FPA Lec6
FPA Lec6
Fayoum University
Faculty of Engineering
Mechanical Engineering Department
FACILITIES PLANNING
Lec_6: Line Balancing Problem
Mohammed Abdelghany
Assistant Lecturer – Mechanical Engineering Department
E-mail/ [email protected]
Tel./ 002 – 01144876702
1. Process layout
2. Product layout
3. Group layout
1
3/29/2020
Product Layout
• A product layout arranges machines in a line according
to the operations sequence that need to be performed
to assemble a particular product.
Eng/ M. Abdelghany 3
Eng/ M. Abdelghany 4
2
3/29/2020
Eng/ M. Abdelghany 5
Definitions
• Flow time; is the time required to complete an item (pass
completely through all stations of the line).
• Cycle time (Takt time):
• Time between unit coming off the end of an assembly line.
• The maximum amount of time the product is allowed to spend at each
workstation.
Eng/ M. Abdelghany 6
3
3/29/2020
Eng/ M. Abdelghany 7
Eng/ M. Abdelghany 8
4
3/29/2020
Eng/ M. Abdelghany 9
• Line efficiency:
= (1 – efficiency)
5
3/29/2020
Eng/ M. Abdelghany 11
Example solution
#1 Precedence diagram
Eng/ M. Abdelghany 12
6
3/29/2020
Example solution
#2 • Desired cycle time
Eng/ M. Abdelghany 13
Example solution
#4 • To balance the line, we must group elements into
workstations so that the sum of the element times
at each workstation is less than or equal to the
desired cycle time of 0.4 minute.
7
3/29/2020
Example solution
• Assembly-line diagram:
#5
• Assembly-line efficiency:
Eng/ M. Abdelghany 15