TITLES GENERAL INSTRUCTIONS PRESENTATION OF DRAWING DATA SPECIFICATIONS SITE DEVELOPMENT SURVEYING AND MAPPING GEOTECHNICAL LANDSCAPING, PLANTING AND TURFING WATER, WASTEWATER AND ENVIRONMENTAL PROTECTION ARCHITECTURAL INTERIOR DESIGN STRUCTURAL PLUMBING HEATING, VENTILATING, AND AIR CONDITIONING FIRE SUPPRESSION SYSTEM OTHER MECHANICAL SYSTEMS AND EQUIPMENT ELECTRICAL AND ELECTRONIC SYSTEMS CORROSION CONTROL AND CATHODIC PROTECTION SYSTEMS COST ESTIMATING ANTITERRORISM/FORCE PROTECTION SUSTAINABLE DESIGN AND DEVELOPMENT QUALITY CONTROL
18 19 20 21
GENERAL APPLICABLE PUBLICATIONS INSTRUCTIONS 1.3.1 Predesign Conference 1.3.2 Negotiation 1.3.3 Design Quality Control Plan 1.3.4 Architectural Studies 1.3.5 Charrette 1.3.6 Health and Safety Standards 1.3.7 Design for the Physically Handicapped 1.3.8 Topographic Surveys, Basements and Utilities 1.3.9 Foundation Investigation 1.3.10 Environmental Regulatory Permits 1.3.11 Sustainable Design 1.3.12 Anti-Terrorism/Force Protection 1.3.13 Lessons Learned DEFINITIONS 1.4.1 Design Analysis 1.4.2 Drawings 1.4.3 Specifications SUBMITTAL REQUIREMENTS 1.5.1 General 1.5.2 Project Definition (10-15%) 1.5.3 Concept Design (30-35%) 1.5.4 Value Engineering 1.5.5 Interim Design (50-65%) 1.5.6 Final Design (unreviewed 100%) 1.5.7 Ready-To-Advertise 1.5.8 Front End Contract Information
1.4
1.5
1-1
CHAPTER 1
GENERAL INSTRUCTION
1.1 GENERAL
The Mobile District Design Manual prescribes standard procedures and instructions to accomplish the required design, drawings, specifications, design analyses, cost estimates, and related support tasks for Military, Support For Others Projects, and, in as far as is applicable, Civil Works construction projects under the direction of the US Army Corps of Engineers (COE), Mobile District. This manual is written for the purpose of assisting designers, both In-house and Architect-Engineer (A-E) consultants, with a consistent logical approach to performing design and developing design related documents. The format presented is for the development of fully detailed 100% complete design drawings and fully edited Unified Facility Guide Specifications (UFGS) for use in a Design-Bid-Build or a PerformancePrice-Trade-Off construction contract acquisition. Technical criteria in this manual are also applicable to the development of Request For Proposal (RFP)documents for design accomplished under the Design-Build construction contract acquisition method. A Design Build RFP may include performance and or/prescriptive specifications which allow/require technical criteria that do not follow the specific requirements of this manual. The Project Criteria/Statement of Work (SOW) will provide project specific criteria and will, in the case of all conflicts, take precedence over the standard procedures and instructions in this Manual. The designer shall document any such conflicts in writing and bring them to the immediate attention of the Mobile District Project Manager (PM) for projects in the design phases and to the Resident Engineer for Design-Build projects that have been awarded. 1.2 APPLICABLE PUBLICATIONS
Applicable publications are listed in the various chapters of this Manual. Unless specifically stated otherwise in this Manual or the SOW, the designer shall be responsible for obtaining all publications applicable to the design of the project. The recommended source for many publications is the Construction Criteria Base (CCB) which contains COE Technical Manuals (TM), Unified Facilities Criteria (UFC), Master Planning Instructions (MPI), Engineering Regulations (ER), Engineering Technical Letters (ETL), and most industry and government standards. The CCB resides on Compact Disk - Read Only Memory (CD-ROM) and is available by subscription from the National Institute of Building Sciences, ATTN: CCB, 1090 Vermont Avenue NW, Suite 700, Washington, DC 20005; telephone (202) 289-7800. Additional project specific publications and references are listed in the SOW. ER 1110-345-700 Engineering and Design - Design Analysis
Design Build Request For Proposal (RFP) Development: Technical Instructions TI-800-01, Design Criteria and TI-800-03, Design Build
1-2
Instructions setsforth general instructions for the RFP development. All instructions shall be followed unless other requirements are specified in the Statement of Work. The Technical Instruction (TI) Manuals TI-800-01 and TI 800-03 are available for downloading from: http://www.hnd.usace.army.mil/techinfo/ti.htm 1.3 INSTRUCTIONS Predesign Conference
1.3.1
The Project Manager (PM) shall request that the designer(s) to attend a predesign conference at the project site and to participate in discussions prior to the preparation of a design budget for in-house designs or fee proposal and actual negotiations for project designed by A-E. During these discussions, all aspects of the required effort, which shall affect the designers effort, will be addressed. The designer shall be furnished a draft SOW which will contain project specific design criteria and instructions. Subsequent to the predesign conference, the designer shall receive a request to furnish a fee proposal for accomplishing the work agreed upon during the conference. 1.3.2 Negotiation
Negotiations shall be held to insure a mutual understanding of the SOW and to reach an agreement on a fair and reasonable fee. During negotiations, the SOW shall be thoroughly reviewed and revised as necessary; and the designer's fee proposal shall be examined and discussed in detail. 1.3.3 Design Quality Control Plan
A Design Quality Control Plan (DQCP) is required for all projects regardless of whether it is designed with In-House staff or by A-E Contract. See Chapter 21, DESIGN QUALITY CONTROL PLAN for specific requirements and a sample Design Quality Control Plan. Whenever a design specialist is required for a particular project, it shall be indicated in the SOW. The DQCP shall contain name(s) of the specialist(s)intended to be used, along with the specialists educational background, experience, and licenses or registrations held. 1.3.4 Architectural Studies
Models, perspectives, and interior/exterior color renderings necessary for a visual presentation to the user shall be furnished only as specified in the SOW. 1.3.5 Charrette
The designer shall conduct a Charrette only as specified in the SOW. Chapter 9 titled ARCHITECTURAL provides specific references on charrettes. 1.3.6 Health and Safety Standards
The facilities, systems, and equipment design standards of the Occupational Safety and Health Act, Code of Federal Regulations, Title
1-3
29, Chapter XVII, Parts 1910 and 1926, as applicable, shall be incorporated by the designer into all engineering design and analyses. In addition, the latest versions of the Life Safety Code and the NFPA Code shall be incorporated into the design. Any problem in incorporating these standards due to conflicts with other technical criteria shall be promptly submitted to the PAE for resolution. 1.3.7 Design for the Physically Handicapped
Unless specifically stated otherwise in the SOW, all facilities shall be designed to be accessible to, and usable by, handicapped persons in accordance with the Uniform Federal Accessibility Standards (UFAS), American with Disabilities Act (ADA), and NFPA Life Safety Codes. 1.3.8 Topographic Surveys, Easements, and Utilities Unless otherwise specified in the SOW, the designer shall obtain the topographic, hydrographic, and utility surveying and mapping data required to properly design the project. Chapter 5 titled SURVEYING AND MAPPING provides specific instructions. Subsurface utility investigation using Ground Penetrating Radar or other means of determining the three dimensional location of underground utility lines is recommended. 1.3.9 Foundation Investigation
Unless otherwise specified in the SOW, the designer shall obtain the foundation investigation (including soil and rock borings, sampling, laboratory testing, and pile load tests, where applicable), as well as tests such as percolation tests for septic tanks, soil resistivity tests for grounding and cathodic protection systems and infiltrometer test for storm water detension ponds. Chapter 6 titled GEOTECHNICAL provides specific instructions. 1.3.10 Environmental Regulatory Permits
The designer's responsibilities for environmental permits are addressed below. (a) The designer shall contact the appropriate Federal, State, local, and interstate pollution and environmental control agencies to determine the permits required and the procedures and documentation necessary to obtain them. A written record of each such contact shall be prepared and furnished within five working days to the Project Manager with copies to all parties involved. (b) Where formal documents are required to be submitted to obtain permits, the designer shall prepare all such documents and provide them in a "ready for signature" condition. This includes necessary copies of the plans, specifications, design analyses, and other required supporting documentation. After review by the COE and comment incorporation, the corrected documents will be forwarded by the COE to the installation for signature by the appropriate official and submission to the appropriate agency. Permit requirements shall be ascertained and documented by the designer during the Concept Design stage.
1-4
(c) The designer shall provide the following information and data for each required permit with the Concept submittal: (1) (2) etc.). (3) Procedure and time necessary to complete the permit application. (4) Fees required. Permitting authority (State, local, etc.). Type of permit required (construction, operation,
(5) Statement that the project is covered by variances or that permits are not required. If a variance is required, the procedures for obtaining the variance shall be provided. If a permit is not required, reasons and supporting justification (i.e., cite State, local, and/or other regulations) shall be furnished. (6) An evaluation of all State and/or local regulations to determine if monitoring devices are needed. Where required, monitoring devices shall be included in the project design. (d) The designer shall provide the completed permit applications not later than the Interim submittal or 60 days prior to the Final submittal, whichever is earlier. Permit applications shall be ready for signature by the appropriate official and submission to the approving authority. (e) With the Final submittal, the designer shall provide all supporting documents, plans, and specifications. The designer shall also have accomplished the necessary coordination to obtain permit application approvals. 1.3.11 Sustainable Design
Sustainable design is an integrated approach to planning, designing, building, operating and maintaining facilities in a collaborative and holistic manner among all stakeholders. It is meant to provide resource efficient, environmentally friendly and healthy facilities with emphasis on renewable energy and recycled materials. Sustainable design is measurable. The measure of Sustainable design is a color rating identifying the level of accomplishment. The project specific criteria, SOW or RFP shall identify the rating level to be achieved. See Chapter 20 SUSTAINABLE DESIGN for specific requirements. 1.3.12 Anti-Terrorism/Force Protection
Anti-Terrorism Force Protection is an inherent part of all projects. See Chapter 19 ANTI-TERRORISM/FORCE PROTECTION for specific requirements. 1.3.13 Lessons Learned
Lessons Learned requirements will be specifically addressed in the project Scope of Work (SOW).
1-5
1.4
1.4.1
The design analysis shall be provided with each submittal. The design analysis is a written explanation of the project design and is expanded and revised for each submission. The design analysis shall contain a summary of the criteria for and the history of the project design, including criteria furnished by the COE, letters, codes, references, conference minutes, and pertinent research. The justification for each major selection and design decision shall be clearly stated. Design calculations, computerized and manual, shall be included in the design analysis. Narrative descriptions of design solutions shall also be included. Diagrams and sketches to convey design concepts may illustrate all written material. Copies of all previous design phase review comments and the specific actions taken in response to each comment shall be included with each submission of the design analysis. A separate section with pertinent notes to the Governments Construction Manager shall also be included. Specific requirements for the design analysis are provided in other chapters of this manual. 1.4.1.1 Media and Format The design analysis shall be printed on 8 x 11 paper except when larger paper 11 x 17 folded to 8 x 11 is required for graphs or special calculation forms. 1.4.1.2 Organization The design analysis shall be in a sequential binding order and bound under a cover indicating the name of the facility. The title page shall carry the designation of the submittal. The complete design analysis presented for final review with specifications and drawings shall carry the designation "FINAL DESIGN ANALYSIS" on the title page. The Final Design Analysis shall be provided in an electronic format with documentation in a MS Word or MS Excel format. Hard calculations and other support documentation shall be scanned into an Adobe .PDF format. 1.4.1.3 Design Calculations The design calculations shall be presented in a form incorporating a title page and index for each volume. When they are voluminous, they shall be bound separately from the narrative part of the design analysis. A table of contents, which shall be an index of the indices, shall be furnished when there is more than one volume. The source of loading conditions, sketches, supplementary graphs, formulas, and references shall be identified. Assumptions and conclusions shall be explained. Calculation sheets shall have dates and names of the persons making the calculations and checkers. 1.4.1.4 Automatic Data Processing Systems (ADPS) When ADPS are used to perform design calculations, the design analysis shall include descriptions of the computer programs used and copies of the ADPS input data and output summaries. An index and a
1-6
description of the computation performed shall precede each set of computer printouts. If several sets of computations are submitted, a general table of contents in addition to the individual indices shall accompany them. The description, for an ADPS printout, shall include the following: (a) Explain the design method, assumptions, theories, and formulae. (b) Include applicable diagrams, adequately identified. (c) State exactly the computation performed by the computer. (d) Provide all necessary explanations of the computer printout format symbols, and abbreviations. (e) Use adequate and consistent notation. (f) Provide sufficient information to permit a check of the results.
1.4.2
Drawings
Drawings are a part of each submittal. The drawings in the Concept submittal may or may not be used later as working drawings. In either case, the Concept drawings show all aspects of how the functional requirements are satisfied but shall not be complicated by unnecessary detail. The Interim drawings, if required by SOW, shall be approximately 60% complete working drawings, which are adequately labeled and cross-referenced for review. Complete, thoroughly checked, and coordinated contract drawings shall be included in the Final submittal. The drawings are made Ready-To-Advertise by the incorporation of the Final review comments. Specific drawing requirements are provided in other chapters of this Manual.
1.4.3
Specifications
An outline list of specifications that the designer proposes to see for the project shall be provided at the Concept and Interim submittals. Edited specifications shall be submitted at the Final. The final contract specifications incorporating all previous review comments are required for the Ready-To-Advertise (RTA) submittal. The specifications shall be developed in accordance with guidance provided in other chapters of this Manual.
1.5
1.5.1
The documents, which the designer shall turn in for each submittal, are listed and generally described below. More specific instructions on number of copies, addressing, and other specific instructions are provided in the SOW. In keeping with Mobile District policy, covers
1-7
for all submittals shall be white with black letterings. (Colored covers on plans and spec books are reserved for advertised solicitations only). Submittals will not include the solicitation number on the drawings, specs or covers. (Solicitation numbers on plans and spec books are reserved for advertised solicitations only.) 1.5.2 Project Definition (10-15%)
This submittal represents approximately 10 to 15% of the design effort, and shall be used to validate projects requirements and the construction cost. The designer shall submit preliminary concept plans, a narrative describing each aspect of the project, and a parametric cost estimates. 1.5.3 Concept Design (30-35%)
This submittal represents approximately 30 to 35% of the design effort and shall be of sufficient detail to show how the users' functional and technical requirements will be met, indicate the designer's approach to the solution of technical problems, show compliance with design criteria or provide justification for noncompliance, and provide a valid estimate of cost. The Concept Design consists of: (a) Design Analysis: (1) Design narrative, notes to Construction Manager, and design calculations for all disciplines. (2) Outline specifications. (3) Environmental permitting memorandums (b) Concept drawings.
(c) Bidding schedule with Bid Options identified when applicable. (d) (e) Concept cost estimate. Required information and data for each required permit.
1.5.4
Value Engineering
Shortly after or in conjunction with the Concept Design submittal, the designer shall perform a Value Engineering (VE) Study if so directed. The VE Study shall provide a candidate list of areas to be considered for value engineering evaluation. Areas listed shall be those that appear too costly due to design constraints placed on the designer by the project criteria and COE guidance and specifications and include alternatives for meeting the project requirements. 1.5.5 Interim Design (50-65%)
This submittal, if required, is primarily to insure that funding limitations are not being exceeded and that the drawings, specifications, design analysis, and cost estimate are proceeding in a
1-8
timely manner and that the design criteria and previous review comments are being correctly interpreted. The Interim Design shall consist of: (a) Design Analysis developed to approximately 60% completion.
(b) Approximately 60% complete drawings including those addressing construction phasing. (c) Detailed cost estimate developed to approximately 60% completion. Identify Bid Option where applicable. (d) Annotated Concept review comments.
(e) Completed permit applications (if an Interim submittal was not required, the completed permit applications are required 60 days prior to the Final submittal).
