Business Processes in SAP S/4HANA Discrete Shopfloor Control
Business Processes in SAP S/4HANA Discrete Shopfloor Control
.
.
PARTICIPANT HANDBOOK
INSTRUCTOR-LED TRAINING
.
Course Version: 26
Course Duration: 1 Day(s)
Material Number: 50166206
SAP Copyrights, Trademarks and
Disclaimers
No part of this publication may be reproduced or transmitted in any form or for any purpose without the
express permission of SAP SE or an SAP affiliate company.
SAP and other SAP products and services mentioned herein as well as their respective logos are
trademarks or registered trademarks of SAP SE (or an SAP affiliate company) in Germany and other
countries. Please see https://www.sap.com/corporate/en/legal/copyright.html for additional
trademark information and notices.
Some software products marketed by SAP SE and its distributors contain proprietary software
components of other software vendors.
National product specifications may vary.
These materials may have been machine translated and may contain grammatical errors or
inaccuracies.
These materials are provided by SAP SE or an SAP affiliate company for informational purposes only,
without representation or warranty of any kind, and SAP SE or its affiliated companies shall not be liable
for errors or omissions with respect to the materials. The only warranties for SAP SE or SAP affiliate
company products and services are those that are set forth in the express warranty statements
accompanying such products and services, if any. Nothing herein should be construed as constituting an
additional warranty.
In particular, SAP SE or its affiliated companies have no obligation to pursue any course of business
outlined in this document or any related presentation, or to develop or release any functionality
mentioned therein. This document, or any related presentation, and SAP SE’s or its affiliated companies’
strategy and possible future developments, products, and/or platform directions and functionality are
all subject to change and may be changed by SAP SE or its affiliated companies at any time for any
reason without notice. The information in this document is not a commitment, promise, or legal
obligation to deliver any material, code, or functionality. All forward-looking statements are subject to
various risks and uncertainties that could cause actual results to differ materially from expectations.
Readers are cautioned not to place undue reliance on these forward-looking statements, which speak
only as of their dates, and they should not be relied upon in making purchasing decisions.
Demonstration
Procedure
Warning or Caution
Hint
Facilitated Discussion
TARGET AUDIENCE
This course is intended for the following audiences:
● Application Consultant
● Super / Key / Power User
● Business User
Lesson 1
Analyzing Master Data for Discrete Manufacturing 2
Exercise 1: Analyze Master Data 7
UNIT OBJECTIVES
LESSON OBJECTIVES
After completing this lesson, you will be able to:
● Describe the Relevant Master Data for Production Orders
Note:
In this section, we will briefly recapitulate the most important concepts.
Additionally, you can also refer to the SAP Application Documentation: Material
Master, BOM, Routing, Work Center, Production Version , PRT.
Materials
Figure 1: Materials
Material master records must be created for the materials that are produced and procured in
a company. In our bicycle company, for example, material master records were created for
the finished bicycles for the required assemblies that are produced in-house, such as frames
or wheels, and for raw materials to be procured via purchasing, such as chains or metal tubes.
In the material master record of each item, planning data, procurement data, production
execution-relevant data, and so on, are maintained.
Bill of Material (BOM)
The material components required for finished products and assemblies are to be defined via
bills of materials (BOMs). The bill of material for a bicycle manufactured in our bicycle
company can, for example, consist of the material components frame, wheel, chain, and
further components. Assemblies, such as the frame of a bicycle themselves have a BOM,
which results in multi-level BOM structures.
You furthermore define, in a BOM, how many components are required to assemble a
product. For example, one bike requires the assembly of two wheels, front and rear wheel,
respectively.
The BOM is used in production planning to determine, for example, how many items of a
purchased raw material are required in a certain time frame. The system then compares the
amount of on-stock items to the required quantity and creates, if necessary, a purchase
requisition. In production execution, the SAP S/4HANA system uses the BOM in a production
order to determine how many items of a raw material are required to produce the requested
quantity. In our example, the production of 100 bicycles would require 200 wheels, 100
frames, and 100 chains.
Figure 3: Routing
Animation: Routing
For more information on Routing, please view the animation in the lesson
Analyzing Master Data for Discrete Manufacturing in your online course.
Routings define, in detail, which operations are to be carried out to manufacture a finished
product or an assembly. The master data specialist also defines the sequence in which the
individual operations must be executed. For example, a routing for the production of a bicycle
can consist of the operations: Pre-assembly, Assembly, and Quality Inspection that must be
executed in the sequence shown in the above figure.
A work center is assigned to each operation to define the physical location where this
operation is to be processed. By assigning a work center, you also specify costing- and
planning-relevant parameters for the individual operations since the master record of a work
center contains essential information that is used for capacity planning, scheduling, and
costing of production orders. In our example, the "pre-assembly" of the bike is executed at
work center assembly I, the operation "assembly" is executed at work center assembly II, and
so on.
Furthermore, production resources/tools (PRTs) can be assigned to an operation. A
production resource/tool assigned in the operation "assembly" can be, for example, a
document with detailed instructions illustrating the main assembly steps to the worker.
A production order for a finished product or an assembly is always created with reference to a
production version of the corresponding material. A production version defines which routing
in combination with which bill of material is to be used for the production order. A suitable
production version is automatically selected when the order is created according to criteria
such as production quantity and production time.
Why do you need production versions in SAP S/4HANA? Let's consider the following
example: Depending on the number of bikes to be manufactured, the Bike Company has two
options to execute the manufacturing process. They can either use an automated assembly
line for high production quantities or a sequence of work centers where operators manually
execute the assembly process for smaller lot sizes. In the latter case, it does not make sense
to use the automated assembly line due to high setup times. However, the BOM is identical for
both production scenarios. To model this scenario in SAP S/4HANA, you can define two
production versions:
● Production version A combines the BOM for the bike with a routing where all operations
are executed on the work center 'Automated Assembly Line'. This production version is
used for lot sizes bigger than, for example, 1000 pc.
● Production version B combines the BOM for the bike with a routing where all operations
are executed on the manually operated work centers 'Pre-assembly', 'Assembly', and
'Quality Inspection'. This production version is used for lot sizes smaller than, for example,
1000 pc.
You are almost finished with displaying the relevant master data for production orders.
Finally, you will learn how to display the remaining master data, routing, and work center.
Note:
If you have access to the practice system, you can now do the exercise Analyze
Master Data.
Business Scenario
Your company manufactures bicycles. As a production engineer, you will analyze the
corresponding master data.
Note:
In this exercise, when a value or object name contains ##, replace ## by the
number your trainer assigned to you.
