Module 3
Module 3
"And I'm
supposed to
inspect this?"
Module Objectives
✓ Determine the Minimum Design Metal Temp
✓ Familiar with welding restrictions
✓ Familiar with basic fabrication requirements
✓ Determine Preheat & PWHT temperatures
✓ Know the NDE requirements for new pipe
✓ Evaluate weld discontinuities
✓ Calculate hydro and pneumatic test pressures
•
Materials
✓ Listed Materials: Material "listed" in B31.3 in
either; Table A-1 or Table 326.1.
✓ Unlisted Materials: Mat'ls not "listed" in B31.3
■Use only if they meet the material property
requirements of the Code
✓ Unknown Materials
• Can not be used for pressure containing
components
1 Selection of material to resist corrosion is not
within the Scope of the Code. (323.5)
..• A trt fi
Ashland Oil's Brittle
Failure - 120' Tank
Points 4 & 5 used to be
connected!
Fabrication - Welding
V Qualified Weld Procedure V Welder Identification
• ASME B&PV Section IX • UniquelD or Symbol
• Can accept some Procedures • Stamp each weld, or;
qualified by Others
• Use weld maps
V Welder Qualification
V Tacks weld
• ASME B&PV Section LV
• Can accept Qualifications by
others
✓ Welding Records
• Employer maintain
procedures and performance
records
• Fused with the root pass
• Made by a qualified welder
V Bad weather - don't weld
V Fillet weld sizing
• Figure 328.5.2
•
• Min. weld size 1/8"
-/05 49
•
2—‘111111111111"
I. The arc is initiated.
2. Hot surface expands & distorts the plate
■ Not much since the hot side is much
weaker than the cool side
3. Completed weld, as heat moves away from
weld Weld contracts
4. Completed weld is distorted & has 4
residual stresses
2) The Principle - As the metals cool they shrink A CS weld that is 3/4 " wide
will shrink about 10 mils.
• The base metal is "anchored". As the weld shrinks, the base pulls the
cooling weld. (Tensile Stress)
• At higher temperatures, the weld metal is weak and ductile. It can be
pulled and reshaped to account for shrinkage.
• At low temperature, the weld metal is stronger and less ductile. It is
not easily "reshaped".
• Remaining pull on the weld once cool - "Residual Stresses"
• If Residual Stresses exceed, strength of weld — Crack
•
• Used to relieve detrimental effects caused from welding
• PWHT temps: Use Tables 331.1.1 & 331.1.3 (Exceptions)
• Heating & Cooling Rates: 331.1.4 (600 • F/hr)
• PWI-H- zone: Width is at least 3 times wall thickness
• Partial HT: Minimum overlap of 1'
g. 0.750" thick, P-1 material, 0.1% Carbon dvo need -11) Pftheet 111110
Examination
1,4 Category D RT Criteria; Table 341.3.2
• Some visual • Dr = wall thickness
• "and" means "lesser of values"
I( Normal Service
✓ Progressive Sampling
• Some visual: materials,
fabrication & assembly • Random Exam Reject
• Take 2 more
• Visual: 5% of all welds
• If these are OK, repair & stop
• RT: 5% of circ weld • If any defects, then
1 Severe Cyclic • Take 2 more for each reject
• If these are OK, repair & stop
• Visual: 100% of
• if any defects, then
Fabrication & assembly
• Exam all or Repair all
• RT: 100% of circ welds • Only those represented by
• MT/PT: All socket-welds this Random Exam
1) A new Normal Service seamless pipe is fabricated. The wall thickness is 0.500" For the
circ welds, determine the maximum allowed dimension for the following discontinuities.
Pressure Testing
17 Purpose of testing Hydrotest
• Find leaks in joints
• Create higher stress than 1.5Px Sr
the operation stress Pr —
• Minimize the risk of brittle
fracture while in-service Pneumatic test
1( All new pipe is tested
Pr =1.I 11
• Cat D - Service Test
NAHA = 0.5 PT OT 25 psig (lesser)
✓ Minimum Hold Time
• 10minutes PRA" = 1.1PT OT PT + 50 psig (lesser)
Plospect = P
"Joints - Uninsulated
() )en Book
1. What is the test pressure for a piping system that will be tested with air? The system is designed
for 400 psig at 600 °F, pipe material is A 106 gr. B.
a) 440 psig
b) 476 psig
c) 509 psig
d) 518 psig
e) 600 psig
f) 694 psig
a) 68 °F
b) 25 °F
c) 33 °F
d) 0 °F
e) -3 °F
f) -10 °F
g) -30 °F
Material: Carbon Steel - A-I06 Gr. B with maximum Carbon content of 0.12%
PP
Wall Thickness: 1.25
a) 10 °F
b) 50 °F
c) 95 °F
d) 200 °F
e) Preheat is not required
4. A pipe is made from A106 Gr B material. A preheat of 50 °F is performed. The weld is made
with multi-layers. Which of the following is correct pertaining to postweld heat treatment?
5. What is the quality factor "E" for a pipe with an electric fusion long weld that is single welded and
has been spot radiographed?
a) 0.60
b) 0.80
c) 0.85
d) 0.90
e) 1.00
f) designer's judgment
7. A new pipe circ weld is made with 8 NPS Schedule 40 pipe. Determine the maximum allowed
limits for the following weld discontinuities. Pipe is considered Normal Service.
a) length of crack
b) length of lack of fusion
c) dopth of inoomploto panotrution
8. A pneumatic test is conducted on a new pipe system. The design pressure for this pipe system is
80 psig. Determine the following pressures.
