Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

01 Mobilization of • Moving vehicles. 4 3 12 High Engineering Control: 1 3 3 Low


manpower and • Overloading. • Traffic calming measures such as speed bumps in high
materials. • COVID-19 Pandemic. risk areas.
• Poor Traffic Management • Establishment of pedestrian walkways
• Collision/ Vehicular accident, • Where possible, one-way system to be established.
• Man-Machine Interface, • All vehicles fitted with audible reverse alarms.
• Being struck by moving • Adequate lighting at site entrances.
equipment/Vehicle • Ensure sufficient third party trained, certified and
competent Traffic controllers, Flagman, Demarcation,
Traffic routes (Access/Exit), traffic and Safety signages to
maintain the traffic management on the site.
• Allocate Designated Pick up and Drop off area.

Administrative Control:
• All vehicle reversing controlled by trained banksmen.
• Provision of adequate signage.
• All vehicles kept within their SWL’s
• All drivers in possession of valid UAE license.
• Temperature check of all drivers at all site entrance gates
(COVID-19 symptom).
• All vehicles compliant with UAE regulations related to
registration.
• Site driving rules posted.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• All Axon drivers HSE inducted and driver awareness


trained.
• All subcontractor supplier drivers given visitor induction
prior to accessing project.
• All private vehicle/pick up/drop off vehicle/bus shall be
parked in designated parking area.
• Authorized vehicles only onsite.

PPE:
• All Workers checked for complete Project PPE availability
at the security gate before entering the project.

Ensure Legal Compliance to

OSHAD SF CoP - 14.0 Manual Handling


OSHAD SF CoP - 17.0 Signage
OSHAD SF CoP - 22.0 Barricading of Hazards
OSHAD SF CoP - 33.0 Working adjacent to roads
OSHAD SF CoP - 36.0 Plant & Equipment
OSHAD SF CoP - 44.0 Traffic Management
OSHAD SF CoP - 51.0 Power lift trucks

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

02 Material Storage • Material storage 4 3 12 High Engineering Control: 1 3 3 Low


& Stacking • Manual handling • COSHH Assessment to be completed for all involved
• Man machine interface material if applicable.
• Material fall during unloading • Use mechanical aids where possible.
• Poor Traffic Management • Barricade the Loading unloading area and display the
• Collision/ Vehicular accident, signage.
• Being struck by moving • Operator and driver shall be trained and certified by
equipment/Vehicle approved 3rd party training institute.
• Unload and stack in accordance with the manufactures’
recommendations
• Minimize height of pallets/stockpile to ensure Safe loading
and unloading.
• Loading and unloading areas shall be appropriate and
adequate space/area with barricade/demarcation,
safety/traffic signage and assign the third party trained
and certified flagman for Heavy and Long vehicles /trucks/
trailers.
• Mechanical aid used wherever possible, Assess the load,
Weights marked on all loads.
• All plant and equipment, lifting equipment and
accessories shall be good condition, inspected and
certified by 3rd party inspection body. Loading capacity
(SWL) identified and marked.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

Administrative Control:
• Carry load close to ground while moving.
• Return all cut pieces, scrap not laid at end of day to
secure areas.
• Use Correct manual handling techniques.
• Adequate training and TBT to the involved work teams.
• Direct and competent supervision.
• Prestart Briefings, and Toolbox Talks
• Ensure each loading/ lift is planned and assessed, avoid
double handling of materials.
• Ensure the route to be travelled is free from obstacles or
hazards and having adequate illumination.
• Ensure each lift is planned and assessed, avoid double
handling of materials.
• Ensure the route to be travelled is free from obstacles or
hazards and having adequate illumination.
• Provide awareness to technicians about ergonomic
principles.
• Inspect the material to be lifted for sharp corners,
firmness / rigidity of the packing.
• Lifting Equipment and accessories must check/inspect
prior to commencing the task.
• Adequate supervision and resource shall be available in
order to an effective health and safety management

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

particularly for tile work involved aiming to avoid


accidents.
• Don't Lift/stack tile bundle on damaged pallets.
• Ensure that operatives shall stay away / safe distance
while Loading/Unloading and Lifting the tile/bundle
• Ensure operatives not take rest/sit on tile bundle, along
with newly constructed tile wall.