1. Execute the Display Multilevel BOM Explosion app to analyze the multilevel BOM structure
of your finished product, T-FSP1## Bike Special.
In the initial screen, enter the following data:
Field Value
Material T-FSP1##
Plant 1010
Alternative BOM 1
2. In the Display Multilevel BOM screen, check the multilevel BOM structure for material T-
FSP1##. Note the BOM structure in the following table:
Field Value
Material
Description
Base Qty (PC)
.1
..2
..2
..2
...3
....4
....4
...3
.1
..2
..2
.1
.1
3. Execute the Display Bill of Material app to display the BOM of material, T-FSP1##.
In the initial screen, enter the following data:
Field Value
Material T-FSP1##
Plant 1010
BOM Usage 1
Alternative BOM 1
4. In the Display Material BOM: General Item Overview screen, review the components of the
BOM and complete the following table.
1. Execute the Display Routing app to display the routing for material, T-FSP1##.
In the Display Routing: Initial Screen, enter the following data:
Field Value
Material T-FSP1##
Plant 1010
2. In the Display Routing: Operation Overview screen, note some information on the
operations in the following table:
Operation Work center Control key PRT
>
>
>
3. Now, select operation 0010 in the Operation Overview table and choose Detail to display
the Operation Details screen. Write down the Setup, Machine, and Labor time elements.
Task 3: Analyze Stocks and Post Goods Receipts for Material Components
In the following exercises, we assume that the stocks of the material components required to
produce the finished product, T-FSP1##, have been procured in sufficient quantities.
You check the stocks of the material components and fill them up to 2000 PC each.
1. Execute the Stock – Single Material tile to analyze the stocks of the material components:
T-SSP1##, T-SSP2##, and T-RSP1##, respectively. How many items are available in plant
1010 at storage location 101B of each material?
Note down the available quantities: T-SSP1## (_____ pc), T-SSP2## (_____ pc), T-
RSP1## (_____ pc).
2. Now, create a goods receipt for the materials so that 2000 pc of each component are
available.
Result
You created goods receipts for the three materials: T-SSP1##, T-SSP2##, and T-RSP1## so
that the following exercises can be executed.
Business Scenario
Your company manufactures bicycles. As a production engineer, you will analyze the
corresponding master data.
Note:
In this exercise, when a value or object name contains ##, replace ## by the
number your trainer assigned to you.
1. Execute the Display Multilevel BOM Explosion app to analyze the multilevel BOM structure
of your finished product, T-FSP1## Bike Special.
In the initial screen, enter the following data:
Field Value
Material T-FSP1##
Plant 1010
Alternative BOM 1
2. In the Display Multilevel BOM screen, check the multilevel BOM structure for material T-
FSP1##. Note the BOM structure in the following table:
Field Value
Material
Description
Field Value
.1
..2
..2
..2
...3
....4
....4
...3
.1
..2
..2
.1
.1
Material T-FSP1##
Description Bike Special
Base Qty (PC) 1
.1 T-SSP1## Frame 1 PC L
..2 T-RSP5## Metal Tube 1 PC L
..2 T-RSP6## Seat Metal Tube 1 PC L
..2 T-SSP3## Bike Paint Red 0,1 L L
...3 T-SPT1## Basic Paint 0,1 L L
....4 T-RPT3## Basic Paint Mix 0,01 KG L
....4 T-RPT4## Solvent Mix 0,1 L L
.1 T-SSP2## Wheel 2 PC L
..2 T-RSP7## Rim with Spokes 2 PC L
..2 T-RSP8## Tyre and Tube 2 PC L
.1 T-RSP1## Chain 1 PC L
.1 T-DSP100 Bike Standard Assembly 1 PC D
Instruction
3. Execute the Display Bill of Material app to display the BOM of material, T-FSP1##.
In the initial screen, enter the following data:
Field Value
Material T-FSP1##
Plant 1010
BOM Usage 1
Alternative BOM 1
4. In the Display Material BOM: General Item Overview screen, review the components of the
BOM and complete the following table.
1. Execute the Display Routing app to display the routing for material, T-FSP1##.
In the Display Routing: Initial Screen, enter the following data:
Field Value
Material T-FSP1##
Plant 1010
2. In the Display Routing: Operation Overview screen, note some information on the
operations in the following table:
Operation Work center Control key PRT
>
>
>
3. Now, select operation 0010 in the Operation Overview table and choose Detail to display
the Operation Details screen. Write down the Setup, Machine, and Labor time elements.
Task 3: Analyze Stocks and Post Goods Receipts for Material Components
In the following exercises, we assume that the stocks of the material components required to
produce the finished product, T-FSP1##, have been procured in sufficient quantities.
You check the stocks of the material components and fill them up to 2000 PC each.
1. Execute the Stock – Single Material tile to analyze the stocks of the material components:
T-SSP1##, T-SSP2##, and T-RSP1##, respectively. How many items are available in plant
1010 at storage location 101B of each material?
Note down the available quantities: T-SSP1## (_____ pc), T-SSP2## (_____ pc), T-
RSP1## (_____ pc).
a) Open the Stock - Single Material app.
c) You find the available quantity in column, Unrestricted-Use stock. The actual quantity
depends.
2. Now, create a goods receipt for the materials so that 2000 pc of each component are
available.
a) Select line item: Std. Storage 2 101B.
c) In column Unrestricted-use Stock, choose the icon to the right of the available quantity
(the icon shows an arrow pointing upwards).
d) In the field Quantity, enter the quantity that is missing so that 2000 pc are available in
total. If 110 pc were available in the first step, enter 1890, tab out of the field, and
choose Post.
f) Change the entry in the field, Material (T-SSP2## or T-RSP1##), choose Enter, and
execute substeps c-e to create goods receipts for the remaining two materials.
Result
You created goods receipts for the three materials: T-SSP1##, T-SSP2##, and T-RSP1## so
that the following exercises can be executed.
LESSON SUMMARY
You should now be able to:
● Describe the Relevant Master Data for Production Orders
Learning Assessment
1. Which of the following statements regarding master data for production orders is
correct?
Choose the correct answers.
X A A production version defines which PRTs in combination with which work centers
are to be used for the production order.
X C The material components and documents required for finished products and
assemblies are to be defined via routings.
2. In the context of production, for which material types must you create material master
records?
Choose the correct answers.
X A Finished products
X B Semi-finished products
X C Raw materials
X D Office supplies
X A Components to be assembled
X B Component quantities
X C Manufacturing operations
X A Components to be assembled
X B Component quantities
X C Manufacturing operations
X A BOM
X B Routing
X C Work center
Lesson 1
Applying the Integration with Production Planning 20
Exercise 2: Assign your Area of Responsibility 23
Exercise 3: Create Planned Independent Requirements, and Run MRP 25
UNIT OBJECTIVES
LESSON OBJECTIVES
After completing this lesson, you will be able to:
● Apply the Integration with Production Planning
The in-house production process starts with the definition of a demand program. There are
two basic planning strategies: make-to-stock production and make-to-order production. In
the case of make-to-stock production, planned independent requirements are created based
on forecasts; in the case of make-to-order production, sales orders are created in Sales. In
our bicycle company, both planning strategies are used. Bicycles with a relatively constant,
predictable sales volume are produced in make-to-stock production, while more expensive
special bicycles that require a more complex production process are produced in make-to-
order production.
The stock and requirements situation for materials is checked regularly in material
requirements planning (MRP). In case of shortage situations, planned orders are created to
cover the planned independent requirements and sales orders. In our bicycle company, an
MRP run is usually carried out once a day.
Close to the time of production, the planned orders are then converted into production
orders. While planned orders represent planned receipts of MRP that can be dynamically
adjusted by the regular planning runs, production orders contain detailed instructions for
production on how to manufacture the materials and can no longer be automatically changed
by MRP. In our bicycle company, planned orders due are converted into production orders
once a day in background processing.
Order execution includes steps such as staging the required material components and
confirming the processed operations. The goods receipts of the finished products in inventory
management complete the order processing for production.
Note:
From a production execution point of view, it does not matter whether production
orders are executed in a make-to-stock or make-to-order scenario.
After having maintained planned independent requirements, they are processed by the MRP
run to generate planned orders.
In the following demonstration, you will see how planned independent requirements are
maintained by the production planner.
Monitor Material Coverage, Execute MRP Run, and Analyze Planning Result
Proposed sales quantities for, for example, make-to-stock manufacturing of bikes, are
maintained as planned independent requirements. The system compares the requirements
and the stock evaluation over time and determines whether the requirement is covered or
not. If the requirements are covered from stock, planned orders or production orders that
already exist, the MRP run does not create additional planned orders. If the requirements are
not covered, the MRP run generates planned orders that can be converted into production
orders to manufacture the missing quantities, for example, bikes.
In the next demonstration, you will learn how to execute the MRP run and compare the
material coverage situation before and after the MRP run.
Note:
If you have access to a practice system, you can now execute the exercises Assign
your Area of Responsibility and Create Planned Independent Requirements, and
Run MRP.
Business Scenario
You must assign your area of responsibility in order to use certain apps in requirements and
capacity planning.
Note:
In this exercise, when a value or object name contains ##, replace ## by the
number your trainer assigned to you.
1. Execute the My Area of Responsibility - MRP Controller to assign your MRP controller,
P##, in plant 1010.
Business Scenario
You must assign your area of responsibility in order to use certain apps in requirements and
capacity planning.
Note:
In this exercise, when a value or object name contains ##, replace ## by the
number your trainer assigned to you.
1. Execute the My Area of Responsibility - MRP Controller to assign your MRP controller,
P##, in plant 1010.
a) Open the app.
d) In the AOR Status column, choose the slider so that it shows a green check mark. The
system issues a confirmation AOR Assigned.
Business Scenario
Based on sales forecasts, a planner specifies requirements for the make-to-stock (MTS)
production of the bicycles. An MRP controller schedules an MRP run, checks the result, and
converts planned orders to production orders.
Note:
In this exercise, when a value or object name contains ##, replace ## by the
number your trainer assigned to you.
1. Execute the Change Material app to set up the make-to-stock planning strategy 40
Planning with final assembly for your finished product, T-FSP1## Bike Special on tab MRP
3 for plant 1010.
2. Execute the Maintain PIRs tile to create planned independent requirements for your
finished product, T-FSP1## Bike Special. Starting from the current week + 2 until the
current week + 10, enter requirements of 30 pc for each week. Activate the requirements.
Result
You maintained planned independent requirements so that you can execute the MRP run and
create planned orders.
1. Execute the Monitor Material Coverage app to check the stock availability for the materials
T-FSP1## and the components T-SSP1##, T-SSP2##, and T-RSP1##.
4. Return to the Stock/Requirements List for product, T-FSP1##, and choose Start MRP
Run.
Result
You successfully executed the MRP run and created planned order for the planned
independent requirements of the finished material, T-FSP1##. On component level, the
creation of planned orders triggered the creation of dependent requirements. As there is
enough stock available, the latter can be fulfilled by quantity on stock.,
Business Scenario
Based on sales forecasts, a planner specifies requirements for the make-to-stock (MTS)
production of the bicycles. An MRP controller schedules an MRP run, checks the result, and
converts planned orders to production orders.
Note:
In this exercise, when a value or object name contains ##, replace ## by the
number your trainer assigned to you.
1. Execute the Change Material app to set up the make-to-stock planning strategy 40
Planning with final assembly for your finished product, T-FSP1## Bike Special on tab MRP
3 for plant 1010.
a) Open the app.
d) In the window, Organizational Levels, enter in the field, Plant, 1010 and choose
Continue.
e) On the MRP 3 tab, in the field, Strategy Group, enter 40 and choose Save.
2. Execute the Maintain PIRs tile to create planned independent requirements for your
finished product, T-FSP1## Bike Special. Starting from the current week + 2 until the
current week + 10, enter requirements of 30 pc for each week. Activate the requirements.
a) Open the app.
b) In the Maintain PIRs screen, enter the following data and choose Go:
Field Value
Material T-FSP1##
Plant 1010
c) Select the line item checkbox for material, T-FSP1##, and choose Create. Do not click
on the line item!
e) In the Maintain Quantities per Period table, maintain the following entries:
Period Draft PIRs
Actual week 0
g) Choose Save.
Result
You maintained planned independent requirements so that you can execute the MRP run and
create planned orders.
1. Execute the Monitor Material Coverage app to check the stock availability for the materials
T-FSP1## and the components T-SSP1##, T-SSP2##, and T-RSP1##.
a) Open the app.
b) Select the line items for materials, T-FSP1##, T-SSP1##, T-SSP2##, and T-RSP1##,
and choose Manage Materials.
b) There are 2000 pc of this material on stock. There are no dependent requirements.
4. Return to the Stock/Requirements List for product, T-FSP1##, and choose Start MRP
Run.
a) Choose T-FSP1## on the left side of the screen.
Result
You successfully executed the MRP run and created planned order for the planned
independent requirements of the finished material, T-FSP1##. On component level, the
creation of planned orders triggered the creation of dependent requirements. As there is
enough stock available, the latter can be fulfilled by quantity on stock.,
LESSON SUMMARY
You should now be able to:
● Apply the Integration with Production Planning
Learning Assessment
X A Quantities to be produced
X B Required components
2. In a make-to-stock scenario, which item do you maintain in the SAP S/4HANA system to
trigger the creation of planned orders?
