufacturer’s commissioning engineer shall supervise the
site tests to ensure that the installation and testing complies with the
manufacturer’s specification.
(d) A full system test shall be carried out utilizing all the plant UPS
services and final plant loads and as a minimum shall include:
1. Load test for a minimum of 24 hours with the UPS loaded with all
plant running, whether connected to the UPS or not, in its normal
17.23.23 Training
17.23.24 Spares
Include recommended spares for two years of maintenance for all parts of
UPS system.
17.24.1 Summary
(b) The ATS shall transfer the load in delayed transition (break-before-
make) mode. Transfer is accomplished with a user-defined
interruption period in both directions adjustable from 1 second to 5
minutes in at least 15 increments.
17.24.2 Scope
functional requirements.
17.24.3 References
(a) All ATS shall be housed in vertical free standing panels similar in
construction to MCCs on Low Voltage switchboards and shall comply
with requirements of 17.20.
(b) ATS shall be designed and constructed such that inspection
maintenance and replacement of parts can be easily possible at site.
Manufacturer’s detailed instructions shall be incorporated in the
maintenance manuals. ATS requiring their complete return to the
manufacturer for service will not be acceptable.
(c) ATS shall have only front access.
(d) ATS shall be of indoor construction, IP 54 degree of protection suitable
for installation in non-vented substations and shall be capable of
operation in the specified ambient conditions without any adverse effect
on ATS.
(e) ATS shall have communication capability for communication with the
central SCADA system through fiber optic network.
17.24.5 Submittals
(a) Perform Work in accordance with NEMA ICS 2.3 or ISO 9002 or other
standards as directed by the Engineer.
(b) Maintain one copy of each document on site.
(a) Deliver, store, protect and handle products to site under provisions of
this section.
(b) Deliver, store, protect and handle products to site with particular
reference to Dubai climatic conditions under this section.
(c) Deliver in 1.2m maximum width shipping splits, individually wrapped
for protection, and mounted on shipping skids.
(d) Store in a clean, dry space. Maintain factory wrapping or provide an
additional heavy canvas or heavy plastic cover to protect units from
dirt, water, construction debris, and traffic.
(e) Handle in accordance with NEMA ICS 2.3 or other approved standard.
Lift only with lugs provided for the purpose. Handle carefully to avoid
damage to motor control center components, enclosure, and finish.
(c) Provide complete listing of all consumable stores and spare parts
used by the Contractor during the maintenance period.
(a) The transfer switch unit shall be electrically operated and mechanically
held. The electrical operator shall be a solenoid mechanism,
momentarily energized. The transfer switch unit shall include both
electrical and mechanical interlocks to prevent both sets of main
contacts from being closed at the same time. Main operators which
include overcurrent disconnect devices OR do not include electrical and
mechanical interlocks will not be accepted.
(b) All transfer switch sizes shall use only one type of main operator for ease
of maintenance and commonality of parts.
(d) All main contacts shall be silver composition. Switches rated 600
amperes and above shall have segmented, blow-on construction for high
withstand and close-on capability and be protected by separate arcing
contacts.
(e) Inspection of all contacts shall be possible from the front of the switch
without disassembly of operating linkages and without disconnection of
power conductors. Switches rated 600 amps and higher shall have front
(a) The controller’s sensing and logic shall be provided by a single built-in
microprocessor for maximum reliability, minimum maintenance, and the
ability to communicate serially through a serial communication module.
(b) A single controller shall provide twelve selectable nominal voltages for
maximum application flexibility and minimal spare part requirements.
Voltage sensing shall be true RMS type and shall be accurate to 1% of
nominal voltage. Frequency sensing shall be accurate to 0.2%. The
panel shall be capable of operating over a temperature range of - 20 to
+60 degrees C and storage from -55 to +85 degrees C.
17.24.17 Enclosure
(b) All standard and optional door-mounted switches and pilot lights shall
be 16-mm industrial grade type or equivalent for easy viewing &
replacement. Door controls shall be provided on a separate
removable plate, which can be supplied loose for open type units.
(a) A four line, 20 character LCD display and keypad shall be an integral
part of the controller for viewing all available data and setting desired
operational parameters. Operational parameters shall also be
available for viewing and limited control through the serial
communications input port. The following parameters shall only be
adjustable via DIP switches on the controller:
(a) Voltage and frequency on both the normal (N) and emergency (E) sources
(as noted below) shall be continuously monitored, with the following
pickup, dropout and trip setting capabilities (values shown as
(e) Source status screens shall be provided for both normal and
emergency to provide digital readout of voltage on all three phases,
frequency and phase rotation.
(d) Two time delay modes (which are independently adjustable) shall be
provided on re-transfer to normal. One time delay shall be for actual
normal power failures and the other for the test mode function. The
time delays shall be adjustable from 0 to 60 minutes. Time delay shall
be automatically bypassed if the emergency source fails and the
normal source is acceptable.
(e) A time delay shall be provided on shut down of engine generator for
cool down, adjustable from 0 to 60 minutes.
(f) A time delay activated output signal shall also be provided to drive an
external relay(s) for selective load disconnect control. The controller
shall have the ability to activate an adjustable 0 to 5 minute time delay
in any of the following modes:
(g) The controller shall also include the following built-in time delays for
Delayed Transition & Bypass-Isolation operation:
1. 0 to 5 minute time delay for the load disconnect position for delayed
transition operation.
(i) All time delays shall be adjustable by using the LCD display and keypad or
with a remote device connected to the serial communications port. The
time delay value displayed on the LCD or remote device shall be the
remaining time until the next event occurs.
17.24.11 Accessories
(a) A three position momentary-type test switch shall be provided for the test
/ automatic / reset modes. The test position will simulate a normal source
failure. The reset position shall bypass the time delays on either transfer
to emergency or retransfer to normal. Switches which require utilizing the
keypad and display function or have no manual time delay bypass
means are not acceptable.
(c) Auxiliary contacts, rated 10 amps, 250 VAC shall be provided consisting
of one contact, closed when the ATS is connected to the normal source
and one contact closed, when the ATS is connected to the emergency
source.
(d) LED indicating lights (16 mm industrial grade, type 12) shall be provided;
one to indicate when the ATS is connected to the normal source (green)
and one to indicate when the ATS is connected to the emergency source
(red).
(e) LED indicating lights (16 mm industrial grade, type 12) shall be provided
and energized by controller outputs. The lights shall provide true source
availability of the normal and emergency sources, as determined by the
voltage sensing trip and reset settings for each source.
(g) Terminals shall be provided for a remote contact which opens to signal
the ATS to transfer to emergency and for remote contacts which open to
inhibit transfer to emergency and/or retransfer to normal. Both of these
inhibit signals can be activated through the keypad or serial port.
(h) The controller shall be capable of accepting a normally open contact that
will allow the transfer switch to function in a non-automatic mode using
an external control device.
At the end of the specified duration the switch shall transfer the load
back to normal and run the generator for the specified cool down
period. A 10- year life battery that supplies power to the real time clock
in the event of a power loss maintain all time and date information.
(j) System Status - The controller LCD display shall include a “System
Status” screen which shall be readily accessible from any point in the
menu by designated key. This screen shall display a clear description of
(k) Self Diagnostics - The controller shall contain a diagnostic screen for
the purpose of detecting system errors. This screen shall provide
information on the status input signals to the controller which may be
preventing load transfer commands from being completed.
(m) Data Logging – The controller shall have the ability to log data and to
maintain the last 99 events, even in the event of total power loss. The
following events shall be time and date stamped and maintained in a
non-volatile memory:
1. Event Logging
i. Date and time and reason for transfer normal to emergency.
ii. Date and time and reason for transfer emergency to normal.
iii. Date and time and reason for engine start.
iv. Date and time engine stopped.
v. Date and time emergency source available.
vi. Date and time emergency source not available.
2. Statistical Data
i. Total number of transfers.
ii. Total number of transfers due to source failure.
iii. Total number of days controller is energized.
iv. Total number of hours both normal and emergency sources are
available.
(a) The ATS shall be rated to close on and withstand the available RMS
symmetrical short circuit current at the ATS terminals with the type of
overcurrent protection shown on the plans.
(b) The ATS and bypass switch shall be UL listed in accordance with UL 1008
and be labeled in accordance with that standard's 1½ and 3 cycle, long-
time ratings.
(a) The complete ATS shall be factory tested to ensure proper operation of
the individual components and correct overall sequence of operation
and to ensure that the operating transfer time, voltage, frequency and
time delay settings are in compliance with the specification
requirements.
(b) ATS shall be subject to all witness tests in compliance with the specified
standards.
(c) The test reports shall identify, by serial number(s), the equipment
involved. No exceptions to the specifications, other than those
stipulated at the time of the submittal, shall be included in the
certification.
(d) The ATS manufacturer shall be certified to ISO 9001 International
Quality Standard and the manufacturer shall have third party
certification verifying quality assurance in design/development,
production, installation and servicing in accordance with ISO 9001.
(a) The Contractor shall use competent persons to install the equipment
and shall provide them with documentary evidence of their
competence, which the Engineer or Employer, or their nominees, shall
be entitled to see at any time.
17.24.25 Installation
(a) Conduct field inspection and testing under provisions of Section PS-
10/1
(b) Conduct field inspection and testing under provisions of this section.
(c) Each control panel shall be tested to demonstrate correct operation of
relaying, fault protection and control equipment. All isolators, fuse
switches, oil and air circuit breakers shall be tested for correct
operation and fault operation. All associated cabling shall be tested for
correct phase connection and insulation resistance.
17.24.28 Demonstration
17.24.29 Training
17.25.1 Description
(a) The work of this Section is integral with the whole of the Contract
Documents and is not intended to be interpreted outside that context.
(b) Coordinate the work with all other services affecting the work of this
Section.
(a) This Section shall include all labour, materials and accessories for the
complete performance of all distribution boards in accordance with the
Specifications and Drawings.
17.25.5 Submittals
(a) Submit fully detailed specifications for the enclosures and components
of distribution boards with relevant sheets of manufacturer’s
catalogues.
(b) Submit confirmation that proposed boards comply with relevant
Specifications, Drawings and Schedule of Points.
17.25.6 General
17.25.7 Busbars
(a) The M.C.B. shall comply with BS EN 60898 Part 1 and amendments
and shall be of category M6 Type 3.
(b) The M.C.B. shall be of the trip free pattern to prevent closing the
breaker on a faulty circuit and shall be engraved to indicate “ON/OFF”
position and rated current.
(c) Trip Settings: As indicated on schedule of points.
(d) Shall have a minimum symmetrical RMS interrupting capacity of 6 kA.
(e) Shall have the thermal overload trips to operate at 125% rated current
and instantaneous magnetic trip to operate at:
i 500% rated current for single pole
breakers. ii 800% rated current for triple pole
breakers.
(a) Current operated earth leakage circuit breakers shall provide accident
protection, by interrupting dangerous contact with voltage, which may
be present in faulty electrical equipment as a result of frame faults,
insufficient insulation or misuse.
(b) The ELCB shall also provide a high degree of protection against earth
leakage, fires and electric shock and can withstand at least 6kA. The
breakers shall generally comply with BS 4293, 1983 and the
recommended specification CEE 227 of the IEC on Rules for the
approval of electrical equipment.
(c) The breaker shall consist of a core balance transformer, a tripping coil
with contact assembly, main supply contacts, ON/OFF switch, a test
button and a trip free mechanism, all enclosed in a robust body of all
insulated material.
(d) Degree of Protection against earth leakage throughout the electrical
installation shall be as indicated on the Drawings
(e) The breaker protecting lighting and/or power circuits shall be mounted
in the panel board enclosure.
17.25.11 Contactors
17.25.12 Installation
17.26.1 SCOPE
(a) This Part specifies the panel mounted and miscellaneous instruments
and equipment to perform the required functions in conjunction with
instrumentation and equipment specified in other parts of this Section.
(b) Enclosures of front panel mounted instruments shall be of uniform
design and colour scheme wherever possible. Front of enclosure
colours shall be compatible with panel colours and subject to final
approval by the Engineer. Normally, compatible standard colours of
the manufacturer shall be acceptable.
17.26.2 REFERENCES
17.26.3 SUBMITTALS
(a) Manufacturer:
1. Instrumentation and control equipment furnished shall
be manufactured by a Company regularly and currently
(a) Trip Amplifiers shall be surface or rack mounted with 220 V a.c. 50 Hz
power supply. Input shall be 4-20 mA d.c. with 1 or 2 independently
adjustable set points, provided as specified in the Project Drawings or
schedule . Outputs shall be SPDT relay contacts rated 220 V a.c. 5A.
17.26.9 TIMERS
Drawings. Timers shall have four types of operation: (1) On Delay (2)
Off-Delay (3) Single Shot, and (4) Duty Cycle timers. Time ranges
shall be as shown in the Project Drawings.
(b) Panel mounted timers shall be of the motor driven adjustable type
with dials and presentable pointers. The timers shall operate from
220 V, single-phase, 50 Hz power and shall be of the square bezel
type for flush panel mounting. Output contacts shall be double throw
and rated for 10 A at 220 V a.c. The number of contact sets shall be
sufficient to perform the required control functions. Where more
contacts are required than are supplied as commercial standards,
control relays of equal rating shall be used to supplement the timer
contacts. When specified, relay contacts shall be supplied as part of
the timer and shall be operated by the timer control power
independently of the timed contacts. Repeatability of the preset time
delays shall be within ±2%. Timers shall be of the plug-in type and
enclosed in dust-proof cases. Connection shall be by numbered
screw terminals in the rear of the timer connector.
(c) On Delay Timers. When a start signal is applied, the timing cycle
begins. Output contacts change state after the time delay is
completed. Contacts shall return to original state when a reset signal
is applied, or power is removed. The timing cycle shall be adjustable.
(d) Off Delay Timers. When a start signal is applied, the output contacts
change state immediately. When the start signal is removed, the
timing cycle begins and the output contacts return to the original state,
when the cycle is completed. Timer shall be reset by a reset signal,
or by removal of power. The timing cycle shall be adjustable.
(e) One shot timers. When a start signal is applied, the output contacts
change state immediately and the timing cycle begins. The output
contacts return to the original state when the cycle is completed.
Timer shall be reset by a reset signal or by removal of power.
(f) Duty Cycle Timers. Two timer cycles shall be incorporated. When a
start signal is applied, the first timing cycle beings. The output
contacts change state at the end of the cycle and the next timing
cycle begins. When this delay is completed, the output contacts
return to the original state. This sequence is repeated until a reset
signal is applied, or power is removed.
(a) Running time meters shall be of the synchronous motor driven type
having a minimum of 6 (six) decimal digits where the least significant
digit shall represent tenths 1/10's (tenths) of hours. Unless specified
otherwise in the Project Specification, they shall not be equipped with
a reset button. They shall be panel mounted with a minimum 60 mm
square bezel. Motor voltage shall be 220 V a.c. single phase 50Hz.
(a) General:
(c) Central Processing Unit. The CPU shall perform the following
function:
1. Scan all inputs, execute relay ladder logic programmes and
generate outputs for the final control elements.
2. Monitor status of the system hardware and provide diagnostic
information.
3. Process scan time shall be 8 milliseconds/kilobyte maximum.
(d) Memory:
1. Random Access Memory (RAM) for real-time programme
execution with lithium battery backup for data retention and
EEPROM backup for permanent storage of programme shall be
provided. The PLC memory shall be as required for the
programme and future requirements subject to a minimum of [16]
Mb.
(f) Programmer/Simulator:
1. Supply one programmer/simulator with PLC software for use by
the Dubai Municipality. Programming shall be through a lap-top
programming unit. Programming shall be user friendly, self-
documenting type, with facility for identification and comments.
PLC programming shall be compliant with IEC 61131-3 standard
(h) Programmer/Simulator:
1. Programming shall be on relay ladder language.
2. Password protected programming through hand held programmer
or personal computer.
(i) A Panel mounted VDU shall be provided for the PLC when specified
in the Project Specification, as per the following specification.
1. A panel mounted CRT or liquid crystal display unit for graphic,
numeric and message display.
2. Membrane keypad with one million cycles minimum operation.
3. 220 V a.c. 50Hz power supply.
4. Enclosure protected to IP65.
5. EEPROM for application program storage.
6. Provide restricted access to the PLC database for simulating or
forcing inputs/outputs.
(a) Float switches are to be the pendant type with the float suspended on
a flexible cable, such that with the float free of the liquid the float and
cable hang vertically, but with a rising liquid level the float will rise and
tend to invert.
(b) Provide float of a robust design that comprise a switch having change-
over contacts encapsulated in a hard plastic foam and connected to a
3 core cable. The whole assembly is to be covered and hermetically
sealed in Hypalon or similar material.
(c) With the tilting action which occurs on rising level, the contacts are to
change-over, but there is to be a dead band between opening one
contact and closing the other, during which period contacts are to be
open. This dead band shall operate over an arc approximately 20o
either side of the horizontal.
(d) In all applications the installation is to be complete with approved
means of preventing the float (and lead) from movement due to draft
or liquid turbulence.
(e) Where float switches are to be used in applications under which they
may be submerged during the normal operation (e.g. pump control
and/or low level alarm); attach them to a weighted stainless steel
chain to minimize movement due to turbulence and to provide a
means of raising the units for maintenance and repair.
(a) General
The system shall comprise of a transducer and a transmitter. Overall
accuracy shall be better than ±1 % of the range with a repeatability of
±0.5 %.
The system shall be intrinsically safe, where required for the
application.
(b) Transducer
Stainless steel 316 construction. Enclosure protected to IP68.
Automatic compensation for changes in ambient temperature shall be
in-built. Transducer shall be supplied complete with mounting
accessories.
(c) Transmitter
Surface or panel mounted transmitter with 220V a.c. 50 Hz power
supply. Microprocessor based transmitter with programmable range
and alarms. Transmitter shall be complete with in-built indication for
level or for flow, if used for open channel flow measurement. 4 Nos.
in-built relay contacts, shall be provided for process and diagnostic
alarms. Transmitter shall be provided with an in-built keypad for
programming the instrument.
(d) Provide a canopy for the transducer and transmitter units, for
protection from direct sunlight.
(a) General
Electronic pressure transmitters shall convert a gauge or absolute
pressure measurement to a 24V d.c. loop powered 4 to 20mA d.c.
output signal. Range shall be as indicated in the Project Specification.
Over range tolerance shall be at least 1.5 times span. Accuracy shall
be ±0.5 percent or better. Isolating diaphragms shall be provided when
specified in Project Specification. A process variable indicating meter
shall be provided. Zero and span adjustments shall be provided.
(b) Construction
The transmitter enclosure shall be IP65, unless explosion proof is
specified in Project Specification. Enclosure and wetted surface
material shall be stainless steel to BS 970.
(a) Provide gauges in the suction and discharge of each pump and
blower.
(b) Gauge: To BS 1780 Stainless Steel glycerine filled
Bourdon type pressure gauge, black scale on white background.
(c) Where equipment and pipe mounted gauges are inaccessible for
reading and are subjected to vibration, gauges shall be mounted
remote with stainless steel tubing connecting to equipment with shut
off valve at equipment and gauge.
(d) Discharge gauge ranges shall be a standard commercially available
range with the maximum reading not less than 5 bar greater than the
pump rated shut off pressure.
(e) Use compound type suction gauges with a minimum range of 750mm
of mercury.
The gauges shall be of first class construction, tropicalized with dust
and damp proof approved non-corroding solid (not plated) materials.
The mechanism shall be of robust design, capable of withstanding the
degree of vibration, shocks and pressure fluctuations normally
encountered with pump operation when protected by snubbers.
(d) Where metering orifices are installed in vertical lines the direction
of flow shall be upwards.
(e) The flow measurement primary element shall have adequate
isolation facilities to allow it’s removal and zero flow checking. To
facilitate the installation or removal of a flow measurement primary
element, the primary element or associated pipework shall be
fitted with a minimum of one flange adaptor/coupling.
(f) Where a control valve (multiposition or on/off) is fitted upstream of a
flowmeter the requirements for symmetrical velocity profile and
lack of swirl shall be exhibited throughout the total range of
movement of the valve.
(g) Where the flow measurement accuracy for an application is specified,
the flow measurement technique utilised shall be as follows:-
OVERALL
APPLICATION WATER FLOW SEWAGE FLOW
ACCURACY
1.0% Electromagnetic Electromagnetic
Flowmeter Flowmeter
Enclosed 1.0% Electromagnetic
Pipelines Flowmeter, Dall tube/ Electromagnetic
insert or orifice plus Flowmeter
D.P. Cell
Open Channel by 1.0% Float Driven shaft
Level encoder/Potentiometer Ultrasonic (level)
Characterisation or Level Transducer
& Ultrasonic (level)
1.0% Float Driven
Potentiometer, Ultrasonic (level)
Ultrasonic or Level
Transducer/Transmitter
& Ultrasonic (level)
(b) Accuracy
1. The flowmeter accuracy is to be ±0.2% of reading in the velocity
range of 10 metres/sec down to 0.5m/s and ±0.05% of reading
down to 0.2m/s.
2. The repeatability of the flowmeter is to be ±0.05% down to 0.5m/s
velocity increasing progressively to ±1% at 0.25m/s.
3. Manufacturer shall calibrate all flowmeters on NAMAS accredited
flow calibration rigs and submit calibration certificates for each
flowmeter.
The following output formats are required and must be isolated from
any common connection to the instrument to prevent common mode
interference. The magnetic flowmeter shall also have field bus
interface to communicate with another field bus device.
(d) Electrodes
1. The flowmeter is to be of a type that prevents polarisation of
electrodes.
2. The primary transducer electrodes are to be capable of being
removed for cleaning. The Contractor is to provide details of the
working space required to allow the electrodes to be removed.
3. The Contractor is to advise on the suitability of cleaning the
electrodes and if it is required for the flowmeter application, then
such device or method of cleaning shall be provided.
(e) Vibration
1. The flowmeter is to be able to endure vibration, when in service,
without any degradation in performance. When flowmeters are
installed in areas where vibration exists, then a suitable anti-
vibration pad is to be provided.
i. Manufacturer's name
ii. Serial number
iii. Nominal internal diameter
iv. Maximum operating pressure
v. Calibration factors
vi. Type of enclosure
vii. Forward flow direction
viii. Weight
ix. Power
(h) Installation
1. The flowmeter is to be suitably flanged to meet the plant maximum
operating pressure. Each flowmeter is to be individually pressure
tested by the manufacturer to at least 1.5 times its flange pressure
rating. A Certificate of Conformity for pressure testing will be
required.
2. Fit the flowmeter with permanent lifting eyes (minimum 25 mm
internal diameter) and provide all relevant test certificates.
3. The Contractor is to include a dimensional arrangement drawing
showing details of length, clearance dimensions and any special
support arrangement. A flange adapter is to be incorporated to
allow removal of the flowmeter.
4. Provide the flowmeter with mating flanges in conformity with the
pipeline.
5. Protect the flowmeter head from direct sunlight if installed in an
exposed location.
1 Sensor
2. Transmitter
(a) Provide a diaphragm seal where shown. Fill with glycerine or silicone.
Provide nickle or zinc plated carbon steel upper housing, 316
stainless steel lower housing, and 316 stainless steel diaphragm.
Provide a filling connection and a flushing connection. Provide 12mm
NPT instrument connection and 25mm NPT or 38mm flanged process
connection as shown.
17.26.21 INSTALLATION
(a) The Engineer reserves the right to have any device, including any
required meter runs, shipped to an independent laboratory for an
operation accuracy check at conditions including upstream and
downstream piping geometry as close as possible to specified
operating conditions. Extra shipping costs shall be paid for by the
Dubai Municipality if test results conform to specified operating
accuracy. If test results indicate that the operating accuracy is not in
accordance with specifications, shipping costs and calibration cost will
be paid for by the Contractor. In such an event, the device will be
returned to the manufacturer for replacement, the replacement device
will be shipped to the independent laboratory for an operation
accuracy check and returned to the manufacturer if it fails the check.
This will continue at no cost to the Dubai Municipality, until a
replacement device passes the check.
17.26.25 TUBING
17.26.27 COMMISSIONING
(b) Test and exercise each device to demonstrate correct operation, first
individually, then collectively, as a functional network.
(e) Unless otherwise specified, tests shall be made to cover at least five
points: approximately 0 per cent, 25 per cent, 50 per cent, 75 per
cent, and 100 per cent of range. Individual device accuracy
requirements shall be as specified by contract requirements, or by
published manufacturer accuracy specifications, whenever contract
requirements are not specified.
(f) Prepare a Test Report showing actual value, instrument value, 4-20
mA value for each test and range of the instrument. If test results
conflict with calibration, then recalibrate and repeat test, until test
results prove calibration to be correct. Each test report shall bear the
The electric power generating system shall have a site capability of 1500
ekW, 1850 kVA, Standby rated, 0.80 power factor, 400 Volt, Wye
connected, three phase, 50 hertz. This power shall be applied for
STANDBY emergency operation.
1 General:
i The operating philosophy for the Stand-by generator sets has
been indicated on the single line diagram. An outline is given
below:
2 Normal status:
i Diesel Generator sets shall normally be on standby and
available for automatic instant start-up and switching of the
appropriate circuit breakers on receipt of a remote signal or
manual control. When at rest, those parameters, which affect
its availability to start and operate, shall be continuously
monitored and if a malfunction occurs, suitably alarmed at the
generator control panel situated adjacent to the generator set
and communicated to the remote control room.
3 Automatic start
i When a loss of normal power occurs and provided automatic
mode is selected, the generator set shall be started
automatically by means of an signal over communication link
or under voltage signal from the electrical distribution system.
ii A test facility shall be provided to simulate the under voltage
signal.
iii Interlocking system shall be initiated to prevent paralleling of
DEWA power sources; prior to connection of load.
4 Manual start
i Provided the manual mode is selected the generator set shall
be capable of being started manually by means of a local
initiation and also from remote control room. When running in
this mode a normal power failure shall result in an automatic
connection of the generator to the switchgear busbars.
5 Test mode
i Starting of the Diesel Generator set shall be by manual
means. This mode shall be used for engine exercising and
test running operations.
6 Shutdown
i Shutdown of the Diesel Generator set shall be manual from
either the local generator control panel or remote shutdown
switch.
ii The Diesel Generator set shall automatically shutdown on
malfunction of its essential auxiliary systems.
iii Emergency and mechanical shutdown facilities shall be
provided.
iv Provision shall be made for remote emergency shutdown.
7 Remote operation and monitoring
i Communication modules and facilities to start and stop each
unit through a personal computer at local panel and also from
control room including monitoring of engine and generator
parameters on real time basis via communication network shall
be included.
ii Provide all necessary hardware and window-based software to
be included.
(a) The operating environment of the power generating system shall be:
Altitude: 500 m
Max Ambient Temperature: 50 C
Fuel Type: Type 2 Diesel
(a) The power generating system shall satisfy the following performance criteria
at site conditions:
Quantity
Power Capability: 1800 ekW/2250kVA, Standby rated
3 Phase Volts: 400 volt
Frequency: 50 Hz
Average Power Factor 0.8
Speed 1500 RPM
Steady state speed +/- 0.50 %
band
Voltage transient Within +/- 10% of rated voltage against
response application of 50% rated kVA
17.27.7 Responsibility
local supplier responsible for service, parts, and warranty for the total
system.
1 Production Tests
The system manufacturer shall perform postproduction tests on
the generator set supplied. A certified report of these tests shall
be available when requested at the time of the generator set
delivery.
2 Drawings/Schematics
All installation drawings and wiring diagrams for the generator set,
controls, and switchgear must conform to a common format.
17.27.10 Submittals
(a) Engine:
1. Type, aspiration, compression ratio, and combustion cycle
2. Bore, stroke, displacement, and number of cylinders
3. Engine lubricating oil capacity
4. Engine coolant capacity without radiator
5. Engine coolant capacity with radiator
6. Coolant pump external resistance (maximum)
7. Coolant pump flow at maximum resistance
(b) Alternator:
1. Model
2. Frame
3. Insulation class
4. Number of leads
5. Weight, total
6. Weight, rotor
7. Air flow
(d) Radiator:
1 Model
2 Type
3 Fan drive ratio
4 Coolant capacity, radiator
5 Coolant capacity, radiator and engine
6 Weight, dry
7 wet
(e) System:
1. Dimensions:
2. Length
3. Width
4. Height
5. Weight, dry
6. Wet
Stack temperature
(a) The manufacturer shall have a local authorized dealer who can
provide factory-trained servicemen, the required stock of replacement
parts, technical assistance, and warranty administration.
2 Warranty Administration
The manufacturer's authorized dealer shall be capable of
administering the manufacturer and dealer's warranty for all
components supplied by the selling dealer (who may or may not be
the same as the servicing dealer).
3 Warranty Terms
The manufacturer's and dealer's warranty shall be for a period of
one year from date of initial start-up or 18 months from the date of
delivery of the unit, whichever comes first.
The bypass valve must be integral with the engine filter base or
receptacle. Systems where bypass valves are located in the
replaceable oil filter are not acceptable. Pistons shall be oil cooled by
continuous jet spray to the underside or inside of the crown and piston
pin.
(e) Governor
The engine governor shall control engine speed and transient load
response within commercial and ISO 8528 tolerances.
indoor tank.
(m) Cooling System
The engine jacket water cooling system shall be a closed circuit
design with provision for filling, expansion, and deaeration. The
cooling pump shall be driven by the engine. Coolant temperature shall
be internally regulated to disconnect external cooling systems until
operating temperature is achieved.
1 Radiator
Heat rejected to the engine jacket water shall be discharged to the
atmosphere through a shaft mounted fan cooled radiator. The
radiator shall be sized to cool the engine continuously while
operating at full rated load and at site conditions.
Long runs of pipe shall be pitched away from the engine and water
traps installed at the lowest point. Exhaust stacks shall be extended
to avoid nuisance fumes and odors, and outlets cut at 45 to minimize
noise.
1 Silencer
The silencer shall be of industrial grade.
2 Exhaust Thimble
An exhaust thimble shall be installed at the point where the
exhaust pipe penetrates the building.
3 Jacket Water Heater
1 Batteries
Batteries for starting and control shall be selected and supplied by
the generator set manufacturer. They shall be Nickel cadmium
type. Batteries should be sized to provide upto 4 starts at an
ambient temp. of 0 deg. C.
(r) Alternator
The alternator(s) shall be rated for Standby service at 1800 ekW, 2250
kVA, 0.80 PF, 400.V, three phase, 4 wire, 50 Hz, 1500 rpm.
1 Alternator Specifications
As minimum the alternator shall be designed, manufactured to
meet following specification.
laminated
Overspeed 125%
capability
Paralleling Provided with cross current
capability
compensation
Voltage Regulation Less than + 0.5% THD Less than
5%
TDF Less than 5%
2 Operating Environment
3 Excitation
4 Voltage Regulator
Alternator output voltage drift no more than +/- 0.5% of rated value
within a 40 change over ambient temperature range of -40øC to
70øC.
to 20 g's
(s) Mounting
The engine and generator shall be assembled to a common base by
the engine-generator manufacturer. The generator set base shall be
designed and built by the engine-generator manufacturer to resist
deflection, maintain alignment, and minimize resonant linear vibration.
Safety shut down protection and LED indication for: i Low oil
pressure
3 Controls:
Alternator voltage level rheostat and frequency control shall be
mounted on the panel face. The engine start-stop switch shall be
door mounted and include positions for off/reset, run/start, stop,
and automatic mode. Start-stop logic shall have provisions for
cycle cranking programmable from 5 to 60 second cycles, for total
crank time of 5 to 120 seconds. Cooldown operation shall be
programmable from 0 to 30 minutes, with a signal to allow removal
of the load from the generator set during cooldown.
4 Shutdowns/Annunciation:
The generator set shall shut down and red flashing LEDs shall
signal operational faults of overcrank, overspeed, high water
temperature, and low oil pressure. High water temperature, low
coolant level, and low oil pressure shall be programmable for
shutdown or alarm. A minimum of three (3) spare fault inputs
shall be available which can be programmed for alarm or
shutdown, with 0-250 second time delay. There shall be a lamp
test switchpad accessible from the front of the panel.
5 Safety Devices:
ISO red emergency stop pushbutton shall be provided, and all
controls, annunciation, and monitors labeled with ISO symbols.
6 Service:
Complete viewing and programming of panel functions shall be
possible from the panel face. Features shall include a fault history
log, engine alarm and shutdown set points, password protection,
spare input programming, hourmeter programming,
voltmeter/ammeter programming, and AC calibration.
(w) Switchboard
1 Standby power supply LV switchboard distribution panel shall be
included in the scope of the generator manufacturer as indicated
on the drawing
2 Provide switchboard with all protection relays for generator and
outgoing feeders with facility for control and monitoring over
communication links using fiber optic cables.
17.27.13 Execution
(c) Installation
1. Voltage,
2. current,
3. Frequency,
4. Temperature,
5. Bearing Temperature,
6. Losses,
7. Efficiency,
8. Fuel Consumption
9. Other parameters as suggested by Manufacturer.
controls.
ii Parts Books - which illustrate and list all assemblies,
subassemblies and components, except standard fastening
hardware (nuts, bolts, washers, etc.).
iii Preventive Maintenance Instructions - on the complete system
that cover daily, weekly, monthly, biannual , and annual
maintenance requirements and include a complete lubrication
chart.
iv Routine Test Procedures - for all electronic and electrical
circuits and for the main AC generator.
v Troubleshooting Chart - covering the complete generator set
showing description of trouble, probable cause, and suggested
remedy.
vi Recommended Spare Parts List - showing all consumables
anticipated to be required during routine maintenance and test.
vii Wiring Diagrams and Schematics - showing function of all
electrical components.
The contractor shall supply a UPS and/or battery backup system with sufficient
capacity to maintain power to the supplied equipment, its peripherals remote
terminal units on main power supply for a minimum period of 4 hrs.
In the event of power failure, the master central system shall be supported by
the uninterrupted power supplies as specified.
The UPS system shall be monitored by the SCADA and a fault in the UPS
system shall be accorded a grade 1 priority status.
The functional design specifications shall detail modes of failure and itemize
signals to be supported by UPS if deemed appropriate.
17.28.1 GENERAL
A. The UPS system shall consist of a UPS module and a battery. The AC
output of the UPS module shall be connected to the critical loads. The
battery shall be connected to the DC input of the UPS.
B. Definitions
1. UPS Module: The portion of the UPS system which contains the
rectifier/charger, inverter, static bypass switch, maintenance bypass
switch, controls, monitoring, and indicators.
