3-The Variable Load
3-The Variable Load
Where:
𝐸𝑛𝑒𝑟𝑔𝑦 𝐶𝑜𝑛𝑠𝑢𝑚𝑒𝑑 𝑜𝑣𝑒𝑟 𝑎 𝑔𝑖𝑣𝑒𝑛 𝑡𝑖𝑚𝑒 𝑖𝑛𝑡𝑒𝑟𝑣𝑎𝑙, 𝑘𝑊 − ℎ𝑟
𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐿𝑜𝑎𝑑 =
𝑇ℎ𝑒 𝑡𝑖𝑚𝑒 𝑑𝑢𝑟𝑖𝑛𝑔 𝑡ℎ𝑒 𝑠𝑎𝑚𝑒 𝑡𝑖𝑚𝑒 𝑖𝑛𝑡𝑒𝑟𝑣𝑎𝑙, ℎ𝑟
𝐴𝑐𝑡𝑢𝑎𝑙 𝐺𝑟𝑜𝑠𝑠 𝐸𝑛𝑒𝑟𝑔𝑦 𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑒𝑑 𝑑𝑢𝑟𝑖𝑛𝑔 𝑡ℎ𝑒 𝑝𝑙𝑎𝑛𝑡′𝑠 𝑜𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑡𝑖𝑚𝑒, 𝑘𝑊−ℎ𝑟
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 =
𝑅𝑎𝑡𝑒𝑑 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝑜𝑓 𝑡ℎ𝑒 𝑝𝑙𝑎𝑛𝑡 × 𝑡ℎ𝑒 𝑐𝑜𝑛𝑠𝑖𝑑𝑒𝑟𝑒𝑑 𝑡𝑖𝑚𝑒 𝑖𝑛𝑡𝑒𝑟𝑣𝑎𝑙,𝑘𝑊−ℎ𝑟
Where:
a. 𝐴𝑐𝑡𝑢𝑎𝑙 𝐺𝑟𝑜𝑠𝑠 𝐸𝑛𝑒𝑟𝑔𝑦 𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑒𝑑 = 𝐺𝑟𝑜𝑠𝑠 𝐸𝑛𝑒𝑟𝑔𝑦 𝑂𝑢𝑡𝑝𝑢𝑡 × 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑇𝑖𝑚𝑒, 𝑘𝑊 − ℎ𝑟
ℎ𝑜𝑢𝑟 𝑑𝑎𝑦𝑠 𝑑𝑎𝑦𝑠 ℎ𝑜𝑢𝑟
b. 𝐶𝑜𝑛𝑠𝑖𝑑𝑒𝑟𝑒𝑑 𝑡𝑖𝑚𝑒 𝑖𝑛𝑡𝑒𝑟𝑣𝑎𝑙 𝑐𝑎𝑛 𝑏𝑒 24 , 30 𝑚𝑜𝑛𝑡ℎ , 365 𝑦𝑒𝑎𝑟 , 8760 𝑦𝑒𝑎𝑟 𝑎𝑛𝑑 𝑜𝑡ℎ𝑒𝑟𝑠
𝑑𝑎𝑦
But if: a. 𝐺𝑟𝑜𝑠𝑠 𝐸𝑛𝑒𝑟𝑔𝑦 𝑂𝑢𝑡𝑝𝑢𝑡 = 𝐸𝑛𝑒𝑟𝑔𝑦 𝐶𝑜𝑛𝑠𝑢𝑚𝑒𝑑 𝑏𝑦 𝑡ℎ𝑒 𝑃𝑙𝑎𝑛𝑡 𝐿𝑜𝑎𝑑 𝑖𝑛𝑐𝑙𝑢𝑑𝑖𝑛𝑔 𝑎𝑢𝑥𝑙𝑖𝑎𝑟𝑦 𝑙𝑜𝑎𝑑
b. 𝑂𝑝𝑒𝑟𝑎𝑡𝑖𝑛𝑔 𝑇𝑖𝑚𝑒 = 𝐶𝑜𝑛𝑠𝑖𝑑𝑒𝑟𝑒𝑑 𝑇𝑖𝑚𝑒 𝐼𝑛𝑡𝑒𝑟𝑣𝑎𝑙
then:
𝐸𝑛𝑒𝑟𝑔𝑦 𝐶𝑜𝑛𝑠𝑢𝑚𝑒𝑑 × 𝑎 𝑡𝑖𝑚𝑒 𝑖𝑛𝑡𝑒𝑟𝑣𝑎𝑙, 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐿𝑜𝑎𝑑
𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 = =
𝑅𝑎𝑡𝑒𝑑 𝑐𝑎𝑝𝑎𝑐𝑖𝑡𝑦 × 𝑡ℎ𝑒 𝑠𝑎𝑚𝑒 𝑡𝑖𝑚𝑒 𝑖𝑛𝑡𝑒𝑟𝑣𝑎𝑙 𝑅𝑎𝑡𝑒𝑑 𝐶𝑎𝑝𝑎𝑐𝑖𝑡𝑦
3. The Plant Use Factor is the ratio of powerplant’s generated output to the product of
plant capacity and the number of hours for which the plant was in operation.
https://testbook.com/question-answer/plant-use-factor-is--5ee9b2a27c693b0d11867a3b
6. The Demand Factor is the ratio of the maximum demand of a system or circuit to the
total connected load
https://www.linkedin.com/pulse/what-demand-factor-diversity-electrical-hub-
1f#:~:text=In%20other%20words%2C%20it%20represents,demand%20of%20the%20whole%20system.&text=Diversity%20factor%20helps%20in%20sizing,operating%20at%20t
heir%20maximum%20simultaneously.