10. Calculate the minimum hydrotest pressure for the following pipe systems:
a) Design Pressure 100 psig @ 500 °F, Material A-106 Gr. B
b) Design Pressure 400 psig @ 800 °F, Material A A-672 Gr. C70
11. Calculate the pneumatic test pressure for the following pipe systems:
a) Design Pressure 200 psig @ 600 °F, Material A-106 Gr. C
b) Design Pressure 400 psig @ 800 °F, Material A A-672 Gr. C70
12. A pipe is being replaced. Calculate the most cost effective pipe schedule for this system. Material
is A-106 Gr. B. Line size is 6 NPS. Design Pressure is 500 psig @ 700 °F. The corrosion
allowance is 0.125".
13. A blind is to be installed into a piping system. Calculate the plate thickness to order for this blind.
Material is A-516-60. Gasket ID is 12.5". Design Pressure is 300 psig @ 400 °F. The corrosion
allowance is 0.125".
14. Determine the thermal growth of a carbon steel pipe that is 600' long pipe and operates at 400 °F.
15. A piping system is fabricated from a P# 5B Group I material, that has a Tensile Strength of 70 ksi.
The wall thickness is 1.5" thick. Determine the following:
b. PWHT Temperature
1. During fabrication, how many welds should be radiographed for a pipe in a Normal Service?
a) 5%
b) 10%
c) 100%
d) Depends of flange class rating
2. If a defect is found when radiographing a pipe weld, how many follow-up radiographs should be
taken?
a) One
b) Two
c) Four
d) Number based on Inspector's judgment
3. Which of the following discontinuities are never acceptable when fabricating a normal service
piping system?
a) Lack of fusion
b) Incomplete penetration
c) Undercutting
d) Slag inclusion
5. The maximum inspection interval for a relief device in normal services is:
a) 3 years.
b) 5 years.
c) 10 years.
d) lesser of 1/2 life or 10 years.
12. The remaining life on a Class 2 pipe is 16 years. Determine the maximum inspection intervals?
a) 5 years for both the thickness measurements and external inspections
b) 8 years for both the thickness measurements and external inspections
c) 10 years for both the thickness measurements and external inspections
d) 5 years external, 8 years thickness measurements
e) 5 years external, 10 years thickness measurements
• 13.
0
g)
8 years external, 5 years thickness measurements
8 years external, 10 years thickness measurements
14. During a repair, preheat in lieu of a full PWHT may be considered only:
a) for P1 & P3 materials.
b) if pipe is classified as Category D.
c) if pipe is not classified as Class I piping.
d) Piping operates above 700 °F.
15. When impact testing is required, how many bars are needed for a "set"?
16. When performing a PWHT, the width of the heat affected zone is a minimum of:
a. 1.0" from either side of the weld.
b. 2 times the width of the weld.
c. 3 times the thickness of the pipe wall.
d. 4 times the width of the weld.
e. 6".
17. Determine the following limits for an injection point. The line size is 14 NPS.
a. Upstream circuit limit:
b. Downstream circuit limit:
c. Upstream limit for extensive inspection:
d. Downstream limit for extensive inspection:
18. Which of the following codes can be used to evaluate an in-service crack?
a. ASME B31.3
b. ASME B&PV Section VIII, Div. 1
c. ASME B&PV Section VIII, Div. 2
d. API 579
e. API 651
f. API 2201
19. During welding if there is excessive misalignment between 2 components, then the thicker
component should be taper at an angle not exceeding:
a. 22.5 degrees.
b. 30 degrees.
c. 37.5 degrees.
d. 45 degrees.
20. During a repair a naphtha line at a crude unit about 1000' of piping will be replaced. How many of
the new welds should be visually inspected?
a. 5%
b. 10%
c. 100%
d. None is required if RT is performed
21. Who must approve all repair work at any designated hold points?
a. any inspector
b. authorized inspector
c. piping engineer
d. authorized inspector and the piping engineer
e. authorized inspector or the piping engineer
12. Order Schedule 40 Cale t„„„: = (500 x 6.625) / 2[(16,700 x 1.0) + (500 x 0.4)] = .098"
Add CA: t wk. = 0.098 + 0.125 = 0.223"
Adjust for mill tolerance: t adj = 0.223 / 0.875" = 0.255"
Pick pipe schedule: Schedule 40 (0.280" nominal thickness)
13. Order 7/8" plate t„,u, = 12.5 x sq root of: (0.1875 x 300) /18,200) = 0.695"
Add CA: t = 0.695 + 0.125 = 0.820"
Pick plate thickness: 7/8" (0.875" nominal thickness)
14. 16.8" G = (2.80 x 600) / 100 = 16.8"
15. a) 400 °F
b) 1250 - 1400 °F
c) 1.5 hrs
I. a) 5%
2. b) two
3. a) Lack of fusion
4. c) the threads do not extend within the last thread on the nut
5. b) 5 years
6. b) Class 2 system
7. a) 1 NPS
8. b) 10 minutes
9. c) stainless steel
13. b) 2"
15. 3 bars
19. b) 30 degrees
20. a) 5%