2. Rectifier/Charger: The portion of the UPS module which converts the
normal source AC input power to DC power for the inverter input and
for charging the battery.
3. Inverter: The portion of the UPS module which converts DC power,
from either the rectifier/charger or the battery, to regulated and filtered
AC power which is supplied to the critical load.
4. Automatic Bypass Switch: The portion of the UPS module which
automatically transfers the critical loads, without interruption, from the
inverter output to the bypass AC power source in the event of an
overload or degradation of the inverter's performance.
5. Maintenance Bypass Switch: The portion of the UPS module which is
used to connect the bypass AC power source to the critical loads
while electrically isolating the static bypass switch, rectifier/charger
and inverter for maintenance purposes.
6. Battery: The battery system that provides DC power to the inverter
input when the normal AC input power to the UPS module fails or in
the event that the rectifier/charger should fail.
7. Critical Loads: Those loads that require regulated continuous AC
power and which are connected to the output of the UPS module.
1. GE Digital Energy
17.28.1.07 STANDARDS
17.28.1.08 SUBMITTALS
2. One certified copy of the factory test report shall be furnished upon
request.
A. The UPS module shall be palletized and shipped via air ride or common
carrier, as specified by the customer.
B. Shipping splits shall be provided such that no section is more than 48"
long.
17.28.1.11 WARRANTY
17.28.2 ELECTRICAL
5. Dynamic regulation:
±3% from nominal for 100% step load.
±2% from nominal for 50% step load.
Recovering to within 1% in less than one cycle
17.28.2.02 RECTIFIER/CHARGER
B. Over-current/Transient Protection
1. The input of the rectifier/charger shall be protected from noise and
transients by an input EMI/transient suppressor network. The
suppressor network shall be fused in order to minimize damage to the
UPS in the event that input transients exceed the rating of the
suppression network.
2. The rectifier/charger shall be electronically regulated and current
limited to protect the connections to the inverter input and to prevent
damage to the battery.
C. Control Circuitry
D. Input Filter
E. Output Filter
17.28.2.03 INVERTER
B. Control Circuitry
The input of the automatic bypass shall be protected from noise and
transients by an input EMI/transient suppressor network. The suppressor
network shall be fused in order to minimize damage to the UPS in the
event that input transients exceed the rating of the suppression network.
The input of the maintenance bypass switch shall be protected from noise
and transients by an input EMI/transient suppressor network. The suppressor
network shall be fused in order to minimize damage to the UPS in the event
that input transients exceed the rating of the suppression network.
A. The UPS front panel shall include a mimic diagram with active LED
indicators showing the actual power path through the UPS.
B. The front panel shall also include the following LED indicators:
i. Summary Alarm
ii. Service Check
iii. Stop Operation
iv. Battery Level (bar graph)
v. Load Level (bar graph)
C. The front panel shall include the following buttons for system operation
and control of the LCD display:
i. System operation buttons:
1. Inverter ON
Inverter OFF
2. Mute (Alarm Silence)
3. Test
4. Load OFF
ii. LCD display control buttons:
1. Metering
2. Alarms
3. Parameters
4. +
5. -
6. OK
D. The UPS shall include an audible alarm-warning device. This alarm shall
sound whenever any abnormal condition occurs. Pressing the Mute
button shall silence the audible alarm. Any subsequent alarm shall cause
reactivation of the status indicator and audible alarm.
1. Battery Display
i. Battery voltage.
ii. Battery current with flow direction.
iii. Battery temperature.
iv. Battery charge level.
v. Estimated backup time at present load.
2. Bypass AC Display
i. Bypass AC voltage - phase to phase.
ii. Bypass frequency.
3. Rectifier Display
i. AC input voltage - phase to phase.
ii. DC output current.
iii. Input frequency.
4. Inverter Display
i. Voltage - phase to neutral.
ii. Output frequency.
iii. Synchronization status.
5. Load status display.
i. Overall load kVA.
ii. Overall percentage load.
iii. Load on Bypass/Inverter.
6. Phase load display 1.
i. Voltage – phase to neutral.
ii. Phase current - amperes.
iii. Phase current – percentage.
A. The UPS shall have 6 alarm contacts for remote signaling. These alarm
contacts shall each be programmable with any of the following signals:
B. The UPS shall have two inputs for connection to external contact closures.
The status of these external contacts can be monitored from the front
panel of the UPS. The default configuration for these external signals
shall be as follows:
i. Aux. Input No. 1 ‘On Generator’
ii. Aux. Input No. 2 not defined
The ‘On Generator’ signal shall be used to optimize operation of the UPS
while AC power is being supplied from an engine-generator. The following
parameters shall be programmable in this mode:
shall allow the user to prevent transfer of the critical load directly to
the output of the engine-generator.
3. Inverter output frequency slew-rate. This parameter shall allow the
user to specify the maximum frequency rate-of-change when the
inverter is phase-locked to an engine-generator. Adjustment range
shall be 0.1 to 20.0 Hz/second, in 0.1 increments. This adjustment
shall be independent of normal operation slew-rate.
4. Recharge capability (enable/disable/delay). This parameter shall
allow the user to select whether or not, and/or when the battery will
be recharged while the UPS is powered from an engine-generator.
This parameter shall be programmable directly in minutes, with zero
disabling battery charging. This will conserve fuel and allow closer
sizing of the engine-generator.
5. The UPS rectifier shall also include a soft-start circuit to limit inrush
current and apply load to the engine-generator gradually.
6. The optional input current distortion filter shall be programmable to
disconnect when the UPS AC source is the output of an engine-
generator.
A. The UPS shall include two RS-232 ports. These ports shall allow full
remote monitoring, control and management of the UPS system. All
access to control functions through these ports shall be protected from
unauthorized access.
17.28.2.09 DESIGN
C. Logic Power Supply: The logic power supply shall receive power from the
battery and AC power sources. It shall be capable of supplying logic power
from any of the available sources.
17.28.2.10 CONSTRUCTION
17.28.2.11 COOLING
A. The UPS shall be forced air-cooled with redundant fans. Inlet air
temperature shall be monitored and displayed.
A. The UPS shall be designed and constructed such that the audible noise
level is reduced to a typical 65 decibel, measured on the A scale at one 5
feet (1.5 meters) from the front of the cabinet.
17.28.2.13 BATTERY
A. The UPS shall include an Emergency Power Off (EPO) circuit. Activating
this circuit shall cause immediate shutdown of all UPS operations. This
operation will shut down the critical load.
B. The UPS module shall include provisions to activate the EPO circuit
remotely by a contact closure.
17.28.3 EXECUTION
17.28.3.01 MANUFACTURING
A. The manufacturer shall design, build, test and arrange for shipment of the
UPS.
B. The manufacturer shall prepare and deliver the required installation
drawings and operation and maintenance manuals with the equipment.
A. The owner shall prepare the site for installation of the equipment.
B. The owner shall arrange for installation of the equipment.
C. The equipment shall be installed in accordance with the manufacturer's
recommendations as well as in accordance with local and national electrical
codes.
1. Najmat Al Kawn Technologies LLC, PO Box 43302, Dubai, United Arab Emirates
2. Star Technology FZCO, P.O Box : 18697, Dubai, United Arab Emirates
3. Transguard Group LLC, P.O Box : 22630, Dubai, United Arab Emirates
4. Scientechnic LLC, P.O. Box 25490, Dubai, United Arab Emirates
Appendix B
General Description
The below is technical specifications for guidance for Cycle digital display counters and the
Contractor to propose as approved or equivalent.
**
Counter Arrangement Sensors Arrangement
General Specifications
Physical Specifications
Page B-1
SECTION 20 ANCILLARY WORKS
**
Approximate Dimensions
Page B-2
Appendix C
Landscape Specifications
LANDSCAPE SPECIFICATIONS
LANDSCAPE SPECIFICATIONS
TABLE OF CONTENTS
1. GENERAL AND PRELIMINARIES 1
1.1 General 1
1.2 Standards, materials, goods and workmanship 1
1.3 Approved trade names / manufacturer/ suppliers 2
1.4 Samples & testing of materials 2
1.5 Manufacturer’s instructions 3
1.6 Ordering materials 3
1.7 Scaffolding 3
1.8 Cutting and Patching 3
1.9 Protection of the works 3
1.10 Site Hoarding 4
1.11 Water for the works 4
1.12 Electricity for the works 4
1.13 Existing site services 4
1.14 Pricing generally 4
1.15 Site facilities and facilities for engineer’s representatives/ temporary services 5
1.16 Maintenance of offices 7
1.17 Delivery, handling and storage of materials 7
1.18 Control and test equipment to be provided by contractor 7
1.19 Site offices for contractor 8
1.20 Contractor's site area 8
1.21 Site progress meetings 8
1.22 Progress photographs 8
1.23 Setting out 9
1.24 Notice boards 9
1.25 Defective work 9
1.26 Erection equipment or other plant 9
1.27 Loading in excess of design load 9
1.28 Building permit & NOC 10
1.29 Permanent irrigation, drainage, water and electricity connections 10
1.30 Handing over 10
1.31 Safety regulations 10
1.32 Accidents 10
1.33 Mobilisation period - contractor's work 10
2 METALWORK AND GLAZING 12
2.1 General 12
2.2 Standards 12
2.3 Finished coating 12
2.4 Aluminium 13
2.5 Storage and protection 15
2.6 Materials 16
2.7 Shop painting materials 16
2.8 Shop coatings for ferrous and galvanised surfaces 16
2.9 Workmanships 17
2.10 Installation 18
2.11 Samples 19
2.12 Sealing joints 19
2.13 Glazing 19
2.14 Glazing materials 20
2.15 Glass openings 20
2.16 Glass installation 20
2.17 Cleaning 21
2.18 Expansion joint trims, etc. 21
3 PAINTING AND DECORATING GENERAL 22
3.1 Materials 23
3.2 Workmanship 25
3.3 Guarantees 27
4 SITE AND STREET FURNITURE 28
4.1 Description 28
4.2 Quality assurance 28
TOC 1 of 5
LANDSCAPE SPECIFICATIONS
4.3 Submittals 28
4.4 Delivery, storage and handling 29
4.5 Site conditions 29
4.6 External timber features. 29
4.7 Street furniture 30
4.8 Product specification sheet 31
4.9 Installation 31
4.10 Maintenance 31
4.11 Maintenance manual 31
5 SOFT LANDSCAPING 32
5.1 Description 32
5.2 Quality Assurance 32
5.3 Quality control program 32
5.4 Submittals 32
5.5 Delivery, Storage and Handling 33
5.6 Site conditions 34
5.7 Certificates 34
5.8 Planting soil 34
5.9 Planting soil constituent criteria 35
5.10 Soil conditioner 36
5.11 Organic compost 36
5.12 Soil moisture retention additives 36
5.13 Soil mixes 37
5.14 Plants 37
5.15 Tree stakes & support 38
5.16 Landscape edging 38
5.17 Tree ties 39
5.18 Geotextile membrane 39
5.19 Root barrier 40
5.20 Drainage composite barrier 40
5.21 Drainage cell/ composite 40
5.22 Advanced trees to 2m 40
5.23 Regular size trees to 1.5m 40
5.24 Medium palms 40
5.25 Regular size palms upto 2.5m 41
5.26 Shrubs, Herbaceous plants, groundcovers 41
5.27 Annual plants 41
5.28 Lawn areas – green grass carpet 42
5.29 Plant supply 43
5.30 Plant substitutes 43
5.31 Soft landscape programme 44
5.32 Planting period 44
5.33 Planting bed preparation 44
5.34 Planting pit excavation 45
5.35 Transporting plants 46
5.36 Plant handling 46
5.37 Planting operations 46
5.38 Completion 49
5.39 Defects liability period 49
5.40 Defective work or materials 49
5.41 Landscape maintenance 50
5.42 Maintenance objectives 50
5.43 Scope of works 50
5.44 Maintenance reports 51
5.45 General maintenance operations 51
5.46 Horticultural maintenance operations 52
5.47 Planting areas 53
5.48 Maintenance period: herbicides and pesticides 54
5.49 Maintenance period: replanting operations 55
5.50 Operations and maintenance manual 55
5.51 Plant supply 55
TOC 2 of 5
LANDSCAPE SPECIFICATIONS
5.52 Maintenance 57
6 HARD LANDSCAPE WORKS 58
6.1 Description 58
6.2 Specifications are to be read in conjunction with the whole document. 58
6.3 Materials not specified in this document 58
6.4 Related references & standards 58
6.5 Levels, ref. points and setting out 59
6.6 Related work 59
6.7 Quality assurance 59
6.8 Source 60
6.9 Mock-ups 60
6.10 Submittals 60
6.11 Delivery, handling and storage 60
6.12 Project conditions 60
6.13 Substrates 60
6.14 Extra material 60
6.15 Samples 60
6.16 Materials specified by client 61
6.17 Materials and quality 61
6.18 General 61
6.19 Concrete Paving 61
6.20 Pre-cast concrete pavers, edgings & kerbs. 62
6.21 Natural stone (including travertine, granite, slate, quartzites and sandstone) 64
6.22 Natural stone gravel 65
6.23 Soil separator/ Geotextile fabric 65
6.24 Drainage Cell & Composite 65
6.25 Execution and workmanship 65
6.26 Concrete unit paving 66
6.27 Pre-cast concrete slabs 68
6.28 Natural stone (including but not limited to, granite, slate and sandstone) 70
6.29 Natural stone gravel – laying 72
6.30 Hard landscape maintenance 73
7 IRRIGATION 74
7.1 General concept of the design 74
7.2 Irrigation system, general 75
7.3 Silence of specification 79
7.4 System explanations 79
7.5 Layout of work 80
7.6 Clean-up 80
7.7 Warranty 80
7.8 Product storage and handling 80
7.9 Operation and maintenance 80
7.10 Irrigation system, materials 81
7.11 Pipes and fittings 81
7.12 Valves 88
7.13 Valve boxes 91
7.14 Basket strainer 91
7.15 Pressure compensating emitters & dripper lines 91
7.16 Pressure compensating bubblers 93
7.17 Pop-up sprayers 93
7.18 Rotor pop up sprinklers 94
7.19 Filtration chamber (not applicable) 94
7.20 Filters (not applicable) 95
7.21 Pressure gauges (not applicable) 95
7.22 Underground warning tape 96
7.23 Electrical equipment (not applicable) 96
7.24 System controlling equipment (not applicable) 99
7.25 Exhaust fan (not applicable) 101
7.26 Valve chamber covers 101
7.27 Pump/filtration chamber (not applicable) 101
7.28 Chamber identification plate (not applicable) 101
TOC 3 of 5
LANDSCAPE SPECIFICATIONS
TOC 4 of 5
LANDSCAPE SPECIFICATIONS
1.1 General
The Conditions of Contract, Bill of Quantities and the Drawings shall be read in conjunction with
the Specifications and matters referred to, shown or described in the former are not necessarily
repeated in the latter.
Notwithstanding the subdivision of the Specifications into various headings, every part is to be
deemed supplementary to every other part and the various parts are to be read with each other, so
far as it may be practicable to do so, or when the context so permits.
In various places throughout this specification and the Bills of Quantities reference is made to the
Standards, Specifications and Bye-Laws issued by the British Standards Institution and other
similar organisations. These references shall in every case be deemed to include the latest edition
or issue of such Standards, Specifications and By Laws including all revisions, amendments and
addenda subsequently issued. Where materials are not specified to be to a particular British
Standard and a British Standard exists in respect of such materials, then the materials shall in all
respects comply with the relevant and current British Standard. In such cases where British
Standards do not exist, the materials used shall be of the best type available and shall generally
be to the Engineer's satisfaction. Reference to British Standards shall not preclude the use of
materials from sources where other standards apply, but no material shall be in any respect, inferior
to those which specifically complies with the relevant British Standard.
Wherever the specifications are stated, they shall comply with latest edition or as specified
therein with the priority of standards as follows:
Materials, goods and workmanship shall be of the best quality of their respective kinds and, as far
as applicable, shall comply in every respect with the requirements of the quoted Standards, Codes
of Practice and Specifications or any other National Standard approved by the Engineer. Preambles
and descriptions of materials, goods and workmanship given in any one section of the
Specifications shall apply throughout the whole of these Specifications unless otherwise described.
The substitution of materials, goods, workmanship and the like from that specified shall only be
permitted with the written approval of the Engineer.
Where the quality of materials is not specified or supplier/manufacturer is not named, the quality
shall be the best obtainable and the workmanship shall be of the highest possible standard to the
satisfaction of the Engineer.
The Contractor shall submit for the approval of the Engineer a list of names and addresses of the
manufacturers and trade-marks or names of all the various types of materials and goods he
proposes to use in the Works. This list shall include reference to the Specifications Clause or Article
to which the materials and goods apply.
All materials used in the Works shall be new and of the appropriate quality all to the Engineer's
approval.
Materials shall be obtained from approved sources and used in accordance with the manufacturer's
printed instructions. In the absence of a specification all materials shall comply with a relevant
standard. The Engineer shall order the removal of any materials which he has not approved.
Page 1 of 113
LANDSCAPE SPECIFICATIONS
No orders for materials and goods shall be placed until approval has been obtained for the materials
and goods from the Engineer.
The Contractor shall note that it is his responsibility to include in his price for the cost of the materials
and products as specified and no adjustment will be allowed should the alternatives be rejected by
the Engineer. Where material is to be imported, the Contractor shall produce documentary
evidence that the materials have been ordered within 8 weeks after the contract has been signed
provided that such imported materials are not needed during the 8 weeks period. Copies of such
orders shall be submitted to the Engineer. Unless such proof has been produced, no claim shall be
considered for extension of time due to non-availability of the materials and it shall be assumed
that all materials necessary for the completion of the works were readily available for purchase
locally.
During the Contract the Contractor shall provide one of the named products and only in exceptional
circumstances where the named products are not available, the Contractor may offer alternatives
from other manufacturers or suppliers. The Contractor shall submit details as required to
substantiate the equivalence of these alternatives. The burden of proof as to the equivalence of the
alternatives to the materials/products specified shall remain with the Contractor.
All products/materials shall have approved National Certificates of conformance similar to BSI
quality Kite Mark or National Agreement Certificate such as BBA for non-standard products and
systems supplied for approval by the Engineer
The Contractor shall furnish for approval within six weeks of commencing the works, all samples
as directed by the Engineer. The Engineer shall check and approve such samples with reasonable
promptness only for conformance with the design concept of the Works and for compliance with
the information given in Contract Documents. The work shall be in accordance with the approved
samples.
1 All samples of hard and soft landscape materials including but not limited to; paving,
cladding, timber, aggregates, mosaics, glass, street furniture and control samples of all
specified plant material shall be delivered to the Engineer's office with all charges in
connection therewith paid by the Contractor and deemed to be included in the Contract price.
2 Where identified in the specifications or as directed by the Engineer the Contractor shall
provide mock up samples of areas of paving, cladding, changes in levels, walls, steps,
ramps, water features etc either in isolation or in conjunction with adjacent items, for
example with street furniture, for the approval of the Engineer. Approved mock up areas
shall be retained either as control samples for work continuation and/or to demonstrate to
the Engineer a clear understanding of the requirements of the specification or to identify
areas requiring further clarification.
3 Duplicate final approved samples, in addition to any required for the Contractor's use, shall
be furnished to the Engineer, one for office use and one for the Site.
4 Samples shall be furnished so as not to delay fabrication, allowing the Engineer reasonable
time for consideration of sample submitted.
5 Each sample shall be properly labelled with the name and quality of the material,
manufacturer's name, country of origin, name of the project, the Contractor's name and date
of submission, and the specification article number to which the sample refers.
6 If required by the Engineer, the samples shall be tested for compliance at the Contractor's
expense in an independent laboratory designated by the Engineer.
Page 2 of 113
LANDSCAPE SPECIFICATIONS
7 Testing of materials and completed works shall be carried out in accordance with DM
Administrative Decision No. 16/2000
8 Monthly Progress Report as well as Final Materials Report both containing the prescribed
summary of minimum testing frequency shall be submitted to the Engineer for approval.
All items or materials shall be delivered to the Site in the manufacturer's original unopened
containers with the manufacturer's brand and name clearly marked thereon.
All items or materials shall be assembled, mixed, fixed, applied, or otherwise incorporated in the
Works in accordance with the printed instructions of the manufacturer of the items or materials
unless specifically instructed otherwise by the Engineer.
The Bills of Quantities shall not be used as a basis for ordering materials and the Contractor is
entirely responsible for assessing the quantities of materials to be ordered. Upon receipt of the
Engineer's order to commence the Works, the Contractor shall immediately place orders for all
required materials and will be held responsible for any delays occurring due to the late placing of
such orders. Prior to finalising material orders, the Contractor shall advise the Employer and await
the Employer's written approval to complete the same.
The Contractor shall pay all expenses, taxes and dues etc. incurred on the procurement of materials
from aboard.
1.7 Scaffolding
The Contractor shall provide, erect, maintain, dismantle, and clear away at completion proper and
adequate scaffolding including that required for Sub-Contractor and Suppliers. Putlog holes shall
be made good to match the adjacent surface as the scaffolding is dismantled. The Contractor shall
be entirely responsible for all safety precautions in connection with the scaffolding including the
provision of all bracing, scaffold boards, toe boards and the like and for its entire sufficiency for the
work.
If in the Engineer's opinion scaffolding is considered dangerous then the Contractor shall rectify the
same at his own expense. All work utilising scaffold shall be halted until the scaffold is corrected all
to the Engineer's written approval.
The Contractor shall be responsible for all cutting and patching and making good required for all
trades for all work and his prices will be deemed to include for all such cutting and patching and
making good.
The Contractor shall cover up and protect the Works from the weather and from damage by his
own or other workmen performing subsequent operations. He shall provide all necessary dust
sheets, barriers and guard rails and clear away same at completion.
The Contractor shall take all reasonable and proper steps for the protection of all places on or about
the Works which may be dangerous to his workmen or any other persons or to traffic. The
Contractor shall provide and maintain warning signs, red warning lamps and barricades as
necessary in all such places. The Contractor shall not load or permit any part of structure to be
loaded with a weight that will endanger its safety.
Page 3 of 113
LANDSCAPE SPECIFICATIONS
The Contractor shall provide a site hoarding at the boundary of the Site as shown on Drawing MP-
03 where required by the Municipality By Laws and to the entire satisfaction of the Municipality and
the Engineer. The Contractor shall allow for applying murals / graphics to 20% of the hoarding
length. All murals and graphics to be to Engineer’s approval. The Site hoarding shall be maintained
during the progress of the Works and shall be dismantled and cleared away upon completion.
The Contractor shall be responsible for ensuring the security of the Site, for protecting same from
trespass and providing all necessary watching and lighting in connection therewith. All temporary
buildings and work areas shall be constructed within the Contract limit.
The Contractor shall make all necessary arrangements and provide all water for the proper
execution of the Works, together with all transport, temporary plumbing, storage and distribution,
pay all charges and alter, adapt and maintain temporary work as necessary and remove and make
good at completion. Extension of time shall not be granted due to failure of and dependence upon
a mains water supply.
The Contractor shall make all necessary arrangements and provide all artificial lighting and power
(maintaining a generator if necessary) for the proper execution and security of the Works including
that required for Sub-Contractor's works and its protection, with all meters, temporary wiring and
fittings, pay all charges and alter adapt and maintain the temporary work as necessary and remove
and make good at completion. Extension of time shall not be granted due to failure of and
dependence upon a mains electricity supply.
The Contractor shall follow up and obtain all the required information relating to any existing site
services, telephone, electrical, water, irrigation and drainage and the like on the site before
commencing excavation or piling. The Contractor shall be responsible for the protection of all
existing services within the site and shall make good at his expense any damage to existing
services resulting from his carrying out of the Works to the satisfaction of the Engineer and relevant
authority. The Contractor shall be responsible for giving notice to the relevant authority where
temporary or permanent re-routing or diverting of existing services is found to be necessary and
shall complete same at his own expense to the Engineer's and respective Authorities' approval.
Works in relation to locating, diverting, repairing or replacing existing services are to be inclusive
of making good the surrounding area and disposal of arisings to the approval of the engineer and
the relevant authority.
Where diversions of services as aforementioned are not required in connection with the permanent
Works, the Contractor shall uphold, maintain and keep same in working order in existing locations.
The Contractor shall satisfy himself as to the scope of the Work shown on the drawings and
described in these Contract Documents and his price shall be deemed to cover all his obligations
under the Contract and all matters and things necessary for the proper construction, completion
and maintenance of the Works. The price shall include for all material, labour and plant - whether
mechanical or non-mechanical - required for the completion of the Contract in accordance with the
Drawings and Specifications, and removing at completion and making good any surfaces disturbed
and if not included in any prices inserted in the Preliminaries for the insurances and bonds required;
for the costs of preparing a tender; for the work in connection with measurements and the final
account; for profit; and for all other establishment charges and on costs of whatever nature. No
claim for additional payment will be allowed for any error or misunderstanding by the Contractor in
these respects.
Page 4 of 113
LANDSCAPE SPECIFICATIONS
The Contractor has to allow in his pricing for all fees required to obtain the building permit and the
DEWA. approval for all electrical works based on shop drawings presented by him and approved
by the Engineer including obtaining the permanent electricity, water and other service connections
necessary for the completion of the Works and paying the respective fees. Refer to item 24 (iv) of
SICET 3.
1.15 Site facilities and facilities for engineer’s representatives/ temporary services
Locations: Inform Resident Engineer of the intended siting of all spoil heaps, temporary works and
services.
Maintain, alter, adapt and move temporary works and services as necessary. Remove when no
longer required and make good.
Page 5 of 113
LANDSCAPE SPECIFICATIONS
Page 6 of 113
LANDSCAPE SPECIFICATIONS
1.15.8 Toilets
Provide for 10 shaded car parks for exclusive use by the Consultant’s representative.
The Contractor shall, for the duration of the Contract, supply sufficient stationary attendance to the
Engineer and shall maintain and pay all water, electricity and telephone charges associated with
the running of the Contract and shall keep the site offices and their surroundings, together with the
furniture, fittings and equipment, in a clean condition and in good repair at all times.
All materials or manufactured items that are liable to damage shall be delivered in the original
package, containers, etc., bearing the name of the manufacturer and the brand.
Materials or manufactured items shall be carefully loaded, transported, unloaded and protected
from damage and exposure to weather or dampness during transit and after delivery to the Site.
Once on site, materials (hard or soft landscape), shall be stored in an appropriate manner, relative
to the individual requirements of the specified item and to the approval of the Engineer. Damaged
material or manufactured items shall not be used in the Work. Any material or manufactured items
damaged during and after fixing in position shall be removed, repaired or replaced by and at the
Contractor's expense as required by the Engineer.
During the Contract, the Contractor shall provide, maintain and clear away on completion the
following listed items of control and test equipment. All items shall be to the Engineer's approval.
The items listed hereunder are indicative and not limited to the items that the Engineer may request
during the Contract.
1 Three sets of six number, 150mm cast iron or steel concrete cube moulds.
2 Slump Apparatus
3 Metric weighing scales.
4 Water tank with thermo-statically controlled heating and cooling for curing concrete test
cubes.
5 Concrete thermometer and replacements.
6 Further the Contractor shall arrange for an independent laboratory approved by
Consultant to do all testing required as per specification.
Page 7 of 113
LANDSCAPE SPECIFICATIONS
The contractor shall provide maintain and clear away on completion of the Contract all necessary
site offices, canteens, messing, temporary buildings, toilets and the like for all site staff employed
by the Contractor and required by subcontractors and suppliers. The offices shall be open at all
normal working hours to receive instructions, notices and other communications.
The contractor shall obtain the approval of the Engineer of the proposed site layout, type and
drainage arrangement of all the buildings prior to erection of same. All buildings shall be supplied
and maintained in good condition and of neat appearance, all maintenance to same as instructed
by the Engineer shall be carried out at the Contractor's expense.
Under no circumstances shall overnight accommodation be permitted on Site except for the site
watchman in carrying out his duties.
Throughout the period of the Contract the Contractor shall maintain the area of his operation within
the limits of the Site in a clean, tidy and safe condition by arranging materials and the like in an
orderly manner. All rubbish, debris, waste materials and the like shall be systematically cleared
from the Site as it accumulates.
The Contractor shall take all steps necessary as directed by the Engineer to minimise or eliminate
dust, noise or any other nuisance which may occur. Plant emitting dust, smoke, excessive noise or
other nuisance shall not be permitted.
The Contractor shall satisfy himself as to the means of access to the Site and other relative items
affecting same for both himself, his Sub-Contractors and Suppliers.
During the course of the Works, Site progress meetings shall be held at fortnightly intervals for the
purpose of co-ordinating the Contractor's works and to ensure that full compliance is maintained.
Minutes of such Site meetings will be recorded, copies will be distributed to all persons concerned
and full effect shall be given to all instructions contained therein.
Prior to such meetings the Contractor shall give to the Engineer's Representative details in writing
of that portion of the Works he proposes to construct during the coming two weeks with details of
the plant and method he proposes to employ. These proposals shall be discussed at the meeting
and no work based on such proposals shall proceed without the approval of the Engineer's
Representative.
The Contractor shall submit all reports as instructed by the Engineer in connection with Site
progress meetings and the day to day management of the Works.
The Contractor shall supply once a month, at the time of submitting his Valuation, thirty six
photographs from 108 exposures showing the progress of the Works. The times and position from
which the photograph are to be taken shall be directed by the Engineer.
The photographs shall be submitted in three copies unmounted of a size not less than 15 x 10
centimeters with the description of the viewpoint stamped in ink on the back. The negative shall
have the date on same and remain the property of the Engineer and no prints from these negatives
may be supplied to others unless previously authorised in writing by the Engineer. The Contractor
shall include for six photographs per month to a size of 25 x 20 cm as directed by the Engineer.
Page 8 of 113
LANDSCAPE SPECIFICATIONS
The Contractor shall be responsible for accurately setting out the Works to the specified positions,
dimension, levels and Building Lines and also checking the site surveys for dimensional and level
accuracy and reporting any discrepancies before building work commences.
The Contractor shall provide the Engineer with all facilities, equipment and labour to enable him to
check the setting out and levels of the Works at all times. The checking of any setting out point,
line or level by the Engineer shall not in any way relieve the Contractor of his responsibility.
All setting out points, benchmarks, site rails, pegs and other survey points shall be clearly marked
and protected from damage or disturbance during the execution of the Works.
The contractor shall provide and maintain two number notice / sign board each shall conform to the
requirements and design guidance of authorities and client Marketing Department.
The boards shall consist of graphic or photographic representations of the project and shall be
lettered in both Arabic and English by skilled sign-writer to include:
A large-scale layout shall be prepared and submitted for the Clients Marketing Departments and
Engineer’s approval prior to fabrication. No advertising material other than that expressly required
by the client shall be permitted anywhere on the site. The siting and layout of Sub-Contractors or
Manufacturer’s sign boards, if allowed, must be submitted for the Clients and Engineer’s approval.
On completion of the works the name boards shall be submitted to the consultant.
Any defective work materials and also deviations from the working details in respect of setting out,
correct lines and levels, verticality, sizes, thicknesses of members and/or any other dimensional
variation of any kind whatsoever, shall be removed and reconstructed or otherwise rectified without
undue delay to the approval of the Engineer and the Contractor shall be responsible for all
additional costs incurred.
If cranes or any other type of plant which places any load on the structure are proposed, all details
of such plant shall be submitted to the Engineer for approval before the work is actually
commenced. If approved by the Engineer and architecturally acceptable, permission may be given
for the structure to be strengthened, in order to carry out loads, and the Contractor shall be
responsible for any resulting additional costs.
The Contractor shall be responsible for making good to the satisfaction of the Engineer any damage
to the permanent structure which may be caused by his plant and equipment.
No loading in excess of the design loading shall be placed on any portion of the structure without
the written permission of the Engineer.
If such permission is granted, all beams or other members of the structure which are subjected to
loading other than the designed loading shall be strengthened and supported to the satisfaction of
the Engineer, and the Contractor shall be responsible for any resulting additional costs. The
Page 9 of 113
LANDSCAPE SPECIFICATIONS
Contractor shall be responsible for making good to the satisfaction of the Engineer any damage to
the permanent structure which may be caused by such excess loading.
The Contractor shall allow for obtaining the building permit and relevant NOC and allow for paying
all fees in connection therewith.
The Contractor shall allow for arranging and obtaining the permanent irrigation, drainage, water
and electricity connections to the proposed development and he shall be responsible for making all
payments in connection therewith. Refer to clause 24 (iv) of SICET 3 and page 1/5 of this document.
Prior to handing over the proposed development the Contractor shall gain the approvals and
respective Completion Certificates from all the local government departments, authorities and the
like that the work has been completed in accordance with their requirements. Any payments in
connection therewith shall be paid by the Contractor.
The Contractor and all persons employed by him on the site in or about the execution of the Works
shall conform in all respects with the provisions of all Acts and Orders and Regulations made by
any competent authority that shall be applicable to the Works or any temporary works and binding
upon the Contractor or persons employed as aforesaid and in particular, but without prejudice to
the generality of the foregoing, much matters as concern the safety, health or welfare of persons
working on the Site. The Engineer may require the immediate removal from the works of any person
who, in the opinion of the Engineer, fails properly to observe the provision of this Clause and such
personnel shall not be again employed upon the works without the permission of the Engineer. The
provisions of this Clause shall apply to and be binding upon any Sub-Contractor employed by the
Contractor.
1.32 Accidents
The Contractor shall promptly report by telephone and in writing to the Engineer and concerned
Authorities any accident whatsoever arising out of or in connection with the performance of the
work whether on or adjacent to the Site which caused death, personal injury or property damage,
giving full details and statements of witnesses.
If any claim is made by anyone against the Contractor or any Sub-Contractor on account of any
accident, the Contractor shall promptly report the facts in writing to the Engineer giving full details
of the claim.
The Contractor shall submit the following items for approval and perform the work described below
during the mobilisation period. Permission to commence permanent works will not be given until
the following is completed. The items listed are intended to be the minimum required. The Engineer
may instruct the Contractor to carry out additional work within the mobilisation period.
Page 10 of 113
LANDSCAPE SPECIFICATIONS
The above submission and works to be performed shall first be approved by the Engineer.
Page 11 of 113
LANDSCAPE SPECIFICATIONS
2.1 General
The Contractor is required to employ approved specialists to supply, or supply and erect all
metalwork items. Working drawings are to be prepared and issued to the Engineer in quadruplicate
for approval in good time to afford no delay to the project and in no case less than eight weeks
before work needs to be put in hand. No work at site or fabrication in factory shall commence prior
to any approval by the Engineer.
