Lecture 1 - Introduction
Lecture 1 - Introduction
3 4
5
Small customers (415/240 V) 6
1
Types of generating plants
Others:
Co-generation e.g. bagasse based : Early supply systems generators were built
Involves capturing waste heat from manufacturing close to the load
industrial process or heating or cooling systems
and using it for power generation Growth in demand led to the establishment of
Produce two forms of energy from one fuel; heat unified grid that spread over large geographical
and either electricity or mechanical energy area
Topping cycle; power generation is primary Initially, the grid consisted of a number of
Bottoming cycle; power generation is secondary geographical zones that were able to meet their
Combined heat and power (CHP) demand
Common in cold countries Inter-zonal transfer was allowed only in
Produce power and use waste heat for heating exceptional circumstances – grid enhanced
buildings by air or water overall security of supply
9 10
11 12
2
Distributed generation
Liberalisation of the power industry has led to re- All these factors have led to the growth of distributed
examination of the trend to develop ever larger generation (DG) or embedded generation
power stations
DG refers to small scale generation units (1 kW – 50
Privatised and new entrants recognised MW) that produce electricity at a site close to
opportunities in generation e.g. modular Combined customers or that are connected to the distribution
Cycle Gas Turbine (CCGT) network
Other developments include:
1. Renewed interest in cogeneration and CHP
2. Renewed interest in renewable generation – in
some countries with financial incentives
13 14
For stand-by or emergency generation in case of Digital Economy – Firms that rely heavily on data
utility company’s supply failure – for increased storage and retrieval, data processing, or research
reliability and development:
As a green energy source using renewable energy Mission Critical Computer Systems
(RE) technology e.g. solar or wind
Communications Facilities
Off-grid application in remote locations –
eliminates need for extension of transmission Continuous Manufacturing Process
and/or distribution network
Fabrication and Essential Services
15 16
3
Homework Transmission
1. Discuss the factors that should be The transmission lines are either underground
considered in choosing the location of cables or overhead conductors with the latter
being more commonly used where the
the following power plants:
transmission distances are long.
i. Coal
ii. Nuclear Transmission voltages are normally classified as
iii. Hydro follows:
HV levels- 115-230kV
2. Discuss the advantages and
EHV levels- 345-765 kV
disadvantages of each of the power
plants listed in (1) above. UHV levels- 1000-1500kV
Disadvantages
Increased fault current thus require CB with
higher interrupting capability.
Disturbance caused by a short circuit on one
system may spread to interconnected systems.
Synchronization difficulties of all generators in
the interconnected systems.
23 24
4
SOME EAPP OBJECTIVES Southern Africa Power Pool (SAPP) member countries
Secure power supply for the Region’s countries
Facilitate the development of electricity market in
the region
Optimize energy resources usage through
socially, economically and environmentally
acceptable investment schemes in generation,
transmission and distribution Aim: To optimise the
Increase power supply to raise regional access to use of available
electricity energy resources in
Reduce regional electricity cost using the region and
interconnection and increased power exchanges support one
among countries another during
emergencies.
25 26
Generation mix and country contributions (2009) 2011/12 installed capacity Vs peak demand
29 30
5
2. Reserve Capacity
e f g=e+f
ESKOM 930 35,136 521.4 521.4 1042.8
ZESA 220 1546 47.5 47.5 95.0
ZESCO 180 1611 42.8 42.8 85.5
BPC 150 578 27.1 27.1 54.1
EdM 38 629 12.3 12.3 24.5
31 32
• 41 Transmission
System Operators
(TSOs)from 34
countries
33 34
35 36
6
Substation bus-bar arrangements
Substations may also be classified as:
1. Outdoor – 33 kV and above for cost and safety 1. Single Bus
reasons.
2. Indoor – 400 V to 11 kV – mainly in urban areas
3. Pole mounted – low capacity upto 500 kVA
4. Underground – whenever space is not
available
37 38
Easily expandable
41 42
7
4. Ring Bus
Disadvantages:
• During fault, splitting of the ring may leave
undesirable circuit combinations
• Each circuit has to have its own potential source
for relaying
Advantages: • Usually limited to 4 circuit positions, although
• Flexible operation larger sizes up to 10 are in service. 6 is
• High reliability • usually the maximum terminals for a ring bus
• Double feed to each circuit
• No main buses
• Expandable to breaker-and-a-half configuration
• Isolation of bus sections and circuit breakers for
maintenance without circuit disruption 43 44
45 46
47 48
8
49 50
Homework
S. Country Population Installed Annual energy Per capita Main generation Other remarks
No. (millions) capacity consumption electricity sources
(MW) (GWh) consumption
(kWh)
1 Egypt
2 Brazil
3 Britain
4 Russia
5 Germany
6 India
7 Argentina
8 China
9 Japan
10 South
Africa
11 Tanzania
12 Malaysia
13 Canada
14 Uganda
15 Singapore
16 Ethiopia
Homework
S. Country Populatio Installed Annual energy Per capita Main generation Other remarks
No. n capacity consumption electricity sources
(millions) (MW) (GWh) consumption
(kWh)
18 Mexico
19 USA
20 Kenya
21 France
22 DRC
23 Sweden
24 Switzerland
25 Zambia
26 Nigeria
27 Malawi
28 Spain
29 Denmark
30 Netherlands
31 Korea
32 Botswana
33 Taiwan
53