Hot Insulation MSRA
Hot Insulation MSRA
Hot Insulation MSRA
Description of the
Hot Insulation work activities (Insulation work of Equipment’s, Pipes, Ducts & Pressure parts )
Task/Activity:
Prepared by: Name: Mr.Kathiresan Assessment Team: Mr.Kathiresh, Mr. Pawan & Mr Shyam
General Project Permits Working Hot Confined Excavation Electrical Pressure Lifting &
required for the activity at Work Space Permit Works Testing Shifting
Heights Permit Permit Permit Permit
Permit
Yes No No No No No Yes
Others Permits:
Rigger
Leagers
Foreman / Supervisor
Scaffolder
Details of Crew An Electrician holding a license & certificate of competency issued or recognized by the State
Personnel specific Government
certification Experienced and trained Insulation worker for temporary works and other miscellaneous works
Experienced and Trained Fitter (Insulation & Sheet), Scaffolder &Sheet Cutter for all temporary and other
works
Trained Lager shall be listed and utilized for all Insulation Shifting & Fixing work.
Externally Trained & Certified Fire Fighting Team shall be listed and available for Fire Emergency
Externally Trained & Certified First Aid Team shall be listed and available for Medical Emergencies
Key Plant , Tools and Hand Tools & DCP Fire Extinguishers
equipment Periodic test & Inspection of Full body harness
(Attach Certification as Regular Inspection by a responsible person not less than 15 days for all Fire Extinguishers
required)
Safe Working Load’s
(SWL’s) for Lifting Third party load test certificate for Life line (Only metal rope of 10 mm is allowed for work)
Equipment:
Specific Identified
Residual Hazards: 1. Fire hazards
(or refer to the task 2. Body Skin / eye injury, Irritation
specific risk 3. Property Loss / damage
assessment(s)) 4. Fall of material during shifting & lifting
5. Inhalation of insulation.
6. Fall of person from height
7. Unskilledd Worker
Specific Training 1. Material Handling Training
required for Activity: 2. Hand tools use & safe operational procedure training Safety
3. Firefighting training.
4. Emergency Evacuation / Fire Mock Drill
5. Height work safety ( Vertigo Test) & PPEs Usage Training
1. Work Method Hot Insulation activity for equipment & Pipes:
Sequence:
1. Obtain general & height work permit from concern approval authorities
2. (Include sketches if 2. Conduct job specific Tool Box Talk to all the crew before commencing insulation activities.
required) 3. Engage Inducted, trained and authorised watcher for insulation& cladding works
4. All welding works must be carried out under the dedicated supervision
5. Inspection of Scaffolding Hand tools before using at site with standard LTTS checklist and provide
Fitness Tag
6. Using Certified MEWP Vehicle for height work insulation purpose
7. Hand tools & machines shall be inspected for any kind of damaged.
8. Ensure that working area shall be in good condition with proper material segregation.
9. If any defect found that should be rectified by electrician/ Mechanic only, and allow to use after
rectification
10. Prior to start insulation work inspect the area that no other workers are working surrounding place
because insulation material can create skin irritation to them.
11. Follow 5s rules before start the work and after work completion.
12. Provide Proper stacking of material on site & it should be covered.
13. Provide barricading surrounding the Insulation work area to avoid unauthorised entry and highlight
P:2014/114153/EHS AMEA Protocols/Construction &Commissioning Protocol/Attachments/Method
Statement Template
Page 2 of 15
Method Statement Risk
Assessment Revision: Date
Issue 1 08/04//2020
Temporary Supports
and Props needed to
facilitate the works: NA
Method of Access and 1. Safe access shall be provided to the workplace means of proper scaffolding with ladder provision
Egress to the work 2. Keep the access route clear
area:
Required
Personnel
Protective
Equipment:
Safety Safety Hearing Respiratory
Hard Hats Hi-Vis
Boots Gloves Protection Eye Protection
Protection Clothing
√ √ √ √ √ √ √
Please Tick: √ / X
Other: Leather Apron, Face shield, Leg Guard, Hand sleeve, Leather hand gloves &Full body safety
harness with shock absorber having double lanyard.
Emergency 1. Mock Drill for Fire Emergency shall be conducted to the crew and well trained
Procedures: 2. Periodically Firefighting training should be conducted
3. Adequate Fire Points shall be located in prominent locations and details must be marked in
logistics plan and same shall be displayed
4. Eye wash / shower shall be kept available
5. Standby emergency vehicle available with all necessary equipment and first aider.
Location of nearest
safety shower and Near Emergency assembly area (as per logistic plan).
emergency exit:
Monitoring / Regular inspection by concern engineers and safety officer at every 7 days on Scaffolding & hand
inspection tools.
requirements for
Avoid to work near high noise / smoke area
the activity:
(E.g. noise / dust
Close, constant and effective supervision by concern supervisor required
monitoring / safety
inspections by EHS
etc.)
