BUILDCROWN MEP SERVICES CONSULTANT LLP.

B - 202, VIGHNAHARTA CHS.,


SECTOR 1, PLOT 7, KHANDESHWAR,
NEW PANVEL- 410206.
Report No: 01
Client: Evernest Developers
Date: 25/01/22
Architect: 07 Architects
Project: Taloje
Area C.L./ Total Total Total
Sl. W/ Diversit Load MD
Description (Sq.Mt. Flat Connection Area C.L. D.G. Load
No. Sq.Mtr y Factor (KW)
) (kW) s /Units (Sq.Mt.) (kW)
TOWER TYPICAL

I RESIDENTIAL FLAT LOAD

1 Wing A 1261.7 75 94.6 1 1262 94.6 1.5 63.1 0.0 0.0

2 Wing B 2223.5 75 166.8 1 2224 166.8 1.5 111.2 0.0 0.0

3 Wing C 2516.5 75 188.7 1 2517 188.7 1.5 125.8 0.0 0.0

4 Wing D 2516.5 75 188.7 1 2517 188.7 1.5 125.8 0.0 0.0

5 Wing E 2142.6 75 160.7 1 2143 160.7 1.5 107.1 0.0 0.0

6 Wing F 2354.1 75 176.6 1 2354 176.6 1.5 117.7 0.0 0.0

7 Wing G 2393.1 75 179.5 1 2393 179.5 1.5 119.7 0.0 0.0

8 Wing H 2435.6 75 182.7 1 2436 182.7 1.5 121.8 0.0 0.0

9 Wing I 2435.6 75 182.7 1 2436 182.7 1.5 121.8 0.0 0.0

10 Wing J 3875.6 75 290.7 1 3876 290.7 1.5 193.8 0.0 0.0

11 Wing k 2946.5 75 221.0 1 2946 221.0 1.5 147.3 0.0 0.0

12 Shops 150 0.0 1 0 0.0 2.5 0.0 0.0 0.0

TOTAL RESIDENTIAL LOAD ( KW ) 12 27101.3 2032.6 1355.1 0.0 0.0

BUILDING LEVEL COMMON AREA LOAD -


II
WING A

Typical floor Passage Area Lighting & Power


1 0.0 7 0.2 1.5 0.1 0.1 0.0
Load

2 Entrance lobby 0.1 1 0.1 1.5 0.1 0.1 0.0

3 Staircase Lighting Load 0.0 8 0.3 1.5 0.2 0.2 0.2

4 Terrace Lighting Load 0.0 1 0.0 1.5 0.0 0.0

5 Refuge Floor / Stilt Park 0.2 1 0.2 1.5 0.1 0.1 0.1

6 Lift Load 7.5 1 7.5 1.5 5.0 5.0 7.5

7 Fire Booster Pump 11.0 1 11.0 1.0 11.0 11.0 11.0

8 PHE Booster Pump 5.5 2 11.0 1.5 7.3 7.3 0.0

9 ELV load 1.0 1 1.0 1.5 0.7 0.7 0.7

10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL COMMON AREA LOAD ( KW ) 31.3 24.5 24.5 19.5


BUILDING LEVEL COMMON AREA LOAD -
III
WING B

Typical floor Passage Area Lighting & Power


1 0.1 7 1.0 1.5 0.7 0.7 0.1
Load

2 Entrance lobby 0.2 1 0.2 1.5 0.1 0.1 0.0

3 Staircase Lighting Load 0.0 8 0.3 1.5 0.2 0.2 0.2

4 Terrace Lighting Load 0.0 1 0.0 1.5 0.0 0.0

5 Refuge Floor / Stilt Park 0.3 1 0.3 1.5 0.2 0.2 0.2

6 Lift Load 7.5 1 7.5 1.5 5.0 5.0 7.5

7 Fire Booster Pump 1 0.0 1.0 0.0 0.0 0.0

8 PHE Booster Pump 5.5 2 11.0 1.5 7.3 7.3 0.0

9 ELV load 1.0 1 1.0 1.5 0.7 0.7 0.7

10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL COMMON AREA LOAD ( KW ) 21.4 14.2 14.2 8.7

BUILDING LEVEL COMMON AREA LOAD -


IV
WING C

Typical floor Passage Area Lighting & Power


1 0.2 7 1.2 1.5 0.8 0.8 0.1
Load

2 Entrance lobby 0.2 1 0.2 1.5 0.2 0.2 0.0

3 Staircase Lighting Load 0.0 8 0.3 1.5 0.2 0.2 0.2

4 Terrace Lighting Load 0.0 1 0.0 1.5 0.0 0.0

5 Refuge Floor / Stilt Park 0.3 1 0.3 1.5 0.2 0.2 0.2

6 Lift Load 7.5 1 7.5 1.5 5.0 5.0 7.5

7 Fire Booster Pump 1 0.0 1.0 0.0 0.0 0.0

8 PHE Booster Pump 5.5 2 11.0 1.5 7.3 7.3 0.0

9 ELV load 1.0 1 1.0 1.5 0.7 0.7 0.7

10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL COMMON AREA LOAD ( KW ) 21.6 14.4 14.4 8.7

BUILDING LEVEL COMMON AREA LOAD -


V
WING D

Typical floor Passage Area Lighting & Power


1 0.2 7 1.2 1.5 0.8 0.8 0.1
Load

2 Entrance lobby 0.2 1 0.2 1.5 0.2 0.2 0.0

3 Staircase Lighting Load 0.0 8 0.3 1.5 0.2 0.2 0.2

4 Terrace Lighting Load 0.0 1 0.0 1.5 0.0 0.0

5 Refuge Floor / Stilt Park 0.3 1 0.3 1.5 0.2 0.2 0.2

6 Lift Load 7.5 1 7.5 1.5 5.0 5.0 7.5

7 Fire Booster Pump 1 0.0 1.0 0.0 0.0 0.0

8 PHE Booster Pump 5.5 2 11.0 1.5 7.3 7.3 0.0

9 ELV load 1.0 1 1.0 1.5 0.7 0.7 0.7

10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0
TOTAL COMMON AREA LOAD ( KW ) 21.6 14.4 14.4 8.7

BUILDING LEVEL COMMON AREA LOAD -


VI
WING E

Typical floor Passage Area Lighting & Power


1 0.1 7 0.8 1.5 0.6 0.6 0.1
Load

2 Entrance lobby 0.2 1 0.2 1.5 0.2 0.2 0.0

3 Staircase Lighting Load 0.0 8 0.3 1.5 0.2 0.2 0.2

4 Terrace Lighting Load 0.0 1 0.0 1.5 0.0 0.0

5 Refuge Floor / Stilt Park 0.3 1 0.3 1.5 0.2 0.2 0.2

6 Lift Load 7.5 1 7.5 1.5 5.0 5.0 7.5

7 Fire Booster Pump 1 0.0 1.0 0.0 0.0 0.0

8 PHE Booster Pump 5.5 2 11.0 1.5 7.3 7.3 0.0

9 ELV load 1.0 1 1.0 1.5 0.7 0.7 0.7

10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL COMMON AREA LOAD ( KW ) 21.2 14.2 14.2 8.7

BUILDING LEVEL COMMON AREA LOAD -


VII
WING F

Typical floor Passage Area Lighting & Power


1 0.1 7 0.8 1.5 0.6 0.6 0.1
Load

2 Entrance lobby 0.2 1 0.2 1.5 0.2 0.2 0.0

3 Staircase Lighting Load 0.0 8 0.3 1.5 0.2 0.2 0.2

4 Terrace Lighting Load 0.0 1 0.0 1.5 0.0 0.0

5 Refuge Floor / Stilt Park 0.3 0.0 1.5 0.0 0.0 0.0

6 Lift Load 7.5 1 7.5 1.5 5.0 5.0 7.5

7 Fire Booster Pump 1 0.0 1.0 0.0 0.0 0.0

8 PHE Booster Pump 5.5 2 11.0 1.5 7.3 7.3 0.0

9 ELV load 1.0 1 1.0 1.5 0.7 0.7 0.7

10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL COMMON AREA LOAD ( KW ) 20.9 14.0 14.0 8.5

BUILDING LEVEL COMMON AREA LOAD -


VIII
WING G

Typical floor Passage Area Lighting & Power


1 0.2 7 1.2 1.5 0.8 0.8 0.1
Load

2 Entrance lobby 0.2 1 0.2 1.5 0.2 0.2 0.0

3 Staircase Lighting Load 0.0 8 0.3 1.5 0.2 0.2 0.2

4 Terrace Lighting Load 0.0 1 0.0 1.5 0.0 0.0

5 Refuge Floor / Stilt Park 0.3 1 0.3 1.5 0.2 0.2 0.2

6 Lift Load 7.5 1 7.5 1.5 5.0 5.0 7.5

7 Fire Booster Pump 1 0.0 1.0 0.0 0.0 0.0

8 PHE Booster Pump 5.5 2 11.0 1.5 7.3 7.3 0.0

9 ELV load 1.0 1 1.0 1.5 0.7 0.7 0.7


10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL COMMON AREA LOAD ( KW ) 21.6 14.4 14.4 8.7

