Work Methodology-Building Works
Work Methodology-Building Works
CITILINK
SOLUTIONS LIMITED
1
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
TABLE OF CONTENTS
WORK METHODOLOGY FOR BUILDING CONSTRUCTION.......................................................1
1.0 PURPOSE.........................................................................................................................................2
2.0 SCOPE..............................................................................................................................................2
3.0 ROLES AND RESPONSIBILITIES................................................................................................2
3.1 Project Leader/Manager...............................................................................................................2
3.2 Site Agent.....................................................................................................................................2
3.5 Supervisor/Foreman.....................................................................................................................3
3.3 QA/QC Engineer..........................................................................................................................3
3.4 Safety Officer...............................................................................................................................3
3.6 Mason...........................................................................................................................................3
3.7 Plumber.........................................................................................................................................4
3.8 Electrician.....................................................................................................................................4
4.0 REFERENCED DOCUMENTS......................................................................................................4
5.0 ABBREVIATIONS..........................................................................................................................4
6.0 INSPECTION AND TESTING.......................................................................................................4
7.0 WORK PERMITS............................................................................................................................4
8.0 HEALTH SAFETY AND ENVIRONMENTAL PROCEDURES..................................................4
9.0 HOUSEKEEPING............................................................................................................................5
10.0 QUALITY CONTROL / ASSURANCE REQUIREMENTS........................................................6
11.0 MATERIALS.................................................................................................................................6
12.0 MANPOWER.................................................................................................................................7
13.0 NECESSARY TOOLS & EQUIPMENT’S...................................................................................7
14.0 DETAILED METHODOLOGY....................................................................................................8
14.1 Initial Survey & Site Checking...................................................................................................8
14.2 Setting Out..................................................................................................................................8
14.3 Excavation for Foundations........................................................................................................8
14.4 Back filling and Compaction......................................................................................................9
14.5 Construction of RCC Foundation, Columns, Grade Beam, Roof Beam and Slab.....................9
14.6 Reinforcing Steel Works............................................................................................................9
14.7 FormWork Construction Methodology....................................................................................10
14.8 Procedure for Placing of Concrete...........................................................................................10
14.9 Compacting / Vibrating of Concrete........................................................................................10
14.10 Curing of Concrete.................................................................................................................11
14.11 Construction Joints Method....................................................................................................11
14.12 Checking Water Content & Slump Testing............................................................................11
14.13 Testing of Concrete................................................................................................................11
14.14 Methodology for Waterproofing Works.................................................................................12
14.14.1 Surface Preparation.........................................................................................................12
2
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
3
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
1.0 PURPOSE
The purpose of this construction methodology is to specify the requirements of civil building
construction activities including excavation, backfilling, and allied activities complying with
the contract documents, project specifications as per the scope of work and approved
drawings/documents.
This method statement also covers requirements for earthworks associated with trenches for
pipelines or service ducts etc.
4
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
2.0 SCOPE
Scope of work for this Method Statement applies to all the civil works related to the
construction of building as per project requirements, referring with approved Civil and MEP
drawings i.e.:
The primary responsibility of carrying out all the activities mentioned in this procedure rests
with the site in charge / project head unless mentioned otherwise. Below are brief details
about different roles.
CITILINK
SOLUTIONS LIMITED
Track project progress against scope information and generate Interim Payments
certificates
3.3 Supervisor/Foreman
3.4 Mason
3.5 Plumber
CITILINK
SOLUTIONS LIMITED
3.6 Electrician
Responsible for the monitoring and implementing of quality related matters and
ensure the works are being executed with the approved Project Quality Plan and
requirements of the Contract Documents, approved method statement and ITPs.
5.0 ABBREVIATIONS
CITILINK
SOLUTIONS LIMITED
Site-in-charge: For the purpose of this procedure, the term Site-In-charge shall mean
Project/Site Engineer.
Site inspection/approval shall be in accordance with the approved Inspection and Test Plan
for all activities in addition to the Quality Control Procedure and Project Quality Plan for the
Project.
All the required site test shall be conducted as per the relevant sections in the specification
documents for all disciplines.
All necessary work permits shall be obtained prior to the commencement of any activity at
site and shall remain valid throughout the entire duration of the operation or as per the dates
and times mentioned.
Safety Barriers and Site sign boards will be installed prior to the work commencement.
Requirements of Health, Safety and Environmental for the project shall be in accordance
with approved Project HSE Plan, the contract document and applicable legal requirements.
