QCP Block Works Maged Fawzy
QCP Block Works Maged Fawzy
QCP Block Works Maged Fawzy
1.0 PURPOSE
The purpose of this procedure is to ensure that quality of works is achieved, and required
inspections and tests are carried out as per the specification and quality plan.
2.0 SCOPE
The procedure applies to all on-site structure for BLOCK WORK, MORTAR AND LINTEL
BEAMS.
3.0 REFERENCES
5.0 RESPONSIBILITIES
5.1 The Project Manager has full authority and overall responsibility to manage,
supervise, and control the works in safe manner.
5.2 The Construction Manager is responsible for ensuring that all the works are carried
out as per the specifications, drawings/shop drawings, inspection and test plan and
method statement.
5.3 The Site Engineer is responsible for ensuring that the whole work is executed
according to the specification and approved method statement.
5.4 The QA/QC Engineer is responsible for monitoring the works are in fulfillment with
the specified requirements that all quality records related to the works are complete.
5.5 The QC Inspector is responsible for monitoring the work and ensures that the work
shall be carried out within the specifications requirements, carry out all the inspections
with the company representatives.
Name: Maged Fawzy Wanis
5.6 The HSE Engineer is responsible for supervising the works to ensure full compliance
with HSE requirements and procedures.
5.7 ITL is responsible for sampling and testing upon request and in accordance with
project specifications.
5.8 Surveyor is responsible for setting out and levels as per approved shop drawings.
6.0.1 QC engineer shall ensure that all testing related to blocks, cement, sand and water are
carried-out. The required control documents are available and have been distributed
to the concerned personnel, and visual inspections of all activities which are involved
in the block work.
6.0.2 Block work shall be carried out under the supervision of Engineers, Foreman. The
masons and labors will be involved in the installation of block works.
6.0.3 Surveyor will maintain the required plumb, levels and layout.
6.0.5 All necessary tests for masonry blocks motor will be done at site.
6.0.6 Frequency of sampling and testing will be maintained and report will be submitted to
the COMPANY.
6.1.1 QC engineer shall ensure that all required control documents are available and have
been distributed to the concerned personnel, and visual inspections of all activities
which are involved in mortar work.
6.1.2 Masonry mortar is produce by mixing approved Portland cement water and Ras Al
Khaima sand (Ratio being one part cement :4 parts sand unless otherwise specified)
conforming to project specifications as referred to in method statement. The proposed
mix design for mortar I part Portland cement- 4 parts 3/16 black ( Ras Al Khaima )
sand, and the water cement ratio will be maintained between 0.40 to 0.45 max unless
otherwise specified . By use of mechanical mixer.
6.1.3 The sand, cement and water will be measured in purpose made measuring / gauge
boxes.
6.1.4 Material shall be stored in dry area adjacent to the work area.
6.1.5 Mechanical mixer and transporting dumper shall be kept clean all the times.
6.1.6 Only material sufficient for use within the required times span and use as quickly as
possible shall be mixed.
6.1.9 Test reports will be submitted after the completion of 7 and 28 days test.
6.2.1 QC Engineer shall ensure that the concrete used in casting the precast lintel meets all
the specified requirements and samples / cubes have been casted.
6.2.2 The opening sizes and the locations shall match the approved drawings.
6.2.3 The Site Engineer shall ensure that the top course is constructed using solid blocks.
6.2.4 Barricade the erection area to ensure safety from falling objects.
6.2.5 All workers engaged on this activity shall wear safety harness and use proper tools.
6.2.6 Furthermore, all workers shall attend safety training pertaining to hazards specific to
this activity held by the HSE Officer.
6.2.7 After placing the precast lintel, the bottom level shall be checked using the level
markings fixed by the Surveyor.
6.2.9 Only trained scaffolders shall be engaged for the erection of scaffolding.
6.2.10 All safety precautions as required by the Risk Assessment study shall be
implemented prior to starting work.
Name: Maged Fawzy Wanis
CHECK SHEET FOR: BLOCK WORK, MORTAR AND LINTEL BEAMS Ref. No.
Rev. No. :00
Page : 1 of 2
SUBCONTRACTOR CONTRACTOR X Date :