BUILDING LEVEL COMMON AREA LOAD -


IX
WING H

Typical floor Passage Area Lighting & Power


1 0.1 7 0.8 1.5 0.6 0.6 0.1
Load

2 Entrance lobby 0.2 1 0.2 1.5 0.2 0.2 0.0

3 Staircase Lighting Load 0.0 8 0.3 1.5 0.2 0.2 0.2

4 Terrace Lighting Load 0.0 1 0.0 1.5 0.0 0.0

5 Refuge Floor / Stilt Park 0.3 1 0.3 1.5 0.2 0.2 0.2

6 Lift Load 7.5 1 7.5 1.5 5.0 5.0 7.5

7 Fire Booster Pump 1 0.0 1.0 0.0 0.0 0.0

8 PHE Booster Pump 5.5 2 11.0 1.5 7.3 7.3 0.0

9 ELV load 1.0 1 1.0 1.5 0.7 0.7 0.7

10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL COMMON AREA LOAD ( KW ) 21.2 14.2 14.2 8.7

BUILDING LEVEL COMMON AREA LOAD -


X
WING I

Typical floor Passage Area Lighting & Power


1 0.1 7 0.8 1.5 0.6 0.6 0.1
Load

2 Entrance lobby 0.2 1 0.2 1.5 0.2 0.2 0.0

3 Staircase Lighting Load 0.0 8 0.3 1.5 0.2 0.2 0.2

4 Terrace Lighting Load 0.0 1 0.0 1.5 0.0 0.0

5 Refuge Floor / Stilt Park 0.3 1 0.3 1.5 0.2 0.2 0.2

6 Lift Load 7.5 1 7.5 1.5 5.0 5.0 7.5

7 Fire Booster Pump 1 0.0 1.0 0.0 0.0 0.0

8 PHE Booster Pump 5.5 2 11.0 1.5 7.3 7.3 0.0

9 ELV load 1.0 1 1.0 1.5 0.7 0.7 0.7

10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL COMMON AREA LOAD ( KW ) 21.2 14.2 14.2 8.7

BUILDING LEVEL COMMON AREA LOAD -


XI
WING J

Typical floor Passage Area Lighting & Power


1 0.3 7 2.4 1.5 1.6 1.6 0.2
Load

2 Entrance lobby 0.5 1 0.5 1.5 0.3 0.3 0.0

3 Staircase Lighting Load 0.1 8 0.6 1.5 0.4 0.4 0.4

4 Terrace Lighting Load 0.1 1 0.1 1.5 0.1 0.1

5 Refuge Floor / Stilt Park 0.6 1 0.6 1.5 0.4 0.4 0.4

6 Lift Load 7.5 2 15.0 1.5 10.0 10.0 7.5

7 Fire Booster Pump 1 0.0 1.0 0.0 0.0 0.0

8 PHE Booster Pump 5.5 4 22.0 1.5 14.7 14.7 0.0


9 ELV load 1.0 2 2.0 1.5 1.3 1.3 1.3

10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL COMMON AREA LOAD ( KW ) 43.2 28.8 28.8 9.8

BUILDING LEVEL COMMON AREA LOAD -


XII
WING K

Typical floor Passage Area Lighting & Power


1 0.2 7 1.2 1.5 0.8 0.8 0.1
Load

2 Entrance lobby 0.2 1 0.2 1.5 0.2 0.2 0.0

3 Staircase Lighting Load 0.0 8 0.3 1.5 0.2 0.2 0.2

4 Terrace Lighting Load 0.0 1 0.0 1.5 0.0 0.0

5 Refuge Floor / Stilt Park 0.3 1 0.3 1.5 0.2 0.2 0.2

6 Lift Load 7.5 1 7.5 1.5 5.0 5.0 7.5

7 Fire Booster Pump 1 0.0 1.0 0.0 0.0 0.0

8 PHE Booster Pump 5.5 2 11.0 1.5 7.3 7.3 0.0

9 ELV load 1.0 1 1.0 1.5 0.7 0.7 0.7

10 Pressurization load Lift well 0.0 0.0 0.0 0.0 0.0 0.0

TOTAL COMMON AREA LOAD ( KW ) 21.6 14.4 14.4 8.7

TOTAL LOAD OF TOWER - TYPICAL 27101.3 2299.4 1536.6 181.5 107.1

COMMON INFRA UTILITY

Grd. FL. Common area Lighting & Power


1 30.00 1 30.0 1.50 20.00 20.0 10.0
Load
2 Pressurization Fan staircase Podium 0.0 0.0 0.0 0.0 0.0

