UNIT – II OPERATIONS RESEARCH

ASSIGNMENT PROBLEM

1. An Automobiles dealer wishes to put five repairmen to five different jobs. The repairmen
have somewhat different kinds of skills and they exhibit different levels of efficiency from
one job o another. The dealer has estimated the number of man-hours that would be required
for each job-man combination. This is given in the matrix form as follows:
JOB
MAN
A B C D E
1 11 17 8 16 20
2 9 7 12 6 15
3 13 16 15 12 16
4 21 24 17 28 26
5 14 10 12 11 15
Find the optimum assignment that will result in minimum man-hours needed.
2. A company is producing a single product and is selling it through five agencies situated in
different cities. All of a sudden there is a demand for the product in another five cities not
having any agency of the company. The company is faced with the problem of deciding on
how to assign the existing agencies to dispatch the product to needy cities in such a way that
the travelling distance is minimized. The distance (in kms) between the surplus and deficit
cities is given in the following distance matrix.
Deficit Cities
Surplus
Cities I II III IV V
A 160 130 175 190 200
B 135 120 130 160 175
C 140 110 155 170 185
D 50 50 80 80 110
E 55 35 80 80 105
Determine the optimal assignment schedule.
3. BMC have decided to carry out repairs of five main roads in the city before the onset of the
monsoon. Five contractors have submitted quotations as under. It is the policy of BMC to
award not more than one contract to a contractor. If the objective of the BMC is to minimize
the cost, how should they award the contracts? How much expenditure should be budgeted?
Contracts Roadways

R1 R2 R3 R4 R5
C1 18 19 14 25 NB
C2 17 18 13 22 24
C3 19 21 18 20 26
C4 17 22 15 24 27
C5 14 21 10 NB 25
(NB – No Bid Submitted)

1
Prof.Shahid Qureshi
(9664847492)
UNIT – II OPERATIONS RESEARCH
ASSIGNMENT PROBLEM

4. In a Plant, 4 employees are to be assigned 4 jobs on one-to-one basis. The cost in Rs.
Thousands for each employee to do each job is given. Find the Optimal combination of
employees and jobs to minimize total cost. (Rs. ‘000)
Employee/Job P Q R S
A 60 50 40 45
B 40 45 55 30
C 55 70 60 50
D 45 45 40 45

5. In a factory 4 workers are there and 4 jobs are to be done. Time required for each worker and
job is given in minutes. Find optimal Assignment of workers and Jobs and optimal total time.
Is this a case of Alternate Optimal solution? If yes, show Alternate optimal solution.
Worker/Job J1 J2 J3 J4
W1 120 100 80 90
W2 80 90 110 70
W3 110 140 120 100
W4 90 90 80 90

6. A Company has 4 machines to do 3 jobs. Each can be assigned to only one machine. The cost
of each job-machine combination is given in the table below in Rupees.
Job/Machine I II III IV
A 9 12 14 18
B 4 6 8 9
C 5 7 9 11
Find the optimal assignment which will minimize the cost. Answer the following questions
with justification:
(i) Is there any Alternate Optimal Assignment?
(ii) Is it possible to maintain the same minimum cost as per optimal solution if Job B is
assigned to either machine II or Machine III?
(iii) Does any Machine remain idle as per optimal assignment?

7. In the modification of a plant layout of a factory BMS auto parts, four new machines M1,
M2, M3 and M4 are to be installed in a machine shop. There are five vacant places A,B,C,D
and E which are suitable for installation. Because of Extra large size, M2 cannot be placed at
C and M3 cannot be places at A. The cost of installing machines location wise in hundred
rupees is as follows:
A B C D E
M1 9 11 15 10 11
M2 12 9 X 10 9
M3 X 11 14 11 7
M4 14 8 12 7 8
Find the optimal assignment.
2
Prof.Shahid Qureshi
(9664847492)
UNIT – II OPERATIONS RESEARCH
ASSIGNMENT PROBLEM

8. A company has 4 machines to do jobs. Each job can be assigned to only one machine. The
cost of each job-machine combination is given in the table below in Rupees.

MACHINES
JOBS
I II III IV
A 51 77 49 55
B 32 34 59 68
C 37 44 70 54
D 55 55 58 55
a) Find an optimal assignment which will minimize the cost, using Hungarian Method.
b) What would be the effect of prohibition of assignment B to IV on the optimal solution.