Before commencing of any work, the required and applicable work permits shall be checked
and ensure all requirements of WP are complied and they are valid until completion of the
activity and as per approved HSE plan.
All personnel accessing their site will wear the mandatory PPE.
Workmen and staff shall wear the mandatory and job specific Personnel Protective
Equipment’s.
Pre-task briefing shall be conducted on every day before starting the day work.
Experienced and HSE inducted workmen shall be deployed for the work.
All personnel shall be cautioned while working near any live lines such as power cable,
water lines, drainage lines, telecom etc.
Hazards identified for the activity shall be disseminated during pre task briefing, especially
for underground services, slip & trip, improper access, excavation tools handling, no access
or egress, vehicle collision, heat exhaustion, which shall be identified and documented
separately by permit to work system as per approved HSE plan.
8
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
First aid stations complete with all first aid equipment’s and trained first aiders shall be
maintained for the initial care.
Safety and security procedures shall be implemented as a minimal, warning signs and lights,
barricades, railing and other safeguards shall be provided as required by the nature and
location of the work.
Electrical and mechanical waste will be segregated at source and transported to dedicated
segregated waste storage area and not be allowed to accumulate on site in undesignated
areas.
Concrete waste will be removed from work areas at regular intervals to designated areas.
Construction waste will be disposed as per local laws & client guidelines by licensed carrier
to a licensed facility.
9.0 HOUSEKEEPING
Housekeeping is the act of keeping the working environment clean from all unnecessary
waste materials.
The equipment/tools/materials required for the work shall be stored /stacked in such a
manner so as to give a safe working atmosphere to the workforce at site.
All workplace areas shall be maintained clear of debris, waste and other rubbish, which shall
be disposed of in segregated containers for disposal.
Adequate number of containers marked appropriate labels for storage and disposal of waste
materials shall be strategically placed throughout the construction areas at all time.
Any spillages, such as oil or grease shall be immediately cleaned up, by absorption in inert
sand or other suitable materials.
The materials for the particular work shall be stored at site so that there is no obstructions to
the work or access to the workforce.
Debris, waste oil containers etc. shall be stacked and placed in a barricaded location away
from the work areas and access routes.
Before leaving the site at end of day, it shall be ensured by the responsible person that the
site area is cleaned and no obstruction is encountered for next day work.
CITILINK
SOLUTIONS LIMITED
Quality Assurance and Control for the above mentioned activities shall be exercised and
recorded in accordance with the contract documents, quality assurance documents and the
approved Project Quality Plan for the project.
The quality assurance shall be ensured for workmanship, equipment’s and materials
conformance to the applicable standards and requirements at every stage of the construction.
This shall be monitored by quality control personnel or designated substitute on the site
during the construction / production / operation.
Quality assurance requirements shall also be imposed upon sub contractors, suppliers,
manufacturers and any other parties associated and involved in the construction project.
All inspections and tests shall be conducted in accordance with written test procedures as
detailed in the Project Quality Plan and Inspection and Test Plan approved by the consulting
engineers.
Applicable documents with latest version such as Inspection & Test Plan, Method
Statements shall be readily available and used by inspection and test personnel at the time of
inspection as referring documents.
11.0 MATERIALS
Material approval shall be obtained for all the materials with reference to Client’s preferred
vendor list, prior to commencement of activities.
Material Inspection Request (MIR) will be submitted to client upon material arrival to
project site store/warehouse.
All materials must be stored properly as per the manufacturer’s recommendations and
quality control procedures.
The material shelf life will be monitored as per Manufacturer’s data sheets.
12.0 MANPOWER
Site Engineer
Supervisor/Foreman
HSE Inspector
QA/QC Inspector
Carpenters
Steel Fixers
Masons
Plumbers
Helpers
Painters
10
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
Operators
Drivers & Technicians
The following equipment’s and tools shall be used for the various activities.
Excavators
Shovels
JCB
Self-Loaders
Bobcat
Tipper Trucks / Trailers
Water Tankers
Rollers/Compactors
Transit Mixers
Concrete pump
Vibrators
Dewatering pump
Mobile crane
Angle Grinders
Cutters
Drilling Machines
Wheel Barrows
Bagger mixer
Hand tools
Upon receipt of Job Instruction / Drawing from Consultant Engineer, an initial site visit to be
made along with the consultant representative to confirm the site and demarcations.
Proper Safety Fencing and site sign boards will be installed prior to the construction
activities.
