0% found this document useful (0 votes)
12 views14 pages

A Late Mover Genetic Algorithm For Resource Constrained Project

Uploaded by

arashjadid2003
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
12 views14 pages

A Late Mover Genetic Algorithm For Resource Constrained Project

Uploaded by

arashjadid2003
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 14

Information Sciences 642 (2023) 119164

Contents lists available at ScienceDirect

Information Sciences
journal homepage: www.elsevier.com/locate/ins

A late-mover genetic algorithm for resource-constrained


project-scheduling problems
Yongping Liu a , Lizhen Huang a,∗ , Xiufeng Liu b , Guomin Ji a , Xu Cheng a ,
Erling Onstein a
a
Department of Manufacturing and Civil Engineering, NTNU, Norwegian University of Science and Technology, Teknologivn 22, 2815 Gjøvik,
Norway
b
Department of Technology, Management and Economics, DTU, Technical University of Denmark, Produktionstorvet, Building 424, room 006,
2800 Kgs. Lyngby, Denmark

A R T I C L E I N F O A B S T R A C T

Dataset link: https:// The Resource-Constrained Project Scheduling Problem (RCPSP) plays a critical role in various
github.com/ypliu2021/algorithm-for-rcpsp management applications. Despite its importance, research efforts are still ongoing to improve
lower bounds and reduce deviation values. This study aims to develop an innovative and
Keywords:
GA straightforward algorithm for RCPSPs by integrating the “1+1” evolution strategy into a genetic
RCPSP algorithm framework. Unlike most existing studies, the proposed algorithm eliminates the need
Heuristic algorithm for parameter tuning and utilizes real-valued numbers and path representation as chromosomes.
Optimization Consequently, it does not require priority rules to construct a feasible schedule. The algorithm’s
performance is evaluated using the RCPSP benchmark and compared to alternative algorithms,
such as cWSA, Hybrid PSO, and EESHHO. The experimental results demonstrate that the proposed
algorithm is competitive, while the exploration capability remains a challenge for further
investigation.

1. Introduction

The Resource-Constrained Project Scheduling Problem (RCPSP) is a key issue in many applications, including job-shop scheduling
[1,2], construction management scheduling [3,4], and assembly shop scheduling [5,6]. The objective of RCPSPs is to find an optimal
schedule that can minimize the total project duration while satisfying resource constraints and precedence constraints among its
activities. However, RCPSP is known to be a non-deterministic polynomial-time (NP) hard problem [7]. For decades, researchers
have studied methods for obtaining high-quality scheduling solutions within an acceptable time, and this area continues to attract
increasing interest.
Recent surveys [8] show that the best exact methods can only solve instances with a maximum of 60 activities without high
resource constraints. However, many real-world projects often have more than 60 activities and are subject to various resource
constraints. Therefore, many recent research efforts have focused on developing heuristic methods for scheduling optimization.
However, finding good lower bound and lower deviation values remains a challenge for many heuristic approaches. One potential
reason is that numerous heuristic methods entail varying parameter configurations, necessitating extensive tuning to attain optimal

*
Corresponding author.
E-mail addresses: [email protected] (Y. Liu), [email protected] (L. Huang), [email protected] (X. Liu), [email protected] (G. Ji), [email protected]
(X. Cheng), [email protected] (E. Onstein).

https://doi.org/10.1016/j.ins.2023.119164
Received 18 May 2021; Received in revised form 9 May 2023; Accepted 13 May 2023
Available online 19 May 2023
0020-0255/© 2023 The Author(s). Published by Elsevier Inc. This is an open access article under the CC BY license
(http://creativecommons.org/licenses/by/4.0/).
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

performance. [9]. For instance, cWSA (combinatoric weighted superposition attraction) [10], hybrid PSO (particle swarm optimiza-
tion) [11] and EESHHO (Elite Evolution Strategy with Harris Hawks Optimization) [12] are three powerful heuristic algorithms that
claimed they can handle medium-scale projects (i.e., a problem with 60 activities), with an average deviation of less than 5%. How-
ever, selecting the right combinations of parameters remains a challenge for these three methods. cWSA integrates various operators,
including the levy flight mechanism [13,23] and SSGS (serial scheduling generation scheme) [14], making it difficult to select the
correct parameters, such as the step size and the length for Levy flight, and the priority rules for the SSGS. Hybrid PSO has five
parameters that need tuning [11], including initial weight, two learning factors, swarm size, and peak length. EESHHO uses Gaus-
sian probability distribution as its core operator of EES [12], where different parameters in the distribution can result in different
solutions. Therefore, for RCPSP, minimizing the level of deviation while reducing the algorithm’s complexity is crucial.
In this paper, we introduce a new genetic algorithm, named late-mover genetic algorithm (LMGA), which aims to reduce the
complexity of search methods for RCPSP. The LMGA framework utilizes the worst offspring to compete with its parent generation
using a local search optimizer as the source of evolution. To simplify the algorithm, we incorporate a “1+1” evolution strategy, which
requires only one individual from the population and one mutation process. Furthermore, we introduce a local search operator into
the model, eliminating the need for any priority rules when building a feasible schedule. We also focus on the representation of the
chromosome path, which not only simplifies direct operations on a solution, but also enhance its interpretability. With these three
strategies, the proposed model is easy to use for real-world problems and requires no parameter tuning. We evaluate the performance
of our approach on instances from the project scheduling problem library (PSPLIB),1 specifically J30, J60, and J120. In summary,
Our proposed model provides a novel alternative for solving RCPSP and it makes the following contributions:

− We propose a simple algorithm based on the conception of “1+1” evolutionary strategy and Micro GA. Compared with cWSA,
Hybrid PSO and EESHHO, the proposed algorithm is a competitive method for RCPSPs.
− Moreover, the proposed algorithm is a promising method for solving RCPSPs as it eliminates the need for parameter tuning and
achieves satisfactory deviation rates. As mentioned previously, parameter tuning is a significant obstacle in optimization, requir-
ing considerable effort for most heuristic methods. In fact, the performance for the same instance can vary greatly, depending
on different combinations of parameters, such as population size and probability values used in the heuristics [9]. In contrast,
the proposed method has made great progress in this regard.

The remainder of this paper is structured as follows. Section 2 reviews related work; section 3 presents the proposed algorithm;
section 4 performs the evaluation; and section 5 concludes the paper and presents the future research directions.

2. Literature review

RCPSP is a well-known problem that has been studied for many years [8]. Three broad categories of methods have been developed
to solve RCPSP: exact methods, heuristics, and meta-heuristics. Exact methods include the Program Evaluation and Review Technique
(PERT) [15,16], Critical Path Management (CPM) [17], Mixed-Integer Programming (MIP) [18,19] and Branch and Bound (BB) [9].
However, PERT and CPM methods assume unlimited resource availability, which is often unrealistic [20]. Whilst, other methods,
such as LIP and BB, can be computationally expensive for problems with many activities [5]. Furthermore, even the best current
exact methods can only solve the problems with a maximum of 60 activities and without high resource constraints [8]. Heuristics
methods are categorized as either single-pass heuristics (constructive heuristics) or multiple-pass heuristics (improvement heuristics),
with Forward-Backward Improvement (FBI) and Neighborhood Search (NS) being their representative methods [9]. In heuristics,
Schedule Generation Scheme (SGS) is widely used to create schedules with one or more priority rules, either in series or in parallel.
However, it is challenging to find an effective priority rule for a wide range of RCPSP [5]. Meta-heuristic methods, such as genetic
algorithms (GA) [21] and difference evolution (DE) [9,20], are also widely used for RCPSPs. However, parameter tuning presents a
potential challenge for these methods, as different combinations of parameters, such as population size and probability values, can
significantly impact their performance [22,9].
Recently, hybrid meta-heuristic algorithms have been developed to improve the performance of RCPSP. However, the combination
of different meta-heuristic methods may not reduce the difficulty of parameter tuning, as different meta-heuristics may require
different parameter settings. Table 1 lists several hybrid algorithms that combine different meta-heuristic methods, such as the
Consolidated Optimisation Algorithm (COA) [5] and the TS-MODE [9]. Although the hybrid strategy provides a feasible approach
to the deficiency problems of evolutionary algorithms, it does not necessarily simplify the parameter tuning process. In fact, the
performance of most algorithms is limited to about 10% in J60 with a considerable effort of parameter tuning, which is not ideal
for many real-world problems. For instance, COA [5], one of the best performing heuristics for RCPSP, uses hybrid strategies with
multiple GA and DE operators, requiring three parameters tuning (CS, PS, and Mrga). Among them, CS has four possible values (10,
25, 50,28 100), PS has four possible values (5, 10, 25, 50), and Mrga has eight possible settings (0.001, 0.01, 0.05, 0.1, adaptive 29
0.05-0.01, adaptive 0.1-0.01, adaptive 0.05-0.001, adaptive 0.1-0.001). It can be time-consuming and difficult to find the optimal
combination for these values.
The GA is highly regarded as the first choice for solving complex optimization problems in EA families, as noted by Santiago
[31]. However, despite numerous efforts to enhance GA performance through the integration of advanced operators, the challenge of

1
http://www.om-db.wi.tum.de/psplib.

2
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

Table 1
Meta-heuristics algorithms for RCPSP.

Reference Algorithm Class Domain Hybrid operators Best average deviation


obtained for J30 and J60

Baykasoğlu and Şenol [10] CWSA Meta-heuristics RCPSPs Levy flight, SSGS, WSA 0.16% and 2.93%
Elsayed et al. [5] COA Meta-heuristics RCPSPs GA, DE 0% and 10.77%
Sallam et al. [9] TS-MODE Meta-heuristics RCPSPs DE, FBI, NS 0% and 10.6%
Zamani [24] ELDRA Meta-heuristics RCPSPs GA, search tree 0% and 10.5%
Goncharov and Leonov [21] GA Meta-heuristics RCPSPs GA, SGS 10.42% for J60
Paraskevopoulos et al. [25] SAILS Meta-heuristics RCPSPs Scatter search, adaptive iterated local search 0% and 10.5%
Fang and Wang [26] SFLA Meta-heuristics RCPSPs SFLA, FBI, SGS 0.18% and 10.66%
Alcaraz and Maroto [27] GA Meta-heuristics RCPSPs GA, FBC 0.24% for J30
Cheng et al. [20] FCDE Meta-heuristics RCPSPs DE, SGS, fuzzy c-means clustering Not mentioned
Tseng and Chen [28] ANGEL Meta-heuristics RCPSPs GA, ACO, SGS 0.09% and 11.27%
Zheng and Wang [29] MAOA Meta-heuristics RCPSPs MAOA, FBI, SSGS 0.01% and 10.64%
Shou et al. [11] PSO Meta-heuristics RCPSPs PSO, SGS 0.4% and 1.33%
Li et al. [12] EESHHO Meta-heuristics RCPSPs EES, HHO, SGS 0.89% and 3.1%

Algorithm 1: LMGA Algorithm.


Input: Profile of project instances (duration,resource constraints,activity logical constraints)
Output: Best schedule found by the algorithm
1 Function LMGA(Profile of project instance):
2 Initialize 𝐴 as an empty set ;
3 Add a random individual solution to 𝐴;
4 Apply UpdateItemsWithLocalOptimizer to the items in 𝐴 (see Algorithm 2);
5 while not Termination Condition do
6 Select the best solution in 𝐴 ;
7 Apply Procedure_2 to the selected subset (see Fig. 2 );
8 Sort the items in 𝐴 ;
9 Apply UpdateItemsWithLocalOptimizer to the last item in 𝐴 (see Algorithm 2 );
10 Sort the items in 𝐴 again;
11 Initialize 𝐵 as an empty set;
12 Add the first and last items of 𝐴 to 𝐵;
13 Convert the first item of 𝐴 into a date-based schedule and store it as father;
14 Generate a random activity list schedule and store it as mother;
15 Apply either TwoPointsCrossover or OnePointCrossover to father and mother and store the result as OffspringGroup (see Algorithms 5 and
6);
16 Find the missing activities for each item of OffspringGroup and insert them randomly back;
17 Apply Make a schedule feasible to the OffspringGroup (see Algorithm 4 );
18 Apply UpdateItemsWithLocalOptimizer for items in OffspringGroup (see Algorithm 2);
19 Add updated OffspringGroup to 𝐵;
20 Set 𝐴 equal to 𝐵;
21 return the first item of 𝐴;

optimizing its parameters remains. For example, D-GA-MBX [32] has three parameters for tuning with the search space decomposition
in GA. IGA-TWD [40] has five parameters for tuning with the time window decomposition method in GA. Additionally, it is interesting
to see that Micro-GA, one branch of GA family, is known for its small population size and stress on elitism [33], in which the
complexity of the algorithm is significantly reduced. At the same time, it is also seen that the “1+1” evolution strategy is the simplest
variant of evolutionary algorithms (EAs) [30], which only requires one individual and one mutation operator. Inspired by these
two algorithms, we propose a new algorithm that addresses the challenges of parameter tuning by limiting the population size to
one individual and eliminating mutation. As a result, the performance is not influenced by parameter combinations and tuning,
allowing for a relatively simple solution finding. However, a strong elitism selection rule from Micro GA may reduce population
diversity, leading to premature convergence. To counter this, we use two strategies: we retain the worst and the best offspring for
the next iteration during the selection and introduce a new random individual into the population when the last round of selection
is completed. This approach guarantees population diversity and is suggested [34,35].

3. The proposed algorithm

The Algorithm 1 describes the proposed algorithm LMGA. In this paper, we introduce the concept of the “1 + 1” evolution strategy
into the GA algorithm, in which the worst solution competes with the best solution by a local search optimizer.
The algorithm consists of two steps: the front part, including steps from 5 to 12, uses real date value solutions as representation.
The back part, including steps from 13 to 15, uses schedule activity solutions as representation (see Algorithm 1). But finally, they
are transformed into date real value solution forms, which will be sent back to front part for evolution. In the following, we use an
example to illustrate the representation in front part of algorithm, a sequence with nine activities (see the upper table in Fig. 1). We
sort the activities according to start dates and obtain a new sequence of activities (the lower table in Fig. 1).