PPE:
• Implement proper task specific personal protective
equipment (PPE) for workers, including gloves and
masks.

Ensure Legal Compliance to


OSHAD SF CoP - 1.0 Hazardous material
OSHAD SF CoP - 2.0 PPE
OSHAD SF CoP - 14.0 Manual Handling
OSHAD SF CoP - 17.0 Signage
OSHAD SF CoP - 22.0 Barricading of Hazards
OSHAD SF CoP - 34.0 Lifting
OSHAD SF CoP - 36.0 Plant and Equipment

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

03 Manual • Uneven ground 4 3 12 High Engineering control : 1 3 3 Low


Excavation work • Soil collapse • Isolate working area from other contractors by protective
• Fall in equipment and person barriers.
• Manual handling • Barricading the area to prevent trip and fall in the
• Unsafe access excavation area , severe injury/penetrating.
• Trip and falls • Conduct the soil test and keep the papers in the site .
• Poor Traffic Management • Avoid soil collapse in the excavation . It is important to
• Collision/ Vehicular accident, ensure that excavation areas are sloped or benched.
• Man-Machine Interface, • Deep Excavated area shall be protected with rigid
barriers/edge protection with warning signs

Administrative control :
• The supervisors must be competent, trained and
experience to complement the safe work procedure.
• Find out the underground utilities presence and properly
isolate the utilities .keep the cad scan report in the site .
• Use defect free hand tools
• All workers must have completed HSE induction and
TBT must be conducted before start of the activity.
• Keep the approved PTW paper in the site .
• 1 .5 m away keep the soil from the excavation edges .
• Provide safe means of access and egress.
• Display signages for not allowed to work any machines 2
meter surrounding of the excavation .

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Different heat related illness, method of prevention and


treatment need be available on site.
• No activity during the wind and sand storm
• No lone working
• Adequate training and competent supervision .
PPE:
• Implement proper task specific personal protective
equipment (PPE) for workers, including gloves and
masks.

Ensure Legal Compliance to


OSHAD SF CoP - 2.0 PPE
OSHAD SF CoP - 14.0 Manual Handling
OSHAD SF CoP - 17.0 Signage
OSHAD SF CoP - 21.0 PTW
OSHAD SF CoP - 22.0 Barricading of Hazards
OSHAD SF CoP - 27.0 Excavation
OSHAD SF CoP – 30.0 Lone Working

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

04 Machinery • Machinery tipping 4 4 16 Extreme Engineering Control: 1 4 4 Moderate


excavation Work • Contact, collision with workers • Isolate working area from other contractors by protective
• Contact, collision with other barriers.
contractor machinery • All plant and Equipment shall be good condition
• Machinery fall in the excavation maintained, fitted with Mirrors, indicating light,
revolving/beacon light, guard on its rotating parts and
Safety devices etc.
• Barricading the surrounding of work area and warning signs
provided to avoid unauthorized entry. Make sure nobody
allowed inside machinery area.
• All machinery to have Fire Extinguisher in cab.
• Exclusion zone to be created around working machinery.
Administrative Control:
• All machinery operators to hold valid license / certification.
• It is necessary to have a trained banks man on site to
provide signals.
• All machinery to be 3rd party inspected
• All operators familiarized with the Safe Working Procedure.
• Prior to mobilizing all machinery to be inspected by
Workshop.
• Operator to carry out daily operator checklist prior to use.
• All plant and Equipment shall be inspected and certified by
ADM approved 3rd party inspection body, maintenance
record and daily Inspection checklist in place.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Windows, lights, Mirrors to be cleaned regularly.

PPE :

• Operators and workers to wear Hi-Visibility Vests, safety


boots and helmets at all times.

