11.8 Instrument Installation Procedure
11.8 Instrument Installation Procedure
11.8 Instrument Installation Procedure
REV ISSUE DATE EXPIRED DATE ISSUE PURPOSE PRE’D CHE’K APP’D
CONTRACTOR
1 of 19
JASA MAINTENANCE SURFACE FACILITIES DI SPG MERBAU
DAN METERING STATION PAGAR DEWA PT PERTAMINA
ZONA 4 FIELD PRABUMULIH
Rev.0
1.0 TITLE
2.0 SCOPE
The specification given are adequate for the majority of applications. However, for
unusual situation, such as very high temperatures and/or pressure, corrosive
conditions etc,. alternate procedure may be required.
3.0 OBJECTIVE
This is to assure that the installation of instruments and devices are done as per
the specification requirements, drawings and applicable codes. To make sure that
all the works are satisfactorily done, tested and accepted according to contract
specifications.
4.0 REFERENCE
5.0 RESPONSIBILITY
5.1 The Instrument Engineer at site shall be responsible for the planning
scheduling and coordination, record and monitor progress of
instrumentation works. To guide the supervisors in the field in terms of
engineering and technical problems.
2 of 19
JASA MAINTENANCE SURFACE FACILITIES DI SPG MERBAU
DAN METERING STATION PAGAR DEWA PT PERTAMINA
ZONA 4 FIELD PRABUMULIH
Rev.0
6.1 GENERAL
6.1.1 Field Engineers will ensure that they are in possession of the
following documents, prior to the commencement of construction
activities:
6.1.2 The work shall be done according to good workmanship by using the
suitable tools and material as stated in the construction drawing and
procedures and it should be studied before carry out any
Instrumentation works.
6.1.3 Form reports which will be in the possession of Field Engineers and
which will be completed during the major construction activities
include:
Full care and pre-caution shall be given by the field management for
the safety and sanitation of workman in the field to prevent accidents
during execution of the works.
3 of 19
JASA MAINTENANCE SURFACE FACILITIES DI SPG MERBAU
DAN METERING STATION PAGAR DEWA PT PERTAMINA
ZONA 4 FIELD PRABUMULIH
Rev.0
6.2.1 When receiving the instrument materials and before delivered to the
field it will be subjected to the following inspections by warehousing:
4 of 19
JASA MAINTENANCE SURFACE FACILITIES DI SPG MERBAU
DAN METERING STATION PAGAR DEWA PT PERTAMINA
ZONA 4 FIELD PRABUMULIH
Rev.0
a) Transmitter will be inspected for zero, span and linearity throughout its
range.
e) All process switches (e.g. pressure) will be verified for correct activation
point.
All field devices on the Instrument check list shall be marked with a “tic”
under each applicable item for every category on the list and non
applicable items shall be marked “N/A”. An item shall be checked off only
when the inspector is satisfied that the installation meets the criteria listed
below. Items failing to satisfy this criteria shall be noted on a “punch list” for
the contractor to rectify.
i. Fabrication
5 of 19
JASA MAINTENANCE SURFACE FACILITIES DI SPG MERBAU
DAN METERING STATION PAGAR DEWA PT PERTAMINA
ZONA 4 FIELD PRABUMULIH
Rev.0
ii. Location
iii. Installation
6 of 19
FABRICATION, INSTALLATION AND
MAINTENANCE SERVICES
Document No.
Project Title : Date :
TMG - FM - SOP - Rev.0
8 March 2022
10021
iv. Painting
i. Location
ii. Installation
7 of 19
FABRICATION, INSTALLATION AND
MAINTENANCE SERVICES
Document No.
Project Title : Date :
TMG - FM - SOP - Rev.0
8 March 2022
10021
• The correct size and type of wiring lugs are used and they are
firmly and properly attached to the wires.
8 of 19
FABRICATION, INSTALLATION AND
MAINTENANCE SERVICES
Document No.
Project Title : Date :
TMG - FM - SOP - Rev.0
8 March 2022
10021
• Cables are identified with the correct tags using the proper
markers.
• Conduit and tray are routed using the most direct practical
path, between it’s terminal points, that generally follows
structural members and/or equipment where possible.
• Conduit bends are neat and properly made using the correct
bending tools for the job.
• Fittings are of the correct type and size and are properly
tightened.
• Tubing bends are neat and properly made using the correct
bending tools for the job.
• Air supply tubing and branch piping is routed using the most
direct practical path, between it is terminal points, that
11 of 19
FABRICATION, INSTALLATION AND
MAINTENANCE SERVICES
Document No.