3
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

Algorithm 2: UpdateItemsWithLocalOptimizer.
Input: 𝑏4 (a feasible activity sequence)
Output: 𝑎𝑐𝑡𝑒𝑠 (a start day value sequence)
1 Function UpdateItemsWithLocalOptimizer(b4):
2 Initialize 𝑎𝑐𝑡𝑒𝑠 as a zero vector of length len(Duration);
3 Initialize 𝑝𝑎𝑟𝑎𝑙𝑙𝑒𝑙 and 𝑠𝑢𝑐𝑐𝑒𝑠𝑠𝑜𝑟 as empty sequences;
4 for 𝑖 ∈ {0, … , len(Duration) - 1} do
5 if 𝑖 = 0 then
6 𝑎𝑐𝑡𝑠𝑖 ← 0 ; // Set the start day of the first activity to zero
7 else
8 Set 𝑡𝑒𝑚𝑝𝑏4 ← 𝑏4[0∶𝑖+1] ; // Get the subsequence of 𝑏4 up to index 𝑖 + 1
9 Initialize 𝑖𝑛𝑑 and 𝑡𝑒𝑚𝑝𝑎𝑢𝑏 as empty sequences;
10 for 𝑚 ∈ {0, … , len(tempb4) - 1} do
11 𝑖𝑛𝑑 ← 𝑖𝑛𝑑 ⊕ {𝑎𝑐𝑡𝑠𝑏4.index(𝑡𝑒𝑚𝑝𝑏4𝑚 ) } ; // Get the start days of the activities in 𝑡𝑒𝑚𝑝𝑏4
12 𝑡𝑒𝑚𝑝𝑎𝑢𝑏 ← 𝑡𝑒𝑚𝑝𝑎𝑢𝑏 ⊕ {𝑎𝑐𝑡𝑠𝑏4.index(𝑡𝑒𝑚𝑝𝑏4𝑚 ) + 𝐷𝑢𝑟𝑎𝑡𝑖𝑜𝑛𝑡𝑒𝑚𝑝𝑏4𝑚 −1 } ; // Get the end days of the activities in 𝑡𝑒𝑚𝑝𝑏4
13 𝑎𝑢𝑏 ← 𝑚𝑎𝑥(𝑡𝑒𝑚𝑝𝑎𝑢𝑏) ; // Get the maximum end day among the activities in 𝑡𝑒𝑚𝑝𝑏4
14 if 𝑏4𝑖−1 ∈ 𝑃 𝐴𝑏4𝑖 −1 then
15 𝑠𝑢𝑐𝑐𝑒𝑠𝑠𝑜𝑟 ← 𝑠𝑢𝑐𝑐𝑒𝑠𝑠𝑜𝑟 ⊕ {(𝑏4𝑖−1 , 𝑏4𝑖 )}; // Add a successor relation between 𝑏4𝑖−1 and 𝑏4𝑖
16 𝑝𝑎𝑎𝑐𝑡 ← 𝑡𝑒𝑚𝑝𝑏4 ∩ 𝑃 𝐴𝑏4𝑖 −1 ; // Get the sequence of predecessors of 𝑏4𝑖 that are also in 𝑡𝑒𝑚𝑝𝑏4
17 𝑝𝑎𝑎𝑐𝑡1 ← 𝑖𝑛𝑑 + 𝑝𝑎𝑎𝑐𝑡.𝐷𝑢𝑟𝑎𝑡𝑖𝑜𝑛; // Get the lower bounds of the predecessors of 𝑏4𝑖 as a vector
18 𝑝𝑎𝑎𝑙𝑏 ← 𝑚𝑎𝑥(𝑝𝑎𝑎𝑐𝑡1); // Get the maximum lower bound among the predecessors of 𝑏4𝑖 as a scalar
19 𝑖𝑛𝑑𝑖 ← 𝑝𝑎𝑎𝑙𝑏, and 𝑎𝑙𝑏1 ← 𝑝𝑎𝑎𝑙𝑏; // Set the corresponding elements of the vectors 𝐢 and 𝐚𝐥𝐛𝟏 to 𝑝𝑎𝑎𝑙𝑏
20 else
21 𝑝𝑎𝑟𝑎𝑙𝑙𝑒𝑙 ← 𝑝𝑎𝑟𝑎𝑙𝑙𝑒𝑙 ⊕ {(𝑏4𝑖−1 , 𝑏4𝑖 )}; // Add a parallel relation between 𝑏4𝑖−1 and 𝑏4𝑖
22 𝑡𝑒𝑚𝑝𝑎𝑙𝑏 ← 𝑖𝑛𝑑 + 𝑝𝑎𝑎𝑐𝑡.𝐷𝑢𝑟𝑎𝑡𝑖𝑜𝑛 − 𝑎𝑢𝑏; // Get the difference between the lower bounds and the upper bound as a vector
23 𝑎𝑙𝑏 ← 0 if min(𝑡𝑒𝑚𝑝𝑎𝑙𝑏) > 0 else max(𝑡𝑒𝑚𝑝𝑎𝑙𝑏) − min(𝑡𝑒𝑚𝑝𝑎𝑙𝑏); // Get the minimum difference if it is positive, or the range of differences otherwise
24 𝑖𝑛𝑑𝑖 ← 𝑎𝑢𝑏 + 𝑎𝑙𝑏; // Set the start day of 𝑏4𝑖 as the sum of the upper bound and the difference
25 while ResourceConstraints(𝑖𝑛𝑑, 𝑏4[0∶𝑖+1] , 𝑎𝑙𝑏1 , 𝑎𝑢𝑏, 𝑟𝑠𝑙) ≠ 0 do
26 𝑎𝑙𝑏1 ← 𝑎𝑙𝑏1 + 1; // Increase the temporary alb value
27 𝑖𝑛𝑑𝑖 ← 𝑎𝑙𝑏1 ; // Set the current index value to the temporary alb value
28 for 𝑛 ∈ {0, 1, … , len(𝑖𝑛𝑑) − 1} do
29 𝑎𝑐𝑡𝑠𝑛 ← 𝑖𝑛𝑑𝑛 ; // Update the start date values vector

30 Return 𝑎𝑐𝑡𝑠;

Algorithm 3: Resource Constraints Calculation.


Input: individual, target activity, alb, aub, resource constraints
Output: sum of resource violations for each day in this period
1 Function ResourceConstraints(individual, targetActivity, alb, aub, resourceConstraints):
2 𝑇2 ← (0, … , 𝑎𝑢𝑏) ; // Create a sequence of days from 0 to aub
3 𝑇4 ← 𝑇2 [𝑎𝑙𝑏 ∶] ; // Subset of days starting from alb
4 sumD ← () ; // Initialize an empty sequence for storing sum of violations
5 for 𝑖 ∈ 𝑇4 do
6 𝐷 ← () ; // Initialize an empty sequence for storing violations
7 for 𝑗 = 0 to length(individual) − 1 do
8 𝐷 ← 𝐷 ⊕ {(ℎ𝐹 𝑢𝑛𝑐(𝑖 − individual[𝑗]) − ℎ𝐹 𝑢𝑛𝑐(𝑖 − individual[𝑗] − duration[targetActivity[𝑗] − 1])) ∗ resourceConstraints[targetActivity[𝑗] − 1]};

9 sumD ← sumD ⊕ { 𝐷};
10 𝐷0 ← (), 𝐷1 ← (), 𝐷2 ← (), 𝐷3 ← ();
11 forall 𝑘 ∈ (sumD − resourceConstraints) do
12 if 𝑘1 > 0 then
13 𝐷0 ← 𝐷0 ⊕ {𝑘1 };
14 if 𝑘2 > 0 then
15 𝐷1 ← 𝐷1 ⊕ {𝑘2 };
16 if 𝑘3 > 0 then
17 𝐷2 ← 𝐷2 ⊕ {𝑘3 };
18 if 𝑘4 > 0 then
19 𝐷3 ← 𝐷3 ⊕ {𝑘4 };
∑ ∑ ∑ ∑
20 𝑡𝑆𝑢𝑚 ← 𝐷0 + 𝐷1 + 𝐷2 + 𝐷3 ;
21 return 𝑡𝑆𝑢𝑚;

Given a feasible schedule sequence of activities, Procedure 1 is used as a local optimizer to generate the best solution according to
the start dates of the activities. This procedure has two steps, namely Date transfer to schedule and Schedule transfer
to date, described as follows:

4
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

Fig. 1. An example of schedule sequence.

Procedure 1 Apply local search to the individual whose index is the last one.

Step 1 : Date t r a n s f e r t o schedule


1 . 1 : Convert t h e date p l a n t o a schedule
1 . 2 : Make t h e schedule f e a s i b l e ( see \ r e f t e x t { A l g o r i t h m \ r e f { a l g : mga } } )
Step 2 : Schedule t r a n s f e r t o date
2 . 1 : I n t r o d u c e a f e a s i b l e schedule
2 . 2 : Make a day p l a n f o r t h e g i v e n schedule ( see \ r e f t e x t { A l g o r i t h m \ r e f { a l g : l o c a l o p t i m i z e r } } )

Algorithm 4: Make a schedule feasible.