Ensure Legal Compliance to


OSHAD SF CoP - 3.0 Noise
OSHAD SF CoP - 17.0 Signage
OSHAD SF CoP - 21.0 PTW
OSHAD SF CoP - 22.0 Barricading of Hazards
OSHAD SF CoP - 36.0 Plant and Equipment
OSHAD SF CoP - 39.0 Overhead & Underground Services
OSHAD SF CoP - 46.0 Underground construction

05 Water proofing • Heat 4 3 12 High Engineering control : 1 3 3 LOW


works • Skin burn • Isolate working area from other contractors by protective
• Eye injury barriers.
• Chemical vapour inhalation due • Barricading the area to prevent trip and fall hazard,
to Inadequate Ventilation severe injury/penetrating.
• • All Cylinders and pipes shall be good condition
maintained, fitted with flash back arrestor, pressure gauge,
Cylinder guard and Safety devices etc.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Ensure the cylinders keep in the trolley .


• Keep a fire extinguisher near the hot work .
• Adequate Ventilation will be ensured.
Administrative Control:

• Adequate training, and competent supervision.


• Adequate traffic management plans.
• Try to keep the Oxy acetylene cylinder away from the
sun light .
• Operators must need ADM approved 3rd party certificates.
• Adequate supervision shall be available full time on site.
• Remove unwanted compostable materials from the site .
• The supervisors must be competent, trained and
experience to complement the safe work procedure.
• Regular housekeeping conducted to clear area of any
obstruction.
PPE
• Implement proper personal protective equipment (PPE)
for operator, including hot work gloves, googles, Apron
jacket and filter masks.

OSHAD SF CoP - 2.0 PPE


OSHAD SF CoP - 14.0 Manual Handling
OSHAD SF CoP - 17.0 Signage

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

OSHAD SF CoP - 21.0 PTW


OSHAD SF CoP - 22.0 Barricading of Hazards
OSHAD SF CoP - 28.0 Hot wor
OSHAD SF CoP - 30.0 Lone working

06 Use of • Machinery tipping 4 4 16 Extreme Engineering Control: 1 4 4 Moderate


machinery for • Contact, collision with workers • All machinery shall deploy outriggers to full extend if fitted.
loading and • Contact, collision with other • All plant and Equipment shall be good condition
unloading such contractor machinery maintained, fitted with Mirrors, indicating light,
as Lifting • Material fall from height revolving/beacon light, guard on its rotating parts and
Safety devices etc.
Equipment,
• Visibility blind spots to be minimized by mirrors.
Plant and • Flashing beacon fitted.
Equipment • All machinery to have Fire Extinguisher in cab.
• Exclusion zone to be created around working machinery.
• Barricading the surrounding of work area and warning
signs provided to avoid unauthorized entry. Make sure
nobody allowed inside machinery area.

Administrative Control:
• All machinery operators to hold valid license / certification.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• All machinery to be 3rd party inspected


• All operators familiarized with the Safe Working
Procedure.
• Prior to mobilizing all machinery to be inspected by
Workshop.
• Operator to carry out daily operator checklist prior to use.
• All plant and Equipment shall be inspected and certified
by ADM approved 3rd party inspection body, maintenance
record and daily Inspection checklist in place.
• Windows, lights, Mirrors to be cleaned regularly.
• The cab floor to be kept clean and free from any
obstacles which may affect the safe operation of the
machine.
• All machinery to be included in Planned Preventative
Maintenance schedule.
• Adequate training to involved work teams.
• Direct and competent supervision.

PPE:
• Operators and workers to wear Hi-Visibility Vests, safety
boots and helmets at all times.

Ensure Legal Compliance to


OSHAD SF CoP - 3.0 Noise

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

OSHAD SF CoP - 17.0 Signage


OSHAD SF CoP - 21.0 PTW
OSHAD SF CoP - 22.0 Barricading of Hazards
OSHAD SF CoP - 36.0 Plant and Equipment
OSHAD SF CoP - 39.0 Overhead & Underground Services
OSHAD SF CoP - 46.0 Underground construction

07 Lifting Operation • Lifting Equipment failure 4 4 16 Extreme Engineering Control: 1 4 4 Moderate


for material • Lifting accessories failure • An exclusion zone will be maintained by rigger /Slinger,
loading and • Overload warning signs to be posted.
unloading • Tipping of machinery • Suitable lifting equipment and lifting gears to be selected
• Personnel and other machinery for the job.
interaction • Wind speed must be regularly inspected with use of
• Fall of Material Anemometer.
• Out riggers if available to be fully extended
• Ground must be compacted and stable to support the
lifting activity.

Administrative Control:
• Permit to work procedure must follow and Obtain prior to
begin the Lifting operation.
• Lifting activity to be stopped on high winds of 38km/hr

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Lifting equipment to be certified and visually checked


before use and must be color coded.
• Lifting Equipment, accessories and operator must be 3rd
party certified.
• Competent lifting Rigger/Slinger employed for any lifting
operations.
• Lifting Equipment shall not be placed near at excavation/
excavated area/overhead/underground services and
where potential to risk of topple
• No person is allowed to walk under a suspended load.
• Good communication between Banksman and Operator
• Ensure Compliance of OSHAD-SF-CoP-34-0 safe use of
lifting equipment and accessories and lifting plan, ALDAR
OSH Management system Rev.07, Approved MSRA.
• Adequate supervision shall be available full time on site,
the supervisors must be competent, trained and
experienced to complement the safe work procedure.
• Operatives shall not allow to stand/work under the
suspended load
• Provide qualified, 3rd party trained and competent Rigger,
Lifting supervisor,
• Lifting appointed person for managing the lifting
operations on the site

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Lifting operation shall not allow with materials binding


wire, packing box etc.

PPE:
• Implement proper personal protective equipment (PPE)
for workers, including gloves and masks.

Ensure Legal Compliance to


OSHAD SF CoP - 2.0 PPE

OSHAD SF CoP - 14.0 Manual Handling


OSHAD SF CoP - 17.0 Signage
OSHAD SF CoP - 22.0 Barricading of Hazards
OSHAD SF CoP - 34.0 Lifting
OSHAD SF CoP - 36.0 Plant and Equipment
08 Handling and • Poor material handling 4 3 12 High Engineering Control: 1 3 3 Low
Storage of • Poor material stacking and • Chemicals must be stored in Client approved chemical
Chemicals storage storage area.
(Paints) • Fire hazard • Chemical storage racks must be made of fire-resistant
• Contact with chemicals non-combustible materials.
• Inhalation of chemical fumes • Control measures such as maintaining air temperature,
• Environmental hazard due to ventilation, fire extinguishers, fire detection system, spill
spillage kits, protective sheets under the storage racks must be in
• Manual Handling place.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Ensure adequate lighting for the chemical storage area.


• Mechanical aid used wherever possible, Assess the load,
Weights marked on all loads.

Administrative control:
• All workers must have completed HSE induction and TBT
must be conducted before start of the activity.
• Complete COSHH assessment for all Chemicals.
• Comply with COSHH assessment.
• Only authorized personnel must be allowed in chemical
storage area.
• Quantities must be recorded in store register.
• Empty chemical containers must be disposed by
approved ADM sub-contractor and records of disposal to
be maintained.
• Chemical must be stored as per the MSDS, must not be
mixed with other chemicals inside the storage area.
• Ensure area is cleared from contamination and
housekeeping is maintained.
• Provide adequate HSE precautions, Fire protections and
Emergency arrangements for Hazardous/Flammable
Chemical storage container
• Ensure each lift is planned and assessed, avoid double
handling of materials.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Ensure the route to be travelled is free from obstacles or


hazards and having adequate illumination.
• Provide awareness to technicians about ergonomic
principles.
• Inspect the material to be lifted for sharp corners,
firmness / rigidity of the packing.

