Punching Shear Calculation (Bridge-34)

PG

Uploaded by

Zam Zam
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

Girder Stagging Calculation For BRIDGE-34

Pipe Calculation Consideration Tie & Cross-Angle Arrangement


Bed Width W = 6.00 m FS = 1.5
Bed Length L= 38.60 m Bed Width W = 6.00 m Ht. nos 2.0 = Hori. LL = 2.00 ton
Pipe@width = 1.20 m Pipe@width = 1.20 m btw Cross = 2.0 nos
Pipe@Length = 1.00 m Pipe@Length = 1.00 m two
Pipe along length = 40.00 nos Pipe Length = 3.00 m tie
length of
Pipe along length = 6.00 nos Pipe Dia = 150.00 mm
cross angle
Total Pipe = 240.00 nos Pipe Thickness = 6.000 mm 1.00
Load Calculation Girder = 40.4 m
Girder = 120.75 ton Expansion = 0.05 m 1.56 1.41
Shutter = 15.00 ton AB Wall = 0.95 m
I-Beam (along width) = 11.76 ton Concrete = 48.3 m3
I-Beam (along length) = 7.57 ton Unit wt of concrete = 2.5 ton/m3 1.20
Cross Angle (along width) = 4.20 ton Shutter = 15 ton 1.00
Cross Angle (along Length) = 4.29 ton I-Beam = 49 kg/m Dist. btw two
Pipe Weight = 15.84 ton Angle = 3.8 kg/m pipe along width Dist. btw two
Live Load = 2.00 ton Pipe = 22 kg/m pipe along length
Total Load = 181.40 ton Sheet pile, Fy = 250 Mpa 1 Mpa = 1000 Kn/m2
190.00 ton Sheet Pile thick = 13 mm
Total allowable Load = 285.00 ton
Load per Pipe, L = 1.19 ton
11.65 kn
Punching Shear Calculation Required Materials
Pipe outer Dia Do = 0.15 m Item Qty. (Rm) Wt (ton)
Pipe Thickness t = 0.006 m I-Beam 395 19.33
Perimeter for Punching Shear P = π×Do Pipe 720 15.84
0.47 m Angle 2232 8.48
Punching Shear V = L/(P*t) U-head 240 nos
4,122.43 kn/m2 Sheet Pile 232
Allowable Shear Calculation
Allowable shear stress (τallow) = fy/(√3*×F.S.)
Sheet pile = 96,225.04 kn/m2 > 4,122.43 OK
Allowable Punching Load Calculation
Allowable Punching Load = fy*P*t/(√3*×F.S.)
Sheet pile = 589.19 kn
Sheet pile = 60.06 ton > 1.19 OK