REQUIREMENTS
Contents
In 1984, the State Government introduced the Flood Prone Land Policy
applicable to New South Wales. The First Floodplain Development
Manual was published in 1986, with Council preparing an Interim Flood
Management Policy 1987 in response to the State Policy and the first
Floodplain Development Manual.
YES NO
YES NO
The extent of flood prone land is determined from flood studies. Council
has adopted flood studies and associated mapping of flood prone land
along the more intensively populated reaches of the Manning River and
its tributaries.
A range of flood planning levels (FPL) may apply depending on the type
of land use and the part of the development in consideration. In
principle, a higher FPL will apply to land uses considered more sensitive
to flood hazards or which may be critical to emergency management
operations or the recovery of the community after a flood event.
Reference Description
FPL = Flood Planning Level (Flood planning levels selected for planning purposes
derived from a combination of the adopted flood level as determined in
floodplain management studies and incorporated in floodplain management
plan)
PMF = Probable Maximum Flood (The largest flood that could conceivably occur
at a particular location).
Objectives
o Ensure the proponents of development and the community in
general are fully aware of the potential flood hazard and
consequent risk associated with the use and development of
land within the floodplain;
o Require developments with high sensitivity to flood hazard (e.g.
critical public utilities) to be sited and designed such that they
are subject to no or minimal risk from flooding, up to and
including the PMF, and have reliable access;
o Allow development with a lower sensitivity to the flood hazard
to be located within the floodplain, subject to appropriate design
and siting controls, provided that the potential consequences
that could still arise from flooding remain acceptable having
regard to the State Government’s Flood Policy and the likely
expectations of the community in general;
o Ensure appropriate development types are compatible with the
Floodplain Development Manual Guidelines in highly sensitive
and/or high hazard classified areas;
o Prevent any intensification of the use of floodways, flood
storage areas or high hazard areas and wherever appropriate
and possible, allow for their conversion to natural waterway
corridors;
o Ensure that design and siting controls required to address the
flood hazard do not result in unreasonable impacts upon the
amenity or ecology of an area;
o Minimise the risk to life by ensuring the provision of appropriate
access from areas affected by flooding up to extreme events;
o Minimise the damage to property, including motor vehicles,
arising from flooding;
o Ensure that proposed development does not expose existing
development to increased risks associated with flooding.
Key terms
Habitable room in a residential situation is a living or working area,
such as a lounge room, dining room, rumpus room, kitchen, bedroom or
workroom. In an industrial or commercial situation it is an area used for
offices or to store valuable possessions susceptible to flood damage.
Floor Levels
• Habitable floor levels to be no lower than FPL4.
• Non-habitable floor levels to be no lower than FPL3 unless justified
by a site specific assessment.
Flood Effects
• Engineer’s report required to certify that the development will not
increase flood effects elsewhere, having regard to:
o Loss of flood storage.
o Changes in flood levels, flows and velocities caused by
alterations to the flood conveyance.
o The cumulative impact of multiple potential developments
in the floodplain.
Evacuation
• Reliable access for pedestrians or vehicles is required from the
building, commencing at a minimum level equal to the lowest
habitable floor level to a refuge area above FPL4. In the case of
alterations or additions to an existing development, this may require
retro-fitting the existing structures if required to support a refuge
area above FPL4.
• Adequate Flood Warning Systems, Signage and Exits are to be made
available to allow safe and orderly evacuation without increased
reliance upon the SES or other authorised emergency services
personnel.
Flood Effects
• Engineer’s report required to certify that the development will not
increase flood effects elsewhere, having regard to:
o Loss of flood storage.
o Changes in flood levels, flows and velocities caused by
alterations to the flood conveyance.
o The cumulative impact of multiple potential developments
in the floodplain.
E4.4 Residential
For additional specific controls for dwellings in rural areas see Part E5.1
Floor Levels
• Non-habitable floor levels are to be equal to or greater than FPL3
where possible, or otherwise no lower than FPL1 unless justified by a
Where site specific assessment.
adverse
• Habitable floor levels are to be no lower than FPL3. In circumstances
impacts on
where construction of a building at FPL3 is likely to have an adverse
adjoining
impact on the adjoining property or the visual amenity of the
properties
location, a variation may be sought.
are likely,
variations • Where the lowest habitable floor area is elevated more than 1.5m
may be above finished ground level, a restriction is to be placed on the title
sought to of the land, pursuant to Section 88B of the Conveyancing Act,
reduce floor confirming that the undercover area is not to be enclosed.
levels no
lower than Building Components and Method
the 1% AEP • All structures to have flood compatible building components below
flood level FPL3.
plus 0.5m
freeboard. Structural Soundness
• Applicant to demonstrate that any structure can withstand the forces
of floodwater, debris and buoyancy up to and including FPL3. An
engineer’s report must be provided.
Evacuation
• A Site Flood Emergency Response Plan is required when elements of
the development, including vehicular and pedestrian access are
below FPL3. The Site Flood Emergency Response Plan should relate
to the landuse and site conditions in conjunction with flood behaviour
up to FPL2 expected to be experienced at the site. The plan should
consider the following specific actions:
o Preparing for a flood;
o Responding when a flood is likely;
o Responding during a flood; and
o Recovery after a flood.