PPE:
• Specific PPE must be available and worn by the workers
as per the MSDS. (Helmet, reflective jacket, coveralls,
safety shoe, splash protective face shields, chemical
rated safety gloves, respiratory mask)

Ensure Legal Compliance to


OSHAD SF CoP - 1.0 Hazardous Materials
OSHAD SF CoP - 2.0 PPE
OSHAD SF CoP - 14.0 Manual Handling
OSHAD SF CoP - 17.0 Signage
OSHAD SF CoP - 22.0 Barricading of Hazards
OSHAD SF CoP - 36.0 Plant and Equipment
OSHAD SF CoP - 54.0 Waste Management
OSHAD SF CoP - 44.0 Traffic Management and Logistics

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

09 Use of • Fall from height operative 4 4 16 Extreme Engineering Control: 1 4 4 Moderate


Scaffolding, /materials. • Proper working platform to be ensured.
working platform • Fall from open edged. • All the open edged areas to be protected prior to work
Working at • Improper working platform. commence by hard barriers.
Height • Collapse of scaffolding. • Provide adequate edge protection /Guardrails. Edge
• Fall from open penetration /shaft. Protections guardrails shall be good, appropriate and as
• Heat stress per the requirements. Guardrails must be fixed with
clamps.
• Ensure proper access/egress in the work area.
• Provide exclusion zone and warning signs surrounding
and underneath the work area to avoid unauthorized
entry.
• Provide adequate fall protection, lifeline and safety
harness while working at edge, where potential to fall from
height and proper anchor point.
• Scaffolding shall be fixed with Top and mid guardrails,
platform, toe board. Scaffolding platform kicker lift to
maintain its stability, cross or diagonal bracing, sole-
board, Scaff Tags, Barricade and Safety signages in
place.
• Scaffolding must inspect before use and within every
7days by competent and 3rd party trained
personnel/scaffolder Supervisor.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Provide exclusion zone and warning signs surrounding


and underneath the work area to avoid unauthorized
entry.
• To ensure that edge protection/ handrails shall be
secured and operatives shall not dismantle/remove it.

Administrative Control:
• Ensure availability of approved MSRA on site and
communicate the safety procedures to the operatives.
• Obtain valid permit from safety department before start of
the activity.
• Adequate supervision to be ensured throughout the
activities.
• Heat stress safety procedure to be communicated to the
operatives.
• Avoid keeping excessive materials on the scaffolding
platform. Operatives shall not be allowed to work/walk
on/over of exposed and unprotected area.
• Employees working where potential to fall from height
must wear safety harness and anchor it to a suitable
anchorage point to avoid falls.
• Ensure scaffolding is erected by competent erector.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Only third party trained and certified scaffolder, supervisor


and competent personnel allowed for scaffolding
activities.
• Ensure compliance of OSHAD-SF-CoP- 23.0- Working at
Height, CoP-26.0 Scaffolding, CoP 37.0 Ladder, ALDAR
OSH Management System Rev. 07 , approved MSRA.
• Operatives shall not be allowed to work/walk on/over of
exposed and unprotected area .
• Ensure that operatives shall not extend their hands, Legs,
heads beyond the building edge and try to approach
insupportable position where potential to risk of fall from
height, severe injury.
• To ensure that tile workers shall not dismantle/remove the
edge protection/ handrails.

PPE:
• Ensure all workers wear their individual safety harness.
• Required PPE to be worn by workers undertaking the
task.