1.5.6
This submittal represents a 100% complete design with the exception of the incorporation of any review comments resulting from the review of the submittal. The Final Design shall consists of: (a) Design Analysis with all items l00% complete. It include all backup material previously submitted and revised necessary, all design calculations, all explanatory material design rationale for any design decisions which would not be an engineer reviewing the Final drawings and specifications, complete notations for Construction Manager. shall as giving the obvious to and
(b) 100% complete drawings including those addressing project construction phasing. (c) Specifications. contract front-end. Final edited specifications including the
(d) Bidding schedule and an Explanation of Bid Items. Identify Bid Options where applicable. (See Chapter 3 for examples.) (e) (f) Detailed 100% complete cost estimate. Annotated Interim review comments.
(g) All supporting documentation required for permit application approvals. 1.5.7 Ready-To-Advertise
This submittal represents a 100% complete design including the complete incorporation of all review comments resulting from the review of the Final submittal.
1.5.8
1-9
The contract front-end (boiler plate) will be completed by the District Specification Unit (EN-DW) and forwarded to the AE for inclusion in the Final Design Submittal.
1-10
2.1
2.2 2.3
APPLICABLE PUBLICATIONS 2.2.1 Internet Addresses SUBMITTAL REQUIREMENT 2.3.1 Project Definition, Concept, & Interim Submittal 2.3.2 Final Submittal (Unreviewed 100%) 2.3.3 Ready To Advertise (RTA) (Reviewed 100%) 2.3.4 CAL File Creation and Submittals DOCUMENT REVIEW AND COORDINATION DRAWINGS 2.5.1 2.5.2 2.5.3 2.5.4 2.5.5 2.5.6 2.5.7 2.5.8 2.5.9 2.5.10 CADD Standards and Naming Convention Drawing Package Assemblage Drawing Size, Title Blocks, Borders and CADD Code Drawing Layout Drawing Fonts and Scales Drawing Standard Lines Styles and Widths Location of Project Elements Plans For Information Only Drawings Drawing Amendments and Change Orders Revisions Computer Aided Design Drafting (CADD) Submittals
2.4 2.5
2.6
DESIGN ANALYSIS 2.6.1 Media and Format 2.6.2 Organization 2.6.3 Design Calculations 2.6.4 Automatic Data Processing Systems (ADPS) SPECIFICATIONS COST ESTIMATES BORING LOGS AND TEST DATA
EXHIBITS 2-1 2-2 2-3 2-4 RTA Report Project Title Block Sample Revision Block Section & Detail Cross References
2-1
2-2
an RTA report. See Exhibit 2-1. All drawing title block information must be as complete as possible for each submittal. Each drawing package submitted shall have an Index of Drawings completed to the extent possible. 2.3.2 Final Submittal (unreviewed 100%) This submittal represents a 100% complete design for the purpose of review before the Ready-To-Advertise submittal. A bounded and half size set 11 x 17 black line prints shall be submitted unless otherwise specified in the Scope Of Work (SOW). A submittal report is required of this submittal and should be presented in the same format as an RTA report. See Exhibit 21. See Chapter 3, SPECIFICATIONS for the Specification requirements. 2.3.3 Ready-To-Advertise (RTA) Reviewed (100%) This submittal represents a 100% complete design including all incorporated comments resulting from comments made at the Final unreviewed submittal. Drawings shall include the solicitation number, file number, and advertising date which will be provided by the Project Architect Engineer (PAE). This will be provided with the final review comments. Computer Aided Drafting Design (CADD) files and a half size set of Computer Aided Language (CAL) files shall be delivered at this submittal and as described in the SOW. RTA submittal must be accompanied by a report listing all drawings and specification being delivered (See Exhibit 2-1). The Mobile District requires that a project be submitted in only one type of CADD system. The SOW will note to the designer the submittal requirements of MicroStation or AutoCAD files. Drawings developed using another CADD system or a mix of the two CADD systems is NOT acceptable. See Chapter 3, SPECIFICATIONS, for the Ready-To-Advertise submittal. 2.3.4 CAL File Creation and Submittals See http://www.sam.usace.army.mil/en/guides/cadd/cals/cals.html for CAL files creation and downloads. CAL files shall be half size plots of originals and may need to be rotated 90 degrees. For assistance, Points of Contact are listed on the web page listed above. 2.4 DOCUMENT REVIEW AND COORDINATION The designer shall check and coordinate each submittal for omissions, repetition, and resolve all conflicts. The designer shall prepare the drawings and specifications with the expectation that the construction contractors shall be able to complete construction without any additional assistance or issuance of modifications to correct design deficiencies. Coordination among disciplines, and between drawings and specifications, is essential. The Unified Facility Guide Specifications (UFGS) contain design information shown as notes to the designer. These notes include restrictions and guidelines on the selections of materials and of construction methods, and may include details and information that must be shown on drawings. The designer shall coordinate these notes, drawings and other submittal data with the guide specifications and customer specific criteria.
2-3
2.5 DRAWINGS 2.5.1 CADD Standards and Naming Convention All drawings shall be created using CADD methods in the latest version of MicroStation or AutoCAD as specified in the SOW. All symbology for CADD files shall be in accordance with the latest version of the A/E/C CADD Standards. The Term Symbology means level/layer line weight and style, names, color, fonts. CADD features not addressed in the A/E/C CADD Standards or the Mobile Districts Design Manual shall conform to normal drafting standards. The CADD standard file naming convention shall be as follows: The first four letters are the sheet references number and the last four are the cadd code. An example of Sheet Ref. S-101 for project M004EA06 would be S101EA06.DGN. This shall insure proper tracking of the project files within the Mobile District. 2.5.2 Drawing Package Assemblage Below is an example for a typical design package sequence. Cover Sheet = Prepared by the Mobile District EN-DW General = Index of Drawings, Site Location, Haul Routes, etc. Survey Paving and Grading Steam Distribution Gas Distribution Water and Sanitary Geotechnical and Materials Landscaping Architectural Interior Design Structural Fire Suppression Plumbing Heating Ventilation and Air Conditioning (HVAC) Mechanical Special Equipment Electrical Electrical Systems Hydraulic and Hydrology 2.5.3 Drawing Size, Title Blocks, Borders, and CADD Codes The Mobile District's standard drawing size is 22" x 34". Any deviation from the standard drawing size requires approval of the Chief of Engineering Division. The Mobile Districts PM shall provide the official CADD title blocks and borders to the designers. This official title block will have the title and location of the project. The CADD Codes will be assigned and given to the designers at this time as well. The drawings title assigned by the designer should clearly define the information contained on that sheet (See Exhibit 2-2 and 2-3). 2.5.4 Drawing Layout Drawings shall be prepared so that they present complete information, void of unnecessary wasted space, duplicate notes, and repetitive details. Only details applicable to the project shall be presented on the drawings. All details shall be titled and numbered in accordance with Exhibit 2-4. Details of standard products, which are adequately covered in the specifica-
2-4
tions, should not be included on the drawings. Drawings shall be detailed to the extent that a cost estimate can be accurately prepared and the project can be constructed without additional information. Drawings are required to meet all drafting standards to insure clarity and legibility when reduced to half size. Legends, symbols, and lists of abbreviations shall be placed on the drawings for clarification. 2.5.5 Drawing Fonts and Scales Only standard fonts, described in the Tri-Service Manual A/E/C CADD Standards, Chapter 3, Graphic Concepts, Table 11, are allowed in the creation of CADD files. Preferred text usage shall be font # 1 Working for MicroStation and Romans for AutoCAD. The preferred font width for Romans is 0.85. No fonts created by third parties or the designers are permitted. Monotext Font (AutoCAD) and Font #0 (MicroStation) are not permitted. 2.5.6 Drawing Standard Lines Styles and Widths All CADD file graphic line weights and styles and colors, shall be standardized using the Tri-Service Manual A/E/C CADD Standards, Graphics Concepts Chapter 3, Tables 7, 8, 9 and 10. 2.5.7 Location of Project Elements To facilitate the location of project elements and the coordination of the drawings, all plans with column grids shall indicate a column line or planning grid. All floor plans (except structural) shall show room numbers. 2.5.7.1 Composite and Key Plans When plans of large buildings or structures must be placed on two or more sheets to maintain proper scale, the total plan shall be placed on one sheet at a smaller scale. Appropriate key plans and match lines shall appear on segmented drawings. Key plans shall be used to relate large-scale plans to total floor plans and individual buildings and complexes of buildings. Key plans shall be placed in a convenient location and shall indicate represented plan area by crosshatching 2.5.8 For Information Only Drawings When drawings from previous contracts are deemed necessary for information purposes only, the words "FOR INFORMATION ONLY (FIO)" shall be printed in bold letters in lower right corner of the drawings near above title block or as near thereto as practical. The original title blocks shall not be changed. For filing and sequential purposes, a Mobile District file number for the new project shall be printed in the margin in the lower right corner of the drawings near the title block. The For Information Only drawings shall be contained as an Appendix placed at the end of the drawing assembly. The RTA Report shall include a list of the FIO drawings (See Exhibit 2-2 and 2-3). 2.5.9 Drawing Amendments and Change Orders Revisions The designer may be involved in two types of drawing revisions Amendments during advertisement and Change Orders after a contract is awarded. The Mobile District PM for each project will provide the Amendment or Change Order Number to be placed on the drawings. This number shall be placed in the lower right corner of the drawings. Example: AMENDMENT NO.0001 or CHANGE ORDER NO. FM-001. All designers are responsible for
2-5
preparing amendments and change orders as specified herein. It is essential that all revised drawing files be delivered to EN-DW for management and archiving purposes (See Exhibit 2-3). For In-House projects, each designer shall submit a report to the Project Architect/Engineer (PA/E) listing each drawing that needs to be included in the Amendment or Change Order. For projects designed by an outside Architectural/Engineering (A/E) Firm, the A/E's Project Manager shall submit a report to the Corps PA/E listing each drawing to be included in the Amendment or Change Order. The A/E's report shall be submitted at the same time the Amendment or Change Order drawings are provided to the PAE. 2.5.9.1 Flagging Drawing Revisions All Amendments and Change Order revisions shall be flagged by a teardrop symbol. The designer should use sound judgment concerning the location of the teardrops. The teardrop symbol should be positioned adjacent to the revision with the tip of the teardrop pointing towards the revision. The teardrop symbol shall be sequentially numbered with 1, 2, 3, etc. for each revision. The first time a drawing is revised, the teardrop shall be given a letter "A" within each "teardrop" symbol. The second time a drawing is revised, the letter B shall be used. The third revision to the same drawing would be flagged with "C" "teardrops" etc. The total number of teardrops for each revision and a short description shall be noted within the revision block (See Exhibit 2-3). 2.5.9.2 Deleted Drawings When necessary to remove a drawing from an existing advertised/awarded contract package, the Index of Drawings sheet shall be flagged with a teardrop symbol on the line of that particular drawing. A line shall be drawn through the listing for that drawing with the word "Deleted" inserted at the end of the title. The "Revisions" block of the index sheet should also be flagged and the deletion noted (See Exhibit 2-3). 2.5.9.3 Added Drawings When drawings are added to an existing advertised/awarded contract project, a teardrop shall be placed on the Index of Drawings sheet adjacent to the added drawing. The new drawings shall use the existing numbering convention with the suffix "A," "B," etc., added to the file number. When the new drawing follows the last existing drawing in the package or at the end of a discipline the next sequential file number shall be used without a suffix. 2.5.9.4 Replaced Drawings When drawings supersede originals, the File Numbers and Sheet References shall match exactly the File Numbers and Sheet Reference numbers of the originals, with one exception. A ".1" shall be added to the end of both numbers. A ".2" if replaced a second time, etc. The Index of Drawings shall be revised to reflect this change. The replaced drawings title block shall have the same information as the original drawing and include a teardrop symbol adjacent to the title block. Note: The CADD file name does not change. Example: Original Drawings Replacement Drawings File No. EGL-123-5 EGL-123-5.1 SHEET Ref. No. S-102 S-102.1
2-6
2.5.9.5 Drawing Revisions on CADD The designer the latest drawing matter how often a remain the same as should take special precaution to insure he is revising CADD files whether by amendment or change order. No CADD drawing data is changed the CADD file name shall the original.
2.5.10 Computer Aided Design Drafting (CADD) Submittals All CADD Drawings for each project shall be submitted in ether AutoCAD or MicroStation as specified in the SOW. Cal files shall also be submitted as half size as required for deliverables with CADD files (See item 2.3.4) All CADD files, RTA, Amendments and Change Orders, shall be submitted on one of the following medias: (a) Compact Disc Read Only Memory CD-ROM, Using "Copy" commands. (b) The Mobile Districts FTP (File Transfer Process) site. Contact The Mobile District office EN-DW at 251-690-3442 to transfer submittals via the Districts FTP site.