Example 1.
A power station supplies the following loads to the consumers
22.5𝑀𝑊
𝐿𝑜𝑎𝑑 𝐹𝑎𝑐𝑡𝑜𝑟𝑠𝑡𝑎𝑛𝑑−𝑏𝑦 = = 0.75
30
𝐿𝑜𝑎𝑑 𝐹𝑎𝑐𝑡𝑜𝑟 𝑓𝑜𝑟 𝑡ℎ𝑒 70𝑀𝑊 𝐵𝑎𝑠𝑒 − 𝐿𝑜𝑎𝑑 𝑃𝑜𝑤𝑒𝑟 𝑃𝑙𝑎𝑛𝑡
30𝑀𝑊×6 + 70𝑀𝑊×6 + 60𝑀𝑊×4 + 70𝑀𝑊×6 + 60𝑀𝑊×2 1380𝑀𝑊−ℎ𝑟
𝐴𝑣𝑒. 𝐿𝑜𝑎𝑑𝐵𝑎𝑠𝑒−𝐿𝑜𝑎𝑑 = = = 57.5𝑀𝑊
24ℎ𝑟 24ℎ𝑟
57.5𝑀𝑊
𝐿𝑜𝑎𝑑 𝐹𝑎𝑐𝑡𝑜𝑟𝐵𝑎𝑠𝑒−𝐿𝑜𝑎𝑑 = = 0.82
70
= 0.75
Example 2
The peak load on a power plant is 60MW. The loads having the
maximum demands of 30MW, 20MW, 10MW, and 14MW are
connected to the plant. The capacity of the power plant is 80MW and
the annual load factor is 0.5
Given:
Plant Capacity = 80MW
Peak Load = 60MW
Individual Capacity = 30MW, 20MW, 10MW, 14MW
Load Factor = 0.5
a) Average Load
From:
𝑎𝑣𝑒𝑟𝑎𝑔𝑒 𝑙𝑜𝑎𝑑 𝑜𝑣𝑒𝑟 𝑎 𝑔𝑖𝑣𝑒𝑛 𝑡𝑖𝑚𝑒 𝑖𝑛𝑡𝑒𝑟𝑣𝑎𝑙, 𝑘𝑊−ℎ𝑟 𝐴𝑣𝑒𝑟𝑎𝑔𝑒 𝐿𝑜𝑎𝑑, 𝑘𝑊
𝐿𝑜𝑎𝑑 𝐹𝑎𝑐𝑡𝑜𝑟 = =
𝑝𝑒𝑎𝑘 𝑙𝑜𝑎𝑑 𝑑𝑢𝑟𝑖𝑛𝑔 𝑡ℎ𝑒 𝑠𝑎𝑚𝑒 𝑡𝑖𝑚𝑒 𝑖𝑛𝑡𝑒𝑟𝑣𝑎𝑙, 𝑘𝑊−ℎ𝑟 𝑃𝑒𝑎𝑘 𝐿𝑜𝑎𝑑, 𝑘𝑊
𝑀𝑊−ℎ𝑟
𝐸𝑛𝑒𝑟𝑔𝑦 𝐺𝑒𝑛𝑒𝑟𝑎𝑡𝑒𝑑 𝑝𝑒𝑟 𝑦𝑒𝑎𝑟 = 262,800
𝑦𝑟
Load Diversity
c) Demand Factor
30 MW
𝑀𝑎𝑥 𝐷𝑒𝑚𝑎𝑛𝑑
𝐷𝑒𝑚𝑎𝑛𝑑 𝐹𝑎𝑐𝑡𝑜𝑟 = 20 MW
𝑇𝑜𝑡𝑎𝑙 𝐶𝑜𝑛𝑛𝑒𝑐𝑡𝑒𝑑 𝐷𝑒𝑚𝑎𝑛𝑑
60 𝑀𝑊
𝐷𝑒𝑚𝑎𝑛𝑑 𝐹𝑎𝑐𝑡𝑜𝑟 = = 0.813
30𝑀𝑊+20𝑀𝑊+10𝑀𝑊+14𝑀𝑊 20 MW
d) Diversity Factor
10 MW
𝐼𝑛𝑑𝑖𝑣𝑖𝑑𝑢𝑎𝑙 𝑀𝑎𝑥 𝐷𝑒𝑚𝑎𝑛𝑑
𝐷𝑖𝑣𝑒𝑟𝑠𝑖𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 =
𝑇𝑜𝑡𝑎𝑙 𝑆𝑖𝑚𝑢𝑙𝑡𝑎𝑛𝑒𝑜𝑢𝑠 𝐷𝑒𝑚𝑎𝑛𝑑
30𝑀𝑊+20𝑀𝑊+10𝑀𝑊+14𝑀𝑊
𝐷𝑖𝑣𝑒𝑟𝑠𝑖𝑡𝑦 𝐹𝑎𝑐𝑡𝑜𝑟 = = 1.23 10 MW
60𝑀𝑊
14 MW
0 hr 24 hr