General Risk Assessment ADDC
General Risk Assessment ADDC
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
Project : Construction of ADDC Khalifa Building and New Control Center at Khalifa City (Balance Work)
Client : ADDC
PAGE1
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
PAGE2
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
PAGE3
AL Rakha Contracting & Gen Transport LLC. REV 00
Sr.No Activity Risk/Hazard Persons Risk Rating Residual Risk
Control Measures Risk Owner
Exposed SR PR RR SR PR RR
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
1. Provide safe access to the working platform with
handrail, mid rail & knee rail.
2. Do not use any defective ladder or any make shift
arrangement
3. Check the ladder before use.
4. Provide suitable safe working platform min. 600 mm
width only for man
Min 1.2 width for man with materials and without any
lapping.
5. Provide Handrail, mid rail &knee rail around the
working platform.
6. Use 1” PP rope before providing the handrail for tie the
full body safety harness
7. Ensure all the workmen wearing the full body safety
harness and tied it above the shoulder level
8. Fix the toe boards all around the working platform and
floor edges to avoid fall materials
1.Fall of Person 20 9. Provide safety net around the working platform and the 1 4 4 ARCGT
2 Working at
All 5 4 floor edges (Low)
Height
2.Fall of 10. Always keep the working area neat & clean and dispose
materials all the debris immediately
11. Don’t keep any loose materials on the platform
12. Use bags to carry and keep the tools
13. Do not drop any materials from the height
14. Use 1” rope to down the materials
15. Don’t stack any of the materials at working area
16. Provide cordoned around the height work area
PAGE5
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
PAGE6
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
PAGE7
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
PAGE8
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
PAGE9
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
PAGE10
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
PAGE11
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
PAGE12
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
Sr.No Activity Risk/ Persons Risk Rating Control Measures Residual Risk Risk Owner
PAGE13
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
Hazard Exposed SR PR RR SR PR RR
Poor site 1. Correct size of crane job
access 2. Appoint a person and lifting assessment needed.
Overturning 3. Driver operator 3rd party trained
/ Stability 4. Examinations and tests, 3rd party inspection
Fall of 5. Nominated Banksman – Means of Communication
Materials /marking
chain failure. 6. Hard standing area
Overhead All site 7. Safe working load indicator
Cranes – 4
20 power cables personnel 4 4 16 8. Wind speeds indicator 1 4 ARCGT
Mobile (Low)
siting. Public. 9. Placing of out riggers
Control of 10. Stability
crane. 11. 3rd party trained Rigger / Banksman
Adverse
weather.
Collision
with other
crane.
Sr.No Activity Risk/ Persons Risk Rating Control Measures Residual Risk Risk Owner
PAGE14
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
Hazard Exposed SR PR RR SR PR RR
PAGE15
AL Rakha Contracting & Gen Transport LLC. REV 00
Sr.No Activity Risk/ Persons Risk Rating Residual Risk
Control Measures Risk Owner
Hazard Exposed SR PR RR SR PR RR
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
PAGE17
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
Mechanical
Mechanical
Heating Access falls 1. Ladders, Steps, Staging
and 3
29 /Cooling / Lifting 3 3 9 2. Method statement for commissioning 1 3 ARCGT
Electrical (Low)
Refrigeration Chemicals 3. Trained operatives
Engineers
Systems
PAGE18
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
Commissioning
Noise
Steam 1. All Commissioning should be carried out under a permit
Ventilation Mechanical
Heat to work system – Method statement Noise
/ Air and 4
30 Dust 2 4 8 2. Dust- Hazards 1 4 ARCGT
Conditioni Electrical (Low)
Gas- Explosion 3. Work at Height
ng Systems Engineers
Leak 4. Hazardous substance assessment for cooling fluids
Pressure testing
Electric shock
Electricians
1. Method statement for commissioning
Electric shock Other
2. Permit to work
Electric Cables persons in 5
31 5 5 25 3. Signage 1 5 ARCGT
Supply Transformers work area (Low)
4. Electric Shock placard
Manual handling Cable
5. Control of fuse boxes – Lock of system, control of keys
puller
PROBABILITY
1 2 3 4 5
SEVERITY PROBABILITY
1 1 2 4 7 11
Insignificant Rare
SEVERITY
2 3 5 8 12 16
Minor Unlikely 3 6 9 13 17 25
Moderate Possible 4 10 14 18 21 25
Major Likely
5 15 18 22 24 25
Severe Almost Certain
PAGE20
AL Rakha Contracting & Gen Transport LLC. REV 00
GENERAL RISK ASSESSMENT FOR ALL ACTIVITIES CARRIED OUT DURING THE CONSTRUCTION
(Risk Rating is calculation is based on Severity of Consequences combined with the probability of occurrence)
Risk Rating
Low= 1 to 10 Medium= 11 to 16 High= 17 to 25