Choose the correct answer.
X A Sales orders
X C Purchase requisitions
X A Production orders
X B Process orders
X C Planned orders
X D Purchase orders
Lesson 1
Executing the Various Steps of Production Order Processing 35
UNIT OBJECTIVES
LESSON OBJECTIVES
After completing this lesson, you will be able to:
● Execute the Various Steps of Production Order Processing
Order Processing
The Bike Company has prepared the necessary master data and the planned orders were
handed over from production planning. Now it's time for production execution. During order
execution, a production order goes through many steps.
Watch the following video to get an overview of the individual steps. In the following units, you
will get to know the most important processing steps in more detail.
Production order goes through many different steps in its lifecycle. The main steps in order
processing are order creation, order release, goods issues, confirmations, and goods
receipts. In principle, a production order can be created in many ways, whereby order
creation by planned order conversion is typical. When an order is created, the required
master data is selected, and the order is scheduled. A corresponding status 'created' is
set. With a status created, an order cannot be processed in production, for example, goods
movements and confirmations cannot be posted. When an order is released, it is made
available to production for processing. A corresponding status 'released' is set. In the release
status, goods issues, confirmations, and goods receipts can now be posted, to name a few
examples. By posting goods issues and material components to production orders, the
corresponding material consumption is recorded and stock quantities and stock values are
decreased. By posting goods receipts for the finished products, the corresponding production
quantities are documented and stock quantities and stock values of the products are
increased.
In between the main steps, the system offers various supporting functions, for example,
availability checks, capacity evaluation and leveling, download to process control, order
printing, material staging, and upload from process control. Between order creation and order
release, you execute various checks ensuring that the order can be correctly
processed. Material availability checks are used to ensure that the required
material components are available in the required quantity at the required time. Capacity
evaluation and capacity leveling are used to ensure that the work centers required in
production are not overloaded, and are used as efficiently as possible. For paper-based
production processes, various order-related documents, for example, goods issue slips,
confirmation slips, and PRT lists, can be printed after order release. In many companies,
manufacturing execution systems are used to orchestrate the flow of the order on the shop
floor. In this case, order information is downloaded from the SAP S4/HANA system to the
process control system and actual data. For example, material consumption and confirmation
data is uploaded in the opposite direction. Before the goods issue postings to the production
order are possible, it might be required that the material components must be staged from a
central storage location to the production storage location.
LESSON SUMMARY
You should now be able to:
● Execute the Various Steps of Production Order Processing
Learning Assessment
1. Which of the following statements regarding the execution of a production order are
correct?
Choose the correct answers.
X A By goods receipt postings for the finished products the corresponding production
quantities are documented and stock quantities and stock values of the products are
increased.
X C The main steps in order processing are material requirements planning, capacity
leveling, goods issues, quality inspections, and goods receipts.
X D Material availability checks are intended to ensure that the work centers required
in production are not overloaded.
2. Which of the following processes can you execute for a production order in status
created?
Choose the correct answers.
X B Goods issue
X C Goods receipt
X D Confirmations
X E Capacity evaluation
3. Which of the following processes can you only execute after a production order was
released?
Choose the correct answers.
X B Goods issue
X C Goods receipt
X D Confirmations
X E Capacity evaluation
4. Which of the following statements about capacity evaluation and leveling is correct?
Choose the correct answer.
X A Capacity evaluation and leveling are intended to ensure that the work centers
required in production are not overloaded.
X B Capacity evaluation and leveling are intended to ensure that the required material
components are available in the required quantity at the required time.
X A Material availability checks are intended to ensure that the work centers required
in production are not overloaded.
X B Material availability checks are intended to ensure that the required material
components are available in the required quantity at the required time.
Lesson 1
Creating Production Orders 40
Exercise 4: Convert A Planned Order 43
UNIT OBJECTIVES
LESSON OBJECTIVES
After completing this lesson, you will be able to:
● Create Production Orders
As already described in the previous unit, planned orders are created by material
requirements planning as planned material receipts to cover requirements. In the case of in-
house production, planned orders are then converted into production orders close to the time
of production. In this unit, we will discuss which methods the Bike Company can use to
convert planned orders to production orders.
In most cases, multiple planned orders are converted into production orders at the same
time. Based on the Bike Company's business requirements, they can convert planned orders
into production orders using collective conversion. During conversion, the system converts
each planned order into exactly one production order (resulting in n production orders for n
planned orders). To select planned orders to be converted, you can specify various selection
criteria, for example plant, MRP controller, opening date, material, and so on.
Alternatively, the MRP controller from the Bike Company can manually convert one planned
order into one production order using individual conversion or even create several production
orders from one planned order by means of partial conversion (for example, if the
manufacturing resources are not available due to unplanned events or if there is a component
shortage). When converting one planned order, it is deleted and replaced by the production
order.
On component level, dependent requirements are replaced by reservations once the planned
order was converted into a production order.
Note:
You can, at any time, also manually create production orders, for example in the
case of urgent, unplanned orders such as repairs or customer order. In this case,
material, quantity, and date must be entered manually when creating the order.
For additional information about manual order creation, refer to the SAP Help
Portal. To obtain more information about planned order conversion, review this
section of the SAP Application Assistance.
When scheduling a planned order, a start date, a finished date, and a planned opening date
are determined. The planned opening date represents the date on which the planned order
should be converted into a production order. In collective conversion, you can specify an
opening period for selecting planned orders that are due for conversion. All planned orders
whose planned open opening date lies within the specified opening period are converted. In
this example, the opening date of the first and second planned order lie within the opening
period and are therefore converted. The third planned order will be converted at a later point
in time when it becomes relevant for production.
Note:
If you have access to a practice system, you can now execute the exercise Convert
a Planned Order.
As an MRP controller, you convert the next planned order into a production order and analyze
the production order from an MRP point of view.
1. Execute the Monitor Material Coverage app and convert the first planned order for the T-
FSP1## material to a production order. Analyze the result of order conversion for the T-
RSP1## component.
Result
You converted the first planned order of the finished material, T-FSP1##, to a production
order.
As an MRP controller, you convert the next planned order into a production order and analyze
the production order from an MRP point of view.
