Case Study 06
Case Study 06
Measure
Equipment
Transformers
Industry / Sector
Automobile
Year of Implementation
1997
q Payback: Immediate
Implementation Highlights
Summary
Energy conservation in transformers exists through transformer load
management, re-distribution of loads and switching off transformers
Case Study # 6
Background
A leading automobile manufacturer has main incomer at 132 kV.
This voltage is stepped down to 11 kV. From 11 kV to 433 V, plant
has several transformers located in eight substations.
During an energy audit, loading on transformers located at various
substations was analyzed. In few of the cases it was observed that
some transformers are grossly under loaded (around 10-20%) and
the scope exists to shift or distribute this load to other transformer
in the substation. This would also ensure optimum level of loading.
While achieving optimum loading, the standby transformers at
various substations were suggested to be kept open on H.T side to
save no-load losses. Also an operating schedule was proposed to
alternate the transformer operation weekly so as to keep them in
good health.
§ In sub station # 1, one transforme r was kept as stand by. This
hot standby transformer can be kept open (Energy savings 0.45
lakh per annum)
§ In sub station # 3, transformers #1 and #2 were drastically
under loaded (i.e, 20% and 15% respectively). Loads of
transformer # 2 were transferred to Transformer # 1 and
Transformer # 2 was switched off (Energy savings 0.37 lakh
kWh/year)
§ In sub station # 7, transformers # 2 and # 3 were drastically
under loaded (i.e, 10% and 25% respectively). Loads of
transformer # 2 was transferred to Transformer # 2 and
Transformer # 2 was switched off (Energy savings 0.42 lakh
kWh/year)
§ In substation # 8, keeping hot standby transformer open,
resulted in energy saving of 0.45 lakh kWh per year.
Details of techno-econmics: