N96DEC31
N96DEC31
A Case Study
the analysis, called the “Data Date,” the only 40 units were completed (BCWP= are that the additional resources will cost
value of the PMB becomes the BCWS. $40,000) and the actual amount spent the same and display a similar perfor-
The BCWS is compared to the BCWP for doing that was $45,000 (ACWP= mance, and that the particular activity
and to the ACWP, all expressed in terms $45,000), we deduce that (a) the project is has no influence on the implementation
of dollars. The cumulative values for the over budget (CV=–5,000; CVP=–13%) of other tasks.
given period are used in order to estab- and (b) the project is behind schedule Forecasting. The utilities discussed
lish a trend and to avoid periodical (SV=–10,000; SVP=–20%). above provide information about the
anomalies. Performance Indices. Performance project performance until the Data Date.
Variances. To measure the project indices are ratios used to determine the This information can be used to identify
performance until the Data Date, the fol- status of the project. problem areas as well as to forecast fu-
lowing variances are used: Cost Performance Index is defined as ture project performance by using the
Cost Variance is defined as CV= performance indices.
BCWP
BCWP–ACWP, or the Budgeted Cost of CPI = The funds required to complete the
ACWP
Work Performed less the Actual Cost of project are estimated based on the expe-
Work Performed. For the work per- For the work performed, the CPI com- rience gained until the Data Date. The
formed we compare the budgeted cost pares the budgeted cost with the actual. value of remaining work, which is the to-
with the actual. The variance was de- CPI<1 means that the project is over tal budget less the Earned Value, is mod-
fined such that a negative value denotes a budget. ified by the Cost Performance Index.
cost overrun. Schedule Performance Index is de- Estimate To Complete is defined as
Schedule Variance is defined as fined as
BAC - BCWP
SV=BCWP–BCWS, or the Budgeted ETC = ,
BCWP CPI
Cost of Work Performed less the Budget- SPI =
BCWS
ed Cost of Work Scheduled. Here we where BAC is the Budgeted cost At Com-
compare the work performed with what The SPI compares the work performed pletion, as approved in the plan.
was scheduled. A negative variance means with what was scheduled. SPI<1 means The Estimate To Complete figure is
that the project is behind schedule. that the project is behind schedule. useful to the project manager for com-
Percentage Variances. The CV and The two indices may give results that parison with the funds on hand. A sig-
SV show deviations from the plan in seem contradictory; for example, CPI>1 nificant difference will usually trigger a
terms of dollars. Are these deviations sig- and SPI<1. The project is within budget, review of the cost estimates of future
nificant when compared to the project which is good, but it is also behind tasks and a search for corrective actions.
value until the Data Date? To evaluate schedule. The money may have been The funds needed for the entire project
this, the variances are expressed in per- saved because not enough work was can be calculated by adding the actual costs
centages of the baseline. done. Can we come back on budget and incurred until the Data Date to the Esti-
Cost Variance (in percentage): on schedule by increasing the number of mate To Complete. The Estimate At Com-
CV resources employed? To answer this we pletion is defined as EAC=ETC+ACWP.
CVP = ´ 100%
BCWP use the Cost-Schedule Index, which is de- Knowing the Budget and the Estimate
BCWP - ACWP fined as At Completion, we can now calculate the
= ´ 100% Cost Variance At Completion, or its nega-
BCWP BCWP2
CSI = CPI ´ SPI = tive quantity, which is more prevalent, the
ACWP ´ BCWS
and Schedule Variance (in percentage): Projected Cost Overrun PCO=EAC–BAC.
SV CSI<1 is indicative of a problem. This can be expressed as a percentage of
SVP = ´ 100% Example 2. As an illustration, consid- the original budget in order to assess the
BCWP
er a second scenario for Example 1: Af- severity of the situation:
BCWP - BCWS
= ´ 100% ter 50 days only 40 units were complet- Projected Cost Overrun (in percentage):
BCWS
ed, but the actual amount spent was only
PCO EAC
Note that a different definition of the $30,000. This may happen, for instance, PCOP = × 100% = − 1 × 100%
SVP can be found in the literature; for if the cost of $1,000 per unit included a BAC BAC
example, see my letter in the September performance bonus which was not paid The project manager will explain the sit-
1996 Project Management Journal. due to slow delivery. Here we deduce uation to senior management and, if nec-
Example 1. To illustrate the use of the that (a) the project is within the budget essary, will negotiate additional funds.
variances, consider a scenario where (CPI=1.33), but (b) the project is behind Example 3. The Forecast To Complete
$100,000 was allocated in the project schedule (SPI=0.80), and (c) the project in Example 1 is $67,500 and the Estimate
budget for a worker to produce 100 can be brought on schedule and be with- At Completion is $112,500, with a Pro-
units of a certain product in 100 working in budget by employing additional re- jected Cost Overrun of $12,500, or 12.5
days. If after 50 days (BCWS=$50,000) sources (CSI = 1.07). The assumptions percent of the initial budget. In Example
40
The Data Performance Measurement
The utilities reviewed above will now be Baseline, or
30 Time Phased Budget
applied to the case study described by In-
gram in his December 1995 PM Network
article, in order to illustrate their utility. 20
The data were presented partly in graphs
and partly in a table; they have been re-
10 Planned completion date:
produced in Table 1. March 25, 1995
Work performance during project im-
plementation is measured against the TPB
plan, which includes all the cost accounts
4-Mar-95
7-Jan-95
11-Mar-95
18-Mar-95
25-Mar-95
19-Nov-94
26-Nov-94
14-Jan-95
21-Jan-95
28-Jan-95
3-Dec-94
31-Dec-94
10-Dec-94
17-Dec-94
24-Dec-94
4-Feb-95
11-Feb-95
18-Feb-95
25-Feb-95
10
utilities reviewed earlier have been calcu-
Earned Value
lated to determine the project perfor-
mance. The calculation results are sum-
14-Jan-95
21-Jan-95
28-Jan-95
11-Mar-95
18-Mar-95
25-Mar-95
19-Nov-94
26-Nov-94
7-Jan-95
10-Dec-94
17-Dec-94
24-Dec-94
31-Dec-94
11-Feb-95
18-Feb-95
25-Feb-95
4-Mar-95
3-Dec-94
4-Feb-95
Data Date
Data Date
10
Data Date
then calculating the aggregate.
The total of the charges to the project
as of the Data Date is the ACWP. Infor-
14-Jan-95
21-Jan-95
28-Jan-95
11-Mar-95
18-Mar-95
25-Mar-95
19-Nov-94
26-Nov-94
1-Apr-95
7-Jan-95
4-Mar-95
10-Dec-94
17-Dec-94
24-Dec-94
31-Dec-94
3-Dec-94
11-Feb-95
18-Feb-95
25-Feb-95
4-Feb-95