Ensure Legal Compliance to


OSHAD SF CoP - 2.0 PPE
OSHAD SF CoP - 14.0 Manual Handling
OSHAD SF CoP - 17.0 Signage

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

OSHAD SF CoP - 22.0 Barricading of Hazards


OSHAD SF CoP - 23.0 Working at Heights
OSHAD SF CoP - 26.0 Scaffolding
10 Use of power • Contact with sharp, rotating parts 4 3 12 High Engineering Control: 1 3 3 Low
tools • Contact with Electricity. • The area underneath where power tools are being used to
• Fire. be cordoned off and nobody allowed entering. Signs to be
• Dust posted.
• Ensure all guards are present, in good condition and used
Work - pieces are held securely in place with vices,
fixtures and clamps.
• Trailing cables are routed away from walkways or covered
to reduce trip hazards.
• Power tools trailing cable and Electrical cables shall not
be attached/connected with conductive metals,
scaffolding components etc.
• Maintain the adequate and safe electrical cables
management and provide adequate electrical cable
hanger/holder/wood stand.
• Electrical cables, cords and sockets must be in good
working order
• Power Tools Lead and Electrical cables shall not be
attached/connected with conductive metals, Scaffolding,
Ladder while using the power tools.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• All power tools on site to be operated on 110 volts. In


case, provision of reduced voltage (110 v) is not practical,
the power supply of each tool must pass through 30mA
RCD/ELCB to mitigate potential risk of shock,
electrocution and other possible danger.

Administrative Control:
• Only trained, experienced operative to operate the
Handheld power tools.
• No fingers to be on the trigger when not in use
• Ensure correct drill bit used for works being carried out
• Only operate when holding the tool on the work piece
• Ensure all tools are returned to box and stored correctly
• Ensure that the correct tools are available and used for
the job. Do not improvise.
• Visually inspect equipment before use. Look for signs of
damage to equipment casing, lead and plug. If damaged
do not use and remove from use.
• All equipment to be well maintained, clean, greased
where appropriate in accordance with manufacturers
requirements.
• Only inspected and approved equipment to be used. No
equipment is to be brought directly from supplier to work.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• First aid kit readily available and easily accessible.


• All users to have been shown the correct use of and
control measures identified by this assessment and
records of training kept.

PPE:
• Operators and workers wear task specific PPE and
always use cut resistant gloves.

Ensure Legal Compliance to


OSHAD SF CoP - 2.0 PPE
OSHAD SF CoP - 14.0 Manual Handling
OSHAD SF CoP - 15.0 Electrical Safety
OSHAD SF CoP - 17.0 Signage
OSHAD SF CoP - 22.0 Barricading of Hazards
OSHAD SF CoP - 35.0 Portable power tools
OSHAD SF CoP - 54.0 Waste Management

11 Temporary • Contact with Electricity. 4 3 12 High Engineering Control: 1 3 3 Low


Electrical Works • Fire. • All Electrical Distribution boards shall be fitted with
• Overloading circuit suitable circuit breakers.
• Overheating • All site power tools to be 110 Volts where possible.
• Short circuit, • Use of approved industrial sockets with correct rating..
• Arcing, • Lock out tag out system (for DB boxes etc).

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Explosion • Suitable earthing for all temporary plant.


• Cable tray, cable stands must be use of non conductive
materials and Electrical Cables/Equipment’s shall be not
Located wet/damp area, where exposed to excessive
temperature, Gas or other materials.

Administrative Control:
• PTW to be issued for all electrical activity.
• Only trained and authorized personnel to complete
electrical installations (DB’s etc.)
• Any 220-240V tools require pre approval of Project MEP
Manager.
• Only authorized and trained personnel to carry out work
with electrical equipment.
• PAT testing for all Electric equipment.
• All electrical equipment shall be colour-coded.
• Availability of Fire points with suitable Fire Extinguisher
(CO2).
• Damaged tools tagged, isolated and removed from
service.
• No ‘hot wiring / splicing of cables onsite. Adequate
training to involved work teams.
• Direct and competent supervision.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Prestart Briefings, and Toolbox Talks to be conducted


before start of each activity.
• All Site DB boxes to be kept locked.
• Routine inspection protocols established for electrical
installations.
• Availability of First Aiders.
• Electrical DBs, cables, and accessories shall be away
from Conductive metals/metallic parts, steel rebar,
scaffolding, Water, wet area etc.
• All temporary electrical supply system including electrical
cables, DG, DB shall be good condition, inspected and
checked on regular basis and maintain the record.
• Maintain the adequate and safe electrical cables
management and provide adequate electrical cable
hanger /holder /wood stand/buried with warning signages.
• Electrical cables, cords and sockets must be in good
working order.
• Cables should be sheathed and shouldn't have any
damage.
• Cables shouldn't be taped or have other non-standard
joints. Outer casing of the equipment/tool must not be
damaged or loose.