2-7
RTA REPORT DRAWINGS and SPECIFICATION TITLE OF PROJECT LOCATION, AND STATE M000E308 (= Cadd Code) W91278-04-R-023 (= Solicitation Number) August 2004 (= Advertisement Date)
(Drawings and Specification listed below are examples) CADD NUMBER X001E308.DWG C001E308.DWG C002E308.DWG C003E308.DWG C004E308.DWG C005E308.DWG C006E308.DWG C007E308.DWG FILE NUMBER EGL-247-01 EGL-247-02 EGL-247-03 EGL-247-04 EGL-247-05 EGL-247-06 EGL-247-07 EGL-247-08 SHT REF. X-001 C-001 C-002 C-003 C-004 C-005 C-006 C-007 DATE ON DRAWINGS July July July July July July July July 2004 2004 2004 2004 2004 2004 2004 2004
TITLE OF DRAWINGS Index of Drawings Location and Vicinity Map General Site Plan South Site Removal Plan North Site Removal Plan Overall Site Layout Overall Site Quantity/Distance Arcs South Site Enlarged Site Plan
SPEC NUMBER 01015 01330 01335 01420 02220A 02300A 02543 02709 02748A 02760A 02763A 02770A 02922A 02964A
TITLE OF SPECS General Provisions Submittal Procedures Environmental Protection Sources for Reference Publications Demolition Earthwork Flexible Pavement Florida Limerock Base Course Bituminous Tack and Prime Coats Field Molded Sealants for Sealing Joints in Rigid Pavements Pavement Markings Concrete Headwalls and Curbs and Gutters Sodding Cold Milling of Bituminous Pavements
EXHIBIT 2-1
2-8
3.1
Purpose Automated Specifications Design Build Request For Proposal Scope Quality of Work
3.2 3.3
OUTLINE SPECIFICATIONS TECHNICAL SPECIFICATIONS 3.3.1 Generating Original Specifications 3.3.2 General Ordering Procedures 3.3.3 Tailoring and Coordination of Specifications FINAL DESIGN 3.4.1 Marked-Up Specifications 3.4.2 Read to Advertise (RTA) INSTRUCTIONS FOR PREPARING RTA AUTOMATED SPECIFICATIONS 3.5.1 Standard Format 3.5.2 Automatic Submittal Register DESIGN BUILD REQUEST FOR PROPOSAL DEVELOPMENT AIDS TO ADVERTISING 3.6.1 General 3.6.2 Aids Required with the Final Design Submittal 3.6.3 Aids Required with the Ready to Advertise (RTA) AMENDMENTS AND CHANGE ORDERS 3.7.1 Specifications Revisions 3.7.2 Specifications Revisions on PC
3.4
3.5
3.6 3.7
3.8
EXHIBIT 3-1 3-2 3-3 3-4 3-5 3-6 3-7 3-8 3-9 Outline Specification Resume of Work List of Drawings Bidding Schedule Bidding Schedule (Options Included) Explanation of Bid Items Explanation of Bid Items (Options Included) Table of Contents Submittal Register (SPECSINTACT Automated)
3-1
3.1.1
This chapter provides guidance for the preparation of contract specifications. Designers shall use the Unified Facilities Guide Specifications (UFGS) on all projects unless specifically directed otherwise. Technical questions relating to preparation of contract specifications should be directed to the Mobile District Project Support Section (EN-DW): Fax No. (251)690-2902, Telephone No. (251)694-3624 Mailing address is: U. S. Army, Corps of Engineers, Mobile District CESAM-EN-DW P. O. Box 2288 Mobile, Alabama 36628-0001 3.1.2 Automated Specifications
The Mobile District has adopted the use of SPECSINTACT software as its automated specification system. Designers are required to prepare specifications using this automated system. This software is available on several sites located on the INTERNET. The following Internet addresses contain the necessary software, help manuals, and Unified Facilities Guide Specifications (UFGS): SPECSINTACT SOFTWARE SUPPORT UNIT Home Page http://specsintact/ksc.nasa.gov CONSTRUCTION GUIDE SPECIFICATIONS - HUNTSVILLE http://www.hnd.usace.army.mil/techinfo/index.asp Updates to the UFGS are done on a monthly basis. The Mobile District home page is the only address that contains both UFGS and Mobile District specific Guide Specifications which are required for use. The internet address for Mobile District Engineering Division Home Page is: http://www.sam.usace.army.mil/en/en.htm *NOTE: It is suggested that users review the Users Guide Manual prior to preparing specifications. Should you have any questions concerning the SPECSINTACT process, contact the Mobile District representative at, (251)694-3624 FAX (251)690-2902 at the Mobile District Office or the SPECSINTACT Support Unit at (321)867-8800. Upon accessing the TechInfo website for a list of UFGS (Unified Facilities Guide Specifications), a list containing UFGS guide specifications will be shown. These lists provide a Divisional break down for the guide specifications. In order to retrieve the required guide specifications, click on the Division in which the specification
3-2
is located (i.e., Division 2; Section 02050 - Demolition). Specifications downloaded from the TechInfo site page are in a compressed (zipped) format. In order to manipulate and use these files, you must unzip them prior to opening the file for use. 3.1.3 Design Build Request For Proposal (RFP) For the development of Request For Proposal (RFP) for a DesignBuild Construction Solicitation, Technical Instruction (TI) Manuals TI800-01 and TI 800-03 are available for downloading under the Engineering Publication heading from: http://www.hnd.usace.army.mil/techinfo/ti.htm 3.1.4 Scope
The designer is responsible for the accurate preparation and coordination of the technical specifications. EN-DW will prepare the non-technical portion of the specifications (i.e., boiler plate or front-end) using input provided by the designer. Although EN-DW will prepare the Special Contract Requirements, the designer will be expected to furnish pertinent information that EN-DW might otherwise be unaware of for inclusion in the Special Contract Requirements. Examples of this information are listed in the paragraph 3.7 AIDS TO ADVERTISING. 3.1.5 Quality of Work
Specifications prepared by the designer must be accurate, clear, and precise and should not be subject to interpretation. The specifications will be specific, free of ambiguities, and well coordinated with the drawings. The designer shall be solely responsible for insuring the relevancy and accuracy of cross-references between technical sections of the specifications. 3.2 OUTLINE SPECIFICATIONS
The designer shall submit a list or outline of specifications with the Concept and Interim Design submittals. The outline specification will summarize and describe the various types of construction, list those specifications that have been selected for use, and provide a description of any specifications which must be developed for the project. Exhibit 3-1 provides an example of a typical outline specification. 3.3 TECHNICAL SPECIFICATIONS Generating Original Specifications
3.3.1
Designer developed original specifications may only be used when UFGS specifications are not available. The original specifications must match the UFGS specifications in format and document arrangement. (a) Functional or Descriptive Specifications:
"Functional or descriptive specifications" are normally prepared using industry standards, manufacturer's data, and other available information. These specifications will be developed by listing parameters, methods, techniques, salient features and other requirements that several manufacturers can satisfy. These specifications will list the essential features, requirements, minimum functions, and other
3-3
factors to clearly indicate the type and quality of item(s) required. Specifications should not be developed around a single manufacturer. (b) Sole Source Specifications:
Sole source specifications are to be avoided. If a particular "Brand" or "Manufacturer's" Name is to used for a product, edit section UFGS 09915 Color Schedule to indicate the Brand or Manufacturers Name. The use of trade names and proprietary items and the drafting of a specification by adopting a manufacturer's description of a particular article or procedures shall be avoided. There may be instances, however, when only one manufacturer's product will satisfy job conditions. For example, in rehabilitation work, updating a particular piece of existing mechanical equipment may require new parts from the manufacturer of that particular piece of equipment. In this case, specifying the "Brand" or "Manufacturer's" name would be acceptable provided that "Sole Source Approval" is received from higher authority. To receive approval, the designer shall provide written "Sole Source Justification" to the Mobile District Project Manager. This justification should be prepared and presented as early in the design process as possible since approval usually takes considerable time. (c) "Or Approved Equal" Specifications:
Experience indicates that a "trade name or approved equal" description is appropriate only as a last resort and should be used with great care and discretion. The project file will be documented to explain the necessity for using this approach in each instance it is used. Further, where the "trade name or approved equal" approach is used, the contract provisions will include those salient features of the item or items specified upon which equality will be determined. 3.3.2 Tailoring and Coordination of Specifications
(a) Each specification used in the preparation of project specifications will be tailored to fit the requirements of the project. Where numbers, symbols, words, phrases, clauses, or sentences are enclosed in brackets [ ], a designer's choice or modification must be made. Applicable requirements shall be edited only to the extent allowed by these designer choices. The designer shall exercise care in making the choice or modification. Where blank spaces are provided for insertion of data or text, the designer shall insert the appropriate data or text. Where entire paragraphs are not applicable, they must be deleted. Paragraphs describing systems or materials not used in the construction of the project should also be deleted. When necessary to add requirements, they must be consistent with the other requirements of the specification and must not unnecessarily restrict products that can be furnished. Prior to marking up each specification for the final design submittal, the designer shall review all notes attached at the beginning of the specification. (b) Each specification used in the preparation of project specifications must be coordinated with other specification sections included in the project and with the project drawings. Duplication of requirements in other sections or on the drawings should be avoided. Cross-referencing of requirements will be done only when necessary to avoid misunderstanding. If the specification states "as shown" or similar wording, the requirement must be shown on the drawings. If the drawings reference the specifications, the specification must cover the
3-4
reference. If a specification references another specification, the referenced specification must be included in the project. The designer shall insure that specifications and drawings are properly used; specifications to establish requirements such as quality and workmanship, and drawings to establish requirements such as layouts and dimensions. 3.4 FINAL DESIGN 100% Unreviewed Submittal Specifications
3.4.1
Marked-up specifications for the 100% Unreviewed final submittal will not be accepted. The designer shall submit full edited specifications at the 100% Unreviewed Final Submittal Design review stage in hardcopy. The SOW will identify the recipient of the hardcopies. The Boiler Plate (Front-end contract clauses) will be furnished to the AE for inclusion in the 100% Unreviewed Final Submittal. The boiler plate will be provided by the PM or PAE identified in the SOW. 3.4.2 Ready to Advertise (RTA)
(a) Following the 100% Unreviewed Final Submittal review, review comments will be provided to the designer. The designer shall incorporate the comments into the specifications and prepare the final specification utilizing automated specification techniques (SPECSINTACT). The Ready To Advertise specification shall be furnished in SPECSINTACT (SGML) format. The cover sheet and notes to the specification writer (if applicable) shall be deleted. 3.5 INSTRUCTIONS FOR PREPARING RTA AUTOMATED SPECIFICATIONS Standard Format
3.5.1
The designer shall utilize the SPECSINTACT files downloaded from Internet to prepare the final specifications. The following must be used. (a) Top Margin: Bottom Margin: Left-hand Margin: Right-hand Margin: 1 1 1 1 inch inch inch inch (Large Oversize fonts will
(b) Courier 10 pitch (small elite). not be accepted. (c) (d) (e) (f)
Specifications shall be presented in Letter quality. Left justification turned on. Right justification turned off. Widows and orphans protection turned on.
(g) Page numbering footers set to allow the computer to automatically number the pages consecutively with the section number included when the document is printed. (Example: 03301-1, 03301-2, 03301-3, etc.) The SPECSINTACT program will automatically generate this function.
3-5
(h) Hard returns placed only at the required locations (i.e., at the end of the paragraphs) to allow the text to word-wrap. Hard returns left after each line in tables and forms to prevent word-wrapping and retain the correct text format. (i) Sketches, drawings, or other attachments to be inserted at the end of a specification section shall be scanned into and Adobe .PDF format. (g) Appendices to be placed in the rear of the specification set should also be scanned into an Adobe .PDF format. 3.5.2 Automated Submittal Register
The Submittal Register will be produced using the automated generation procedures found in the SPECSINTACT software commands. Exhibit 3-9 provides an example of a Submittal Register generated using the automated procedures. 3.6 DESIGN BUILD REQUEST FOR PROPOSAL (RFP) DEVELOPMENT
For Design Build Request for Proposal (RFP) packages. All instructions shall be followed unless other requirements are specified in the Statement of Work. Technical Instructions TI-800-01, Design Criteria, and TI-800-03, Design Build Instructions, sets forth general instructions for the RFP development. 3.6.1 Requirements For Table Of Contents This to be used outline is unique and section illustrates the required Table of Contents that is for section 01010 Design Requirements of the RFP. This to be followed unless project specific requirements are require additional topic headings. E X A M P L E REQUIRED TABLE OF CONTENTS FORMAT
Solicitation Number Project CADD Code Section 01010 DESIGN REQUIREMENTS TABLE OF CONTENTS 1. 2. 3. 4. 5. 5. 6. 7. 8. 9. 10. 11. 12. 13. DESCRIPTION OF FACILITY..........................................................2 DESIGN REQUIREMENTS..............................................................2 GENERAL REQUIREMENTS AND DEFINITIONS.............................................2 SITEWORK.........................................................................4 LANDSCAPING......................................................... ...... ..6 ARCHITECTURAL...................................................................15 STRUCTURAL AND COMPREHENSIVE INTERIOR DESIGN REQUIREMENTS.......................24 STRUCTURAL DESIGN...............................................................30 HEATING, VENTILATING AND AIR CONDITIONING.......................................36 PLUMBING........................................................................42 FIRE PROTECTION.................................................................45 MECHANICAL SPECIAL EQUIPMENT....................................................46 ELECTRICAL SYSTEMS..............................................................46 ELECTRONICS.....................................................................51 01010-1
3-6
3.6.2
This section illustrates the required paragraph numbering format to be used when developing section 01010 DESIGN REQUIREMENTS for all design discipline sections. No additional underlining, bolding of fonts or text effects shall be added. E X A M P L E
Design and Construction of Project Name Number Project Location Code 7. 7.1 STRUCTURAL DESIGN General Design Requirements Codes and References IBC 2003 International Building Code 2003 General Building Requirements
7.1.1
7.1.2 The Structural Engineer shall be responsible for the design of the complete structural building system. Structural design shall be in accordance with the criteria, requirements, and guidance provided in IBC 2003 as modified by UFC 1-20001. In addition, the Structural Engineer is responsible for the design of all lesser related structures such as utility vaults, pits, retaining walls, etc., although they may be shown on other disciplines drawings. 7.1.3 7.2 Structural steel and reinforced concrete are acceptable framing systems.
Design Loads Codes and References Minimum Design Loads for Buildings and Other Structures
7.2.1
ASCE 7-02
7.2.2 Design dead, live and wind loads and load combinations shall be in accordance with IBC 2003, unless specified otherwise herein. 7.2.3 Live loads shall be applied in accordance with ASCE 7-02. The following floor areas shall be designed using the stated loads, as a minimum: Offices/Access Floor Areas Conference/Break Rooms 100 psf 100 psf
7.2.4 Wind loads shall be based on a 90 miles/hr Basic Wind Speed, Building Classification Category IV, and Exposure Category C, as described in ASCE 7-02. 7.2.4.1 Wind loads shall be computed and applied in accordance with ASCE 7-02.
7.2.4.2 All parts of all structures shall be designed for the specified wind velocity and shall be tied together to provide an integrated resistance to high wind effects. 01010-9
3-7
3.7
3.7.1
In addition to the drawings and specifications, the designer is required to furnish certain "Aids to Advertising". These aids are discussed below and will be furnished as indicated. 3.7.2 Aids Required with the 100% Unreviewed Final Design Submittal (a) Resume of Work:
The designer shall furnish a "Resume of Work" statement. This will be a brief written description of the work involved and will include a listing of approximate quantities. The project title and location, including the City/Base, State and County will be furnished. The construction cost range will be selected from the ranges listed below and included at the end of the resume. less than $25,000 between $25,000 and $100,000 between $100,000 and $250,000 between $250,000 and $500,000 between $500,000 and $1,000,000 between $1,000,000 and $5,000,000 between $5,000,000 and $10,000,000 over $10,000,000 Exhibit 3-2 is an example of an acceptable "Resume of Work". (b) Estimate of Construction Time:
The designer shall furnish an estimate of the time to construct the project. Consideration will be given to construction contractor procurement of materials and any associated "lead" time, sequence of construction, phasing requirements, anticipated climatic conditions to be encountered during construction, etc. Rationale will be included to back up the designer's estimated construction time. 3.7.3 Aids Required with the Ready to Advertise (RTA) Submittal
All aids required with the RTA submittal must be furnished to the Mobile District on CD-Rom or via the FTP web site. Acceptable formatting is limited to MS Word and Adobe .PDF formats. (a) List of Drawings
An example of a "List of Drawings" is included as Exhibit 3-3. The list of drawings consists of file numbers, the latest date, and the drawing titles. Drawing Titles entered on the List of Drawings must match exactly the titles on the individual drawings. (b) Bidding Schedule
An example of a typical "Bidding Schedule" is shown in Exhibit 3-4. A "Bidding Schedule containing Options is shown in Exhibit 3-5. Bid items will be "lump-sum job" items in preference to "unit price" items. Unit priced items shall be included only with prices approved from the Project Manager. The designer is advised that the bidding schedule
3-8
must be coordinated with the Mobile District Cost Estimating Branch and with EN-DW. Payment paragraphs are no longer required. Bid items identified in the bidding schedule shall be supplemented by the Explanation of Bid Items. Explanation of Bid Items shall be submitted along with the bidding schedule at final and RTA design stages. Examples of "Explanation of Bid Items" are located in Exhibit 3-6 and 3-7, and 3-8. (c) Table of Contents An example
The designer shall prepare and submit a "Table of Contents". is included as Exhibit 3-9. (d) List of Government-Furnished Equipment
The designer shall provide a description, weight, size, quantities, and approximate value, if applicable of Government Furnished Equipment. (e) Information Concerning Salvageable Material, if applicable.
(f) Special Provisions Covering Unusual Situations, i.e., interface problems, outages, security and/or safety requirements, storage area, construction sequences and phasing requirement (if applicable), access to site, early completion dates, etc. Any questions concerning the above-listed submittals should be directed to EN-DW for resolution. 3.8 AMENDMENTS AND CHANGE ORDERS
Following the Ready to Advertise submittal by the designer, the project will be advertised for construction. During the advertisement period as discrepancies, oversights, omissions, and other changes surface, the designer will be required to prepare affected drawings and specifications for amendment. Similar changes may also be required to be performed by the designer during construction in the form of a Change Order. Amendments and Change Orders shall be structured in the format specified below: 3.8.1 Specification Revisions for In-House Projects
When specification revisions are necessary, the designer shall mark-up the existing advertised specification in red pencil to reflect the revisions, and submit the marked-up pages to the PA/E along with a typed report listing the specification sections and section paragraphs to be incorporated in the Amendment or Change Order. The PA/E will consolidate the Amendment or Change Order package and provide it to ENDW for final typing and preparation. If an entire new section is to be added to the project, the designer shall prepare the section in SpecsIntact and submit it for issuance with the amendment or change order. 3.8.2 Specification Revisions for A/E Designed Projects
When specification revisions are necessary on a project designed by an outside Architectural/Engineering (A/E) firm, the A/E shall electronically make revisions to each affected specification paragraph. Each affected specification paragraph shall be inserted into a MS Word document in the order of appearance in the original contract documents. Additions to paragraphs shall be shown in "bold", "underlined", and
3-9
"italicized". (Ex: text). Deletions shall be shown as "struck-thru". (Ex: text). Each specification paragraph inserted in the Word document shall be preceded by a short sentence written to identify the specification section from which the paragraph originates, and to provide brief instructions for the Specification Engineer in EN-DW. If an entire new section is to be added to the project, the A/E shall include an instructional sentence in the location where the new specification will be inserted.