1. Execute the Monitor Material Coverage app and convert the first planned order for the T-
FSP1## material to a production order. Analyze the result of order conversion for the T-
RSP1## component.
a) Open the app.
b) Select the check box for line items corresponding to materials, T-FSP1## and T-
RSP1##, and choose Manage Materials.
c) In the section, Material Details, for material, T-FSP1##, select the drop-down in
column, Actions, for the first planned order. Note: The button shows Edit and a
chevron pointing downwards. Select the chevron!
d) Choose Convert.
h) In the section, Material Details, for material, T-RSP1##, there is one order reservation
(corresponding to the production order you created in step e) and eight dependent
reservations (for the remaining eight planned orders).
Result
You converted the first planned order of the finished material, T-FSP1##, to a production
order.
LESSON SUMMARY
You should now be able to:
● Create Production Orders
Learning Assessment
1. If you convert one planned order, what is the result in the SAP S/4HANA system?
Choose the correct answer.
2. What happens in the SAP S/4HANA system if you convert a planned order?
Choose the correct answers.
3. Which information must you provide if you manually create a production order?
Choose the correct answers.
X A Material to be manufactured
X B Quantity to be manufactured
X C Required components
X D Routing to be used
X A You convert planned orders into production orders at the beginning of each
quarter.
X B You create a list of planned orders at the beginning of each week and manually
convert them to production orders.
X C You convert planned orders into production orders that are due for production in
the near future.
5. Which options does the SAP S/4HANA system offer to create production orders?
Choose the correct answers.
X B You can automatically create a production order if the supplier confirms your
purchase order for required raw materials.
X E You can automatically create production orders by executing the MRP run.
Lesson 1
Releasing Production Orders 50
Exercise 5: Release a Production Order 55
Lesson 2
Posting Goods Issues for Production Orders 59
Exercise 6: Post Goods Issues for a Production Order 63
Lesson 3
Confirming Production Orders 67
Exercise 7: Confirm Operations of a Production Order 71
Lesson 4
Posting Goods Receipts for Production Orders 75
Exercise 8: Post the Goods Receipt for a Production Order 79
UNIT OBJECTIVES
LESSON OBJECTIVES
After completing this lesson, you will be able to:
● Release Production Orders for Execution
Order Release
Current Process Step
The next step in the lifecycle of a production order is the order release. From a business
perspective, the Bike Company releases orders that are ready for production execution. This
means that, for example, all required components are available (→ availability checks) and
the manufacturing resources have enough free capacity to execute the order(s) as planned
(→ capacity evaluation and leveling). As you can see in the figure, order release is usually
executed after availability checks and/or capacity evaluation were performed.
What happens during availability check? As discussed in chapter Business Process Overview:
From Planning to Order Execution, you assemble components to manufacture a product. In
our bike example, frames, wheels, chains, and so on, are assembled to the Special Bike. These
components must be available at the production site. In a nutshell, the availability check in
SAP S/4HANA compares the quantity of a component that is required by a production order
to the, for example, available quantity of a component. If there is enough to be used, the
availability check is positive and the production order can be executed. If there is a
component shortage, the system informs the user accordingly and the production order
cannot be executed. In this case, additional components must be procured or components
from other, less important orders must be reallocated to this production order to be able to
execute this order.
Note:
For more information about missing parts and the availability check, refer to the
SAP Help Portal.
What happens during capacity evaluation? Similar to component checks, the manufacturing
resources, for example, an assembly line, must have enough free capacity so that an order
operation can be executed on that resource. Capacity evaluation compares the capacity
offered by a work center to the capacity required by an operation. If there is enough capacity,
you can execute the order as planned. Otherwise, the production supervisor must reschedule
orders that are currently allocated to this machine so that enough free capacity is available to
execute the order in question.
After component availability checks and capacity evaluation is done, you release the order. It
is only then that the subsequent processing steps, such as order printing, goods issue
postings, confirmations, and goods receipt postings can be executed in the SAP S/4HANA
system. From a technical point of view, releasing the order corresponds to a status change
from created to released: Only after this status change, you can execute the subsequent
processing steps.
If the SAP S/4HANA system is configured accordingly, the shop order papers are
automatically printed upon order release. Shop order papers might be required to process an
order if your company does not leverage a paperless production process, for example, using a
manufacturing execution system. Some examples of shop order papers are:
● Time tickets or confirmation slips: With these documents, the shop floor personnel
documents their efforts.
● Pull list or material withdrawal list: With these documents, the shop floor personnel are
informed about the components that shall be assembled. Sometimes, warehouse
personnel use these documents to execute material stating.
● Object overview: Using this list, shop floor personnel gets an overview over the entire
order. From a business perspective, you would usually use this document as a process slip
that accompanies the order through the entire production process.
Note:
For more information about shop order papers, refer to the SAP Help Portal.
Finally, the lifecycle image shows the optional step, download to process control: You use this
functionality in SAP S/4HANA if you execute your production process leveraging a
manufacturing execution system (MES), for example, SAP Digital Manufacturing or any other
third party MES. After order release, the order and related data is transferred to the MES that
takes over execution from that point in time. During production execution, workers interact
with the MES by confirming produced quantities, efforts, component consumptions, etc.
Afterward, the MES transfers this data back to the SAP S/4HANA system (upload from
process control) to ensure that data across systems is consistent.
You must first decide whether you want to release an entire production order or individual
operations of one order. If you release the entire order, the operations in the order are
automatically released. If you release individual operations of one order, you must also
respect the sequence of operations.
Usually, you release an entire order so that the shop floor personnel can smoothly execute a
production order without additional system constraints. However, if you want to ensure that a
subsequent operation can only be executed after a previous operation was completed, you
release the individual operations of an order one after the other. From a business perspective,
you typically choose the latter approach for complex orders (with many operations) that
require that the sequence of operations is strictly followed.
Individual Release
When individually releasing orders or operations, you manually release each object
individually in the system. For example, if an express order is received from a customer and
you immediately want to start production of the requested product, you manually create the
express order and directly release it so that the requested product can be immediately
produced.
Collective Release
Usually, you don't release orders or operations individually since a high manual effort is
required. Instead, you select several orders and release them collectively, for example, using
the Manage Production Orders app. To select production orders to be released, you can
specify various selection criteria, for example, plant, production scheduler, release date,
material, and so on. In our Bike Company example, all orders that are due for execution in the
next week are automatically released by the Production Supervisor in the week prior to
execution.
Note:
In principle, this approach corresponds to the time-oriented conversion of planned
orders which we discussed in a previous chapter.
Note:
If you have access to a practice system, you can now perform exercise Release a
Production Order.
As a production supervisor, you release the production order for the finished product, T-
FSP## Bike Special, and review the operation status as well as the result of the component
availability check.
1. Use the Manage Production Orders app to analyze and release a production order for the
T-FSP1## material. When you start the app for the first time, you must specify as an area
of responsibility a combination of plant, 1010, and production supervisor, P##.
3. Click in the line of the production order to proceed to the order details. Review the data on
the tabs, Order Information, Components, Order Schedule, and Confirmation. What is the
operation status? Have the quantities been committed?
4. Now, release the order and review the operation status and committed component
quantities.
Result
After releasing the order, all operations of the order are also released. The required
component quantities are now committed.
As a production supervisor, you release the production order for the finished product, T-
FSP## Bike Special, and review the operation status as well as the result of the component
availability check.
1. Use the Manage Production Orders app to analyze and release a production order for the
T-FSP1## material. When you start the app for the first time, you must specify as an area
of responsibility a combination of plant, 1010, and production supervisor, P##.
a) Open the app.
c) In the My Area of Responsibility - Production Supervisor screen, assign the AOR Status
for production supervisor P## in plant 1010.
d) Choose the Back button to navigate to the Manage Production Order screen.
3. Click in the line of the production order to proceed to the order details. Review the data on
the tabs, Order Information, Components, Order Schedule, and Confirmation. What is the
operation status? Have the quantities been committed?
a) In the list, Orders, choose the line item of the production order to navigate to the order
details.
b) On the application header, choose the tab, for example, Order Information, and review
the data.
c) On the application header, choose the tab, Order Schedule, and review the operation
status. All three operations are in status, Created, as shown in the column, Status.
d) On the application header, choose the tab, Components, and review the component
coverage. As indicated by the red status bar in the column, Coverage, the items have
not been committed, yet.
4. Now, release the order and review the operation status and committed component
quantities.
a) Choose Release.
b) On the application header, choose the tab, Order Schedule, and review the operation
status. All three operations are in status, Released, as shown in the column, Status.
c) On the application header, choose the tab, Components, and review the component
coverage. As indicated by the green status bar in the column, Coverage, the items have
been committed now.
Result
After releasing the order, all operations of the order are also released. The required
component quantities are now committed.
LESSON SUMMARY
You should now be able to:
● Release Production Orders for Execution
LESSON OBJECTIVES
After completing this lesson, you will be able to:
● Post Goods Issues for Production Orders
Goods Issues
Current Process Step
Let's continue with the next step in the production process of our new bike. After order
release, goods issues are posted by the warehouse clerk or shop floor personnel. From an
inventory perspective, the number of components on stock is decreased. In our scenario, this
means that the bike components (for example frame, wheels, chains, etc.) are withdrawn
from the warehouse, the respective on stock quantity is decreased and the component
consumption is posted against the order.
How do you know which components shall be withdrawn from inventory? When an order is
created, the system automatically determines the bill of material and creates a reservation for
all required material components in the required quantity. Each material component of the
order receives a separate item number within the reservation. You can only withdraw the
reserved materials from the warehouse if the operation to which the materials are assigned in
the order has already been released. For each reservation item, the following information is
available:
As you can see in the figure above, material staging might precede the goods issue posting:
This is a warehouse process that organizes the staging of a material from a central storage
location to your production storage location before you can post the goods issue in the
system, for example, if purchased components are delivered to the Bike Company's central
warehouse, but their shop floor corresponds to a separate storage location in the SAP S/
4HANA system.
Assuming that the required component materials are already available at the production
storage location, 101B in our example, you can post a goods issue to a production order using
one of the following options:
● Manual goods issue posting, for example, using the Post Goods Movement or Pick
Components for Production Orders apps.
● Automatic goods issue posting together with the order confirmation, for example, using
the Confirm Production Order app.
● Automatic goods issue posting together with the operation confirmation, for example,
using the Confirm Production Order Operation app.
In the case of manual goods issue posting, the system proposes the component quantity and
the issue storage location since both are maintained in the reservation item. You can either
accept the proposed values or change the quantities and/or storage locations as required.
You can withdraw a lower quantity if, for example, you only manufacture a fraction of the
ordered quantity, or a higher quantity if, for example, some components were destroyed
during the assembly process.
In the case of automatic goods issue posting (→ component materials with a backflush
indicator) together with a confirmation posting, the system automatically posts a goods issue
at the storage location maintained in the reservation item when the operator posts the order
or operation confirmation. The withdrawn quantity scales linearly with the confirmation
quantity. For our bike example, confirming five bikes would result in a goods issue posting of
five frames and ten wheels, respectively.
Note:
You should always use backflush when you don't want to stage materials for a
specific order. It is assumed that the material is already staged and available at
storage location for consumption. Typical application areas are flow and assembly
lines and the staging of less valuable materials (for example, screws, grease, etc.).
The following functions are executed when a goods issue is posted. The on-stock quantity of
the withdrawn components is decreased by the goods issue quantity. Reservations are
reduced. If the entire reserved quantity was withdrawn, the final issue indicator is set. At the
same time, the reservation is removed from the Stock and Requirements list as it is not
relevant anymore. Actual component costs are determined and accounted to the order. The
order header status Goods Movement Posted is set. Material documents are generated. To be
able to easily analyze goods issues to production orders, SAP recommends enabling the
documentation of goods movements in customizing.
Goods Issue Posting with the Post Goods Movement App and the Picking List
Now that you know the options to post goods issues, let's see how to do this in SAP S/
4HANA. In the following demonstration, you will learn how to analyze a production order using
the order report. Afterward, you will see how you can post the goods issue of assembled
components. Finally, you will learn how to analyze the effect of the goods issue posting on the
production order.
Note:
If you have access to a practice system, you can now execute the exercise Post
Goods Issues for a Production Order.
For the production order of your finished product, T-FSP1##, you post the goods issues in the
picking list and check the result.
1. Use the Pick Components for Production Orders app to post the goods issues for all three
components of the production order for the T-FSP1## material.
2. In the SAP Fiori Launchpad, execute the Manage Production Orders app to analyze the
material components of your production order. Proceed to the production order details
tab, Components, and review the open quantities. How many items are open for each
component?
3. In the SAP Fiori Launchpad, execute the Monitor Material Coverage – Net Segments app to
check the stock/requirements situation for the components: T-SSP1##, T-SSP2##, and
T-RSP1##. How many items remain on stock? How many dependent requirements are
displayed?
Result
You posted the goods issue to the production order. The material reservation is completely
consumed and therefore not displayed any more in the Manage Material Coverage app. The
stock quantity decreased.
For the production order of your finished product, T-FSP1##, you post the goods issues in the
picking list and check the result.
