District Cooling plant-Maroun-Khoury

Download as pdf or txt
Download as pdf or txt
You are on page 1of 57

District Cooling System

Design Parameters
District Cooling System Table of Contents

Table of Contents

1. Why District Cooling?

2. Design Parameters

– District Served
– Identifying a Feasible FAR of District Served
– Cooling Load Estimation
– Thermal Energy Storage
– Availability of Potable Water, TSE & Treatment and Sea Water
– Space Limitations and choice of location
– Design of Plants & Networks
– Chilled Water Temperatures
– Power Demand & Combination with Power Generation
– Opex and Capex Analysis

3. Creating Fit-for Purpose Plants to Suit End-User Parameters

– End User Parameters


– Optimal Plant Capacity
– Plant Configurations

4. District Cooling Plants – Designed by Dar Al-Handasah


District Cooling System Introduction

Why District Cooling?

• District Cooling rapid growth is due to:

– Increasing demand for comfort cooling, flexibility and reliability.

– A growing trend toward outsourcing operations to specialist companies that can provide the
service more efficiently.

– Reductions in peak electricity demand provided by district cooling.

– Cost-effectiveness.

– Environmental consideration.

– Costumer value provided by district cooling service.

– Centralized system reduces the use of usable land area compared to an ordinary
Decentralized system.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
District Served

District Served

• District cooling serves a variety of district types:

– Residential

– Hospitality Complexes

– Office parks

– Commercial developments

– Airports

– Community Facilities

– Medical Facilities

– Educational Facilities

– Sports Facilities

– Etc …
District
District Cooling SystemCooling Systems
– Design Parameters Identifying a Feasible FARIntroduction
of District Served

Identifying a Feasible FAR of District Served

• Quick steps for identifying a feasible Floor to Area Ratio (FAR) of District served, which is a major factor in
assessing the feasibility of a District Cooling system.

– Estimate the FAR for each District type i.e. Residential, Commercial …

– Estimate the capital cost of the district cooling plant (DCP) for each FAR/District type at different cooling
capacities.

Note that the district cooling plant cost rate decreases with higher FAR and larger capacity plants.

– Based on the cost rate computed and local financing parameters, estimate the DCP charging rate for each
FAR and cooling capacity.

– Estimate the de-centralized system charging rate.

– Compare the DCP charging rate to the de-centralized operating cost and identify the feasible FAR for the
specific project.
District
District Cooling SystemCooling Systems
– Design Parameters Cooling Load Estimation Introduction

Cooling Load Estimation

• Proper cooling load demand estimation affects the design, operation and cost-effectiveness of the
district cooling system.

• Peak district cooling demands for buildings in the Middle East range from 20 to 52 m2/ton
depending on the building usage type.
– Residential: 25 m2/ton
– Commercial: 20 m2/ton
– Office: 17 m2/ton
– Hotel: 22 m2/ton
– Warehouse: 35 m2/ton

• Diversity factor in range of 70-90% depending on the building usage type is used as step between
the peak and actual cooling load. A diversity factor of 75% is usually used in the Middle East
region.

• A peak-day load profile should be modeled based on building usage type, occupancy schedule,
weather, HVAC system characteristics and other case-specific variables.
District
District Cooling SystemCooling Systems
– Design Parameters Cooling Load Estimation Introduction

Cooling Load Estimation


• Below is an illustrative district cooling system peak-day load profile for a sample mix of building
usage types in the Middle East.

• Such difference between the average daily load and the hourly peak load provides an opportunity
for thermal storage to be used.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Thermal Energy Storage

Thermal Energy Storage

• Thermal Energy Storage is a viable technology that can improve the DCP economic feasibility by:

– Shifting electrical demand to off-peak hours and to take advantage of low-cost off peak
electric rates.

– Reducing the DCP capacity and thus reducing the equipment requirements which offer
energy cost savings where energy costs are based on time-of-day or real-time pricing.

– Improving chillers efficiency allowing more continuous operation at outputs closer to full
capacity, thus, minimizing part load losses.

• The following Thermal Energy Storage can be adopted:

– Stratified chilled water storage system

– Ice storage

– Eutectic storage system (Phase Change Materials – PCM)


District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Thermal Energy Storage

Stratified chilled water storage system

• Advantages:
– Most common system type used.
– Simplest concept.
– More efficient refrigeration
equipment can be used (higher chilled
water temperatures).
– The system gets more economical as
the size of the storage tank increases.
– Simpler to interface with other
building chilled water systems.

• Disadvantages:
– Laminar flow in storage tanks can
promote increased organic growth,
therefore the treatment of the water
requires additional attention.
– Requires a large volume and footprint
for storage capacity.

Thermal storage tank - PNU


District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Thermal Energy Storage

Ice Storage

• Advantages:
– The volume of ice storage vessel is typically 15 to 20 percent that of water TES (water stores Energy
at 20 Btu/lb. and ice can store at 144 Btu/lb.).
– Packaged equipment usually used.
– Ability to increase the system ΔTs (reducing pipe and pump sizes, pump horsepower, etc.). This
reduces the initial costs as well as the operating costs.

• Disadvantages:
– The lower evaporator temperatures produce higher electrical consumption since the Compressors are
not as efficient as conventional discharge temperatures.
– More complex concept.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Thermal Energy Storage

Eutectic Storage System

• Two or more substances mixed in a way to provide a desired melting/freezing


point.

• Advantages:
– Larger thermal energy storage capacity relative to its physical size.
– Utilizing the latent heat capacity of eutectic mixtures without the need
for minus circulation temperatures.
– Offers wide range of operating temperature (between 4°C and 89°C),
covering the majority of the chilled water application. Eutectic Beams
– The positive temperatures offered allow the designers to utilize
conventional chilled water equipments.
– Lower stand-by losses.

• Disadvantages:
– Many PCMs have poor thermal conductivity and therefore require large
heat exchange area.
– Some PCMs are corrosive and require special containers.
– Higher system cost. Eutectic Storage Tank
– More complex concept.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Thermal Energy Storage

Thermal Energy Storage

Comparison between thermal energy storage systems


District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Availability of Potable Water, TSE & Treatment and Sea Water

Availability of Potable Water, TSE & Treatment and Sea Water

• Makeup water is required to replace water lost during cooling tower operation, due to:

– Evaporation.
– Blow down.
– Drift (negligible with drift eliminators).

• Make up water for the cooling tower could be supplied from different sources:

– Potable water
– Treated Sewage Effluent (TSE)
– Sea water
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Availability of Potable Water, TSE & Treatment and Sea Water

Potable Water

• Potable water requirement: 0.08 m3/TR/day

• Advantages:

– Usage of potable water for make-up water will increase the cycle of concentration within
the system, and thus decreasing the volume of make-up water needed.

– No need for special fabricated chilled water equipments.

• Limitations:

– The availability of potable water in GCC countries.

– If available, potable water may be charged at high rates which will affect the economical
feasibility of the district cooling system.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Availability of Potable Water, TSE & Treatment and Sea Water

Treated Sewage Effluent (TSE)

• TSE requirement: 0.12 m3/TR/day

• Advantages:

– Relatively low cost compared to potable water.

– Presents a sustainability measure in terms of recycling water.

– It is available for industrial usage.

• Limitations:

– TSE may require polishing and further treatment; poor quality TSE may result in Fungi growth in
cooling tower basin.

– TSE water may contain percentage of dissolved ammonia which react with copper causing corrosion.

– Condenser piping should be fabricated with copper-nickel alloys, the alloys’ composition percentage
is according to the amount of ammonia and chlorides content.

– During early development, fresh water should be provided to substitute TSE.

– Higher volume of make-up water is needed due to the lower number of cycles of concentration.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Availability of Potable Water, TSE & Treatment and Sea Water

Haram Central Utility Complex – TSE Polishing System

TSE Polishing System


District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Availability of Potable Water, TSE & Treatment and Sea Water

Sea Water

• Advantages:

– Present no concern for the cost of water.

– Present no concern for the availability of water.

• Limitations:

– Water should be taken from a considerable depth since the Gulf seashore is shallow and
water temperature may go above 30 °C in summer time.

– Piping and condenser-tube materials must be capable of withstanding the aggressive nature
of seawater.

– The biological activity of the sea must be controlled.

– Higher volume of make-up water is needed due to the lower number of cycles of
concentration.

– Salt lowers the water vapor pressure, and thus making the seawater a less effective coolant.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Availability of Potable Water, TSE & Treatment and Sea Water

Pearl Island – Desalination Plant


• Lakes
• Water Reservoirs
• TSE
• RO Plant
• Blow Down
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Availability of Potable Water, TSE & Treatment and Sea Water

Pearl Island – Desalination Plant

• Plant capacity is 35,000 m3/day able to feed make up water at 400 ppm TDS to cooling towers and it
contributes to potable water supply and irrigation system as back up.

• The irrigation system is partially served from CT blow down with the remaining irrigation needs from
treated sewage effluent when becomes available.

• Treated water from plant at 400 ppm with Post Treatment supplying cooling tower make up water.

• CT blow-down and treated water from plant at 400 ppm with post treatment supplying the irrigation
system.

• Alternative of using 800 ppm without post treatment for irrigation is possible thru a set of valves.

• Potable water from the plant feeding partially the Island potable water tank.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Availability of Potable Water, TSE & Treatment and Sea Water

Pearl Island – Desalination Plant

Diagrammatic Control
Scheme for Water
Networks and Lakes
Filling
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Space Limitations & choice of location

Space Limitations & choice of location

• Area availability for the DCP

• Road accessibility for each heavy truck maneuverability

• Location should be with minimal environmental impact on the surroundings.

• Noise impact must be considered

• Low emissions to the buildings

• Choosing location to be as near as possible from buildings being served to minimize pipe work
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Space Limitations & choice of location

Space Limitations & choice of location


• Some indicative District Cooling System plot requirements

DCP Load (ton) Installed Chiller Modules Cooling Plant Dimensions Plot Requirements
20,000 4 37 m x 61 m 110 m x 105 m
25,000 5 49 m x 61 m 120 m x 105 m
30,000 5 49 m x 61 m 120 m x 105 m
35,000 6 49 m x 61 m 125 m x 105 m
40,000 7 61 m x 61 m 140 m x 105 m
45,000 8 61 m x 61 m 140 m x 105 m
50,000 9 73 m x 61 m 150 m x 105 m
55,000 10 73 m x 61 m 160 m x 105 m
60,000 11 85 m x 61 m 170 m x 105 m
65,000 11 85 m x 61 m 175 m x 105 m
70,000 12 85 m x 61 m 175 m x 105 m
75,000 13 97 m x 61 m 190 m x 105 m
80,000 14 97 m x 61 m 190 m x 105 m
85,000 15 110 m x 61 m 200 m x 105 m
90,000 16 110 m x 61 m 200 m x 105 m
95,000 17 121 m x 61 m 220 m x 105 m
100,000 18 121 m x 61 m 220 m x 105 m

• The plot requirements include space for the cooling plant building, thermal storage tank and make-up
water tanks.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Design of Plants & Networks

Design of Plants and Networks

• The main equipments in the chilled water plant are as follows:

– Air-Cooled or Water-Cooled chillers, commonly used capacities: 2000 TR, 2500 TR and 5000
TR

– Primary pumps, commonly used as constant speed, circulate the chilled water through the
chillers within the plant

– Variable speed secondary pumps circulate the chilled water from the primary system
through the chilled water distribution network to and from each building location

– Cooling towers: field erected induced draft, counter-flow, FRP & mounted on concrete
basin

– Condenser water system including pumps, side-stream filtration

– Control system
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Design of Plants & Networks

Design of Plants and Networks

• The network layout is to be selected to feed all facilities through loop networks, to insure system
redundancy.

• Piping corridor (directly buried pipe) or tunnel shall be used for chilled water pipes.

• Maximum water velocity in forced mains shall be the lesser of 4.6 m/s.

• The earthwork requires that the backfill above the top of the pipe is at least 0.90m.

