MBA Project Guidelines (Synopsis and Project Report) - Updated
MBA Project Guidelines (Synopsis and Project Report) - Updated
Project Synopsis
Title of the project
Introduction and Objectives of the Study
Problem Statement (including Literature
Review)
Research Methodology and References
Phase 1
Guide Registration
Educational Qualification
MBA Project Experience Certificate
Phase 2
Project Work
Conducting Project Work
Preparing Project Report
Submitting Project report
Project presentation and viva-voce
2.1 Phase I: Project Synopsis and Guide Registration
Project Synopsis process
2.1.1 Project Synopsis Submission for Approval
The student needs to submit the project synopsis for approval through LMS
portal. The project synopsis should be prepared in consultation with the guide
and the guide should approve the project synopsis.
2.1.2 Content of Project Synopsis
The project synopsis needs to be prepared keeping in mind the following points.
a) Title of the project – Maximum 20 words (Refer Section: 2.2.1.1)
b) Introduction and Objectives of the Study - Maximum 200 words (Refer
Section: 2.2.1.2 & 2.2.1.3)
c) Literature Review and Problem Statement – Maximum 500 words (Refer
Section: 2.2.1.4)
d) Research Methodology and References – Maximum 500 words (Refer
Section: 2.2.1.5)
2.1.3 Instructions for Submitting the Project Synopsis
1. Submission of project synopsis is an online process. Project synopsis details
and the guide details should be filled in the appropriate sections in the LMS
portal.
2. Student can choose a project guide of his/her choice who meets the
University criteria, and get the guide registered with the University by
submitting the necessary documents of the guide (Guide Registration Form
(Annexure II), MBA/equivalent degree's marks sheets, degree certificate and
work experience certificate) along with the project synopsis in the format
(Provided in LMS portal), which should be manually signed by both the guide
and the student.
3. If the project guide is an already approved guide by the University, student
may choose “Existing Guide” option. In that case, student must know the
guides’ registration number (issued by the University) and contact number of
the guide to fill the online form. Student can find the list of approved guides
based on their specialization and location in the LMS portal under ‘Approved
Guide List’.
4. If the project guide chosen by the student is not registered, then ‘New Guide’
option has to be chosen and the details of the guide have to be filled in.
5. While entering the new guide detail, if the guide details provided by the
student matches with the details of an existing guide in the University
database, a message pops up alerting the student. In such case, the student
needs to click ‘Back’ button to select ‘Existing Guide option’ to proceed.
6. Only in the case of new guide registration, the evidence for guide
qualification and experience certificates along with the Guide Registration
Form (Annexure II) are to be uploaded on LMS portal, for verification by the
University.
7. Student needs to take print of the completed ‘Synopsis and Guide Acceptance’
document and both - the student and the guide should sign the form.
8. Scanned copy of this printed form is to be uploaded for approval by the
Project Steering Committee of the University.
9. Incomplete forms without the signatures will not be processed.
10. File formats supported to upload ‘Synopsis and Guide Acceptance form’ is in
.pdf only.
11. File formats supported to upload ‘Guide Registration Form (Annexure II),
Guide Qualification and Experience Certificates’ are .zip and .rar only.
12. The file size to be uploaded should not exceed 3MB.
13. Multiple submission of project synopsis is not allowed.
14. Student needs to ensure that he/she provides a valid e-mail id and mobile
number to receive confirmation message on approval/ re-submission.
15. The submitted project synopsis will be processed by the Project Steering
Committee.
16. Synopsis which does not adhere to the guidelines will be rejected and has
to be re-submitted for approval again.
17. Possible reasons for synopsis rejection could be
i. The guide is not approved.
ii. The project synopsis is not signed by the guide and or the student.
iii. Change suggested in the title or any other content of the synopsis.
iv. An additional explanation is needed.
v. The scope of work needs to be enhanced.
vi. Guide details not matching with existing records.
18. If the project synopsis is rejected due to Guide being rejected, the student
needs to re-submit both the project synopsis and the guide details.
19. Students can see the status (Not Submitted / Submitted / In-review / Rejected /
Graded) of the project synopsis in the LMS Login.
20. Through E-mail / Mentor calls, they may be informed to the student regarding
the status of the submitted synopsis/project.