3-10
E X A M P L E OUTLINE SPECIFICATIONS FOR MOTOR REPAIR SHOP FY 95, LINE ITEM 289 FORT RUCKER, ALABAMA SECTION 6 ELECTRICAL
1. The facility will be fed by a 112-1/2 kVA, 3-phase, 12470Y to 208Y/120-volt, pad-mounted transformer. Primary cable (15 kV) will extend underground from an existing pole on X Street to the transformer. The secondary service will extend underground from the transformer to the meter location on the north side of the building. 2. Power and lighting distribution will be from a 208-volt, 3-phase, 4-wire circuit breaker main panelboard located in the Mechanical and Equipment Room. 3. Generally, interior lighting will be of t he fluorescent type utilizing 40-watt rapid-start lamps and low-energy ballasts. Exterior lighting on the building and in the parking area will be, respectively, 150-watt and 400-watt luminaries with high-pressure sodium lamps. 4. Special systems or designs to be provided: Low-voltage switching: Class I, Div. 1, Gr. D hazardous classification for the garage area per the NEC. 5. Automatic fire detection system will provide supervised fire alarms of the noncoded type. A public address system will be provided for the working bays and parking areas. 6. SPEC NUMBER 16370 16375 16415 16721 16760 TITLE Electrical Distribution System, Aerial Electrical Distribution System, Underground Electrical Work, Interior Fire Protection and Alarm Systems Intercommunications System
Exhibit 3-1
3-11
RESUME OF WORK The site of work is located in Okaloosa County, Florida, at Eglin Air Force Base, and includes the following principal features and approximate quantities: (a) Construction of a gymnasium containing approximately 10,000 square feet of floor space, consisting of concrete floor slabs, concrete frame, concrete frame, concrete masonry unit walls, open-web steel joists, steel deck and built-up roofing. Interior work includes plumbing, heating, air conditioning, and electrical work. Gymnasium to be furnished with miscellaneous gymnasium equipment. (b) Gas line - 500 feet of 1-1/2 inch pipe.
(c) Water line - 400 feet of 3-inch pipe; 3-inch gate valve; connection to existing 10-inch line. (d) (e) (f) (g) Sanitary water - 285 feet of 6-inch pipe; 1 manhole. Sprigging - 1.6 acres. Landscaping for the gymnasium building. Exterior electrical work.
(h) Clearing and grubbing, including removal of portable wooden bleachers (16' X 74') - 2.9 acres. (i) (j) Unclassified excavation - 1,500 cubic yards. Unclassified borrow - 500 cubic yards.
(k) 1-1/2 inch flexible pavement, including tack and prime coats and 7-1/2 inch stabilized aggregate base course - 700 square feet. (l) (m) (n) (o) (p) 4-inch concrete sidewalk - 500 square yards. 6-inch asphalt concrete curb - 50 linear feet. Precast concrete bumper curbs - 13 each. 4-inch painted stripes - 150 linear feet. Storm Drainage System 6-inch pipe 8-inch pipe 10-inch pipe 72 linear feet 200 linear feet 58 linear feet
The cost of this work is estimated to be between $1,000,000 and $5,000,000. Construction duration for this project is estimated to be 360 days.
Exhibit 3-2
3-12
FILE NO. HOW-102-1 HOW-102-2 HOW-102-3 HOW-102-4 HOW-102-5 HOW-102-6 HOW-102-7 HOW-102-8 HOW-102-9 HOW-102-10 HOW-102-11
LATEST DATE February 2004 February 2004 February 2004 February 2004 February 2004 February 2004 February 2004 February 2004 February 2004 February 2004 February 2004
TITLE Index of Drawings Location/Vicinity Map Survey Site Plan Dike Details and Elevations Dike Drainage Plan Miscellaneous Details Miscellaneous Details Floor Plan Wall Sections Water Plan
Exhibit 3-3
3-13
W91278-04-R-
Item No.
Description
Estimated Quantity
Unit
Unit Price
Estimated Amount
1.
Renovate Building 6
JOB
XXX
2.
Site Work
JOB
XXX
3.
Asbestos Abatement
JOB
XXX
TOTAL
Exhibit 3-4
3-14
NOTES FOR BIDDING SCHEDULE NOTE NO. 1. To better facilitate the public bid opening process, all modifications to bids are to be submitted on copies of the latest bid schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to bid items, all bidders should state their revised prices for each item. The company name should be indicated on the face of the bidding schedule to preclude being misplaced. NOTE NO. 2. Bidders must insert a price on all numbered items of the Bidding Schedule. Failure to do so will disqualify the bid. NOTE NO. 3. If a modification to a bid is submitted and provides for a lump-sum adjustment to the total estimated cost, the application of the lump-sum adjustment to each unit price and/or lump-sum price, in the bid schedule must be stated or, if it is not stated, the bidder agrees that the lump-sum adjustment shall be applied on a prorated basis to every bid item in the bid schedule. *
3-15
BIDDER'S NAME:____________________________
W91278-04-R-0130
BIDDING SCHEDULE _______________________________________________________________________ Item Estimated Unit Estimated No. 1. 2. 3. 4. Description BASE BID Commons Building. Building A. Building B. Site Work. Quantity 1 1 1 1 Unit JOB JOB JOB JOB Price XXX XXX XXX XXX Amount _________ _________ _________ _________ _________
TOTAL BASE BID OPTION NO. 1 5. 6. Add Two Structural Bays to Building A. Site Work associated with Option No. 1. 1 1 JOB JOB XXX XXX
OPTION NO. 2 7. 8. Add Two Structural Bays to Building B. Site Work associated with Option No. 2. 1 1 JOB JOB XXX XXX _________ _________ _________ _________
TOTAL OPTION NO. 2 TOTAL BASE BID PLUS OPTION Nos. 1 and 2
3-16
EXPLANATION OF BID ITEMS This section comprises an explanation of the bid items GENERAL: identified in the bid schedule. This section is a general scope of work for the bid items described in the bidding schedule and is not intended to be all encompassing in the descriptions. All work specified herein shall be accomplished in accordance with the procedures prescribed in the technical provisions of the specifications and the plans/details as shown on the contract drawings. The Contractor shall bid each type of work under the applicable bid item. Measurement for payment will be made as specified. Payment described for the various bid items will be full compensation for all labor, materials, and equipment required to complete the work. Compensation for any item of work described in the contract but not listed in the bid schedule shall be included in the payment for the item of work to which it is made subsidiary. MOBILIZATION AND DEMOBILIZATION Payment for costs associated with mobilization and demobilization will be made under the contract lump sum price. Also refer to the clause entitled Payment for Mobilization and Demobilization in Section 01000. (a) The Government will pay all costs for the mobilization and demobilization of all of the Contractor's plant and equipment at the contract lump sum price for this item. (1) SIXTY (60%) percent of the lump sum price upon completion of the Contractor's mobilization at the work site. (2) The remaining FORTY (40%) percent upon completion of demobilization. The Contracting Officer may require the Contractor to furnish cost data to justify this portion of the bid if the Contracting Officer believes that the percentages in paragraphs (a)(1) and (2) of this clause do not bear a reasonable relation to the cost of the work in this contract. CLEARING BCDMMS CONTAINMENT Measurement. The unit of measurement for Clearing of the Bayou Casotte Dredge Material Management Site (BCDMMS) Containment will be the acre as measured by survey and computed to the nearest 1/10th of an acre. The measure will not include footprint areas under perimeter dikes, on-site borrow areas, weirs, outfall pipes, and haul roads, which shall be paid under the applicable bid item for DIKE CONSTRUCTION and WEIRS AND OUTFALL PIPES. Payment. Clearing will be paid for once for having successfully removed and disposed of cleared materials. If the Contractor obtains borrow material from on-site in accordance with Bid Item 4, Option No. 1; the area excavated will not be measured again for payment under this item. Payment will constitute full compensation for all labor, hauling, equipment, tools, supplies, and incidentals necessary for performing all work required for the unit price item. WEIRS AND OUTFALL PIPES Work associated with this bid item includes excavating through embankment (paid for under bid items No. 4 Dike Construction, Option No. 1 and/or No. 2 as applicable) to install weirs and outfall pipes to line and grade. Payment for weirs and outfall pipes, including Exhibit 3-6
3-17
foundation preparation, dewatering, excavation, backfilling, materials, labor, tools, fabrication, painting, equipment and operations in connection with constructing and installing weirs with outfall pipes will be made at the contract lump sum price which shall be full compensation for costs associated with this item. Not included for payment under this item is geogrid and filter fabric, which shall be paid for once under Bid Item No. 5 Geogrid (perimeter dikes). DIKE CONSTRUCTION (Option No. 1 On-Site Borrow) Measurement. The unit of measurement for on-site borrow will be the cubic yard, computed by the average-end-area method from Contractor provided cross sections taken of the unexcavated borrow area(s) after clearing, grubbing and stripping have been completed; and cross sections surveyed again by the Contractor after excavation of borrow is completed. The volume to be paid for will be the number of cubic yards of material measured in its original position, removed from the excavation areas, and incorporated into perimeter dike embankment. The volume will not include that excavated without authorization or the volume of any material used for purposes other than dike construction. The volume will not include that used for haul road construction which shall be considered subsidiary to dike construction. The measurement will not include the volume of any excavation performed prior to the taking of elevations and measurements of the undisturbed grade after clearing, grubbing, and stripping. No allowance will be made for the removal of any material outside the limits of excavation lines shown on the drawings. Payment. Payment will constitute full compensation for all work to open, operate, maintain, and close on-site borrow areas; including all survey, labor, clearing, grubbing, stripping, stockpiling, dewatering, excavation, hauling, placing, compacting, shaping, spreading, harrowing, sprinkling, removing objectionable materials, equipment, tools, supplies, and incidentals necessary to complete the work. Payment will also constitute full compensation for and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for the unit price item. Payment will also constitute full compensation for constructing, operating, and maintaining required any required haul roads. Restoration of areas (if any) impacted by haul roads will not be measured for payment and all cost incidental to this restoration shall be included in the contract price for Option No. 2 Off-Site Borrow. DIKE CONSTRUCTION (Option No. 2 Off-Site Borrow) Measurement. The unit of measurement for off-site borrow will be the cubic yard, computed as the number of uniform water-strucktop level truck loads of borrow delivered and accepted. The actual quantity for payment will be based on a measurement of each truck's water-struck volume the first time it comes on site. The volume will not include material that is not incorporated into the permanent work. The volume will not include material brought to the site that is unsatisfactory material (as defined in the specifications) for dike construction. Exhibit 3-6 cont
3-18
Payment. Payment will constitute full compensation for all borrow provided by the Contractor from private off-site sources. Payment will constitute full compensation for all labor, clearing, grubbing, stripping, stockpiling, dewatering, excavation, hauling, placing, compacting, shaping, spreading, harrowing, sprinkling, removing objectionable materials, equipment, tools, supplies, and incidentals necessary to complete the work. Payment will also constitute full compensation for performing any associated Contractor quality control, keeping records, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for the unit price item. Restoration of areas (if any) impacted by haul roads will not be measured for payment and all cost incidental to this restoration shall be considered subsidiary to this bid item. GEOGRID (perimeter dikes) Measurement. Geogrid will be measured for payment by the square yard in place. Measurement will be the nearest square yard. No allowance will be made for material in overlaps. Payment. Payment will be made at the contract unit price for item Geogrid which price and payment shall constitute full compensation for furnishing all plant, labor, material and equipment and performing all operations in connection with placing the geogrid complete. No measurement of nor payment for will be made for overlaps, connections and/or securing pins, and all costs incidental thereto shall be included in the contract unit price for Bid Item 5. Geogrid (perimeter dikes). No measurement of nor payment for will be made for geogrid replaced because of damage due to either fault or negligence of the Contractor. MARSH FILL Measurement. The unit of measurement for marsh fill will be the cubic yard, computed by the average-end-area method from Contractor provided cross sections taken before fill operations begin and before the excavation of any floatation channel by the Contractor, and after the fill is accepted in place. The volume to be paid for will be the number of cubic yards of material measured in place. The volume will not include any material placed outside of the marsh fill area as specified and shown on the drawings. The volume will not include any material placed by the Contractor to backfill optional floatation channel excavation. Payment. Payment will include costs associated with preparing the site for filling in accordance with the plans and specifications, surveys, opening and closing Mitigation Borrow Area C as applicable and specified, the total cost of off-site borrow if required, and shaping to line and grade. Costs incidental to construction, maintenance and restoration of haul roads and/or access corridors, shall be considered subsidiary and not be measured and paid separately. Payment will constitute full compensation for all fill material, labor, excavation, shaping, hauling, equipment, tools, supplies, and incidentals necessary to complete the work, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests and reports, and for performing all work required for the unit price item. Exhibit 3-6 cont
3-19
RIPRAP Work associated with this bid item includes furnishing and placing all materials required for the construction of stone breakwater dikes and/or shoreline revetments in accordance with the plans and specifications. These materials shall include but may not be limited to stone riprap, aggregate bedding material, filter fabric, and geogrid. Measurement. Geogrid, filter fabric, and bedding material used in the construction of stone breakwater dikes and/or shoreline revetments will not be measured separately for payment, but shall be considered subsidiary to Bid Item 7. Riprap. Foundation preparation (including both marine and upland sections) for the placement of riprap dike and/or revetment shall similarly be subsidiary. Measurement of riprap stone shall be in accordance with the following: 1. Riprap stone will be measured by the ton (2,000 pounds) dry in its natural state, as determined by truck scales, railroad scales, or barge displacement. Except as specified below, barge displacement or railroad scales will be allowed only when placement is performed directly from the barge or railroad car to its final location. No payment will be made for riprap stone and/or bedding material placed outside the lines shown on the drawings. 1.1. Truck Weights
When stone is delivered by truck from quarry, barge or railroad siding, it shall be weighted on approved truck scales before being placed in the work. At the Contracting Officer's Representative's option, and if the Contractor can prove to the Contracting Officer's Representative that stone from barge to trucks, or railroad to trucks, goes directly to final placement without any waste, the Contracting Officer's Representative may waive the requirement for truck weights and accept barge or railroad weights. 1.2. Railroad Weights
When stone is delivered by rail, railroad car determination of weights shall be used. The railroad cars shall be weighted before and after loading, or before and after unloading, by a sworn weighter at the quarry or at the destination, upon scales in a manner satisfactory to the Contracting Officer's Representative. Railroad certificates of weight will be acceptable.
3-20
1.3.