Input: an activity sequence 𝑥
Output: a feasible activity sequence
1 Function MakeScheduleFeasible(x):
2 while True do
3 𝑣𝑖𝑜𝑙𝑎𝑡𝑖𝑜𝑛 ← 0 ; // Initialize violation counter
4 for 𝑖 ∈ {0, … , len(𝑥) − 1} do
5 if not list(𝑥[𝑖 ∶] ∩ 𝑃 𝐴𝑥𝑖 −1 ) then
6 continue ; // Skip to the next iteration if there’s no intersection
7 else
8 𝑣𝑖𝑜𝑙𝑎𝑡𝑖𝑜𝑛 ← 𝑣𝑖𝑜𝑙𝑎𝑡𝑖𝑜𝑛 + 1 ; // Increment the violation counter

9 if 𝑣𝑖𝑜𝑙𝑎𝑡𝑖𝑜𝑛 = 0 then
10 break ; // Break the loop if no violations
11 𝑏 ← 𝑥.copy() ; // Create a copy of the activity sequence x
12 for 𝑖 ∈ {0, … , len(𝑥) − 1} do
13 𝑖𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛 ← list(𝑥[𝑖 ∶] ∩ 𝑃 𝐴𝑥𝑖 −1 ) ; // Get the intersection of subsequences
14 if not 𝑖𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛 then
15 continue ; // Skip to the next iteration if there’s no intersection
16 else
17 𝑠1 ← choice(𝑖𝑛𝑡𝑒𝑟𝑠𝑒𝑐𝑡𝑖𝑜𝑛) ; // Choose a random element from the intersection
18 𝑡𝑒𝑚𝑝 ← 𝑥𝑖 ; // Store the current element in a temporary variable
19 𝑠2 ← 𝑥.index(𝑠1) ; // Get the index of the randomly chosen element
20 𝑏𝑖 ← 𝑠1 ; // Update the copied sequence with the chosen element
21 𝑏𝑠2 ← 𝑡𝑒𝑚𝑝 ; // Update the copied sequence with the previously stored element

22 𝑥←𝑏 ; // Update the activity sequence with the modified copy


23 return 𝑥 ; // Return the feasible activity sequence

In Step 1.1, the schedule sequence is generated by sorting the start dates in ascending order. For example, in Fig. 1, the activities,
1 and 2, have the same start date of 0, which is at the head of the schedule sequence. However, activity 2 is added behind activity
1, since it is larger than activity 1. Activity 7 starts on date 9 which is in the 6th place after the activities are sorted by the start
date. Thus, activity 7 is moved one place ahead after the sorting. After sorting, it is possible for activity list to violate the precedence
constraints. Therefore, Step 1.2, a correction mechanism, is made to generate a feasible schedule, as described in Algorithm 4.
As shown in Fig. 1, the schedule of activities is determined when the corresponding start dates are sorted. However, the relevant
activity schedule sequence may violate the logic precedence relationship, as the start dates are randomly chosen. In Algorithm 4, we
check the activity sequence from the top to bottom. During the checking process, if one activity (A) is found its succedent activity (B)
stands in front of it, which means there is a violation of precedence constraints, then the positions of A and B will be exchanged and
the checking procedure will restart again from the first activity according to the new adjusted list. Then, a feasible schedule sequence
that satisfies the dependent constraints among activities can be achieved through our checking process. The relevant information can
be seen in the Algorithm 4.

5
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

Fig. 2. Procedure 2: GA crossover.

We now address the resource constraints by the process of “schedule transfer to date”. Step 2 (schedule transfer to date)
in Procedure 1 is essentially a local optimization process, which is further described in Algorithm 2 (Make a day plan for the
given schedule in “schedule transfer to date” in Procedure 1). The process to check “whether resource constraints are
violated?” (see the step 25 in Algorithm 2) is the key to solving the resource constraint problem. The relevant details can be seen
in the Algorithm 3 (Resource Constraints calculation), verified by the following two equations. The first is called the heavy side
function (see Equation (1)). If the independent variable is positive, then the function will generate output 1, otherwise 0.
{
1 if ∃𝑥 ⩾ 0
𝑓 (𝑥) = (1)
0 otherwise
The second function is used to calculate the computing resource 𝑗 for all activities at day 𝑡 (see Equation (2)):
𝑛
∑ [ ( ) ( )]
𝑅𝑗 (𝑡) = 𝑟𝑖𝑗 ∗ 𝑓 𝑡 − 𝑠𝑖 − 𝑓 𝑡 − 𝑠𝑖 − 𝑑𝑖 (2)
𝑖=1

where 𝑓 (⋅) is noted as the heavy side function; 𝑠𝑖 is the start date of activity 𝑖; 𝑑𝑖 is the duration of activity 𝑖; 𝑟𝑖𝑗 is the computing
resource 𝑗 required for the activity 𝑖; and 𝑅𝑗 (𝑡) is the total resource 𝑗 within an available limit at date 𝑡. As the above two equations
have been validated for resource calculation, e.g., construction management [36], we just follow these strategies. When the resource
constraints are violated, an additional penalty is given to the makespan for fitness evaluation. In Algorithm 2, given the setting date
for the plan, if a penalty is applied after checking, the algorithm will increase one day for activity until the resource constraints are
met.
Therefore, in Procedure 1, our algorithm can provide the local best date plan that meets not only the resource constraints, but
also the logic precedence relationship of activities. Unlike traditional SGS [8], our algorithm does not require priority rules to create
a feasible schedule.
We now describe Procedure 2 shown in Algorithm 1. This procedure is used to generate offspring through the crossover described
in Fig. 2. In contrast to traditional GA in which the mutation occurs after the crossover, the proposed method directly executes
the crossover operator on the parent generation to obtain an offspring. At the end of front part of Algorithm 1, the best and worst
solutions are selected from the individuals generated by mixing parents and their offspring. The two-point crossover in Fig. 2 is
included to produce a similar offspring 𝑏 as from the solution 𝑎. As the activity list schedule sequence is determined by the start
dates, a new date real value schedule sequence can be generated if the logic precedence relationship of the start dates is changed.
By crossover, most of the sections in the parent schedule sequence are kept, while only a few sections are adjusted. However, the
resulting offspring need further optimization by a local search operation, as they may not satisfy the time and resource constraints
(see Procedure 1).

6
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

Fig. 3. Procedure 3: GA crossover.

The two-point and one-point crossover in Procedure 2 are shown in the following:

Algorithm 5: Two-points crossover.


Input: Two solutions 𝑎 and 𝑏
Output: A new offspring 𝑐
1 Function TwoPointsCrossover(a, b):
2 Choose two random numbers 𝑖 and 𝑗 such that 1 ≤ 𝑖 < 𝑗 ≤ 𝑛, where 𝑛 is the length of the solutions ; // Select two random indices
3 Divide each solution into three sections: 𝑎1 , 𝑎2 , 𝑎3 and 𝑏1 , 𝑏2 , 𝑏3 ; // Split solutions into sections
4 𝑐 ← 𝑎1 ⊕ 𝑏2 ⊕ 𝑎3 ; // Create offspring by concatenating sections
5 return 𝑐 ; // Return the new offspring

A new offspring is created by combining solution 𝑎 and solution 𝑏 with a one-point crossover, described as follows:

Algorithm 6: One-point crossover.


