Hydropower Field Visit Report
Hydropower Field Visit Report
Hydropower Field Visit Report
A
REPORT ON
HYDROPOWER FIELD VISIT
Jan, 2023
ABSTRACT
This is to recommend that the Field Assessment report entitled “A Hydropower Field Visit
Report” is prepared as per the requirement of course Hydropower Engineering for civil
engineering 4th year 1st part.
This Academic report has been prepared as per observation carried out under guidance of Er.
Nischal Aryal Sir , Er. Prakash Thapa Sir and Er. Aditya Gautam Sir. The field was based on
the result of own observation and the secondary data collected.
During field visit, I got opportunity to learn the different components of hydropower their
operation mechanism. The report has definitely been a great deal of hard work and
perseverance which has resulted in a fruitful journey and a wonderful experience as a whole.
I have gained a lot not only in the field of knowledge on the subject matter but also in
working procedure.
Prashant Joshi
i
ACKNOWLEDGEMENT
The visit was conducted at the various Hydro Power Project around Pokhara and Tanahu.
This journey has been fruitful to me as I was able to look into all the details of the Hydro
Power Plant and also observe the maintenance work being carried out there.
I am grateful to all the staff of those Hydropower Project Plant as well as the Power House
for their great hospitality and answering all queries without any hesitation.
Finally, I would also like to thank who directly or indirectly helped us to successfully
complete the field work.
Prashant Joshi
ii
Table of Contents
ABSTRACT...............................................................................................................................................i
ACKNOWLEDGEMENT............................................................................................................................ii
CHAPTER 1.............................................................................................................................................1
1.1 Background..................................................................................................................................1
1.2 Objectives....................................................................................................................................1
1.3 Introduction.................................................................................................................................1
1.4 Field Visit Area............................................................................................................................2
1.5 Types of Hydropower Plant Based on Head, Storage Capacity...................................................2
1.6 Components of ROR, PROR and Storage Type Projects...............................................................5
1.7 Status of Hydropower in Nepal....................................................................................................8
CHAPTER 2 : SETI HYDROPOWER PROJECT............................................................................................9
2.1 Introduction.................................................................................................................................9
2.2 Location Map...............................................................................................................................9
2.3 Salient Features of SHPP............................................................................................................10
2.4 Some Pictures of SHPP...............................................................................................................11
CHAPTER 3: FEWA HYDROPOWER PROJECT........................................................................................16
3.1 Introduction...............................................................................................................................16
3.2 Location Map.............................................................................................................................16
3.3 Salient Features of Fewa Hydropower Project...........................................................................17
3.4 Some Pictures of Fewa Hydropower Projects............................................................................18
CHAPTER 4: TANAHU HYDROPOWER PROJECT....................................................................................19
4.1 Introduction...............................................................................................................................19
4.2 Location Map.............................................................................................................................19
4.3 Salient Features of Tanahu Hydropower Project.......................................................................20
4.4 Some Pictures of THP.................................................................................................................20
Conclusion...........................................................................................................................................22
Bibliography.........................................................................................................................................22
iii
LIST OF FIGURES
iv
CHAPTER 1
1.1 Background
The hydropower field visit was organized by the Department of Civil Engineering , Everest
Engineering College in order to acquire the practical knowledge about the hydropower
project. The hydropower tour was held on 12th to 14th Poush, 2079.
1.2 Objectives
The main objectives of our field visit were:-
1.3 Introduction
Hydroelectric power, also called hydropower, electricity produced from generators driven
by turbines that convert the potential energy of falling or fast-flowing water into mechanical
energy. In the early 21st century, hydroelectric power was the most widely utilized form
of renewable energy; in 2019 it accounted for more than 18 percent of the world’s total power
generation capacity.
In the generation of hydroelectric power, water is collected or stored at a higher elevation and
led downward through large pipes or tunnels (penstocks) to a lower elevation; the difference
in these two elevations is known as the head. At the end of its passage down the pipes, the
falling water causes turbines to rotate. The turbines in turn drive generators, which convert
the turbines’ mechanical energy into electricity. Transformers are then used to convert the
alternating voltage suitable for the generators to a higher voltage suitable for long-distance
transmission. The structure that houses the turbines and generators, and into which the pipes
or penstocks feed, is called the powerhouse.
1|Page
1.4 Field Visit Area
Mainly during the trip, we visited three places to enhance the knowledge of Hydropower
projects. These three places are:-
2|Page
Such Plants utilize the concept of recycling the same water by using pumping
selecting.
c) Tidal Power Plants:
Only a few plants like ‘La Rance’ in France have been in operation using tidal
energy of sea water.
d) Depression Power Plants
3|Page
Fig 1: Layout of ROR Projects(Source: Researchgate.net)
b) Peaking run of river plants (PROR)
The increased load during peak hours, ROR plants may be constructed with
pondage which can regulate daily or weekly hydrograph to run the plant under
full capacity. This type of Plant is known as peak run of river plant.
Eg, Marsyangdi (69 MW), Middle Marsyangdi (70 MW).
c) Storage Plant
Those plants which can regulate the hydrograph of the river by one or more
seasons are termed as storage plants.
Dam is constructed to create a storage reservoir that develops the necessary
head for the powerhouse.
Powerhouse is located at the foot of the dam or away from the dam.
Water is carried through tunnel to powerhouse.
Carry over from monsoon to dry storage.
Suitable from medium to high head project.
Eg, Kulekhani (60 MW), 2(32 MW), 3(14 MW).
4|Page
Fig 2: Layout of Storage Type Projects(Source: Electricalleasy.com)
d) Pump Storage Plants
Plants having water reservoir at u/s as well as d/s of powerhouse, which
collects water in the u/s reservoir by pumping water from d/s reservoir using
cheaper energy.
a) Diversion Weir
It is type of structure place across the river to divert a part of river flow(water) to
the various water conveyance systems through the intake.
b) Intake
It is a structure to divert water into a conduit leading to the power plant or simply
defined as a structure to divert water to a waterway.
5|Page
Trash Rack screen are provided entry of floating debris and coarse bed load into
the water conveyance system.
It is well equipped with a control gate to regulate flow down the conveyance
system.
c) Gravel Trap
A gravel Trap shall be required to flush out bed sediments that enter the
approach canal back into the river.
The necessity of a gravel trap may arise awing to faulty design of the river
intake.
The gravel trap is constructed close to intake in order to prevent gravel from
getting into the approach channel.
The main function of the gravel trap is to collect the bed load, smaller than the
trash rack opening size, entering through it to the approach canal.
d) Settling Basin
It is the structure to remove suspended sediments from the conveyance water
for Power plant.
It shall be designed to ensure that the water entering the water conveyance
system is free from sediments that can damage the penstock and turbines
runner due to abrasion.
This can be achieved by reducing the turbulence level in the water flow to
allow suspended sediments particles to settle out from water body and deposit
on the bottom of the basin.
The settled sediment is subsequently discharge back into the river through a
flushing arrangement consisting of flushing gate and canal.
e) Headrace Conveyance
Usually, a canal or tunnel or Pipe or a combination of these for the purpose of
delivering design flow to the forebay or surge tank with a minimum energy
losses.
6|Page
f) Forebay
The structure located at the beginning of the penstock shaft satisfying the
function of supply required flow to the turbine during start up, accommodate
the reject flow during shut down, reduce water hammer effect is called
forebay
The forebay is equipped with a time screen/trash rack to prevent floating
debris into the penstock pipe and ultimately to the turbines.
It serves as a secondary settling basin as well and a sediment sluice to remove
settle suspended particles
g) Surge Tank
It is located between the headrace pressure conduit and the steeply sloping
penstock pipe.
In some instances, Surge tanks are applied both upstream of the penstock and
downstream of the powerhouse.
It is generally a cylindrical storage reservoir which is connected to a penstock
pipe close as possible to the turbine.
The main function of surge tank is to protect the long pressure tunnel and
penstock pipe from high water hammer effect caused due to sudden
acceptance and rejection of loads and to use or to receive or store water when
the turbine is decreased.
h) Penstock
It is a pipe that conveys the flow from the forebay or surge tank to the turbine
that are designed to carry water to the turbines with the least possible loss of
head consistent with the overall economy of the project.
i) Anchor Blocks
An anchor block is an encasement of a penstock designed to restrain the pipe
movement in all durations.
These structure prevent the pipe from sagging and becoming overstressed.
7|Page
j) Powerhouse
It is the structure complex where all the equipments for providing electricity
are suitably arranged.
Two basic requirements for powerhouse planning are functional efficiency and
aesthetic beauty.
k) Tailrace
It disposes the design flow discharged by hydraulic turbine after power
generation.
Governmental policies have stressed the potential for microhydro schemes to provide
economically productive mechanical and electrical services for the people living in the hilly
regions. Although the country has the potential of generating 43,000 megawatts of
hydropower, only 327 megawatts have been developed thus far. The government has put into
place a number of legal and institutional provisions to encourage hydro power development.