PPE:

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• All workers in the electrical activity must be provided with


task specific PPE.
Ensure Legal Compliance to
OSHAD SF CoP – 2.0 PPE
OSHAD SF CoP – 15.0 Electrical
OSHAD SF CoP – 17.0 Signage
OSHAD SF CoP – 21.0 PTW
OSHAD SF CoP – 22.0 Barricading of Hazards
OSHAD SF CoP – 24.0Lock out/ Tag out
12 Manual • Heavy loads 3 2 6 Moderate Engineering Control: 1 2 2 Low
Handling tasks • Uneven loads • Mechanical aids to be used where possible.
• Poor technique. • Materials to be stacked on level ground close to the work
• Unsafe posture site by mechanical means if possible.
• Physical Hazard • Ensure the route to be travelled is free from obstacles or
• Material fall from height hazards and having adequate illumination.
• Incorrect lifting offloads
• Improper stacking Administrative Control:
• Collapse of load • Ensure each lift is planned and assessed, avoid double
• Sharp edges. handling of materials.
• Pinch Points • All staff HSE inducted.
• Slip/trip/fall • Prestart Briefings, and Toolbox Talks ref: manual
handling.
• Provide awareness to technicians about ergonomic
principles.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Large or oversized items not to be manually handled in


stairways or limited access locations.
• Job rotation for lifting tasks.
• Regular breaks.
• Consider two (2) person lift.
• No stacking above shoulder level.
• Selection of materials based on weight / size e.g. 25kg
bags not 50kg, or 3m pipe lengths not 6m if possible.
• Inspect the material to be lifted for sharp corners,
firmness / rigidity of the packing.

PPE:
• Selection and use of appropriate PPE.

Ensure Legal Compliance to


OSHAD SF CoP - 2.0 PPE
OSHAD SF CoP - 4.0 First Aid
OSHAD SF CoP - 5.0 Occ. Health
OSHAD SF CoP - 14.0 Manual Handling
13 Working in • Heat related hazards 3 3 9 High Engineering Control: 1 3 3 Low
Adverse • Skin ageing. • Establish designated shelter areas where workers can
Weather • Eye strain. seek stay during adverse weather.
Conditions • Thermal Radiation. • Ensure proper drainage systems are in place to prevent
• UV Radiation. flooding on the construction site

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Wind speed must be regularly inspected with use of


Anemometer.

Administrative Control:
• Lifting activity to be stopped on high winds of 38km/hr
• Monitor weather forecasts regularly to anticipate adverse
conditions in advance.
• Implement a clear communication plan to relay weather
updates and changes in work plans
• Adjust work schedules to avoid the most severe weather
conditions if possible.
• Train workers on recognizing signs of adverse weather
and taking appropriate precautions.
• Regularly inspect and maintain equipment to minimize the
risk of malfunction in challenging weather.
• Have emergency response plans in case of severe
weather events.
• Encourage workers to stay hydrated and take breaks in
shaded areas during extreme heat
• Provision of drinking water for all work locations
• Prestart Briefings, and Toolbox Talks.
• Toilets to have urine colour-charts posted to aid self-
assessment of dehydration levels.
• Availability and awareness of First Aiders.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

• Adequate training to involved work teams.


• Direct and competent supervision.

PPE:
• Provide appropriate personal protective equipment (PPE)
for extreme weather conditions (e.g., rain gear, cold-
weather gear).

