0% found this document useful (0 votes)
24 views

Assignment 1

My assignment from my school

Uploaded by

Misganaw Kejela
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
24 views

Assignment 1

My assignment from my school

Uploaded by

Misganaw Kejela
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Assignment 1 (10 points)

1. Three turbo-generators each having capacity of 10000kW have been installed at a


hydropower station. During a certain period of load, the load on the plant varies from
12000kW to 26000kW. Calculate
(a) Total installed capacity
(b) Load factor
(c) Plant factor
(d) Utilization factor
2. During a low water week, a river has an average daily flow of 32 m3/sec with a fluctuation
during the day requiring a pondage capacity of approximately 15% of the daily discharge. A
HEP is to be located on the river which will operate 5 days a week, 24 hours a day, but will
supply power at varying rate such that the daily load factor is 55% corresponding to which
the pondage required is equal to 0.2 times the mean flow to the turbine. On Saturday and
Sunday all the flow is ponded for use on rest of the days. If the effective head on the
turbines when the pond is full is to be 25 m and the maximum allowable fluctuation in pond
level is 1 m find (a) the surface area of the pond to satisfy all the operating conditions, (b)
the weekly output at the switch board in kwh. Assume turbine efficiency 55% and generator
efficiency 92%
3. The following data refer to a proposed hydroelectric power plant: turbines, total power
to be produced=30MW, normal operating speed=150revmin-1, net head available=16m;
draft tube, maximum kinetic energy at exit of draft tube=1.5% of H, efficiency of draft
tube=85%, vapour pressure=3m of water, atmospheric pressure=10.3 m of water.
(a) What size, type, and number of units would you select for the proposed plant?
(b) Starting from first principles, determine the turbine setting relative to the tailrace
water level.