WK 3 Part 1 Workbreakdown Structures
WK 3 Part 1 Workbreakdown Structures
WK 3 Part 1 Workbreakdown Structures
WBS defines;
i. Work to be performed
ii. Identifies the needs of expertise
iii. Assists in selection of project team
iv. Establish a base for project scheduling and control
The WBS often appears as an outline with the Level 1 tasks on the
left side and successive levels appropriately indented. It is a
picture of a project subdivided into units of tasks, subtasks. Each
activity has to be properly defined and can be further breakdown
into sub-activity Normally three layers of breakdown are able to
well define the project. Work breakdown Structure is the end
product of the WBA process. In the end, the works required
towards the product/facility are clearly shown.
WBS Format
Project Name:
Phases/Stages
Column
Column/Level format
Level 1 Level 2 Level 3 Level 4
Construction of Temporary Retaining
Bus Transit Works System
Station Soil
Improvement
Excavation
Permanent Piling
Works Sub Structure Pile Cap and
and SuperStump
Structure Ground Beam and
Works Slab
Column
Roof Beam and
Flat Roof
Architectural Brick laying
Works Plastering
Painting
Tiling
M&E Works Plumbing
Lighting
Ventilation
Fire protection
External Works Drains
Access road
Testing and RI Inspection
Commissioning Certificate of
Statutory
Completion
(CSC)
Hierarchy Format
Work Breakdown is the backbone for any planning and
controlling of time and cost. Not only that schedule of operations
are based on these analysis, estimates and costing revolves around
Work Breakdown and resources (machinery, material and
labour) can be allocated efficiently and accordingly. Quality and
safety plans can be drafted based on WBS.