Agenda
PDRI Overview Section Contents PDRI Categories Score Definition Levels Time The Tool PDRI Savings Benefits to DOD Implementation Tier Designations Online Training PDRI publications
2
BUILDING STRONG
SM
PDRI Overview
What is the Product Definition Rating Index? Developed by private sector in late 1990s
Response to end-product construction deficiencies Evaluation tool applied at successive project gates Early high-risk ratings may trigger later actions
A simple and easy-to-use tool for measuring the degree of scope definition for completeness
Identifies and precisely describes each critical element in a scope definition package Allows team to quickly predict factors impacting project risk
BUILDING STRONG
SM
BUILDING STRONG
SM
BUILDING STRONG
SM
BUILDING STRONG
SM
BUILDING STRONG
SM
1000 Points
0 Points
BUILDING STRONG
SM
90 to 120 minutes
10
BUILDING STRONG
SM
Each element is weighted, algorithm generates a composite score for the project Normalized from 0 to 1000 Recommend a broad team composition 500 is good at planning stage (subjective!!) 300 is good at design stage (subjective!!) 200 is good by RTA (Ready To Award)
11
BUILDING STRONG
SM
Comparison of Projects with PDRI Above & Below 200 Building Projects PDRI Score
Performance
Cost
Schedule
< 200
3% over budget
5% behind schedule
> 200
9% over budget
21% behind schedule
Change Orders
8% of budget
(N=25)
11% of budget
(N=83)
Reduce cost growth by 6% Reduce schedule slip by 16% Reduce change orders by 3% of budget
BUILDING STRONG
SM
Benefits to DoD
Early identification / management of project risk elements Standard approach to Lifecycle Costing Institutionalize procedures for
Risk Management Risk Communication
Target project-level resources to high-risk elements Identify, track Action Office responsible for risk by element
Use of PDRI Action List
Risk Management improves customer end product Reduce scope creep Fewer mods reduce cost, time growth Early customer input and buy-in
PDRI enables targeted, holistic, and quantitative approach to Risk Management
13
BUILDING STRONG
SM
Implementation
Implementation at Code 0 (Planning Charrette) Code 6/7/T (DBB-Design Charrette, DB-RFP Development, AB) PM Review (over the shoulder) Code 3 (Parametric Design) ENG 3086 Tier 3 designation may trigger a 3rd PDRI assessment Retarget project resources on risk buydown Previous PDRI rating used as additional data input prior to Tier designation Implementation Procedures PDRI rating at 75% in Charrette
Generation of PDRI Action List
Attach PDRI assessment to 1391 Tab C Follow-up on PDRI Action List from PM & Design team
MILCON timeline
GY -1 Guidance Year Design Year Budget Year Program Year
Action List
PDRI assessment at Code 0 PDRI assessment at Code 6/7/T
Action List
14
SM
BUILDING STRONG
Tier Designations
Tier 1
Pres-bud and prior year un-awarded projects that have no perceived problems and will be "forecasted" and "scheduled" for an award within the goals established by for the FY
Tier 2
Project with known or perceived problems but are still expected to be awarded/executed this fiscal year will be "forecasted" and "scheduled" for award within FY
Tier3
Projects with problems and cannot be awarded within fiscal year include: Projects with any incomplete NEPA documentation. These will not be "forecasted" for award in the FY but should be scheduled for award as appropriate based on the assumption the NEPA doc will be completed prior to he scheduled Ready to advertize date. The P2 "issues comment" will be used to provide the NEPA completion dates
Projects on hold (code 4 - on hold; code 5- deferred and code 8- cancelled) status per customer request.
Projects that have scope, pa issues and/or other delaying factors that are recognized by the customer as being irresolvable within sufficient time to award within the FY.
15
BUILDING STRONG
SM
Online Training
16
BUILDING STRONG
SM
PDRI Publications
http://construction-institute.org/pdri/
17