Vendor S Scope of Supply: "Details and Drawings For Cyclones and Other Internals"
Vendor S Scope of Supply: "Details and Drawings For Cyclones and Other Internals"
Vendor S Scope of Supply: "Details and Drawings For Cyclones and Other Internals"
1. Design, Fabrication and supply of Reactor Internals with all auxiliaries as per
HPCL approved QAP (QAP will be finalized after PO placement), details &
drawings provided in the Tender.
2. Once the QAP is approved, QAP requirements shall be followed without any
deviations.
3. MOC of the cyclones, plenum and Hex mesh & refractory lining to be installed
into cyclones as per Annexure-II- “Details and Drawings for Cyclones
and Other Internals”.
4. The overall weight of new internals shall not exceed the existing ones to avoid
any additional weight on the reactor foundation/civil design.
5. Also There should not be any significant change in height of reactor to avoid
any major piping modifications. Hence, any design modification to be done
accordingly.
6. Following points are also covered under Vendor scope:
i) Supply of all raw materials required for accomplishing supply of the Reactor
Internals is in vendor scope. HPCL will not supply any materials to the
Vendor.
ii) Supply of all Reactor Internals’ support arrangements like support lugs,
rods, gusseting & reinforcement arrangements, support plates, Fasteners,
nuts, washers etc. required to install the Reactor Internals in entirety.
iii) Refractory lining and heat curing for Reactor internals wherever required
with refractory supporting Hex mesh, anchors, anchor bars, corner tabs,
edging bars, termination strips, etc. as per Exxon Refractory Spec B 19-3-2
(Annexure-V).
iv) Following improvements are required to be made in new cyclones
to improve mechanical integrity as per OEM–
a. Fabricator shall carry out welding of all 6 hex while installing hex
mesh inside cyclone components. Agency shall note that this shall
overrule only 2 hex welding as advised in Annexure-V.
b. Upgradation of refractory material (Resco R Max or Equivalent)
c. Increase in refractory thickness at high erosion prone areas.
d. After PO placement, vendor shall prepare new cyclone system
drawing and get it okayed by the OEM and submit to HPCL for
approval/records.
v) For field joints, welding and refractory application will be done by site
contractor engaged by HPCL under the supervision of Vendor
representative, as per Exxon Refractory Spec B 19-3-2 (Annexure-V). (the
vendor shall follow the same document for refractory application while
fabrication of components at their site). For this, Vendor to estimate the
Refractory material, Anchors, Hex-mesh etc. required for site
joints and provide details of the same along with the dispatch of
Reactor Internals.
vi) SPARES: The following shall be supplied by the vendor as spares along with
supply of cyclones:
a. Minimum 5% of installed quantity of the Hex-mesh, anchors,
refractory.
b. Minimum 5% of all installed fasteners, subject to a min. of 50
numbers for each type/size.
vii) Preparation of Item for transporting, loading / unloading and coordination
for transportation to HPCL Vizag refinery.
Page 1 of 1
Details of Reactor Internals in FCCU-I
Page 1 of 4
Details of Reactor Internals in FCCU-I
1.4. Details of Refractory in Cyclones:
1.4.1.Hexmesh 25mm in Cyclones with Resco AA22S
1.4.2.Hexmesh 19mm in Dipleg with Resco AA22S
Approx
Sr.
Dimension Dimensions
No
(mm)
1. D7 5100
2. H1 300
3. R1 630
4. R2 1800
5. R3 1600
Page 2 of 4
Details of Reactor Internals in FCCU-I
3. Details of Dome:
3.1. Metallurgy: SA516Gr70 Normalised
3.2. Thickness: 49mm
3.3. Dimensions & NDT : As per drawings attached in Annexure-VI
4. Details of Plenum:
4.1. Metallurgy: SA516 Gr70 Normalised.
4.2. Thickness: 25mm.
4.3. Dimensions:
Approx
Sr.
Dimension Dimensions
No
(mm)
1. R4 2600
2. D8 3600
3. D9 5300
4. D10 2900
5. D11 2200
5. Details of Riser:
5.1. Top section :
5.1.1.Metallurgy: - C1/2 Mo (A204 GrB)
5.1.2.Length : Approx. 3Mtr.
5.1.3.Inner Dia: Approx 1170mm
5.1.4.Refractory: 25mm Hexmesh + Resco AA22S
5.2. Bottom Section upto nozzle 1N:
5.2.1.Metallurgy: C1/2 Mo (A204 GrB)
5.2.2.Length: Approx. 18 Mtr.
5.2.3.Inner Dia: Approx 1170mm
5.2.4.Refractory: 25mm Hexmesh + Resco AA22S
6. Refractory Details:
Dome
Page 3 of 4
Details of Reactor Internals in FCCU-I
Plenum
Bill of
Material
Page 4 of 4
Process Data Sheet for Reactor Unit : FCCU-I
Cyclones Visakh Refinery
Other details
Number of cyclones in series 2
Number of cyclones in parallel 3
Reactor height (Tan-to-Tan) mm Note-3
Reactor diameter (ID lining) mm Note-3
Catalyst bed elevation in reactor (min/normal/max) mm Note-3
Design Details
st nd
1 Stage 2 Stage
Inlet Height mm Note-3 Note-3
Inlet width mm Note-3 Note-3
Barrel Dia mm Note-3 Note-3
Barrel height mm Note-3 Note-3
Outlet tube dia mm Note-3 Note-3
Outlet tube penetration mm Note-3 Note-3
Main cone Dia mm Note-3 Note-3
Main cone height mm Note-3 Note-3
Cyclone length mm Note-3 Note-3
Dust hopper dia mm Note-3 Note-3
Dust hopper length mm Note-3 Note-3
Dipleg dia mm Note-3 Note-3
Dipleg length mm Note-3 Note-3
Total Cyclone Length mm Note-3 Note-3
st nd
Cyclone Performance Units 1 Stage 2 Stage
Catalyst loss kg/hr Note-7
Cyclone pressure drop (inlet to outlet for each stage 2
kg/cm (g) Note-7
and cumulative total)
Process Data Sheet for Reactor Unit : FCCU-I
Cyclones Visakh Refinery
portion of the diplegs shall have lining from termination to 1 m above the maximum bed level.
6 Cyclone dipleg shall have a termination valve (trickle valve or splash plate) as per vendor's
specifications. Valve opening direction should be such that it will not interfere with primary cyclone
dipleg.
7 Vendor to indicate and confirm
8 Vendor to provide elevation plan views of cyclone layout.
9 Vendor to confirm refractory life
Note: