ITPM - UNIT - II - Chapter 1
ITPM - UNIT - II - Chapter 1
• Project Scheduling:
• Project Scheduling, Introduction to PERT and CPM,
Critical Path Calculation, Precedence Relationship,
Difference between PERT and CPM, Float Calculation
and its importance, Cost reduction by Crashing of
activity.
• Resource Management
– Having finished with resource forecasting, you can also see what
skills and, consequently, what specialists are necessary to bring
the idea to life, and when they are necessary. That means you can
start allocating resources.
• 6. Resource Leveling
– Resource leveling is a technique used to adjust
the project schedule to resolve resource conflicts
and optimize resource utilization. It involves
redistributing or smoothing resource allocations
over time to ensure a balanced workload and
prevent resource overallocation or shortages.
Dr. G. Ramanjaiah, Assoc. Prof.
• 7. Schedule Compression Techniques
– Schedule compression techniques such as crashing
and fast-tracking are used to shorten project
durations and accelerate project schedules to meet
tight deadlines or overcome schedule constraints.
Crashing involves adding resources or increasing
their efficiency to reduce task durations, while fast-
tracking involves overlapping sequential tasks to
expedite project completion.
– Pessimistic time:
– This is the longest it can take to complete a project activity.
It's the maximum project duration based on worst-case
scenario analysis.
• Disadvantages of PERT:
– In complex projects, many find PERT hard to interpret, so they may
also use a Gantt chart, another popular method for project
management.
– It can be tedious to update, modify, and maintain the PERT
diagram.
– Maintenance of PERT is also expensive and complex.
– The actual distribution of may be different from the PERT beta
distribution which causes wrong assumptions.
– It under estimates the expected project completion time as there is
chances that other paths can become the critical path if their
related activities are deferred. Dr. G. Ramanjaiah, Assoc. Prof.
CPM
• CPM full form is the Critical Path Method.
• The critical path method is a technique that allows
you to identify tasks that are necessary for project
completion.
• The critical path in project management is the
longest sequence of activities that must be finished
on time to complete the entire project.
• In CPM, we are supposed to assume that the project
duration is certain.
• It is generally used to ascertain every activity’s
earliest possible starting time.
• The queue is avoided by differentiating critical and
non-critical activities.
Dr. G. Ramanjaiah, Assoc. Prof.
• This also helps in reducing time. Any activity
can be treated as a critical activity if any delay
of such can delay the whole process.
• It is mostly found in construction, research
projects, engineering, aerospace, plant
maintenance, and software development.
• A CPM method developed should contain four
values. There is a list of activities required to
finish the project, the duration of each activity
to complete, and any dependencies between
the activities and milestones to be achieved.
• Using this, the longest path from the activities
to the milestone or endpoints is found.
• This process also decides critical activities. It
determines the least time to complete the
project.
• Disadvantages of CPM
– For beginners its difficult to understand
– Software too expensive
– Sometimes, to structure CPM is too time-
consuming
– It cannot control and form the schedule of a
person involved in the project
– Allocation of resources cannot be monitored
properly
Dr. G. Ramanjaiah, Assoc. Prof.
Comparison PERT technique CPM technique
Basis
It is a technique of project It is a statistical technique of
management, used to manage the project management that
Meaning
uncertain activities (time) of a controls the well-defined
project. activities of a project.
Controls Control of time Control of time and cost
Orientation Event-oriented technique Activity-oriented technique
Research and development project Projects are of repetitive nature,
Type of project such as civil construction
projects such as building ships.
Model Probabilistic Model Deterministic model.
Estimates Three-time estimate One-time estimate
High precision time estimation and Reasonable times estimates and
Appropriate for
predictable activities unpredictable activities
Non-repetitive and complex projects repetitive and non complex
Nature of jobs
projects
No differentiation Differentiates in critical and non-
Differentiation
critical activities
Crashing Non-applicable Applicable
concept
Project type Research and development projects Non-research projects
Dummy Dummy activities are not used Dummy activities are used for
activities Dr. G.ofRamanjaiah,
representing a series tasks Assoc. Prof.
Aspect PERT CPM
Nature of Job It has Non-repetitive nature of job. It has repetitive nature of job.
• Start-to-Start (SS):
– In this relationship, two tasks can start simultaneously,
but Task B cannot start before Task A has begun.
– Example: Data collection (Task B) can start at the same
time as Data analysis (Task A), but not before it.
• Start-to-Finish (SF):
– This relationship is less common and implies
that Task B cannot finish before Task A starts.
– Example: Maintenance (Task B) cannot finish
before Upgrades (Task A) start.
– 1. Flexible Scheduling
• Buffer for Delays: Float provides a buffer for tasks that might
take longer than expected. If a task has float, it can be
delayed without pushing back the entire project timeline.
– 2. Risk Management
• Mitigating Risks: Projects often encounter unforeseen issues
or delays. Float acts as a cushion, giving project managers a
safety net to handle these risks without derailing the project.
• 4. Project Optimization
– Efficient Use of Time: Float helps in optimizing the project
schedule by identifying areas where time can be saved or
extended. This ensures that the project runs as smoothly as
possible.
– Maximizing Efficiency: With float, project managers can push
non-critical tasks without affecting overall timelines, making
the project execution more flexible and efficient.
Dr. G. Ramanjaiah, Assoc. Prof.
• 5. Communication and Stakeholder
Management
– Setting Realistic Expectations: Float allows for setting
more realistic deadlines and expectations with
stakeholders. It helps in managing expectations regarding
potential delays and overall project timelines.
– Transparent Updates: Float helps in providing clear
updates to stakeholders about project progress and any
potential delays.