Dam Project Work (G1) Best of Best
Dam Project Work (G1) Best of Best
Dam Project Work (G1) Best of Best
1. INTRODUCTION ............................................................................................................................... 3
1.1 Objective.................................................................................................................................. 3
1.4 Summary.................................................................................................................................. 4
2.2 Evaporation.............................................................................................................................. 7
2.3 Sedimentation.......................................................................................................................... 8
3 Dam design...................................................................................................................................... 9
8 Reference ...................................................................................................................................... 39
1. INTRODUCTION
Now a day’s construction of earthen dams especially for irrigation purpose are common in
Ethiopia but experience on the design and construction of concrete dams are limited.
Embankment dams are constructed from natural materials excavated or obtained near by the
dam site. They are of relatively (compared with concrete dams) soft and elastic structures. So
the foundation requirements are lower compared to other dam types.
An embankment dam has the following advantages, suitability to wide valley and relatively steep
sided gorges, adaptability to abroad range of foundation condition, their design is extremely
flexible in its ability to accommodate different fill materials earth fill homogenous or zoned
internally, the unit cost of an earth dam material have risen much more slowly in real terms than
those of concrete dams.
Considering the above advantage and disadvantages, the proposed type of dam is an
embankment dam. In semi-arid part of Ethiopia, there is a significant water scarcity problem
particularly during dry season and excess runoff (flood) in rainy season. This may be due to poor
watershed management practice and an ever growing of communities’ water demand for
irrigation and other consumption use.
Moreover, in Ethiopia the farming practice is merely rainfall dependent agriculture. To modify
such practice and to ensure food-self sufficiency of community the government is striving to
expand irrigation projects.
This irrigation scheme can be addressed by constructing zoned embankment dam from local
available materials so as to make the project cost minimal.
1.1 Objective
In analyzing of this earth dam, we are going to achieve the following objectives.
Fixing the preliminary section of the dam,
Designing of filters
analyzing the slope stability of the dam body
seepage analysis
1.2 Location
This Micro earth dam is located in Afar National Regional State
Our earth dam has main features like an embankment dam body, reservoir and others terminal
structures.
- Planning the reservoir for balancing the total water demand, dead and live storage
allocation,
- Designing the dam body with checking for seepage and stability analysis,
1.4 Summary
1. Free board:-The free board is calculated to be 1.20m
2. Dam height: - The dam height is calculated to be 23 m.
3. Crest length of the dam: - we have taken the crest length of the dam to be
354m, but may vary on site Condition, probably there is an increase in the
crest length due to Abutment conditions.
4. Top Width:-The top width is calculated to be 4.5 m.
5. Embankment and cutoff slope: - We have provided a slope of 3:1 for U/s
and 2.5:1 for D/s side of the Embankment. We have Provided 1:1 slope for
Cut off.
6. Berm: - we have provided 11.5 m height and 3 m width berm on the D/s side
of the embankment.
10. Drainage Trench:-We have provided trench of 1m Depth and 0.5 m bottom
Width.
The Size of command area to be irrigated is 150 ha with a peak duty of 2l/s/ha. And the irrigation
is required for the three dry months. The source of water is fully from the reservoir storage and
the river flow is completely dry in these months.
The average demand for the crop to be irrigated in this three month period is calculated 1.1l/s/ha
Irrigation demand =1.1l/s/ha *150 ha =165l/s
Irrigation water demand for 3 months is 128.3 ha.m
The use full volume of the reservoir and thus the full supply level (FSL) equivalent to the normal
water level (NWL) should be determined in order to enable the water supply of irrigation
demand of the command areas.
2 RESERVOIR PLANNING
2.1 General
Reservoirs are created in order to maintain a dependable flow over a length of time. Fluctuation
in monthly catchment yield can be evened out by a reservoir that is generally created by building
physical barrier, dam, across the river.
Construction of a dam across the river obstructs the flow and water heads up behind the dam,
creating a reservoir. Surplus water from the reservoir is allowed to spill over a spillway, suitably
placed to the side of embankment dam type so as to avoid overtopping danger of flood.
Reservoir storage is generally made up of dead storage, live storage and flood storage. The dead
storage is provided to absorb the sediment inflow to the reservoir. Water of this space is not
usually utilized because this only allowed absorbing the incoming sediment volume over the
economic life span of a reservoir.
