Estimating Costing Civil 5
Estimating Costing Civil 5
Estimating Costing Civil 5
asia
LECTURE NOTES
ON
CIVIL ENGINEERING
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
INDEX
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
EXERCISE
Short Answer Questions
1. State the requirements of an estimate?
2. Briefly Explain need for estimation?
3. What is work charged establishment?
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
4
Chapter
2 MEASUREMENT OF MATERIALS
AND WORKS
UNITS OF MEASUREMENTS:
The units of measurements are mainly categorised for their nature,
shape and size and for making payments to the contractor and also. The
principle of units of measurements normally consists the following:
a) Single units work like doors, windows, trusses etc., are
expressed in numbers.
b) Works consists linear measurements involve length like
cornice, fencing, hand rail, bands of specified width etc., are
expressed in running metres (RM)
c) Works consists areal surface measurements involve area like
plastering, white washing, partitions of specified thickness
2
etc., are expressed in square meters (m )
d) Works consists cubical contents which involve volume like earth
work, cement concrete, Masonry etc are expressed in Cubic metres.
[BASED ON IS 1200 REVISED]
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
3. R.R.Masonry in
CM (1:6) for
a) Footings 1 19.2 0.6 0.5 5.76
b) Basement 1 19.2 0.45 0.6 5.184
3
Total 10.944 m
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
3
TYPES OF ESTIMATES
DETAILED ESTIMATE:
The preparation of detailed estimate consists of working out
quantities of various items of work and then determine the cost of each
item. This is prepared in two stages.
i) Details of measurements and calculation of quantities:
The complete work is divided into various items of work such as
earth work concreting, brick work, R.C.C. Plastering etc., The details of
measure-ments are taken from drawings and entered in respective columns
of prescribed proforma. the quantities are calculated by multiplying the
values that are in num-bers column to Depth column as shown below:
Details of measurements form
Length Breadth Depth/
S.No. Description No (L) (B) Height Quantity Explanatory
of Item m m (D/H)m Notes
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
Types of Estimates 14
ABSTRACT OF ESTIMATE FORM
Item No. Description/ Quantity Unit Rate Per Amount
Particulars (Unit)
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
Types of Estimates 16
a) Area of walls at floor level.
2
b) Internal shafts of sanitary installations not exceeding 2.0m , lifts,
airconditionsing ducts etc.,
c) Area of barsati at terrace level:
Barsati means any covered space open on one side constructed on
one side constructed on terraced roof which is used as shelter
during rainy season.
d) Porches of non cantilever type.
Areas which are not to include
a) Area of lofts.
b) Unenclosed balconies.
c) Architectural bands, cornices etc.,
d) Domes, towers projecting above terrace level.
e) Box louvers and vertical sunbreakers.
b) Cubical Contents Method: This method is generally used for multistoreyed
buildings. It is more accurate that the other two methods viz., plinth area method
and unit base method. The cost of a structure is calculated approximately as the
total cubical contents (Volume of buildings) multiplied by Local Cubic Rate. The
volume of building is obtained by Length x breadth x depth or height. The length
and breadth are measured out to out of walls excluding the plinth off set.
The cost of string course, cornice, carbelling etc., is neglected.
The cost of building= volume of buildings x rate/ unit volume.
c) Unit Base Method: According to this method the cost of structure is
deter-mined by multiplying the total number of units with unit rate of
each item. In case schools and colleges, the unit considered to be as 'one
student' and in case of hospital, the unit is 'one bed'. the unit rate is
calculated by dividing the actual expenditure incured or cost of similar
building in the nearby locality by the num-ber of units.
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
jntuworldupdates.org Specworld.in
Smartzworld.com Smartworld.asia
Types of Estimates 18
Example 3.2 : The plinth area of an appartment is 500 sqm. Detemine
the total cost of building from the following data:
3
a) Rate of construction = Rs.1230/--per m .
b) The height of appartment = 16.25 m
c) Water Supply, Sanitary and Electrical installations each at
6% of building cost.
d) Architectural appearance @ 1% of building cost.
e) Unforeseen item @2% of Building cost.
f) P.S. and contingencies @4% of building.
Solution :
a) The Cost of building = cubic content x cubic rate
= 500 ×16.25 ×1230 = Rs. 99,93,750/-
b) Provision for water supply, sanitary and
Electrical installations water supply and sanitation each @ 6%
= 99,93,750×18 =Rs.17,98,875/−
100
i.e total percent = 3×6 = 18% building cost
jntuworldupdates.org Specworld.in