These provisions have been successful in legalizing and standardizing the facilities, subsidies
and cooperation to be provided to the private sector. This strategy has been adopted to ensure
that smaller schemes come on line at regular intervals and provide a better match between
growths of supply and demand. In the mid-1990s, the government reinstated the policy of
providing a direct subsidy of 50 per cent(in remote mountain regions 75 per cent) for
electrical components used in micro hydro systems. This subsidy is equivalent to about 20
per cent of the total cost, which is typically $1,600 per kilowatt. Credit is also available for
micro hydro schemes from the Agricultural Development Bank of Nepal, including a line of
credit available for rural development from the Asian Development Bank. (NEA, 2016)
8|Page
CHAPTER 2 : SETI HYDROPOWER PROJECT
2.1 Introduction
Seti Hydropower Station is a run of river type with installed capacity of 1.5 MW and design
generation of 9.8 GWh consisting of 3 units each 0.5 MW. It is located at Nadipur, Pokhara
and was commissioned in 1985 AD with assistance from Government of People’s Republic
of China and Government of Nepal. The power canal for this power station is jointly used for
irrigation purposes looked after by Department of Irrigation and hence, the operation of this
power station is affected by irrigation as well. Weir and radial gate are used near the intake
for the diversion of water from river to intake. The cumulative generation of Seti HPS has
reached 254.77 GWh till 2011/12 from its first run. The station has generated 11.62 GWh in
FY 2010/11 and 10.41 GWh in FY 2011/12 with decrease of 10.37%. The station contributed
0.25% of the total energy in the INPS in 2011/12.
9|Page
2.2 Location Map
Turbine
10 | P a g e
Number and Type :3, Horizontal Francis
Generator
11 | P a g e
2.4 Some Pictures of SHPP
12 | P a g e
Figure 6: Weir of Seti Hydropower
13 | P a g e
Figure 8: Intake of Seti HPP
14 | P a g e
Figure 10: Desanding Basin of Seti HPP
15 | P a g e
Figure 12: Turbine used in SHPP
16 | P a g e
CHAPTER 3: FEWA HYDROPOWER PROJECT
3.1 Introduction
Fewa hydropower station is a canal drop type power station having an installed capacity of
1.0 MW and located at Pardi, Birauta, Pokhara with an annual design generation of 6.5 GWh.
It consists of 4 units each 0.25 MW. It was commissioned in 1969 AD and developed jointly
by Government of India and Government of Nepal. The public encroachment of power canal
leading to power house is a concern for normal operation regardless of the availability of
generating units. Currently, three units are in operation and Unit No. 4 is not in operation due
to problem in generator turbine coupling. The main Canal starts from the barrage which is
located at one end of Fewa Lake at a popular tourist destination called Dam site.
17 | P a g e
3.3 Salient Features of Fewa Hydropower Project
Turbine
Generator
18 | P a g e
3.4 Some Pictures of Fewa Hydropower Projects
19 | P a g e
CHAPTER 4: TANAHU HYDROPOWER PROJECT
4.1 Introduction
Tanahu Hydropower Project is located on the right bank of Seti River, about 150 km west of
Kathmandu near Damauli, the district headquarters of Tanahu District. This is the storage
type project, which is planned to have an installed capacity of 140 MW with an estimated
annual energy generation of 585.7 GWh. The Project is designed for at least six hours of
peaking operation during the driest months of the year. This will play a vital role in Nepal’s
seasonal energy security and reduction of energy import.
The outputs of the Project will be i) a 140 MW hydropower plant and related transmission
system— 37 km, 220 kilovolts (kV)—made operational ii) increased rural electrification
(covering 17,636 households).The Project will expand access to clean and sustainable energy
in Nepal. Its outcome will be increased efficiency and reliable supply of hydropower energy.
20 | P a g e
4.3 Salient Features of Tanahu Hydropower Project
The Tanahu Hydropower Project consists of the following main components:
A concrete gravity dam with a maximum height above foundation level of 140m and
an estimated total concrete volume (including dam body, spillway, and appurtenant
structures) of over 920,000 m³.
A 25km long storage reservoir with a total volume of some 295 million m³.
An underground tunnel of 7.4m diameter and 1,388.75 length.
An underground powerhouse with two Francis Turbines and an installed capacity of
140 MW and capable of generating on average some 585.7 GWh of electricity during
the first 10 years of operation.
Major Construction Packages
a) Package 1- Headworks
b) Package 2- Waterway, Powerhouse and Related Equipments
c) Package 3- 220 kV Transmission Line
21 | P a g e
Figure 18: Draft Tube Tunnel of THP (Source:thl.com.np)
22 | P a g e
Conclusion
We gain the practical knowledge about the different component of the hydropower plant. We
also get the knowledge of the current situation of the hydropower plant and the current
problem in the plant. We also got the chance to make the comparison between the different
hydropower plant. Overall we got the chance to see what we have read in theory. In such a
way We completed our Hydropower tour at Pokhara meeting all our objectives in a fruitful
way.
Bibliography
http://conference.ioe.edu.np/ioegc10/papers/ioegc-10-022-10034.pdf
https://www.academia.edu/22523306/Hydropower_field_report_pokhara
https://www.britannica.com/science/hydroelectric-power
https://www.researchgate.net/
https://en.wikipedia.org/wiki/Seti_Hydropower_Station
https://web.archive.org/web/20200616163551/https://www.nea.org.np/generation/
index.php
https://thl.com.np/(updated on Jan-2023)
Manual Of Hydropower Engineering ( Authors: Er. Birendra Pandit, Er. Rajan
Pandey, Er. Surendra Katwal)
23 | P a g e