The foundation location of building shall be set out and elevations marked by the Land
Surveyor using steel pins and paint markings.
In case of any obstruction or existing services, it shall be intimated to the Consultant and
necessary modifications shall be carried out after getting approval from Consultant Engineer.
Prior to commencement of excavation, the location shall be checked to ascertain the type of
soil to be excavated and appropriate equipment shall be deployed.
11
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
The excavation work for building shall be carried out by using excavator and the excavated
soil to be tested for suitability and shall be stock piled at convenient locations at site if
suitable for back filling purpose and surplus soil to be loaded in to the tippers and unloaded
at designated location later.
Battered excavation slopes greater than 1.5 meter height shall be supported and all locations
where the excavation extents below the ground water table, a dewatering system shall be
provided which will lower ambient groundwater levels.
The resulting groundwater level shall be at depth which is sufficiently below the excavation
level so as to allow the safe and proper execution of the work.
Excavated soil shall be piled at least 2.0 meter away from all the sides of the excavated area
and the area shall be protected by barricading and unauthorized entry shall be restricted. For
deep excavations more than 1.50 meter or average man height depth with loose soil, sides
shall be protected by means of temporary shoring and strutting.
Excavation shall be carried out for a width of at least 500 mm beyond the horizontal outside
limits of the building.
In narrow spaces, due to confined space condition suitable safety measures & ventilation
shall be arranged.
On reaching the required level of excavation, the surface shall be leveled and cleaned of all
traces of loose material.
All excavated areas shall be barricaded and appropriate signs shall be provided as required.
Over excavation should be provided with SRC 20 concrete to the required level.
Back filling shall be done in layers of not more than 250mm loose thickness and each layer
thoroughly watered and rammed to ensure Minimum Dry Density of 95%.
Testing of compaction will be performed as directed by the engineer. Earth work under
substructure shall be provided with anti-termite treatment for the approval of the Engineer.
14.5 Construction of RCC Foundation, Columns, Grade Beam, Roof Beam and Slab
The bottom of excavation shall be compacted and offered for inspection and testing by the
consultant Engineer. Over excavation should be provided with SRC 20 concrete to the
required Level.
12
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
On approval of above activity, 75mm thick blinding concrete shall be laid to the required
levels and size, supplied from approved ready mix plant.
After completing the excavation works, activities for Foundation to be carried out first,
followed with columns up to slab height completed later plinth and inside room work to be
started.
Engineer’s approval will be obtained for reinforcement work before using in permanent
works.
All reinforcement will be kept to protect from damage, free from dirt, loose mill scale, rust
scale paint, oil, or other foreign substances.
As per the specifications & drawing, the bar bending schedules & bar lists, cutting schedules
for each individual structure will be prepared by the contractor and will obtained the
approval from the engineer.
Manual cutter or mechanical cutter will be used for cutting of bars & bending machine will
be used for bending of bars.
All reinforcement will be cleaned by a wire brush or any other means before placing.
Reinforcement placed should comply with the drawings. Lap length will be taken into
account according to the project specification when binding reinforcement bars.
Supports and scaffolding will be GI pipes, Arco props, sawn timber or round timber.
The dimensions & position of formwork will be carefully checked after erection.
Oil or grease will be used to avoid adhesion of mortar and to achieve a smooth surface.
Before placing concrete all dirt, wood chips, hardened concrete or mortar and all other
foreign matter will be removed from the forms.
Before fixing of form work, detailed drawing will be submitted to the engineer for approval.
Well qualified foreman will be appointed for fixing on formworks & reinforcement work.
13
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
The method for placing of concrete will be worked out to prevent segregation of the material
& Engineer’s approval will be taken before concreting begins.
Before placing concrete all formwork therein will be cleaned of all extraneous material and
dust and made free of any standing water.
In continuing concrete, fresh concrete will be placed before the already placed concrete is
less than 20 minutes.
Concrete of specified grade will be placed & compacted in horizontal layers normally not
exceeding 300mm in depth.
Concrete will not be dropped from a height greater than 1.5 meter to prevent segregation.
Concrete will be free of all rock pockets, honey combs & voids.
Complete Records showing the details of placing concrete in each part of the work will be
maintained and will be available for inspection at the site.
For this stand by units will be available in the site during the period of compacting.
Continuous curing will be carried out in a moist atmosphere for a minimum period of 10
days and for a further period required by engineer.
Concrete area will be kept covered with hessian clothes or Polyethylene sheets which will
retain moist throughout the curing period.