Barge
Displacement
When the stone is delivered by barge, the following procedure will be used: Each barge will be accurately measured and shall be fitted with gages graduated in tenths of a foot. The gages shall be located on each corner of the barge near the lower end of the rake, with two additional gages amidships, if deemed necessary by the Contracting Officer. Fore and aft displacement due to load will not differ more than 10 percent from their mean for the determination of tonnage, except in unavoidable cases. In determination of tonnage, the change in gage readings due to unloading of stone will be used, that is, from the load marks to light marks. All gage readings will be made in still water, the density of which has been determined by a pycnometer, hydrometer, or other approved method. All barges shall be pumped dry (within the limits of the pump suction) before each gaging and limber holes shall be kept open so that any water in the barge will flow freely to the pump suction. All equipment, dirt and other material which is on the barge when gaged "loaded" shall remain on the barge until after the barge is gaged "light". From the difference of the "loaded" and "light" gagings the tonnage of the stone shall be determined. The Contractor shall furnish displacement tables of barges to be used, certified as to their accuracy by a person or firm, other than the Contractor, accustomed to performing this type of service and approved by the Contracting Officer or his representative. 2. Determination of Actual Weight Per Solid Cubic Foot of Stone
For stone from sources listed hereinafter, the Contractor shall submit for approval a certificate stating the actual weight per solid cubic foot of the stone he plans to used on the job. If the source of stone is not among those listed hereinafter, the Contractor shall submit for approval certified copies of test data which show the actual weight per solid cubic foot of the stone. 3. Determination of Actual Estimated Quantities of Stone Material
The estimated quantity of stone shown in the bidding schedule is based upon an in-place density of 1.65 tons per cubic yard for riprap using a stone with a unit weight of 165 pounds per solid cubic foot. After the Contractor has submitted the unit weight of the stone to be used in the work, as specified hereinbefore, this unit weight will be applied to the estimated quantity show in the bidding schedule, for the purpose of determining a new quantities. These new quantities will be the quantities subject to the variation as specified in the CONTRACT CLAUSES, Section 00700, paragraph 52.211-18. Payment. Payment for all riprap stone, will be made at the contract unit price per ton for riprap, which price shall constitute full compensation for preparing foundation, furnishing hauling and placing filter fabric, geogrid, and bedding, and hauling, placing, and maintenance of the riprap stone until accepted. Payment shall constitute full compensation performing all operations in connection with placing riprap breakwater dikes and shoreline revetments complete. Payment will not be made for stone or other material lost or placed outside the lines shown on the drawings. EXHIBIT 3-6 cont
3-21
MARSH SPECIES PLANTING Work associated with this bid item includes furnishing marsh plant species, planting, protecting, and monitoring of the marsh plants. Payment for costs associated with marsh species planting will be made under the contract lump sum price. Payment under Bid Item 11, Marsh Species Planting will constitute full compensation for all labor, materials, equipment, reporting, monitoring, replanting as specified and testing required to complete the work. SITE WORK Payment for costs associated with Site Work will be made under the contract lump sum price. Payment under bid item Site Work will constitute full compensation for all other work not otherwise covered in any other bid item. This payment will be full compensation for all labor, materials, and equipment, and performing all operations in connection with and required to complete the work. END OF SECTION Exhibit 3-6 (end)
3-22
EXPLANATION OF BID ITEMS This section comprises an explanation of the bid items GENERAL: identified in the bid schedule for the "AIRFIELD UPGRADE" and "TAXIWAY RAMP". This section is a general scope of work for the bid items described in the bidding schedule and is not intended to be all encompassing in the descriptions. All work specified herein shall be accomplished in accordance with the procedures prescribed in the technical provisions of the specifications and the plans/details as shown on the contract drawings. The contract drawings delineate the limits of the bid items. The Contractor shall bid each type of work as specified below, under the applicable bid item for "AIRFIELD UPGRADE" or for "TAXIWAY RAMP". 1. Payment under the bid items will constitute full compensation for furnishing all materials, equipment, plant, tools, and all labor costs and other associated incidentals necessary to complete the following work: a. b. c. d. e. clearing and grubbing compacted fill material storm drainage system soil cement grassing
Payment will be made under the applicable bid item at the contract lump sum price for "AIRFIELD UPGRADE" or for "TAXIWAY RAMP". Measurement for payment will not be made.
Exhibit 3-7
3-23
GENERAL: This section comprises an explanation of the bid items identified in the bid schedule. This section is a general scope of work for the bid items described in the bidding schedule and is not intended to be all encompassing in the descriptions. All work specified herein shall be accomplished in accordance with the procedures prescribed in the technical provisions of the specifications and the plans/details as shown on the contract drawings. The Contractor shall bid each type of work under the applicable bid item. Measurement for payment will not be made. Payment described for the various bid items will be full compensation for all labor, materials, and equipment required to complete the work. Compensation for any item of work described in the contract but not listed in the bid schedule shall be included in the payment for the item of work to which it is made subsidiary. BASE BID Bid Item 1. Commons Building
This bid item contains all building work as described by the drawings and specifications for the Unaccompanied Officers Quarters as they apply to the Commons Building portion of the project to five feet outside the building. Bid Item 2. Building A
This bid item contains all building work as described by the drawings and specifications for the Unaccompanied Officers Quarters as they apply to the Building A portion of the project, to five feet outside the building, except for that work indicated between column lines C and E. The design of the structural bracing shall be modified by the following; All systems shall be transitioned as required due to the deletion of the two structural bays. Bid Item 3. Building B
This bid item contains all building work as described by the drawings and specifications for the Unaccompanied Officers Quarters as they apply to the Building B portion of the project, to five feet outside the building, except for that work indicated between column lines R and T. The design of the structural bracing shall be modified by the following; All systems shall be transitioned as required due to the deletion of the two structural bays.
Exhibit 3-8
3-24
Bid Item 4. Site Work This bid item contains all site and landscape work as described by the drawings and specifications for Unaccompanied Officers Quarters except that work as describe between column lines C and E between column lines R and T. The site plan shall be modified, leaving the Commons Building in place and moving the ends of the two dormitory buildings toward the Commons Building. The sidewalks will remain at each end and midway of both Dormitory buildings. All utilities will remain the same. The areas at the end of the Dormitory buildings will be graded to the same elevations and sloped away from the buildings, following the same drainage patterns. The landscape plan shall be modified by deleting one Natchez Crepe Myrtle on each side of the sidewalk, which accesses the center of each of the dormitory buildings. The open areas at the end of the dormitory buildings shall be sodded similar to the rest of the disturbed areas. BID OPTION NO. 1 Bid Item No. 5. Option No. 1 This bid item contains all building work as described by the drawings and specifications for the Unaccompanied Officers Quarters as they apply to the Building A portion of the project between column lines C and E to five feet outside the building. Bid Item No. 6. Option No. 1 This bid item includes all site and landscape work as described by the drawings and specifications for the Unaccompanied Officers Quarters between column lines C and E. BID OPTION NO. 2 Bid Item No. 7. - Option No. 2 This bid item contains all building work as described by the drawings and specifications for the Unaccompanied Officers Quarters as they apply to the Building B portion of the project indicated between column lines R and T to five feet outside the building. Bid Item No. 8 Option No. 2 This bid item includes all site and landscape work as described by the drawings and specifications for the Unaccompanied Officers Quarters between column lines R and T. * End of Explanation of Bid Items *
3-25
W91278-04-R-0130 TABLE OF CONTENTS BIDDING REQUIREMENTS Standard Form 1442 - Solicitation, Offer, and Award Bidding Schedule Explanation of Bid Items Standard Form 24 - Bid Bond Standard Form 28 - Affidavit of Individual Surety Standard Form LLL - Disclosure of Lobbying Activities Instruction to Bidders Representations, Certifications and Other Statements of Offerors Construction Contract Clauses Special Contract Requirements
SPECIFICATIONS DIVISION 1 - GENERAL REQUIREMENTS Section 01330 01440 01560 Submittal Procedures Contractor Quality Control SAM Form 696 Environmental Protection
DIVISION 2 - SITE WORK Section 02110 02222 02225 02241 02776 02831 02935 Clearing and Grubbing Excavation, Trenching, and Backfilling for Utilities Systems Earthwork for Roadways, Railroads, and Airfields Stabilized Aggregate Surface Course Lining System Chain Link Fence Turf
Exhibit 3-9
3-26
W91278-04-R-0130 TABLE OF CONTENTS (CONT.) DIVISION 7 - MOISTURE PROTECTION Section 07418 Architectural Standing Seam Roof System
DIVISION 16 - ELECTRICAL Section 16370 16375 16415 16642 Sacrificial Electrical Electrical Electrical Cathodic Distribution System, Aerial Distribution System, Underground Work, Interior Protection System (Impressed Anodes)
Current
and
3-27
4.1
GENERAL 4.1.1 Scope 4.1.2 Quality of Design APPLICABLE PUBLICATIONS PROJECT DEFINITION (10-15%) CONCEPT REQUIREMENTS DESIGN (30-35%) 4.4.1 Concept Design Analysis 4.4.2 Concept Drawings 4.4.3 Specifications INTERIM DESIGN (50-60%) 4.5.1 Preliminary Design Analysis 4.5.2 Interim Drawings 4.5.3 Specifications FINAL 4.6.1 4.6.2 4.6.3 DESIGN (UNREVIEWED 100%) Final Design Analysis Final Drawings Final Specifications
4.5
4.6
4.7
READY-TO-ADVERTISE SUBMITTAL REQUIREMENTS (l00%) 4.7.1 RTA Design Analysis 4.7.2 RTA Design Drawings RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS 4.8.1 Mandatory Requirements 4.8.2 Specific Requirements
4.8
4.9
GENERAL INSTRUCTIONS RELATIVE TO DESIGN OF STORM DRAINAGE SYSTEM FOR OTHER THAN AIRFIELDS 4.9.1 References 4.9.2 General 4.9.3 Notes To Designer 4.9.4 Drainage Design Criteria 4.9.5 Procedure for Design of Storm Drainage Systems For Other Than Airfields
EXHIBITS 4-1 4-2 4-3 4-4 4-5 4-6 4-7 4-8 Tables Figure Figure Figure Figure Figure Figure Plan A, B, and C I II and Figure III IV and V VI and VII VIII and IX X and XI Design Example
4-1
Profile - Design Example Table - Hydraulic Design For Culverts Table A - Blank Form Table B - Blank Form Table C - Blank Form Storm Drain Pipe and Structure Schedule
4-2
This chapter states criteria, requirements, and guidance for civil design. The design shall be accomplished in accordance with appropriate manuals and pamphlets and with basic criteria furnished in Statement of Work. 4.1.2 Quality of Design
It is the purpose of the COE to obtain excellent siting and civil design resulting in efficient and economical paving, grading, and drainage conditions. 4.2 APPLICABLE PUBLICATIONS TI 800-01 TI-800-03 TM 5-820-4/ AFM 88-5, Ch 4 AFI 32-1042 ETL 94-01 TM 820-3/ AFM 88-5, Ch 3 EM 1110-2-410 and TM 5-803-5 TM 5-822-2/ Roads, AFM 88-7, Ch 5 EIRS 81-05 TM 5-822-5/ Open AFB 88-7, Ch 1 TM 5-822-7 TM 5-822-8 Design Criteria Design Build Instructions Drainage for areas other than Airfields Standards for Marking Airfields Standard Airfield Pavement Marking Schemes Drainage and Erosion-Control Structures for Airfields and Heliports Design of Recreation Areas and Facilities, Access Circulation Installation Design General Provisions and Geometric Design for Streets, Walks and Open Storage Areas Dimensions for Typical POV Parking Areas Pavement Design For Roads Streets, Walks, and Storage Areas. Standard Practice for Concrete Pavements Bituminous Pavements - Standard Practice
4-3
Airfield and Heliport Planning and Design Pavement Design for Airfields
General Considerations The Designer shall develop a conceptual site plan, which encapsulates the project requirements. The plan should be an efficient layout with emphasis given to user requirements. The plan shall show building locations, parking areas, roads, limits of paving and hardstands, and pedestrian access points. The plan shall be developed so that a preliminary cost estimate can be prepared. 4.4. CONCEPT DESIGN REQUIREMENTS (30-35%) Concept Design Analysis
4.4.1.
a. General overview of major site features planned, such as building orientation, drainage patterns, parking provisions, traffic circulation, provisions for the handicapped, security requirements, airfield pavement work, etc. b. Provide a description of any locations of wetlands, as defined by Federal and/or State criteria, historically significant areas, or areas with endangered species of wildlife within the project site area. All areas shall be defined by qualified professionals and flagged in the field. The topographic survey shall label and present the defined areas. Geometric coordinates shall be clearly shown on the design drawings for all environmental areas, such as an IRP site or wetland boundary. c. Provide applicable State/local flood requirements.
d. Discuss existing site features including general topography, acreage, boundaries, adjacent site usage, etc. e. 4.4.1.2. Discuss impacts of new construction on existing facilities. Removals
a. Preliminary discussion of items requiring removal or relocation. b. materials 4.4.1.3. a. Method and location of the disposition of waste or salvage Geometry Provide rationale for locating major site elements.
b. Airfields: Provide list of specific clearances based on airfield criteria and list reference manual(s) for all portions of the new work.
4-4
c. Work Other Than Airfields. Provide set back requirements or specific clearance requirements for major features of work, such as buildings, parking areas from streets, hardstands, etc. 4.4.1.4. Storm Drainage
a. Provide a summary of specific Federal, State and/or local stormwater permit requirements for water quality/quantity for the project including fees for permit applications and the name of the agency to whom the permit application check will be written. Discuss the impacts on the site design. If no stormwater permits or requirements are required, provide a statement to that effect. Provide documentation from the appropriate regulatory agency and regulators name. b. Discuss the preliminary stormwater design scheme and discuss impacts on the existing stormdrain systems. c. Provide selected design values to be used in the storm drainage calculations such as surface runoff coefficient, retardance coefficients, infiltration rate, and rainfall intensity based on a 10year and the 100-year storm frequency. d. Provide preliminary sizes of stormdrain pipes.
e. Provide preliminary size and preliminary calculations for required stormwater treatment/storage ponds. Discuss impacts on the project site. f. Provide preliminary Pre and Post construction discharge values for the 10-year & 100-year storm event. g. 4.4.1.5. Discuss the proposed stormdrain pipe materials. Grading
a. Discuss existing site features affecting grading such as buildings, streets, curbs, walks, fences, water courses, ponds, elevation of high ground water, rock outcrop, etc. b. Provide minimum elevation to provide flood protection (if applicable). c. d. Planned finished floor elevation. Cut or fill requirements and rough estimate of quantities.
e. Discuss minimum and maximum slopes to be used in the design for embankments, ditches, pipes, etc. 4.4.1.6. a. Pavement Structure Design Vehicular Pavements Thickness Design.
(1) Specific design values for which pavement thickness is based including the number, type, and maximum weights of vehicles, category of traffic, class road or street, and resulting design index.
4-5
(2) Flexible Pavements - required thickness of base and pavement (7-1/2 inch (19cm) minimum) based on the design index and established subgrade CBR. (3) Rigid Pavements - required thickness of nonreinforced concrete pavement (6-inch (15cm) minimum) based on a 28-day flexural strength concrete of 650 psi and the established modulus of subgrade reaction. b. Aircraft Pavement Thickness Design. The Site Develop Unit of the Mobile District Corps of Engineers shall prepare all airfield pavement structures and materials specification. (This information shall be provided to the A-E if the project is being designed under contract.) (1) Flexible Pavements - specific design values for which pavement thickness is based including the airfield class, type traffic area, gross weight of aircraft, number of passes, subgrade CBR, and resulting minimum thickness of base and pavement. (2) Rigid Pavements - specific design values for which the pavement thickness is based including the type of aircraft gear, gear design load, modulus of subgrade reaction or resultant modulus of both subgrade and base course, flexural strength of concrete, and resulting pavement thickness. (3) For project requiring airfield pavement, the designer shall coordinate with Geotechnical Branch, Geotechnical and Dam Safety Section (EN-GG), for required material investigations and specification requirements. Notification of the proposed pavements should be given EN-GG as soon as possible to allow time for any needed sampling. c. Discuss the proposed base course type and select subgrades. Provide intended compaction requirements. 4.4.1.7. a. Road and Streets, and Parking Areas Provide listing of traffic volumes and vehicle types.
b. Provide AASHTO design vehicle for which turning movements are to be provided for and corresponding minimum turning radius. c. d. e. f. g. h. Provide project design speed. Provide maximum degree of curvature and control grades. Provide sight and stopping distance requirements. Provide lane and shoulder widths. Provide cross-slopes for lanes and shoulders. Embankment slopes.
i. Requirements for curbs, sidewalks, guardrails, traffic signs and markings, fencing, etc. j. Rights-of-way and easements
4-6
Parking and Open Storage Areas Type vehicles to be accommodated Size of individual parking spaces and number to be provided Number and location of handicapped parking spaces General location of parking or storage areas Location of ingress and egress Pedestrian access Use of 90o, 60o, or 45o parking and relation to traffic Miscellaneous Site Features Curbs, and curbs and gutters - types and locations Sidewalks - width, and locations Fencing - justification, type, size and location of gates Railroads Type of service for which track shall be provided. Anticipated volume Maximum grade and degree of curvature
d. Features of track construction such as thickness and type of ballast, weight of rail, dimension of ties, size of turnouts, etc. e. Special requirements for track scales, bumpers, signals, grade crossings, derailers, etc. 4.4.1.11. NPDES Construction Permit
Provide specific requirements for State and Federal NPDES Construction Permit for the project. 4.4.1.12. Erosion and Sediment Control Plan
Describe intended design of sediment and erosion control for the project. 4.4.1.13. Outline Specifications
List all Army Corps of Engineers Unified Facilities Guide Specifications that the designer prepares to use for the project. 4.4.1.14. Additional Information
4-7
4.4.2.
a. Indicate project site. Provide preliminary borrow and spoil areas, haul routes, and contractors access to the site. b. c. Provide State vicinity map. Provide Location map for local access to project site.
