11.5 Static - Eqp - Proc010 - Ok
11.5 Static - Eqp - Proc010 - Ok
11.5 Static - Eqp - Proc010 - Ok
REV ISSUE DATE EXPIRED DATE ISSUE PURPOSE PRE’D CHE’K APP’D
CONTRACTOR
1.0 SCOPE
2.0 OBJECTIVE
This is to assure that all the installation of static equipment is follow the Codes,
Specification and Client requirements. To maintain the acceptable workmanship
during the installation works.
3.0 REFERENCE
4.0 RESPONSIBILITIES
5.1.1 All equipment shall be checked on received at site for any damage
and any missing parts from the packing list. If any discrepancies
found shall be reported as described in the material control
procedure. An OSD (Overage, Shortage, Damage) report shall be
prepared for any discrepancies.
5.1.2 Normally these equipments such as Heat Exchangers are has
purging protection with N2. This condition of purging shall be
checked and controlled in weekly period. If the pressure of
purging is decrease or become zero pressure, we shall be reported
to Client, whether the purge will be fill-in again or not.
5.1.3 Care shall be taken to transportation and storage of the equipment
to make sure proper procedures are adopted as per manufactures
recommendations.
5.3.1 The orientation four position ( 0º, 90º, 180º and 270º ) to be
marked on the equipment for checking orientation as per drawing.
5.3.2 Leveling and verticality shall be done with packing plates and
shims to correct location and elevation and checked with plumb at
least 4 points.
5.3.3 If not specified, maximum plumb not more than 25 mm or 1/200 h
wherever the smaller to be used.
5.3.4 Once the equipment has been set in correct location and elevation
and approved the base can be grouted with approved grouting
materials.
5.3.5 Before grouting, recheck the concrete surface to ensure that it is
free from dirt, oil, grease, or any loose materials.
5.3.6 The surface to be grouted shall be saturated with water for at
least 24 hours in advance. Any free standing water must be
removed before placing the grout.
5.3.7 The excess or protruding liner has to be cut-off and welded
together.
5.3.8 All attachments can be connected to the equipment after the grout
is set as per manufactures instructions.
5.4 Inspection
When equipment has been installed and ready for inspection, the QC
Engineer shall arrange and to invite the Client Representative to witness
and approve the location and orientation check as per Inspection & Test
Plan (ITP).
6.0 DOCUMENTATION
6.1 All Inspection Records shall be filed and documented as per procedure
6.2 After construction works are finished as contract, all original required
documentations as per contract shall be submitted to Client and copied
for our file.