2.2 Standards
Materials used in this Section shall comply with British Standards, the British Codes of Practice,
DIN Standards, American Standards and American Society for Testing and Materials, or Local
Authority Standards and Codes whichever are the more stringent.
Applicable provision of the following British Standards shall apply to these works as follows:‑
1 Mild Steel shall comply with BS 4360, sections generally shall comply with BS 4: Part 1, hollow
sections with BS 4848: Part 2 and angles with BS 4848: Part 4. Steel plate and sheet shall
comply with BS 1449: Part 1 and steel tubes to BS 1775.
2 Stainless Steel Tubes shall comply with BS 3014, and stainless steel plate with BS 1449: Part
2.
3 Aluminum alloy extruded sections shall comply with BS 1161 or BS 1474 and aluminium alloy
drawn tube with BS 1471. Anodising process when applicable to comply with BS 3987.
4 Brass work as indicated on the drawings shall comply with the various appropriate Standards.
5 Fastenings unless otherwise specified shall be of the same metal as the item being fixed, with
matching coating or finish. Wood screws shall comply with BS 1210. Bolts, Screws and nuts to
BS 4190, machine screws and nuts to BS 4138 and self‑tapping screws to BS 4174.
6 Plugs shall be proprietary fibre plastics or other approved type.
7 Bitumen solution for cold application shall comply with BS 3416, Type 1.
2.3.1 General
The finished coating shall be as stated on the Drawings and applied strictly in accordance with the
manufacturer's instructions.
The colour of the coating shall be selected from available ranges if not stated elsewhere in these
Documents. The Contractor shall offer samples for approval prior to the final selection and the
manufacturer of these elements.
The aluminium anodising shall comply with BS 3987 and be integral colour hardcoat anodising
550kp/mm² hardness, minimum 25 microns thick.
The colour of anodising shall be as described on the drawings. Samples of colour including limits
of colour variation shall be submitted to the Engineer for his approval before work commences. The
Engineer reserves the right to reject the products of any supplier who cannot guarantee a
reasonable limit of colour variation, the acceptable limit of variation being at the Engineer's
discretion.
All aluminium sections that are to receive a polyester powder coating shall be given a caustic etch
followed by an anode oxide treatment to obtain an architectural class 1 anodic coating. Anodization
should be not less than 20 micron thickness.
Page 12 of 113
LANDSCAPE SPECIFICATIONS
All aluminium works shall be finished in coloured electrostatic polyester powder coating as per DIN
standard 53151, 53152, 53153, 53156 or equal and approved to RAL colour subject to the
Engineer's approval.
Powder coating of all mild steel elements shall be as per relevant the British Standard and to the
approval of the Engineer.
Unless otherwise stated mild steel shall be spray coated with Epoxy based paint to be factory
applied in two layers, primer coat 0.3 mils dry film thickness and finished colour coat minimum 1.0
mils dry film thickness, minimum overall thickness of 1.3 mils dry film thickness. Inside corners,
channels and the like shall be visually covered to the extent possible. The Engineer shall select the
colour from the range available.
The coating shall be applied to properly cleaned and pre‑treated galvanised steel sections.
Application shall be by approved applicators and the Contractor shall provide certified details of
same. The pretreatment and application of the coating shall conform to all ASTM, BS, DIN
Standards and the like as stated in the Supplier's printed Specifications.
As and when instructed by the Engineer, the Contractor shall provide certificates from independent
laboratories that the minimum thickness as stated in these Documents has been applied to all
sections. Failure to provide such information shall result in the complete installation being rejected
and replaced at the Contractor's expense.
All aluminium surfaces that are to be in contact with cured concrete, mortar, steel and other metals
shall have the contact surfaces protected wherever they may entrap moisture or corrosive
elements. Metals that are to be in contact with mortar or concrete shall be protected with a two coat
bituminous coating.
Prime paint steel parts of anchors, anchor inserts, reinforcement, supports, and all parts after field
welding or bolting with zinc chromate. Minimum dry film thickness of 1 mil for zinc chromate.
2.4 Aluminium
2.4.1 General
All aluminium elements i.e. doors, windows, frames, transoms, mullions, etc, where shown on the
drawing shall be manufactured of extruded section of aluminium alloy to B.S. 1474. Heat treatable
free from defects type, 11.9. They shall be supplied by a manufacturer approved by the Engineer.
Fittings shall be aluminium alloy in accordance with B.S. 1473.
All exposed surfaces shall be light etched and anodised in a satin or matt finish to the colour
indicated on the drawings. The thickness of anodising shall be guaranteed to be 20 microns (.020
mm) by the manufacturer and shall be polished to a mirror-like surface.
Aluminium coated materials shall not be permitted in lieu of the aluminium items specified herein.
Samples of the anodized finish must be offered for approval before proceeding.
All aluminium sections shall present clear, straight and shapely defined lines and shall be free from
defects and imperfections that may impair their strength.
The Contractor shall be responsible for the protection of all aluminium work until the completion of
the Works, and only units in perfect working order and in perfect condition will be accepted. All
Page 13 of 113
LANDSCAPE SPECIFICATIONS
hardware, screws, bolts and other necessary accessories shall be of aluminium or other non-
corrodible material and shall match in colour and consistency the finish of the anodised aluminium.
Where aluminium is in contact with wood, the wood shall be treated with pentachlorophenol or
equal and approved, 5% minimum concentration, followed with the protective measures described
for aluminium in contact with wood or other absorptive materials.
The aluminium work shall be fabricated and anchored so that work will not be distorted nor the
fasteners overstressed from the expansion and contraction of the metal.
2.4.2 Protection
Before shipment from the factory, aluminium surfaces requiring protection shall be given a coating
which will protect the metal during construction. In areas where appearance of the finish on
aluminium items is important a coating of methacrylate lacquer shall be applied.
Apply two sprayed coats or water-white methacrylate lacquer having a total minimum thickness of
0.125 mm, which when applied to the aluminium surface shall be capable of withstanding the action
of lime mortar for a period of at least one week in an atmosphere of 100% relative humidity at 100
degree F and the action or 10% (by weight) muriatic acid for a period of six hours at 70 degree F
and the action of atmospheric weathering for a period of 12 months. Alternatively a thick adhesive
tape may be used. The coating or tape shall be applied in the manufacturers plant to the exposed
surfaces of all aluminium components subject to staining from alkaline mortar and plaster abrasion
and other construction abuses.
2.4.3 Workmanship
The Contractor shall furnish all aluminium units as indicated on the drawings.
Workmanship and installation shall be in accordance with recommended standards of First Class
Aluminium Manufacturers.
The Contractor shall furnish all labour materials and equipment to complete the aluminium work
indicated on the drawings or specified herein to the satisfaction of the Engineer.
Work shall include all parts and accessories for all variations of fabrication techniques required for
a complete installation, caulking, priming and back coating and shop drawings.
All aluminium work shall be performed in a shop where grade of metal work is of recognised quality
acceptable to the Engineer. All items shall be installed plumb, straight, square, level and in proper
elevation, plane, location and alignment with other work. All work shall be fabricated for adjustment
to field variations, fitted with proper joints and intersections and adequately anchored in place.
All workmanship and finishes shall be first class, strictly in accordance with the best practice. All
work shall be complete in every detail. Finished work shall be approved by the Engineer before
the job will be accepted.
Where aluminium surfaces come into contact with metals other than stainless steel, zinc, white
bronze or small areas of other metal compactable with aluminium, they shall be kept from direct
contact with such parts by painting the dissimilar metal with a primer, followed by one or two coats
of aluminium metal and masonry paint of other approved suitable protective coating, excluding
those containing lead pigments, or a non-absorptive tape or gasket shall be placed between
aluminium and dissimilar metals. Steel anchors and connecting members shall be hot dip
galvanized or zinc plated after fabrication.
Aluminium in contact with wood or other absorptive materials which may become repeatedly wet
shall be painted with two coats of aluminium metal and masonry paint or a coat at heavy bodied
bituminous paint. Alternatively paint the wood or other absorptive material with two coats of
aluminium house paint and seal joints with a good caulking compound.
Before application of lacquer, the manufacturer shall remove all fabrication compounds, moisture,
dirt accumulations and other foreign materials to ensure proper lacquer adhesion.
Page 14 of 113
LANDSCAPE SPECIFICATIONS
Upon completion, the Contractor shall clean all aluminium work as required by removing protective
tape and other coating, using mild soap or detergent and clear petroleum spirits. Acid, caustics
and abrasives shall not be used. Where cleaners are used to remove excess sealing compounds
care shall be taken to prevent damage to seal or staining or damage to adjacent work.
General
All windows and doors are to be constructed by approved specialist suppliers of light, medium or
heavy section to suit location, local building regulations, and particular requirements noted on the
drawing as to weight and profile.
All frames should be made to fit the actual openings with a 5mm clearance all round. Discrepancies
in overall width or height exceeding 5mm will not be allowed and the frames will be rejected in such
cases. Any small discrepancies shall have the gaps suitably backed and then filled with gun‑applied
water repellent mastic sealant.
All nuts, bolts, washers and screws used for assembly and fixing shall be of adequate strength for
their purpose within the and shall be stainless steel grade 18/8.
All sealants used in the assembly of, and in the fixing of cladding and window framing, shall be
non‑setting to allow thermal movement without detriment to those joint sealants used for peripheral
caulking and shall be one part silicone sealant and shall conform to BS 4245. All spliced joints
between mullions will be sealed with an approved silicone product, compatible with other sealants
and packings used.
All ironmongery shall have the same finish as the frames and shall be approved by the Engineer.
At all opening windows and doors and where there are louvred screens and doors, a flyscreen shall
be provided to the approval of the Engineer, constructed following the principles and specifications
as described elsewhere in this specification.
Glazing sections shall be set in special heat resisting PVC and of channel type. Separate glazing
sections on each side of the glass will not be permitted.
The following table indicates the basic requirements for window construction. The weights of
framing make no allowance for beads, glazing bars, opening light framing, coupling mullions or
transoms.
All materials shall be stored in protected areas on site and shall be fully protected against the effects
of weather.
Page 15 of 113
LANDSCAPE SPECIFICATIONS
All materials shall be carefully handled and stored under cover in a manner to prevent deformation
and damage to the materials and to shop finishes, and to prevent rusting and the accumulation of
mud, dirt or other foreign matter on the metal work. All such damage and accumulation shall be
corrected prior to erection.
2.6 Materials
All materials shall be new stock, free from defects, impairing strength, durability or appearance and
of best commercial quality for each intended purpose.
Provide all anchors, bolts, sleeves, spigots and other parts required for securing each item of work
of this Section to the construction, including furnishing to concrete workers all required inserts and
sleeves for use in concrete and furnishing to masons of all anchors, bolts, and other items required
to be built‑in masonry.
All exposed fastenings shall be of the same material finish as the metal to which applied, unless
otherwise noted.
Welding rods shall conform to British Standards and the recommendations of the metal welding rod
manufacturer.
Bolts and nuts where used, shall be in accordance with B.S. 1400 or 1769. Bolts shall be of
sufficient length to show at least one full thread beyond the nut after tightening. Bolted joints subject
to vibration shall be securely locked.
Washers, where used, shall be in accordance with B.S.4320. The size of the holes shall not exceed
the bolt diameter by more than 2mm.
The cramps for fixing wood frames to walls shall be 200mm long 30mm wide and 3mm thick and
shall have one end bent and twice countersunk drilled for screwing to the frame and the other end
fishtailed for setting into walling.
All fixing cramps, wall tiles, anchors etc., shall be galvanised mild steel proprietary type such as
Pepcon International (Al Tayer), Harris and Edgar or equal and approved. The Contractor is
responsible for submitting suitable samples to Engineer for approval.
Where Site Electrical Rooms or Substations are required, the Contractor must allow for all
necessary galvanised steel channels and chequered plate as directed by the Engineer including
framing, supports, handrailing etc., as necessary.
Shop paint for un-galvanised ferrous surfaces shall be a high quality, lead free, rust‑inhibitive
primer, as approved by the Engineer.
Shop paint for galvanised metal shall be high quality, zinc rich, metal primer especially formulated
for use on galvanised metal, as approved by the Engineer.
2.8.1 Galvanising
- All ferrous metal under this Section for exterior use in addition to any other interior items
specifically so specified, shall be of hot dip galvanized, including all bolts,
Page 16 of 113
LANDSCAPE SPECIFICATIONS
- Hot‑dip galvanising process shall comply with BS 729 as applicable. After galvanising,
processed items shall be straightened free of all warpage and distortion caused by the hot dip
process.
- Galvanised surfaces to receive paint coatings shall be given hot phosphate (bonderizing) shop
pretreatment.
- Furnish to the Engineer, a certified statement that galvanising and hot‑phosphate pre-
treatments comply fully with this Specification.
- All materials (plain and galvanised) (including non‑ferrous where specified for paint finish) under
this Section shall be given a shop coat of primer as specified, using the appropriate primers
specified previously in this Section.
- Immediately before painting, remove all rust, loose mill scale, dirt, weld flux, weld spatter and
other foreign material with wire brushes or steel scrappers. Remove all grease and oil by use
of detergent or solvent as recommended by the manufacturer of the proposed painting system.
- Apply paint by spray process in strict accordance with manufacturer's printed instructions to dry
film thickness recommended. Apply thoroughly and evenly and work well into corners and joints
taking care to avoid sags and runs.
- Do not paint surfaces to be embedded in concrete, or to be welded in the field.
- After erection, sand smooth and retouch all portions of the shop coats chipped or damaged
during erection, and coat all field welds and connections with the same paint used for all the
shop coat.
- All aluminium surfaces in contact with cement or concrete surfaces are to be given two coats of
bitumen based paint before being fitted.
2.9 Workmanships
- Co‑ordinate and provide details of the work as necessary to ensure co‑ordination with related
building elements and services. Liaise as necessary to ensure co‑ordination of the work with
related building elements and services, provide fabrication/installation drawings and other
information requested, submit sufficient copies of drawings, etc., for approval. Make any
necessary amendments in accordance with any comments of the Engineer and without delay
and re‑submit unless it is confirmed that this is not necessary and submit sufficient copies of
final version of drawings, etc., for distribution to all parties.
- Take site dimensions and submit Drawings as detailed elsewhere in these documents, showing
elevations, plans and full size sections, proposed methods of fixing, proposed methods of
forming joints, any proposals for fabricating large components in more than one piece.
- Prepare control samples as requested and obtain Engineer's written approval of appearance
before proceeding with manufacture.
- Fabricate metalwork carefully and accurately to ensure compliance with and performance
requirements, using types and grades of metal appropriate for the purpose. Finished work must
be free from distoration and cracks. Use proprietary products to manufacturer's
recommendations.
- Pre‑finished metal may be used if the finish complies with this specification, the methods of
fabrication do not damage or alter appearance at finish and the finish is adequately protected
during fabrication.
- Cold formed work, use brake presses or cold rolling to produce accurate profiles with straight
arrises. Unless specified otherwise, mitre junctions of identical sections. Remove all burrs and
sharp arrises which would be visible after fixing or a hazard to the user. After thermal cutting
stainless steel grind off material which is liable to corrode.
- When assembled all moving parts must move freely and without binding.
- Prepare surfaces of metals to receive adhesives by degreasing and abrading mechanically or
chemically and form bond under pressure. Use adhesives in accordance with manufacturer's
written recommendations.
- Mechanical joints shall be tight with no visible gaps. Where screw heads will be visible after
component is fixed, or raised screw heads would interfere with any moving part of component,
use countersunk machine screws unless specified otherwise. Mechanical joints of components
Page 17 of 113
LANDSCAPE SPECIFICATIONS
which will be located externally shall be bedded in bedding compound, including all mating
surfaces, cleats and other fixings.
- Thoroughly clean surfaces to be welded and ensure accurate fit using clamps and jigs where
practicable. Use tack welds only for temporary attachment unless specified otherwise. Make
joints with parent and filler metal fully bonded throughout with no inclusions, holes, porosity or
cracks. Completely remove all traces of flux residue and slag. Prevent weld spatter falling on
surfaces of materials which will be self-finished and visible in completed work. Butt welds which
will be visible in completed work shall be finished smooth, flush with adjacent surfaces.
- Metal arc welding shall be to BS 5135 or other methods subject to approval. Welding of stainless
steel shall be TIG welding to BS 3019: Part 2, or other methods subject to approval. Use double
bevel butt welds, backing bars to remove heat, jigging, tack welds and any other measures
necessary to minimise distortion.
- Remove slight distortion by light hammering, taking care not to damage surface finish. Welding
of aluminium alloys shall be TIG welding to BS 3019: Part I, or MIG welding to BS 3571: Part I,
or gas welding to BS 1126, or other methods subject to approval. Welding of copper alloys shall
be fusion welding to BS 1077 for copper, or other methods subject to approval.
- Apply metal coatings after fabrication is complete and all fixing holes have been drilled, unless
otherwise, specified. Before applying coating remove all welding slag, weld spatter, anti‑spatter
compounds, paints, grease, flux, rust, burrs, and sharp arrises and make good all defects which
would show after application of coating and finish surfaces smooth.
- Galvanising shall comply with BS 729, sherardising to BS 4921, zinc spraying of iron and steel
surfaces shall comply with BS 2569: Part I and Vitreous enamelling of steel surfaces with BS
3830. Surfaces of stainless steel, bronze and brass which will be visible in the completed work
shall be finely polished.
- All sections shall be protected to prevent distortion of metalwork during transit, handling, storage
and fixing and damage to arrises, projecting features and surfaces which will be exposed in the
finished work. Prevent contact with mud, ashes, plaster and cement and provide protective
coverings as necessary and remove on completion.
- Position metalwork accurately, plumb, level and true to line. Fix securely to prevent pulling
away, deflection, or other movement during use. Do not distort when tightening fastenings and
the like.
- Do not use railings or balustrades as strutting or supports after fixing for other works. Do not
weld, braze or solder on site without approval.
- Fastenings shall be concealed where practicable. Thickness or metal and details of assembly
and supports shall give ample strength and stiffness. Joints exposed to weather shall be formed
to exclude water. Do all cutting, punching, drilling and tapping required for attachment of
hardware and of work by other trades.
- Generally metalwork shall conform to all Local Authority By‑Laws, and, in lieu of other specific
legal requirements, shall support any live loads which may normally be imposed plus a safety
factor of 2.5.
2.10 Installation
- All work shall be installed adjusted by experienced workmen all in accordance with the
manufacturer's installation instructions and in full conformity with the approved shop drawings,
samples and other submitted data. Under no circumstances shall materials be installed on
surfaces that contain condensation, dirt, grease or other foreign encountered materials that
would hinder or prevent proper installation and functioning for the use intended.
- All work shall be carefully and accurately assembled with proper and approved provision for
contraction and expansion and set in correct locations as per approved detailed shop drawings,
all level, square, plumb and aligned with other work. All joints between framing and structural
building shall be sealed in order to be watertight and weatherproof and to satisfy all other
requirements of the Engineer.
- Frames shall be site verified and manufactured with a maximum 2.5mm tolerance around the
opening in the structure. These joints are to be finished by applying an approved sealant into a
polystyrene foam backing strip.
- All works are to be fully protected for the duration of the contract from damage by other trades.
The Engineer shall approve the method of protection.
Page 18 of 113
LANDSCAPE SPECIFICATIONS
- If for any reason final finishes become scratched, abraded or damaged during transport,
delivery, storage or erection, it shall be the Contractor's responsibility to remove or repair those
defective areas or components as directed and to the complete satisfaction of the Engineer.
- Repair work shall be identical to the manufacturer's applied finish with regard to gloss, finish
and visual appearance. Field touch up of painted metalwork is permitted only with the written
permission of the Engineer. Where touch up is not an authorised means of repair the damaged
materials must be replaced by new.
- Upon completion of work all protective coverings from all exposed surfaces shall be removed.
All surfaces shall be cleaned using soap or detergents as recommended by the aluminium
manufacturers to remove sealants, discolouration and any other foreign material. Defection of
any type determined by the Engineer shall be repaired at the Contractor's expense.
- Extreme care shall be taken when cleaning the exterior portion to protect all other adjacent
works.
2.11 Samples
Submit duplicate samples of all finished materials for approval by Engineer. The samples will show
the full range of finishes and mechanical properties to be expected in the finished product. Where
physical samples would otherwise be too large, examples will be given that can be readily inspected
locally, or the Contractor will provide facilities for the Engineer's inspection at the Contractor's
expense.
Unless specifically called for, size and form of each sample shall be as directed by the Engineer.
The Contractor shall ensure that joints are dry and remove all loose material, dust and grease.
Adjoining surfaces which would be impossible to clean if smeared with sealant shall be masked.
Backing strips shall be inserted in all joints to be pointed with sealant. When using backing strips,
the Contractor shall not leave gaps and shall not reduce depth of joint for sealant to less than the
minimum recommended by the manufacturer.
Cavities shall be filled and jointed with sealant in accordance with the manufacturer's
recommendations.
Sealant shall be tooled to form a smooth flat bead. Excess sealant shall be removed from adjoining
surfaces using cleaning materials recommended by the sealant manufacturer, and shall be left
clean.
2.13 Glazing
All glazing work shall be installed by skilled workmen experienced in this work in accordance with
BS 6262.
The Contractor shall fix all glass with the required gaskets, clips, beads, etc.
All glass shall be of the type, shape and size indicated on the drawings and/or specification
hereunder. All types of glass shall be free waves, bubbles, and other defects. All glass panels shall
have rounded edges to prevent any damage to gaskets.
The Contractor shall produce on request all invoices or advice notes from suppliers to confirm that
the glass is of the standard specified.
Any scratched, broken or otherwise defective glass is to be removed and replaced by the Contractor
at his cost during or on completion of the Works.
Page 19 of 113
LANDSCAPE SPECIFICATIONS
2.14.1 General
The Contractor shall submit representative samples of all glass he proposes to install in the Works.
On receipt of the Engineer's approval of same the Contractor shall commence the procurement of
the glass.
All glass shall comply with the Specification given below and shall be delivered to the site in cut
sizes and in packages marked as to the quality of the content.
2.14.2 Mirrors
Mirrors shall be of uniform thickness, free from waviness, air bubbles and the like. Representative
samples of mirror shall be submitted for the Engineer's approval. The mirror glass shall be clear
and silvered by nitrate precipitation, protected by copper plating with a protective plastic coating on
the reverse side. The mirrors shall be 6 mm thick and cut to sizes as shown with ground and
polished edges. The mirrors shall be set on 20 mm thick plywood backing plugged and screwed to
wall.
The glass framing shall both structurally support and adequately cushion the glass. To prevent
mechanical and thermal stresses on the glass, the framing system shall provide openings that are
within the tolerances for squareness, corner offset and bow.
If the variations from these tolerances are anticipated, details of same shall be advised to the
Engineer. If site conditions are found to be outside these tolerances corrections must be made
before the openings are glazed.
Workmanship shall generally be in accordance with CP 152 and respective British Standards.
The glass is to be delivered to the site with adequate protection to prevent damage and where
possible it is to be fixed in position immediately after delivery. When fixed the Contractor is to take
all necessary precautions to prevent damage during succeeding building operations and will be
entirely responsible for the replacement of any broken or damaged glass at his own cost.
The Contractor is to be solely responsible for determining the exact sizes of glass required,
including a tolerance of 2mm to each edge and he is recommended to check the necessary
dimensions on site.
No glazing is to be carried out until rebates have been painted with primer. Glazing beads as
applicable are also to be primed before fixing.
All mastic is to be neatly struck off to agree exactly with site lines inside and out.
Rates are to include for all necessary Spriggs, clips, setting blocks, location blocks and distance
pieces and for taking off and later re‑fixing loose beads.
Glass apertures in timber doors are to be bedded in chamois leather glazing strip, black ribbon
velvet or P.V.C. glazing strip to the approval of the Engineer.
Page 20 of 113
LANDSCAPE SPECIFICATIONS
2.17 Cleaning
All glass shall be thoroughly cleaned and polished on both sides and all paint spots and the like
completely removed to the satisfaction of the Engineer.
The Contractor is to provide, at all expansion joints in floors, roofs, ceilings, walls and columns,
appropriate extruded aluminium expansion joint cover system as appropriate and as shown on the
drawings and fixed in accordance with the manufacturer's printed instructions including all
necessary components and fixings.
Floor, wall, roof and ceiling joint covers shall be approved joint seals 50 mm deep. Butt joints within
continuing runs shall be a maximum of 6 m apart and will be sealed during installation using patent
butt joint sealing method and be finished standard grey.
Transition pieces at changes of direction and at joints between horizontal and vertical joint covers
shall be factory fabricated.
Page 21 of 113
LANDSCAPE SPECIFICATIONS
GENERAL
The painting materials shall be obtained from an approved manufacturer (but priority shall be given
to local manufacturers when complying with the required specification) and shall be supplied ready
mixed in the manufacturer's sealed and branded containers. Each container shall bear the maker's
brand name, identification of contents and directions for its proper use. All material must be
thoroughly stirred before use.
All sealers, primers, undercoats and thinners shall be the products recommended by the
manufacturers of paint used for the finishing coat.
Unless otherwise indicated on the Drawings colours shall be selected by the Architect.
The term "Paint" as used herein includes emulsions, enamels, lacquers, sealer and other coating
or inorganic finish, whether used as primer, intermediate or finish coats.
The Contractor shall protect all painting and decorating work and shall provide adequate dust
sheets, canvases, etc., in order to protect adjacent work.
All painting and decorating shall be applied by skilled workmen experienced in this work.
The Contractor shall repaint at his own expense any work where the paint is found to be incorrectly
applied.
Brushes, pails, kettles, etc. used in carrying out the work shall be clean and free from foreign matter.
They shall be thoroughly cleaned before being used for different types or classes of materials.
The Contractor is to submit to the Engineer for approval the brand and quality of the paints he
proposes to use. If approval is given to a brand of paint the contractor shall use the primers
undercoat, etc., manufactured or recommended by the manufacturer of that brand and
notwithstanding anything herein contained shall prepare the surface and carry out the work in
accordance with the manufactures specification to give the best finish required on the surface to
be painted.
All paints to be used under this Contract shall be delivered to and stored on the Site in sealed
labeled containers a minimum of 30 days prior to application. Upon notification by the Contractor
that the material is at the Site. Samples of each material shall be obtained at random from sealed
containers by the Engineer in the presence of an authorized representative of the Contractor.
Samples shall be clearly identified by commercial name, type of paint and intended use. If judged
necessary by the Engineer the paint sample may be tested for compliance at the Contractor's
expense in a laboratory designated by the Engineer.
Complete colour charts for the paints to be used shall be submitted to the Engineer for approval
and the preparation of the colour schedules.
Paints shall be factory manufactured and delivered to the site in unbroken containers which shall
show the designated name, formula, colour, manufacturer's directions and name of manufacturer
all of which shall be plainly legible at the time of use.
Pigmented paints shall be supplied in containers not larger than 25 kg. All paints shall be products
that have a minimum of 2 years satisfactory field service.
Mixing and applications of paint shall be in accordance with the specification of the manufacturers
concerned and to the approval of the Engineer. The mixing of paints, etc., of different brands before
or during painting materials shall be allowed except strictly as detailed by the manufacturers and
as approved by the Engineer. Spraying will only be allowed with the Engineer's written approval.
Page 22 of 113
LANDSCAPE SPECIFICATIONS
3.1 Materials
The materials to be used as required by the Schedule of Finishes and the drawings shall be of the
best quality and of approved types, obtained from an approved manufacturer.
- The product shall be thoroughly mixed and ground. It shall not be settled, caked or thickened to
such a degree that it cannot be mixed easily with a paddle by stirring to a good uniform brushing
consistency.
- The colour of the paint shall match the approved sample.
- Paint shall show no evidence of cracking, chipping, flaking or dusting.
- Paint shall not skin (form a thin membrane surface on the top of the liquid) within 48 hours in a
filled closed container.
- Paint in the containers during and after application shall not be abnormally pungent, offensive
or disagreeable.
- Paint shall show easy brushing, good flowing and spreading and good levelling properties.
Those properties shall be demonstrated on test specimens at the request of the Engineer. Coats
that have any noticeable pull under a large brush and that show poor spreading and flowing
properties will not be acceptable.
- Paint shall dry to a uniform, smooth, flat or semi-gloss appearance under conditions of
illumination and wearing. There shall be no laps, skips, highlighted spots or brush marks. Tinted
paints shall dry to a uniform colour.
- Relocating of a previous painting surface shall produce no lightening softening or other film
irregularities.
3.1.2 Knotting
Knotting shall be composed of dissolved shellac or other resin which remains unaffected by the
resinous materials in the wood or the following paint coating, thereby preventing the resinous
materials in the timber leaching into the paint film and causing discoloration or defective drying, it
shall be in accordance with B.S 1336.
3.1.3 Filling
3.1.4 Stopping
Stopping for woodwork to receive clear finish shall be tinted to match surrounding woodwork, to
approval.
Stopping for internal woodwork, plywood, hardboard, and fibreboard shall be linseed oil putty to BS
544. tined to match the colour of the undercoat.
Stopping for external woodwork shall be white lead paste and gold size well mixed.
3.1.5 Thinners
Thinners shall be approved turpentine or white spirit to BS245 where paints are specified to be
water thinned, in which case fresh water shall be used for thinning.
3.1.6 Satin
Stain for woodwork shall be an approved brand of oil stain complying with B.S.1215.
Page 23 of 113
LANDSCAPE SPECIFICATIONS
The etch primer shall be mordant solution, slightly acidic in nature and containing solvents, for
applying to new smooth metallic surfaces to remove grease, organic soaps and provide a physical
key, or other equal and approved.
3.1.9 Varnish
Varnish for interior woodwork shall be an approved brand, oil varnish. Varnish shall form a hard
flexible transparent and quick drying film.
Linseed oil for woodwork shall be refined linseed oil to comply with B.S 246.
Priming paints shall be the primer recommended by the manufacturer of the finishing paint or:
- For woodwork lead based or priming paint to comply with B.S 2521 and 2523.
- For steel work red oxide priming paint to comply with B.S 2524.
- For galvanized, zinc or aluminium work grey zinc chromate priming paint.
- For concrete, blockwork, plaster, plasterboard and the like alkali priming paint.
3.1.12 Undercoating
The rust inhibiting primer shall be calcium plumbate red head, chromate, zinc chromate or other
equal and approved primer.
Finishing paints shall have either a matt, eggshell, semigloss or gloss appearance as indicated on
the schedule requested by the Engineer or these Specifications. Allowance must be made for a full
colour range.
The clear finish is to be polyurethane matt lacquer or other equal and approved. To external timber
works the clear finish shall be clear (unstained) preservative oil
Emulsion paint shall have either a matt or eggshell appearance as indicated on the schedule or
requested by the Engineer or these Specifications.
Page 24 of 113
LANDSCAPE SPECIFICATIONS
External walls and other surfaces indicated on the drawings shall be painted with proprietary paint
as stated in the Particular Specification. The paint shall be applied strictly in accordance with the
manufacturer's printed instructions.
3.2 Workmanship
3.2.1 General
The Contractor shall carry out all tests necessary for determining the colours and shades of the
finishes and the appropriate methods of application. Sample panels shall be completed in
accordance with Architect's instructions.
All work shall be performed in accordance with the manufacturer's written instructions.
Before application of any paint or finish all surfaces shall be cleaned, dried and prepared as
specified hereinafter, all to the Architect's approval, no work shall commence until this approval is
given in writing to the Contractor.
The Contractor shall coordinate work to ensure that factory primed items are primed or painted as
required in the Specifications.
All metal fittings such as hardware and fastenings, etc., not required to be painted shall first be
fitted and then removed before the preparatory processes are commenced. When all painting is
completed the fitting shall be cleaned and refixed in position.
Before painting floors must be washed and every possible precaution shall be taken to keep down
dust before and during the painting processes. No paint shall be applied to surfaces structurally or
superficially damp and all surfaces must be ascertained to be free from condensation,
efflorescence, etc., before the application of each coat.
No exterior or exposed painting shall be carried out under adverse weather conditions such as rain
, extreme humidity, dust storms, high temperature of surface etc.
All coats of paint must be thoroughly dry before subsequent coats are applied, and rubbed down
with fine waterproof abrasive where necessary.
All coating shall be well applied, leaving no sags, laps, brushes or other defects. Each coat must
thoroughly dry before next coat is applied. All work must be carefully cut into a true line and left
smooth and clean.
Details of mixing and application shall be in accordance with the Specifications of the manufacturer
concerned and to the approval of the Architect. The mixing of paint, etc., of different brands before
or during application will not be permitted. No dilution of painting materials shall be allowed except
strictly as detailed by the manufacturers and as approved by the Architect.
On surfaces which are not accessible to paint brushes or rollers paint shall be applied by spraying
or with sheep skin daubers. All surfaces to be painted shall be thoroughly covered with paint.
Method of paint applications shall be approved by the Architect prior to the commencement of the
work.
Brushes, pails, kettles and all other tools and equipment used in carrying out the work shall be
maintained in good working order, and shall be clean and free from foreign matter. They shall be
thoroughly cleaned before being used for different types or classes of materials.
The Contractor will be required to repaint, at his own expense any work on which the paint is found
to be incorrectly applied. The Contractor shall be responsible for protecting from damage the paint
work and all other work during and after operations including the provision of all necessary dust
sheets, covers, etc. All paints dropping shall be cleaned up as the work proceeds.
Page 25 of 113
LANDSCAPE SPECIFICATIONS
All loose and defective paint shall be removed from previously painted surfaces before re painting.
All burning off must be done by skilled workmen. The blow lamp must not be used on surfaces
adjoining glass. Damage to adjacent surfaces shall be made good at the Contactor's expense.
Prior to hand over the Contractor shall carry out all remedial painting work due to damage caused
by others, adjustment and easing of joinery and metal work testing and commissioning of service
installations and the like all as instructed by the Architect. On completion, leave Works clean and
tidy to the Architect's approval.
Concrete, blockwork and plaster surfaces to be painted or decorated shall have all cracks cut out
and made good to the satisfaction of the Architect.
Plasterboard surfaces shall have taped joints and the surface puttied to the satisfaction of the
Architect. The surfaces shall be completely dry and shall be brushed free of impurities immediately
prior to the commencement of the painting work.
Efflorescence shall be completely removed by rubbing down with dry coarse cloths followed by
wiping down with damp cloths and allowed to dry. All surfaces shall be rubbed down with fine glass
paper and brushed free of dust before applying any form of decoration.