The live storage is a water pounding space provided to meet the total water demand that the
reservoir supposed to serve in its economic life. The purpose of this storage is to even out or
balance the fluctuations in the inflow and total maximum water demand.
The live storage is provided above the dead storage level and to the normal pool level. Outlets
are provided at the bottom suitable level of live storage. The reservoir live storage capacity is
determined by either excess deficit method or mass curve method after the water demand is
quantified. The Elevation –area capacity method is used to calculate as below.
V= h/2(Ao+A1)
Where Ao, A1, A3... An = the area enclosing each contour
h= vertical distance between contours
V= Storage capacity
The normal pool level(NPL) above river bed level fixed by taking in to consideration the
demands ,yields , reservoir area-capacity elevation, sedimentation and evaporation etc. aspects
shows that the NPL is to be fixed at 2542.00m a.m.s.l, the calculation is as follow
2.2 Evaporation
Due lack of a complete set of metrological data in the given location, it would be very difficult to
estimate the actual evapotranspiration losses in an irrigation scheme. To allocate Evaporation we
consider 15% of the reservoir capacity.
Estimated Evaporation = 15% Reservoir capacity
2.3 Sedimentation
Sedimentation data are rarely available, so to determine the sediment load to the reservoir and
hence to allocate dead storage considering 15% sedimentation
=0.15*268.27ha.m= 40.24ha.m
From the reservoir capacity curve the elevation of the dead storage can be taken as 2535m
268.27+40.24 =308.52ha.m
From the reservoir capacity curve the elevation of the dead storage can be taken as 2542m
In this case the last three factors are considered to fix the useful life of the dam, since those
factors are the critical factors to determine the life of the dam. The dam is filled by the sediment
after 25 and 50 yrs., if the catchment is untreated. But if the catchment is treated, the expected
filling time of the dam by the sediment may be longer.
Hence, considering quality of workmanship during catchment treatment and risk due to the
incoming sediment useful life of the project which is taken here as 30 years of the project.
1 Sedimentation analysis
2. Existing Topography condition
By analyzing the above factors the initial intake level is fixed at 2535.00m a.s.l for 25 years
sediment load and its distribution and considering the experience of the economic life the dam, to
increase the service life of the dam, the silt level rises to the full supply level. That is
2542.00ma.s.l hence to use the reservoir water effectively 7 meter height front entrance intake
structure is Provided.
3 Dam design
But different literatures dictate that foundation depths greater than 10m are not economical.
Therefore, the following alternatives have been over viewed to decide the type of cut off (partial
or positive).
Decision: Considering advantages and disadvantages among the above mentioned alternatives
A bottom width of the trench is provided to satisfy requirement of piping that is 10% to 30% of
hydraulic head .so we take an average 20%
3.2 Abutments
Left Abutment: - The left abutment of this dam project has relatively gentle to moderate slope
Right Abutment:-The right abutment has relatively steep slope that it forms cliff at some
portion
We have done two trials to gate the safest economical depth and length
Crest Length L 12
Discharge C 1.7
Q=CLH3/2 30
Reservoir flood Routing For CL=12m
Capacity, Outflow,
S.No Elevation S(m3) Q(m3/s)
1 2542.0 0.00 0.00
2 2542.2 149514.27 1.82
3 2542.4 299028.53 5.16
4 2542.6 448542.80 9.48
5 2542.8 598057.06 14.60
6 2543.0 747571.33 20.40
7 2543.2 1066477.49 26.82
8 2543.4 1385383.64 33.79
9 2543.6 1704289.80 41.29
10 2543.8 2023195.96 49.27
11 2544.0 1594530.79 57.70
12 2544.2 2104750.09 66.57
13 2544.4 2614969.40 75.85
S.No
1
2
3
4
5
6
7
8
9
10
11
12
13
Considering safety on one hand and economical construction of the spill way on the other side
adapt spillway crest length of 12m and the depth is 1.4m with free board.