Input: Two solutions 𝑎 and 𝑏
Output: A new offspring 𝑐
1 Function OnePointCrossover(a, b):
2 Choose a random number 𝑖 such that 1 ≤ 𝑖 < 𝑛, where 𝑛 is the length of the solutions ; // Select a random index
3 Divide each solution into two sections: 𝑎1 , 𝑎2 and 𝑏1 , 𝑏2 ; // Split solutions into sections
4 𝑐 ← 𝑎1 ⊕ 𝑏2 ; // Create offspring by concatenating sections
5 return 𝑐 ; // Return the new offspring

Inspired by the mutation approach set out in [37], we generate another new offspring at the last step in Procedure 2 directly
from the mutation of the parent generation, in which it selects a random activity and reduces it by a random number. Details are as
follows:

Algorithm 7: Mutation.
Input: A solution 𝑎
Output: A new offspring 𝑐
1 Function Mutation(a):
2 Choose a random activity 𝑘 and record its start date 𝑠𝑘 ; // Select a random activity
3 Choose a random number 𝑑 between 0 and 𝑠𝑘 ; // Select a random date shift
4 𝑐←𝑎 ; // Initialize offspring with the original solution
5 𝑐𝑘 ← 𝑠𝑘 − 𝑑 ; // Update the start date of activity 𝑘
6 return 𝑐 ; // Return the new offspring

When a temporary best solution has been generated by the front part of our algorithm, the back part of algorithm will produce
two feasible schedule sequences using Procedure 3, as shown in Fig. 3.
Procedure 3 performs the one-point crossover, which is the same as the crossover in Procedure 2. It should be noted that here the
chromosome is a schedule activity sequence. In Procedure 3, two new active schedules are generated (see Fig. 3). However, since the
generated schedules may not follow the constraints of the logical relationships, they must be corrected to feasible schedules using the
procedure step 16 and 17 in Algorithm 1. Two offspring schedules are generated by the traditional GA one-point crossover process,
which will be sent back to the front part, optimized by the local search operation of Procedure 1.

7
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

4. Experiments

4.1. Experimental settings

We conducted the experiments on a laptop with a 1.90 GHz Core (TM) i7-8650 CPU, 16 GB RAM and Windows 10 installed.
All programs were implemented with Python 3.6. We use PSPLIB for benchmarking with the problems of J30, J60 and J120, which
correspond to 480, 480 and 600 instances. An instance can have 30, 60 or 120 activities.
For all tests, we use a population size of 1 and set the probability of crossover to 1 to save computing resources. We design the
following three test cases according to the problems and termination conditions.

− Test 1: Only J30 and J60 were tested. For J60, we record the makespan (i.e., the duration between start and end times of a job)
of each instance with 30 iterations.
− Test 2: Only J30 and J60 were tested. Test 2 aims to check the consistency and exploration ability of the proposed algorithm.
Therefore, there is a small adjustment for the termination here. The test will end as long as either of the following two conditions
is met: 1) the best makespan is found; or 2) the best makespan is not found, but the iteration reaches 60.
− Test 3: Only J120 was tested. All instances were explored. The test ends when the best makespan is found. Given the condition
that the best makespan is not found, if the number of iterations is more than 15, then the test ends.

The deviation (noted as dev) is used to measure the quality of the algorithm [38] defined as follows:
𝐹 − 𝐿𝐵
dev = (3)
𝐿𝐵
where 𝐹 is the makespan of an instance found by our algorithm and 𝐿𝐵 is the low-bound optima given by PSPLIB. The optima is
obtained from [39].2
Therefore, the average deviation (noted as adev) for each problem can be defined as:
∑𝑛
𝑑𝑒𝑣𝑖
adev = 𝑖=1 × 100% (4)
𝑛
where 𝑑𝑒𝑣𝑖 is the deviation of an instance, 𝑖, and 𝑛 is the number of instances of a problem.

4.2. Results and analysis

This section will use the PSPLIB benchmark to evaluate the proposed algorithm, namely J30, J60 and J120, and then compare
them with state-of-the-art algorithms. Note that the following experimental results and relevant supplement files are stored at https://
github.com/ypliu2021/algorithm-for-rcpsp.

4.2.1. Results for J30 sets


Fig. 4 presents a summary of the results from two tests conducted on all 480 instances within the J30 sets, which are categorized
into eight groups. In Test 1, the largest group contains instances with a deviation less than or equal to 0%, accounting for 394
instances or 82% of the total. This group’s cumulative probability is also 82%, indicating an 82% chance of reaching the optimum
solution in a single experiment.
The following three groups consist of instances with deviations between 1% and 2%, 2% and 3%, and 3% and 4%, comprising 41,
20, and 13 instances, respectively. When considering a deviation below 4%, the cumulative probability rises to 97.5%, suggesting a
97.5% likelihood of reaching the optimum solution with a deviation under 4% in a single experiment.
Interestingly, there are only 12 instances exhibiting deviations between 4% and 7%, with no instances exceeding 7%. The average
deviation is a mere 0.453%, while the average time spent on each instance is 5.06 seconds. Detailed information on the solutions
can be found in the supplementary materials (refer to Supplement 1: Results for J30 in Test 1).
In comparison to Test 1, the cumulative probability distribution curve for Test 2 reveals a slight improvement in the search
results, as illustrated in Fig. 4(b). The average deviation is reduced to 0.355%, while the average CPU time increases to 9.49 seconds.
As anticipated, a greater number of instances (413) are discovered in Test 2 with the optimal lower bound, leading to a reduction
in the count of middle groups. Further details on the solutions can be found in the supplementary materials (refer to Supplement 3:
Results for J30 in Test 2).
Based on the aforementioned results, it can be safely concluded that the proposed algorithm for J30 exhibits consistent perfor-
mance. The average deviation for this algorithm is approximately 0.4%, with an average time consumption of 7.5 seconds.

4.2.2. Results for J60 sets


Fig. 5(a) displays the experimental results of Test 1 for the J60 sets, which are organized into 23 groups according to deviations
ranging from 0% to 22%. The first group, with deviations less than or equal to 0%, encompasses the majority of instances, totaling

2
The optimum comes from https://ptal.github.io/scheduling-data.html, in which the last date was 29 August, 2019.

8
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

Fig. 4. Experimental deviation frequency and cumulative probability distribution for J30 sets.

346 or 72% of the 480 instances. In contrast, the other groups contain significantly fewer instances. For instance, the second-largest
group comprises only 20 instances with deviations between 1% and 2%.
A notable observation is the presence of 38 instances, classified as hard cases, with deviations between 9% and 22%. These
instances account for 8% of the total 480 instances. The cumulative probability curves indicate that in a single experiment, 93.34%
of instances achieve a fitness value with a deviation of less than 10%. Only 32 instances remain unsolved using the proposed method.
With an average deviation of 1.99% and an average CPU time of 13.35 seconds, the proposed method demonstrates well handling of
the J60 sets. Further details on the solutions can be found in the supplementary materials (refer to Supplement 2: Results for J60 in
Test 1).
Fig. 5(b) presents the results of Test 2, revealing two subtle changes in comparison to Test 1. First, in the initial group with
deviations less than or equal to 0%, 351 instances are found to have low-bound optima (see Supplement 4: Results for J60 in Test
2). Second, the remaining groups exhibit a tendency towards a left-skewed distribution. For instance, the number of instances in
the third group, with a variance between 2% and 3%, increases from 12 to 17. Although the starting point of Test 2 has risen by
1.45%, the cumulative probability distribution remains largely unchanged. This indicates that our algorithm consistently manages
medium-sized problems, such as the J60 set. Notably, in Test 2, the average deviation is 1.74%, and the average CPU time is 29
seconds. These results align with expectations, as more time was devoted to exploring optima in Test 2. Consequently, based on the
findings from both tests, we can deduce a final deviation of 1.87% and an average CPU time of 22 seconds.