The surface of the hardened concrete will be cleaned and made free from laitance, and will
also have an exposed aggregate finish.
The fresh concrete will be placed and compacted so that it bonds properly to the prepared
surface of the previously laid concrete.
Laitance on the surface will be completely removed from the concrete in order to achieve a
good bond with fresh concrete.
14
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
Between one and two hours after placing concrete, water will be sprayed gently and laitance
will be removed with two brushes, one with soft and other with hard bristles.
After finishing this operation, just the tips of the aggregate should be visible.
If the laitance has hardened, a wire brush will be used to remove it.
Water stops in construction joints will be installed & approval for this will be taken from the
engineer.
Frequent slump test will be carried out in accordance with BS 1881 on samples of concrete
taken immediately before placing to determine the consistency of concrete.
All the test reports will be maintained in the site office & will be available for the inspection
whenever required.
All necessary arrangements for the sampling & testing of fresh & harden concrete in
accordance with the BS 1881 will be taken.
Crushing test will be carried out on concrete cubes formed in 150mm molds.
One set of cubes (2 cubes crushed in 7 days & other in 28days) will be done to maintain the
quality of work.
Particular care will be taken to ensure that the test cubes are stored under uniform conditions
in the site & during any transit between site & concrete testing laboratory.
Ensure that all preceding activities are completed which cannot be accessed after
waterproofing works are inspected, released and approved.
Obtain MEP clearance and clearance from other specialist trades which may not be
accessible after waterproofing, prior to commencing waterproofing works.
All surfaces to receive waterproofing to be clean, dry and free from dirt, dust, oil and grease.
Wall Protrusions that likely to punch through the waterproofing films to be removed either
by using a chipping hammer or grinder.
15
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
Prepare and level the concrete surfaces for waterproofing either by chipping, hacking or
scraping the surface.
Repair the excessive pinholes, and similar imperfections (if any) to eliminate uneven
surface.
Raise an inspection request for surface preparation (RFI) prior to the waterproofing work
commences.
Immediately after the inspection use Viscose Elastic type adhesive tape at weak joints and
sharp edges.
Levels should be true, square and in plumb at locations as indicated on the approved shop
drawings/IFC drawings.
Install waterproof level pads also to serve as guides in controlling the final thickness of the
waterproof and the finished plane of the waterproofed surface, relative to the accessories
installed.
Ensure all other trades in the said location are put on hold during the waterproof application
so to protect and avoid any damage to the waterproofing layers.
Apply first coat using a manual brush application uniformly at a workable consistency.
Floor application should continue to the vertical wall face up to a minimum of 150mm as per
the project specifications.
Ensure all surfaces to receive waterproofing fluid application firmly to achieve good
adhesion and to be in one continuous operation.
16
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
Approved Bitumen Impregnated Protection Boards should be provided for protection with
sufficient lapping as per the manufactures recommendation.
Footings shall be protected by 4mm thick waterproofing membrane sheets laid on concrete
surfaces primed with bituthene primer.
Laid sheets shall be protected from Damage by using bituminous protection boards or 40mm
SRC screed concrete as horizontal protection.
Vertical faces shall be protected against damage from backfilling by using protection boards.
Approval shall be obtained from the Engineer prior to commence the backfilling works.
Block works shall be done as per approved drawings and shall comply with project
specifications.
All block works executed below ground level built with S.R.C cement and shall built in
S.R.C mortar.
Normal weight Hollow Blocks having a minimum compressive strength of 7.0 N/mm2 shall
be used.
Samples of each type of masonry unit and accessory shall be submitted to consultant for
approval. Approval is mandatory before start of work.
Marking up of exact location of block walls and openings as per approved shop drawings
shall be done before commencing the work.
Block marked areas shall be cleaned and wet before starting the activity for block work.
17
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
One course of block only will be executed for testing and approval by the consultant.
Walls shall be kept level at all times and carried up in a uniform manner. No part being
raised more than 1500mm above any adjacent unbuilt course.
Angles & Reveals shall be kept true, square and plumb all the time.
Horizontal joints shall be leveled all the time and vertical joints in alternate courses shall be
plumb and line.
Opening frames shall be set and maintained square, plumb, true and furnished with anchors.
Install reinforced concrete block lintels or GI steel lintels over openings as per approved
shop drawing or cast in places as per specification.
Top of block partitions and sides will be supported by using galvanized steel anchors/ties as
per approved shop drawings and material submittals.