Dam height = Normal pool level (NPL) above river bed + water head over the spill way crest +
Free board + settlement allow
Hs: wave height = 0.032 √(VF) +0.76 – 0.24 F1/4,for F<32km(lecture slide of
embankement dam design and Analysis)
V: wind velocity (km/hr)
S: wind setup
R: Wave Run up=50%Hs
Calculation of the Fetch distance:
The fetch distance is calculated based on the given Topo map of the reservoir area. First the
central radial is selected by trial and error to achieve the maximum fetch length. This length is
lined relatively normal to the axis of the dam body and to reach the top most distance /contour
that will have water from the impoundment of the dam. Next to fixation of the central radial
other fetch lines are drawn up to 45 for both sides from the central radial spacing 5 among each
fetch line and their corresponding lengths are measured from the horizontal projection on the
central radial line. The calculations to obtain the effective fetch are summarized below:
Fetch 343.426
Calculated effective fetch=0.34km, but adopt the minimum effective fetch to be 0.8km to have
reasonable wind velocity ratio.
From USBR a wind velocity for design of small dams is 80km/hr is recommended. So Use wind
velocity V=80km/hr for wave height calculation.
Hs=
Hs = 0.032*√80*0.8+0.76-0.24*(0.8)0.25
Hs = 0.789m
So R = 0.5*789 = 0.3945m
So D = (2543.4-2522)/2=10.7m
Therefore S = = 0.0077m
Fb = Hs + R + S
= 0.789+0.3945+0.0077 = 1.19m, Take Freeboard of 1.2m
Into account by keeping the construction crest level above the design crest level by the
Estimated settlement. Since the height is less than 30 m we consider 2% of the dam height is
taken as an allowance for settlement.
There are different recommendations by different literatures for top width of small dams
0.2 * 23 10
=14.6 feet =4.44m
Japanes’ code
W (m) 3.6 * H 1 / 3 3
=7.24m
Empirical formula,(lewis,2002)
W (m) H 0.5 1
W (m) 230.5 1
=5.79m
Since the most commonly method used is the USBR, the result obtained from this method is
adopted for the design purpose i. e 4.44m≈4.5m (take)
Berms are provided to protect the d/s face from since the level increase the water pressure
decreases, provided that the sections meet the stability requirement. In addition to this for the u/s
slope Rip-raps is provided. Berms are provided at d/s side 11.5m height above the bottom and
3m width with 0.46m layer thickness (sherard et.al 1963). So we have 1 berms.
Sherard et al. (1963) suggested the following criteria. Core width of 30% to 50% of the water
head have proved satisfactory for any soil type and dam height. We take 30%
W= 0.3*20=6m
3.9 Shell materials and slope protections
Relatively pervious materials are used as u/s and d/s shell zones of the embankment for
increment of stability and protect the core.
3.10 Transition
So to avoid the migration of core materials to the coarser zone (shell material), 0.5m
thickness transition which satisfy the filter criteria is provided b/n the core and shell
material in the upstream side of the dam.
a. / U/S Slope
The upstream slope has to be protected against the erosive actions of waves by dumped
Rock, rip-rap hand pack which is large enough to dissipate energy and strong resistance for
abrasion and durable enough to with stand for long period. The riprap is extended from the
crest of the dam to bottom level. Laid by hand in a more or less definite pattern with
minimum amount of voids and with top surface relatively smooth. In addition to u/s of the
dam, riprap is provided at the top of the dam. The thickness of the riprap should be 0.3m
for wave height of 0.789m and below the riprap gravels for transition is not required,
because the shell material acts as the transition material, since the shell consists of gravel
material also.
b. D/S Slope
Downstream slope governed by the fill material. The zoned dams with downstream shell of
rock or cobble fill do not need additional slop protection. Slope protection is required for
all conditions against erosion by wind and rainfall. If not protected, gully can develop. A
simple way to provide protection for soil slopes like this is to plant grasses.
3.12 . Seepage control Analysis and drainage of embankment
Seepage occurs through the body of earthen dam and also through their pervious
foundation. The amount of seepage has to be controlled in all conservation dams and the
effect of seepage (that is position of phreatic line) has to be controlled for all dams, in order
to avoid their failures
4 4.75 95
10 2 90
20 0.84 85
40 0.42 75
60 0.25 60
140 0.105 45
200 0.075 30
4 4.75 100
10 2 94.73684
20 0.84 89.47368
40 0.42 78.94737
60 0.25 63.15789
Step-3: prepare adjusted gradation curves for base soils that have particles larger than
the No 4 sieve
Step-5: Determine the max allowable D15 for the filter (Table 26–2).
40 A
For the third category, MaxD15 4 * D85 0.7 0.7
40 15
D85=0.66mm
40 31.58
MaxD15 4 * 0.66 0.7 0.7 1.355mm Say this control point-1
40 15
Since we don’t have significant D15 passing, take the minimum possible value=0.1mm from the
table above. Control point 2.
