0% found this document useful (0 votes)
47 views

Example Problem

Uploaded by

Lakshmi Prameela
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
47 views

Example Problem

Uploaded by

Lakshmi Prameela
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Example Problem

A project consists of the following activities with their respective durations and dependencies:

Activity Duration (days) Predecessors


A 4 -
B 3 A
C 5 A
D 2 B
E 6 C, D
F 4 E

Tasks:

1. Determine the earliest start (ES), earliest finish (EF), latest start (LS), latest finish (LF),
and slack for each activity.
2. Identify the critical path.

Solution Steps

1. Calculate ES and EF:


o Activity A:
▪ ES = 0
▪ EF = ES + Duration = 0 + 4 = 4
o Activity B:
▪ ES = EF of A = 4
▪ EF = 4 + 3 = 7
o Activity C:
▪ ES = EF of A = 4
▪ EF = 4 + 5 = 9
o Activity D:
▪ ES = EF of B = 7
▪ EF = 7 + 2 = 9
o Activity E:
▪ ES = Max(EF of C, EF of D) = Max(9, 9) = 9
▪ EF = 9 + 6 = 15
o Activity F:
▪ ES = EF of E = 15
▪ EF = 15 + 4 = 19
2. Calculate LS and LF:

Start from the end of the project:

o Activity F:
▪LF = EF = 19
▪LS = LF - Duration = 19 - 4 = 15
o Activity E:
▪ LF = LS of F = 15
▪ LS = LF - Duration = 15 - 6 = 9
o Activity D:
▪ LF = LS of E (D is not directly linked to F) = 9
▪ LS = LF - Duration = 9 - 2 = 7
o Activity C:
▪ LF = LS of E = 9
▪ LS = LF - Duration = 9 - 5 = 4
o Activity B:
▪ LF = LS of D = 7
▪ LS = LF - Duration = 7 - 3 = 4
o Activity A:
▪ LF = Min(LS of B, LS of C) = Min(4, 4) = 4
▪ LS = LF - Duration = 4 - 4 = 0
3. Calculate Slack:

Slack = LS - ES

o Activity A: 0 - 0 = 0
o Activity B: 4 - 4 = 0
o Activity C: 4 - 4 = 0
o Activity D: 7 - 7 = 0
o Activity E: 9 - 9 = 0
o Activity F: 15 - 15 = 0
4. Identify the Critical Path:

The critical path consists of activities with zero slack. In this case, the critical path is:

A → B → D → E → F (Total Duration = 19 days)

Summary

• Critical Path: A → B → D → E → F
• Total Project Duration: 19 days
• All activities have zero slack, indicating they are critical

You might also like