List of Tables
Table no. Title Page
List of Figures
The same name should be given for the figures as they exactly appear in the
text. List of Figures
Figure no. Title Page
List of Symbols and Abbreviations 1.5 line spacing should be adopted for
typing the matter under this head. Standard symbols, abbreviations etc. should
be used.
List of Symbols
List of Abbreviations
Sl. No. Abbreviated Full Page no.
Name
Table of contents:
It is the list of all the contents of the report. A specimen is shown below.
Chapter no. Title Page no.
1 Introduction
1.1 Detail 1
1.2 Detail 5
1.3 Detail 10
2 Literature Review
2.1 Detail 14
2.2 Detail 21
Chapters The main text will be divided into several chapters and each chapter
can be further divided into several divisions and sub-divisions. Each chapter
should be given a relevant title. Tables and figures in a chapter should be
placed in the position with respect to the reference where they are cited. The
same name should be given for the table as they exactly appear in the text
above the table. The caption of the table must be present above the table. 1.5
line spacing should be adopted for typing the matter under this head.
Table 1
Field 1 Field 2 Field 3 Field 4 Field 5 Field 6
The same name should be given for the figure as they exactly appear in the
text below the figure. The caption of the figure must be present below the
figure. 1.5 line spacing should be adopted for typing the matter under this
head.
Headers and Footers should be used sparingly. The title of the project must be
on the left side of the header and chapter name must be on the right side of
the headers. Page numbers are to be placed on the right side of the footer.
They should be typed single space and placed directly underneath in the very
same page, which refers to the material they annotate.
Questionnaire/Balance sheets/Reports used in the study may be included as
Annexure. Instructions
The text in the printed copies must be in black colour. 1.5 line spacing should
be used for typing the general text. The general text shall be typed in the font
style
- Times New Roman and font size - 12. Font 14 may be used for titles.
ANNEXURE I
SUBMISSION OF PROJECT SYNOPSIS AND GUIDE ACCEPTANCE FORM
(To be submitted to the Project Steering Committee)
PART A: Synopsis Registration
I. Student Details:
1. Name of the Program:
2. Name of the Student:
3. Roll Number:
4. Session & Year:
5. Elective:
II. Project Details
6. Title of the Project:
7. Introduction and Review of Literature: (Not more than 500 words)
8. Objectives of the Study: (Not more than 200 words)
9. Research Methodology and References: (Not more than 500 words)
III. Guide Details:
10. Name of Proposed Guide:
11. Guide Registration No. (If available):
12. Designation:
13. Affiliation:
14. Qualification:
15. Total Experience:
16. Communication Address:
17. Contact No.:
18. E-mail ID:
PART – B: Guide Acceptance
DECLARATION
I hereby declare that this project synopsis is an original work carried by me and
has not been/will not be submitted to any other University for fulfilment of any
course of study.
Place:
Date:
(*Filled in application forms to be signed by both student and the Guide. Forms
must be scanned in either .pdf/.doc format and submitted through the LMS
student’s Login. For uploading, please refer section 2.1.5 of this document)
1. Name:
2. Date of Birth:
3. Present Employer: Affix Your Latest Photo
4. Designation:
5. Contact Details:
i) Residential Address:
ii) Office Address:
iii) All communications to be sent to: Residential/ Official address (tick anyone)
iv) Contact No.:
v) E-mail id:
10. Education Qualification (start with highest qualification): (Please attach
photocopies of degree certificates)
S. No. Name of Specialization Year of Institution/University Class
the Passing Obtained
Degree
Signature Signature
(Faculty in-charge) (Project Steering Committee)
(Note: Filled in Registration forms must be scanned in either .pdf / .doc format
and submitted along with credentials (Scanned copy of Degree Certificates,
PAN Card (for Domestic Guide), Passport (for Foreign Guide) and Experience
Certificates of the proposed guide) on LMS portal- link).
ANNEXURE- III
ANNEXURE – IV
BONAFIDE CERTIFICATE
SIGNATURE
Name of the Guide
Guide Registration Number
ANNEXURE – V
DECLARATION BY THE STUDENT
I also declare that this project report is my original work and has not been
previously submitted for the award of any Degree, Diploma, Fellowship, or
other similar titles.