3 Ventilation Fan Load 0.0 2.50 0.00 0.0 0.0

4 Club House - Swimming Pool 20.00 1 20.0 1.50 13.33 0.0 0.0

5 Fire Fighting Load

Fire Jockey Pump 4 0.0 0.50 0.00 0.0 0.0

Fire Main Pump 2 0.0 0.00 0.00 0.0 0.0

6 Plumbing Load 75.00 1 75.0 1.50 50.00 50.0 15.0

7 Sump pump load 0.0 1.50 0.00 0.0 0.0

8 STP load 50.00 1 50.0 1.50 33.33 33.3 6.7

9 STP Transfer Pump test 10.00 1 10.0 1.50 6.67 6.7 0.0

10 OWC load 20.00 1 20.0 1.50 13.33 3.3 0.0

11 Irrigation Pump Load 7.50 1 7.5 1.50 5.00 2.5 0.0

12 ELV load 0.0 1.50 0.00 0.0 0.0

13 External,Facade & Landscape lighting load 25.00 1 25.0 1.50 16.67 8.3 5.0

TOTAL LOAD OF COMMON INFRA UTILITY FOR BUILDINGS 237.5 158.3 124.2 36.7
BUILDCROWN MEP SERVICES CONSULTANT LLP.
B - 202, VIGHNAHARTA CHS.,
SECTOR 1, PLOT 7, KHANDESHWAR,
NEW PANVEL- 410206.
Report No: 1
Client: Evernest Developers
Date: 25/01/22
Architect: 07 Architects
Project: Taloje

TOTAL SUMMARY OF ELECTRICAL LOADS WITH DG LOAD


D.G. Load in KW
Connected Max. KW for
Sr. No. of Load Demand Grid KW for Fire
N0 Description Flats (KW) (KW) Emergency Emergency
1 TOWER TYPICAL 2299 1537 182 107
2 COMMON INFRA UTILITY 238 158 124 37
Total Load 0 2537 1695 306 144
Overall diversity Factor
(0.8 for Trafo. & 0.8 for 1356 245 115
D.G. Set for Grid & 0.8 for DG set for Fire
Emg.)
Maximum Demand in KVA at 0.8 PF for 1695 306 144
Transformer & at 0.8 PF for D.G.Set
Considering 80% Loading on Xmer & 80% 2119 382 180
Loading on D.G.Set
Say 04# 630 01# 500
kVA kVA
BUILDCROWN MEP SERVICES CONSULTANT LLP.
B - 202, VIGHNAHARTA CHS.,
SECTOR 1, PLOT 7, KHANDESHWAR,
NEW PANVEL- 410206.
Report: 01
Client: Evernest Developers
Architect: 07 Architects
Date: 25/01/22
Project: Taloje

ESTIMATED AVERAGE ANNUAL ELECTRICITY CONSUMPTION


AVG.KWH/
SR.NO LOAD DESCRIPTION AVG (KW) QTY AVG.HRS/ DAY
DAY
1 BUILDING COMMON AREA LOAD
1.1 Typical floor Passage Area Lighting & Power Load 9.5 1 10 95
1.2 Staircase Lighting Load 2.6 1 10 26
1.3 Terrace Lighting Load 0.3 1 4 1
1.4 Refuge Floor / Stilt Park 2.13 1 6 13
1.5 Normal Lift Load 60 1 6 360
1.6 Fire Booster Pump 11 1 0 0
1.7 PHE Booster Pump 88 1 4 352
1.8 ELV load 8 1 12 96

2 COMMON AREA LOAD


2.1 Grd FL + Common area Lighting & Power Load 20 1 10 200
2.2 Fire Fighting Load (Jocky Pump) 0 1 0.2 0
2.3 Ventilation load 1 0.2 0
2.4 Club House - swimming pool 13 1 2 27
2.5 Plumbing Load 50 1 4 200
2.6 STP load 40 1 2 80
2.7 OWC load 13 1 2 27
2.8 Irrigation Pump Load 5 1 2 10
2.9 ELV load 0 1 12 0

3 External,Facade & Landscape lighting 16.67 1 6 100


Average KWH/ Day for Building Common area & Utilities 1586
Average KWH/ Annum for Building Common area & Utilities 578968