Step 7 : Preventing the use of gap graded filter materials by narrowing the width of the allowable
filter design band by determining the ratio of max.D15 to min D15 sizes use table 26-4 i.e. (
max.D15/min.D15 less than or equal to 5 )
=maxD15/minD15<=5
Max D15=0.5
Step 8: To prevent gap-graded filters both sides of the design filter band will have a coefficient
of
Uniformity (CU), defined as:
D60
CU 6
D10
D 60
6 D 60 0.42 6 2.5mm
Second calculate A Max. Allowable D60 by using 0.42
This is control point 3
Determine the min. allowable D60 size by using
Max.D 60 max .D60 2.5
5 Min.D 60 0.5mm
Min.D 60 5 5
Step 10: Determine Max. D90 & Min. D10 to minimize segregation during
construction.
min .D15 0. 1
First calculate Min. D10 by using Min.D10 0.083 , which is less than 0.5
1.2 1.2
then the Max.D90 = 20mm.
4 0.5 60 Minimum
2 0.1 15 Minimum
5 0.075 5 Minimum
coarser limit
6 75 100 Max
7 20 90 max
3 2.5 60 Max
1 0.5 15 Max
Design filter
band
Design band by determining the ratio of max.D15 to min D15 sizes use table 26-4 i.e.
(Max.D15/min.D15 less than or equal to 5)
Maximum D15=1.355 (look for step-6 above)
=maxD15/minD15<=5
= 1.355/0.1=13.55 which needs adjustment
Since the main purpose of the filter is to serve as a drainage material the minimum D15 is to be
changed by keeping the maximum D15 value the same.
1.355/ Min D15=5
Min D15=0.27mm, Say control point 2
Step 8: To prevent gap-graded filters both sides of the design filter band will have a coefficient
of
Uniformity (CU), defined as:
D60
CU 6
D10
max .D15 1.355
1.13mm
First calculate a max. D10 by using 1. 2 1. 2
D 60
6 MaxD60 1.13 6 6.78mm
1.13
This is control point 3.
Determine the min. allowable D60 size by using;
Max . D 60 max .D 60 6 .78
5 Min .D 60 1 . 355 mm
Min .D 60 5 5
Which is less than 0.5 then the Max.D90 = 20mm. This is control point 7
Step 11: connect control points 4,2 & 5 to form a partial design for the fine side of the filter band
.Connect control point 6,7,3 & 1for the coarse side of the drainage filter band.
Table: 7 Filter act as drainage
Finer limit Remark
4 1.355 60 Min
2 0.27 15 Min
5 0.075 5 Min
coarser limit
6 75 100 Max
7 20 90 max
3 6.78 60 Max
1 1.355 15 Max
Design
filter band
Where FRL=2542.00masl
MDDL= 2535masl
=2540.25masl or 18.25m
Rock toe
In order to improve the drainage in the dam body and to minimize the effect of tail water on
d/s side of the dam 25% of reservoir head rock toe is provided.
Rock toe height at maximum dam height
=25%*H H=23 0.25*23 = 5.75m = 6m
Drainage trench
To collect through horizontal filter foundation and runoff from d/s side of the dam and
discharge it away from the dam,0.3m thickness dry stone pitching (that is bedding on 0.2m
gravel thickness drainage) trench of depth 1m with bottom width of 0.5m and side slope of
1:1 provided at d/s toe of the dam. Both side of the drain join to the stream and its bed slope
varies with OGL.
B) Seepage Control through foundation (Cut off Trench)
The amount of water entering in to the foundation is controlled by adapting positive impervious
cutoff made of silt and clay material (i.e. the same property with core material).
A bottom width of the trench is provided to satisfy the requirement of piping that is 10% to 30% of
hydraulic head .so we take an average 20% of water hydraulic head
Width = 0.2*20m =4m and with side slope of 1:1 on both side.
It is therefore absolutely essential to determine the position of phreatic line as its position will
enable as to determine following things.
The stability analysis is carried out for the following conditions with the suggested
minimum factor of safety (USACE).