4.4.2.2. Geometric Layout Plan a. Provide an overall site plan showing total development.
b. Show the proposed geometry of the site plan using a minimum scale of l" = 30'(1:500), unless otherwise directed. Include the existing topography without contours that shall remain after construction. c. Use graphic symbols to distinguish new and existing site work, and provide legend to define graphic symbols. d. Provide sufficient geometric information to adequately locate all new major site elements. e. Identify the grid state system used. Include a north arrow.
f. Provide centerline stationing for all roads, streets, parking areas, runways, taxiways, etc. 4.4.2.3. Grading and Drainage Plan
a. Show the complete drainage concept using either finished contours or slope arrows include preliminary storm drainpipe sizes. b. directed. c. plan. d. Show the proposed finished floor elevation and critical spot elevations. e. for each. Provide control monuments, list horizontal and vertical data Use a minimum scale of l" = 30' (1:500), unless otherwise Show and identify all existing buildings and facilities on
f. Reflect existing utilities with the topography. If necessary for clarity, show removals, relocations, and new work for utilities on separate plans. g. All contour intervals shall be 1 foot (25cm), unless otherwise directed.
4-8
4.4.2.4. a.
Removal Plan Indicate items to be removed. Indicate pavement layer thickness for
a. Airfields: Provide preliminary profile for runway and/or taxiway centerlines. Provide edge of pavement profiles if applicable for milling and overlay projects. Show existing ground line and preliminary new finish grade with percent new grades indicated. b. Roads, Streets, & Parking Areas: Provide preliminary profile for centerlines. Show existing ground line and preliminary new finish grade with percent new grades indicated. 4.4.2.6 Typical Section for Airfields, Roadways & Parking Areas
a. Roadways: Provide preliminary typical sections for each different roadway width. Indicate lane widths, shoulder widths, and cross-slopes. b. Parking Areas: various parking areas. Provide preliminary typical section for
c. Airfields: Provide preliminary typical sections for runways, taxiways, and aprons. 4.4.3 Specifications
Provide a basic outline in accordance with Chapter 3, SPECIFICATIONS. 4.5. INTERIM DESIGN (50-60%) Comply with comments from the
Advance from concepts into design. concept review. 4.5.1. Preliminary Design Analysis
Update and expand the Concept Design Analysis to support the submittal and include the following, as applicable: 4.5.1.1. Storm Drainage Design
a. Complete storm drainage design-calculations consistent with the requirements of the applicable TMs and based on the design values established in the Concept Design Analysis. b. Provide a map outlining drainage areas affecting new construction. c. Use the General Instructions Relative for the Design of Storm Drainage Systems for Other Than Airfields based on TM 5-820-4 (See paragraph 4.9 below). d. Provide complete calculations for sizing retention and/or detention ponds. Provide calculations verifying compliance with all
4-9
State regulations. Coordinate calculations with applicable State Regulatory Agencies. Provide documentation of coordination meetings. e. Provide watertight joints for drainage pipe under all pavements (aircraft and vehicular) when the pipe is placed in a noncohesive soil (see TM 5-820-4, paragraph 2-06j). Provide soil tight joints at all other locations. g. directed. 4.5.1.2. Contour intervals should be 1 foot (25cm), unless otherwise Pavement Design
a. Complete flexible and rigid pavement design calculations consistent with the requirements of the applicable TM's and based on the various design values in the Concept Design Analysis. b. allowed. c. thickness. d. 4.5.1.3. Present complete calculations for pavement options to be Provide materials to be used in pavement structure and their Provide the minimum compaction requirements. Additional Information
List additional information or criteria needed for final design. 4.5.2. Interim Drawings
Although it is intended that major items of work be shown separately, different items may be shown on the same sheet provided that the presentation is sufficiently clear to permit legible reproduction at half-scale. 4.5.2.1. Location and Vicinity Maps
a. Indicate all items of site work, which shall require removal or relocation. b. Provide dimensioning for removal items such as pavements, curbs, sidewalks, etc. 4.5.2.3. Geometric Layout Plan
a. Complete the geometric layout of all items of new work using offset dimensions from existing structures or, use coordinates for locating new work. b. c. Include in the plan information on specific items of work. Provide locations of soil boring locations and designations.
d. Complete the legend to include all items and symbols shown on the plans. Symbols should be consistent between successive drawings.
4-10
e. Show on the plan the construction centerline, right-of-way limits, and all-important topographical features such as fences, buildings, streams, railroads, etc. f. Locate or make reference to monuments and benchmarks for horizontal and vertical control. g. Provide complete survey information necessary for establishment of the survey centerline, new structures, building column lines, runway centerlines, etc, including coordinates or computed bearings, radii, curve data, superelevation requirements, point of intersection of centerlines, etc. h. When superelevation is required, include in the plan a diagrammatic profile of how the superelevation is obtained and also tables of shoulder slopes versus cross slopes for the superelevated section. i. Note on the plans the size and type of all existing structures and the manner in which they are to be utilized, removed, or otherwise affected by new work. j. If widening of the pavement is required in curves provide sufficient details to facilitate the construction. 4.5.2.4. Grading and Drainage Plan
a. Indicate all items of work superimposed on the existing topography. b. Indicate the proposed contours for new grading and provide spot elevations as required to facilitate field layout. All contour intervals should be 1 foot (25cm), unless otherwise directed. c. Layout the new storm drainage system using the symbols covered in the legend. d. Identify drainage structures with number designations corresponding to those used in the storm drainage schedule to be included in the drawings. e. Indicate the finished floor elevations of new buildings.
f. Locate or make reference to monuments and benchmarks for horizontal and vertical control. 4.5.2.5. Storm drain profiles
a. Provide profiles for all storm drains and roadway culverts. Indicate invert elevations of all drainage structures, storm drainpipe with size and invert elevations, ground profile, and new or existing structures or utilities crossing the new storm drain. 4.5.2.6. Profile Sheets for Airfields, Roads, and Parking Areas
a. Provide the centerline profile. Unless otherwise directed, use a vertical scale of 1 = 5 (1:50) or as appropriate to terrain. Indicate and label beginning and ending tie points.
4-11
b. c. d. profile.
Provide elevations at points where changes of grade occur. Indicate the lengths of vertical curves. Indicate the existing ground line at centerline on the
e. Indicate the percentage of slope for all grade lines. Provide special information pertaining to the profile and affecting the design such as curb grades, gutter grades, drainage structure inverts and top elevations, etc. f. Station. g. 4.5.2.7. Provide centerline grade elevations at each 50-foot (15M) Show new and existing drainage structures on the profile. Miscellaneous Details
Plans shall include the following, a. b. clarity. c. d. e. f. 4.5.2.8. Minimum paving and compaction requirements. Typical sections through the building site as required for Legend. Storm drainage pipe and structure schedule. Parking layout. Superelevation and widening details. Concrete Joint Plans
a. Concrete Joint Layout Plans: Provide a joint layout plan for each concrete apron, hardstands, road, pavement, etc. Joint plan shall clearly indicate the required joint type for all joints as well as slabs which require reinforcement. The scale of layout plans shall be 1=20 (1:200m) unless otherwise approved. b. Concrete Joint Grading Plans: Provide a joint grading plan for all concrete pavements, aprons, hardstands, roads, etc. Grade for each joint intersection shall be provided on the plan at the specific joint. Only joints with grades, which can be linearly interpolated, may be omitted. Sufficient grades must be provided to facilitate calculation of all joints in the plan. c. Concrete joint details: Provide details of all joint types as applicable to the project. Provide detail of joint sealant. d. Sidewalk joint layout: Provide details of sidewalk joints for entrances at buildings, handicap ramps, and circular drives, etc, as applicable. 4.5.2.9. Erosion and Sediment Control Plan (BMP Plan)
a. For all projects with land disturbance provide a sediment and erosion control plan. Plan shall design the necessary best
4-12
management practices required to control sedimentation and erosion throughout the life of the construction project. b. Provide calculations in the design analysis for sizing sedimentation basins, ditches, ditch liners, etc. c. Provide details as required for all erosion and sediment control devises. d. Provide erosion and sediment control phasing notes.
e. Provide a Storm Water Pollution Prevention Plan. Plans shall be in accordance with the current EPA requirements and state/local requirements. The plan shall be coordinated with the Sediment and Erosion Control Plan. 4.5.3 Specifications
The outline specifications previously submitted for concept phase shall be revised, updated, further developed and resubmitted in accordance with Chapter 3, titled SPECIFICATIONS. 4.6. FINAL DESIGN (UNREVIEWED 100%)
Advance design to completion complying with comments from the previous reviews. 4.6.1. Final Design Analysis
Update previously prepared analysis to support final plans and specifications. Any required permit application packages shall be included as an appendix in the Final Design Analysis. 4.6.1.1. NPDES Construction Permit Application
a. Provide a completed application for the District Engineers signature, for applicable projects requiring State and Federal NPDES Permitting. The PM shall provide the name, title, address, etc. for officials signing permit applications. b. Provide Best Management Plan certification for State projects requiring certification of the Best Management Plans. 4.6.2. Final Drawings Add general notes to drawings as required.
a.
b. Insure correct cross-referencing among site drawings for appropriate details, sections, match lines, etc. c. Eliminate all conflicts (horizontal and vertical) among site plans and architectural, structural, and utilities plans. 4.6.3. Final Specifications
a. Complete draft of specifications to cover all items of site work. Any required permit applications, permit approval letters, and/or any requirements that apply to project construction shall be included as an appendix in the specifications.
4-13
b. Insure consistency of terminology between plans and specifications for notations on specific items of work. c. Perform check to insure adequate referencing for construction details. 4.7. READY-TO-ADVERTISE SUBMITTAL REQUIREMENTS (l00%) Final Design Analysis
4.7.1.
Complete analysis supporting the requirements of the project. 4.7.2. Final Design Drawings and Specifications
Complete thoroughly checked drawings and specifications, with all comments from the final review incorporated. Any required permit applications, permit approval letters, and/or any requirements that apply to project construction shall be included as an appendix in the specifications. 4.8 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS
TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs. 4.8.1 Mandatory Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development: a. Storm Drainage System. EPA National Pollution Discharge Elimination System (NPDES) permits for construction activities may be required. The Design-Build contractor should be made aware of this in the RFP. The Design-Build contractors design will determine the need for the permit. If the permit is required, the D-B contractor will prepare the documentation for the Storm Water Pollution Prevention Plan (SWPPP) and monitoring plan. This documentation will be submitted to the Contracting Officers Representative (COR). The COR will submit the documentation for permit application. b. 4.8.2 See TI 800-03 for additional mandatory requirements.
Specific Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria:
(1) Include special site design requirements and a preconcept plot plan (if available). b. Partial Project Criteria:
4-14
(1) Include special site design requirements and a preconcept plot plan (if available). c. Full Project Criteria: (1) Preliminary Site Plan (includes grading, stormwater management, utility services, paving, curbing, walks.) (2) Preliminary Landscaping Plan or allowance amount. Pavement Design Analysis. (3) Edited Specifications (includes preliminary specifications on all sitework items including paving sections, earthwork, utilities.) NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements.
4.9. GENERAL INSTRUCTIONS RELATIVE TO DESIGN OF STORM DRAINAGE SYSTEMS FOR OTHER THAN AIRFIELDS 4.9.1. References TM 5-820-4, Drainage for Areas Other Than Airfields. Design compilation sheets (4 total).
a. b.
c. Sample "Storm Drainage Pipe and Structure Schedule" (To be included on the Plans as appropriate). 4.9.2. General
For the design of other than airfield storm drainage systems, the procedure that follows and, as appropriate, TM 5-820-4 shall be utilized. Design compilation sheets, reference l.c., shall be used during the design and included as a part of the design analysis. The design analysis shall also include an overall drainage map depicting individual drainage areas, assumed paths, and slopes of runoff used to compute times of concentration, and the types of surface within the individual areas. For projects located in the states that require storm water permits, the designer shall perform the drainage design in accordance with the state's criteria. The designer shall maintain a complete record of the criteria and calculations. 4.9.3. Notes To Designer
a. The "Procedure for Design of Storm Drainage Systems for Other Than Airfields" was developed to consolidate and clarify design criteria and procedures presented in TM 5-820-1 and TM 5-820-4, to facilitate designs of other than airfield drainage systems, and to achieve design consistency. b. This design procedure in no way relieves designers of their responsibility to comply with the provisions and requirements of TM 5820-4.
4-15
c. The storm runoff design procedure presented in Steps l through l2 in 4.9.5 applies to both the closed storm drainage system and individual culverts. The pipe sizing procedure presented in Steps l3 through l9 applies to closed storm drainage systems only. Individual culverts shall be sized using procedures contained in TM 5-820-4. 4.9.4. Drainage Design Criteria
a. The criteria and procedures are for areas up to one square mile, where only peak discharges are required for design, and ponding is not permitted. b. The design storm shall be based on l0-year storm frequency with no ponding. The designer will check the 100-year event through the proposed system to insure no flooding or damage occurs. c. Minimum times of concentration, tc, of l0 minutes for paved areas and 20 minutes for grassed areas shall be used. d. Manholes or junction boxes shall be provided at points of change in conduit grade or size, at junctions with laterals or branches, and wherever entry for maintenance is required. Distance between points of entry shall be not more than about 300 feet for conduits with diameter smaller than 30 inches. Conduit alignment between entry points shall be straight, except for 30 inches and larger sizes. e. Pipe discharge velocities must not be less than 2.5 fps to provide for adequate pipe cleansing. f. Minimum pipe sizes shall be l2 inches for closed drainage systems and l8 inches for individual culverts, unless unusual or special design considerations warrant using smaller pipe. g. Storm drainage systems shall be constructed in accordance with specifications Section CE 02720. The specifications contain instructions and information that must be considered during design. h. Metal pipes will receive paved inverts when pipe velocities exceed 6 fps. i. coating. j. coating. k. Plain Galvanized Steel pipes shall receive bituminous Aluminized Steel, Type 2, will not require bituminous Plastic pipes shall be HDPE Double wall.