• Separation between chilled water pipes and any other adjacent utilities are at minimum 0.50m in
vertical and horizontal directions.

• ETS are located in buildings basements or in dedicated outdoor chambers.


District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Design of Plants & Networks

Princess Nora Bint Abdul Rahman University - Piping Tunnel

Piping Tunnel Design Piping Tunnel As-built


District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Chilled Water Temperatures

Chilled Water Temperatures

• The difference in chilled water supply and return temperatures (Delta T) is a key parameter in the
design and operation of district cooling systems.

• The higher the Delta T, the less flow, pump energy and equipment capacity need to satisfy cooling
requirements.

• Delta T should be assessed in order for the system elements (buildings HVAC systems, ETS,
distribution system, DCP) operate together without compromising performance.

– Normal Delta T of 6.7 Deg °C; high piping & pumping cost

– Medium Delta T of 8.9 Deg °C; optimized piping & pumping cost but special arrangements
at consumers side

– Large Delta T of 13.3 °C; highly optimized piping & pumping cost but very special
arrangements at consumer side
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Power Demand & Combination with Power Generation

Power Demand & Combination with Power Generation

• The power consumption rate reaches 1 kW/TR for all related water-cooled plant equipments,
while 1.7 kW/TR for all related air-cooled plant equipments.

• Power generation can be used to decrease the demand of direct electric power; Gas turbines
present an efficient technology for central station power generation.

• The high quality waste heat can be recovered to generate:

– Additional power using steam turbines in a combined cycle scheme


– Refrigeration via steam turbine driven chillers in a combined heat and power (CHP)
application.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Power Demand & Combination with Power Generation

Power Demand & Combination with Power Generation


• Heat recovered from the turbine exhaust used to generate steam that powers steam turbines
producing additional electrical output.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Power Demand & Combination with Power Generation

Power Demand & Combination with Power Generation


• The turbine exhaust is utilized via heat recovery steam generators which produce steam serving
steam driven centrifugal chillers.
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Opex and Capex Analysis

Opex and Capex Analysis

• CAPEX items:

– Chillers
– Primary chilled water pumps
– Secondary pumps
– Tertiary pumps
– Cooling towers
– Heat exchangers
– Expansion tanks
– Piping
– Electrical substations
– Medium voltage cables

• OPEX items:

– Annual running costs:


• Make-up water
• Electricity
– Annual maintenance costs:
• Preventive maintenance
• Predictive maintenance
• Overhauling
District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Opex and Capex Analysis

CAPEX
Initial costs comparison between centralized and decentralized systems.

*Based on Jabal Omar Project


District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Opex and Capex Analysis

OPEX – Running cost


Annual running costs comparison between centralized and decentralized systems.

*Based on Jabal Omar Project


District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Opex and Capex Analysis

OPEX – Maintenance Cost


Annual maintenance costs comparison between centralized and decentralized systems.

*Based on Jabal Omar Project


District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Opex and Capex Analysis

Present Worth Comparison


Present Worth comparison between centralized and decentralized systems.

*Based on Jabal Omar Project


District
District Cooling SystemCooling Systems
– Design Parameters Introduction
Opex and Capex Analysis

Pay-Back Period
Pay-back Period when choosing centralized system over the decentralized one.

1.75

*Based on Jabal Omar Project


District
District Cooling SystemCooling Systems
– Creating Fit-for Purpose Plants to Suit End-User Parameters End Introduction
User Parameters

Creating Fit-for Purpose Plants to Suit End-User Parameters

• For a district cooling system to be successful, it is essential that all elements of the system are
integrated without compromising performance.

– District cooling plant


– Chilled water distribution system
– Building HVAC systems.
– Energy transfer stations

• Supply water temperature is limited by the district cooling plant and distribution system
performance.

• Return water temperature is limited by cooling coil performance in customer buildings.

• For district cooling systems serving old facilities, service providers are penalizing consumers in
case of un-match between the air handling equipments low DT and the plant optimized high DT.

