25 Examples of PMP Questions and Answers
25 Examples of PMP Questions and Answers
Answers
1. A project has a 60% chance of a $100,000 profit and a 40 percent of a US
$100,000 loss. The Expected Monetary Value for the project is:
1. $100,000 profit
2. $60,000 loss
3. $ 20,000 profit
4. $40,000 loss
Compute both positive and negative values and then add them:
2. Assuming that the ends of a range of estimates are +/- 3 sigma from the
mean, which of the following range estimates involves the LEAST risk?
Reference: The PMBOK® Guide, 5th Edition, Page 312, Figure 11.1
8. The project manager meets with the project team to review lessons
learned from previous projects. In what activity is the team involved?
1. Performance management
2. Scope identification
3. Risk identification
4. Project team status meeting
9. During a bidder conference, you see that one bidder is your close friend.
What should your next step be?
1. Risk value
2. Present value
3. Expected monetary value
4. Contingency budget
12. All of the following are ALWAYS inputs to the risk management process
EXCEPT:
1. Historical information
2. Lessons learned
3. Work breakdown structure
4. Project status reports
1. Use the best guess and estimate all activities since there will be changes
as the project progresses and more information becomes available
2. Involve people who will be doing the work to get estimates
3. Estimate for what the cost will allow and include buffers
4. None of the above
14. Risk tolerance is determined in order to help:
If you know the tolerance of the stakeholders, you can predict how they
might react to different situations and risk events. This information can help
assign levels of risk on each work package activity.
15. You are running a project to engineer and implement a set of business
processes and a software solution for customer relationship management.
The project involves a large number of organizations―a major corporation
and many suppliers of different sizes. During the project, you observe the
effects of the differences between the companies’ corporate cultures. This
leads to different expectations on how the project should be handled—as
well as to frequent misunderstandings between stakeholders. Another effect
is a growing degree of distrust and skepticism. What should you try first to
integrate the diverse stakeholder groups?
16. You are finding it difficult to evaluate the exact cost impact of risk. You
should evaluate on a(n):
1. Quantitative basis
2. Numerical basis
3. Qualitative basis
4. Economic basis
If you cannot determine an exact cost impact to the event, use qualitative
estimates such as Low, Medium, and High.
17. A project manager is quantifying risk for her project. Several of her
experts are offsite but wish to be included. How can this be done?
1. Do a Monte Carlo analysis using the Internet as a tool
2. Apply the critical path method
3. Determine options for recommended corrective action
4. Apply the Delphi Technique
1. Conflicts distract the team and disrupt the work rhythm. You should
always smooth them when they surface.
2. A conflict should be handled in a meeting so that the entire team can
participate in finding a solution.
3. Conflicts should be addressed early and usually in private, using a direct,
collaborative approach.
4. You should use your coercive power to quickly resolve conflicts and then
focus on goal achievement.
1. Identify Risks
2. Perform Quantitative Risk Analysis
3. Plan Risk Response
4. Monitor and Control Risks
1. Initiation
2. Planning
3. Execution
4. Closing
26. Alpha and Beta are two projects considered by a company. $50 million
net profit is expected of Alpha and $45 million from Beta. Both are lucrative
and rewarding projects, but the company can only invest in one of the
projects. If Alpha is chosen, calculate the opportunity cost?
1. $45 million
2. $95 million
3. $5 million
4. $50 million
$45 million. The value of the alternative not chosen is called opportunity
cost.
27. You are the manager of a project which involves constructing five
bridges. The project comprises five sequential phases with each phase
completing one bridge. After the first phase of the project is complete, which
process group of the second phase should follow?
1. Executing
2. Closing
3. Initiating
4. Planning
28. The aim of a project is to investigate the technical, economic and social
feasibility of constructing a hydroelectric dam. The project charter is
approved by the project sponsor. What is the next step to be performed?
1. Identify Risks
2. Develop Project Management Plan
3. Develop Project Charter
4. Identify Stakeholders’
Identify Stakeholders
29. While managing a software upgrade project for your company you realize
that your sponsor has high authority in decisions but low interest. What
stakeholder management strategy should you employ to ensure the
sponsor’s continued support?
30. The project sponsor asks for a copy of the document that contains the
description, owner, source, priority, and status of product requirements.
Which project document is the question?
1. Start identifying stakeholders so that you can engage them as required for
project planning
2. Hold a project kick-off meeting with the aim to inform and engage
stakeholders and obtain commitment
3. Review the project charter to get high-level information about the project
4. Share project scope with the involved team to establish common
understanding about project deliverables
Review the project charter to get high-level information about the project
32. While monitoring the baseline cost of a project, it is noted that the
project expenses are higher than expected at this point. What is the most
likely cause of this?
33. Recently, you promoted your star programmer, Pam, to lead the agile
development team. Pam was a fantastic software coder, and you thought the
promotion would mean that she could now share her expertise with the other
development team members. But, you observe that Pam’s performance in
her new role is underwhelming and not at par with your expectations. Which
empirical rule have you ignored or forgotten while considering Pam’s
promotion?
1. Pareto concept
2. Murphy's law
3. Expectancy theory
4. Halo effect
Halo Effect
1. Project sponsor
2. Project team
3. Project manager
4. Any stakeholder
Any stakeholder
37. You want to replace a contractor because they are not performing to the
agreed-upon standards and engage another contractor for the same job. You
need to determine the specific legal procedure for the early termination of
the contract. What should you do?
38. In a project divided into four phases in sequence, what should the project
manager do when the second phase is over and the third one is about to
begin?
43. You are the head of a software development project where the
developers involved are working within a rented office space. It’s taking
longer than anticipated to write the code. You have requested the landlord to
rent the office for another week. Unfortunately, the landlord informs you that
the office is booked for that period. You capture the problem in the project
documents. What should you do next?
44. You are part of a project team that’s designing a new type of vehicle. You
are on the brink of getting started with working on a set of tasks (work
package) for the braking system of the vehicle. You would like to assess the
acceptance criteria before beginning the work. Where should you look in
order to find this information?
1. Requirements documentation
2. The WBS dictionary
3. Project management plan
4. Activity attributes
1. Send a summary of how the final product fulfilled the business needs
2. Transfer the completed assembly line to operations
3. Send a formal writing to the vendors notifying that the contracts have
been completed
4. Make the final payment to the suppliers
47. Your project team members are writing code in pairs and assessing each
other's work to review and determine if the code follows the requirements
documentation. Which of the following results will be obtained from this
process?
Verified Deliverable
48. The construction project has many people and specialized teams at the
work site every day. Frequent and seamless communication between the
team leads is vital to ensure safe and efficient progress. Which agile
ceremony can be incorporated in this project to boost timely cross-functional
communication?
1. Retrospectives
2. Daily standups
3. Iteration reviews
4. Risk-based spikes
51. The following table is an activity list that includes the duration and
predecessor for a series of project activities. What is the duration of the
critical path?
1. 14
2. 11
3. 13
4. 9
14
52. A project manager, while developing the stakeholder register, lists down
the potential stakeholders and chooses to use a data gathering method
known as brain writing. What is the first thing to do when using this method?
53. A project manager communicates primarily through email with her team
members, internal and external project stakeholders. Certain techniques are
incorporated to ensure there are no misunderstandings. Which of the
following is not considered one of these techniques?
Communication register
Reference: Managing Project Quality by Timothy J. Kloppenborg and Joseph
A. Petrick
Conclusion
If you are considering working toward your PMP exam, Simplilearn offers a
variety of project management courses that will help you pass, including the
PMP Certification training course. Our PMP training courses are conducted by
certified, highly experienced professionals with at least 10 years of
experience.