1. Use the Pick Components for Production Orders app to post the goods issues for all three
components of the production order for the T-FSP1## material.
a) Open the app.
b) In the window, Picking List: Initial Screen, in the field, Material, in the section, Selection
at Header Level, enter T-FSP1## and choose Execute.
c) The system displays the Order Information System: Detail List of Components result
list. The result list should contain three entries (materials: T-SSP1##, T-SSP2##, T-
RSP1##) for one production order.
d) Select all three line items. You can select more than one line item by holding the ALT
key on your keyboard. Alternatively, choose Select All in the table selection menu in
the upper left of the table (icon with several boxes).
e) Choose Picking.
f) In the table, Goods Movements Overview, select all three line items by checking the
check box.
g) Choose Post.
h) The system returns to the window, Order Information System: Detail List of
Components. Choose Refresh.
2. In the SAP Fiori Launchpad, execute the Manage Production Orders app to analyze the
material components of your production order. Proceed to the production order details
tab, Components, and review the open quantities. How many items are open for each
component?
a) Open the Manage Production Orders app.
e) For all three components, the open quantity is 0 as shown in the column, Quantity.
3. In the SAP Fiori Launchpad, execute the Monitor Material Coverage – Net Segments app to
check the stock/requirements situation for the components: T-SSP1##, T-SSP2##, and
T-RSP1##. How many items remain on stock? How many dependent requirements are
displayed?
a) Open the Monitor Material Coverage – Net Segments app.
b) Select the line items for the three component materials: T-SSP1##, T-SSP2##, and T-
RSP1##.
e) In the table, Material Details, on the right the Stock quantity should be 1970 pc
(provided that you increased the stock to 2000 pc as requested in previous exercises -
if you increased to a different value, the remainder stock might be different).
f) There are eight dependent requirements. The component reservation disappeared due
to the goods issue posting.
g) Repeat steps d-f for the two other materials. There should be eight dependent
requirements, respectively. The remainder quantity for T-SSP1## (Frame) should also
be 1970 pc. The remainder quantity of T-SSP2## (Wheel) should be 1940 pc since we
withdrew two wheels per bike.
Result
You posted the goods issue to the production order. The material reservation is completely
consumed and therefore not displayed any more in the Manage Material Coverage app. The
stock quantity decreased.
LESSON SUMMARY
You should now be able to:
● Post Goods Issues for Production Orders
LESSON OBJECTIVES
After completing this lesson, you will be able to:
● Confirm Production Orders
Order Confirmations
Current Process Step
Let's continue with the next step in the production process of our new bike: Manufacturing the
bike and executing order confirmations. After the shop floor workers at the Bike Company
have taken the necessary materials from the warehouse, they assemble the bikes as stated in
the routing. For each operation of the order, they have to, for example, keep track of how
many bikes they have assembled, report when they began and completed the work, and how
much time they've spent on the individual steps. In SAP S/4HANA, this process is known as
production order confirmations.
Confirmations are the premise for progress control and the basis for cost charging of internal
activities performed for the order. For this reason, confirmations should be carried out by the
shop floor workers as promptly as possible. You can confirm individual operations of one
order or entire orders. As a prerequisite, the orders and/or operations must be released.
Figure 17: Example of an Operation Confirmation (left side) and its Effect on the Order (right side)
values that are different from the proposal if, for example, packaging took longer than
initially planned in the routing.
After posting the confirmation, the order and operation status values are updated to either
partially confirmed (PCNF) or confirmed (CNF): An order is partially confirmed if at least one
but not all of the operations have been confirmed (operation status PCNF or CNF). An order is
finally confirmed when all operations have been finally confirmed (status CNF).
Figure 18: SAP S/4HANA Offers Various Options for the Confirmation of a Production Order
Depending on the Bike Company's business requirements, the system offers various variants
for order confirmation. From all available options, the following two are most frequently used:
● Production order confirmation on order header level
In this scenario, you enter a confirmation for the entire order. From a business
perspective, you usually use this scenario for orders with only one or few operations, or for
orders where you are not interested in the detailed order progress. If you enter a
confirmation on order header level, the system automatically confirms all operations. You
can either confirm the order in one confirmation posting or post multiple order
confirmations until the order quantity was reached. After posting an order confirmation,
the system sets a respective confirmation status on order header level.
● Time ticket confirmation on operation level
In this scenario, you enter a confirmation for each operation in the order. From a business
perspective, you usually use this scenario for bigger orders containing many
manufacturing steps where you want to get a detailed overview about the progress of each
manufacturing operation. Similar to the previous case, you can either confirm each
operation in one confirmation posting or post multiple operation confirmations until each
operation of the order is fully confirmed. After posting an operation confirmation, the
system sets a respective confirmation status on operation and order header level.
Due to the different requirements that arise in practice, SAP provides several confirmation
apps, for example:
● Confirm Production Order
● Confirm Production Order Operation
● And other variants for confirmation
Note:
For one production order, you can either post an order-related confirmation or an
operation-related confirmation. As soon as you posted one confirmation type for
an order, for example, a production order confirmation, you cannot post the other
confirmation type, for example, a time ticket confirmation, and vice versa.
If you made a mistake, you can of course also cancel a confirmation (see Canceling of
confirmations).
As shown in the lifecycle figure above, you can also upload data from a process control or
manufacturing execution system (MES). If your company uses an MES system, the shop floor
personnel interacts with the MES instead of the SAP S/4HANA system. However,
confirmation data is also available in the SAP S/4HANA system since confirmation data
recorded in the MES is automatically transferred via an interface to the ERP system.
Order-related Confirmation
You now know that there are two options to confirm production orders. Let's get to know how
these options are executed in SAP S/4HANA. In the following demonstration, you will learn
how to confirm a production order on header level and analyze the effects of the confirmation.
Operation-related Confirmation
In the next demonstration, you will learn how to confirm operations of a production order and
how to analyze the effects of the confirmation.
Note:
If you have access to a practice system, you can now execute the exercise Confirm
Operations of a Production Order.
For the production order of your finished product, T-FSP1##, you confirm the operations and
analyze the result.
1. Use the Manage Production Orders app to retrieve the number of your production order.
2. Use the app, Confirm Production Order Operation, to confirm operation 10 of the order.
Confirm the yield quantity and the setup/machine/labor times as proposed by the
system.
3. Stay in the app, Confirm Production Order Operation, to confirm operations 20 and 30 as
described in the previous step. Do not change the proposed yield quantity and setup/
machine/labor time.
Result
You have now confirmed all three operations of your production order for the T-FSP1## Bike.
The order status is now confirmed.
For the production order of your finished product, T-FSP1##, you confirm the operations and
analyze the result.
1. Use the Manage Production Orders app to retrieve the number of your production order.
a) Open the app.
d) You should find the order number in the column, Order. The number should start with
100....
