0% found this document useful (0 votes)
35 views7 pages

WK 3 Part 1 Workbreakdown Structures

Download as docx, pdf, or txt
Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1/ 7

WORK BREAKDOWN ANALYSIS (WBS)

Work Breakdown Structures and Statements


Work Breakdown Structures and Statements is an established tool for
structuring a project so that all the individual component and elements
are identified in a hierarchical format. It addresses the technical
SCOPE OF THE WORK, to which resources are allocated.
Note: In this course we are concentrating on one project at a time not
multiple projects. With multiple projects, the planning and resource
allocation task can be even more complicated. Complications will
arise when we deal with trade-offs.

WBS are used because they:


 Provide a framework for the organization and management of
the project to understand fully the scope of work involved for
the project
 Provide a framework for planning and controlling
 Breakdown the project into manageable
activities/tasks/components
 Provide a clear view of the project that cover all the works in an
easy to understand way.
 Useful as a quantitative for pricing, allocating responsibilities
and costs, durations and quality and safety related requirements.
In civil engineering, works are breakdown into various key
operations/activities. Work breakdown analysis assists PM in
dividing the overall project into manageable
tasks/operations/activities.

How to do Work Breakdown Analysis


It is an analysis of
1) Segmentalising/grouping the major works (Level/layer 1)
2) Then detailing the sub works under the major works
(Level/layer 2)
3) More work details can be put forward under the sub works.
(Level/layer 3 or 4)

WBS defines;
i. Work to be performed
ii. Identifies the needs of expertise
iii. Assists in selection of project team
iv. Establish a base for project scheduling and control

In developing a WBS, few characteristics should be considering


are:
i. Definable: can be described and easily understood by project
participants.
ii. Manageable: a meaningful unit of work where specific
responsibility
and authority can be assigned to a responsible individual.
iii. Estimateable: duration can be estimated in time required to
complete,
and cost can be estimated in resources required to complete.
iv. Independent: minimum interface with or dependence on other
ongoing elements (i.e., assignable to a single control account, and
clearly distinguishable from other work packages).
v. Integratable: integrates with other project work elements and
with
higher level cost estimates and schedules to include the entire
project.
vi. Measurable: can be used to measure progress; has start and
completion dates and measurable interim milestones.

How do we conduct a WB Analysis?


1) Identify the major components of project (Level 1), which can be
clearly obtained from the scope and the drawings and specifications. Say,
1. Preliminaries
2. Building 1
3. Building 2
4. Drainage Work
5. Road Work
6. Water Work
7. Sewer Work
8. Landscaping, etc

2) With Layering System, breakdown the work into sub-tasks


2. Building Work
2.1Foundation Work
2.1.1 Piling
2.1.2Hacking of piles
2.1.3 Pile caps

The WBS often appears as an outline with the Level 1 tasks on the
left side and successive levels appropriately indented. It is a
picture of a project subdivided into units of tasks, subtasks. Each
activity has to be properly defined and can be further breakdown
into sub-activity Normally three layers of breakdown are able to
well define the project. Work breakdown Structure is the end
product of the WBA process. In the end, the works required
towards the product/facility are clearly shown.

WBS Format
Project Name:

Phases/Stages

Layer 1 Layer 2 Layer 3 Layer 4


Foundation work Piling Delivery of piles 1 Foundation work
Preparation 1.1 Piling
Driving piles 1.1.1 Delivery of piles
Joining 1.1.2 Preparation
Testing 1.1.3 Driving piles
Pile caps Hacking 1.1.4 Joining
Conreting 1.1.5 Testing
bar bending
formork
Building Ground beam clearing
Concreting
bar bending
formork
slab

Column

More Examples of WBS format:


Layer format

Column/Level format
Level 1 Level 2 Level 3 Level 4
Construction of Temporary Retaining
Bus Transit Works System
Station Soil
Improvement
Excavation
Permanent Piling
Works Sub Structure Pile Cap and
and SuperStump
Structure Ground Beam and
Works Slab
Column
Roof Beam and
Flat Roof
Architectural Brick laying
Works Plastering
Painting
Tiling
M&E Works Plumbing
Lighting
Ventilation
Fire protection
External Works Drains
Access road
Testing and RI Inspection
Commissioning Certificate of
Statutory
Completion
(CSC)

Hierarchy Format
Work Breakdown is the backbone for any planning and
controlling of time and cost. Not only that schedule of operations
are based on these analysis, estimates and costing revolves around
Work Breakdown and resources (machinery, material and
labour) can be allocated efficiently and accordingly. Quality and
safety plans can be drafted based on WBS.

You might also like