QUESTION 1:
Scott has just been given a project that has a specific completion date. After a discussion with top
management, he finds that while the date is important the cost is more important and a slip in
delivery would be acceptable if required to meet the cost targets. The completion date is best
classified as
a. Constrained.
b. Reduced.
c. Accepted.
d. Limited.
e. Optional.
Correct Answer: c
______________________________________________________________________________
QUESTION 2:
The _________ is used to assist in making project trade-offs among schedule, budget, and
performance objectives.
a. Responsibility matrix
b. Work breakdown structure
c. Project priority matrix
d. Work package
e. Criterion matrix
Correct Answer: c
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
Justification: The project priority matrix helps prioritize and balance the trade-offs between
different project constraints such as schedule, budget, and performance. It aids in decision-
making by clarifying which aspects are most critical and how to adjust one constraint in relation
to others.
______________________________________________________________________________
QUESTION 3:
All of the following are ways the WBS helps in managing projects EXCEPT
a. With cost and time estimates the WBS makes it possible to plan, schedule and budget the
project.
b. It provides management with information appropriate to each level.
c. Can be used to define communication channels.
d. Allows the project manager to establish the overall objective of the project.
e. As it is developed, organizational units and individuals can be assigned responsibility of
work packages.
Correct Answer: d
Justification: The WBS is primarily used for planning, scheduling, budgeting, defining
communication channels, and assigning responsibilities. However, the overall objective of the
project is typically established before the WBS is developed, rather than being set by the WBS
itself.
_____________________________________________________________________________
QUESTION 4:
What is the lowest level of decomposition in the Work Breakdown Structure called?
a. Work package
b. Deliverable
c. Sub-deliverable
d. Project.
Correct Answer: a
Justification: In the WBS, work packages represent the most granular level of task
decomposition. They are specific, manageable units of work that are used to allocate resources,
estimate costs, and track progress.
______________________________________________________________________________
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
QUESTION 5:
What is the total amount budgeted for design costs in this time-phased budget?
a. $5,250
b. $4,500
c. $9,750
d. $12,550
Correct Answer: c
_________________________________________________________________________
QUESTION 6:
Which of the following is a good condition for top-down estimating?
Correct Answer: d
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
Justification: Top-down estimating is best suited for internal, small projects where there is less
complexity and less need for detailed breakdowns. In such projects, the overall estimate can be
made based on experience or historical data without needing extensive detailed analysis. For
larger, more complex projects, more detailed estimating methods would typically be required.
_____________________________________________________________________________
QUESTION 7:
Which of the following would be the best method for projects where the final product is not
known and the uncertainty is very large?
a. Function point
b. Template
c. Learning curve
d. Phase estimating
e. Apportion
Correct Answer: d
Justification: Phase estimating involves breaking the project into phases or stages and making
estimates for each phase as more information becomes available. This method is particularly
useful when dealing with high uncertainty, as it allows for adjustments and refinements as the
project progresses and more details become known.
______________________________________________________________________________
QUESTION 8:
The salary of the project manager would be an example of what type of cost found in a project?
a. Labor
b. Direct
c. Direct project overhead
d. General and administrative overhead
e. Salary
Correct Answer: c
Justification: The salary of the project manager is typically considered a direct project overhead
cost because it is associated with managing the project but is not directly tied to a specific project
task or deliverable. It falls under overhead costs that are necessary for the project but not directly
assignable to a specific cost object.
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
______________________________________________________________________________
a. 22
b. 21
c. 20
d. 19
Correct Answer: b
Activity A: EF = ES + Duration = 0 + 5 = 5
Activity B: EF = ES + Duration = 0 + 7 = 7
Activity C: EF = ES (of A) + Duration = 5 + 8 = 13
Activity D: EF = ES (of A) + Duration = 5 + 7 = 12
Activity E: EF = ES (of B) + Duration = 7 + 4 = 11
Activity F: EF = Max (EF of C, EF of D) + Duration = Max (13, 12) + 8 = 21
Determine the Early Start Time for Activity G:
Activity G: Starts after both E and F, so:
ES (for G) = Max (EF of E, EF of F) = Max (11, 21) = 21
___________________________________________________________________________
NPTEL Online Certification Courses
Indian Institute of Technology Kharagpur
QUESTION 10
The AOA network of a small project is shown below, wherein the alphabet is the activity and numeric
value is the duration.
a. a-c-g
b. a-d-f-g
c. a-d-h-i
d. b-e-f-g
e. b-e-h-i
Correct Answer: d
Comparing the total durations of all paths, the longest path is Path b - e - f - g with a duration of
20. Thus, the critical path for the given network is:
(d): b - e - f - g