Slices 6 through 10 contain both embankment and foundation soils, and these slices were divided
into two portions for calculating the slice weights. The average height in each soil was
determined and used to compute the area and weight for that portion of the slice. The weights of
two parts of the slices were then added to compute the total slice weight. The bottoms of slices 1
through 5 are located in the embankment soil and were assigned the shear strength properties of
the embankment. The bottoms of slices 6 through 10 are located in the foundation, and these
slices were assigned the shear strength properties of the foundation soil.
Computations for the final value of the factor of safety (F = 1.81) are shown in the table. The
magnitude of the factor of safety can be directly read from the following picture attached next to
this page.
Computations were also performed for three trial values for the factor of safety: 1.0, 1.5, and 2.0.
The computed values for each trial value are plotted versus the assumed values in Figure. As can
be seen in the figure, the computed value of F varied only slightly with changes in the assumed
value.The final value of the factor of safety is read at the point where the line drawn with trial
value and 450 line drawn from the origin
Figure shows Slope used for calculations for end-of-construction stability condition
F=1.223
45o line
Figure shows Slope used for calculations for end-of-construction stability condition
An embankment dam under construction or at the end of construction should have to have a
factor of safety 1.5 or greater [both for the upstream and for the down stream slope] (P. Novak,
pp71) hence some adjustment should be taken in order to better the factor of safety.
Properties of thee embankment Properties of the foundation
emn KN
= 18 m3/ g foun= 17.8 KN/m3
Cem KN/
ban= 8 m3 Cfound= 10 KN/m3
emb degre
an= 33 e
Slope of
slip
Weight surface
() MFor different [CL+Wtan]/MFor different
Heig degree factor of safety ,F factor of safety ,F
Sliding Slic ht Slice Total C,
2
surfac e Width (Hav area(M Emb/Fou Weight(w L=B/cos KN/M Degr
3
e in No (B),m g)m ) nd ) W sin ee 1 1.21 1.22186 F=1 F=1.5 F=2
1 5 7 35.00 626.50 626.50 48 465.40 7.47 8 33 0.0000 0.7231 0.7226 3182.30054 3231.91358 3234.2442
embankment
2 2.25 13 29.25 523.58 523.58 43 356.93 3.08 8 33 0.7912 0.7809 0.7804 2309.71844 2340.32013 2341.75421
3 2.25 17 38.25 684.68 684.68 37 411.87 2.82 8 33 0.8514 0.8423 0.8419 1766.13794 1785.28022 1786.17504
4 12 20 240.00 4296.00 4296.00 31 2211.59 14.00 8 33 0.9023 0.8945 0.8942 1696.97868 1711.80029 1712.49163
5 9 22 198.00 3544.20 3544.20 24 1440.87 9.85 8 33 0.9492 0.9430 0.9427 1178.47224 1186.18256 1186.54138
16.71 167.10 2991.09 790.900864 792.442248 792.513638
6 10 1.29 12.90 230.91 3222.00 18 995.16 10.51 10 26 0.9619 0.9600 0.9599
12 108.00 1933.20 827.072361 828.040283 828.085077
7 9 3 27.00 483.30 2416.50 11 460.86 9.17 10 26 0.9883 0.9871 0.9871
Foundation
The above results are taken as Acceptable for the dam X-section at deepest point
5 Spillway Design
The spillway is used to dispose the routed flood to downstream from the dam. Spillway is constructed as a
safety measure against overtopping and the consequent damages and failures.
7 Dam Instrumentation
The primary purpose of dam instrumentation is to provide data useful for determining whether or
not an embankment or foundation is behaving in accordance with engineering predictions.
The number and type of instrumentation differ widely from dam to dam. In this particular case
,staff gauge and monuments are provided.
1. Staff gauge
Used to measure reservoir water level and spillway discharge level
To measure the level of the out flows in the spillway 3.8m height staff gauge constructed
from the reinforced concrete is installed on the spill way wall at the co
ntrol structure.
Similarly to measure the reservoir water , staff gages, constructed from reinforced
concrete at 1m vertical interval between full reservoir level and minimum draw down
level shall be installed on the u/s slope of the dam.
2. Monuments
To monitor the movement of the dam a total (4) monuments are to be provide along the
crest of the dam
8 Reference
Amhara National Regional state Water Resource Development Bureau, Small scale
Irrigation project design report.
Irrigation Engineering and Hydraulic structure Text Books,Garg
USBR design small of dams
Soil Mechanics and Foundation Engineering (Dr. Arora,2004)
Lecture Slide.