Concrete blockwork and plastered surfaces which are to receive paint shall be given one thin coat
of oil putty and allowed to dry for at least two days. The surfaces shall then be rubbed down with
fine glass paper and given a second thin coat of oil putty and when completely set shall be rubbed
down again with fine glass paper before applying the painting system.
Emulsion paint shall be applied by brush or roller and shall consist of primer and two full coats of
paint.
Texture paint shall be uniformly applied at a rate of not less than a 4m² per litre by overlapping,
crisscross rollers or spray in accordance with the manufacturer's instructions. Where finished
surfaces are described as having smooth texture finish, the overall thickness of the applied finish
shall be less than 1.5 mm. Where finished surfaces are described as having rough texture finish,
the overall thickness of the applied finish shall be not less than 2 mm. Finished surface shall be
uniform in sheen colour and texture, free from runs, sags, crawls or other defects.
Oil paint shall be applied by brush or roller and shall consist of a priming coat, two undercoats and
one finishing coat of paint. Fire resistant paint shall be applied in three coats over a primer all in
strict accordance with the manufacturer’s instructions.
All plastered or rendered surfaces shall be twice stopped with approved putty filler. The first coat
of stopping shall be applied after the primer coat has dried out completely. And the second coat
after the first undercoat application. Each coat of stopping shall be allowed to dry and harden
thoroughly and shall then be rubbed by sandpaper until smooth surface is achieved.
The emulsion or P.V.A paint is to be applied in three coats, the first a thinned coat and the other
two full coats. Each coat shall be allowed to dry and harden thoroughly before the next coat is
applied.
Where shown on the Drawings or required by the Architect the wood shall be stained with a water
or spirit stain to the approval of the Architect.
The coats of lacquer shall be applied on joinery by brush or spray, either in the joinery shop or on
Site as directed by the Architect.
Page 26 of 113
LANDSCAPE SPECIFICATIONS
The stain finish to woodwork shall be an approved manufacturer's oil stain system applied strictly
in accordance with the manufacturer's instructions.
All surfaces are to be thoroughly dry and cleaned and sanded down and all nail holes or similar
defects shall be filled and levelled up with approved stopping. The finish shall be applied in two
coats. The first coat shall be pigmented stain wax brush applied. The surface shall be allowed to
dry for 2 10 minutes and then rubbed with a cloth in a rotary motion to remove excess stain and
produce an even surface.
The first coat shall be allowed to dry completely before application of the second coat. The second
coat shall be natural (clear) stain wax, buffed. The Architect shall select the stain colour and the
Contractor shall allow for preparing sample panels for approval and these sample panels will
provide the standard for the work.
3.2.5 Varnishing
All surfaces to be varnished shall be thoroughly dry and cleaned and sanded down and all nail
holes or similar defects shall be filled and levelled up with approved hard stopping. Sanding shall
follow the line of the grain. Knots shall be treated with two coats of knotting.
Two or three coats of clear varnish shall be applied as recommended by the manufacturer of the
varnish or as directed by the Architect.
Woodwork to be painted shall be cleaned of impurities. Knots shall be treated with two coats of
knotting.
Priming paint shall be applied by brush. Two coats shall be applied to end grain. Priming paint shall
be applied on Site after the Architect has approved the joinery and before it is fixed. When the
priming paint is dry, all cracks, holes, open joints and the like shall be filled with stopping and rubbed
down with fine floss paper.
Two undercoats and one finishing coat of paint shall be applied by brush. The priming paint and
undercoats shall be lightly rubbed down with glass paper to remove blemishes, and all dust
removed before the application of subsequent coats.
Steelwork delivered to the site un-primed shall be cleaned of impurities, scrapped and wire brushed
to remove rust and painted with one coat of priming paint applied by brush.
Steelwork delivered to Site primed shall be cleaned of impurities and damage to the priming paint
and made good with priming paint.
Galvanized metalwork to be painted shall be cleaned of impurities. Where rusting has occurred the
rust shall be removed by wire brushing and made good with an approved rust inhibitor. The surfaces
shall be coated with a mordant solution, washed with clean water and painted with two coats of
priming paint applied by brush.
Metal which is concealed shall be prepared and primed as above and shall be painted with two
priming coats and one finishing coat of paint applied by brush.
3.3 Guarantees
For all external and internal painting works, the Contractor shall provide a guarantee for material
and workmanship to be valid for a period of five years from the date of practical completion
certificate.
Page 27 of 113
LANDSCAPE SPECIFICATIONS
4.1 Description
Division 1, General Requirements, is a part of this Section and shall apply as if repeated here.
Provision of labour, materials, accessories, equipment and services required to supply and install
exterior furnishings, as indicated on drawings and specified herein.
Sampling and Testing shall be the responsibility of the Contractor and shall be performed at no
additional cost to the Employer. Tests shall be performed in sufficient number to ensure that
materials and performance meet the specified requirements and as detailed in the specifications.
Samples for testing shall be collected as approved by the Engineer and each sample shall be
divided in two parts, one part shall be submitted to the Engineer, and the other part shall be
submitted for testing. Copies of test results shall be furnished to the Engineer for approval. Trial
mix of every class of concrete shall be verified by DM-DCL.
Product certification shall be as described in clause 1/12.16 in page GS 1/11 of Volume 2 –Part
DM General Specifications of Roads Department.
The Contractor shall submit his proposed work method statement for approval prior to commencing
each item of work. The Statement shall detail proposed sequence of work, hold points, testing
frequency and document control.
Quality control program shall be detailed in the Monthly Progress Report as well as in the final
Materials reports and submitted to DCL for review as stated in clauses no. 1.2, 1.3, 1.4 and 1.6 in
Page 1/1 of this specification.
4.3 Submittals
4.3.1 Samples
Samples and chemical analysis of the following shall be submitted to the site in accordance with
the General Conditions, or as directed from time to time to confirm compliance with specification
requirements:
Page 28 of 113
LANDSCAPE SPECIFICATIONS
Before commencing work the Contractor shall submit to the Engineer all catalogue cuts, diagrams,
drawings and such other data as may be required to demonstrate compliance with the
Specifications for review and approval.
The Contractor shall submit manufacturer's recommendations for installation and commissioning
of each material and piece of equipment for approval prior to commencing work.
The Contractor shall submit manufacturer's listing of spare parts for approval prior to
commissioning any piece of equipment.
The Contractor shall maintain As Built drawings of all works carried out.
Submit manual of maintenance procedures 30 days before end of maintenance period for
Employer's use.
All products shall be delivered in the manufacturer's original protective packaging and shall be
inspected at the time of delivery.
Any products, which are found to be damaged, not in accordance with Specifications, or date
stamp, expired, shall be immediately removed from the site and replaced.
Sensitive materials shall be properly protected during transport from point of manufacture or
production and during storage prior to delivery to the site.
All products shall be handled and stored in accordance with printed recommendations of the
manufacturer.
All site storage areas shall be shaded, at all times. Precautions shall also be taken to protect items
sensitive to sunlight or heat prior to placement. All furniture shall be protected with heavy duty
plastic (bubble wrap) from the time of installation until handover following an inspection and
approval by the Architect. Any damage during construction is at the Contractors risk.
Ensure that the location of buried utilities and other services have been clearly identified during
installation and confirmed by investigation.
Immediately repair damage to utilities, structures, and permanent buried and above ground
services, should it occur, at no additional cost to Employer.
Page 29 of 113
LANDSCAPE SPECIFICATIONS
free from bows, twists, crooks and waves that cannot be corrected in the works process. The
Contractor shall submit warranties as to origin of the timber.
4.6.1 Origin
The Contractor shall furnish certificates indicating the origin of the timber.
All timber shall be pressure treated with an approved preservative to protect against rot and insect
attack. The Contractor shall furnish the Engineer with Certification of the preservative process.
All timber shall be treated with an approved fire retardant in accordance with the requirements of
the relevant Municipality Department. The Contractor shall furnish the Engineer with Certification
of the process.
4.6.4 Hardware
Rough hardware such as nails, screws, clips etc shall be hot dipped galvanised.
Anchor bolts shall conform to ASTM including embedment length, hooked end shall be used in all
situations of concrete embedment.
Provide standard steel washers and nuts. Field welding shall not be permitted.
Joints shall be tight and so formed to conceal shrinkage. All nail heads in finished work shall be
countersunk
4.6.5 Quality
It is not the intent of this specification to define the types, sizes and installation methods for each
item of work. The methods of detailing and construction shall be equal in quality of similar details
as may be shown on the drawings. The work that is finished shall be coated/stained and shall be
free from defects or blemishes on the surfaces exposed to view that will show after the finish coat
has been applied.
4.7.1 Certificates
Copies of the following certificates shall be submitted to the Engineer prior to acceptance of
materials.
- Importation, transportation and any other certificates for furniture and materials required by
national or local laws.
- Any other certificates required by the Engineer.
4.7.2 Warranties
All components of each product/system shall be protected against failure and/or performance
deficiencies by the manufacturer’s warranty. All warranties shall be specific and non-pro-rated and
shall guarantee against material and labour defects for a minimum of five (5) years.
All materials and fabrication shall be of the highest quality available and shall be identified by the
official grade mark of the appropriate regulatory or testing authority and the manufacturers name.
Page 30 of 113
LANDSCAPE SPECIFICATIONS
4.9 Installation
For each of the products/system specified and requiring a manufacturer’s warranty and Contractors
maintenance bond, the proposed installation contractor must provide evidence of the
manufacturers license to install and evidence of a minimum of five (5) years’ experience in the
installation of similar products on projects of similar complexity and size.
All furniture to be installed strictly in accordance with manufacturers specification unless otherwise
instructed.
4.10 Maintenance
During the period from installation to handover the Contractor shall maintain the furniture in
accordance to the manufacturers specification including cleaning, repairing and reapplication of
paint/preservative treatments as required.
The Contractor shall compile a comprehensive Maintenance Manual, which will include the
following:
Page 31 of 113
LANDSCAPE SPECIFICATIONS
5 SOFT LANDSCAPING
GENERAL
5.1 Description
Division 1, General Requirements, is a part of this Section and shall apply as if repeated here. BS
3936-Part 1 Nursery Stock, Trees and Shrubs and BS 4428 General Landscape Operations apply
to this Contract.
Provision of labour, materials, accessories, equipment and services required to install trees,
shrubs, hedges, soil, soil ameliorants, as indicated on drawings and specified herein.
Sampling and Testing shall be the responsibility of the Contractor and shall be performed at no
additional cost to the Employer. Tests shall be performed in sufficient number to ensure that
materials and performance meet the specified requirements and as detailed in the specifications.
Samples for testing shall be collected as approved by the Engineer and each sample shall be
divided in two parts, one part shall be submitted to the Engineer, and the other part shall be
submitted for testing. Copies of test results shall be furnished to the Engineer for approval.
The Contractor shall submit his proposed work method statement for approval prior to commencing
each item of work. The Statement shall detail proposed sequence of work, hold points, testing
frequency and document control.
5.4 Submittals
5.4.1 Samples
1 Samples and chemical analysis of the following shall be submitted to the site in accordance with
the general requirements, or as directed from time to time to confirm compliance with
specification requirements.
▪ Dune sand, organic and inorganic amendments
▪ Soil conditioner & Organic compost
▪ Fertilizer
▪ Soil additives & ameliorants
▪ Salt Barrier / geotextile
▪ Drainage materials / Root barrier/ items
▪ Tree support / staking materials
1 Keep approved samples on-site, in an approved, protected location, until work has been
inspected, approved and accepted.
Page 32 of 113
LANDSCAPE SPECIFICATIONS
The contractor shall prepare full shop drawings detailing location, size, density, specification and
final quantities of plant material, together with method of support, planting method and planting pit
details as detailed in the tender drawings and described in this specification. The shop drawings
shall be submitted for the approval of the Engineer prior to works commencing.
Before commencing work the Contractor shall submit to the Engineer all catalogue cuts, diagrams,
drawings and such other data as may be required to demonstrate compliance with the
Specifications for review and approval.
The Contractor shall submit manufacturer's recommendations for installation and commissioning
of each material and piece of equipment for approval prior to commencing work.
The Contractor shall submit manufacturer's listing of spare parts and obtain approval prior to
commissioning any piece of equipment.
The Contractor shall maintain As Built drawings of all works carried out.
Submit manual of maintenance procedures thirty (30) days before end of maintenance period
for Employer's use.
All products shall be delivered in the manufacturer's original protective packaging and shall be
inspected at the time of delivery.
Any products, which are found to be damaged, not in accordance with Specifications, or date
stamp, expired, shall be immediately removed from the site and replaced.
Page 33 of 113
LANDSCAPE SPECIFICATIONS
Sensitive materials, such as fertilisers, plants, etc. shall be properly protected during transport from
point of manufacture or production and during storage prior to delivery to the site.
All products shall be handled and stored in accordance with printed recommendations of the
manufacturer.
All site storage areas shall be shaded, at all times. Precautions shall also be taken to protect items
sensitive to sunlight or heat prior to placement.
Ensure that the location of buried utilities and other services have been clearly identified
during installation and confirmed by investigation.
Immediately repair damage to utilities, structures, and permanent buried and above ground
services, should it occur, at no additional cost to Employer.
5.7 Certificates
Copies of the following certificates shall be submitted to the Engineer prior to acceptance
of materials.
Remove from site immediately any soil which is not to specification or is insufficiently clean.
For all purposes, on site dune sand of less than 1000 TDS shall be provided, mixed and spread
or placed in mixture.
The soil shall be free draining, non-toxic and capable of sustaining healthy plant growth. The soil
shall not contain calcium carbonate, subsoil, refuse, roots, heavy clay, noxious weeds, phytoxic
materials, coarse sand, rocks, brush, litter or any other deletrious materials.
The planting medium shall consist of dune sand mixed with soil conditioner or organic fertiliser
composed of pasteurised compost and inorganic amendments, thoroughly mixed.
The Contractor shall prepare as built drawings for soiling and submit to the Engineer for approval.
Four sets to be submitted at handover.
Page 34 of 113
LANDSCAPE SPECIFICATIONS
Sand (2mm to 0.05mm) 70% to 80% Silt (0.05mm to 0.002mm) 25% to 30% Clay (<0.002mm)
5% max
- 4-20 % (by weight) at 18ºC (65 ºF) using Walkley-Black method RB427.
- No roots larger than 15mm diameter or longer than 200mm shall be allowed.
5.9.3 Conductivity
Acidity
pH: 5 – 7.5
Page 35 of 113
LANDSCAPE SPECIFICATIONS
Soil conditioner shall be an organic compost or other fibrous approved organic matter suitable for
mixing with planting soil to make a friable growing medium for plants. It shall be resistant to rapid
decay, free of soluble salts below 900ppm, pH 6-7 and free of large lumps of debris.
Submit 1-litre sample with back up test data before applying on site.
Submit samples and test data for approval before applying on site. All composts are to be sterilised
before being packed for transport. Odorous materials shall be subject to rejection.
5.12.1 Fertilisers
Shall be non-toxic to human, birds and animals under normal use. The approved product shall be
delivered to site in original unopened containers. Fertilizer shall be in the form of slow release
granular, tablets or spikes as dictated by plant type. Each shall be coated with Urea and/or sulphur
31%. Compound fertiliser (Osmocote, Emirates Bio- fertilizer or equivalent) shall be composed of
16% soluble Nitrogen, 18% Phosphoric acid and 5% water soluble potash plus iron. Available
equivalents are subject to Engineers approval.
Organic Fertiliser
All organic fertilisers shall be balanced and certified fertilizer with 40-50% Organic Matter (OM), PH
6-7, smell-free and retains moisture up to 30% of its weight. It shall be heat treated and free of
weeds, nematodes, Fusarium, bacteria and any other harmful microorganisms. Samples of organic
fertiliser to be used must first be submitted to the Client’s Landscaping Unit for approval.
Pine bark Nuggets shall be used as mulching to all planting in potted plants. Average 25mm pine
bark nuggets shall be at 40-50mm depth mulch above soil level. Recommended colour for the pine
bark nuggets shall be dark brown. Typical pine bark nuggets shall be Metpap Trading or equivalent
brands.
Mulches shall be free from soluble salts or toxic materials, resistant to rapid decay, an approved
friable-composted organic material or an approved mix and shall have a pH of between 5.5–7.
Initial mulching is to take place within two (2) days of installation of plants.
Submit samples and pH values for approval, before applying on site. Hydroponics
Page 36 of 113
LANDSCAPE SPECIFICATIONS
All plant containers shall be equipped with a sub-irrigation system. Sub-irrigation system shall
include a water supply shaft for water and liquid fertilizer, a reservoir that holds up to 26.5 litres of
water depending on the size of the planter and a water level indicator to show the water level left
in the reservoir. Plant containers shall be fixed with a removable plug to its drainage outlet.
Light expanded clay aggregate shall be approved low-density inert material such as expanded clay
or volcanic scoria or other porous aggregate capable of being compacted within the soil zone to
90% compacted without being crushed. Free from dust and debris, pH 6 – 6.5 and free of soluble
salts.
A 2-litre sample shall be submitted and tested, as part of soil mix, for physical and chemical
performance.
Refer to Section 13 Part 10 for particular specification of green roll layer and green flocks.
Unless otherwise agreed, the Contractor shall apply the following soil mixes as appropriate for
planting, subject to Engineer’s confirmation and approval.
For use in planter boxes, planter beds, roof planter and plant containers/ pots. This shall be
prepared under controlled mixing conditions such as on a concrete floor to ensure even mixing and
free from contamination. Planting
▪ Soil 40%
▪ Soil Conditioner 20%
▪ Organic Compost 25%
▪ Light Weight Aggregates 15%
For use on open ground plant beds in a park this will be the ratio. Ensure even mixing and free
from contamination. Planting medium to meet DM standard and inclusive of 10% water saving
material as specified in section 13
5.14 Plants
All plants shall be from an approved source. Samples of all plants to be used in this contract shall
be submitted for approval with the height and girth of all trees/shrubs matching the specification in
the tender documents. All imported plants shall be acclimatized for a minimum period of 4 months
prior to delivery to site. All plants shall be free from disease, infestation and infection.
All plants shall be first class representation of their normal variety or species, having strong growth.
Drawn plants with soft growth requiring additional supports other than specified are not acceptable.
All trees shall be free from disfiguring knots, abrasions of the bark or wind injury or other
disfigurements and shall bear evidence of proper pruning.
Page 37 of 113
LANDSCAPE SPECIFICATIONS
Unless otherwise specified, three tree stakes shall be provided for all newly planted palms and
shall be sawn timber treated with an approved preservative applied by the vacuum pressure
impregnation method.
All stakes shall be 2.50m free of projections and pointed at one end. Stakes shall be 50 x 50 mm
(net section); the length below ground to be 1.0 m minimum and the length above to be 1.5m,
unless otherwise approved by the Engineer. Smaller stakes to 1.0m may be required for some
situations as determined by the Engineer.
The palm shall be supported by 10mm gauge galvanized steel cable and tensioned via a galvanized
steel turnbuckle. The cable shall be fixed to each stake and create a loop around the truck (see
13.2.27 Tree Ties below). Cables shall be spaced equally around the trunk at 120º, the angle of
support shall be 45º.
Unless otherwise specified, individual palms shall be supported by 10mm gauge galvanized steel
cable fixed to the interior face of the concrete palm pit / planter and tensioned via a galvanized steel
turnbuckle. The cable shall be secured to the internal face of the palm pit / planter using galvanized
steel bolts and hooks, and then looped around the truck (see .27 Tree Ties below). Cables shall
be spaced equally around the trunk at 120º, the angle of support shall be 45º.
Unless otherwise specified, two tree stakes shall be provided for all newly planted trees and shall
be sawn timber treated with an approved preservative applied by the vacuum pressure
impregnation method.
All stakes shall be 3m free of projections and pointed at one end. Stakes shall be 50 x 50 mm (net
section); the length below ground to be 1.0 meter minimum and the length above to be 1.2m, unless
otherwise approved by the Engineer. Smaller stakes to 1.5m may be required for some plants as
determined by the Engineer.
Appearance: Note: Tanalith pressure treated timber offers protection against fungal and insect
attack, including termites, for both in and out of ground contact, interior and exterior applications
when treated to the correct end use specification. Tanalith treated timber has an initial natural green
coloration.
Upon external exposure, the green color slowly weathers to a warm, honey brown and in the longer
term becomes a natural silver grey. This weathering process does not indicate any compromise in
preservation protection.
5.16.1 Description
Landscape edging as a border between planting beds, pathways, drives, mulch & rock division, or
anywhere separation and definition is required.
Page 38 of 113
LANDSCAPE SPECIFICATIONS
5.16.2 Delivery
Material should be ordered and accepted in original shipping cartons of standard size. Please note
quant-ties per box on inside of brochure. Material should be stored in a flat area with boxes
protected from rain.
5.16.3 Material
Preparation
Ensure that all underground utility lines are located and will not interfere with the proposed edging
installation before beginning work. Locate border line of edging with string or other means to assure
border straightness and curves as designed. Dig trench 1 inch deeper than set of edging bottom.
Placement
Set edging into trench with top at 1⁄2 inch above compacted finish grade on turf side with side
having loops for stakes placed on opposite side of turf. Drive stakes through edging loops until
locked in place. Requires 5 stakes evenly spaced for each 16’ section, or 3 stakes evenly spaced
for each 8’ section with a total of 8 stake loops available in each 16’ section if necessary. Provide
additional stakes at approximately 24 inches apart, longer stakes, heavier gage stakes, or any
combination of
previously mentioned as necessary to firmly secure edging for permanent intended use.
Corner/angles
Where edging sections turn at corners or at angled runs, cut edging partially up through its
height from bottom and turn back to desired angle.
Sections to lock together without offset or double thickness at the joints and secured with two 12"
stakes at every joint.
All aluminium landscape edging shall be at least 3.2mm thick X 100mm deep X 20-60cm long.
Finish Mill 9 natural aluminium) or as specified in the drawings.
Rubberised flexible tree ties shall be used to tie the tree to the stake; ties shall be manufactured
specifically for the purpose of tying trees and shall allow appropriate flexibility and adjustment as
the tree grows.
Ties shall be placed at no higher than 1/3 the total height of the plant. Plants requiring staking at a
higher level may be rejected.
Salt Barrier (hydrophobic), geotextile material (non-woven composite geotextile) laying on all sides
and base of planting beds and lawn areas, to prevent fluctuating tidal underground water being
drawn into root zone. Typical geotextile shall be Terram (Hydrophobic), Salt Barrier or equivalent
brands.
Page 39 of 113
LANDSCAPE SPECIFICATIONS
Surround root barrier shall be used to protect plant roots from penetrating and damaging concrete
slabs or walls for all planter boxes and extensive green roofs. Typical root barrier shall be DeepRoot
or equivalent brands.
Advanced trees are large size container grown trees pruned during growth to produce a tight well-
rounded head, and a straight stem clear of leaves or twigs. Trees shall be 40-60 mm circumference
of stem when measured 1.0m from ground level and shall have a clear straight stem of minimum
1.0m. The head shall be well balanced and rounded and contain at least four main branches, giving
an overall height of 2m at the time of planting. Pruning at the time of removal from the nursery will
not be permitted. In dry weather conditions, trees are to be sprayed with approved anti-transpirant.
Rootball dimensions: Diameter 400mm x 350mm deep minimum.
Regular sized trees are container grown with a 40-60 mm circumference of stem when measured
100 cm from ground level.
The head shall be well balanced and contain at least four main branches, giving an overall height
of 1.5m at the time of planting. Pruning at the time of removal from the nursery will not be permitted.
In dry weather conditions, trees are to be sprayed with approved anti-transpirant. Rootball
dimensions: diameter 300mm x 300mm deep minimum.
Note: All trees and palms are to be purchased and stored in suitable nursery conditions within 1
month of the start of the contract.
Note: All dimensions shown with tolerances (i.e. 120-150mm) refer to maximum and minimum
dimensions that will be accepted. Measurement of all plants of one species shall, as a minimum,
average between the upper and lower figures (i.e. in the above case 135mm).
Palms shall be a minimum of 900mm circumference of stem when measured 1m from ground level,
and shall have a clear straight trunk of at least 4m with minimum 8-12 fronds. All plants are to be
selected to give a maximum height variation between plants of 300mm in stem height between soil
level and the base of the lowest leaf at the time of planting. The heads of the palms shall be well
balanced and evidence of one new growing shoot, all free from pest or disease attack. No dead
leaves are to be present, and all leaves on the plants shall be free from yellowing, tears or splits,
and cut leaves will not be permitted.
Any flowers, fruits and suckers shall be removed before being brought to site, and cut cleanly from
the base of their stems. Imported material shall be acclimatised for at least six months before
removal from the nursery.
Page 40 of 113
LANDSCAPE SPECIFICATIONS
▪ Palms shall be balled and burlapped unless container grown are available.
▪ Offshoots will not be acceptable. They shall have a vigorous root system, crown of new
leaves, proper colour of leaves of an adult palm and sufficient hardiness.
▪ Prior to transporting for transplanting, all suckers, flowering and fruiting parts and
approximately thirty percent of fronds shall be removed. The remaining fronds shall be
sprayed with an anti-desiccant during transplanting, lifted to enclose and protect the
growing tip, wrapped in Hessian and securely tied in position. The roots shall be balled
and the Hessian tied.
▪ The crown shall be protected at all times and shall be burlapped for transport and until
the palm is growing successfully in its final location.
These are as above, but of smaller size. Palms shall be a minimum of 300mm circumference of
stem when measured 1m from ground level, and shall have a clear straight trunk of at least 2.5m
with a minimum 5-8 fronds. The heads of the palms shall be well balanced and evidence of one
new growing shoot, all free from pest or disease attack. Imported material shall be acclimatised
for at least six months before removal from the nursery.
5.26.1 Shrubs
Shrubs shall meet requirements for spread or height indicated in the drawing and/or specified in
this contract. Shrubs shall be new season stock having been transferred to the current container
size a minimum of twelve (12) weeks prior to inspection in the nursery. Measurement of height and
stem calliper for shrubs shall be taken from the ground level to the average height of the shrubs
and not the longest branch or stem. Shrubs, unless otherwise specified, shall have at least three
(3) stems and shall be well balanced and bushy with strongly developed fibrous root system, free
from pest and disease. All shrubs shall be grown in containers of appropriate dimensions suitable
for the size of the plant (minimum size 4 litres).
Herbaceous plants are non-woody perennials of clump forming habit. Such plants shall have well-
developed stems with good symmetry and a healthy root system, free from pest and disease.
Herbaceous plants shall be container grown with evidence of growing shoots emerging above soil
level. All shrubs and herbaceous plants shall be cultivated in containers of appropriate dimensions
corresponding to the size of the plants and the requirements of the species. Clumps of herbaceous
plants may include rhizomes, corns, tubers or roots. Multi stemmed species such as Cyperus sp.,
Raphis sp., etc. shall have a minimum of five (5) stems.
5.26.3 Groundcovers
Groundcovers are low growing, 500mm or less, or prostate shrubs or herbaceous plants whose
habit is to totally cover the soil. All ground cover species shall be evenly balanced to allow equal
growth in all directions. Plants shall have fully developed root system and leaves. Rooted cuttings
will not be accepted. All plants shall be container grown.
To be well grown in 120mm pots (jiffies or plastic containers) and shall have minimum of 4 flowers
at planting.
Page 41 of 113
LANDSCAPE SPECIFICATIONS
- Grass stolons shall be vigorous, and healthy, free from disease, insect pests, weeds, other
grasses and any other harmful or deleterious material
- Grass stolons shall be 75mm to 150mm length, with 3 to 6 buds.
- Grass stolons shall be as identified on the Planting plans.
1 Prior to beginning planting operations the irrigation system must be completely operational
ensuring 100% coverage.
2 Bring the water content of the area to be planted to field capacity and allow water to percolate
until standing water disappears.
3 Apply complete fertilizer at the rate of 0.25 kg nitrogen per I00m2 prior to planting stolons.
4 Cultivate to a depth of200mm.
5 Keep dry dormant stolons refrigerated 0-3 C until the area to be planted is prepared. Do not
exceed two weeks of refrigeration. Soak stolons in water after removing from cold storage and
prior to planting.
6 Do not exceed two days of storage on job site. Stolons are to be kept moist, shaded and
ventilated during such storage.
7 Plant during the time of year when day time temperatures do not exceed 38°C and night time
temperatures are not below 15°C. Mean temperature should exceed 26 C. Water within 15
minutes of planting at 38 C, 30 minutes at 28°C, 60 minutes at 21 C, and 120 minutes at l6 C.
8 Plant utilizing a disc to cut in stolons and followed by a cultipacker roller, or other technique
approved by the Engineer.
9 Water as necessary to keep the stolon bed moist until germination. Once grass is up begin
lengthening intervals between irrigation.
10 Sow at 6 bushels per 100 square meters.
- Turf shall be well-established lawn grass, vigorous, well rooted and healthy, free from
- disease, insect pests, weeds, other grasses and any other harmful or deleterious material
- Turf sods shall be 60cm x 30cm and shall be as identified on the Planting plans.
- Turf sods shall have full coverage and root development that will support its own weight without
tearing when suspended vertically by holding the upper two comers.
- Damaged turf sods shall not be accepted.
Page 42 of 113
LANDSCAPE SPECIFICATIONS
11 Turf shall be laid with closely fitted joints and the ends of the strips staggered. Plug openings
with turf.
12 The area shall be thoroughly watered to penetrate the subsoil to at least a 30cm depth.
13 Watering shall be repeated as necessary to keep the turf moist and until the turf has rooted in
the subgrade.
14 Once the laying of the turf is complete, the area shall be rolled to settle and firm the surface.
Plants shall be obtained from an approved source. Plants in transit shall be adequately and
carefully packed and protected against mechanical damage, extremes of temperature and wind.
Transport shall be in fully covered vehicles.
Plants must be first class representatives of their species or varieties and must have normal, well-
developed stem, branch or cane systems. Plants must be free from sun damage, abrasions of bark,
wind injury or any other disfigurement. Trees must have straight trunks, be well branched with
symmetrical tops, and intact leaders.
Pot-grown plants shall be well-developed and have sufficient well-formed roots to hold together
intact after removal from containers but at the same time not to be root- bounded.
The Engineer shall, at random, inspect plant root balls prior to planting. Any root balls that are
damaged, root bound or circulating shall be rejected.
It is the responsibility of the contractor to ensure that the specified plant species and sizes (refer
plant schedule) are held in a local nursery are correctly labelled and are available for inspection
prior to delivery to site and prior to installation.
When indicated on the drawings or bill as "matched" shall mean trees of the same species that are
all within a range of + or - 300mm in height measured to the top of the crown of the tree and within
5mm in overall diameter of the trunk measured at 1000mm from grade level. "Matched" shall mean
trees are similar in height, shape and form. All plants of the same species shall be of a uniform size
(according to Plant Schedule) and shape.
The tender must be based upon plants that are available. If plants are unobtainable or in sizes that
vary from the specified size, alternatives may be submitted with the Tender, stating how they differ
from the Specification. Such substitutions may not be acceptable and submission of further
alternatives may be required. Approval shall be obtained from the Landscape Architect prior to any
substitution.
After the tender period, no substitutions will be considered and specified plants will have to be
procured by whatever means are necessary in order to meet the completion date set.
The Contractor shall ensure that adequate replacements are available for any losses during the
Contract Period.
5.30.1 Execution
The works in this section shall be executed by a firm with extensive experience, and currently
actively engaged in successfully constructing and maintaining similar landscape projects in the
UAE and to a Municipality approved standard.
The site superintendent in charge of the work shall have at least ten (10) years landscape
construction experience on high standard projects.
Page 43 of 113
LANDSCAPE SPECIFICATIONS
Schedules are required prior to works starting showing program of implementation for each type of
landscape work. Planting plans and schedules shall be submitted with documentation of plant types
and sizes, together with dates anticipated for each type of planting.
Plant in sufficient time to ensure all plants are well established at the time of project handover. The
contractor shall submit a planting program for approval by the Engineer before any planting begins.
The programme shall provide a phased planting schedule beginning a minimum of:
- Six (6) months before completion of contract for trees and palms.
- Three (3) months before completion of contract for shrubs.
- Two (2) months before completion of contract for ground covers and sedums.
Plants which are not to be planted on the day of delivery to site are to be stored as follows (or by
other approved methods):
- Store plants in an approved well-ventilated and shaded area, protected from excessive heat (or
early morning cold), wind and sun.
- Plants shall be stored in an upright position; care should be taken to provide enough space
between plants so that light reaches all around to the bottom of the plant in order to avoid
burning when planted out.
- Special attention should be given to plants with balled and burlapped roots (earth balled and
Hessian ‘burlap’ i.e B&B). Root ball shall be protected by a cover of burlap. Cover shall be kept
wet at all times to prevent drying out of rootball.
- Plants not intended to be planted within three days shall not be stored within a building or any
area of low intensity lighting. Plants shall be kept well-watered and protected from wind or sun
damage.
- For all stored plants apply an approved anti-desiccant before moving plants to the final location.
Plant palms, trees, shrubs, bushes and groundcovers only during periods that are normal for such
work as determined by local weather conditions, within the following months:
Do not plant when persistent cold or drying winds are likely to occur or when the soil is waterlogged
or excessively dry. Obtain approval to vary planting schedule if exceptional conditions are
expected. Provide forty eight (48) hours’ notice prior to commencing planting, maintenance or
replacement works.
Planting medium for trees, shrubs, bushes and groundcovers is to be composed of dune sand,
compost and organic fertiliser well mixed together.
Prior to the placement of Dune Sand all planting beds shall be fully lined with Terram Salt Barrier
to the depths specified in this specification, which shall be jointed to ensure an unbroken barrier
coverage to the whole planting bed area. The Salt Barrier shall be jointed in accordance with
manufacturers lap seam and stapling method.
The planting medium shall be free of plants or their roots, sticks, building materials, chemical
pollutants, subsoil, or any other deleterious matter. Planting medium shall not be prepared or
handled in a wet condition. Planting medium shall be examined and approved on site before
placing.
Subsoil under planting beds shall be retained and used as subsoil for landscape works. Subsoil
shall be made free from any builders waste or other material that might impede or otherwise
Page 44 of 113
LANDSCAPE SPECIFICATIONS
negatively effect root development. Subsoil shall be separated from dune sand by the salt barrier
lining to the planting bed area. Any deleterious material removed shall be replaced with approved
dune sand.
Approved landscape soil additives shall be mixed evenly with existing dune sand top soil to provide
the specified soil mix. In some cases this can be done insitu i.e. for grass and ground cover areas.
