Attachment 3-PCSB Baronia Fire
Attachment 3-PCSB Baronia Fire
Attachment 3-PCSB Baronia Fire
INVESTIGATION REPORT
JULY 29th, 2004
BNP-B
PRESENTATION OUTLINE
1. SUMMARY
2. BACKGROUND
3. THE FIRE ACCIDENT
4. INVESTIGATION TEAM
5. FINDINGS
6. TRIPOD BETA ANALYSIS
7. CONCLUSION
8. RECOMMENDATIONS
2.0 SUMMARY
Production
Manifold
V200
V400
8"
Hotwork Area
Cellar Deck Drip pan sleeve
hole
BNP-B PROCESS LINES TO V-300 INLET LINE
V-200
V-400
L.P Sep @ BNP-B
LP Sep
8" 4"
V-300
2 " Fuel Gas Scrubber Surge Vessel
Liq.Outlet HOTWORK
TEST 4"
PUMPS
HDR
4"
4X COTPs
3"Flange
cracked
opened.
TEST HDR
BNDP-B BNDP-J
SUMP PUMP SUMP PUMP
7.0 TRIPOD BETA V3 ANALYSIS
Active failures:
Safety precautions were not adequately identified in the work
permits.
Drip pan drain system was not checked for blockage.
Insufficient time lapse between hot work completion and
hydrocarbon draining.
7.1 TRIPOD BETA V3 ANALYSIS
Latent Failures:
The draining rate was not properly controlled to prevent excessive
accumulation of hydrocarbon in the drip pan.
Hazards associated with the hydrocarbon draining not adequately
addressed.
Inadequate risk assessment. Procedure to identify the hazards of
hydrocarbon draining to the drip pan was not adequately
addressed.
Failure to check all the process line connections to the header
before draining.
Drive to reduce shutdown durations.
Improper housekeeping of drip pan and drainage system
Change in implementation plan.
Insufficient time allocated to complete hot work activities in the
shutdown period.
Heat residue from the last oxy-acetylene cutting of the 8" line was
not eliminated.
Insufficient fire fighting equipment specified in the SISO.
Escape route for working in drip pan below grating not identified
(confine space).
8.0 CONCLUSION
Prepare Hazard and Effect Register for Baronia and ensure that
hazards associated with hydrocarbon draining be thoroughly
addressed.
Action party: BON by Q1 2005
Include schematic drawing of system to be de-oil, gas free and
isolation system required in PTW. Inventory of hydrocarbon drained
and released must be known.
Action party: Assets/BTS immediate
Implement project on paper (IPOP) for systematic challenging and
optimization of shutdown activities.
Action party: Assets/BTS immediate
Enforce management of change procedure for a change of work
schedule. Highlight requirement in SISO.
Action party: Asset immediate
9.0 RECOMMENDATIONS
Review JHA for hot work activities; highlight danger of heat residue
as source of ignition.
Action party: BTS immediate
Review requirement of fire fighting requirements and escape routes
as specified in the SISO.
Action party: Assets by Q4 2004
Prepare procedure for working inside drip pan.
Action party: Assets by Q4 2004
Prepare drip pan and sump management procedure during
engineering activities
Action party: Assets immediate
END