Project Title : Date :
TMG - FM - SOP - Rev.0
8 March 2022
10021
i. Location
12 of 19
FABRICATION, INSTALLATION AND
MAINTENANCE SERVICES
Document No.
Project Title : Date :
TMG - FM - SOP - Rev.0
8 March 2022
10021
ii. Installation
iii. Cabling/Wiring
• The correct size and type wiring ferrules are used and they
are firmly and properly attached to the wires.
13 of 19
FABRICATION, INSTALLATION AND
MAINTENANCE SERVICES
Document No.
Project Title : Date :
TMG - FM - SOP - Rev.0
8 March 2022
10021
• All cables enter and leave field junction boxes from the
bottom, or sides when necessary, but not from the top.
6.5.1 General
14 of 19
FABRICATION, INSTALLATION AND
MAINTENANCE SERVICES
Document No.
Project Title : Date :
TMG - FM - SOP - Rev.0
8 March 2022
10021
6.5.2 Organization
6.5.3 Communications
Three portable radios will be assigned to each check out team. One
in the control room, one in the rack room one in the field. Each
team’s set of three radios shall operate on a frequency independent
from other check out teams. Each radio shall have it’s own spare
15 of 19
FABRICATION, INSTALLATION AND
MAINTENANCE SERVICES
Document No.
Project Title : Date :
TMG - FM - SOP - Rev.0
8 March 2022
10021
6.5.4 Documentation
Phase B
- YS – 170 + FA – M3 + DAQ Panel
SLS - D
- FA – M3 + DAQ
SLS – A
- DCS existing
- PFCD existing
6.5.5 Preparations
A daily check out plan will be prepared for each team by the
instrument engineer(s).
This plan will be based on the requirements of the commissioning
schedule and all document necessary to execute the work shall be
prepared in advance.
Before starting each day’s work the check out teams will attend a
short meeting with the engineer for distribution of the appropriate
documentation and to discuss the planned activities.
Another short meeting will be held at the end of each day for
collection of the documentation and to discuss the day’s work.
6.5.6 Methods
ii. The field instrument technician will prepare the devices for
check out as required and secure the devices as necessary
after the check out is complete.
e.g. Remove covers, check wiring, turn on air and/or power
supplies, open process taps, disconnect signals, connect
test equipment, perform test procedures, reconnect signals
and wiring, reinstall covers, etc.
iii. The DCS engineer will direct the actual testing activities once
the field device has been prepared. He will operate the DCS as
required and perform any special manipulations such as
bypassing interlocks or forcing outputs when necessary to
execute a particular test(Yokogawa scope).
17 of 19
FABRICATION, INSTALLATION AND
MAINTENANCE SERVICES
Document No.
Project Title : Date :
TMG - FM - SOP - Rev.0
8 March 2022
10021
6.5.7 Procedures
ii. Identification tags for all devices, junction box, cables, etc. shall
be verified as being in place and correct.
iv. DCS indications must correspond to the signals sent from the
field devices. Engineering units, zero and full scale values,
linear, compensations, integrate, graphic dynamics, state
descriptors etc. in both the field devices and the DCS must be in
concordance with each other as well as with the engineering
documentation.
vi. Signal shall be sent to and from the DCS to confirm correct
connectivity and functionality only. Activities such as calibrating
field devices, programming the DCS, modifying control strategic,
changing graphics etc. are to be avoided during loop checking.
vii. Only small repairs and corrections that can be made quickly
(within a few minutes) shall be done by the check out team (e.g.
– changing wires from N.O. to N.C. contacts on switches,
reversing signal polarities, etc.). More extensive changes should
be noted on the punch list for later action by others.
18 of 19
FABRICATION, INSTALLATION AND
MAINTENANCE SERVICES
Document No.
Project Title : Date :
TMG - FM - SOP - Rev.0
8 March 2022
10021
viii. The check out team must, however, troubleshoot all problems
until the cause of the fault is determined. Any problems or
deficiencies placed on the punch list must be accompanied by a
description of the corrective action to be taken.
ix. Control valves and other final control elements shall have their
power or air supplies turned on and they shall be fully stroked
from 0 % to 100 % via the DCS. Correct control action in
automatic mode shall be verified if possible.
xi. After a loop check has been successfully completed power and
air shall remain turned on to the field devices and process
connections shall remain open, unless specific instructions to
the contrary have been given by an authorized person.
7.0 ATTACHMENT :
19 of 19