Care shall be taken to ensure salt barriers to planting beds are not damaged or penetrated during
soil mixing and placement procedures.
Setout and construct planting areas to the specified shape and levels, position plants using pegs
and obtain approval before commencing planting. Adjust positions if instructed. Mowing strips are
to be installed prior to the commencement of planting as identified on the drawings and to the
approval of the Engineer.
Minor refinement to the design with adjustments to lines, levels and grouping of plants during
planting process is required.
Planting shall not commence until setting out positions have been approved. Any planting where
positions were not approved prior to planting may require adjustment.
Plants shall be spaced evenly to ensure when established, the plants will completely fill the areas
indicated.
Excavate pit to a minimum depth of 1.55m, and break up base to a depth of not less than 200mm,
line all sides and base with drainage composite terram 1BZ geotextile material. Lay a 40-70mm
layer of wadi pebbles to pit base and firm.
For shrubs and bushes; excavate whole planting area to a depth of not less than 0.5m below
finished grade and lay Terram Salt Barrier to full extent of planting bed. Excavate individual planting
pits not less than 0.5m diameter (must be greater than diameter of the rootball by a minimum of
twice the root ball width). Break up bottom of pits to a depth not less than 200mm, ensure salt
barrier is not penetrated or damaged during this process.
For groundcovers; excavate whole planting area to a depth of not less than 300mm below finished
grade and lay Terram Salt Barrier to full extent of planting bed. Excavate individual planting pits not
less than 300mm diameter (must be greater than diameter of the rootball by a minimum of twice
the root ball width). Break up bottom of pits to a depth not less than 200mm, ensure salt barrier is
not penetrated or damaged during this process.
All excess excavated material shall be removed from site. Do not mix excavated subsoil with topsoil.
Planting pits shall be tested by filling with water. Conditions permitting the retention of water for
longer than two (2) hours shall be reported prior to proceeding with work.
Page 45 of 113
LANDSCAPE SPECIFICATIONS
Transporting time should be programmed to commence very early each day to avoid excessively
hot weather. Immediately prior to transporting plants are to be inspected then, prepared and packed
with care in accordance with recognised standard practice for the kinds of plants concerned.
During transportation, plants are to be packed adequately to ensure protection from damage of any
kind. Covers are to be placed over plants when transported. For short transit period (2 hours or
less), use a covered truck using tarpaulin or similar material in order to protect the leaves from
damage.
For more than two (2) hours transit period, the foliage needs to be sprayed with an anti- desiccant.
At all times roots should be protected from wind and direct sun, using wet straw or other suitable
material. Root systems are not to dry out at any time. Earth balls are to be firm and intact and
contained in Hessian (Burlap).
Plants will be inspected upon arrival at site. Any plants damaged during transport will be rejected.
Plants should be moved by handling the container only in order to reduce breakage of
branches/leaves.
Balled and Burlapped (B & B) plants should be handled with caution to maintain the firmness of the
balls. Protect against damage to stems and branches.
All plants should be unloaded and checked immediately upon arrival to the site and should be
watered, and kept in a moist condition at all times until they are planted on the site.
Check ties of each tree or shrub to prevent fracture of branches.
- Planting height, and/or presentation shall be sufficient to achieve the size and condition detailed
on the drawings at or before project handover.
- Planting shall be ordered, regular, neat and tidy and in accordance with good horticultural
practice and to the satisfaction of the Engineer.
- Prior to planting, check soil level in planting pits and make even allowing for root ball to be
positioned according to correct level.
- Cut back broken and damaged roots to sound growth, treat cut ends with an approved tree
wound dressing.
- For trees, shrubs or bushes: thoroughly spray with anti-desiccant soon after planting (do not
apply in rainy weather). Ensure full coverage of underside of foliage.
- Plant palms, trees, shrubs or bushes upright in centre of pit and at original soil depth unless
otherwise instructed.
- For all plants:
· Plants shall be planted so that after settlement they will be at the nursery (original) growing
medium depth (the soil mark on the stem is an indication of this). Therefore the planted
finished level is to be 30 mm above surrounding level to allow for settlement.
- Plants shall set in the centre of the pits.
Page 46 of 113
LANDSCAPE SPECIFICATIONS
- Approved topsoil shall be placed in layers around the root ball, by hand. Each layer shall be
carefully tamped so as to avoid injuring the roots or the root balls, or disturbing the position of
the plant.
- For balled trees: when growing medium is up to 2/3 of the root ball height, ties shall be cut and
the top portion of burlap on B & B plants shall be folded back carefully, not disturbing the root
ball integrity. Soil should be watered in plant pits at this stage, and allowed to settle around the
roots. After the water has been absorbed, the backfilling shall be completed and tamped lightly.
Any settling shall be brought up with soil mixture medium.
- Position root ball and backfill with approved top soil mix, placed around root ball in layers not
greater than 100mm using water to ensure proper compaction and elimination of voids.
- Immediately after planting trees, shrubs or bushes, carefully cut back damaged, dead or
diseased branches, remove weak, thin or malformed growth and treat with an approved tree
wound dressing.
Watering
Plants should be watered immediately after planting.
A circular watering basin slightly larger than the planting hole shall be formed. Immediately after
planting, all plants shall be thoroughly watered in.
Palms, trees, shrubs, ground covers and annuals should be watered thoroughly immediately after
planting. First watering must be with sufficient amount to saturate the growing medium.
Fertilising
Inorganic fertilisers and the like are to be:
Non-toxic to humans, birds and animals under normal use. Approved and delivered to the site in
original unopened containers.
All inorganic fertilisers shall be in slow release sulphur coated granular or tablets, and shall be dry,
free-flowing and free of lumps.
The fertilisers shall have a guaranteed N.P.K (15 – 15 – 15) plus trace elements – Iron and Sulphur
or available equivalent analysis for palms, trees, shrubs and ground covers.
Fertilizer shall be packed in standard waterproof containers, clearly marked with the name of the
manufacturer, weight and analysis.
All fertilisers shall be stored in a weatherproof storage place and in such a manner that it will stay
dry and its effectiveness is not impaired.
For beds, spread approved organic fertilizer to planted area and cultivate to 200mm depth.
Establish necessary supporting system (e.g. stakes for trees and shrubs), use proper ties,
thickness and height to match plant to be supported (subject to Engineers approval).
Immediately following planting, trees and shrubs shall be braced upright in position, preventing
excessive motion, by guy wires or by stakes with ties or by both as per detail drawings. Ensure that
stakes do not penetrate the Salt or Drainage Barriers.
Page 47 of 113
LANDSCAPE SPECIFICATIONS
Removal of tree stakes should occur once the trees are stable (tree stakes and tree guys should
remain for a maximum of twelve (12) months).
In some cases, stakes might be left in place to protect the trees or the shrubs, but ties should be
removed.
Stakes, guy wires and ties shall be checked at least every four (4) months to ensure that they are
not causing a depression in the bark of the tree or the shrub and shall be loosened, repaired or
replaced as necessary.
Stake trees using a minimum of two (2) tree stakes to protect from wind action, while allowing
flexibility. Maintain palm tree fronds in a wrapped condition using hessian. Ensure plants are
upright.
After planting, irrigate, and spray with pesticides or fungicides as required, to achieve optimal
growth free from pests and as approved by the Engineer.
The Engineer reserves the right to inspect plants either at place of growth or on site before planting
to verify compliance with requirements for name, variety, size and quality, condition of balls and
root systems, presence of insects and/or disease infections, injuries, and latent defects.
Any plants that do not show healthy growth, shall be replaced. Plant in sufficient time to achieve
performance requirements at handover.
Three months after planting or during the months of March to April or October to December spread
sulphur coated slow release fertiliser at rates according to manufacturer’s directions for plant type.
Water suitable for irrigation will normally be supplied to the project free of charge. The Contractor
shall ensure adequate supplies of sweet water are available, and make arrangements to
compensate for any shortfalls.
If water supply is or is likely to be restricted by emergency legislation, inform the Engineer without
delay and ascertain availability and additional cost of second class water from an approved source.
If planting has not been carried out, do not plant until instructed.
5.37.7 Drainage
After planting, the area surrounding the plant shall be restored to finish grade and excess soil,
empty containers and rubbish disposed of properly.
Check all plants one week after planting for signs of windshake and loosening due to soil
subsidence, firm and make good as necessary. Prune any weak or dead branches according to
good horticultural practice. Check stakes and ties to ensure they are properly positioned and
functioning correctly.
Page 48 of 113
LANDSCAPE SPECIFICATIONS
Plants that are found to be missing, defective or in poor condition, prior to Substantial Completion
of the works, shall be immediately replaced by the Contractor.
It is the Contractor’s responsibility to ensure that all plants, lawn and planted areas are protected
from the ingress of sand and exposure to windblown sand.
Wind deflecting fences consisting of black shade cloth doubled over a three wire fence 1.2m in
height are to be erected as and when required and to the approval of the Engineer.
5.38 Completion
The Engineer shall certify the date when, in his opinion, Substantial Completion of the works has
been achieved. Substantial Completion will not be awarded until at least 95% of all plant material
is in living, healthy condition and is planted as per specification quantities.
Plants that are found to be missing, defective or in poor condition, prior to Substantial Completion
of the works, shall be immediately replaced by the Contractor.
The first thirteen (13) weeks (or the period specified in the Bill of Quantities) of the Defects Liability
Period is considered as the ‘Consolidation Period’.
Generally Consolidation includes all maintenance of the landscape works in this Contract for
a period of thirteen (13) weeks from the Date of Substantial Completion.
Defects Liability includes all repair, amendment, rectification, reconstruction and making good of
defects, imperfections, shrinkages or other faults as may be required by the Engineer during the
twelve (12) months Defects Liability Period or within fourteen (14) days after its expiration as a
result of an inspection made prior to its expiration.
The thirteen (13) week (or the period specified in the Bill of Quantities) Consolidation Period will
commence after an inspection of the Works by the Engineer that finds all the works satisfactory to
grant Substantial Completion for the entire project or agreed portions thereof.
During the Consolidation Period, any plants or grass areas that are dead, or which do not show
healthy growth and satisfactory foliage condition are to be replaced by the Contractor at his
expense.
Such items shall be replaced immediately upon discovery and shall be replaced again, if necessary,
at the Contractor's expense to ensure that (theft and vandal damage excepted) the site remains in
peak condition throughout the Consolidation Period.
At the end of Maintenance Period and Defects Liability Period, the Contractor shall conduct a joint
inspection of the works with the Engineer, Resident Landscape Architect, etc.
Submit program for replacement works to the Engineer as soon as defective works are identified.
Page 49 of 113
LANDSCAPE SPECIFICATIONS
5.41.1 Generally
The Contractor shall maintain the whole of the landscape and irrigation works as indicated on the
Drawings and as specified in this Contract from the completion of the Consolidation Period until the
completion of the Defects Liability Period.
Undertake all works and provide all tools, equipment, plant and machinery necessary to maintain
the landscape works as specified and in accordance with good horticultural practice.
The cost of all such equipment and machinery together with the cost of fertilizers, pesticides,
herbicides, mulch and any other equipment and/or materials required on a regular and scheduled
basis to fulfill the requirements of the Specification shall be included in the tender price.
Where loss/damage has not resulted from negligence on the part of the Contractor, the cost of
supply and planting of replacement plants; repair of theft, vandal and other damage caused by
agencies beyond the control of the Contractor; and, the cost of supply and installation of irrigation
(and other electrical equipment) replacement parts and/or repairs not covered by warranties are to
be submitted to the Engineer and approval obtained prior to carrying out the works. Such works
will be valued on the basis of the Bill of Quantities/Schedule of Rates and/or on a "cost plus"
percentage basis as submitted as part of the Tender. All other works shall be included in the Tender
price.
Notwithstanding anything to the contrary in the Contract, the Engineer may instruct the Contractor
to perform urgent maintenance works. Should the Contractor fail to carry out the work within seven
(7) days of such notice, the Engineer reserves the right without further notice to employ others to
carry out such work at the expense of the Contractor.
It is the objective of the Employer to maintain the landscape of the development in peak condition
at all times.
The Contractor shall allow for completing the maintenance operations, specified in accordance with
the approved Maintenance Manual and Programme as submitted by the Contractor together with
all other works he considers necessary to achieve this objective throughout the Contract Period.
The ‘Maintenance Period’ shall be the thirty nine (39) weeks period (or the period specified in the
Bill of Quantities) following the end of the thirteen (13) week Consolidation Period until the end of
the twelve (12) months Defects Liability Period. During the Maintenance Period, the Contractor
shall have a full time presence on site and shall be responsible for:
The satisfactory maintenance of all soft landscape, irrigation and nominated hard landscape works
and parts thereof, including, but limited to;
Page 50 of 113
LANDSCAPE SPECIFICATIONS
- Maintaining hard paved and walled areas free of graffiti, dirt, litter, weeds and any other
undesirable material;
- Adjustment, cleaning and minor repairs to paving, site furniture, structures, fences,
sculpture, etc;
- Mechanical sweeping of all nominated roads;
- Reporting on and making good theft and vandal damage, as instructed;
- Inspection and reporting on potential safety hazards on play equipment.
- Maintenance and monitoring of all park lighting
- Maintenance and monitoring of all water feature
- The Contractor will train the Employers’ personnel during this period as specified in order to
enable a smooth handover of the works upon completion.
- Presenting the site at all times during the Contract in a clean and tidy condition to the satisfaction
of the Engineer; and
- All other work necessary to maintain a healthy, clean, neat and tidy landscape in accordance
with the objectives stated above.
The Contractor shall submit to the Engineer a weekly Maintenance Report detailing operations and
areas covered and identifying any problems or issues that require further action. Payment may be
withheld if maintenance reports are not submitted every seven days. The Contractor shall submit
a sample format for approval during the first week following Contract award.
Generally: All landscaped areas shall be kept clear of litter at all times and collection frequency
shall be adjusted as necessary to achieve this objective.
All rubbish to be carted to an approved waste / recycling collection area. The Contractor shall meet
all fees for haulage and dumping.
Leaf litter
Generally: Leaf litter, twigs and grass cuttings shall be raked up from lawn, grass and paved areas
on the occasion of each mowing and collected separately for re- use/composting where possible
or removed from site.
Windblown Sand
Generally: Windblown sand shall be removed from lawn and paved areas as per the general
maintenance operations and/or immediately following a storm event. All areas of open sand liable
to become windblown are to be screened with a 1.2m high wind-deflecting fence to be installed at
the Contractor expense to the approval of the Engineer.
Street sweeping
Generally: Sweep all nominated roads and pathways within the site by mechanical means once per
month to remove all sand, litter and other debris.
Paving
Generally: Sweep to keep free from rubbish, dirt, grass clippings, leaf litter, etc. Mechanically clean
paved areas as necessary to maintain the highest standards of presentation.
Page 51 of 113
LANDSCAPE SPECIFICATIONS
Weed Control
Maintain free from weeds and grasses by hand weeding or by application of approved herbicide.
5.45.2 Replacement
Report any obstructions, areas of ponding, serious staining or defects in the paving and provide
quotation for making good. On receipt of approval, replace paving as instructed.
5.45.3 Safety
Erect safety barricades to enclose areas of defective paving that may constitute a hazard until
repairs have been completed.
Generally: Ensure all site furniture, structures and fences are well presented and maintained in
good working order at all times.
Bollards and other Vertical Elements: Re-set levels of elements that deviate from alignments and
re-paint/re-stain any damaged elements. Replace components or whole items where repair is not
possible. Provide quotations for replacement and obtain approval before proceeding.
All damage or theft occasioned to the landscape (hard and soft) shall be reported immediately upon
discovery together with a quotation for repair/replacements as required. Repair works shall
commence immediately upon receipt of instruction to proceed.
All graffiti shall be reported to the Engineer immediately upon discovery. Submit quotations for
removal of any other graffiti and obtain approval to proceed.
5.46.1 Trees
Generally: Inspect all trees to ensure that irrigation system is operating effectively and trees are
not exhibiting signs of stress. Remedy any problems evident by repairs to irrigation system, pruning
or other appropriate action as required.
Inspect stakes and ties (including guard ties) and adjust and replace as necessary to prevent trees
being damaged by wind or chaffing. Loosen ties regularly to prevent strangulation and damage to
bark. Replacement stakes and ties shall match those installed at planting.
5.46.3 Pruning
Prune to remove dead, diseased, damaged and dying limbs; to remove obstructions to pedestrian
circulation; to shape as appropriate to species; and as directed. Refer also to Section 13.20 Item
4 Pruning and Dead Heading.
Page 52 of 113
LANDSCAPE SPECIFICATIONS
5.46.4 Replacement
Remove any dead or dying trees (salvaging stakes for re-use) and report to Engineer.
Maintain a weed and grass free area of 600mm diameter around each tree in grass.
The Contractor shall replace any trees that are permanently damaged by line trimming operations
at his own expense.
Generally: Maintain garden beds free from litter, grass, weeds and any pest/disease infestations.
Remove any dead, diseased or dying plants immediately upon discovery and report to Engineer.
Rake mulch to maintain even coverage and top-up as necessary with mulch as specified, to
maintain minimum depth of 50mm.
Obtain the Engineer's approval prior to proceeding with replacement planting. Replace any
individual plants that have failed to thrive with species of the same type and cultivar. Any
widespread failures of one species are to be reported so that an appropriate substitute can be
identified prior to replacement. Fertiliser – refer also to Section 13.20 Item 3.
Soil tests
To maintain a suitable pH level of 6.5-7 for growth and to optimise the fertiliser application regime,
soil test shall be conducted once a year in February. Obtain two samples from locations as directed
by the Engineer and obtain full analysis with recommendations. Records shall be kept of soil test
results. Specialist advice shall be sought for application rates of soil ameliorants and fertilisers, to
adjust the pH and nutrient levels in accordance with recommendations.
Garden Beds
Fertilise every six (6) months using slow release fertiliser (Osmocote, Emirates Bio-Fertiliser or
equivalent) applied in accordance with Manufacturer's recommendations.
Generally: The main objective is to maintain as natural an appearance as possible, including the
removal of excess dead and degenerating material and regular tip pruning to encourage new
growth and maintain form.
Page 53 of 113
LANDSCAPE SPECIFICATIONS
All work is to follow correct horticultural techniques and, is to be implemented at such a time and
in such a way to avoid the loss of any foliage or floral colour.
In cases where odd shaped, woody plants have developed, heavy pruning may be necessary,
unless the shape is desirable according to the Engineer. The Contractor shall cut back the dead
branches towards the main stem, removing small portions of the branch at a time until a satisfactory
result has been achieved.
Groundcovers shall be allowed to spill onto the edges of paths, kerbs and recalls. Where plant
growth inhibits the use of paths, roads, etc or extends over mowing edges, trimming shall be carried
out to produce informal wavy edges, not hard straight lines.
Trees
Selectively prune low level lateral growth on street trees to prevent sight lines from being obscured
and to allow unrestricted pedestrian movement. Pruning shall be gradual, always leaving ample
branch and foliage coverage typical of the growing habit of the tree species.
5.47.6 Arisings
Collect all debris arising from pruning and dead heading operations and remove from site.
Generally: Identify the problem and advise the Engineer of the proposed treatment. Employ
approved treatment method until the problem has been eliminated.
Major Infestations
Infestations in unacceptably high levels shall be treated by an approved pesticide of low toxicity.
Pesticides shall be used in strict accordance with the manufacturer's instructions at minimum rates.
Biodegradable pesticides shall be used wherever possible. Mechanical applicators shall be
precisely calibrated and care taken when applying to minimise the effect on plant and animal life.
Maintain all planted areas in a weed-free condition at all times without injuring the plants. Use only
qualified and experience staff when employing herbicides and shall ensure that herbicide
applications are carried out in accordance with current safety regulations and manufacturer’s
instructions.
5.48.2 Approval
All chemicals proposed for use must be to the approval of the Engineer.
5.48.3 Application
Chemical sprays shall be used only in still conditions and during weekday early mornings or when
public use of the site is at a minimum. Chemicals shall only be applied strictly in accordance with
the Manufacturer's recommendations.
Page 54 of 113
LANDSCAPE SPECIFICATIONS
Take all precautions necessary to protect other users of the site (be they other Contractors, the
public, residents or the like) and private property from any harmful effects of herbicide and pesticide
applications.
5.48.5 Notification
Give the Engineer, Employer and adjacent residents at least 24 hours’ notice of the intention to
apply chemicals, clearly stating the reason for their use and expected date and time of application.
Obtain their written approval prior to proceeding with the chemical applications.
Costs for the supply and installation of replacements for vandalised or stolen plants shall be
prepared in accordance with the Schedule of Rates and shall be submitted to the Engineer and
approval obtained prior to carrying out the works.
Any plants that degenerate due to Contractor's negligence will be reinstated at the Contractor's
expense.
The Contract shall compile a comprehensive Operations and Maintenance Manual, which will
include the following:
This manual shall be submitted for approval at least two (2) weeks prior to Substantial Completion.
The Contractor shall provide all necessary attendance to facilitate the procurement, delivery,
storage, installation and maintenance as is required according to the General Specification and
under the terms of the following Supply Schedule.
General
This section details the supply categories for the supply of plant material for this contract. In the
event that the Client supplies plants this section shall apply. There are three types of plant supply
and installation categories detailed as follows.
Page 55 of 113
LANDSCAPE SPECIFICATIONS
The client shall advise which type of plant supply and installation category shall apply.
Unavailability of stock
Any delays due to the unavailability of species or specific plant sizes are to be reported immediately
to the Engineer. Where required substitute species or additional quantities may be sourced by the
Client through commercial nurseries. The Engineer shall instruct the Contractor where this is the
case.
Consolidation period
- The consolidation period determines the liability for replacement of plant materials.
- The consolidation period is twelve (12) weeks from the time the plants are supplied.
- Any dead, dying, diseased or unhealthy plant material supplied by the client that under the
maintenance of the Contractor, is deemed to be unsuitable by the Engineer or the Contractor,
shall be replaced by the Client at his expense.
Category A
- This category covers the plant supply and installation by the Contractor.
- The Contractor shall be responsible for the procurement, delivery, storage, installation and
maintenance as is required according to the Contract documentation and relevant
Specifications.
- The Contractor is responsible for the maintenance of the plant material for the duration of the
contract.
Category B
- This category covers the plant supply only by the Client with installation by either party.
Page 56 of 113
LANDSCAPE SPECIFICATIONS
- The Client shall be responsible for the replacement during the consolidation period.
- The Contractor must provide irrigation to all plant material supplied and installed by the Client
as if it were the Contractors.
- Should the plant species die during the Client’s consolidation period as a result of lack of
irrigation; the Contractor shall replace the item for the Client at the Contractors expense.
- Should the plant species die during the Client’s consolidation period as a result of accident /
vandalism or any other uncontrolled acts, the Client shall replace the item at the Client’s
expense.
5.52 Maintenance
All maintenance regardless of the Supply Schedule Category is to be carried out by the Contractor
for the period specified under the General Specification and Bill of Quantities.
The Contractor is responsible for the maintenance of the plant material for the duration of the
contract.
Date for submission of monthly activity report indicating record of maintenance carried out during
contract period.
Page 57 of 113
LANDSCAPE SPECIFICATIONS
6.1 Description
The work included in this Section covers the various types of paving finishes and their installation.
The section includes but is not limited to concrete kerbs, concrete unit pavers & slabs, natural stone
paving, joint materials, gravel courses.
Where materials are referred to in this and other sections of this document (i.e. concrete), no one
section shall take priority over another: All relevant clauses shall apply.
Materials that have not been individually specified in this document shall be of international
standard: The minimum acceptable standard shall be the relevant British Standard (if applicable),
Australian Standard, American Standard or ISO.
The following reference standards included in this section shall apply as specified in section 01090.
- AASHTO M17-77, Standard Specification for Mineral Filler for Bituminous Paving Mixtures.
- AASHTO M20-70, Standard Specification for Penetration Graded Asphalt Cement.
- AASHTO M140-70, Standard Specification for Emulsified Asphalt.
- AASHTO M208-72, Standard Specification for Cationic Emulsified Asphalt.
- AASHTO M226-78, Standard Specification for Viscosity Graded Asphalt Cement.
Page 58 of 113
LANDSCAPE SPECIFICATIONS
- BS 435:1975(1993) – Specification for dressed natural stone kerbs, channels, quadrants and
setts
- BS 5931:1980 – Code of practice for machine laid, in situ edge details for paved areas
· Part 1:1986– Specification for pavers
· Part 2:1986– Code of practice for design of lightly trafficked pavements
· Part 3:1986– Method of construction for pavements
- BS6717– Precast concrete paving blocks
· Part 1:1993 – Specification for paving blocks
· Part 3:1989 – Code of practice for laying
- BS7263 – Precast concrete flags, kerbs, channels, edgings and quadrants
· Part 1:1990 – Specification
· Part 2:1990 – Code of practice for laying
- BS7533:1992 – Guide for structural design of pavements constructed with clay or concrete
block pavers
- BS 340 : 1979, Specification for precast concrete kerbs, channels, edgings and quadrants.
- BS 434 : Bitumen road emulsions (anionic and cationic)
· Part 1 : 1984 Specification for bitumen road emulsions.
· Part 2 : 1984 Code of practice for use of bitumen road emulsions.
- BS 598 : Sampling and examination of bituminous mixtures for roads and other paved areas.
· Part 1 : 1974 Sampling.
· Part 2 : 1974 Methods for analytical testing.
· Part 3 : 1985 Methods for design and physical testing.
- BS 1446 : 1973 Specification for mastic asphalt (natural rock asphalt fine aggregate) for roads
and footways.
- BS 1447 : 1973 Specification for mastic asphalt (limestone fine aggregate) for roads and
footings.
· Latest editions of all relevant British Standards shall be used with current amendments and
additions.
· Any differences between their requirements and this specification shall be submitted to the
Engineer for his ruling.
- The works are to be set out from primary datum levels and setting out points indicated on the
drawings or from information provided by the Engineer
- The Contractor shall submit his proposals for setting out and controlling the alignment of the
works, to the Engineer and obtain his approval prior to the start of construction. The Contractor
shall supply to the Engineer details of the value and location of all temporary benchmarks and
reference points he establishes.
- Should the Contractor dispute the original ground levels shown on the drawings he shall agree
these with the Engineer before disturbing the original ground
Carefully examine all of the Contract Documents for requirements which affect the work of this
section.
Paving works shall be carried out only by skilled workers, with suitable machinery, and supervised
by foremen experienced in the type of paving specified.
Paving shall be performed by a firm who has equipment adequate for the project, and skilled
tradesmen so that placing is performed expeditiously; and is known to have been responsible for
satisfactory installations similar to that specified during a period of at least five years.
Page 59 of 113
LANDSCAPE SPECIFICATIONS
6.8 Source
Provide kerb/paving units which are the products of one supplier and one quarry as specified. Stone
material shall comply with the standards of the National Granite Quarries Association (NGQA).
6.9 Mock-ups
Before beginning primary work of this section, provide mock ups of paving and edging types (min.
area 3.0m x 3.0m) at locations acceptable to The Engineer and obtain Engineer's acceptance of
visual qualities. Protect and maintain acceptable mock ups throughout the work of this section to
serve as criteria for acceptance of this work. Acceptable mock ups may be incorporated into
finished work.
6.10 Submittals
- Product Data: Submit manufacturer's product data, installation instructions, use limitations and
recommendations. Provide certifications stating that materials comply with requirements.
- Verification Samples: Submit representative samples of each element that is to be used in the
finished work, showing the full range of colour and finish variations expected. Provide at least
four unmounted units.
- Provide large scale shop drawings for fabrication and installation of all kerb, paving, wall and
structure work to include plans and details showing exact size, shape, profile, curvature, finish
and installation method.
Deliver, store and handle kerb/paving units in strict compliance with manufacturer's instructions
and recommendations. Store above ground and protect from damage and soiling.
Weather: Perform work only when existing and forecasted weather conditions are within the limits
established by International Masonry All Weather Council Guide Specification and the mortar
admixture manufacturer.
6.13 Substrates
Proceed with work only when substrate construction is complete and accepted.
Provide wrapped, packed and labeled extra material to construct 10m2 of each type, size and
configuration of paving used on the Project. Deliver to the clients store, location to be advised by
the Engineer.
6.15 Samples
- Samples of all materials to be used shall be submitted for approval before construction
commences. Samples shall be submitted in a timely manner allowing for manufacture and / or
procurement times. Rejection of a sample submitted by the contractor shall not be an excuse
for delay of any sort, nor justification for extension of any kind.
- The approved samples shall be clearly labelled and retained on site for the duration of the
project as the standard for all material or work of that type.
- In addition to the individual samples of all paving materials, a sample area of 3.0m x 3.0m shall
be prepared for approval by the Engineer for each paving layout as described in Clause 14.1.8.
Page 60 of 113
LANDSCAPE SPECIFICATIONS
This specification may contain information regarding materials that may be supplied by the client.
However, it remains here for the purpose of information only.
6.17.1 Scope
The following section deals with individual materials under the following headings:
- Description of materials
- Quality required
6.18 General
Where materials used in this section have been specified elsewhere in this document, the relevant
clauses shall apply to this section. Materials that have not been individually specified shall be of
first class quality and the minimum standard acceptable shall be the relevant British Standard
where applicable.
This section shall conform to requirements for granular fill specified in: General Specification (Civil
works - Section 3)
This section shall include performance of concrete work as specified in: General Specification (Civil
works - Section 4)
Shape, size, colour and finish of units shall be as described in the material schedule, refer to
Particular Specification section13, Part 2.
Contractor shall be required to provide shop drawings indicating colour and pattern for Engineers
approval.
When using cut units to fit pattern or area the Contractor shall ensure that not less than one third
of full size units shall be used. Paving which uses units below this size or those which in the opinion
of the Engineer do not achieve the requirements of this specification shall be rejected by the
Engineer.
Colours shall be as specified on the drawings or as specified by the Engineer. Discoloured or faded
blocks shall not be accepted.
Page 61 of 113
LANDSCAPE SPECIFICATIONS
Samples on site are to be prepared in advance of work commencing. Sample panels are required
to ensure that the colours, textures and finishes are to the satisfaction of the Engineer.
No work will be accepted that fails to meet the standards of the approved samples.
As much of the above will be propriety products approved by the consultant, they can only be
changed with the consultant’s approval of a proprietary product that is supported with its own
technical data sheets and has a proven record of being used in similar circumstances.
All pavers must be manufactured according to British Standards and complying with BS.6617
19116 and BS6717: Part 3 19119. Required BS values are as follows:
Pavers shall be delivered to site packaged, complete with original manufacturer seals and
warranties.
Under no circumstances shall pavers that fail to meet these requirements be incorporated in the
Works.
Units should be made using either ordinary Portland cement to BS12 or white cement binder, using
drinking quality water. Aggregates shall be approved natural aggregate complying with BS882
Granite or Marble chips. Pigments should be used in powder form and should conform to BS1014.
Units should be treated with a solvent based silane siloxane solution, which penetrates the pores
of concrete and reacts with moisture to form a hydrophobic polysiloxane lining to capillaries leaving
a permanent, hard wearing and dust free surface.
Units should be textured where required on the drawings, and processed in a fully automated Shot
blasting machine to expose the natural colour of the aggregate.
The tolerances should be a maximum dimension deviation of; Thickness- 3mm, Length and Width
2mm, Difference between diagonals -2mm, Flatness winding and bowing 1mm.
Compressive strength of pavers should be tested in accordance with BS6717 and shall not be less
than 30N/mm2 at age of seven (7) days.
Transverse strength, when sampled and tested as described in annex B of BS 7263: Part 1: 1994
shall not be less than 14kn. Pavers should conform to BS 7263, wet press process, as
manufactured by CONSENT LLC or Transgulf Cement Products LLC or similar approved to the
following specification.
Page 62 of 113
LANDSCAPE SPECIFICATIONS
- Sides – Smooth
- Edges – Sharp
- Surface Treatment – Anti stain
- Compressive strength >30 N/mm2
- Water Absorption 1-4%
All precast units delivered to site shall have a Certificate of Compliance issued by the manufacturer
in accordance with item no. 12 of BS 6073 where the independent laboratory mentioned therein
shall be the local Municipality Construction Quality Control and Research Section or the relevant
local Municipality equivalent.
Precast units shall be delivered to site packaged, complete with original manufacturer, seals and
warranties.
Under no circumstances shall slabs that fail to meet these requirements be incorporated in the
Works.
All pre-cast Kerbs are to meet the specification requirements of the local Municipality Roads
Department.
Page 63 of 113
LANDSCAPE SPECIFICATIONS
Refer to Engineer’s specification for details of the pre-cast concrete kerbs to be used within this
contract.
6.21 Natural stone (including travertine, granite, slate, quartzites and sandstone)
Stone slabs, cladding, pavers or copings are to match the approved sample obtained from the
approved quarry / source.
The contractor shall confirm in writing that the quarry can supply the quantity required for the project
to the dimensions and quality stated in the project documents and this confirmation shall be
provided at the time of submitting the sample for approval.
The Contractor shall ensure that samples provided of natural stone are from supplies, sufficient
and continuous to meet the requirements of the Project. The Engineer must be notified in writing
if the materials are not readily available in sufficient quantities to meet the specification prior to
placing orders or arranging samples.
The Contractor shall expedite the samples of natural stone for the approval of the Engineer
following his appointment, to take account of the long lead-time and delivery schedules associated
with procuring natural stone items.
Stone slabs, cladding, pavers or copings are to be free from any defects that could adversely affect
the integrity of the material. They shall be free from any mark or defect on the face visible in the
completed works that could, at the landscape architects discretion, mark the integrity or appearance
of the finished work
Samples submitted for the Engineer’s approval shall not be smaller than 3.0m x 3.0m and in the
case of slabs for use in work where the patterning, colour, or matching of pieces is of particular
importance larger samples shall be provided upon the Engineer’s instruction.
Size, colour and finish of all granites and natural stones shall be as described in the material
schedule (Refer to Particular Specification 13, Part 2.)
- Portland Cement: Provide ASTM C-150 Portland Cement, Type I or II, of natural colour or white
as needed to produce colour selected
- Hydrated Lime: ASTM C 207, Type S.
- (Aggregates: ASTM C 144 and as indicated below:
· For joints narrower than 6mm use aggregate graded with 100 % passing the No. 8 sieve
and 95 % the 16 sieve.
· For pointing mortar, use aggregate graded with 100 % passing the No. 16 sieve.