Housekeeping Maintain 5 S at site as part of each job.
Control Measures:
Traffic Follow all traffic control regulation at the site.
management
Conduct training for driver and operator for safe control and introduce regulations.
requirements:
(hazardous or
non-hazardous)
For segregation - Identified scrap / waste has to be collected and segregated in a
separate place / yard with colour codes and must have proper signage as ‘’NOT IN USE’’
Segregation
methods:
How waste is Manually or by tractor shifting the scrap materials from work location to designated scrap yard
transported to
designated
waste
collection areas
etc.:
Services to be
supplied by
Insulation Material & sheets
Others:
Other information
& Comments:
NA
Identification & Protection of “Live Services”
Area(s) Walked:
In the event of damage to the service, Depend on repairs – Service will be carried out at work location or send back to
is all repair equipment on site? service stations.
Risk
Process Steps Potential Hazards Control Measures
Evaluation
Consequence Rating
Responsibility
Probability Rating
S. No
List the basic steps Consider Safety, Health, Consider Design, Procedure, Practices, Skill
Risk Score
for the task Damage, Fire, Quality, Training, Special Rules, Health & Hygiene Control,
Production Problems, etc. Personal Protective Equipment, etc.
1 Manpower Mobilization 1.Unfit workmen 1.Ensure all workmen undergone on medical examination
and Induction Training 2.Lack of skill & awareness 2.Before sending to an Induction program proper screening /
skill test need to be conducted
3.All the workmen properly inducted by Fluid line & LTTS
Fluidline /
4.Maintain all the Medical / Screening / Induction record at site 2 2 4
office Forbes
5.Issue ID card to them
6.Provide Induction sticker on helmet to all Inducted workmen
for identification
7.Provide sticker about Worker’s trade on their helmet
2 Conducting Training on 1.No adequate knowledge related 1.Workmen should know each & every work step 3 2 6 Fluidline /
MSRA and Daily Tool Box to the job 2.Before start the work conduct training on approved MSRA Forbes
Talk 2.Negligence towards safety and all workers must be briefed about the work methodology
3.Behavioral issues and associated risks
MSRA must be briefed to 3.Periodic training must be identified and to be conducted
all the workmen & staff according to the EHS training requirements & as per training
involved in the task schedule
4.Training material must be most relevant to the subject and to
make them understand from their level of knowledge
5.Trained all the Insulation workers & sheet fitters and work
supervisors involved in the hot insulation work activity
6. Conduct firefighting training and emergency mock drill
11 Hot insulation work 1. Boom lift failure 1. Vehicle documents like insurance, PUC, TPI to be 3 3 9 Fluidline /
using by Boom Lift 2. Material / person fall ensured Forbes
3. Un-authorized operation 2. Operator’s driving license (LMV) and experience
Operating a Telescopic 4. Person entry into swing certificate to be verified
Boom Lift area 3. Inspect boom lift as per checklist and provide
5. Injuries to operator, inspection tag
Prepare work area workers, standby 4. Daily inspection to be carried out prior to use the
6. Fire to boom lift due to equipment
Operate Boom lift hydraulic oil. 5. Ensure safe access and firm ground for safe
movement of boom lift
6. Only authorized operator allowed to operate
7. Warn people in work area, utilize barricades, traffic
cone or caution tapes to keep bystanders a safe
distance from swing area, job area, buildings & power
lines
8. Operator enters the bucket and attaches lanyard to
designated anchorage point and worker must use full
body harness while working inside the bucket
9. Never exceed the posted lifting capacity (including
worker,materials and tools)
MSRA Induction Verification. To be signed by all participants in the task prior to commencement.
I have read this MSRA, understand its content and acknowledge its conditions and my responsibilities :
Name: Name:
Reviewed By (Archytype)
Sign & Date: Sign & Date:
Name: Name:
Approved By (BUNGE)
Sign & Date: Sign & Date:
Step 1 Decide S - How severely could it hurt someone? Step 2 Decide Likelihood - How likely is it that an incident will happen?
Step 3 Assess the risk - Decide Risk Level (Score) Step 4 Decide Action
4
4
High 8 12 16 20
Liklihood
3
3
Medium 6 9 1122 15
Low 2 4 6 8 10
1
P:2014/114153/EHS AMEA Protocols/Construction
1 &Commissioning Protocol/Attachments/Method Statement Template
In signification 2 3 3 3
Page 15 of 15