Planning Engineer Interview Questions
Planning Engineer Interview Questions
We use the quantity we need to track material availability like rubber lining of steel
tanks, coatings project, etc.
Sometimes, we have to use all three methods on a single project to get a more
intensive project updated status.
QUESTION-11: HAVE YOU HEARD ABOUT THE KICK
OF MEETING?
Answer: Yes, I have handled a number Kick of Meetings on different projects &
companies. The kick-off meeting is usually the first meeting of all major stakeholders,
including the Project Manager with his team and the Owner’s representatives. Here, we
discuss high-level overall plans, things like how we will execute, and once things get
clearer as the project goes forward, we do rolling wave planning.
These meetings can be conducted at the new phase that starts during the execution of
the project also.
Here, B is much more productive than A, and hence you need to raise the skill level of
A-type Mason by proper training, etc.
1. Primavera P6 Professional
2. Primavera P6 EPPM (Web Client)
3. Primavera Contractor
Now, Primavera Contractor is the least costly and hence does not have many features
like Enterprise and Admin menus are not available. It is limited to 2000 activities only.
No Microsoft Project XML file support, No Resource Roles, No Enterprise Project
Structure (EPS), and installed only as standalone. Still, it is a great and powerful
application. The interface is as of Primavera P6 Professional. A person that uses
Primavera P6 Professional can handle it with ease.
Now let’s compare the other two major giants Primavera P6 Professional & Primavera
P6 EPPM
EPPM has some edge over Professional as it has more visual aids, can handle more
projects at once, installation is faster, need to be installed on only one machine. In
contrast, professionals should be installed on each machine. Professional is small-scale
as compare to EPPM as it only can handle 100,000 activities. EPPM has more graphs,
dashboards, and pivot tables to help the management review the status quickly. In
contrast, you need to use third-party software like MS Excel to visualize better when
using P6 Professional.
MS Project is user-friendly as most people are familiar with Microsoft products like MS
Excel buy Primavera P6 needs some basic skills/training to operate.
You can read more about these here MS Project and Primavera P6.
QUESTION-41: HOW DO YOU TRACK THE PROGRESS
OF A PROJECT?
Answer: There are three ways to track the progress of a project
Person-hours
Cost
Quantities
Every client has his/her preferences to use any of the above methods, but I use Man-
hours. The reason is it gives me proper control of resources that make tracking quite
easy and effective. One can get realistic manpower requirements for a particular
project.
Many clients prefer cost, but if a Project Manager filters activities with higher costs and
gets it done first, it will show some fake overall progress. But it is good to have a proper
cash flow forecast.
Quantiles are preferred where material management is required mainly, and it also
helps track the KPIs of a construction site. But being a planner, I must say tracking is
tough with this method as you need to track most of the materials.
Different possible scenarios are reviewed, and the best one is merged after approval.
Scenarios Like: If your actual plan is lagging and the Project Manager asks if I provide
you with some extra resources (shift), then how long will it take to catch up?
QUESTION-43: WHAT IS THE USE OF CLAIM DIGGER
IN PRIMAVERA P6?
Answer: The handiest function is to compare two schedules for any change.
The Clam Digger is one more exclusive kind of function in Primavera P6. Although it is a
separate product nowadays, it is a built-in Primavera P6.
Claim Digger helps track any change between two projects in terms of Activity deleted,
added, change in relationships, change is duration, change in cost, change in units,
change is % age complete mainly.
Rolling wave planning is done at the deliverable level. It can be like a weekly lookahead
base or even is done daily on foreman levels. It could be monthly as per the
stakeholder’s requirements. See below for a pictorial view.
QUESTION-45: DIFFERENTIATE AMONG WBS, WORK
PACKAGE, AND ACTIVITY?
Answer: WBS: Work Breakdown Structure- WBS is simply a decomposition of all the
works to complete any project. A WBS is arranged in a hierarchy having a clear and
logical group. A WBS is deliverable-oriented.
Work Package: WP is the lowest level of any work breakdown structure from which we
can manage the cost and duration estimation.
Activity: A discrete, planned portion of work to be performed in a project.
Still, confusing? Let’s understand by example.
Say that we are building a house, and flooring is one of the WBS (depending on the
team how they define WBS in a plan). Now, these different floors are different work
packages. A team performs various activities like soil compaction, waterproofing,
concrete blending, rebars, etc., to complete the floor.
To understand, activities will complete work packages, and that will ultimately complete
the WBS. It’s like a bottom-up scenario.
By the way, I have never used the flag as it is an obsolete type term in Primavera P6
nowadays.
You can read more about How to Review and Submit a Baseline Plan.
QUESTION-48: WHAT ARE THE DIFFERENT MAJOR
TYPES OF DRAWINGS YOU SEE ON A
CONSTRUCTION PROJECT?
Answer: There are four types we normally came across 1. Tender Drawings 2.
AFC/IFC, 3. Shop Drawings, and 4. As-built Drawings
Tender Drawings: The Clients release drawings included in the tender documents for
pre-qualified Contractors. Some time these are also referred to as Design drawings.
Approved for Construction Drawing: AFC – Approved for Construction or IFC –
Issued for Construction both terms are being used for drawings and documents
approved by authorities after review. IFC/AFC is a stamped or marked document, or
you can say one of the controlled documents. Even some people are using the term IFC
as Information for Construction or Instructions for Construction. Another name is IFR –
Issued for Information.