- Coloured Mortar / Grout Pigments: Natural and synthetic oxides and chromium oxides,
compounded for use in mortar mixes. Use only pigments with record of range of manufacturer's
standard colours and shall to Consultants approval. For Hardscape grouting and mortar refer to
section 13, part 9
- Water: Clean, non-alkaline, potable. Do not use water in latex modified grout or mortar mixes.
Granite, Slate, Travertine, Quartzite & Sandstone should be supplied by an approved supplier.
Page 64 of 113
LANDSCAPE SPECIFICATIONS
Natural Stone Gravels are to match the approved sample obtained from the approved quarry /
source.
The Contractor shall confirm in writing that the quarry can supply the quantity required for the
project to the dimensions and quality stated in the project documents and this confirmation shall be
provided at the time of submitting the sample for approval.
The shape, size, colour and finish of all natural stone gravels shall be as described in the material
schedule. Refer to Particular Specification 13, Part 2.
Colour and grade samples shall be submitted to the Engineer for approval.
Soil separator/Geotextile fabric shall be non-woven 75% polypropylene / 25% nylon, weight 10g/m²,
0.3mm thick, with good permeability to water. It shall be resistant to all naturally occurring soil
acidities and resistant to tearing and stress, manufactured by an approved supplier.
Drainage cell/ composite should be manufactured by durable and resistant to chemicals high
impact polystyrene material with compressive strength of >300kN/m2. Individual sections shall be
close butted.
Horizontal and vertical drainage cell should be manufactured from perforated high impact
polystyrene sheet bonded with a non-woven filter fabric on both sides.
Drainage cell drains excess water only. Water flow rate of 80 litres/min. or more is recommended.
6.25.1 General
- The Contractor shall employ only appropriately skilled operatives in the laying of the specified
finishes.
- All work shall be carried out in accordance with manufacturer's recommendations.
- Damaged or disfigured units shall not be used.
- Finished work shall have an even overall appearance with even joint widths and free from any
discolouration.
- In-situ concrete infill in any area of work shall not be accepted unless approved by the Engineer.
Concrete blocks and pavement tiles shall be bedded as detailed and specified or shall match the
existing bed to the approval of the Engineer.
Page 65 of 113
LANDSCAPE SPECIFICATIONS
Service Covers
The levels of any existing and proposed service covers in pedestrian or vehicular hard landscape
areas shall be adjusted as necessary to marry in with the proposed paving levels.
In all areas of pedestrian paving, recessed man hole covers shall be used as specified and shall
be appropriate for infilling with the specified surface finish. Covers shall be infilled to match the
adjacent paving pattern and joint lines. In pedestrian areas where occasional vehicle over-run is
expected all covers hall be heavy duty type to accommodate vehicle point loading.
In areas of vehicular paving the Engineer will advise the Contractor which service covers shall be
heavy duty recessed type.
Paving shall be laid right up to the edge of the service covers. Any existing concrete surrounding
the covers shall be broken out.
The Contractor is responsible for ensuring all works are adequately protected and, if the Contractor
is working in the vicinity of works completed by others, which these too are adequately, protected.
Particular attention shall be made to protecting areas of natural stone prior to the application of
stone sealant to ensure that stone is free of all dirt, debris and surface markings and that these are
not sealed within the finished surface of the stone, post sealant application.
All pavings bedded on mortar shall be kept free from pedestrian traffic for a minimum of four (4)
days and vehicular traffic for 10 days after laying.
All pavings with dry, semi-dry or plastic mortar jointing shall be protected from rain, dust storms,
chemical attack and the harmful effects of heat, wind, flowing water, vibrations and shocks by
appropriate means for at least three (3) days immediately after filling the joints.
In the event of a dispute over standards of materials, reparation and workmanship, it is the
responsibility of the contractor to be aware of the above British Standards copies and ensure that
the contractor is aware of his contracted responsibilities as described in said standards. The above
British Standards form part of the contract documentation and, as such, are deemed to be included
in the rates for the works.
6.26.1 General
Finished unit paving to have an even overall appearance with no visible joints showing, free of
mortar and any other unnatural stains.
Movement joints in the paving and bed should be sited every 10m or as approved on working
drawings to suit patterns or fixed objects.
Perimeter and intermediate movement joints shall be incorporated in the paving in accordance with
the recommendations of BS 6213 Part 5; 1990 Section 6.
Lines and levels of finished surface shall be smooth and even to prevent ponding.
Lay paving units upwards from the bottom of slopes where creep may occur.
Unit paving bedded on mortar must be kept free from pedestrian traffic for 4 days and vehicular
traffic for 10 days after laying.
Page 66 of 113
LANDSCAPE SPECIFICATIONS
Restrict access to paved areas as necessary to prevent damage from site traffic, especially oil and
diesel spillage.
Cutting of pavers shall be carried out with a mounted cutting saw with a diamond tipped blade. No
mechanical splitters are to be used.
The setting out of paving and related features is to be submitted in detailed Contractors shop
drawings which shall take into account actual site conditions.
Permissible deviation from specified levels to be +-6mm over 3m. Paving to be set 6mm above
drainage outlets and 3mm above kerbs to allow for settlement.
The base for concrete unit paving shall be a concrete bed and screed as covered in the general
specification.
Before starting work ensure that the base is sound, clean, suitably close textured, free from
movement under compaction and free from compaction ridges, cracks and loose material, and the
levels and falls of the base are as detailed, within the tolerance specified.
Mortar bedding shall consist of freshly mixed moist mortar 1:3 cement: sand mortar with plasticiser
as required, using sand complying with BS 882 grading M or F.
The mortar shall be spread to achieve a nominal compacted thickness as shown in drawings, to
reach a total finishes profile (paver thickness and mortar) of 90mm.
Mortar which has been mixed for more than 1 hour shall be discarded.
Units shall be laid on a full mortar bed and bedded down to line and level with a pavers maul.
Where units are laid with close joint (i.e. 2 to 4mm) jointing sand shall be brushed into the joints.
Where units are laid with a wide joint (i.e. 6 to 10mm) the whole of the joints shall be filled with
mortar.
Mortar mix shall be semi dry cement: sand to BS 882 grading limits M, proportions as specified and
coloured as required by the Engineer.
The paving shall be dry prior to joining. The joints shall be carefully and thoroughly filled with mortar
using a proper pointing tool and slotted masking shield.
The joint shall be flush, recessed or raised as detailed or as required by the Engineer.
Any mortar stains or droppings on the face of the paving shall be removed.
Page 67 of 113
LANDSCAPE SPECIFICATIONS
6.26.8 Regularity
Where appropriate in relation to the geometry of the surface, the variation in gap under a 3m straight
edge placed anywhere on the surface to be not more than 6mm.
On completion the finished surface level shall be within 6mm of the design level and the maximum
deviation within the compacted surface, measured by a 3m straight edge, shall not exceed 6mm.
The level of any two adjacent pavers shall not differ by more than 2mm. Any areas of paving which
do not comply with these tolerances shall be removed, and sand laying course lifted and re-laid
and the paving blocks re-laid to the correct levels.
Dimensional accuracy, uniformity of joint gaps, alignment and squareness shall be checked after
paving the first three rows of pavers and thereafter at regular intervals. If joints begin to open, the
pavers shall be knocked together using the hide mallet.
During the period immediately following completion and up to handover, paving shall be
maintained. Any mortar stains or droppings on the face of the paving shall be removed.
6.27.1 General
Finished slab paving to have an even overall appearance with no visible joints showing, free of
mortar and any other unnatural stains.
Page 68 of 113
LANDSCAPE SPECIFICATIONS
Movement joints in the paving and bed should be sited every 10m or as approved on working
drawings to suit patterns or fixed objects.
Perimeter and intermediate movement joints shall be incorporated in the paving in accordance with
the recommendations of BS 6213 Part 5; 1990 Section 6.
Lines and levels of finished surface shall be smooth and even to prevent ponding.
Lay paving slab upwards from the bottom of slopes where creep may occur.
Slab paving bedded on mortar must be kept free from pedestrian traffic for 4 days and vehicular
traffic for 10 days after laying.
Restrict access to paved areas as necessary to prevent damage from site traffic, especially oil and
diesel spillage.
6.27.2 Laying
Precast paving slabs used for vehicular and pedestrian carriageways will be laid to the pattern
shown on the drawings. Any change to the drawings is to be agreed with the Engineer prior to such
change.
The paving slabs shall be laid on the sand in a manner so as not to disturb those slabs already laid.
Each slab shall be placed firmly against its neighbour so that they fit closely together.
Where slabs do not fit at the edge, restraints or other obstructions such as manholes or up stands
the gaps shall be filled using cut slabs. Any damaged or broken slabs shall not be laid.
In all cases cutting shall be undertaken using a diamond tipped masonary saw. Mechanical splitters
may no be used.
Any slabs damaged during compaction shall be replaced at the direction of the Engineer.
The setting out of paving and related features is to be submitted in detailed Contractors shop
drawings which shall take into account actual site conditions.
Permissible deviation from specified levels to be +-6mm over 3m. Paving to be set 6mm above
drainage outlets and 3mm above kerbs to allow for settlement.
The base for concrete slab paving shall be a concrete bed and screed as covered in the general
specification.
Before starting work ensure that the base is sound, clean, suitably close textured, free from
movement under compaction and free from compaction ridges, cracks and loose material, and the
levels and falls of the base are as detailed, within the tolerance specified.
Mortar bedding shall consist of freshly mixed moist mortar 1:3 cement: sand mortar with plasticiser
as required, using sand complying with BS 882 grading M or F.
Page 69 of 113
LANDSCAPE SPECIFICATIONS
The mortar shall be spread to achieve a nominal compacted thickness as shown in drawings, to
reach a total finishes profile (paver thickness and mortar) of 90mm.
Mortar which has been mixed for more than 1 hour shall be discarded.
Units shall be laid on a full mortar bed and bedded down to line and level with a pavers maul.
Where units are laid with close joint (i.e. 2 to 4mm) jointing sand shall be brushed into the joints.
Where units are laid with a wide joint (i.e. 6 to 10mm) the whole of the joints shall be filled with
mortar.
Mortar mix shall be semi dry cement: sand to BS 882 grading limits M, proportions as specified and
coloured as required by the Engineer.
The paving shall be dry prior to joining. The joints shall be carefully and thoroughly filled with mortar
using a proper pointing tool and slotted masking shield.
The joint shall be flush, recessed or raised as detailed or as required by the Engineer.
6.27.9 Regularity
Where appropriate in relation to the geometry of the surface, the variation in gap under a 3m straight
edge placed anywhere on the surface to be not more than 6mm.
On completion the finished surface level shall be within 6mm of the design level and the maximum
deviation within the compacted surface, measured by a 3m straight edge, shall not exceed 6mm.
The level of any two adjacent pavers shall not differ by more than 2mm. Any areas of paving which
do not comply with these tolerances shall be removed, and sand laying course lifted and re-laid
and the paving blocks re-laid to the correct levels.
Dimensional accuracy, uniformity of joint gaps, alignment and squareness shall be checked after
paving the first three rows of pavers and thereafter at regular intervals. If joints begin to open the
pavers shall be knocked together using the hide mallet.
The edge restraints to the paved area shall be laid in advance of the laying course and all obstacles
within the area, such as manhole covers. Shall be constructed to the correct finished levels.
During the period immediately following completion and up to handover, paving shall be
maintained. Any mortar stains or droppings on the face of the paving shall be removed.
6.28 Natural stone (including but not limited to, granite, slate and sandstone)
6.28.1 General
Finished paving to have an even overall appearance with no visible joints showing, free of mortar
and any other unnatural stains.
Movement joints in the paving and bed should be sited every 10m or as approved on working
drawings to suit patterns or fixed objects.
Page 70 of 113
LANDSCAPE SPECIFICATIONS
Perimeter and intermediate movement joints shall be incorporated in the paving in accordance with
the recommendations of BS 6213 Part 5; 1990 Section 6.
Lines and levels of finished surface shall be smooth and even to prevent ponding.
Lay paving units upwards from the bottom of slopes where creep may occur.
Paving bedded on mortar must be kept free from pedestrian traffic for 4 days and vehicular traffic
for 10 days after laying.
Restrict access to paved areas as necessary to prevent damage from site traffic, especially oil and
diesel spillage.
Stone slabs, cladding, pavers or copings are to be sawn cut or as otherwise stated on the drawings.
They shall be worked fully square from faces for the full width and thickness of the piece or as
otherwise shown on the drawings for particular pieces
Cut paving units neatly and accurately with a diamond tipped masonry saw to give true junctions
with edgings and adjoining finishes. Edges shall not be chipped or corners broken, and will be
rejected if chipped or broken. Repair with silicones, glues, masticks or any other method will not be
accepted.
6.28.3 Sealant
Prior to laying any natural stone paving the Contractor shall apply to all surfaces and edges a coat
of premium, no-sheen, natural look, water based penetrating sealer/impregnator. Any edges which
have been sealed and then sub-sequentially cut shall be resealed to the approval of the Engineer,
prior to installation. An additional coat shall be applied to the exposed surface after installation.
Sealant to be applied in accordance with the manufacturers printed instructions, and shall be by an
approved supplier.
The setting out of paving and related features is to be submitted in detailed Contractors shop
drawings which shall take into account actual site conditions.
Permissible deviation from specified levels to be +-6mm over 3m. Paving to be set 6mm above
drainage outlets and 3mm above kerbs to allow for settlement.
The base for natural stone paving shall be a concrete bed and screed as covered in the general
specification.
Before starting work ensure that the base is sound, clean, suitably close textured, free from
movement under compaction and free from compaction ridges, cracks and loose material, and the
levels and falls of the base are as detailed, within the tolerance specified.
Page 71 of 113
LANDSCAPE SPECIFICATIONS
The units shall be solidly bedded on a mortar mix of 1 part cement to 5-6 parts clean sharp sand
by volume. Alternatively the units may be bedded on a semi-dry mix consisting of 1 part cement to
3 ½ - 4 parts sand by volume (12:4-4 ½ by weight) to BS 882.
The mortar shall be spread to achieve a nominal compacted thickness as shown in drawings, to
reach a total finishes profile (paver thickness and mortar) of 90mm.
Mortar which has been mixed for more than 1 hour shall be discarded.
The units shall be dampened on the back with clean water and tapped into position with a mallet.
Any bed material brought to the surface at the joints shall be wiped from the face of the stone with
a damp sponge or cloth immediately the stone is in position.
Mortar mix shall be semi dry cement: sand to BS 882 grading limits M, proportions as specified and
coloured as required by the Engineer.
The paving shall be dry prior to jointing. The joints shall be carefully and thoroughly filled with mortar
using a proper pointing tool and slotted masking shield.
The joint shall be flush, recessed or raised as detailed or as required by the Engineer.
Any mortar stains or droppings on the face of the paving shall be removed.
6.28.8 Regularity
Where appropriate in relation to the geometry of the surface, the variation in gap under a 3m straight
edge placed anywhere on the surface to be not more than 6mm.
Where detailed the fill areas shall be regraded, filled with suitable matching material and compacted
as specified to the approval of the Engineer.
The subgrade shall be graded to even running falls to achieve the detailed levels against paved
and planted areas.
The surface of the subgrade shall have all stones and similar material larger than 25mm removed.
The subgrade surface shall be free from all rivulets, crusting and caking.
The sub-grade shall be inspected and approved by the Engineer prior to the laying of the gravel.
Laying of gravel shall be to the depths as indicated on the drawings. All gravels are to be laid on
an approved geotextile fabric over a compacted subgrade.
The subgrade and if required a 50mm layer of levelling sand shall have sufficient cross fall to ensure
adequate drainage.
Gravels shall be raked, rolled, and watered as necessary to achieve a smooth surface of even
depth to even running falls in accordance with the layout detailed on the drawings and on the
approval of the Engineer.
Page 72 of 113
LANDSCAPE SPECIFICATIONS
Upon completion of all work specified within the Specification, the Contractor shall furnish to the
Employer, manufacturers literature on the "Care of all areas of external Hard Landscape" for future
maintenance use. This literature will be included as a section within the Hard Landscape O & M
Manual.
The Contract shall compile a comprehensive Operations and Maintenance Manual, which will
include the following:
This manual shall be submitted for approval at least two (2) weeks prior to substantial completion.
The handover of a completed document to the satisfaction of the engineer shall be a condition of
substantial completion.
Page 73 of 113
LANDSCAPE SPECIFICATIONS
7 IRRIGATION
Table 7.2
Type of irrigation system for each type of plantation shall be as per the section 2 (Irrigation System,
Materials) of this specifications and contract drawings for Installation details.
Contractor can arrange the area in different blocks with individual solenoid valve.
Each block (solenoid valve) shall serve only one type of irrigation head or system used.
Daily Operation time for the proposed irrigation system shall not exceed 10 hours.
For pipe sizing mean velocity of flow in Main or lateral pipes shall not exceed 1.5 m/sec. The total
head loss in Main line not to exceed 4.0 meter.
Contractor to provide ring Main with suitable no. of isolation valves to the approval of the Engineer.
Total friction loss from the far end of the lateral up to solenoid valve shall not exceed 2.5 metre.
The total head loss in solenoid valve assembly not to exceed 3.0 meter.
Arrangement of sprayers shall be in such a way that water spray from sprayer should not hit the
stems of the palm trees.
All materials and execution of the works shall be as per Dubai Municipality (DM) Drainage and
Irrigation Department Specifications and standards and to the approval of DM Irrigation Engineer.
Page 74 of 113
LANDSCAPE SPECIFICATIONS
7.2.1 Scope
This contract is for construction, completion and statutory maintenance of Automatic Irrigation
System as shown on the Contract drawings.
The contract shall include for the complete installation, testing and commissioning of the automatic
irrigation system summarized below and as per this specification and contract drawings:
1 Laying the Main , Submain and lateral lines for Automatic Irrigation scheme;
2 Laying of Ducts for Mains, Submains, Laterals and Control cables under footpaths and roads.
3 Laying Bubblers and Drip Systems as shown on the contract drawings;
4 Laying of Sprayer system for grass areas as shown on contract drawings;
5 Providing Automatic control system for irrigation network through Controllers, Communication
& Power supply cables, electric remote control valves, etc.;
6 Providing Control Panels required for the system as specified.
7 Providing tie-in Connection to existing TSE irrigation main and irrigation water supply line
complete with all required valves and fittings.
8 Removing of the existing soil, filling of fresh Sweet soil & gravel and the levelling & contouring
shall be done as per landscape drawings.
9 Reinstatement of the affected areas and as required during the progress of the project;
10 Arrange for permanent power supply
The Contractor shall include for all materials, labor, plant and tools.
Contractor shall propose and construct a tie in connection chamber as per the drawings and shall
make the connections to DM effluent line complete with all fittings (Tee, flange adapters), valve,
valve chamber etc to engineers approval.
Location of tie in connection to be approved by engineer andDM roads and planning departments.
Connection of power supply and signal cable for irrigation controller from nearest DM filtration
chamber / DM Irrigation controller is part of the contract.
All crossings across major roads/dual carriageways and U-turns shall be either through ducts or no
dig method.
It shall be done strictly as per DM specifications and to the Aprroval of the concerned Departments.
Back filling and road base to be tested by an approved independent laboratory at least one test per
200 mtr. interval and part thereof & 30 mtr interval and part thereof respectively or as per the
request at specific location by DM Roads Department Services Co-ordination Office & by the
Engineer.
Sweet soil filling, levelling and contouring for landscape areas shall be as per the landscape
drawings and also providing the tree pits is part of the contract. The sweet soil shall be taken from
Khawaneej borrow pits. The landscape patterns should be marked with lime powder, stakes and
nylon ropes. Shapes and dimensions of these patterns are shown in detail in the landscape
drawings.
The contractor to modify all the existing manhole chambers; in the proposed Landscape area (if
required); to the approval of the Engineer and the concerned service authorities; in order to match
its top levels with the proposed landscaping levels.
The contractor shall reinstate all roads and footpath where affected by the installation of irrigation
system to the approval of the engineer and DM Roads Department.
Refer to the attached “ Particular specification and relevant application of Administrative order No.
16 and 22 for Drainage, Sewerage and Irrigation Projects.”
Page 75 of 113
LANDSCAPE SPECIFICATIONS
7.2.2 Submittals
The contractor shall submit to the Engineer the following documentation for review and approval,
before commencing work:
All catalogue cuts, diagrams, samples, drawings and such other data may be required to
demonstrate compliance with the specification.
Prior to start of any work at site the contractor has to approach all Service Authorities in Dubai to
get their no objection for the work included in this contract and a record drawings for their existing
services. Copy of these drawings and no objection certificate should be submitted to the Engineer
before starting the actual work at site.
Please note that the contractor to make detail survey of existing levels in the contract area. Trial
pits should be taken at every 50 meter interval, mark all the existing services in reference to the
road edge & building line along with its depth from existing the ground level & the proposed
Landscape finish level.
Contractor to check availability of all the existing ducts that are marked on the tender drawings.
Contractor to propose the route of Irrigation piping based this information.
All this information regarding trial pits, existing and proposed levels, availability of existing ducts
shall be made available to DM Engineer within mobilisation period of the contract. All this
information shall be made available on hardcopy & in Digital format to DM as it is required for
adjusting landscape and pipes/services alignment.
Any delay to provide the above-mentioned information regarding trial trenchs, existing services &
levels which affects the progress of works shall be the responsibility of the Contractor. The Dubai
Municipality keeps the right to take necessary action and penalise the Contractor in such
circumstances.
The successful contractor shall submit shop drawings, for approval by the Engineer, for the
following:
1 In case of any conflict between contract drawings and any existing or future services which may
necessitate re-routing proposed irrigation Main or laterals, the contractor has to prepare the
shop drawings accordingly and submit it to the Engineer for approval. This should be considered
as integral part of the contract.
2 The Filtration Chamber mechanical, electrical and civil works shop drawings. Necessary
modifications to the existing feeding chambers (civil and mechanical). Valve chambers including
valves, pipe works and civil works. Electrical control equipment with circuit diagrams.
3 Details of mainline, Profile drawings for Mainline, lateral pipes and other typical connections.
4 Wiring diagrams including conduits, pull boxes, sizing and calculations to verify that cable sizing
is in accordance with DEWA regulations and equipment manufacturers recommendations.
5 Electrical power and control wiring diagrams for irrigation controllers, field wiring and grounding
including all interfaces.
6 Sketch plans for drip line layout.
7 Sketch plans for Sprayer and Sprinkler layouts.
8 Detail of valve chambers and any modification to the existing feeding chambers.
The approval shall not relieve the Contractor of any of his responsibility under the contract for
successful completion of the work.
Page 76 of 113
LANDSCAPE SPECIFICATIONS
Emitters
Certification of coefficient of manufacturer's variation.
The contractor shall submit manufacturers’ recommendations for installation and commissioning of
each material or piece of equipment for approval prior to commencing work. Recommendations
shall include testing methods, storage requirements, (if applicable) maintenance and operational
data. The contractor shall have a copy of the manufacturers' instructions available on site at all
times while works in progress and shall follow these instructions unless otherwise authorized to
deviate by the Engineer.
The contractor shall submit manufacturer's list of spare parts for approval prior to commissioning
any piece of equipment. Recommendations shall include stocking recommendations, exploded
assembly diagrams illustrating location and spare parts to be utilized and all relevant operational
data.
The contractor shall submit his proposed work method statement for approval prior to commencing
work. The statement shall detail proposed sequence of work, hold points, testing frequency and
document control.
The contractor shall submit a program of works as per the clause 14 of the condition of the contract
for approval.
The contractor also shall submit monthly progress report at the end of each month including all the
works constructed during the month with photographs, numbers of staff and laborers, cash flow,
test reports, overall progress and general details as per engineer approval.
At such time as the list of materials has been approved by the Engineer, the Contractor shall provide
four (4) sets of manufacturer's technical and maintenance literature to the Engineer. Data sheets
shall provide sufficient technical information to identify each product and shall include the name
and the address of the nearest supply firm which should have a local representative in the Emirates
of Dubai.
Contractor Must Submit All Circuit Diagrams Of Electrical Installation Along With Samples And
Specifications Of Materials Proposed In Order To Obtain Approval Prior To Fabrication Or
Installation.
Page 77 of 113
LANDSCAPE SPECIFICATIONS
As-built drawings
The Contractor shall maintain one set of contract drawings for the sole purpose of recording
accurate changes made; as the work progresses ("As-Built" conditions) of the irrigation system. All
changes previously approved and all completed work shall be recorded on these drawings.
The contractor shall prepare as-built drawings clearly showing all location, depths, slopes, heights,
shapes and dimensions of all the works as executed. All valve locations and piping shall be
dimensioned and recorded (except that wire locations, common to pipe ditches, need not to be
dimensioned). The contractor should clearly mention location of lines, chambers etc. in reference
to building line and center line of the roads. The contractor must submit as built drawings for all
electrical installations.
Sizes of the all the as-built drawings should same as that of DM Drainage & Irrigation Department
Standard (approx. 120cm X 60cm) size.
All as built drawings should be prepared using Micro-station program (latest version for windows).
Mainline layouts to be on DM survey sheets (scale 1:1000) as per Dubai municipality Drainage &
Irrigation Department requirements and approval. As-builts drawings of Mainline layouts of
Automatic Irrigation system Main and Irrigation Network Mains should on separate drawings for
each.
Contractor should prepare and submit as-builts drawings for the pipeline profiles of the Mainlines
which are of size 4” and above. Pipeline profile drawings should be in Horizontal scale of 1:1000
and Vertical scale of 1:100. Pipeline profiles to be submitted on separate drawings with clear
references to Mainline layout drawings marked on the same.
The Contractor to follow the Standards (regarding Legend, linestyles, colours, levels, size of
drawings etc.) of DM Drainage and Irrigation Department while preparing As-built Drawings.
Chambers Schedule are to be prepared indicating all relevant Construction items and giving co-
ordinates for each manhole in compliance with DM gird System.
The contractor must submit as built drawings for all the electro-mechanical installations. All the
details of the installed equipment regarding Manufacturer and Model No., type, size etc. shall be
provided in the legend of the drawings.
Pipeline profile drawings should be in Horizontal scale of 1:1000 and Vertical scale of 1:100.
Lateral line Layouts for Sprinklers/sprayers, Drip and bubblers shall be in Scale 1:500.
All the Layout drawings should be shown on background of light coloured Landscape as-builts, for
easy reference.
The Contractor should follow the Standards (regarding Legend, linestyles, colours, levels, size of
drawings, title block etc.) of DM Drainage and Irrigation Department while preparing As-built
Drawings.
After final approval to the As-built drawings, contractor to submit the following before the final taking
over of the project.
1 Three complete sets of "As-Built Drawings" folded properly and provided in Plastic folders as a
part of Operation & Maintenance Manual.
2 A set of mother prints (on heavy grade Polyester) and
3 A copy of computer discs: CDs (with proper titles and plastic enclosure box) please note that
zip files will not be accepted.
Provisional acceptance will not be considered unless contractor submits all the above-said as built
drawings.
Page 78 of 113
LANDSCAPE SPECIFICATIONS
Notes
1 Contractor to check all existing irrigation system within the contract area (along with existing
filtration chambers) and shall record those details in the as-built drawings of the project.
2 Contractor to prepare & submit the detailed records results of trial pits and trenches. All such
information shall be submitted to DM in digital format and hard copies.
3 Contractor to prepare & submit the detailed results of trial pits and trenches for records. Record
of all trial holes executed under this contract shall be made available in the form of drawings
(Scale 1:1000 for Plans & 1:100 for sections) to be the part of as-built set of drawings. These
drawings shall be made available to Services Co-ordination Unit of Roads Department, Dubai
Municipality. All such information shall be submitted to DM in digital format and hard copies.
A digital copy of Operation & Maintenance manual complete with Valve operation Schedule, Circuit
& control diagrams shall be submitted to DM along with As-built drawings
Submit one copy of the manual to the Engineer for review and Three final copies to the Client after
the final approval of the Engineer. Provisional acceptance will not be considered unless contractor
submits complete O & M manuals and as-built drawings.
The apparent silence of the specification, drawings or other contract documents as to any detail or
the apparent omission from them of a detailed description concerning any point, shall be regarded
as meaning that only the best general practice is to be used. All interpretations of the specifications
will be made by the Engineer on this basis.
During site visits by the Engineer, operation of the system will be delineated to all authorized
persons desiring such information.
Three copies detailed system operation and maintenance brochure will be provided to the Client at
the completion of the project by the Contractor.
Page 79 of 113
LANDSCAPE SPECIFICATIONS
The Contractor shall stake out the irrigation system in accordance with the scaled plans. Staking
shall be erected in such a manner as to insure permanency of the staked locations until such time
as the irrigation system is installed. Stakes shall be placed to show location of valves, pipelines
and control head. Stakes shall be flagged with bright flagging for ease of location. All staking by
the Contractor shall be subject to approval of the Engineer.
The Contractor shall stake the landscape patterns as shown on the landscape drawings. These
patterns shall be marked with lime powder and nylon ropes for future use by DM Horticulture section
during plantation phase.
7.6 Clean-up
During the course of construction, the Contractor shall remove waste material from the site
continually as is necessary to keep the site in an orderly manner. Waste material shall be removed
from the work site and not to be used as back-fill material. Upon completion of the contract, the
Contractor shall remove all waste equipment and parts and leave the site in a neat and orderly
condition.
7.7 Warranty
All work included under this contract shall be warranted by the Contractor against all defects and
malfunction of materials and workmanship for a period of one year from the date of completion of
works. Should problems arise with the system during the warranty period, all necessary repairs
and/or replacements shall be made by the Contractor in an expedient manner at no additional
cost to the Client.
The Contractor shall be responsible for operation and maintenance of the system for a period
of one year from the completion date.
All products shall be delivered in the manufacturers’ original protective packaging and shall be
inspected at time of delivery. Any product which are damaged and not in accordance with
specifications, or date stamp expired, shall be immediately removed from the site and replaced.
Evidence must be submitted to verify materials, such as uPVC pipes, solvent cement , rubber
gaskets etc., have been properly protected during transport and storage prior to delivery to the site.
All products shall be handled and stored in accordance with printed recommendations of the
manufacturer.
All site storage areas shall be shaded at all time. Pipe stacks shall be designed to ensure that pipes
and especially pipe sockets are not deformed during storage and/or effected by sunlight.
Precautions shall also be taken to protect items sensitive to sunlight or heat prior to backfilling
operation. uPVC pipes shall on no account be exposed to sunlight for more than two days in
summer, or one week in winter. Any pipe, whether installed or not, which is observed to be
sunburn, or oval, shall immediately be removed from the site and replaced.
The contractor will be responsible for operation, scheduling, and inspection of the system for one
year till completion of end of defects liability period. Contractor should provide a skilled operator,
a pipe filter and a helper who are experienced in widely irrigation requirements over various planting
times and climatic conditions for the optimal performance of the irrigation system. All these staff
should be available for full time on the site. Operating the system should be combined with the
instructions of the designer to formulate a set of standard operating procedures for the system.
During the planting and establishment time of the plantation Irrigation operation should be provided
Page 80 of 113
LANDSCAPE SPECIFICATIONS
Complete inspections are necessary during the operation of the irrigation system as follows:
Inspections of all the irrigation equipment line sprayers, sprinklers, dripper lines, injection system
etc., should be done regularly during the operation of the system for their proper and optimal
operation. Each zone should be inspected for excessively wet areas that might indicate leaks and
dry patches which indicate improper coverage of the sprayers / sprinklers.
Drip lines, and irrigation pipes should be inspected for breakages and attended immediately to
repair the same.
Arc and throw of sprayers and sprinklers should be inspected and adjusted in such a way that it
will not throw the water on the roads and stems of the palm trees. All the pressure regulators of
solenoid valves should be adjusted to give the recommended pressures.
7.10.1 Scope
The scope of this section includes a description of materials and methods for the hydraulic element
of the system.
All materials covered by this specification shall be from an approved local representative in the
Emirate of Dubai qualified to provide the appropriate level of technical support.
All equipment, fittings and accessories shall be suitably rated to comply with the system design and
operating parameters.
Note: Following are general specifications of D.M. for the Irrigation materials, the items which are
not required in this project shall not be considered in the scope of the works.
uPVC piping shall be fabricated from unplasticized polyvinyl chloride according to BS 3505:1968
and BS 3506:1969. Rating and size shall be as shown on the drawings but not less than class D.
Pipe shall be supplied in lengths no smaller than six (6) meters. Each length of pipe shall bear
markings of identify type and grade. All piping shall show no evidence of blisters, grooves or other
extrusion marks. The Contractor shall provide three (3) samples of each size, one meter in length
for approval prior to supply and installation. All pipes three inches ( 3") and above to be with Lock
Ring Socket. The socket to be integral part of the pipe and in accordance to BS 4346 part 2 : 1970
and it should incorporate a triple compression rubber seal complying with BS 2494 : part 2 and
when jointed offers three-fold hydraulic security under both positive and negative pressure heads.
The socket should have the same wall thickness as the pipe with an extra sleeve to maintain the
correct pressure rating at the joint.
All joints in pipe shall be made by solvent welding using adhesive solvent and primer as
recommended, in writing, by the manufacturer and approved by the Engineer. All cans of solvent
and primer shall have labels intact and shall be stamped with date of manufacture. No cans dated
over two years old will be permitted. No thinning of solvent or primer will be permitted. Lubricant
and solvent cement used to make joints shall be approved in writing by the pipe manufacturer or
his designated representative and the Engineer. Only male joints may be used up to 2".
Page 81 of 113
LANDSCAPE SPECIFICATIONS
Joints larger than 2" shall not be threaded. All threaded joints shall be made up using PTFE tape
or an approved equal thread sealant.
Pipes sized 1-1/4 " and larger shall be of class D (12 bars working pressure) and smaller pipes
shall be class E ( 15 bars working pressure ). Fittings shall be fabricated from UPVC according to
BS 4346.
For sizes upto 6” uPVC fittings shall be used. All uPVC pipes and fittings should be covered by
licensed Kite mark. All uPVC fittings shall be of pressure ratings not less than 15 bar at 20 deg.
Celcius and 9 bar at 50 deg. Celcius.
For sizes 8” and above GRP fittings with 15 bar pressure ratings shall be used in chambers.
On no account saddle and cross type connections be made to uPVC pipe should be used. All uPVC
pipes passing through ducts shall be solvent weld joints.
Flange adopters & couplers shall be PN 16 and in accordance with BS 4504. All Bolts and nuts
(whether part of the coupler or for fixing) shall be A4-70 stainless steel.