2. Use the app, Confirm Production Order Operation, to confirm operation 10 of the order.
Confirm the yield quantity and the setup/machine/labor times as proposed by the
system.
a) Open the app.
b) In the field, Order, enter the order number from the previous step.
d) Choose Enter.
g) Review the machine time. The system should propose 450 min.
h) Review the labor time. The system should propose 450 min.
i) Choose Save.
3. Stay in the app, Confirm Production Order Operation, to confirm operations 20 and 30 as
described in the previous step. Do not change the proposed yield quantity and setup/
machine/labor time.
a) In the field, Order, enter the order number from the previous step.
c) Choose Enter.
d) Choose Save.
e) In the field, Order, enter the order number from the previous step.
g) Choose Enter.
h) Choose Save.
Result
You have now confirmed all three operations of your production order for the T-FSP1## Bike.
The order status is now confirmed.
LESSON SUMMARY
You should now be able to:
● Confirm Production Orders
LESSON OBJECTIVES
After completing this lesson, you will be able to:
● Post Goods Receipts
Goods Receipts
Current Process Step
Let's continue with the next step in the production process of our new bike: Posting the goods
receipt after all production steps have been executed. The Bike Company has completely
processed a production order for 10 bikes of their new model. Now, the final step in the
production process is to transport these bikes to the designated storage area in your
warehouse and officially record their arrival at the warehouse through a goods receipt.
Posting the goods receipt is the last step in the lifecycle of a production order. When you post
the goods receipt, the on-stock quantity is increased. Once all manufactured items were
delivered to the warehouse, the production order is not relevant to production any more.
As shown in the figure, you have the following options to post a goods receipt:
● Manual goods receipt posting, for example, using the Post Goods Movement app.
● Automatic goods receipt posting together with the order confirmation, for example, using
the Confirm Production Order app.
● Automatic goods receipt posting together with the operation confirmation, for example,
using the Confirm Production Order Operation app.
From a business perspective, manual goods receipt posting is usually executed by the
production operator as a last step of the production process or by the warehouse clerk after
the manufactured goods were received in the goods receipt area of the warehouse. You use
automatic goods receipt if, for example, storage systems automatically transfer the
manufactured goods from the shop floor to the warehouse.
As you can also see in the figure, the goods receipt is posted at a storage location, 101A, in our
example. This storage location is maintained in the order header and proposed by the system
when you post the goods receipt. In case of automated goods receipt, the system posts the
goods receipt at this storage location.
Irrespective of whether you use automated or manual goods receipt, you can post multiple
goods receipts (partial receipts) or the goods receipt of the entire manufactured quantity.
When you manually post the goods receipt, the system proposes the yield quantity of the
order or the last operation as receipt quantity (in case of a single goods receipt posting). In
the case of multiple goods receipt postings, the proposed quantity is reduced by the quantity
that was already received in stock.
The following functions are executed when a goods receipt is posted: The On Stock quantity is
increased by the goods receipt quantity. The order status is updated to either partially
delivered or delivered. The delivered quantity is updated in the order. Actual costs are
determined and credited to the order. Production Order is removed from the monitor material
coverage list if it was fully delivered, and finally, material documents are generated.
Note:
If you have access to a practice system, you can now execute the exercise Post
the Goods Receipt for a Production Order.
For the production order of your finished product, T-FSP1##, you post the goods receipt and
check the result.
1. Execute the Post Goods Movement app to post the goods receipt for your production
order. Select the Goods Receipt for Order process and accept the proposed quantity. Do
not forget to check the OK indicator before saving the goods receipt.
2. Execute the Stock – Single Material app to analyze the stock of your product, T-FSP1##.
How many items are now on stock in plant, 1010, storage location, 101A?
3. Execute the Manage Production Orders app to review the production order. What is the
current status? What are additional status values?
4. Execute the Monitor Material Coverage Net Segments app to analyze the stock/
requirements list of your product, T-FSP1##. Analyze and interpret the current situation.
Result
You posted the goods receipt for the produced material. The stock quantity of the finished
product increased accordingly. Since the production order is not MRP relevant any more, the
order is not displayed in the Stock and Requirements List any more.
For the production order of your finished product, T-FSP1##, you post the goods receipt and
check the result.
1. Execute the Post Goods Movement app to post the goods receipt for your production
order. Select the Goods Receipt for Order process and accept the proposed quantity. Do
not forget to check the OK indicator before saving the goods receipt.
a) Open the app.
d) Now, enter the order number from the previous exercise (e.g. 1000306) in the input
field to the right of the drop-down where you selected Order.
e) Choose Enter.
f) If the Detail data section in the lower part of the screen is expanded, scroll down to the
bottom. You should see the check box Item OK in the bottom left. Select this check
box.
g) If the Detail data section is not expanded, select the check box OK in the table.
i) Choose Check.
j) If the system issues the Document is O.K. message, choose Post. Otherwise, verify that
you really checked the OK indicator. Usually, if you've forgotten to check this indicator,
the system issues the message: You have not flagged any items as OK.
2. Execute the Stock – Single Material app to analyze the stock of your product, T-FSP1##.
How many items are now on stock in plant, 1010, storage location, 101A?
a) Open the app.
3. Execute the Manage Production Orders app to review the production order. What is the
current status? What are additional status values?
d) Choose the Delivered status to display additional status values. The order status is
also, for example, Confirmed.
4. Execute the Monitor Material Coverage Net Segments app to analyze the stock/
requirements list of your product, T-FSP1##. Analyze and interpret the current situation.
a) Open the app.
b) Select the line item corresponding to the T-FSP1## material and choose Manage
Materials.
c) In the Stock / Requirements List, the Stock quantity should be 30 pc. The production
order is no longer relevant for MRP and therefore not displayed any longer in the
Stock / Requirements List.
Result
You posted the goods receipt for the produced material. The stock quantity of the finished
product increased accordingly. Since the production order is not MRP relevant any more, the
order is not displayed in the Stock and Requirements List any more.
LESSON SUMMARY
You should now be able to:
● Post Goods Receipts
Learning Assessment
1. Which functions can only be performed after a production order has been released?
Choose the correct answers.
X A Goods issues
X B Confirmations
X C Capacity planning
X D Availability checks
X B Quantity
X C Storage location
X D Vendor
4. Which of the following functions are executed in the system when you post a goods issue?
Choose the correct answers.
5. Which options are available if you want to post a manual goods issue to a production
order?
Choose the correct answers.
X D Operation activity times (e.g. setup time, machine time, labor time)
X C Operation status
X A Scrap
X C Rework
X D Yield
X E Inspected quantity