Saudi Kad Piping Calculation
Saudi Kad Piping Calculation
no Description 20" dia 24" dia 30" dia 28" dia COST/DIA INCH
8" 650mm cf
electrode weight
Sch Thk kg /mtrs
60 9.525 1.058 2.811
Manpower
welder 1 40 30 400
fitter 1 30 30 300
helper 2 14 30 280
rigger 1 1 10 30 100
supervisor 1 10 40 100
qc 1 10 40 100
200 1280
8" 650mm cf
electrode weight
consumable cost
required for 8"
Sch Thk kg /mtrs
160 24 4.493 5.3916 3.50454 42.05448
80 13 1.318 1.5816 1.02804 12.33648
40 9 0.789 0.9468 0.61542 7.38504
1 Manpower cost 46
2 Camp per inch 10
3 Consumable 6
4 Radiography 8
5 Break even 70
6 Overhead 5% & 2%contigency 5
7 profit 25% 19
Total Cost 94
Grinding /gas cost /deisel/maint
consumable cost per inch
5.25681 10.51362
1.54206 3.08412
0.92313 1.84626
Avarage 5.148
###
###
8" 650mm cf
weld deposit
weld deposite in kg /mte
manpower
welder 1 40 30 400
fitter 1 25 30 250
helper 2 14 30 280
rigger 1 1 10 30 100
supervisor 1 10 30 100
qc 1 10 30 100
180 1230 82
SAR
Break Even 82
Camp per inch 9
Consumable 7.5
98.5
profit 15% 14.775
Overhead 5% 4.925
total CTC 118.2 591000
consumable cost consumable cost per inch Grinding /gas cost /deisel
42.05448 5.25681 10.51362
12.33648 1.54206 3.08412
7.38504 0.92313 1.84626
15.444
98.5 119.185
SAUDIKAD NA1 - PIPING FABRICATION COST ESTIMATION
S.No Description Cost/Dia inch
1 Manpower cost 46.00
2 Camp per inch 10.00
3 Consumable 6.00
4 Radiography 8.00
5 Break even 70.00
6 Overhead 5% & 2%contigency 4.90
7 profit 25% 18.73
8 Total Cost 94
NOTE:
1. ALL WELDOLLETS TO BE CONSIDER 4 TIMES FROM THE ACTUAL DIA INCH
2. ALL RF PADS TO BE CONSIDER 3 TIMES FROM THE ACTUAL DIA INCH
3. REMOVING OF INTERNAL FBE COATED PIPE WHILE BEVELING TO BE CONSIDER 5 SAR/DIA INCH
4. CONSIDERING 100% RT FOR ALL THE WELDING JOINTS