The flood plan should be consistent with the relevant NSW SES
FloodSafe Guide.
Structural Soundness
• Applicant to demonstrate that any structure can withstand the forces
of floodwater, debris and buoyancy up to and including FPL3. An
engineer’s report must be provided.
Flood Effects
• Engineer’s report required to certify that the development will not
increase flood effects elsewhere, having regard to:
o Loss of flood storage.
o Changes in flood levels, flows and velocities caused by
alterations to the flood conveyance.
o The cumulative impact of multiple potential developments
in the floodplain.
Flood Effects
• Engineer’s report required to certify that the development will not
increase flood effects elsewhere, having regard to:
o Loss of flood storage.
o Changes in flood levels, flows and velocities caused by
alterations to the flood conveyance.
o The cumulative impact of multiple potential developments
in the floodplain.
Evacuation
• A Site Flood Emergency Response Plan is required when elements of
the development, including vehicular and pedestrian access are
below FPL3. The Site Flood Emergency Response Plan should relate
to the landuse and site conditions in conjunction with flood behaviour
up to FPL2 expected to be experienced at the site. The plan should
consider the following specific actions:
o Preparing for a flood;
o Responding when a flood is likely;
o Responding during a flood; and
o Recovery after a flood.
Floor Levels
• All floor levels to be no lower than FPL1.
Structural Soundness
• Applicant to demonstrate that any structure can withstand the forces
of floodwater, debris and buoyancy up to and including FPL3. An
engineer’s report must be provided.
Flood Effects
• Engineer’s report required to certify that the development will not
increase flood effects elsewhere, having regard to:
o Loss of flood storage.
o Changes in flood levels, flows and velocities caused by
alterations to the flood conveyance.
o The cumulative impact of multiple potential developments
in the floodplain.
Evacuation
• A Site Flood Emergency Response Plan is required when elements of
the development, including vehicular and pedestrian access are
below FPL3. The Site Flood Emergency Response Plan should relate
to the landuse and site conditions in conjunction with flood behaviour
up to FPL4 expected to be experienced at the site. The plan should
consider the following specific actions:
o Preparing for a flood;
o Responding when a flood is likely;
o Responding during a flood; and
o Recovery after a flood.
The flood plan should be consistent with the relevant NSW SES
FloodSafe Guide.
Floor Levels
• Habitable floor level to be no lower than FPL3. Where this is not
practical due to compatibility with the height of adjacent buildings,
or compatibility with the floor level of existing buildings, or the need
for access for persons with disabilities, a lower floor level may be
considered. In these circumstances, the floor level is to be as high as
practical, and, when undertaking alterations or additions no lower
than the existing floor level.
• Non-habitable floor levels to be equal to or greater than FPL3 where
possible, or otherwise no lower than FPL1 unless justified by a site
specific assessment.
• A restriction is to be placed on the title of the land, pursuant to
Section 88B of the Conveyancing Act, where the lowest habitable
floor area is elevated more than 1.5m above finished ground level,
confirming that the undercover area is not to be enclosed.
Structural Soundness
• Applicant to demonstrate that any structure can withstand the forces
of floodwater, debris and buoyancy up to and including FPL3. An
engineer’s report may be required.
Flood Effects
• Engineer’s report required to certify that the development will not
increase flood effects elsewhere, having regard to:
o Loss of flood storage.
o Changes in flood levels, flows and velocities caused by
alterations to the flood conveyance.
o The cumulative impact of multiple potential developments
in the floodplain.
Objectives
o To ensure that new dwellings approved in the floodplain in rural
agricultural and large lot residential are structurally sound for
relevant flood conditions;
o To ensure that the dwelling, the residents, farm equipment and
stock are protected during floods.
Development Controls
Development on a mound.
Development Controls
1. Replacement of an existing dwelling in a flood prone area,
irrespective of the hydraulic category, will be assessed as a new
dwelling. Habitable floor levels to be no lower than FPL3.
2. All structures below FPL3 will require flood compatible building
components and the applicant to demonstrate that the new
structure can withstand the forces of floodwater, debris and
buoyancy up to and including FPL3. An engineer's report must be
provided.
3. Concession may be considered in regard to Car Parking and
Driveway Access with appropriate justification.
Development Controls
1. Filling on flood controlled land is not permitted unless a report
from a suitably qualified engineer is submitted to Council that
certifies that the development will not increase flood affectation
elsewhere.
2. Filling of floodway areas is not permitted.
3. Filling of individual sites in isolation, without consideration of the
cumulative effects is not permitted. A case by case decision
making approach cannot take into account the cumulative impact
of flooding behaviour, and associated risks, caused by individual
developments. Any proposal to fill a site must be accompanied by
an analysis of the effect on flood levels of similar filling of
developable sites in the area.
4. This analysis would form part of a flood study prepared in
accordance with Council’s requirements as outlined in Appendix G
of the DCP.
Development Controls
1. Fencing within a floodway or high hazard flood risk area will not
be permissible except for security / permeable / open type /
safety fences of a type approved by Council.
2. Council will require a development application for all new solid
(non-porous) and continuous fences above 0.6m high, in the high
hazard flood risk areas.