Concrete block walls and partitions shall be reinforced horizontally each second course, last
top course, second and third course above lintels and below sills of opening with the
required over lap.
After completing of each section of the walls, cleaning shall be done to the down surfaces
and curing will start immediately.
Final inspection shall be carried out for the entire work for approval of the engineer.
Prepare surfaces for the smooth or non-absorbent solid surfaces that do not have the suction
capability to receive a solid plaster bases by chipping, wire brushing or sand blasting, as
appropriate.
18
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
Install beads at their locations plumbed and squared. And it will be best achieved by using
galvanized nails or small quantities of mortar and as per manufacturer’s recommendations.
Now install the corner, control joints and movement beads at locations indicated in the
drawings and manufacturer’s instructions.
Spray water on the wall surface and throw the spatter dash mix (scratch coat) by using a
spatter dash manual machine in a way to form a rough layer 3-5mm thick without any
attempt to level or smooth it. The rough surface shall be kept damp with fine water spray or
by covering with polyethylene sheet until it sets down.
Apply plaster/render coat after the scratch coat had hardened. Initially, a thin coat is
troweled on the scratch coat to ensure a thorough bonding at the surface.
The remainder of the render coat is then built up using wooden float to receive textured
finish until the required thickness met.
Apply final thin coat plastering using steel trowel on the interior surface to match with the
Architect’s sample as specified.
The coating thickness shall not deviate more than +/- (6.4mm in 3m) from the trueness of the
plastered finish, as measured with straight edge placed on the surface.
The newly applied external coatings shall be cured and protected against frost, heat, and rain
for the first 48 hours using canvass, cloth or sheet, hung clear at the plaster surface.
Moist curing by applying a fine fog spray of water, generally twice daily in the morning and
evening.
All the doors & louvers shall be Galvanized Steel (powder coated) as per approved drawings
and specifications.
Doors should be distributed according to the layout and door code marking.
Level should be marked using proper level instrument showing clearly the floor finish level.
Necessary reference lines and elevation shall be reflected using permanent pen marking.
19
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
Ensure the reference labels on delivered doors are correctly reflected from references
provided and carefully inspected considering the code/mark per designated location.
The door is then positioned and with the lay-out reference string carefully positioning the
door on both its horizontal and vertical alignment with the use of level bar plumbs.
The door frame is then temporarily fixed using clamp and wedge at the top and bottom of
the door opening.
Screws are drilled into the edges on locations where the frame will be supported until proper
depth into the concrete wall.
With the frame fixed and pinholes or slots drilled into walls, prepare for the setting of the
door following the procedure specified in the installation manual supplied by the door
manufacturer.
Architrave shall be accurately shaped to fit the contour of the door frame surface.
Clearance around the door shall be +/-3 mm (unless otherwise specified) in order that door
opens and closes without any obstacles by the door frame.
Cleaning and removal of excess materials at the work area shall be done prior to the
inspection and approval by the consultant.
Any work done without such approval shall be redone to the Engineer’s satisfaction, without
additional expense to the Employer.
Manufacturer’s chart showing all the variety of paint/texture coating shall be submitted for
color/texture selection.
The Engineer will furnish a schedule of color/texture of each area and surface.
Approved quality Weather Shield/Weather Coat paint shall be used for painting the exteriors
of the structures or other surfaces where specified on the drawings as directed by the
consulting engineer.
The plastic emulsion paint/vinyl emulsion paint or similar as approved by the Engineer shall
be used for interior surfaces.
20
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
Textured coating wherever specified shall be acrylic resin based coating composed of acrylic
copolymers, natural quartz, natural marble chips, metallic oxide, antibacterial and antifungal
additives, and expanders, foaming and setting agents and shall be applied in accordance with
approved manufacturer’s recommendations.
All material shall be delivered to site in their original unbroken containers or packages &
shall bear the manufacturer’s name, label, brand & formula & will be mixed and applied in
accordance with his directions.
All oil, grease, dirt, dust, loose mill scale and any other foreign substance shall be removed
from the substrate surface to be painted/coated, polished and white washed by the use of a
solvent and clean wiping material.
Following the solvent cleaning, the surface shall be cleaned by scrapping, chipping, blasting,
wire brushing or other effective means as approved by the Engineer.
Surfaces of stainless steel, aluminum bronze and machined surfaces adjacent to metal work
being cleaned or painted shall be protected by effective masking or other suitable means,
during the cleaning and painting operations.
All the surfaces to be painted/coated with approved quality paint/coat shall be free from
dust, dirt, fungus, lichen, algae etc.