Threaded riser pipe used to support valves and sprinklers and fittings may be galvanized steel, or
brass. All galvanizing shall be carried out after threading.
Polyethylene pipes for drip lines shall be manufactured from linear low-density polyethylene
incorporating a minimum of 2.8% carbon black and shall have a working pressure of 4 kg/cm2.
A random samples of drip pipes shall be subjected to the Teepol crack resistance test. The
samples shall be immersed in a bath containing a solution of 10% Teepol and 90% water
maintained at 50 degrees C. The pipe should resist the solution without showing any fatigue or
crack for a period of 150 hours.
All fittings for drip line shall be compression type. Insert barbed type fittings secured by plastic
ratchet clips shall not be used.
For the trees planted (in planters) in the tiled areas and in grass areas; a common drip line (with
single dripline riser for several trees) running through conduit is not allowed. A separate dripline
riser from PVC lateral line shall be provided for each tree/planter.
The pipes for bubbler and dripline risers connections shall be as per BS. 1972-67 class C.
The fittings for the above pipes should be of compression quick joint type with minimum 12 bar
nominal pressure.
Steel pipe shall conform to API standard schedule 80 or other equal and approved. Welded fittings
shall be schedule 80 and weldneck. Flanges shall be in accordance with BS4504 PN16. All bolts,
nuts and washers used for flange assembly or integral with bolted couplers shall be stainless steel
(A4-70).
All Pipes and fittings to be coated inside and outside by electrostatic fusion bonded epoxy to
average DFT 150 microns, or by fusion bonded plastic powder coating to average DFT 500
microns.
Threaded steel pipes and fittings used for risers shall be hot dip galvanized mild steel class ( C ) in
accordance with BS 1387.
Page 82 of 113
LANDSCAPE SPECIFICATIONS
All G.I. & Steel Pipes and fittings to be coated, inside and outside with electrostatic fusion bonded
epoxy to average DFT 150 microns or by fusion bonded plastic powder coating to average DFT
500 microns.
Any galvanized pipe installed in contact with the soil shall be wrapped with at least two layers of an
approved petrolatum impregnated tape of min. thickness of 1.15mm and applied with 50% over lap.
The wrapping tape shall extend a minimum of 100 mm above the soil. Steel piping and fittings
shall only be installed above ground or otherwise specified.
Joints shall be threaded and sealed with PTFE tape or some other approved method. Connections
to the flanged equipment shall be via threaded flanged adopters. All bolts, nuts and washers used
for flange assembly or integral with bolted couplers shall be stainless steel A4-70.
Ductile iron pipe and fittings shall be in accordance with BS 4772 or ISO 2531. They shall be
supplied by an internationally known and approved manufacturer. Ductile iron pipes and fittings
shall be supplied, stored, laid, back-filled and tested in accordance with CP 2010. The pipes shall
not exceed 5.5 meters in length and push-in or flexible mechanical joints shall be used unless
otherwise stated .
Where flanged joints are used, the flanges shall be faced and drilled to PN16 as defined in BS
4504, unless directed otherwise. Flanged joints shall be made with inside bolt circle gaskets as
described in BS 4865 part 1, and gaskets from plain rubber to BS 1737. Bolts shall be stainless
steel Grade A4-70, complete with nuts and washers. The threaded portion of bolts shall be of such
length that at least two threads shall protrude beyond the nut when tightened.
Pipe barrels shall be class K9, tapers, bend and pipes with cast on flanges shall be class K12, and
tees shall be class K14.
The internal and external surfaces of all ductile iron pipes and fittings shall be coated according to
one of the following methods:
Asbestos cement pipes shall be class 18 confirming to the requirements of ISO 160:1980 with 5m
length. The cement shall be sulfate resistance to BS 4027. The joints shall be of Reka type coupling
or approved equal. All AC pipes and joints shall be coated externally with bitumen.
Couplers shall be made from the same materials as the pipe and shall be flexible allowing a
deviation of 1 to 5 degrees under normal circumstances. Jointing couplers shall be multi-toothed
EPDM rubber seal. Rubber seals should conform with BS 2494.
Copies of all test reports and certificates of compliance shall be submitted to the Engineer for each
consignment delivered to the site. Witnessing of factory testing by the Engineer may be required
prior to delivery. The AC pipes and couplers should be manufactured by the same manufacturer in
Dubai Emirate and to be approved be the Engineer.
All pipes and fittings shall have a resin rich inner layer, having a minimum thickness of 1.0 mm and
a resin rich outer layer having a minimum thickness of 0.25mm incorporating one layer of "C" glass.
The remainder of the liner shall consist of at least one layer of 450 g/m powder bound acid resistant
chipped glass strand mat having a glass content between 25 and 30 % by weight.
All glass reinforcement shall be of the "ECR" type. All pipes and fittings shall have an stiffness of
not less than 7500 N/M and satisfy the requirement of ASTM D 3262-87. Pipes shall withstand
longitudinal tensile force of 100 N/mm of circumference. All the flanges shall be PN16.
Page 83 of 113
LANDSCAPE SPECIFICATIONS
All fittings (including bends, tees, reducers and flanges) used with AC pipelines shall be GRP (glass
fibre reinforced plastic) fittings and shall comply with the following specification:
BS 5480 : 1990 Glass Fibre Reinforced Plastics (GRP) pipe and Fittings for use for water
supply Sewerage; parts 1&2.
General
This specification covers the design manufacture and testing of glass fibre reinforced plastic (GRP)
pressure fittings for use with Asbestos cement pressure pipe in nominal sizes 80mm and larger.
GRP fittings and pipe shall be designed and manufactured in accordance with AWWA C950-88
and the requirements herein. All components shall be produced by one manufacturer.
The manufacturer shall be approved by Dubai Municipality and must demonstrate the experience
and capability to produce fittings of the same diameter and pressure range as those required. The
manufacturer shall be certified to ISO 9002 or BS 5750 Part : 2. Full range of fitting diameters used
for the project must be manufactured and delivered by the same manufacturer.
Construction
GRP fittings shall have the following principal construction:
A corrosion resistant, resin rich having a minimum thickness of 0.5mm. The liner surface in contact
with water shall be reinforced with “C” glass veil or mat impregnated with Vinylester or Epoxy Resin.
The liner shall be continuous along the circumference of the pipe and shall be of uniform thickness
and composition.
A structural wall consisting of continuous glass filament findings and/or woven rovings and chopped
glass reinforcement and may include fine fillers, all impregnated with Isophethalic, Vinylester or
Epoxy resin as required.
GRP fittings and flanges shall be designed in accordance with AWWA C950 for service at the
following conditions:
Flange X flange fittings shall be designed for installation above ground (in chambers) without thrust
blocks. Flange branches on Spigot Tees shall be designed to resist end thrust from closed valves.
Spigot joints, where specified shall have the same outside diameter (OD) as approved by Dubai
Municipality for Asbestos cement (AC) pipe to which it is to be joined. The joint dimensions and
tolerances shall be equal to AC pipe spigots such that joint remains watertight under all normal
operating and surge conditions. The spigot ends shall be clearly marked with a “homeline”
indicating the proper insertion limit for the AC couplings. The spigot width shall not be less than
half the AC coupling joint width.
Flanged joints, where specified shall be GRP filament would flanged manufactured from Epoxy or
Vinylester resin and glass reinforcements. Flanges shall be flat faced and drilled to BS 4504 PN 16
drilling pattern.
Page 84 of 113
LANDSCAPE SPECIFICATIONS
GRP Flange gasket (full face) design and thickness shall be as recommended by the GRP fitting
manufacturer. Hand lay-up flanges shall not be acceptable.
Laminated or adhesive joints used in the fabrication of fittings shall be equal or superior in strength
to the sections they join. The thickness of laminated joints shall not be less than the wall thickness
of the adjoining pipe section. All hand laminations or windings shall utilize only one type of resin
throughout.
Chemical requirements
GRP fittings shall be not impart any date, odour or colour to drinking water. GRP pipe/fittings shall
be certified and listed for portable water use by the water research center (WRC) U.K., in
accordance with BS 6920 or by the National Sanitation Foundation (NSF) - USA in accordance with
NSF standard 14.
Dimensions
GRP fittings shall be produced in Metric sizes and shall be classified by their nominal inside
diameter (ND). The actual fitting inside diameter shall not be less than that shown in the table
below:
All standard fittings up to and including diameter 300 mm used in the distribution system shall be
filament wound on precision steel moulds. Standard 90 and 45 degree bends of nominal diameter
300mm and smaller shall be of the smooth radius type, having a turning radius of 1.5 times the
bend nominal diameter. Fittings diameter 350mm and larger may be of the moulder or mitered
(manufactured from GRP pipe sections) construction and internal surfaces shall be finished
smooth.
The thickness of GRP flanges shall not be less than shown in the table below:
Page 85 of 113
LANDSCAPE SPECIFICATIONS
The wall thickness of GRP fittings shall be determined by the manufacturer to meet the design
requirements of this specifications but shall in no case be less than the minimum thickness shown
in the table below:
Mechanical properties
Page 86 of 113
LANDSCAPE SPECIFICATIONS
Table 7.6
Visual Requirements
GRP fittings shall be free from delamination, crazing, dry areas or cracks. Spigot ends shall be
free from end delamination, torn edges and gauges and shall be finished smooth to ensure water
tightness. All laminates shall be fully cured with a minimum Barcol hardness of 33 when tested in
accordance with ASTM D2583.
Testing
Routine tests
The following test shall be carried out by the GRP pipe/fittings manufacturer at the frequency
specified. Test results and certificates shall be submitted to the Engineer for each consignment
delivery. Witnessing of factory testing by the Engineer may be required. The Dubai Municipality
and the Engineer shall have the right to retain up to 2% of the material delivered back to the factory
for inspection and /or testing by their representative at no additional cost.
Test Frequency
Visual Inspection every item
Dimensions every item
Hydraulic pressure at 24 bars once per 10 Flg. x Flg. for 30 seconds
items
Stiffness once per 100 items
Barcol hardness (resin cure) every item
Axial & Hoop Tensile stress once per 100 items
All GRP pipe used for fitting fabrication shall be factory
pressure tested at 24 bars for 60 seconds.
1 Long-term hydrostatic design pressure of the GRP pipe or fitting shall be established in
accordance with AWWA C950 Section 2.4.2.
2 Short-term hoop tensile strength shall be within the ultimate strength of the pipe fittings.
Laminated joints and flanged joints shall withstand a hydrostatic test pressure of 3.5 times the
rated working pressure with no signs of leakage or weep. For Flanges joints, the flanges shall
be blinded and the ends unrestrained during the test.
Page 87 of 113
LANDSCAPE SPECIFICATIONS
Submittals/drawings
Prior to start of production, the fittings manufacturer shall submit to the Engineer detailed drawings
of each fitting required for approval. Design calculations, samples and sample testing may also
require by the Engineer for approval at no extra cost to the client.
For flanged fittings, the manufacturer shall submit before delivery, the recommended gasket details,
the bolt torque sequence and maximum recommended torque for each flange shall be supplied.
Markings
Each fitting shall be indelibly marked with the following:
- Manufacturer’s name or trade mark
- Nominal diameter (ND) in mm (inside and outside)
- Pressure rating in bars
- Manufacturing date, month & year
- Inspection mark
- Coupling “homeline”, “position” position on spigot end.
Dust cap should be fixed at the end of each 4mm tube to prevent insects and dirt from entering
the tube. The cap should be durable plastic and heat resistant.
All drip tubes tubes shall be hold on the soil by Staple stake. The stake should be polypropylene,
minimum 220mm long, durable and heat resistant. Tails of the stakes shall be provided with integral
barb type flaps to increase retention in soil. The drip line shall be hold on the soil by the same
length staple stake at 10 m interval. The stake shall be featured separated surface to grip the drip
line.
7.12 Valves
Automatic remote control valves shall be of the sizes prescribed on the plan. The valves shall be
normally closed diaphragm type with slow opening and closing action for protection against surge
pressure. Actuation shall be by encapsulated type solenoids and rated 24 volts, 50 cycle unless
otherwise specified.
Construction shall provide for convenient access to functional parts without removal of valve from
system plumbing. A manual flow control adjustment, with shut-off capability, shall be furnished on
all valves. Valve pressure rating shall not be less than 200 PSI.
The diaphragm shall be of nylon reinforced BUNA-N rubber, and provide for a positive seal
between bonnet and body. The solenoid functional parts shall be of stainless steel, brass or bronze
for corrosion resistance. Diameter shall be as shown on plan. A mechanism shall be provided for
bleeding of the diaphragm chamber for manual operation. Valves shall be fabricated from heavy
cast brass or bronze. The valve shall be capable of working under dirty (Treated sewage) water
conditions. Inlet and outlet shall be threaded B.S.P.
All valves shall be provided with a pressure regulator capable of regulating downstream pressure
between 15 to 100 PSI ( within an accuracy of +or- 5PSI) regardless of upstream pressure. It shall
provide full and accurate pressure regulating capabilities irrespective of whether it is operated
electrically or manually. The pressure measurement should be possible via schrader valve or
integral pressure gauge.
Page 88 of 113
LANDSCAPE SPECIFICATIONS
All the solenoid valves shall have its dedicated unique nos through a decoder system. This decoder
shall be water proof and works on low power signal from irrigation controller. Decoder shall be
compatible to irrigation controller.
In each distribution chamber there shall be master solenoid valve. It shall be connected to irrigation
via compatible decoder. Material of construction shall be glass wool nylon (3”- female threaded) &
ductile iron (4” – flanged PN 16).
Check valves three inches ( 3") and above shall be double flanged single door swing type
having ductile iron body and gunmetal seat to BS1400 .Pressure Rating to be PN 16 or more. All
valves shall be coated with epoxy internally and externally to average DFT 300 microns for
protection against corrosion of body components. All nut bolts to be of stainless steel grade 316/
A4-70.
Check valves of two inches (2") and smaller shall be spring type manufactured from Brass or
Bronze. Inlet and outlet to be BSP female threaded. The spring to be of stainless steel. Pressure
rating to be PN16 or more.
Gate valves three inches ( 3") and larger shall be double flange, ductile iron waterworks valves,
with wedge type gate and non-rising stem. Valves shall be manufactured in accordance with
DIN3352. All valves shall be coated with epoxy internally and externally to average DFT 300
microns for protection against corrosion of body components. Valves installed below ground
shall be provided with stem cap for key operation.
Valves to have non rising stem of stainless steel , stem nut brass or cast aluminium bronze with
gun metal. Body components shall be of Ductile cast iron SG GGG-50 . Stem sealing by elestomer/
NBR rubber ‘O’ rings.
Up to size DN 400 resilient seated Gate valves are preferred with ductile iron wedge fully covered
with special grade elastomer EPDM rubber. Heavy duty steel keys with head configuration to
fit operating nut and handle length as required for proper above ground operation shall be provided
in numbers specified by the Engineer.
Valves above ground shall be provided with hand wheel. Nominal pressure for the valves shall be
16 bar or more. All bolts and nuts to be stainless steel grade A4-70.
Gate valves two inches (2") in diameter and smaller shall have non-rising stem and be
manufactured from brass or bronze according to BS 5154. Inlet and outlet to be screwed BSP.
Rating to be PN16 or above.
Provide automatic double orifice air vents at all high points on the pressure mains. Air valves and
other similar items shall confirm to BS 2591. Automatic air valves shall have non corrosive floats in
chambers with clear space ensuring blockage free operation. All components for the air valve
actuating mechanism including lever shall be stainless steel.
The body and cover of the valve should be of bronze or ductile iron with phenolic primer coating.
Nozzles with seals and actuating mechanism to be located in the removable upper plate connected
to the valve body using stainless steel (grade 316/A4-70) bolts. Valves shall be coated with epoxy
internally and externally to average DFT 300 microns for protection against corrosion of body
components. All nut bolts to be of stainless steel grade 316/ A4-70
Pressure rating of the valve shall be 16 bar. The internal components shall be stainless steel. The
valve size and installation shall be as per site conditions and engineer instruction.
7.12.5 Electrically actuated Butterfly valve
Page 89 of 113
LANDSCAPE SPECIFICATIONS
Electrically actuated Butterfly valves shall comply in all respects with DIN 3354 - PN16 Body of
Ductile cast iron SG GGG-40 Valve disc shall be of Stainless steel 316.
All valves shall be coated with epoxy internally and externally to average DFT 300 microns for
protection against corrosion of body components.
Butterfly valve shall be flanged type to DIN 250 , part 1 for PN 16 , face to face dimensions to DIN
3202-K1 corresponds to ISO 5752 , concentric type , streamlined design.
With replaceable seat ring , fusion bonded on backing ring , leak tight closure on both directions.
For operation at differential pressure at maximum 16 bars with operating gears with eletric part
turn actuator .
Variant DN-40-300 ,K1, Seat ring NBR (BUTA N ) , Shaft S.S. 1.4005, Maximum working
temperature +80 degree celcius with maximum working pressure 16 bars.
Electric actuators shall have to open and close of at least 60 seconds and shall be provided with
an auxiliary operating wheel. The motor control should allow for stepped closing of valve pausing
at ½ closed and ¼ closed.
Motor and electrical protection shall be in strict accordance with the electrical specifications and
DEWA regulations; motors shall be rated to operate at an ambient temperature of 50 degrees
centigrade, and a relative humidity of 100 %.
Electrically actuated butterfly valve shall be connected to low pressure cut-off switch for automatic
closing of valve in case of low pressure (downstream of valve) due to any breakage in the system.
But valve should not be closed if both downstream and up- stream pressure is low.(due to
shutdown/ breakage of TSE Network Main). For this purpose Contractor should arrange a
differential pressure switch and arrange required control in combination with other controls.
Complete control of the valve including partial closing of valve should be possible.
The valve shall open and close in modulating action. On pressure reversal, valve shall close tightly.
Adjustable pressure range shall be from 1.0 kg/cm2 to 8.5 Kglcm2
These valve shall be installed in the pump room as shown on drawings to release excess pressure
away from the system.
The valve shall be flanged, diaphragm type , hydraulically operated, pilot controlled, and modulating
type. The pilot shall be brass and tubing of copper/brass. The valve shall be fast opening and slow
closing. The valve shall be flanged and of ductile iron body. All internal and external exposed
surfaces shall be FDA approved epoxy coated to minimum DFT 300 microns. All nut bolts to be of
stainless steel grade 316/ A4-70.
Page 90 of 113
LANDSCAPE SPECIFICATIONS
Air valves (1" or smaller only ), quick coupling valves, solenoid valves and wires pull boxes to be
installed in an access box of sufficient size to permit ready removal of the valve inner assemblies
without removing the box from the ground. Valve names and numbers must be clearly marked
inside and outside of the box with permanent plastic tags.
Valve boxes shall be fabricated from reinforced plastic and minimum recommended size shall be
as follows:
Cover Depth
Q.C.V. 250 mm (dia.) 230 mm
Pull box, Air valve 1” & Flush valve 430 x 295 mm 300 mm
Solenoid valves up to 2” 590 x 349 mm 380 mm
Solenoid valves above 2” and isolation valves
825 x 495 mm 450 mm
up to 3”
Measurement are taken from the top of boxes. Covers shall be secured by stainless steel (A4-
70)bolts.
Please note - installation of plastic valve boxes in Paved areas and Sikkas are not allowed. All the
valve chambers/pull boxes in paved areas and sikkas shall be in RCC and with heavy duty ductile
iron manhole covers.
Ductile iron basket strainer with bolted cover, inlet and outlet to be flanged and drilled to NP 16.
The strainer should be stainless steel with 1/8 inch. perforations. Working pressure is 150 psi. All
bolts and nuts to be stainless steel grade 316 /A4-70. The basket strainer shall be coated internally
and externally with coal tar epoxy 300 DFT micron.
Emitters shall be constructed from durable black-heat resistant plastic. The emitters shall be of
barbed configuration which can be inserted easily in to Polyethylene tubing. Pressure
compensation shall be achieved by a flexible orifice located in resilient Silicone Elastomer
diaphragms. The orifice should be self-flushing type and shall clean itself during each irrigation
cycle at the start up and the shutdown. The emitters should have manual flushing capability also.
The emitter exponent shall be 0.10 or less. The body and the diaphragm should be resistant to high
concentration of Chlorine, fertilizers and pesticides.
Page 91 of 113
LANDSCAPE SPECIFICATIONS
Irrigation equipment. Dripperline shall consists of linear low density Polyethylene tubing with
pressure compensating, self-flushing type integral drip emitters. The tubing shall have an minimum
outside diameter (O.D.) 16mm and thickness of 1.1 mm + 0.05mm. Pipes for drip lines shall be
manufactured from low density polyethylene incorporating a minimum of 2.8% carbon black,
antioxidants in an amount not exceeding 0.5% and shall have a nominal pressure PN 6.
A random samples of drip pipes shall be subjected to the Teepol crack resistance test. The
samples shall be immersed in a bath containing a solution of 10% Teepol and 90% water
maintained at 50 degrees C. The pipe should resist the solution without showing any fatigue or
crack for a period of 150 hours.
The emitters must be pressure compensating according to ISO9260 and emission rate of the
emitter shall remain constant at varying water pressure from 1bar to 4.5 bar. The flow path in emitter
must ensure turbalant flow and emitter must confirm to excellent pressure compensation and self
claning/ Flushing mechanism. The emitter must be clogging resisting and the fitration requirement
not more than 150 mesh. Coefficient of variation shall be less than 5%. the flow of emitter must
remain same /constant at temperatures varying from 0 to 60 deg. celcius.
The product must have warranty against cracking and performance for 7 Years.
Number of dripline risers shall be as per Engineer’s approval. Separate dripline risers shall be for
each planter. Each tree in grass areas shall be provided with separate dripline riser. Drip stakes
shall be provided at eact point of change in direction of drip line and spacing between drip stakes
shall not be more than 10.0 meters
The capacity and spacing of the inbuilt emitters in the surface dripperline shall be as follows:
- For planting shrubs: discharge rate of each emitter shall be 3.5 lph. Spacing between emitters
in the dripperline shall be 50 cm. Spacing between dripper lines should be 30 cm.
- For desert shrubs: discharge rate of each emitter shall be 2.3 lph. Spacing between emitters in
the dripperline shall be 50 cm. Spacing between dripper lines should be 50 cm.
- For ground covers: discharge rate of each emitter shall be 3.5 lph. Spacing between emitters
in the PC dripper line shall be 50 cm. Spacing between dripper lines should be 50 cm; if the
plant density is 3 to 4 plants per square meter.
- For shrubs; on line PC emitters of 8 GPM 2 Nos per plant if if the plant density is 1 to 2 plants
per square meter.
- For desert ground covers: discharge rate of each emitter shall be 2.3 lph. Spacing between
emitters in the dripperline shall be 50 cm. Spacing between dripper lines should be 50 cm.
- For planting hedge: discharge rate of each emitter shall be 3.5 lph. Spacing between emitters
in the dripperline shall be 30 cm x 2 lines with 50 cm spacing.
- For desert hedge: discharge rate of each emitter shall be 2.3 lph. Spacing between emitters in
the dripperline shall be 50 cm x 2 lines with 50 cm spacing.
- For cactus and succulents: discharge rate of each emitter shall be 2.3 lph. Spacing between
emitters in the dripperline shall be 50 cm. Spacing between dripper lines should be 50 cm.
Material specification of the subsurface dripperline shall be same as the surface dripperline stated
above.
Subsurface dripperline shall have an emitter protection from root intrusion without requiring EPA-
approved handling and shall not use harsh chemicals or treated filters for the protection.
The product shall be dual-layered to provide unmatched resistance to chemicals, algae growth,
and UV damage.
Page 92 of 113
LANDSCAPE SPECIFICATIONS
Emitters of the subsurface dripperline shall have extra-wide path combined with self-flushing action
to act as resistance to clogging at the outlet hole.
The product shall contain at least 20% post-consumer recycled polyethylene which qualifies for
LEED credit 4.2.
The capacity and spacing of the inbuilt emitters in the subsurface dripperline shall be as follows:
- For lawn area: discharge rate of each emitter shall be 2.3 lph. Spacing between emitters in the
dripperline shall be 50 cm. Spacing between dripper lines should be 30 cm.
Bubblers shall be constructed from UL stabilized engineering grade plastic and rubber and shall be
pressure compensating in the range 2.00 to 5.00 bar, delivery shall be umbrella pattern, flow shall
be 0.5 gpm. Inlet shall be 1/2 inch. female threaded.
Stakes for bubblers shall be constructed from strong temperature resistant polypropylene plastic
construction with protective stop collar, length shall be 12 inches each side of inlet with barbed side
inlet suitable for class “ C “ polyethylene pipes, outlet shall be 1/2 inch. external male thread.
The sprayers shall have a high level impact strength corrosion resistant body, stem and nozzle.
Pop - up height should be 4". The sprayer shall have a heavy duty stainless steel retraction spring
and piston with slip clutch to facilitate nozzle positioning. The sprayer shall incorporate a wiper seal
to protect the internal mechanism against ingress of foreign material and prevent pressure blowout
and shall have an easily accessible under nozzle screen. The wiper seal should be co-molded type
that ensures flow-by of less than 0.10 US. gpm at low pressure and complete sealing at pressure
greater than 10 psi. The sprayer shall have 12 mm (1/2") threaded inlet.
All sprayers should be provided with built-in seal-a-matic check valve and in stem pressure
regulator to maintain constant outlet pressure of 30 psi.
The sprayer shall have the following performance specification at 2 Bar operating pressure:
Other series nozzles namely 5 and 10 shall also have corresponding discharge rates to have
precipitation rates similar to those above.
Page 93 of 113
LANDSCAPE SPECIFICATIONS
The nozzles shall have precipitation rates matched across sets and across patterns. The standard
nozzle shall be capable of covering 4,5 metre radius at 2.0 bar pressure.
Spacing for the sprayers with standard nozzle shall be 4 meters. For small areas sprayers with low
flow nozzles shall be used as shown on drawings.
Turbine or gear drive rotor pop up sprinklers, full and part circle operation with Memory-Arc to
automatically return nozzle stream to set arc. Part circle adjustment shall be from mimimum 40
deg. to 350 degrees. All adjustments of the sprinklers shall be from the top.
The internal mechanism is water lubricated. Heavy-duty plastic case with multi-function wiper seal
and heavy duty retraction stainless spring. All sprinklers should be provided with seal-A-matic
check valve. Bottom inlet to be 3/4" BSP female threaded. Pop up height to be not less than 3 5/8".
The nozzles of all the sprinklers shall be low-pressure models for proper performance even at low
pressures.
The sprinkler shall approx. match the following performance specification a 3.0 bar operating
pressure:
Spacing for these sprinklers shall be not be more than 10.0 meters.
Spacing for these low angle sprinklers shall be not be more than 6.5 meters.
Sprinklers in tree areas should be with low trajectory angle.
- Centrifugal pumps shall be in-line vertical, multistage, having cast iron body and base. The
pump section (shaft, impellers, guide vanes and chambers) shall be of stainless steel. The
mechanical shaft seal shall have diamond polished Tungsten Carbide or Silicon Carbide seal
faces and heat resistant O-ring. Thrust bearing shall have ample capacity to carry the weight
of all rotating parts plus the hydraulic thrust of the impellers. Motors shall be closed coupled
type.
- Pumps shall be suitable for treated sewage/ brackish water.
Page 94 of 113
LANDSCAPE SPECIFICATIONS
- Sump pump is required for the Pump Chamber, location and arrangement should be as per
details drawings.
- The pump shall be of robust construction and suitable for pumping corrosive, treated effluent
with high sand content. It should operate at minimum 100mm depth of water.
- Pump body, impellor as well as vital pump components to be of Stainless steel
- Capacity of these pumps should depend on the calculation by the Engineer considering the
whole network of water supply. Delivery line of these pumps to be connected to the nearest
storm water Drainage manhole. This connection shall strictly be as per the specifications & the
requirements of Drainage & Irrigation department.
- Float switch to be provided to operate these pumps automatically if the level of water inside the
filtration chambers comes up.
- All switches and control devices related to these pumps to be fixed in the electric control panel.
- Drain line to be connected from fertilizer room to sump pump pit in Filtration Chambers.
Automatic self-cleaning filters specifically designed for use with organic contaminants. Cleaning
shall be effected by a hydraulically powered suction scanner, automatically activated when the
differential pressure across the filter reaches an adjustable level, nominally 5 psi.
The screen shall be stainless steel grade 316 with 200 micron mesh size. Flushing line to be
connected to the soak pits or nearest storm water drainage manhole.
The control system shall feature a failsafe timer to prevent continuous flushing due to malfunction.
The control System for the filters should be such that it will not flush the filters if the pumps and/or
irrigation system is not operating. Filters should flush; only during the operating hours of the
Irrigation System.
The screen area shall not be less than 400 sq. inch.
All the filters shall have isolation valves in the suction as well as delivery side for easy maintenance.
The controller for the filters shall be equipped with timer and pressure differential control unit.
Controller will be fixed in the Electric control panel.
All nuts and bolts shall of stainless steel grade 316 or A4-70.
The filter body and internal parts including flanged connection shall be stainless steel.
Pressure gauges to be connected to suction and delivery side of each filter, pressure gauges to be
mounted in the Electric control panel in isolated compartment.
Pressure gauges for filtration chambers shall be stainless steel, direct reading, Glycerin filled
capable of 0-10 kg/cm2 register with 0.25 graduations.
Gauge shall be of glass or Plexiglas faced drip-proof and minimum dia. of 50 mm.
Gauge cock shall be of same size as pressure gauge and be fabricated from stainless steel.
Page 95 of 113
LANDSCAPE SPECIFICATIONS
Warning tape shall be laid above main pipes. Tapes shall be durable and detectable by Electro-
Magnetic means using low output generator equipment. They shall remain legible and color fast
in all soil conditions at PH values of 2.5 to 11.0 inclusive.
The tapes shall be flexible and subject to the Engineer's approval. Width of the tape should be at
least 6"(150 mm.).
Tape shall be orange color with black text in Arabic and English as ‘CAUTION: IRRIGATION
PRESSURE MAIN BELOW’. The text on the tape shall be permanent ink bonded to resist
prolonged chemical attack by corrosive acids and alkaline with message repeated at a maximum
interval of two meters. The tapes shall be laid 300 mm above the pipeline.
The tape shall be continuous over pipelines and at joints there should be a minimum of one meter
over lapping.
All electrical equipment shall be in accordance with DEWA regulations and electrical specification.
Enclosures shall be protected in accordance with IP55 for equipment installed above grade and
IP58 for equipment installed below grade.
Wiring to and from control panels shall be routed in pvc conduit below the ground. Above grade
conduit to be liquid tight flex, or galvanized steel, provision to be made for inspection tee's and ells
to facilitate removal in the future.
1 SIEMENS
2 TELEMECANIQUE
3 ABB.
All electrical wire for underground use shall be single core soli ‘Underground Feeder” type insulated
with a flame retardant thermoplastic compound, rated for 600 volts and direct burial. Twisted paired
cable shall be laid to communicate between irrigation controller and solenoid valves decoder. The
cable shall be 12/14 AWG single core cable. The maximum coverage from decoder cables shall be
up to 3 Kms. The Contractor shall prepare a wire sizing chart with effective lengths of each station
and common wires, which shall be submitted for approval prior to commencement of work. Cable
markers shall be used for indicating valve number each cable at both ends as well as at splices.
Cables shall be laid in PVC conduits.
Two-way twisted decoder signal cables should be laid in separate conduits between irrigation
Controller and Main control panel for future use. Separate wire to be laid for each solenoid valve,
and valve combination to be arranged at the respective field satellite. Power cables for Irrigation
controllers shall be armoured cables without any conduit for it.
Two-way Signal wire between the Main Control Panel and the Irrigation controllers should be
double jacketed, two conductor cable intended for future central control system.
The cable manufacturer should certify that the insulated conductors have been tested for and meet
the requirements of U.L.
The two conductors shall be colour coded with one conductor BLACK and the other RED. The
conductors shall be tin coated, soft drawn, annealed solid copper conforming to the requirements
of ASTM-33.
The cable shall be suitable for direct burial in the earth, whoever it is required to be installed in
ducts or conduits.
Page 96 of 113
LANDSCAPE SPECIFICATIONS
Pull boxes shall be provided in every place of change in direction of conduit piping, near to solenoid
valves. In any case spacing between adjacent pull boxes in a line shall not exceed 50 metres.
Size of the cable depends on the distance between the Main Control Panel and the field Controllers
and according voltage loss calculations.
Separate conduit & pull boxes should be used for Two-way signal cables.
All wire connections at electric remote control valves and all splices of wire in the field shall be
made using wire connectors. The wire connectors shall be specifically designed to ensure water-
proof underground wire connections. The connectors shall be under-writers laboratories listed
water-resistant wire connectors, rated 600 volts for PVC insulated copper wire with insulation
temperature rating of 105 degree C.
The connector shall be insulated with color coded, pliable, vinyl skirt. The shall feature alive spring
which assures a tight grip even on small wire combinations.
All wire connections to be arranged in plastic pull boxes at fixed interval distances of max. 100
meters and/or at any change of direction.
Pressure switches shall be fabricated from die cast aluminium per ASTM B-85 and designed to
meet IP65 specifications. Transducers shall be fabricated from brass and buna N.
The pressure switches shall incorporate an alternating fulcrum balance plate allowing independent
adjustment of both set and reset point over the full range.
Both set and reset points shall be adjustable 1.40 to 14 bar, having a minimum deadband range
less than or equal to 1.40 bar. Repeatability shall be +/-0.5% to 2% of full scale. Switches shall be
vibration resistant and shall have front access to electrical connections and adjustment nuts.
Flow sensing and control system to sense the flow data and display that data as both flow rate and
volume on digital indicator.
Flow sensing and control system to sense the flow data and display that data as both flow rate and
volume (in US gallons) on digital indicator.
Page 97 of 113
LANDSCAPE SPECIFICATIONS
Digital Indicator displays for both flow rate and total volume to be provided and to be mounted
inside the panel. The digital indicator unit should be powered with external 220 volts AC power
supply and rechargeable Lithium battery. The unit can run of internal or external power and should
have automatic changeover switch which is activated during a power failure. The battery will be
automatically recharged during normal operation.
Flow reading should be on the indicator in the panel at site. Factory Calibration Certificate shall
be provided with the Flow Meter.