4.2.3. Results for large-scale schedule


Fig. 6 provides a summary of the experimental results for the large-scale J120 sets, consisting of 600 instances. Three prominent
peaks are evident in the data. The first peak represents the largest group with a deviation of 0%, featuring 168 instances solved at
optimal values. The second peak comprises 43 instances, exhibiting a deviation between 9% and 10%. The third peak encompasses
two groups: 34 instances with a deviation between 7% and 8%, and 33 instances with a deviation between 13% and 14%.
The cumulative probability curve demonstrates that 554 instances have a deviation below 16%, signifying a 90.83% probability
of attaining a fitness value in a single experiment. Among the groups with a deviation between 0% and 16%, an average of 25
instances displays a deviation of 8.96%. The relevant standard deviation is 9.5%, indicating that the number of instances lies within
two standard deviations from the mean—specifically, within the range of (25 - 2 × 9.5, 25 + 2 × 9.5). Furthermore, 46 instances

9
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

Fig. 5. Experimental deviation frequency and cumulative probability distribution for J60 sets.

Table 2
Average deviation values obtained by GA and other state-of-the-art algorithms for J30.

Reference Algorithm Schedules


<1,000 1,000 5,000

Elsaved et al. [5] COA 0.04(%)


Hua et al. [40] IGA-TWD 0.24(%) 0.06(%)
Liu et al. [32] DGA-DJ 0.23(%) 0.08(%)
This study LMGA 0.4(%)
Sallam et al. [9] TS-MODE 0.06(%)
Paraskevopoulos et al. [25] GH+SS(LS) 0.03(%)
Baykasoğlu and Şenol [10] CWSA 0.16(%)

exhibit a deviation above 16%. In conclusion, the average deviation for this test is 6.8%, suggesting a 50% probability of finding a
solution with a deviation between 6% and 7% in a one-time experiment. The average usage time amounts to approximately 28.85
seconds.

4.3. Comparison with state-of-the-art algorithms

RCPSP is a classic problem and many algorithms have been investigated for it since 1995 [8]. We choose the algorithms listed
in Tables 2 and 3 for comparison, because of their good performance in terms of deviation. In Table 3, AD denotes the average

10
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

Fig. 6. Experimental deviation frequency and cumulative probability distribution for J120 sets.

Table 3
Comparisons between EESHHO, Hybrid PSO, cWSA, and GA (this study) for RCPSPs.

Reference Algorithm Schedules J30 J60 J120


AD MD PO PB AD MD PO PB AD MD PO PB

This study LMGA 1,000 (J30, J60) 0.4% 7% 84% 0% 1.87% 22% 72.5% 0% 6.8% 29% 28% 0%
1,000 (J120) (168/600)
Shou et al. [11] Hybrid 5000 0.40% 6.78% 83.96% 0.00% 1.33% 10.34% 71.88% 0.00% 6.4%3 17.53% 31.67% 0.00%
PSO
Baykasoğlu and cWSA 5000 0.16% 91.6% 2.93% 68.33% 14.72% 16.83%
Şenol [10] (440/480) (328/480) (101/600)
Li et al. [12] EESHHO 5000 0.89% 74.58% 3.1% 11.5% 15%
(358/480) (90/600)

deviation of all instances, while MD is the maximum deviation. A negative deviation means a shorter project duration. PO represents
the percentage of instances for which the procedure has found optimal or best-known solutions. PB represents the percentage of
instances for which the procedure has found solutions better than the benchmark. In Table 2, COA was developed by Elsayed et al.
[5] for the J30 set, with a low deviation of 0.04%. According to [8], GH+SS(LS) is the best algorithm for J30 RCPSP, with a deviation
of only 0.03%. COA ranks second according to the deviation.
Compared with the algorithm mentioned above, from the perspective of deviation, our algorithm still needs to expand its searching
capacity. The distance is not so far. In fact, the average deviation of our algorithm under J30 is only 0.4%, but we expect that it can
be smaller for 5,000 schedules, because it succeeds in finding the optima for 82% of the instances in the J30 set. Moreover, it should
be noted that the performances of above mentioned algorithms are achieved by using considerable parameter tuning. In contrast
with them, our algorithm is easy to use without the need of parameter tuning.
Table 3 compares our algorithm with three competitive alternatives: cWSA [10], Hybrid PSO [11], and EESHHO [12]. Among
these, cWSA optimally solves 440 of the 480 problems [10], outperforming both Hybrid PSO and EESHHO. Our algorithm demon-
strates comparable results when handling the J30 set, as depicted in Fig. 4. Specifically, our method achieves optima for 394 and 413
instances in Test 1 and 2, respectively (refer to Supplement 1 for Test 1 and Supplement 3 for Test 2). In comparison to Hybrid PSO,
cWSA, and EESHHO, our algorithm obtains similar results without the need for parameter tuning, as shown in Fig. 4. This highlights
the competitive performance of the proposed method when dealing with J30 instances.
Table 4 gives the results for the J60 set. According to the survey in [8], GA (FBI) is ranked as the best for the J60 set, with the
lowest deviation of 10.42% per 5,000 experiments. The other three algorithms have an average deviation of less than 3%, including
cWSA [10], Hybrid PSO [11] and EESHHO [12] (see Table 3). Hybrid PSO is the best, with a deviation of 1.33%. However, it should
be noted that this value is obtained with different bases. COA, TS-MODE, GA(FBI) are calculated based on the CPM standard, which
is stricter than the base used by cWSA, EESHHO, and Hybrid PSO. Therefore, it is difficult to compare their performance between
these two groups. Since our base is similar to that of cWSA, EESHHO and Hybrid PSO, it is possible to compare ours with them. In
fact, our algorithm is comparable to cWSA and Hybrid PSO (see Table 3), e.g., the PO ratio with 346 and 351 out of 480 instances
optimally solved for Tests 1 and 2, respectively (see Fig. 5). Based on the above results, we can conclude that the proposed algorithm
is competitive with these three algorithms, especially considering that the results are obtained without parameter tuning.

11
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

Table 4
Average deviation values obtained by LMGA and other state-of-the-art algorithms for J60.

Reference Algorithm Schedules comment


1,000 5,000

Elsayed et al. [5] COA 10.581(%) CPM base


Sallam et al. [9] TS-MODE 10.629(%) CPM base
Goncharov and Leonov [12] GA(FBI) 10.42(%) CPM base
This study LMGA 1.87(%) benchmark base
Baykasoğlu and Şenol [10] CWSA 2.93% benchmark base
Shou et al. [11] Hybrid PSO 1.33% benchmark base
Li et al. [12] EESHHO 3.1% benchmark base

Table 5
Average deviation values obtained by LMGA and other state-of-the-art algorithms for J120.

Reference Algorithm Schedules comment


1,000 5,000

Elsayed et al. [5] COA 31.19(%) CPM base


Sallam et al. [9] TS-MODE 30.59(%) CPM base
Baykasoğlu and Şenol [10] CWSA 14.72% benchmark base
Shou et al. [11] Hybrid PSO 6.43% benchmark base
Li et al. [12] EESHHO 11.5% benchmark base
This study LMGA 6.8(%) benchmark base

For large-scale projects (J120), the survey in [8] shows that most algorithms can achieve a minimum deviation of 30.45% after
50,000 experiments, including COA and TS-MODE. cWSA, Hybrid PSO and EESHHO can do even better, with deviations as low
as about 10% (see Table 5). However, this is because they use different baselines for comparison. In order to compare them on
equal footing, the targeted algorithm for comparison here will be cWSA, Hybrid PSO, and EESHHO. Hybrid PSO is the best in terms
of deviation, which is 6.43% (see Table 5), and ours is comparable, which is 6.8%. It is better than CWSA (11.5%) and EESHHO
(14.72%). In terms of PO ration, Hybrid PSO also ranks best (see Table 3), up to 31.67%, while the other two are around 16%. Ours
can be ranked second according to the PO ratio (28%) and the average deviation (6.87%). Note that these values were obtained using
1,000 instances. As mentioned earlier, our average deviation can be smaller with more iterations; for example, about 30/% of the
J120 set can find the low-bound optima with our algorithm. In particular, the results are obtained without parameter tuning, which
is a significant improvement. Based on these results, we can also conclude that our algorithm is a competitive method, compared
with cWSA, Hybrid PSO, and EESHHO in solving large-scale project optimization problems.