4.9.5. Procedure For Design Of Storm Drainage Systems For Other Airfields Step 1 - Columns l through l4 of Table "A" of Exh. 4-1 shows data necessary for drain inlet design. The drainage area for each inlet is calculated with respect to the paved, bare soil and turfed surface conditions within the area. These areas are entered in Columns 2, 3, and 4. The total drainage area for each inlet is then entered in Column 5. Surface runoff coefficients "C" are assigned from Figure II of Exh. 4-3 based on the predominant paved, bare soil, and turfed surface conditions encountered in the overall drainage area and are entered at
4-16
the top of Columns 2, 3, and 4. Only under unusual circumstances shall bare surface areas be considered in the drainage calculations. The weighted coefficient "C" for inlet number 1 is calculated as follows:
A
Step 2 - The actual length of runoff "L" for each inlet or design is scaled from contour maps, etc., with respect to the paved, bare soil and turfed surface conditions encountered. The sum of the individual lengths involved is entered in Column 7. Considerations must be given to the type of flow (sheet, channelized, ditch, swale, etc.), slopes, (along the flow path), and surface retardence coefficients when selecting the runoff length. Sheet flow is assumed to become channelized flow on unpaved surfaces after a sheet flow distance of 200 feet. The selected length of runoff should represent a realistic path of flow measured perpendicular to contours and one that shall provide the maximum runoff flow time (time of concentration). The actual runoff length "L" for inlet 1 drainage area was determined to be 260 feet. The first 200 feet occurred with sheet flow on an average grass surface sloping at 0.70%. The next 35' occurred with channelized flow on an average grass surface sloping at 0.70%. The assumed surface retardence "n" was 0.40 for sheet flow and 0.20 for channelized flow. The remaining 25 feet of runoff occurred an asphalt paved surface sloping at 0.50% and having a retardence "n" of 0.02. Retardence "n" is the term used to designate the resistances to sheet, channelized, and ditch flow caused by various surface conditions such as vegetation, surface and alignment in the path of flow. Retardence coefficients are assigned from Figure III of Exh. 4-3. The average retardence "n" for inlet number 1 is calculated as follows:
L Surface 1 (nSurface 1)+LSurface 2 (nSurface 2) = 200 (0.4)+35(0.20)+25 L Total 260
Enter in Column 8. The average slope "S" for inlet number l is calculated as follows:
L
Surface l (SSurface l) + LSurface 2 (SSurface 2) = 235 (0.7) + 25 (0.5) = L Total 260 Enter in Column 9. Equivalent length "LE" is now calculated using Formula I: LE = 2.5 Ln/ s Where LE = equivalent length in feet for n = 0.4 and 5 = l% L = actual measured distance of flow path in feet n = average retardence coefficient S = average slope in percent of flow path For inlet number l, LE is calculated as follows: LE = 2.5 (260) (0.34) = 268' 0.68 Enter in Column l0
Step 3 - The time required for surface runoff to reach an inlet or design point when traveling along the previously determined flow path is the time of concentration "tc. The time of concentration for each
4-17
inlet or design point is obtained from Figure V of Exh. 4-4 using equivalent lengths of runoff "LE" from Column 10. The time concentration for inlet number 1 was determined from Figure V to be 22.1 minutes using the equivalent length of runoff "LE" value of 268 feet. The 22.1 figure is rounded to 22 minutes and entered in Column 11. Step 4 - Select a design storm index from Figure I of Exh. 4-2, based upon the location of the project, and enter at the top of Table A of Exh. 4-1. For this example, the project is located in Columbus, Mississippi, which yields a design storm index of 2.6 in./hr. Step 5 - Using Figure VI of Exh. 4-5 for inlet number 1, enter the chart from the left using tc" = 22 min. from Column 11 and read rainfall intensity under design storm index 2.6 as 4.60 in./hr. Enter in Column 12. Step 6 - Infiltration "F" is the term used to refer to the absorption of rainfall by the ground during a design storm following a rainfall of one hour. Infiltration rates are assigned from Figure IV of Exh. 4-5 according to the predominant type of soil and ground cover encountered in the overall drainage area, and are shown at the tops of Columns 2, 3, 8, and 4. The weighted infiltration "F" for inlet number 1 is calculated as follows: 0.06 (0.0) + 1.83 (0.5) = 0.48, enter in Column 13. 1.89 Step 7 where, Q C A i F = = = = = The Rational Method for computing runoff is Q = CA(i-F)
runoff in cubic feet/sec surface runoff coefficient area (acres) intensity (in./hr.) infiltration rate (in./hr.)
The runoff for inlet number l is calculated as follows: Q = 0.42 (l.89) (4.60 - 0.48) = 3.3 cfs. Enter 3.3 cfs in Column l4. It is essential at this point to check the capacity of inlet No. l. All inlets, etc., must be sized to accommodate the design storm runoff without ponding. Step 8 - Columns 15 through 28 of Table "B" Exh. 4-1 show data necessary to calculate rate of inflow into drains. Enter in Column 17 distance between inlets. Enter in Column 18 the areas calculated and shown in Column 5 of Table "A. Accumulate areas as each contributes to the entire system and enter in Column 19. The weighted runoff coefficient "C" for drain 2-3 is calculated as follows: 1.89 (0.42) + 1.72 (0.57) = 4.49 3.61 Enter in Column 20. The weighted runoff coefficient for drain 5-6 is calculated as follows:
4-18
5.33 (0.46) + 2.07 (0.40) + 1.21 (0.60) = 0.47 8.61 Enter in Column 20. Step 9 - As runoff accumulates and increases in its passage through the system, the increase in runoff is not the summation of the peak runoff of each individual area, but is an increase modified by various factors. The major factor is the decreasing intensity of the storm effect on the lower areas due to the increasing time of concentration. To attain the maximum rate of runoff at a given point, the storm must continue long enough to produce the maximum rate of inflow into each upstream drain inlet and to permit the inflow to travel through the drain from the "critical inlet" to the given point. The "critical inlet" is the inlet whose drainage area requires the longest time of concentration within the pipe system being considered. The "critical inlet" and its time of concentration "tc" are determined from Column 11 of Table "A" and entered respectively in Columns 21. and 22. Pipe flow time from the "critical inlet" to the given point is referred to as "drain time" "td. Drain time is computed using an assumed average pipe velocity of 6 f.p.s. and entered in Column 23 for individual pipe runs. The drain time, "td, from the "critical inlet" to the given point is accumulated in Column 24. The critical time of concentration, "tc, for the individual pipe run design, is calculated by adding "tc" for the critical inlet from Column 22 to the accumulated drain time "td" from Column 24. The sum of the two, rounded to the nearest minute, is entered in Column 25. Step 10 - With the time of concentration calculated in Column 25, storm intensity "i" for the drains can be derived as in Step 5, above, and entered in Column 26. Step 11 - The weighted infiltration rate "F" for drain 2-3 is calculated as follows: 1.89 (0.48) + 1.72 (0.33) = 0.41 Enter in Column 27. Step 12 - The rate of inflow into the drains is calculated as in Step 7 above and entered in columns 28 and 32. Step 13 - Columns 29 through 42 show data necessary for the design of storm drains. Pipe sizes, gradients, and velocities are determined on the basis of flowing full using Manning's equation (Q = 1.49 x R2/3x S1/2x A). All projects shall include designs for smooth interior and fully-paved c.m. pipe ("n" = 0.024). Nomographs shown in Figures VII may be used for the design of circular pipe having respective "n" values of 0.012 and 0.024. On occasion when non-circular pipe and/or pipe having other "n" values are required, they shall be designed using the Manning's Equation. Hydraulic Design Series No. 3 of "Design Charts for Open-Channel Flow" published by the U. S. Department of Transportation, Federal Highway Administration (Reprinted 1979) is an acceptable design aid that may be used to design for these special conditions. Pipe roughness coefficients "n" for various pipe are shown in Figure X of Exh. 4.7.
4-19
Step 14 - The pipe roughness coefficient "n" is entered in the appropriate space of the top of Table "C" of Exh. 4-1. For this example, an "n" value of 0.012 is being used. Step 15 - Enter Figure VII of Exh. 4-5 using the design discharge from Column 32. Select a pipe size such that a line drawn from the design discharge from Column 32 through the selected pipe size intersects the slope and velocity lines at minimum values. Slopes for the required pipe size should be held to a minimum consistent with limitations imposed by cover requirements, proximity to other structures, and interference with other utilities. Also, pipe sizes and slopes should be selected such that flow velocities in successive pipes remain fairly constant. To avoid ponding at intake points (inlet, catch basins, etc.), pipe inverts and velocities must be established such to maintain the kinetic energy line (velocity head V2 plus the entrance 2g loss, head (K V2) at or below the top or gutter line elevation of the intake structures. In most cases, providing minimum pipe cover shall fulfill or exceed the velocity head plus entrance loss requirement. Both conditions, however, must be checked to ensure that ponding shall not occur. In profile proceeding downstream, the crowns of pipes where sizes progressively increase shall be matched. Crowns of incoming laterals shall be matched to that of mainline. Additional lowering of an outgoing pipe shall be required to compensate for head loss within the junction structure. Step 16 - For pipe 1-2, a Q of 3.3 cfs (from Column 32) is entered into Figure VII of Exh. 4-5. At a slope of 0.85%, a 12" pipe shall handle the design discharge with a reasonable velocity. A line drawn through the pipe size of 12" and a slope of 0.85%, intersects the discharge line at 3.5 cfs and the velocity line at 4.6 fps. This indicates the capacity of the pipe flowing full is 3.5 cfs at a velocity of 4.6 fps. Enter the selected pipe size and slope into Columns 33 and 34, respectively. It is now necessary to determine the Velocity in the pipe for the design Q of 3.3 cfs. Compute the ratio of the design discharge (3.3 cfs) to the flowing full discharge (3.5 cfs) as follows: Q Design = 3.3 = 0.94 Q Full 3.5 Enter the bottom of Figure IX of Exh. 4-6 at 0.94 and project a vertical line intersecting the "Capacity" curve. Continue the line horizontally from this point intersecting the "Velocity" curve. The partial full to full flow velocity ratio (VDesign/VFull) is interpreted as 1.135 by projecting a vertical line from the "Velocity" curve to the bottom of Figure IX of Exh.4-6. The partial full or Pipe 1-2 design velocity (VDesign) is found to be (4.6) (1.135) = 5.2 fps and is entered into Column 35. Step 17 - Head losses at junction structures shall now be taken into account. A loss coefficient "K" shall be selected from Figure XI of Exh. 4-7, depending on the type of junction. The "K" which produces the largest head loss at the junction shall be selected. For pipe l-2 passing through inlet number 2, a "K" value of 0.20 is selected from Figure XI. The head loss is calculated as follows: HL= K V2= 0.20(5.22)= 0.08' 2 g 2(32.2)
4-20
and is entered in Column 37. This value is the amount of lowering required below the entrance invert of pipe l-2 for pipe 2-3 as it exits inlet number 2 to compensate for head loss through inlet. This lowering is in addition to any lowering required due to change in pipe size. Step 18 - For each junction structure, the finished grade at the structure shall be determined and entered in Column 40. The upper and lower inverts of each pipe are then calculated and entered in Columns 38 and 39, respectively. Actual depths of cover are calculated for each pipe and entered in either Column 41 or 42, whichever is applicable. Inverts shall be set so as to maintain the cover requirements specified in Tables II-1 through II-9 of TM 5-820-4 for pipe located under traffic areas and/or high fills. The minimum cover for reinforced concrete Class III or corrugated metal pipe is l.0 foot for Civil Works Recreation and Public Use projects. In non-traffic areas, l.0 foot minimum cover is required. Step 19 - Maximum permissible outfall velocities for non-erosive flow are given in Table 9-l of TM 5-820-3. Pipe 5-6 outfalls into an existing silty-clay bare soil ditch, which permits a maximum nonerodable velocity of 3.5 fps (from Table 9-l). The discharge velocity in pipe 5-6 is 6.4 fps; therefore, energy dissipation, erosion protection and/or discharge velocity reduction (increase pipe size and/or reduce pipe slope) is required to prevent erosion of the outfall ditch. A good design shall require analysis of several feasible alternatives to determine the most economical method of controlling erosion.
4-21
5.1 5.2
5.3 PROJECT DEFINITION 5.3.1 General Statement of Surveying and Mapping services 5.3.2 Existing Horizontal and Vertical Site Control 5.4 CONCEPT OF SURVEYING AND MAPPING SERVICES 5.4.1.1 Geodetic and Control Surveys 5.4.1.2 Topographic Engineering and Construction Surveys 5.4.1.3 Route Location Surveys 5.4.1.4 Quantity Surveys 5.4.1.5 Layout Surveys 5.4.1.6 Hydro Engineering and Construction Surveys 5.4.1.7 Precise Surveys 5.4.1.8 Boundary and Cadastral Surveying 5.4.1.9 Photogrammetric Services 5.4.1.10 Supplemental Map Control 5.4.1.11 Cartographic Surveying 5.4.1.12 Subsurface Utility Investigations 5.4.1.13 Mapping and Charting 5.4.1.14 Digital Data 5.4.1.15 AutoCAD Layering Standard 5.5 5.5.1 5.5.2 5.5.3 5.5.4 5.5.5 5.5.6 5.6 MINIMUM TECH STANDARDS FOR SURVEYING AND MAPPING SERVICES Registered Land Surveyor Horizontal and Vertical Datum Survey Monuments Site Plan drawing (s) Compliance with Applicable Laws Security Clearance DESIGNER'S RESPONSIBILITY FOR UNSATFACTORY SITE SURVEYS
5-1
5.1
GENERAL
This chapter presents general requirements for surveying and mapping and the processing of the data that may be required for the work necessary in the design and advance planning of assigned projects. All labor, materials, and equipment necessary to perform site surveying and mapping services is required. Adequate professional supervision and quality control to assure the accuracy, quality, and completeness of the site surveys is required. Work may be required anywhere within the boundaries or assignments of the Mobile District in connection with the acquisition of site surveys and preparation of maps. 5.2 APPLICABLE PUBLICATIONS
The Engineering Manuals (EM's) listed will take precedence over District Manuals. Engineering Manuals (EM's) and Technical Manuals (TM's) may be acquired from the address below or www.usace.army.mil/inet/usace-docs. Corps of Engineers Publications Depot 2803 52nd Ave. Hyattsville, MD. 20781-1102 5.2.1 The following EM's and TM's may be applicable for site surveying and mapping for design of assigned projects: 5.2.1.1 Safety Standards of the Corps of Engineers Safety and Health Requirements Manual, EM-385-1-1, dated 3 November 2003. All personnel are required to adhere to these standards. 5.2.1.2 Standards Manual for U. S. Army Corps of Engineers ComputerAided Design and Drafting (CADD) System, Tri-Service A/E/C CADD Standards Manual. 5.2.1.3 Standards Manual for U. S. Army Corps of Engineers NAVSTAR Global Positioning System Manual, EM 1110-1-1003, dated 1 July 2003. 5.2.1.4 Standards Manual for U. S. Army Corps of Engineers Photogrammetry Manual, EM 1110-1-1000, dated 1 July 2002. 5.2.1.5 Standards Manual for U. S. Army Corps of Engineers Topographic and Field Surveying and Mapping, EM 1110-1-1005, dated August 1994. 5.2.1.6 Standards Manual for U. S. Army Corps of Engineers Hydrographic Surveying, EM 1110-2-1003, dated January 2002. 5.2.1.7 Standards Manual for U. S. Army Corps of Engineers Engineering and Design Geodetic and Control Surveying, EM 1110-1-1004, dated 1 June 2002.
5-2
5.2.2 The Manual of Instructions for Geodesy, Cartography, Hydrography and Photogrammetry for the Mobile District, dated January 1988, can be acquired from: U. S. Army Engineer District, Mobile Attention: CESAM-EN (Survey Unit) Post Office Box 2288 Mobile, Alabama 36628-0001 5.3 PROJECT DEFINITION 5.3.1 General Statement of Surveying and Mapping Services
The designer shall submit a general statement (scope of work) as to what type surveying and mapping services will be required for the site plan. The following information is required: 5.3.1.1 Name and location of the project.
5.3.1.2 Type of surveying and/or mapping services (geodetic, topographic, hydrographic, route location surveys, etc.). 5.3.1.3 English or metric surveys.
