Unit 1linear Measurements
Unit 1linear Measurements
The fundamental principles upon which the surveying is being carried out are:
1. working from whole to part.
2. After deciding the position of any point, its reference must be kept from at least
two permanent objects or stations whose position have already been well defined.
The purpose of working from whole to part is
• To localise the errors and
• To control the accumulation of errors.
This is being achieved by establishing a heirarchy of networks of control points.
The less precise networks are established within the higher precise network and
thus restrict the errors. To minimise the error limit, highest precise network
(primary network) Figure of control points are established using the most
accurate / precise instruments for collection of data and rigorous methods of
analysis are employed to find network parameters. This also involves most skilled
manpower and costly resources which are rare and cost intensive.
The reference of any point, say X, has to kept with respect to, at least, two permanent objects or
well defined points, say Y and Z. Generally, this has been achieved by taking measurement of
two parameters. The location of a point, say X can be done as shown in the figure below.
Scales: Scale is fixed ratio that every distance on the plan bears with corresponding
distance on the ground
1cm - 10 m
(on map) (on ground)
Representative Fraction (R.F.) (unit less)
1cm/10mX100 = 1/1000
a) Obstacles to ranging
b) Obstacles to Chaining
c) Obstacles to both chaining and Ranging
• Optical method
• Electronic Method
Direct measurement of distance using tape is difficult when the terrain is rough or
the site is congested. Indirect measurement of distance using optical method is
not suitable for high accuracy measurement. Thus, to obtain high accuracy
measurement in difficult terrain or for long distance, measurements are taken
electronically.
Electronic Method
• Electronic Distance Measuring (E.D.M) instruments have been
developed quite recently.
• These are practically replacing the measurement of distances
using chains or tapes. There is a large variety of such instruments
and depending upon the precision required the instruments
should be used.
• Electronic measurement of distance is being carried out either by using
an electro-optical (light wave) device coupled with reflector (also
called Laser Range Pole) or by a pair of electromagnetic (microwaves)
instruments.
• It is usually an integrated unit called EDMI (Electronic distance -
measuring instrument) consisting of an electro-wave generator, an
oscillator, a modulator, a transmitter, and a receiver etc. The type,
range and accuracy of an EDM instrument depend on the type of
carrier waves it can generate and subsequently can transmit, receive
and analyze
• An EDM instrument generally gets mounted in the framework of an
electronic theodolite. The net result is a single instrument termed as
total station (Figure 10.1) which can be used to measure all the
fundamental measurements involved in surveying.
Limiting the Length of an Offset in Chain Survey
Putting the values of α (the angular error) and s (the scale) in the above
equations, the limiting length of the offset (l) can be found out.
Errors in Length and Direction Combined:
Sometimes the error in measuring the length of the offset also occurs. In that case, referring to the
These errors could be identified and adjusted and can be modelled. Suitable corrections can be
applied to the measurements for obtaining greater accuracy. Following are some of the
important corrections applied to measurements using chain or tape
Correction for Erroneous Length of Chain/Tape
The chain surveying depends only on linear measurement of distances. For traversing only
the errors in distance measurements are of importance and significance. Measuring devise
either chain or tape can either be longer or shorter than the designated length. The measured
distance will be smaller than the actual if the length of chain is longer than the designated
length. It will be larger than the actual if the chain is shorter than the designated length. The
actual measured distance can be corrected by the following formula :
where,
α = Coefficient of thermal expansion,
Tm = Mean temperature in the field during measurement,
T0 = Standard temperature for the tape, and
L = Measured distance.
Correction for Pull
Correction for pull or tension is applied when during measurement the applied pull is
more than the pull at which the tape was standardised. As far as possible the pull applied
during the field observation should be equal to the standardised pull so that the correction
becomes zero. However, if
different pull is necessary, this correction (CP) is given by :
where,
P = Pull applied during measurements (kg or N),
P0 = Standard pull,
L = Measured length,
A = Cross-sectional area of the tape (cm2 or mm2), and
E = Young’s modulus of elasticity (kg/cm2 or N/mm2).
Correction for Sag
Correction for sag is applied when the tape is stretched on supports between two
points, it takes the form of a horizontal catenary. The horizontal distance will be
less than the distance along the curve. The difference between horizontal distance
and the measured length along catenary is called sag correction and it is always
negative.
This correction (Cs) is given by :
where,
l = The length of the tape (in m) suspended between the supports,
P = Pull applied in kg or N, and
w = Weight of the tape in kg or N per m run.
Random or Accidental Errors
Random or Accidental errors can occur due to lack of perfection of human eye and or
human behaviour. Even the best and efficient surveyor can have fatigue effect after
working for long duration in strenuous environment causing observational errors. The
random errors cannot be eliminated entirely, whatever precautions are undertaken.
These may, however, occur in either direction and hence, tend to compensate and, thus,
are not serious in nature. These normally follow the law of chance and, thus, can be
analysed with the help of probability theory. Using suitable probability distribution
functions, these errors can then be adjusted, distributed among
various measurements and accounted for. Each surveying method or process can be
assigned a reliability factor (or risk factor) for accuracy depending on the analysis of
probability behaviour.