4.4. Discussion

Our method diverges from most existing studies in two aspects. Firstly, the number of experimental schedules is within 1,000
schedules in the J30 and J60 sets, respectively. In contrast, many studies use 5,000 or even 50,000 schedules to assess algorithm
consistency. We argue that testing with such a large number of instances is of limited use for the results. For the J30 or J60 set,
due to the premature character of the heuristic algorithms, the deviation distribution is determined when 1,000 or 5,000 schedules
are applied (see Figs. 4 and 5 for deviation results). Consequently, increasing the number of experiments will not significantly alter
the distribution, as evidenced by the minimal alterations in the cumulative probability curve illustrated in Fig. 4. Furthermore, as
shown in Figs. 4 and 5, the complexity of solving instances in the J30 and J60 sets is different for a given method, since the number
of difficult instances is different in the two sets, i.e., about 12% and 34% in the J30 and J60 sets, respectively (see Figs. 4a and
5a). These findings suggest that utilizing 50,000 schedules to evaluate the algorithm’s performance is not an optimal option, as the
heuristic method relies on random choices. There exists the possibility of getting the optimum solution, although this probability can
be extremely low. As a result, the performance of the algorithm is likely to be biased towards easier instances. Secondly, our approach
is distinct from other algorithms in that it employs real-valued solutions and path representations as chromosomes, enabling direct
operation on instances without the need for priority rules to construct a feasible schedule. This feature is particularly advantageous,
as Elsayed et al. have previously highlighted the challenge of identifying an efficient priority rule that performs well across a broad
range of RCPSPs [5].
Additionally, the proposed method employs an evolutionary algorithm that utilizes a uniform random choice in the crossover
process to generate new offspring. As shown in Figs. 2 and 3, the random choice yields one or two random integers for the posi-
tions. This random sampling can be regarded as uncertain input to the algorithm, potentially leading to varying random schedules,
and consequently, uncertainty in the resulting schedules. Hence, the generated offspring schedules may not outperform the parent
schedule, causing a slower convergence speed due to the increased time spent on the inefficient track-and-error process. To date,
many methods are available to mitigate this uncertainty, e.g., [41–43]. Since the relationship between the random choice outcomes
and their fitness values can be viewed as a Monte Carlo (MC) experiment, methods such as MC dropout, Markov chain Monte Carlo

12
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

techniques, and Bayesian inference can be effective ways to minimize the issue of low sampling efficiency. However, as uncertainty
lies beyond the scope of this paper, we will explore this aspect in future work.
Furthermore, the proposed method primarily employs the local search operations to solve RCPSP without parameter tuning (see
Procedure 1). However, numerous algorithms are designed to tackle problems across a wide range of application domains, such as
hybrid PSO for RCPSP [11], health problems [44,45], and mixed-variable problems [46]. This results in the significant challenge of
tuning parameters for different specific domains. Consequently, the adaptive parameter tuning (APT) strategy was introduced in the
hybrid PSO [46], which heavily relies on the Cauchy distribution and the Gaussian distribution with fixed variances. In fact, this
issue is well-known for most new meta-heuristic algorithms. For example, the Whale Optimization Algorithm (WOA) claims to have
fewer and simpler tuning parameters [47], but fine-tuning the step size becomes critical and significantly affects its performance.
The Gray Wolf algorithm (GWO), developed based on the leadership hierarchy of gray wolves and their hunting strategies, also
faces performance issue due to the control vector. As a result, numerous variants of the GWO algorithm have emerged, such as
the Grouped Gray Wolf Optimizer (GGWO) and the Enhanced Gray Wolf Optimizer (IGWO), which incorporate different parameter
tuning operators. In contrast, our algorithm streamlines the process by integrating the “1+1” strategy into a Genetic Algorithm
framework, eliminating the need for parameter tuning. This enhancement makes our method significantly more user-friendly.

5. Conclusions

RCPSP is a common challenge for many applications. Most existing algorithms require significant effort in parameter tuning to
achieve satisfactory results. In this paper, we propose a new method for RCPSP by incorporating a “1+1” evolutionary strategy
into the genetic algorithm framework. This proposed algorithm requires only a single population size and employs a 100% mutation
probability, thereby eliminating the need for laborious parameter tuning and simplifying its usage. Additionally, our approach utilizes
both real-valued solutions and path representations as chromosomes, eliminating the need for priority rules to establish a feasible
schedule. We conducted a comprehensive evaluation of the proposed algorithm using J30, J60, and J120 instances, and compared its
performance with high-performing algorithms such as hybrid PSO, cWSA, and EESHHO. The results demonstrate that our proposed
algorithm is particularly simple and promising for solving RCPSPs. This study represents an attempt to address RCPSPs without
parameter tuning while maintaining good accuracy. However, enhancing the search capability of the proposed algorithm remains a
challenge, which will be left for future work.

CRediT authorship contribution statement

Conceptualization, Y.L. & L.H; methodology, Y.L.; investigation and resources, Y.L., L.H.; writing-original draft preparation, Y.L.
and X.L.; writing-review and editing, ALL; supervision, Y.L. and L.H.; project administration, Y.L. and L.H.; funding acquisition,
L.H. All authors have read and agreed to submit the manuscript.

Declaration of competing interest

The authors declare that they have no known competing financial interests or personal relationships that could have appeared to
influence the work reported in this paper.

Data availability

https://github.com/ypliu2021/algorithm-for-rcpsp.

Acknowledgements

This research was supported by two projects: Reinforcing the Health Data Infrastructure in Mobility and Assurance through Data
Democratization (288856) and circle Wood (328698), funded by the Norwegian Research Council. It also received support from the
Flexible Energy Denmark project (8090-00069B) funded by the Innovation Fund Denmark.

Appendix A. Supplementary material

Supplementary material related to this article can be found online at https://doi.org/10.1016/j.ins.2023.119164.

References

[1] M. Thenarasu, K. Rameshkumar, J. Rousseau, S.P. Anbuudayasankar, Development and analysis of priority decision rules using MCDM approach for a flexible
job shop scheduling: a simulation study, Simul. Model. Pract. Theory 114 (2022) 102416.
[2] R. Chen, B. Yang, S. Li, S. Wang, A self-learning genetic algorithm based on reinforcement learning for flexible job-shop scheduling problem, Comput. Ind. Eng.
149 (2020) 106778.
[3] J. Liu, Y. Liu, Y. Shi, J. Li, Solving resource-constrained project scheduling problem via genetic algorithm, J. Comput. Civ. Eng. 34 (2) (2020) 04019055.
[4] G. Selvam, T.C. Tadepalli, Genetic algorithm based optimization for resource leveling problem with precedence constrained scheduling, Int. J. Constr. Manag.
1 (10) (2019).