• Service providers shall involve in reviewing buildings design and ensure systems are done to match
the essential requirements.
District
District Cooling SystemCooling Systems
– Creating Fit-for Purpose Plants to Suit End-User Parameters Introduction
Optimal Plant Capacity

Optimal Plant Capacity

• Optimal plant capacity is based on several parameters:

– Plant construction cost.


– Space allocation
– Project phasing

• Based on previous experience, recent studies in the Middle East region showed that for residential
& commercial developments the most economical plant capacities fall in the range of 15,000 -
60,000 TR.
District
District Cooling SystemCooling Systems
– Creating Fit-for Purpose Plants to Suit End-User Parameters Plant Introduction
Configurations

Plant Configurations – Alternative 1

• Cooling towers are located above the


chiller building

• Above ground thermal storage tank

• Above ground water tanks

• Stand alone electrical substation


District
District Cooling SystemCooling Systems
– Creating Fit-for Purpose Plants to Suit End-User Parameters Plant Introduction
Configurations

Plant Configurations – Alternative 2

• All facilities are included in one building including pump, chiller, cooling towers, electrical
substation and administration.

• The thermal storage tank is provided underground.


District
District Cooling SystemCooling Systems
– Creating Fit-for Purpose Plants to Suit End-User Parameters Plant Introduction
Configurations

Plant Configurations – Alternative 2

• Such alternative offers a more compact design, providing major savings in terms of plot area.

• Suitable for District Cooling Plants located in residential areas.


District
District Cooling SystemCooling Systems
– Creating Fit-for Purpose Plants to Suit End-User Parameters Plant Introduction
Configurations

Plant Configurations – Alternative 3

• The chillers are provided with sea water


cooling instead of cooling tower.

• Provides major savings in terms of plot


area.

• Reduces noise problems from cooling


towers fans.

• No consumption of potable or treated


sewage water for cooling tower make up.

• Roof of plant can be used as car park,


sports facilities or garden.
District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Princess Nora Bint Abdul Rahman University

• Project total built-up area =


2,000,000 m²

• Chiller plant built-up area =


26,250 m²

• Current chiller plant capacity =


65,000 T.R.

• Total plant capacity = 90,000


T.R.
District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Princess Nora Bint Abdul Rahman University

Utility Area

Chiller Plant

Utility tunnel
District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Princess Nora Bint Abdul Rahman University

Chillers installed in PNU DCP


District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Princess Nora Bint Abdul Rahman University

Radiators installed in PNU DCP


District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Makkah (Misfala) DCP

• Chiller plant capacity = 45,000


T.R.

• Centrifugal water cooled


chillers.

• Water cooling by air radiator.


District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Dubai International Airport

• Cooling Load = 110,000 T.R.

• Cooling load served by 6 Central


Utility Complexes (CUCs)

• Cooling towers located on the


roof.
District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Dubai International Airport

• Cooling Load = 110,000 T.R.

• Cooling load served by 6 Central


Utility Complexes (CUCs)

• Cooling towers located on the


roof.
District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Dubai International Airport

• Cooling Load = 110,000 T.R.

• Cooling load served by 6 Central


Utility Complexes (CUCs)

• Cooling towers located on the


roof.
District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Dubai International Airport

• Cooling Load = 110,000 T.R.

• Cooling load served by 6 Central


Utility Complexes (CUCs)

• Cooling towers located on the


roof.
District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Pearl Island

• One DCP located at the


center of the Pearl Island

Water Treatment Plant


Plant Power
(For CT water make up
Substation, 3 no
and potable water), 6 TR
TR each 50 to 60
with total of 19.8 MVA
MVA
District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Pearl Island
Garbage
Collection
• Plant cooling capacity Building
= 130,000 T.R.

Water
Treatment
Plant
District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Pearl Island

• 26 site erected cooling


towers each at 5,000 TR
District
District Cooling SystemCooling Systems Introduction
District Cooling Plants – Designed by Dar Al-Handasah

Dubai Airport

• 16 sets of twin chillers


each set of 5,000 TR
| DCP Design Challenges EIA | CT Transmissions

CT Emissions

Need for CFD simulation tools


| DCP Design Challenges

CFD
District Cooling Systems

Thank You

You might also like