REDUCTION IN CONSUMPTION BY USING ENERGY SAVING MEASURE

1 Energy saving using LED light for Lift Lobby & Staircase
Diff Between 12W LED and 20W CFL Lighting Fixt 8 W which comes to 40 %
Diff Between 18W LED and 30W CFL Lighting Fixt 12 W which comes to 40 %
40 % of saving by using LED light as compare to
40%
CFL light
Energy saving using VFD for pumps, Basement
20%
2 ventilation and Lift with High Efficiency Motors
Energy saving using Automatic Timer operation Against Manual operation for External,Facade & Landscape &
3 Common Area Lighting
25% lights will be off for 8 hours 25%
25% lights will be off for 4 hours 25%
4 Energy saving using Low Loss Transformer as per ECBC Against Conventional Transformer
Low Loss 630kVA Transformer losses are 5.8kW
as per ECBC norms compare to Conventional 5%
Transformer whose losses are 6.1kW
5 Use of Solar Water Heater for -----Flats 100%
A Energy Saving Due to LED Lamp
1 Typical floor Passage Area Lighting & Power Load 95 40 57.1 38
2 Staircase Lighting Load 26 40 15.4 10
3 Terrace Lighting Load 1 40 0.8 1
4 Refuge Floor / Stilt 13 40 7.7 5
Common area Lighting & Power Load (80%
180 40 108.0 72
5 Lighting Load)_
6 External,Facade & Landscape lighting 100 40 60.0 40

B Energy Saving Due to VFD & High Efficiency Motors


1 Saving in lift by using V3F drives 360 20 288.0 72
2 Saving in Plumbing pump by using VFD 552 20 441.6 110
Energy Saving Due to Automatic Timer operation Against Manual operation for External,Facade &
C Landscape & Common Area
Saving in External,Facade & Landscape &
Common Area from 10pm to 2 am by switching 100 25 75.0 25
1 off 25% total lights & from 2am to 6am by
switching off 50% total lights

D Energy saving due to Low Loss Transformer as per ECBC Against Conventional Transformer
1 04 nos.630 kVA transformer 4 5 3.8 0.2
Average KWH/Day saving 374
Average KWH/Annual saving 136346.48

TOTAL ANNUAL SAVING OF BUILDING COMMON AREAS & UTILITIES 136346


SAVING IN PERCENTAGE % OF BUILDING COMMON AREAS & UTILITIES 24%
BUILDCROWN MEP SERVICES CONSULTANT LLP.
B - 202, VIGHNAHARTA CHS.,
SECTOR 1, PLOT 7, KHANDESHWAR,
NEW PANVEL- 410206.

Report: 01
Client: Evernest Developers Date : 25/01/22
Architect: 07 Architects
Project: Taloje

SR.NO ESTIMATED RENEWABLE ENERGY REQUIREMENT FOR -------------


A. Energy Saving summary using Solar Water Heater Against Electrical water Heater
Total no. of Flats in Building 544
Power Consumption by Geyser in each flat in kWH/day considering 1 hours of operation 2
Power Consumption by Gyser in kWH/day for entire Building per day 1088
Total no. of flats considered on Solar water heaters ( For 544 Flats ) 544
Energy saving with solar water heater in kWH/day 1088
Total Hot water requirement for Solar water heater in Litres considering 100 liters per flat (Considering 15 54400
liters water for each person)
Total no. ofrequired
Total area Solar Water Heater
for Solar Panel
Water required
Heater onon
Panel Terrace area
Terrace (Considering
area 125 30%
in sq. Mtrs with liter panel
spaceeach)
for 348
maintainance 1358

Total % of Average KWH/ Day Energy generated from Solar Water Heater with Actual Average
KWH/ Day Energy consumption of Geyser 100%
B. Energy Saving summary using Solar PV cells
Estimated Average KWH/ Day Energy consumption Without using Energy Saving Measures 943
Estimated Average KWH/day saving by using Energy Saving Measures 374
Actual Average KWH/ Day Energy consumption 569
Total no. of Solar PV Panel fit on Terrace area (Considering 325Wp each) 45
Total kWp from Solar PV Panel (Considering 325Wp each) 15
Total area required for Solar PV Panel on Terrace area in sq. Metres ( Considering 10 sq. Meter space for 1 145
kWp requirement )
Total Average KWH/ Day Energy generated from Solar PV Panel (As per Ministry of New & Renewable
73
Energy Solar Rooftop Calculator.)
Total % of Average KWH/ Day Energy generated from Solar PV Panel with Actual Average KWH/
Day Energy consumption 3%
SUMMARY FOR RENEWABLE ENERGY REQUIREMENT
Total no. of Solar Water Heater Panel required on Terrace area(Considering 100 liter panel ) 348
Total kWp from Solar PV Panel (Considering 250Wp each) 15
Total area required for Solar Water Heater & PV Panel on Terrace area in sq. Metres 1503
Total usable area available on Terrace area in sq. Mtrs