Electromagnetic Flowmeter
General
Flow meter shall comprise of a flow sensor and a transmitter unit. The transmitter and Display Unit
shall be remotely mounted in the Main Control Panel. The flowmeter shall be microprocessor
based, modular design. Total measuring system shall be suitable for a minimum ambient
temperature of +60oC. Each meter shall be provided with the validation on site without removing
the sensor. Flowmeter processor unit must be digital to reduce noise level. All inputs, outputs and
power supply shall be galvanically isolated. Overall accuracy should be 0.5% and repeatability
shall be 0.1% or 0.5 mm/s (o.r = of reading)
Each unit shall have electromagnetic compatibility shoud be more than 10 V/m and shall withstand
and isolation test up to 1600 V for 2 sec.min. Complete flowmeter should have good resistance to
shock and vibration. It should withstand acceleration of 2g/2h per day, 10-100 Hz.
Sensor
Submersible, flanged process connection of carbon steel material with zinc aluminium alloy coating
rated suitably for application. Metering tube shall be at least SS 304. Each sensor should have 2
measuring electrodes, 1 empty pipe detection electrode and 1 reference electrode. It is essential
to have additional empty pipe detection electrode for proper detection of pipe condition. Electrodes
material shall be stainless steel SS 316. Sensor housing material should be powder coated die-
cast aluminium. Sensor lining shall be polyeurethane suitable for potable water. Each sensor shall
be protected to IP 67 or IP 68 as required. If the sensor is installed in a flow chamber sensor must
be IP 68. Also, IP 68 protection shall be from the manufacturer, without using any external kit or
gell locally. The conection cable between the sensor and transmitter should be original and fitted
and potted from the manufacturer. The sensor and transmitter shall be connected with 10m cable
from the manufacturer. The coil cable shall be 2x0.75 mm2 PVC braided copper shield and the
signal cable shall be 3x0.38 mm2 PVC braided copper shield.
In case of non-conductive pipe materials grounding rings shall be used for proper grounding or
complete meter must be isolated.
Transmitter
The transmitter must be microprocceor based remote wall mounting type. It shall have modular
design and field configurable by its built-in buttons via matrix. Transmitter housing shall be robast
powder coated diecast aluminium construction with IP 67 protection. It is essential that the
transmitter is of modular design for ease of maintance and future expendability. In case of any
fault in the transmitter one should be able to change individual modules. Outputs shall be analog
output (HART) and pulse/frequency. It should have 2 line, 16 character LC display for flow rate
and totalized flow indication. Transmitter should be configurable for error messages, empty pipe
detection, flow direction etc.
The sensor and transmitter shall be connected with 10m cable from the manufacturer. The coil
cable shall be 2x0.75 mm2 PVC braided copper shield and the signal cable shasll be 3x0.38 mm2
PVC braided copper shield. The meter should be able to operate at the voltage range of 100 – 260
VAC, 45 – 65 Hz supply.
Digital Indicator displays for both flow rate and total volume to be provided and to be mounted
inside the panel. The digital indicator unit should be powered with external 220 volts AC power
Page 98 of 113
LANDSCAPE SPECIFICATIONS
supply and rechargeable Lithium battery. The unit can run of internal or external power and should
have automatic changeover switch which is activated during a power failure. The battery will be
automatically recharged during normal mains operation.
Flow sensing and control system should sense high flow rate (above the max. flow rate for any
combination of valves) and close the butterfly valve in filtration chamber.
All control panels should be assembled by one of the following approved companies:
1 Blackburn Sterling.
2 SCIENTECHNIC.
3 Bin Ghalib.
4 ABB.
5 DANWAY
6 Al Ghandi Switchgear Industry
Electrical control panels for this project shall be constructed of mild steel sheet enclosures with
stainless steel 316 lock and hinges front opening door having a protection range not lower than IP
65 according to IEC and to be class 3. The panel shall have provision for connecting to generator.
The Control Panel For Filtration Chamber shall be Form 2 and that for pumping station ,Class3 (
Form 4 ) and all the control panels to be fixed in GRP kiosk on concrete base (300 mm above
ground level)
The panels to be fixed inside the filtration chamber as per the Engineer’s approval and shall include
the followings:
1 Irrigation pump control system
2 Flow meter displays.
3 Sump pump control system
4 Exhaust fan control.
5 Butterfly valves control gear.
6 Lighting system.
Panel shall have main circuit breaker for the power main and earth leakage protection. Each power
circuit should have circuit breaker, earth leakage protection and power indication lamp. Each switch
and light on the exterior of the panel shall be marked with an engraved plastic name identifying
each item. Trunking shall be used when wiring the panel. The panels shall have serially numbered
terminals for terminating all incoming and outgoing cables. Anti-condensation heaters should be
provided inside the panel. The panel shall be installed above Pump or filtration chamber. Pump or
filtration system Control panels shall strictly be as per DEWA and /or DM standard Specifications
in all aspects and subject to the Engineer’s approval. The pumping system controls shall be initiated
from the main pump controller up on defined fall of pressure in the main line network. The pumping
system shall shut down at low flow, under pressure, low water level and motor trip.
None of the pumps shall be operated if water in the tank is below a pre-determined suction level.
This shall be achieved by means of a low-water level shut-off sensor. The sensor shall shut down
the pumps when the water level falls below the situation level and start the pump again when water
level ascends 30cms, above the suction level. The sensing probes shall have working voltage less
than 24 volts AC or as specified elsewhere.
The duty pumps shall start either based on a timer or from a signal given from remote controllers.
The assist pumps shall start and shut-off according to the demand of flow. The irrigation duty pumps
shall start with a time lapse of 0.30 minutes with an electronic timer. The jockey pumps shall operate
by switching in and out according to demand. Pumps shall be controlled by pressure switches,
which shall be adjusted to provide a CASCADE” operation, depending on the amount of water
required on the field. The jockey pumps shall shut down automatically once the main pump starts.
Page 99 of 113
LANDSCAPE SPECIFICATIONS
Automatic change over to the standby pumps shall be provided. All parameters shall be set to the
requirements of the system and to the approval of the engineer.
Manual and automatic operation of sump pump is to be provided. The sump pump is to be
controlled by a water level sensor. The pump shall start when level in sump rises to a pre-
determined level and shall stop when level falls below a pre-determined level. During abnormal rise
of water level, the sump pump should run continuously and should the pre-set danger level of
water is reached, an alarm system is activated. An audible alarm circuit is be to linked to the sump
pump control panel. Automatic on-off for sump as required by sensing water level in the pump
house shall be provided.
Permit pumps to shut-off when the discharge pressure in main line falls below 1.0 kg/cm² for a
period of one (1) minute continuously. Signal to be given by a pressure switch installed downstream
after check valve. Pressure switch shall work only on “automatic”. A pressure switch of the
diaphragm type with minimum cut-in pressure of one (1) kg/cm² and a cut-off pressure of four (10)
kg/cm² shall be used. All other systems and components of panel shall be as per DM and DEWA
standards. The contractor shall include for all associated costs for all required additions and
modifications to match the electrical installations and programming to DM and DEWA standards
and requirements.
Same as above to accommodate the control system and injection pump switch gear.
The irrigation controllers shall be solid-state type and shall have 220 volts power input and 26.5
volts, 50 cycles.
If the input voltage to the controller is other than 220 volts AC, the Contractor must ensure
continuous regular voltage to controllers equivalent to the input voltage marked out on the
controllers. If voltage fluctuations are noted, controllers must be equipped with automatic voltage
regulations.
The controllers shall have 24 stations as mentioned on drawings. The controller should be
weatherproof lockable cabinet with minimum one meter high Stainless steel pedestal. The pedestal
to be fixed on proper concrete base, 300mm above ground level. Irrigation Controller shall be
installed in GRP Kiosk enclosure.
The two way signal cables from the controllers shall be laid up to the Main electric control panel for
future use. The power supply for all Controllers on a filtration chamber should be taken from single
source.
Power supply to the controllers should be by armoured cables. No conduit is required for these
armoured power cables. Contractor to provide calculations for cable sizing for the Engineer’s
approval. Size of the power cables should not be less than 2.5 mm2 x 4 core.
The Contractor has to check the number of electric valves connected to each station, if number
exceeds the manufacturer’s recommendation a multi-station relay has to be included with the
corresponding controller. Lightning protection shall be provided for all controllers.
Allow cascade flushing of filters if differential pressure exceeds 0.30 bar, or on command from
central controller. Flush time to be adjustable. Control panel to be provided with a flush counter
(resettable) and a selector switch to allow manual flushing, and/or cancelling each automatic
function.
Controller to be provided with circuits to flow switch mounted in the flush lines to detect any flow of
water after the flushing cycle has ceased, and linked to the alarm circuit, time delay 2.00 minutes.
The controller will be mounted inside the electric control panel.
Extra heavy duty industrial type Aluminium body exhaust fan size 18" to be fixed in the
Pump/filtration chambers, minimum three nos. of 8” dia GRP vent pipes to be fixed in each
Pump/filtration chamber for circulation of the air in the chambers.
The isolation valves shall be in R.C.C. chambers as shown in the detail drawings.
The Contractor has to propose a design for chambers to suit the site conditions.
The covers shall be double triangular heavy duty ductile iron cover with clear opening 600x900
mm, bitumen epoxy coated. The cover should be loosely coupled by stainless steel bolts and nuts.
Covers to be painted green and should as per DM standard. The word of "IRRIGATION" in English
and Arabic should be casted on the covers.
Valve chambers with depth more than 1.5 meters shall be provided with a heavy duty aluminium
ladder.
There shall be insertion type flow sensor to record real time flow in the tertiary irrigation network.
A R.C.C. filtration chamber has to be constructed by the contractor in this contact. Chamber is
required for filters arrangement, flow sensors and fertilizer injection system .
The filtration chambers shall be in reinforced cement concrete (with Proper finishing including
painting and lights) as per detailed drawings and shall be as per DM general specifications.
The access cover for filtration chamber shall be minimum 1200x1400mm of heavy duty aluminium
checkered plate with stiffeners and lifting handles and painted green. The cover should be lockable
and easy to open and should be tight to prevent dirt or soil into the chamber. The contractor has to
propose a design for the chamber to suit the site condition.
The filtration chamber shall be provided with two spare electrical sockets (Capacity 15 KW) for
future use.
Flushing pipe line from Filters and discharge line of sump Pump to be ended seperately ten meters
away of the chamber in 2m x 2m x 3m soak pit filled with gravel or to be connected to the nearest
storm water system as per Engineer’s approval
The contractor must provide the engineer with structural, mechanical and electrical shop drawings
for approval. These drawings must be presented for approval upon award of contract.
Chamber Identification plate is to be made to sizes shown on drawing and shall be of "DMiralty
Brass" BS Code No.CZ III BS 2871. The plate to be 5 mm thick with two lags 150 mm long 20 mm
wide by 5 mm thick welded at the back. The plate is to have engraving 2 mm deep as shown on
the drawings for each relevant chamber.
The electrical control panel shall be constructed of mild steel sheet enclosures with stainless steel
hinges and lock front opening door having a protection range not lower than IP 55 according to IEC
and to be class 3. The panel shall have provision for connecting to generator.
The contractor should provide single phase and three phase waterproof power sockets (one each),
and three fluorescent light for filtration chamber.
The fertilizer/chemical injection unit shall comprise of 300 litre rigid polypropylene make tank with
reinforced ribs mounted on a pedestal and dosing pump with a range of 2 to 20 l/h, calibrated in 2
l/h or less increments, complete with valves and fittings, filters and connecting pipes.
The elevated make up tank shall have level marks molded into the side of the tank. A second outlet
complete with stop-cock shall be provided in bottom of tank for draining and washing out. An
agitator shall be provided to ensure that there is no separation of liquids. The agitator unit shall be
removable to allow access for cleaning the tank.
The dosing pump shall be constructed of corrosion resistant material, close coupled to a suitable
splash proof electric motor. The unit shall have an operating head of 70m over the full flow range.
The injection rate shall be set manually to required flow.
7.31 Ducting
uPVC ducts shall be class C to BS3506. Asbestos cement ducts shall be class 12, to ISO-R-160
made with sulfate resistant cement bitumen coated from outside.
Duct markers shall be used and should be aluminium and shall clearly indicated the name in Arabic
and English : IRR " .
7.32 Execution
Prior to trenching all services crossing or running close to the line of the trench shall be identified
and exposed. In addition, the line of the trench shall be swept using an approved detection device,
capable of detecting both live and 'dead' cables.
Trenches shall be made as narrow as practicable, but not less than the pipe diameter plus 300 mm,
and shall provide sufficient room for laying jointing and testing. The width of the trench at the crown
of the pipe shall not exceed the pipe diameter plus 600 mm. Sheeting, bracing and shoring shall
be used to provide for the safety of all personnel for all trenches.
The trench bottom shall be composed of stable uniform sand with no protuberances that might
cause point loading of the pipe. The trench formation shall be trimmed to an even finish which will
provide continuous support for the pipe. Additional excavation shall be carried out at the position
of the pipe socket to ensure proper joint assembly and pipe support.
If the existing formation is unsuitable for direct laying, the pipes shall be laid on a bed of
imported sand 100 mm thick ( minimum ). This sand may be sourced from sieved excavated
material, but should not contain any particles larger than 5 mm, and should have good self-
compacting properties.
De-watering shall be provided to remove any surface or ground water entering the excavations.
Ground water level shall be maintained at least 100 mm below the bottom of each excavation.
The trench should not be excavated more than 3 days production rate in front of pipe laying.
Pipes shall be center loaded leaving joints exposed within three days of laying. Initial back-fill shall
be by hand in 300 mm lifts, and carried out in such a manner as to ensure adequate support
under the pipe and distributed evenly to ensure there are no voids under or to the side of the pipe.
Back-fill material shall be sand and shall be compacted by water tamping once the level of back-fill
reaches the crown of the pipe.
For pipe sizes 4" (dia) and above , back-fill material shall be deposited in 300 mm lifts in general
areas and compacted to relative degree of compaction of 95% ( by approved method )and tested
by large pouring method. In paved areas layers shall be 150 mm and back-fill shall be compacted
layer by layer to reach relative degree of compaction of 95% to DM roads department approval.
Mechanical compactors shall not be used until there is a minimum of 300 mm above the crown of
the pipe.
Back-fill material shall be sand and shall not contain any particles larger than 25 mm for the
first 100 mm above the pipe; thereafter back-fill material shall contain no particles larger than 50
mm.
Whenever ambient temperatures exceed 35 degrees centigrade, center loading for PVC pipes
greater than 3" shall only be carried out in the early morning , or shall alternatively be preceded
by cooling of the pipe string by application of water.
For pipe sizes of 3" and below compaction as mentioned is not required.
PVC pipes shall be stored on site in a covered pipe store. Pipe stacks shall not be greater than
seven layers or two meters high. Pipes shall be shielded from the sun at all times and shall be
placed on a sand bed, or on supports at least 75 mm wide and placed not greater than 1.50 m
apart; side supports shall be similarly constructed and placed not greater than 3.00 m apart. The
pipe store shall allow for circulation of air. Rubber sealing rings shall be stored inside closed boxes
in a shaded place, and shall on no account be exposed to sunlight for more than a few hours.
Pipes shall be transported on the site on a flatbed trailer, and should never be dropped or dragged
along the ground.
Spigot ends of all pipe shall be chamfered to a depth of half the wall thickness at an angle of 15
degree. Pipes cut on site should be cut square to the pipe axis with a fine-toothed saw. All swarf
and burrs should be removed from the pipe prior to assembly of joints. Pipe cutters may be used
for 1" pipe. Spigot insertion depth shall be measured and marked on all pipe larger than 3" using
indelible ink to allow checking at a later date.
Ring joints shall be made using an approved non-ionic lubricant compatible with the sealing ring .
Pipes sized up to 8" may be jointed using a crowbar and a timber protection piece, joints larger
than 8" shall be assembled using a clamped lever device. Before back-filling joints shall be checked
to ensure that the spigot is inserted to at least 90% of the socket depth in all circumstance.
Solvent welding shall be carried out by experienced fitters who fully understand the technique, and
have successfully made a solvent weld joint in the presence of, and to the approval of the Engineer.
Helpers brought up on site may only be allowed to make solvent joints after inspection of their
technique by the Engineer.
Solvent welded joints made on pipe 3" and above shall be preceded by lightly sanding both surfaces
to be jointed using a medium glass paper or clean emery cloth. Solvent "cleaner" shall be applied
to all mating surfaces using a dauber or brush (application using rags will not be allowed). After
ensuring that mating surfaces are clean and dry solvent cement shall be applied in sufficient
quantities to ensure bonding, but not in excessive quantities that will leave appreciable residues
inside the pipe.
Brush size shall be 3/8" round for 1" pipe, 1" flat for 1-1/2" pipe and 2" flat for larger pipes. Solvent
cement should be applied by two people simultaneously for pipe 3" and above. Immediately after
application of solvent cement pipes shall be pushed together in a smooth continue motion, that
ensures that the spigot is at least 90% inserted into the socket, the joint shall be held for a
minimum of 20 seconds after insertion, and then surplus cement shall be cleaned from the outside
of the pipe using a rag or paper. Solvent cement and cleaner shall be provided in tins with brush
or dauber fixed to the lid of the tin. The lids shall be firmly closed at all times except when the joint
is being made. Any tins of solvent cement that become viscous or hardens shall be disregarded.
On no account shall brushes on which solvent cement has hardened be used for making joints. All
fitters involved in solvent cement jointing shall be provided with safety gloves that prevent solvent
touching the skin, gloves shall be kept in good condition and shall be replaced periodically.
Jointing shall not be carried out in windy conditions (wind speeds greater than 18 km/hour). All
lines shall be capped at the end of the day’s work.
uPVC mains with sizes 8" and above shall have minimum cover of of 1.2 mete over the top of the
pipe. Mainline sizes 6" and below should have minimum cover of 1.0 meter. Pipes should be laid
in such a way it should have minimum clear space as per DM standards & requirements from other
services and trees.
Please note that uPVC lateral lines should have minimum cover of 60 cm over the crown of the
pipe. laterals should be laid in such a way it should have minimum clear space as per DM standards
& requirements from other services.
Minimum distance of uPVC Lateral lines for drip and bubblers system from the centre line of trees
shall be as follows:
Surface drip line pipe shall be installed above ground as shown on the drawings and shall be
anchored to the ground with staple stake at every 10m.
Subsurface drip line shall be installed 150mm below the top soil level as shown on the drawngs
and shall be laid on top of the layer of landscape roll on the lawn area.
7.36 Valves
Butterfly valves, Gate valves, air valves and solenoid valves shall be installed as shown on the
drawings. Installation shall be neat tidy. Valve boxes shall be installed level and aligned with the
pavement.
Cover of the valve chambers and valve boxes shall be level and aligned with pavement as
instructed by the Engineer.
Equipment shall generally be installed to achieve optimal irrigation efficiency and to accommodate
the requirements of the landscaping. All irrigation equipment such as spray heads and emitters
shall be installed only after all the laterals and risers are flushed thoroughly. The half circle spray
heads should be installed at least 50 cm away from kerb stone.
The contractor has to follow strictly the instruction of the suppliers and provide the Engineer with
all technical information related to these equipment.
7.39 Testing
The length of test section shall be maximum 500 m or as directed by the Irrigation Engineer. The
pipe length to be tested may be blanked off using a blank iron or steel flange previously drilled and
tapped for test equipment connection and strutted as necessary against end thrust. The blank
flange may be attached to the pipeline by a V.J. flange adopter or similar fitting.
Testing should not be carried out against closed valves. All charging and testing should preferably
be carried out from lowest point of the under test section and all testing equipment should be
located at this point.
The pressure gauge also should be located at the lowest point or adjustment must be made for the
level of the pressure gauge relative to the pipes location.
Prior to testing, care should be taken to ensure that all anchor blocks have attained adequate
maturity and that any solvent welded joints included in the pipe system have developed full
strength. Correct support and anchorage of any above ground sections of the pipeline is also
necessary. Underground pipelines should be back-filled, taking particular care to consolidate
around lengths which may have been deflected to negotiate curves.
The main pipe should be charged slowly, preferably from the lowest point with any air cock in the
open position. They should be closed in sequence from the lowest point only when water visibly
free from aeration is being discharged through them.
Satisfactorily charged, the main should be allowed to stand overnight to allow any residual air to
settle-out . Re-venting is then necessary and any water deficiency should be made-up.
Pressure testing can then begin by pumping slowly until it reaches to 9 bar. This pressure shall be
kept for 24 hours.
A permissible water loss of 3 litters per 1000 m length per 25 mm nominal bore per 24 hours shall
be considered reasonable for PVC pipe.
For AC pipes the pressure test should be according the manufacturer's recommendation.
7.39.2 Painting
Dry film thickness (DFT) of all painted valves and spool pieces shall be measured on delivery to
site. DFT shall be the average of no less than three measurements, with no one measurement less
than 75% of nominal average DFT.
Holiday tests shall be carried out on internal and external surfaces on delivery, and also on external
surfaces prior to back filling.
All crossings across major roads/dual carriageways and U-turns shall be either through ducts or no
dig method .
Where it is necessary to cross roads in order to complete the work, the Contractor should first
obtain N.O.C. from service companies and submit where appropriate for road cutting to DM's road
Department. The Contractor should follow strictly DM's regulations. Ducts to laid at least 100 cm
below Asphalt surface.
Road cutting will only be permitted if it can be proved that all forms of non-desruptive method of
crossing is possible. In the event of road cutting is permitted, the reinstatement of wearing course
shall be extended to 15m from each side of the disturbed edge of trench.
Traffic diversions shall be carried out in accordance with the requirements and approval of Dubai
Municipality Roads Department & Dubai Traffic Police. If trench is left open overnight , proper lights
& caution lights shall be provided.
Trenches to be back filled with fine gravel around ducts to minimum depth of 50 cm. Remaining
depth to be back filled with 15 cm thick layers of Subkha or sub grade material with minimum 30%
CBR properly compacted & tested by approved Independent Laboratory.
Road crossings for the main and lateral pipes or cables should be carried out preferably by
horizontal drilling. Wherever it becomes impossible to drill because of existing services or any other
reasons acceptable by Irrigation Engineer, the road cutting shall be done as specified above.
Any tiled area damaged during construction, drilling or road cutting should be reinstated.
Separate ducts shall be used for irrigation pipes, electrical cables, control wires and maxi-com
signal wire.
At each bend, diversion or at the end of pipeline, a thrust block shall be provided. Heavy duty
polyethylene sheet shall be used to wrap the pipe at the point of contact between pipeline fittings
and the thrust block. Design of the thrust blocks shall be done by the Contractor and to be approved
by the Engineer.
All the electrical installations shall operate at a system voltage of 380 volts AC three phase four
wire 50 cycles.
The entire works shall be carried out in strict accordance with this specification and instruction as
issued by the Dubai Electricity and Water Authority.
Each electrical equipment, cable and complete system shall be thoroughly inspected and tested
before finally placing in service under the full responsibility of the Contractor. All tests shall be
made in compliance with respective regulations, recommendations and standards. Any
modifications or repairs deemed necessary upon completion of the tests shall be executed at the
Contractor's expenses. Further tests shall be carried out on any modified or repaired equipment
until it is certified trouble free and acceptable for its intended service. All testing shall be
demonstrated to the Engineer in a manner to be agreed later.
All electrical equipment under these contract documents shall have passed adequate routine
factory tests. Field tests shall be made by qualified personnel, approved by the Engineer. The
Contractor shall furnish all apparatus, material, labor and facilities for performing the required tests.
Unless otherwise specified the individual electrical equipment shall undergo the following tests in
accordance with the IEC recommendations or other approved standards.
In workshop:
- High voltage test.
- Check on mechanical function.
- Pre-test of functional sequences.
At site:
- Visual inspection.
- Insulation test (megger test).
- Check of functional sequences.
The Contractor shall submit to the Engineer acceptance test certificates of all tests carried out
in his workshop including all measuring data and subsequent evaluation.
The following tests are to be carried out for all cables as a minimum:
- Resistance measurements
- Insulation test with specified AC power frequency test voltage
- Insulation resistance measurement of every individual cable length at site
- Electrical continuity test for all controls.
The following test shall be carried out upon completion of the earthing system:
- Measurement of the conductance of the earthing wires
- Measurement of the intermediate resistance of the earthing electrodes
The contractor shall provide at his expense the necessary qualified personnel and measuring
instruments of the above measurements.
Panels shall be installed onto concrete bases (300mm above ground level). Control wire shall be
color coded, and provided with tags. Control cable shall be bundles and tied with a plastic cable
tie at least every 5 meters, installation of cable bundles in conduit shall be carried out in such a way
as to preclude the possibility of stretching the cable, or damaging the insulation. All cable splices
shall be waterproof, and made inside valve or conduit boxes, leaving at least one meter of spare
cable neatly coiled at each joint, and bend.
Panels shall be individually earthed by an approved copper clad grounding rod minimum length 15
mm x 3 meter rod driven down into the water table and connected to the controller by a brass clamp
and a 4 mm2 grounding wire as per DEWA and engineer approval.
All stages of the control system installation shall be supervised by a factory trained engineer,
recommended by the manufacturer who has previously been in charge of all aspects of installation
of a similar control system and approved by the engineer.
The field controllers shall be installed as per approved location on the drawing. Controller shall be
installed on the concrete bases (300mm above ground level) and shall be in pedestal enclosure as
specified, control wire shall be color coded, and provided with tags.
Control cable shall be bundles and tied with a plastic cable tie at least every 5 meters, installation
of cable bundles in conduit shall be carried out in such a way as to preclude the possibility of
stretching the cable, or damaging the insulation.
All cable splices shall be waterproof, and made inside valve or conduit boxes, leaving at least one
meter of spare cable neatly coiled at each joint, and bend.
Controllers shall be individually earthed by an approved copper clad grounding rod minimum length
15 mm x 3 meter rod driven down into the water table and connected to the controller by a brass
clamp and a 4 mm2 grounding wire. Decoders, encoders, and terminators shall be installed in
plastic valve boxes, and their function and reference number shall be clearly indicated in indelible
ink.
7.48 Flushing
7.49 Fieldwork
Commissioning of fieldwork and equipment shall include all works required to bring the system into
service, and to make sure that it is operating efficiently, and shall include but not be limited by the
following:-
A full cycle shall be run four times, and total system flow rates shall be recorded, and stations shall
be adjusted in accordance with the instructions of the Engineer, based on the results of these trials.
Trials shall only be carried out after all valve's pressure have been adjusted. During these trials
main line head losses shall be verified by installing pressure recorder at the start and the end of
the main line.
Three standard irrigation schedules shall be developed in accordance with the requirements of the
Engineer, and tested per controller schedule as above.
Each particular function of the system shall be demonstrated in accordance with an approved
commissioning procedure developed by the contractor.
Operational and maintenance manuals shall be prepared and submitted for approval in draft form
prior to commencement of commissioning. Manuals shall contain comprehensive operational
schedules, recommended spare parts lists, manufacturers' operating data, Catalogues and
exploded parts diagrams where applicable for the entire irrigation scheme. The materials used for
the system shall be listed in the manual.
Manuals shall be revised in accordance with Engineers instructions, and reflect, and record the
results of the commissioning procedures described above. Three bound copies of the manual shall
be delivered to the Engineer prior to the date of substantial completion certificate issuing.
The contractor must submit As Built drawings for all works included in this contract. Completion
certificate will not be issued unless the contractor submits the As Built drawings.
Three complete set of ‘As Built’ drawings along with a negative and all diskettes should be
submitted before handing over of the project.
All as-built drawings to be of DM Drainage and Irrigation Department standard size and prepared
using Microstation for Windows version 5.5 or latest). As built of Mainline Layouts to be prepared
on DM Survey sheets (scale 1:1000) as per the requirements of DM Drainage & Irrigation
Department.
Note: Contractor to check and include all existing irrigation system (along with existing filtration
chambers) in the as-built drawings
The Contractor to remove the existing soil in the proposed plantation area up to 60cm depth &
dispose-off and refill the area with fresh sweet soil. The Contractor has to refer to the landscaping
drawings. Levelling and contouring shall be done as per the Landscape drawings and to the
approval of the Engineer. The minimum acceptable depth of sweet soil filling in proposed planting
area is 50 CM.
Contractor will remain responsible for maintaining the levels of sweet soil against wind erosion till
the final hand over of the project.
Contractor to make tree pits and fill them with fresh sweet soil. The size of tree pits to be as follows:
- Pits for Date Palms: 2m x 2m x 2m
- Pits for Ornamental trees: 1.5m x 1.5m x 1.5m
- Pits for shrubs: 1m x 1m x 1m
The existing sweet soil should not be used for filling the top 50 cm layer and tree pits.
7.53.2 Contouring
The Contractor has to level the landscaped areas and bring it to the contours as shown in the
landscaping drawings. Contractor to make arrangements to prevent the loss/ drifting of soil due to
wind. Contractor will be responsible for maintaining the levels and contours of the sweet soil till the
Final Handing over of the project.
7.53.3 Gravel
The Contractor must use gravel size 20-40 mm / or as specified to fill the areas as shown on
landscape drawings. Depth of filling with gravel shall be at least 100 mm.
The contractor to modify all the existing chambers in the proposed Landscape area (if required); to
the approval of the Engineer and the concerned service authorities; in order to match the proposed
landscape levels.
8 ARCHITECTURAL FEATURES
All plant and ancillary equipment’s shall comply with the requirements of the contract documents.
The scope as given here under this Section and other relevant related section is the absolute base
minimum requirements of general form and nature to be complemented with the supply of additional
equipment so as to complete the installation in accordance to the best possible international
standard and to the satisfaction of the owner/engineer.
The Contractor should specifically note that the supply of equipment and installation are to be
completed in all respect as specified in the contract. Any additional equipment and works that may
be involved or required to complete the installation as specified and that are required to satisfy the
required performance of the feature shall be supplied, installed and commissioned without any
additional cost or delay to the Contract.
The Main Contactor shall engage a specialist sub-contractor to affect the complete works under
this section to the satisfaction of the Owner/Engineer
The Contactor shall provide proof of Manufacturer’s warranty for all site furniture items. A minimum
of 5 years warranty shall be provided.
8.1 Balustrade
8.2 Railing
All plant and ancillary equipment’s shall comply with the requirements of the contract documents.
The scope as given here under this Section and other relevant related section is the absolute base
minimum requirements of general form and nature to be complemented with the supply of additional
equipment so as to complete the installation in accordance to the best possible international
standard and to the satisfaction of the owner/engineer.
The Contractor should specifically note that the supply of equipment and installation are to be
completed in all respect as specified in the contract. Any additional equipment and works that may
be involved or required to complete the installation as specified and that are required to satisfy the
required performance of the feature shall be supplied, installed and commissioned without any
additional cost or delay to the Contract.
The Main Contactor shall engage a specialist sub-contractor to affect the complete works under
this section to the satisfaction of the Owner/Engineer
The Contactor shall provide proof of Manufacturer’s warranty for all site furniture items. A minimum
of 10 years warranty shall be provided.
1. Dedicated Security IDF (6m2) with minimum dimension of 2m. with standard IDF specifications
2. Supply of Firewall Fortinet FG-40F-3G4G with 3 year support
3. Supply of Cisco CBS220 manageable full POE+ switch (or equivalent to specification, subject to
SMD approval) as per the number of end points and minimum 2 Uplink Ports and dual power
supply with 3 year vendor support
4. Supply and installation of 24U 600 x 800 rack equipped with 16A dual PDUs powered 16A
industrial sockets (one of the PDUs through the UPS)
5. Rackable UPS capable of power the entire rack for at least 4 hours, subject for testing and approval
by Security Department of RTA.
6. Supply and installation of copper and fiber patch panels in Security IDF
7. Supply and installation of UTP structured cabling from Security IDF to security endpoints
8. Supply copper and single mode fiber patch cords
1. Civil containment and Electromechanical works for all Physical Access Control devices
2. Single fire interface module must be provided at S e c u r i t y IDF Room near to the Door
Controllers for integrating Fire Alarm system with Access Control system as per the approved drawing
Note: Main contractor should coordinate directly with Corporate Security engineers for all security
related requirement
1. Access Control Requirements
Contractor shall submit material submittal to SMD and get approval prior to supply any
security equipment.
Contractor shall directly coordinate with SMD Engineers and ensure installations pre-
requisites are complied with RTA’s standards.
All equipment shall be supplied with three year warranty.
Single door controller with two reader interface shall be supplied with single door license.
EM Locks shall be supplied according to the door type and holding force.
EM locks shall be supplied with covered bracket and necessary accessories with built-in
and external door sensor.
EM Locks shall be able to operate in fail safe mode in operations
EM Lock shall have status monitoring using built-in NO/NC SPDT contact rated
1Amp/12-24VDC with LED indicators
EM Locks shall be complied with FR Standards (NFR 60-90minutes)
EM Locks shall be certified by UL, BS476
The Smart Access control Panel with power supply supplies power to the Access Control Module and
peripherals even when the main power supply is interrupted. The internal battery charger keeps the
optional batteries fully charged and checks battery status and performance continuously and
accurately. Smart PSU shall be able to sense power status and battery status to be sent to the Access
Controller when there is an alarm.
PSU Complies with all relevant build and technical quality requirements and offers class 1
security with 3-year warranty.
PSU Protected against short-circuit and can be analyzed remotely using on-board
inputs/outputs.
Automatic battery monitoring, Power consumption monitoring, feed multiple modules.
When the batteries are fully charged, the unit provides emergency power at maximum load for
8-10hours.
Clear status indication – LED indicator lights clearly show all of the status information relevant
to the power supply including batteries.
Power ratings shall be 220VAC-12VDC/5A minimum, light in weight and compact in size.
Inputs to be available : 1monitored, freely definable, intended for voltage-free contact
Enclosure shall be able to be customized according to the specifications and RTA’s standards in
terms of size, color coat, logo, lettering, chassis ID, heat dissipation grills, knockouts, etc.
Access control Panel shall be tamper protected, input shall be volt free dry contact to feed
access controller, key locked, vandal resistant preferably IP65.
Single ACP to serve PSU, door control units, battery, relays, tamper switch and indicators.
1.5 Backup Battery
Specifications
9. Warranty : 3Years
1.6 Siren
Specifications:
1. Model : ROLP/SV/R/D
2. Brand : Eaton
3. Voltage : 9-28VDC
6. IP Rating : IP65/IP66
1. Model : CPK-860A
2. Brand : YLI
4. Colour : ‘Green’ in colour with text “Emergency Door Release” in white lettering.
5. Dual separate contact monitoring type (double pole), providing independent contacts for
6. Emergency Break Glass unit should be sited adjacent to the door on the secure side when the
break glass is activated this should break the direct power to the magnetic lock giving free exit
and an audible alarm should also sound until reset. BG units should not be visible from outside,