13
Y. Liu, L. Huang, X. Liu et al. Information Sciences 642 (2023) 119164

[5] S. Elsayed, R. Sarker, T. Ray, C. Coello, Consolidated optimization algorithm for resource-constrained project scheduling problems, Inf. Sci. 418 (2017) 346–362.
[6] D. Arkhipov, O. Battaïä, A. Lazarev, An efficient pseudo-polynomial algorithm for finding a lower bound on the makespan for the Resource Constrained Project
Scheduling Problem, Eur. J. Oper. Res. 275 (2019) 35–44.
[7] J. Blazewicz, J. Lenstra, A. Kan, Scheduling subject to resource constraints: classification and complexity, Discrete Appl. Math. 5 (1983) 11–24.
[8] R. Pellerin, N. Perrier, F. Berthaut, A survey of hybrid metaheuristics for the resource-constrained project scheduling problem, Eur. J. Oper. Res. 280 (2020)
395–416.
[9] K. Sallam, R. Chakrabortty, M. Ryan, A two-stage multi-operator differential evolution algorithm for solving Resource Constrained Project Scheduling problems,
Future Gener. Comput. Syst. 108 (2020) 432–444.
[10] A. Baykasoğlu, M. Şenol, Weighted superposition attraction algorithm for combinatorial optimization, Expert Syst. Appl. 138 (2019) 112792.
[11] Y. Shou, Y. Li, C. Lai, Hybrid particle swarm optimization for preemptive resource-constrained project scheduling, Neurocomputing 148 (2015) 122–128.
[12] C. Li, J. Li, H. Chen, A. Heidari, Memetic Harris Hawks Optimization: developments and perspectives on project scheduling and QoS-aware web service
composition, Expert Syst. Appl. 171 (2012) 114529.
[13] W. Kaidi, M. Khishe, M. Mohammadi, Dynamic Levy flight chimp optimization, Knowl.-Based Syst. 235 (2022) 107625.
[14] G. Ulusoy, Ö. Hazır, Resource constrained project scheduling, in: An Introduction to Project Modeling and Planning, 2021, pp. 199–250.
[15] I.A. Kartini, T. Aspiranti, A.M. Rani, Implementation of program evaluation and review technique (Pert) to optimize shophouse development projects, J. Manag.
Energy Bus. 1 (1) (2021).
[16] E. Akan, S. Bayar, Interval type-2 fuzzy program evaluation and review technique for project management in shipbuilding, Ships Offshore Struct. 17 (8) (2022)
1872–1890.
[17] D. Sarkar, K.N. Jha, S. Patel, Critical chain project management for a highway construction project with a focus on theory of constraints, Int. J. Constr. Manag.
21 (2) (2021) 194–207.
[18] D. Ioan, I. Prodan, S. Olaru, F. Stoican, S.I. Niculescu, Mixed-integer programming in motion planning, Annu. Rev. Control 51 (2021) 65–87.
[19] A. Ham, Dial-a-ride problem: mixed integer programming revisited and constraint programming proposed, Eng. Optim. (2021) 1–14.
[20] M. Cheng, D. Tran, Y. Wu, Using a fuzzy clustering chaotic-based differential evolution with serial method to solve resource-constrained project scheduling
problems, Autom. Constr. 37 (2014) 88–97.
[21] E. Goncharov, V. Leonov, Genetic algorithm for the resource-constrained project scheduling problem, Autom. Remote Control 78 (2017) 1101–1114.
[22] A. Ezugwu, D. Prayogo, Symbiotic organisms search algorithm: theory, recent advances and applications, Expert Syst. Appl. 119 (2019) 184–209.
[23] E. Emary, H. Zawbaa, M. Sharawi, Impact of Lèvy flight on modern meta-heuristic optimizers, Appl. Soft Comput. 75 (2019) 775–789.
[24] R. Zamani, An evolutionary implicit enumeration procedure for solving the resource-constrained project scheduling problem, Int. Trans. Oper. Res. 24 (2017)
1525–1547.
[25] D. Paraskevopoulos, C. Tarantilis, G. Ioannou, Solving project scheduling problems with resource constraints via an event list-based evolutionary algorithm,
Expert Syst. Appl. 39 (2012) 3983–3994.
[26] C. Fang, L. Wang, An effective shuffled frog-leaping algorithm for resource-constrained project scheduling problem, Comput. Oper. Res. 39 (2012) 890–901.
[27] J. Alcaraz, C. Maroto, A robust genetic algorithm for resource allocation in project scheduling, Ann. Oper. Res. 102 (2001) 83–109.
[28] L. Tseng, S. Chen, A hybrid metaheuristic for the resource-constrained project scheduling problem, Eur. J. Oper. Res. 175 (2006) 707–721.
[29] X. Zheng, L. Wang, A multi-agent optimization algorithm for resource constrained project scheduling problem, Expert Syst. Appl. 42 (2015) 6039–6049.
[30] S. Droste, T. Jansen, I. Wegener, On the analysis of the (1+1) evolutionary algorithm, Theor. Comput. Sci. 276 (2002) 51–81.
[31] A. Santiago, B. Dorronsoro, H. Fraire, P. Ruiz, Micro-genetic algorithm with fuzzy selection of operators for multi-objective optimization: 𝜇FAME, Swarm Evol.
Comput. 61 (2021) 100818.
[32] Z. Liu, Z. Hua, L. Yang, R. Deng, Search space decomposition for resource-constrained project scheduling, Autom. Constr. 134 (2022) 104040.
[33] C. Coello, G. Pulido, A micro-genetic algorithm for multiobjective optimization, in: International Conference on Evolutionary Multi-criterion Optimization, 2001,
pp. 126–140.
[34] R. Madadi, C. Balaji, Optimization of the location of multiple discrete heat sources in a ventilated cavity using artificial neural networks and micro genetic
algorithm, Int. J. Heat Mass Transf. 51 (2008) 2299–2312.
[35] F. Au, Y. Cheng, L. Tham, Z. Bai, Structural damage detection based on a micro-genetic algorithm using incomplete and noisy modal test data, J. Sound Vib. 259
(2003) 1081–1094.
[36] Y. Toklu, Application of genetic algorithms to construction scheduling with or without resource constraints, Can. J. Civ. Eng. 29 (2002) 421–429.
[37] H. Zoulfaghari, J. Nematian, N. Mahmoudi, M. Khodabandeh, A new genetic algorithm for the RCPSP in large scale, Int. J. Appl. Evol. Comput. 4 (2013) 29–40.
[38] A. Halim, I. Ismail, S. Das, Performance assessment of the metaheuristic optimization algorithms: an exhaustive review, Artif. Intell. Rev. (2020) 1–87.
[39] M. Vanhoucke, J. Coelho, A tool to test and validate algorithms for the resource-constrained project scheduling problem, Comput. Ind. Eng. 118 (2018) 251–265.
[40] Z. Hua, Z. Liu, Y. Yang, L. Yang, Improved genetic algorithm based on time windows decomposition for solving resource-constrained project scheduling problem,
Autom. Constr. 142 (2022) 104503.
[41] M. Abdar, F. Pourpanah, S. Hussain, D. Rezazadegan, L. Liu, M. Ghavamzadeh, P. Fieguth, X. Cao, A. Khosravi, U. Acharya, A review of uncertainty quantification
in deep learning: techniques, applications and challenges, Inf. Fusion 76 (2021) 243–297.
[42] S. Chakraborty, D. Paul, S. Das, t-Entropy: a new measure of uncertainty with some applications, ArXiv Preprint, arXiv:2105.00316, 2021.
[43] C. Tzelepis, V. Mezaris, I. Patras, Linear maximum margin classifier for learning from uncertain data, IEEE Trans. Pattern Anal. Mach. Intell. 40 (2017)
2948–2962.
[44] A. Alkeshuosh, M. Moghadam, I. Al Mansoori, M. Abdar, Using PSO algorithm for producing best rules in diagnosis of heart disease, in: Proc. of International
Conference on Computer and Applications, 2017, pp. 306–311.
[45] M. Zomorodi-moghadam, M. Abdar, Z. Davarzani, X. Zhou, P. Pławiak, U. Acharya, Hybrid particle swarm optimization for rule discovery in the diagnosis of
coronary artery disease, Expert Syst. 38 (1) (2021) e12485.
[46] F. Wang, H. Zhang, A. Zhou, A particle swarm optimization algorithm for mixed-variable optimization problems, Swarm Evol. Comput. 60 (2021) 100808.
[47] Y. Duan, C. Liu, S. Li, Battlefield target grouping by a hybridization of an improved whale optimization algorithm and affinity propagation, IEEE Access 9 (2021)
46448–46461.