PSP Module 3
PSP Module 3
Resource calendars make sure that work resources (people and equipment) are
scheduled only when they are available for work. As a usual practice, the
working time settings in the resource calendar match the project calendar.
However, you can customize the resource calendar to show individual schedule
information, such as vacations, leaves of absence, or equipment maintenance
time.
It becomes necessary to create and define a resource calendar for each category
of resource indicating the availability period and nonworking time. For example,
you can assign a resource to a calendar that you created for carpenters who may
be working during a time that is different from the electrician.
A resource calendar would ensure the schedule would conform with the
resource availability based on timing and the quantity.
RESOURCE SCHEDULING
Resource requirements in conjunction with ES and LS schedules
Resource profiles
Resource usage
Non-consumable resources
Demand 4
3
2 2
1
0 1 2 3 4 5 6 7
Supply
3 3
9
RESOURCE PROFILE
ES - LS Resource Profile
10
9
8
7
6
Equivalent Person 5
4
3
2
1
0 Late
1 2 3 4 5 Early
6 7 8 9 10 11 12
Time in Weeks
NON CONSUMABLE RESOURCE
Required Available
12
10
Equivaltent Persons
0
1 2 3 4 5 6 7 8 9 10 11 12
Work Period
RESOURCE LEVELLING
The goal of resource leveling is to optimize the use of resources and
ensure the resource demanded does not exceed availability.
Try to avoid or minimize the irregular pattern of resource usage
especially for a non-consuming resource.
Some conflicting demand can be avoided by performing certain
activities ahead of the scheduled start.
Some non-critical activities (with float) could be delayed without
delaying the project completion date.
Consider extending the duration of certain activities and so
reducing the demand for resources over the duration of the activity.
Or a combination of any of the above adjustments.
Consider delaying the critical activities and allowing the project to
be delayed to optimize the resource usage.
RESOURCE LEVELLING
SCHEDULE COMPRESSION
NORMAL
SCHEDULE
1 A 15 16 B 35
1 15 15 16 20 35
FAST TRACKED
SCHEDULE
1 A 15 6 B 25
1 15 15 6 20 25
5
CRASHING.
Crashing is a process of expediting project schedule by allocating
additional resources and reducing the activity durations. Crashing
critical path activities is the practice of reducing their duration while
retaining the logical relationships.