Design of Uasb

The document provides details for designing a UASB reactor with a flow rate of 12m3/day. It specifies that the reactor should have dimensions of 1x1x2 meters with a 45 degree inclined gas-liquid-solid separator taking up 5% of the total volume. This requires the overall depth of the reactor to be 2.64 meters to compensate for the separator volume. It also lists bills of quantity for construction, including site clearance, transport, labor, and material costs.

Uploaded by

Edward Maganga
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
864 views2 pages

Design of Uasb

The document provides details for designing a UASB reactor with a flow rate of 12m3/day. It specifies that the reactor should have dimensions of 1x1x2 meters with a 45 degree inclined gas-liquid-solid separator taking up 5% of the total volume. This requires the overall depth of the reactor to be 2.64 meters to compensate for the separator volume. It also lists bills of quantity for construction, including site clearance, transport, labor, and material costs.

Uploaded by

Edward Maganga
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2

DESIGN OF UASB Given flow (Q) = 12m3/day  Depth of the reactor (assumed ) = 2m  Upflow velocity = 0.

5 m/s  Hydraulic retention time


 

= 4 hrs
 Area of the reactor (A) =
2

  

= 1m Shape of the reactor : Rectangular unit of net dimensions 1x1 m , free body to be provided can be 0.2 m Design of GLS  Inclination angle 450  Volume of the GLS = 5% of the total volume of the reactor  Effective volume of the reactor = area depth = 1m2 2.2 m = 2.2 m2  Volume of GLS = 5% 2.2 m3 =0.11 m3 (4 sides ) =0.44 m3 Depth to compensate volume of GLS
      

= 0.44 m3=
1 m2 Overall depth of the reactor

0.44m

= 2m + 0.2 m +0.4 m = 2.64 m

BILLS OF QUNTITY FOR CONSTRUCTION OF THE UASB REACTOR


COST FOR CONSTRUCTION OF THE UASB REACTOR ITEM DESCRIPTION 1 General Site clearance Transport cost Labour cost 2 Construction materials QUANTITY UNIT RATE AMOUNT