Client/Consultant/PMT issues these drawings to EPC, Contractors, Supplier, Vendors,
Sub-Contractor, or Manufacture.
Shop Drawings: IFC is What to do & Shop Drawing is How to do? It is a drawing
produced by the contractor, supplier, vendor, sub-contractor, or manufacture in a
simplified way to be understandable to the hand executers at site or staff.
These are the most detailed drawings on any project. But before going for construction,
approval is a must from the Clients. Any major change/minor should be addressed.
As-Built Drawings: It shows that how actually the final project has turned out. It
contains all suggested modifications required later on site. These are mainly used for
maintenance teams later on.
QUESTION-49: HAVE DO YOU APPLY FOR AN
EXTENSION OF TIME OR CONDUCT A DELAY
ANALYSIS?
Answer: First, I will gather delay events as per the contract. Like letters we have
sent/received for potential delays before 14 or 28 days of the event to occur (as per
contract), e-mails, minutes of meetings, or any legal document supporting is collected.
Second, I will use these events with facts and figures to perform delay analysis in
Primavera P6 as per the terms and conditions mentioned in the contract. There are
many Delay Analysis Techniques, namely, Impact as Planned, Time Impact Analysis,
Planned vs. As-Built, As-Built For, Windows Analysis, etc.
Once the second step is completed, I will evaluate overhead costs, Recheck Equipment
Warranties, Material Shelf Life, etc. Finally, present it to the concerned.
I will compile a summary like the one below for top management. All the backups will be
attached to this presentation.
QUESTION-50: WHAT IS THE DIFFERENCE BETWEEN
RESOURCE LEVELING AND RESOURCE
SMOOTHING?
Answer: Both Resource Leveling and Resource Smoothing are Resource Optimization
Techniques. We use these techniques to get optimum results from our resources.
Every schedule is a resource constraint, and during the development, we may find
peaks like in one month/week we need 250 men-counts, but in others, we only need
around 150-200 men-counts. Hence, we will use resource optimization techniques to be
averaged and get a possible smooth graph. The same is applicable to deal with other
resources line Materials, Equipment, etc.
On a construction project, we normally use the following terms for these key
stakeholders.
You can learn more about Recovery Plan & how it is prepared here: How to Make a
Recovery Plan?
QUESTION 62: WHAT IS LEAD AND LAG IN
PRIMAVERA P6?
Answer: Both are the time duration that we can put to wait or accelerate the successor
activity. A lag is a lazy start, and the lead is an acceleration for the successor activity. A
lead is just a negative lag.
QUESTION 63: WHAT IS FAST TRACKING &
CRASHING?
Answer: Both are schedule compression techniques. Once a project plan is lagging,
then we are asked to make a recovery plan. In the recovery plan, we use these
techniques/techniques. In fast-tracking, we put activities in parallel. This increases risk.
But in crashing, we add more resources to cover up the lag. This is not risky, but you
need more budget in this scenario. If you need to accelerate because of the other party
like the client-side, then being a contractor always ensures acceleration. That may have
a higher unit rate than in the actual contract.
QUESTION 64: DIFFERENTIATE BETWEEN GANTT
CHART & NETWORK DIAGRAM?
Answer: Both are project management tools that help the teams to see the project at a
glance.
Gantt Chart displays activities, tasks, events plotted against time. It gives information
like activities start & finish, overlaps among activities. Start and end at the WBS level
and the whole project as summary bars. The length of the bars represents the duration
of any particular activity or task. The network Diagram explains the linkage of activities
that helps to understand the flow of work.
QUESTION 65: HOW MUCH FLOAT IS ALLOWED IN
ANY PLAN?
Answer: There is no hard and fast rule for this, but they say 10% of the total project
duration is allowed as a thumb rule. For example, if the total duration is 300 days, then
30 days float is OK to go. If it is higher, then you need to adjust your P6 logic to
decrease it to the optimum required level. By the way, it depends on the project of the
project.
QUESTION 66: HOW MUCH LAG IS ALLOWED IN ANY
PLAN?
Answer: Lag is undesirable in a plan, so does the lead. Sometimes, lag is allowed, but
they say any activity should be less than half of the total duration of that activity. For
example, if any activity duration is 14 days, then lag should be less than 7 days. Long
legs are highly undesirable. You can adjust by proper logic during sequencing activities.
QUESTION 67: NEW PROJECT MANAGER DID NOT
LIKE YOU DEFINED WBS IN THE APPROVED PLAN;
WHAT WILL YOU DO NOW?
Answer: No problem, I will use the Activity Codes function in Primavera P6 to get the
Both PERT and CPM help the project manager of the stakeholders manage and control
the project outcomes systematically.
We use PERT if we have time priority and cannot delay any. But we use CPM to control
both Time & cost simultaneously.
QUESTION 75: WHAT IS A BANANA CURVE?
Answer: During planning, we load a program with resources like Manhours, Quantities,
and or Cost. Software like Primavera P6, MS Project, etc., can give us two types of
curves for early and late dates. When we combine these curves, it gives us a shape like
a banana. That’s why it is called Banana Curve.
If the project slips below the Red zone, then it is an alarming thing that should be fixed
immediately without any delay.
If the above ratio = 1, it gives them confidence that the critical path is real and project
completion is intact.
If the ratio is <1, the critical path that we derived is consistent. There is a high chance;
the project may fail.
If the ratio >1, the project is in good health, will get completed ahead of schedule.