Ensure Legal Compliance to


OSHAD SF CoP - 4.0 First Aid
OSHAD SF CoP - 5.0 Occ. Health
14 Waste • Accumulation of waste 4 3 12 High Engineering Control: 1 3 3 Low
Management • Air Emission • Ensure before and after the task housekeeping must
• Land Contamination carried out and dispose waste in provided temporary
disposal area
• Ensure that incompatible waste is not mixed.
• Dispose all waste to the designated trash bin according to
its classification.
• Training shall be competency-based and include; waste
classification, Waste storage, transport and disposal
methods
• Operatives shall determine the potentially hazardous
properties of their waste
• Drip trays to be used for keeping the fuel containers.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Risk
Classification Initial Classification Residual
Risk Risk
Action to be Taken to Reduce the Risk

Risk Rating (R)

Risk Rating (R)


Probability (P)

Probability (P)
Level Level

Severity (S)

Severity (S)
S (Abide by the *Hierarchy of Safety Controls)
Activity Element Significant Potential Hazards Low/ Low/

PxS

PxS
No. (Include reference to corresponding legal and other
Moderat Moderate/
requirements)
e/ High/ High/
Extreme Extreme

Administrative Control:
• Spill kits to be used if necessary.
• Maintain the level of housekeeping at all time.
• Tool box talks shall be conduct to all operative regarding
the potential hazard of poor waste management

PPE:
• Use Mandatory PPE such as hand gloves, safety shoes
and dust mask.

Ensure Legal Compliance to


OSHAD SF CoP - 1.0 Hazardous Materials
OSHAD SF CoP - 2.0 PPE
OSHAD SF CoP - 14.0 Manual Handling
OSHAD SF CoP - 54.0 Waste Management

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Risk Grading Matrix

SEVERITY
PROBABILITY
Insignificant (1) Minor (2) Moderate (3) Major (4) Catastrophic (5)
Rare (1) 1 2 3 4 5
Possible (2) 2 4 6 8 10
Likely (3) 3 6 9 12 15
Often (4) 4 8 12 16 20
Frequent/Almost Certain (5) 5 10 15 20 25
Absolutely Unacceptably High
15 - 25 Extreme Risk
Activity or industry should not proceed in current form
Unacceptably High
8 - 12 High Risk Activity or industry should be modified to include remedial planning and action and be subject to detailed OHS
risk assessment
Acceptable but must be managed at “As Low As Reasonably Practicable” (ALARP) Activity or process can
4–6 Moderate Risk
operate subject to management and / or modification
Acceptable without required further action
1 -3 Low Risk
No action required unless escalation of risk is possible

*Hierarchy of Safety Controls (Controls identified may be a mixture of the hierarchy in order to provide minimum operator exposure)

Elimination Eliminate the hazard (Where possible)


Substitution Provide an alternative that can perform the same and is safer to use.

JEET-HSE-Form-55 Rev. 00
The Sustainable Investment
Co. SPV Ltd.

PROJECT CLIENT DEVELOPER PROJECT MANAGER ENGINEER CONTRACTOR SUB CONTRACTOR

OSH RISK ASSESSMENT

Company Name: JEET Construction LLC Project Title: The Sustainability City Yas Island
Work/Activity Description: Swimming pool Civil and MEP Construction work. Rev: 00
Rev Date: 19-08-2024

Engineering Controls Provide or construct a physical barrier or guard or technical measures.


Administrative Controls Develop policies, procedures, practice and guidelines, in consultation with employees, to mitigate the risk. Provide
training, instruction and supervision about the hazard.
Personal Protective Equipment Personal Protective Equipment designed to protect the individual from the hazard.

Prepared By: NIMAL BALAKRISHNAN Prepared By: TARIQ RADWAN Approved By: IBHRAHIM AL TITI
Designation: HSE Engineer Designation: HSE Manager Designation: Project MANAGER
Signature: Signature: Signature:

Date of Next Review (as applicable): 18/02/2025 Company Stamp: ……………………………