Oil paint, varnish and lime wash should always be removed by scraping and washing.
Paints and coating materials shall be in a thoroughly mixed condition at the time of
application.
All work shall be done in a workman like manner leaving the finished surface free from
drips, ridges, waves, lapse and brush marks.
Paint shall be applied under dry and dust free conditions unless approved by the Engineer
paint shall not be applied when the temperature of the metal or the surrounding air is below
7 degree centigrade.
When paint is applied by spraying, suitable measures shall be taken to prevent segregation of
the paint in the container during painting operation.
Effective means shall be adopted for the removing all free oil and moisture from the air
supply lines of the spraying equipment.
Each coat of paint shall be allowed to dry or harden thoroughly before the succeeding coat is
applied.
21
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
Surface to be painted that will be inaccessible after installation shall be completely painted
prior to installation
Coats of Weather Shield Coat paint and textured coating shall be applied in accordance with
manufacturer’s instructions or as directed by the Engineer.
For painting only as much material should be mixed as can be used up in one hour.
After the first coat the surface will be soaked evenly four or five times and the second coat
shall be applied after leaving for at least overnight.
Where shown on drawings all the exterior finishes shall be painted/coated with Weather
Shield/weather coat paint or texture coated in approved color/textures as per the
manufacturer’s specifications.
The number of coats shall be shown on the drawings or as directed by the Engineer.
Plastic emulsion paint, vinyl emulsion paint or matt enamel paint of the approved make and
shade shall be applied to surfaces as shown on drawings as per manufacturer’s instructions.
Material Samples as per Project specifications shall be submitted for the approval of finish,
texture, color and thickness from Engineer.
The GRC panels shall be stored at site in a dry, clean and leveled area properly protected
from any accidental damage.
Before erection the Site Engineer/Supervisor shall check the panel size as per the approved
drawings, the color and texture with the approved sample and for any damage while loading
& unloading. Any major defects, if noted, in any panel will be rejected and sent back to the
Factory for replacement.
Prior to the starting of installation, the lifting equipment i.e. crane and the access to the site
have to be arranged.
Prior to the starting of grc panel installation, co-ordinate with the Engineer and make sure
that all levels and reference levels are as per the approved drawings.
22
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
Alignment is required for the exterior face of the panel and proper marking with string lines
to be done prior to the start of installation.
Based on the confirmation of alignment and marking of fixing points, approved brackets are
fixed to the structural frame.
Ensure proper access to the fixing area from the storage area.
The GRC panels will be lifted with suitable lifting devices by using the lifting points
provided by manufacturer.
The GRC panels are set level, plumb, square and true within the allowable tolerances and
fixed to the bracket with suitable approved loose fixings.
After the Engineer checks the finishing of panels, sealant work is carried out according to
the project specifications using the approved sealant and backing rod.
Utmost care shall be given to apply the joint sealant as to not stain the GRC panels.
After fixing of the panel for the alignment, plumpness and squareness (with
allowable tolerances).
On finishing the patching works prior to sealing the joints.
After completion of the joint sealants when ready for final hand-over.
Tool Box meetings shall be conducted on every day before the start of the work.
All personnel shall be cautioned while working near the pipes/ cables.
Hazard identification shall be done during toolbox meetings especially for hot weathers.
23
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]
WORK METHODOLOGY
CITILINK
SOLUTIONS LIMITED
In order to ensure a safe working environment during the entire construction period, the
following safety measures will be implemented for Machinery and Equipment:
Prior to use any machinery/equipment at site, it shall be inspected and certified by qualified
person.
All operators and driver are to be equipped with valid driver’s/operator’s license or permit
from concerned government agency.
Also authorized signalman shall be assigned together with the operator or driver.
All lifting equipment as well as its accessories such as sling wire, nylon sling, shackles,
chain blocks, crane hook and latch shall be inspected periodically.
PPE shall be issued to all workers such as safety shoes, hard hat, working gloves, ear plugs,
safety goggles and safety belt and or safety harness for workers who will be assigned in
elevated places. Wearing of the basic PPE shall be enforced fully.
Emergency contact numbers for Project Manager, Site Engineer and Safety officer shall be
displayed on working area prominently.
You can download the construction methodology in pdf format by clicking the below link.
Also you can download complete civil work method statements from our portal page.
24
P.O.BOX 316-01001, Kalimoni, Kenya Cell: 0783 202 020 Email: [email protected]