9. PQR Ltd. Produces 4 different products viz. pen, ink, pencil and rubber using 4 workers viz.
Alok,Satish,Vaze and Rathod who are capable of producing any of the four products and they
work effectively for 7 hours a day. The time (in minutes) required for producing each product are
given in the following matrix along with the profit.
Workers/Products Pen Ink Pencil Rubber
Alok 6 10 14 12
Satish 7 5 3 4
Vaze 6 7 10 10
Rathod 20 10 15 15
Profit/unit 3 2 4 1
Find out the assignment of workers to product which will maximize the profit.

10. A Five Star Hotel, which has four banquet halls used for function. The hall are of same size
but with varying facilities. Four parties approached to reserve a hall for a function on the same
day. These parties were told that the first choice among these 4 halls would cost Rs. 10,000/- for
the day. They were told to indicate the 2nd, 3rd and 4th preferences and the price they would be
willing to pay – Two parties A and D told that they were not interested in halls 3 and 4.
The following table shows the preference wise income details. What would be the optimal
assignment to maximize the total revenue? (‘000)
Parties/Hall 1 2 3 4
A 10 9 - -
B 8 10 8 5
C 7 10 6 8
D 10 8 - -

11. A college head of department has to provide teachers to all courses offered by his department
for imparting highest possible quality of education. He has got three professors and one teaching
assistant (TA). Four courses must be offered. After detailed analysis and evaluation, the head of
the department has arrived at the following relative ratings (100 = best rating) regarding the
ability of each instructor to teach each of the four courses respectively.
3
Prof.Shahid Qureshi
(9664847492)
UNIT – II OPERATIONS RESEARCH
ASSIGNMENT PROBLEM

COURSE I COURSE II COURSE III COURSE IV


Professor 1 60 40 60 70
Professor 2 20 50 60 70
Professor 3 20 30 40 60
TA 30 10 30 40
How should the head of department assign his staff to the courses to optimize educational quality
in his department?
12) A Company has four machines and 3 jobs. Each job can be assigned to one and only one
machine. The cost of each job on each machine is given in the following table:-
JOB/Machine A B C D
I 18 24 28 32
II 8 13 17 19
III 10 15 19 22
Determine the optimal assignment so as to minimize the cost using Hungarian Method. Is there
any alternate solution? If yes, find same.

13) A Company has four territories open, and four salesmen available for an assignment.
Territories are not equally rich in their sales potential. It is estimated that a typical salesman
operating each territory would bring in the following annual sales:-

Territory I II III IV
Annual Sales (Rs.) 1,26,000 1,05,000 84,000 63,000

The four salesmen also differ in their ability. It is estimated that, working under the same
conditions, their yearly sales would be proportionately as follows.

Salesman A B C D
Proportion 7 5 5 4

If the criterion is to maximize expected total sales, then the intuitive answer is to assign the best
salesmen to the richest territory, the next best salesman to the second richest, and so on. Verify
this answer by the assignment techniques.
14) WELLDONE Company has taken the third floor of a multi-storied building for rent with a
view to locate one of their Zonal Offices. There are five main rooms on this floor to be assigned
to five managers. Each room has its own advantage and disadvantages. Some have windows,
some are closer to the washroom or to the canteen or to the secretarial pool. The rooms are of
different sizes and shapes. Each of the five managers were asked to rank their preferences
amongst the rooms 301, 302, 303, 304 & 305. Their preferences were recorded in a table as
indicated below:

4
Prof.Shahid Qureshi
(9664847492)
UNIT – II OPERATIONS RESEARCH
ASSIGNMENT PROBLEM

MANAGER
M1 M2 M3 M4 M5
302 302 303 302 301
ROOMS 303 304 301 305 302
304 305 304 304 304
- 301 305 303 -
- - 302 - -
Most of the managers did not list all the five room since they were not satisfied with some of
these rooms and they have left off these from the list. Assuming that their preference can be
quantified by numbers, find out as to which manager should be assigned to which room, so that
their total preference ranking a minimum.
15) An Engineering company has branches in Mumbai, Calcutta, Delhi and Nagpur. A Branch
Manager is to be appointed one at each city, out of the four candidates A,B,C & D. Depending
on the branch manager and the city, the monthly business in the city varies in Lakhs of rupees as
per the details below:
Branch
City
Manager
MUMBAI CALCUTTA DELHI NAGPUR
A 2 3 1 1
B 5 8 3 3
C 4 9 5 1
D 8 7 8 4
Suggest which manager should be assigned to which city so as to get maximum total monthly
business.

*****************************THE END*****************************