Lesson 1. Project Management
Lesson 1. Project Management
PROJECT MANAGEMENT
INTRODUCTION
A project is composed of jobs, activities, functions or tasks that are related one to the
other in some manner, and all of these should be completed in order to complete the
project. Every project has one specific purpose: it starts at some specific moment and
it is finished when the objectives have been fulfilled.
PROJECT MANAGEMENT
i) Material resources,
ii) Manpower resources.
OBJECTIVES
1
Project Planning:
Scheduling:
Controlling:
2
The solutions at various stages are then integrated to obtain the final outcome. Although each
stage requires different expertise, it usually includes both technical and managerial activities
in the knowledge domain of the specialist.
Preconstruction stage
The preconstruction phase of a project can be broken into conceptual planning, schematic
design, design development, and contract documents.
Conceptual design:
- Very important for the owner.
- During this stage the owner hires key consultants including the designer and project
manager, selects the project site, and establish a conceptual estimate, schedule, and program.
- The owner must gather as much information as possible about the project.
- The most important decision is to proceed with the project or not.
Schematic design:
- During this stage, the project team investigates alternate design solutions, materials and
systems.
- Completion of this stage represents about 30% of the design completion for the project.
- Designing the main systems and components of the project.
- Good communication between owner, designer, and construction manager is critical during
this stage because selections during this design stage affect project appearance, construction
and cost.
- This stage takes the project from 30% design to 60% design.
Contract documents:
- Final preparation of the documents necessary for the bid package such as the drawings,
specifications, general conditions, and bill of quantities.
- All documents need to be closely reviewed by the construction manager and appropriate
owner personnel to decrease conflicts, and changes.
- With the contract documents are almost complete; a detailed and complete cost estimate for
the project can be done.
3
Procurement Stage (Bidding and award stage)
- The project formally transits from design into construction.
- This stage begins with a public advertisement for all interested bidders or an invitation for
specific bidders.
- In fast-track projects, this stage overlaps with the design stage.
- If the project is phased, each work package will be advertised and bid out individually.
- It is very important stage to select highly qualified contractors. It is not wise to select the
under-bid contractors.
Construction stage
- The actual physical construction of the project stage.
- This stage takes the project from procurement through the final completion.
- It is the time where the bulk of the owner’s funds will be spent.
- It is the outcome of all previous stages (i.e., good preparation means smooth construction).
- The consultant will be deployed for contract administration and construction supervision.
- Changes during construction may hinder the progress of the project.
Closeout stage
- Transition from design and construction to the actual use of the constructed facility.
- In this stage, the management team must provide documentation, shop drawings, as-built
drawings, and operation manuals to the owner organization.
- The as-built drawings are the original contract drawings adjusted to reflect all the changes
that occurred.
- Assessment of the project team’s performance is crucial in this stage for avoiding mistakes
in the future.
- Actual activity costs and durations should be recorded and compared with that was planned.
This updated costs and durations will serve as the basis for the estimating and scheduling of
future projects.
The Project Manager: The project manager is the individual charged with the overall
coordination of the entire construction program for the owner. These include planning,
design, procurement, and construction. Among his/her duties:
4
- Investigate alternative solutions for the problems.
- Develop a detailed plan to make the selected program reality.
- Implement the plan and control the project.
Architect: An architect is an individual who plans and design buildings and their associated
landscaping. Architects mostly rely on consulting engineers for structural, electrical, and
mechanical work.
Engineer: The term engineer usually refers to an individual or a firm engaged in the design or
other work associated with the design or construction. Design engineers are usually classified
as civil, electrical, mechanical depending upon their specialty. There are also scheduling,
estimating, cost, and construction engineers.
Owner/Client
Project Manager
Consultant Contractor
Foreman
Workers
5
CONFLICT & CONFLICT MANAGEMENT
Conflict is an inevitable and unavoidable part of our everyday professional and personal
lives.
Conflict management is the process of limiting the negative aspects of conflict while
increasing the positive aspects of conflict.
The aim of conflict management is to enhance learning and group outcomes, including
effectiveness or performance in an organizational setting.
CAUSES OF CONFLICT
Misunderstanding
Personality clashes
Competition for resources
Authority issues
Lack of cooperation
Differences over methods or style
Low performance
Value or goal differences
Lack of When one person does not share information with the
cooperation whole group.
Differences over When agreement does not exist on standard ways of
completing a task.
methods or style
Low performance When individuals are not working to their potential.
6
CONFLICT: CONSTRUCTIVE VS DESTRUCTIVE
Conflict is destructive when it:
— Diverts energy from more important issues and tasks.
— Deepens differences in values.
— Polarizes groups so that cooperation is reduced.
— Destroys the morale of people or reinforces poor self- concepts.
7
Questions:
1. What is project management and write the objectives of project management?
2. Describe the phases of project management.
3. What do you mean by project planning and project schedule?
Or, Write short note on project planning and project schedule.
4. What is mean project controlling?
Or, Write short note on project controlling.