5.3.1.4 Site map to scale showing area to be surveyed (acres, length of route location survey, etc.). Scale required for the new survey (1"=30", 1"=50", 1"=100", 1"=200', etc.) and contour interval (1', 2', 5', etc.). 5.3.1.5 General description of utilities (above and/or underground) that will be located (if applicable), along with other special requirements or features that need to be identified such as trees or wetland areas. 5.3.2 Existing Horizontal and Vertical Site Control
Existing horizontal and vertical control shall be obtained from the Corps of Engineers at the following address: U. S. Army Engineer District, Mobile Attention: CESAM-EN (Survey Unit) Post Office Box 2288 Mobile, Alabama 36628-0001 5.3.2.1 The Government will furnish all pertinent horizontal and vertical control data on file. The following information is required: a) Location and name of the project. b) General site map showing location and coordinate values (NAD27 or NAD83) of the project area. 5.4 CONCEPT OF SURVEYING AND MAPPING SERVICES
5.4.1 The following surveying and mapping services may be necessary in the design and advance planning of assigned project(s): 5.4.1.1 Geodetic and Control Surveys
5-3
Includes surveys in which the figure and size of the earth are considered and is used for precise location of basic points suitable for controlling other surveys. Includes all orders of horizontal and vertical control surveys, geodetic astronomy, gravity and magnetic surveys in accordance with the Standards and Specifications for Geodetic Control Networks published by the Federal Geodetic Control Committee. Conventional, electronic instrumentation, inertial, satellite and other survey methods, as applicable, may be utilized. 5.4.1.2 Topographic Engineering and Construction Surveys
Includes acquisition of topographic surveying and mapping data representing three dimensional spatial relationships on the earth's surface. This data may be required for planning, cost estimating, engineering, design, construction, master planning, operations, and recording as-built conditions. Conventional and electronic instrumentation, remote sensing, inertial, satellite and other survey methods, as applicable, may be used. 5.4.1.3 Route Location Surveys
Preconstruction and/or final cross sections and computations of quantities. 5.4.1.5 Layout Surveys
Staking of buildings, structures, utilities, roads, railroads, etc. 5.4.1.6 Hydrographic Engineering and Construction Surveying
Surveys of channels, lakes, rivers, bays and open coastal waters in support of engineering design, construction, operations and maintenance. Includes acquisition of hydrographic and surveying and mapping data representing three dimensional spatial relationships on the earth's surface. This data may be required for planning, cost estimating, engineering, dredging, design, construction, sedimentation, master planning, operations and as-built conditions. Conventional and electronic instrumentation, and remote sensing, inertial, satellite, side scan sonar, subbottom profiling, marine magnetometer, and other surveying methods, as applicable, may be utilized. 5.4.1.7 Precise Surveys
Third order or better horizontal and vertical surveys to monitor movement of structures or precise location of structures. 5.4.1.8 Boundary and Cadastral Surveying
Includes property, boundary and easement surveys, etc. Conventional, electronic instrumentation, inertial, satellite, and other survey methods, as applicable, may be utilized. 5.4.1.9 Photogrammetric Services
Includes acquisition of surveying and mapping data from measurement of photographs representing either three dimensional or planimetric spatial
5-4
relationships on the earth's surface. Stereo plotting, bridging, photographic laboratory and reproduction services, acquisition of aerial photography, drafting and scribing, photogrammetric mapping to include film negatives, film and glass positives, photo indexes, photo enlargements, computations, scribecoats, compilation histories, and mapping on stable base materials my be required. 5.4.1.10 Supplemental Map Control (SMC)
Establishment of third order horizontal and vertical control on photo identifiable points for photogrammetric mapping. 5.4.1.11 Cartographic Surveying
Includes acquisition and assimilation of topographic and/or hydrographic surveying and mapping data for preparation of maps, charts, and similar products for planning. Conventional and electronic instrumentation, inertial, satellite and other survey methods, as applicable, may be utilized. 5.4.1.12 Subsurface Utility Investigations
Where there are a number of known utilities and communication lines crossing the proposed construction site, a Subsurface Utility Investigation is recommended. Typically, Subsurface Utility Investigations are categorized based on the quality of information obtained in an ascending level as follows: Quality Level D - A search of all reasonably accessible utility databases from surveys, Base As-Built drawings and Base maps, and public utility company drawings. Quality Level C - A physical site investigation of aboveground infrastructure associated with utilities such as manholes, valve boxes, utility poles, etc, to access the general accuracy of surveys, Base AsBuilt drawings and Base maps, and public utility company drawings. Quality Level B - involves the use of surface geophysical techniques to determine the existence and horizontal position of underground utilities and communication lines utilizing electromagnetic, two-dimensional ground penetrating radar (GPR), Computer Assisted Radar Tomography (CART), or other means. Quality Level A - involves the use of nondestructive digging techniques, such as vacuum extraction, at critical points to determine the precise horizontal and vertical position of underground utilities, as well as the type, size, condition, material, and other characteristics. The minimum acceptable Subsurface Utility Investigation shall be a Quality Level B. All subsurface utilities and communications lines shall be located to an accuracy of +/- 6-inches (0.15M). All subsurface utility information obtained during the investigation shall be shown on drawings containing the topographical survey. 5.4.1.13 Mapping and Charting
Includes the preparation (i.e., design, compilation , digitizing, scribing, drafting, and printing) of map and chart products. These depict man-made and natural features of a part to the surface of the earth in their correct positions and at an established scale relative to
5-5
a coordinate reference system. These maybe associated with engineering, land/boundary, geodetic and/or cartographic surveys. Conventional, electronic, or computer assisted design & CADD systems as applicable may be utilized. 5.4.1.14 Digital Data
A design file with the survey data is required in the latest release of both MicroStation and AutoCAD. The designer shall store and maintain a copy of all electronically created digital files (CD's, tapes and disc) through the construction phase of the project. The CD's, tapes and disc shall be made available to the government upon request and shall be maintained with no additional cost to the Government. 5.4.1.15 AutoCAD Layering Standard
The list of standard Cadd layer names shown in Exhibit 5-1 shall be utilized for topographical surveys. Where strict adherence to this naming standard is not possible, the layer names assigned shall easily identify those elements placed on that particular layer, and follow the same layer naming logic. 5.5 MINIMUM TECHNICAL STANDARDS FOR SURVEYING AND MAPPING SERVICES Registered Land Surveyor
5.5.1
All surveying and mapping services shall be accomplished under the direction/supervision of a Registered Land Surveyor in the State in which the project is located. Site plan mapping shall be signed and Sealed with the following statement: "I HEREBY STATE THAT THIS SURVEY AND DRAWING (S) MEETS OR EXCEEDS THE MINIMUM TECHNICAL STANDARDS FOR THE PRACTICE OF LAND SURVEYING IN ALABAMA, FLORIDA, GEORGIA, MISSISSIPPI OR TENNESSEE". 5.5.2 Horizontal and vertical Datum
All site plan surveying and mapping shall be referenced to the datums required by the scope of work. The site survey shall be accomplished with no less than third (3rd) order accuracy and procedure. Assumed coordinates and vertical positions can be used only with the Government's permission. CADD drawings shall indicated what horizontal and vertical control datum were used for the site surveys. 5.5.3 Survey Monuments
A minimum of three (3) permanent survey control points shall be established on or adjacent to the design site. Survey control points must be established in areas that will not be disturbed prior to and during the construction phase of the project. Designation and date established shall be stamped on each survey control point. No less than third (3rd) order horizontal and vertical control shall be established on each survey control point. A detailed description with horizontal and vertical datum shall be indicated on the site plan survey and design drawings. The following are requirements for a survey monument: 5.5.3.1 Be composed of a durable ferrous or magnetic material with minimal length of eighteen (18) inches and cross-section area of material of 0.3 square inches.
5-6
5.5.3.2 Be identified with durable marker or cap bearing designation, date and Registration Number of the land surveyor in responsible charge. 5.5.3.3 Be detectable with conventional instruments for finding ferrous or magnetic objects. 5.5.4 Site Plan drawing(s)
All permanent survey control points established on site shall be shown on the final design drawings. Inserts on the drawing and/or digital files shall show a detailed sketch of the location with description of the permanent control points established on site. Course chart on the drawings shall show coordinate and vertical values of each permanent monument. The following is a example of a course chart: NAME OF PROJECT AND LOCATION DESIGNATION OF POINT
21A-3B 21A-3C BB-3 21A-3D 212-3 212-4
NORTHING NAD 27
345,123.34 345,140.66 345,340.45 345,450.98 345,003.45 256,234.67
EASTING NAD 27
1,234,456.00 1,234,400.56 1,234,645.14 1,234,823.34 1,234,700.98 1,989,067.00
ELEVATION NGVD 29
234.56 FT. 246.98 FT. 250.42 FT. 254.10 FT. 224.21 FT. 225.90 FT.
5.5.5
All personnel shall strictly observe the laws of the United States or other governing body affecting operations at all sites. The personnel shall comply with all applicable laws under which they are operating including those concerning the inspection and operation of equipment and the licensing of engineers, land surveyors, pilots, mechanics and other personnel. It is further understood and agreed that the designer assumes full responsibility for the safety of his employees, plant, and materials. 5.5.6 Security Clearance
Personnel working on military projects shall be capable of obtaining a temporary security clearance. The following information could be required if the project is located in a restricted area: Full Name, Position, Social Security Number, Date of Birth, Place of Birth, Security Clearance, Citizenship, Drivers License Number and State of Drivers License. Include with this list the Name and Phone Number of a Point of Contact in case of an Emergency. It is the responsibility of the Designer to assure all personnel listed can obtain the clearance. 5.6 DESIGNER'S RESPONSIBILITY FOR UNSATISFACTORY SITE SURVEYS
If the site surveying and mapping services is found to be in error prior to and through the construction phase of the project, the designer shall
5-7
be responsible for all cost in connection with correcting such errors. The designer shall be and remain responsible to the Government in accordance with applicable law for all damages to the Government caused by negligent performance of any services.
5-8
STANDARD AUTOCAD LAYERS FOR TOPOGRAPHICAL SURVEYS Below are AutoCAD layers used by the Mobile District's Site Development Section to aid the site designer in the development of site model files. The layering names follow the same basic scheme as dictated in the TriService CADD Standard with the addition of the suffices "DM" for Demolition (removal), "EX" for existing features, and "NW" for new or proposed features. These layers allow easier manipulation of layers by other disciplines when using the Site Model File as a reference file to their designs. The surveyor has the liberty of creating additional layers, however, the Corps recommends that the same basic logic as represented in the Tri-Service Standard be used. The Color and Linetype of each drawing entity shall be drawn using the BY-LAYER setting. This will allow the color and linetype to be easily manipulated to suit the District's or the Base's pen table. C-ANN0-PATT C-ANNO-DIMS C-ANNO-KEYN C-ANNO-NOTE C-ANNO-NPLT C-ANNO-SYMB C-ANNO-TEXT Miscellaneous Patterns, Hatching. Dimension Lines, Arrowheads, and Text. Keynotes with leaderlines and arrowheads. General Notes Construction Lines, viewport windows. Miscellaneous Symbols. Miscellaneous Text, leaderlines, and text. - Apron outline.
C-APRN-OTLN-DM C-APRN-OTLN-EX C-APRN-OTLN-NW C-APRN-TXT-DM C-APRN-TXT-EX C-APRN-TXT-NW C-BLDG-OTLN-DM C-BLDG-OTLN-EX C-BLDG-OTLN-NW C-BLDG-TXT-DM C-BLDG-TXT-EX C-BLDG-TXT-NW C-CONTMJ-LINE-DM C-CONTMJ-LINE-EX C-CONTMJ-LINE-NW C-CONTMJ-TEXT-DM C-CONTMJ-TEXT-EX C-CONTMJ-TEXT-NW C-CONTMN-LINE-DM C-CONTMN-LINE-EX C-CONTMN-LINE-NW C-CONTMN-TEXT-DM C-CONTMN-TEXT-EX C-CONTMN-TEXT-NW C-ELEC-LINE-DM C-ELEC-LINE-EX C-ELEC-LINE-NW
- Apron text.
Exhibit 5-1
5-9
C-ELEC-TXT-DM C-ELEC-TXT-EX C-ELEC-TXT-NW C-FENC-LINE-DM C-FENC-LINE-EX C-FENC-LINE-NW C-FENC-TXT-DM C-FENC-TXT-EX C-FENC-TXT-NW C-GAS-LINE-DM C-GAS-LINE-EX C-GAS-LINE-NW C-GAS-TXT-DM C-GAS-TXT-EX C-GAS-TXT-NW C-PAVE-JNT-DM C-PAVE-JNT-EX C-PAVE-JNT-NW C-PAVE-TXT-DM C-PAVE-TXT-EX C-PAVE-TXT-NW C-PKNG-OTLN-DM C-PKNG-OTLN-EX C-PKNG-OTLN-NW C-PKNG-PVMK-DM C-PKNG-PVMK-EX C-PKNG-PVMK-NW C-PKNG-TXT-DM C-PKNG-TXT-EX C-PKNG-TXT-NW C-RAIL-CNTL-DM C-RAIL-CNTL-EX C-RAIL-CNTL-NW C-RAIL-OTLN-DM C-RAIL-OTLN-EX C-RAIL-OTLN-NW C-RAIL-TXT-DM C-RAIL-TXT-EX C-RAIL-TXT-NW C-RIPR-OTLN-DM C-RIPR-OTLN-EX C-RIPR-OTLN-NW C-ROAD-CNTR-DM C-ROAD-CNTR-EX C-ROAD-CNTR-NW C-ROAD-CURB-DM C-ROAD-CURB-EX C-ROAD-CURB-NW
- Fence lines
- Pavement Joints
- Parking outline
- Parking text.
- Railroad centerlines.
- Railroad outlines.
- Railroad text.
- Riprap outline
- Road centerline.
5-10
C-ROAD-GARD-DM C-ROAD-GARD-EX C-ROAD-GARD-NW C-ROAD-OTLN-DM C-ROAD-OTLN-EX C-ROAD-OTLN-NW C-ROAD-TXT-DM C-ROAD-TXT-EX C-ROAD-TXT-NW C-RUNW-CNTL-DM C-RUNW-CNTL-EX C-RUNW-CNTL-NW C-RUNW-OTLN-DM C-RUNW-OTLN-EX C-RUNW-OTLN-NW C-RUNW-TXT-DM C-RUNW-TXT-EX C-RUNW-TXT-NW C-SIGN-OTLN-DM C-SIGN-OTLN-EX C-SIGN-OTLN-NW C-SIGN-TXT-DM C-SIGN-TXT-EX C-SIGN-TXT-NW C-SNSW-LINE-DM C-SNSW-LINE-EX C-SNSW-LINE-NW C-SNSW-MNHL-DM C-SNSW-MNHL-EX C-SNSW-MNHL-NW C-SNSW-TXT-DM C-SNSW-TXT-EX C-SNSW-TXT-NW C-STEAM-LINE-DM C-STEAM-LINE-EX C-STEAM-LINE-NW C-STEAM-TXT-DM C-STEAM-TXT-EX C-STEAM-TXT-NW C-STRM-HDWL-DM C-STRM-HDWL-EX C-STRM-HDWL-NW C-STRM-LINE-DM C-STRM-LINE-EX C-STRM-LINE-NW C-STRM-MNHL-DM C-STRM-MNHL-EX C-STRM-MNHL-NW
- Road Text.
- Runway centerlines.
- Runway outline
- Runway Text
- Signs
- Sign Text
- Steam lines
5-11
C-STRM-TXT-DM C-STRM-TXT-EX C-STRM-TXT-NW C-SURV-BND-LNS C-SURV-BND-TXT C-SURV-CNTL-PTS C-SURV-CNTL-TXT C-TAXI-CNTR-DM C-TAXI-CNTR-EX C-TAXI-CNTR-NW C-TAXI-OTLN-DM C-TAXI-OTLN-EX C-TAXI-OTLN-NW C-TAXI-TXT-DM C-TAXI-TXT-EX C-TAXI-TXT-NW C-TOPO-BORE C-TOPO-COOR C-TOPO-GRID C-TOPO-SPOT-DM C-TOPO-SPOT-EX C-TOPO-SPOT-NW C-TOPO-TXT-DM C-TOPO-TXT-EX C-TOPO-TXT-NW C-VEG-OTLN-DM C-VEG-OTLN-EX C-VEG-OTLN-NW C-VEG-TXT-DM C-VEG-TXT-EX C-VEG-TXT-NW C-WALK-OTLN-DM C-WALK-OTLN-EX C-WALK-OTLN-NW C-WALK-TXT-DM C-WALK-TXT-EX C-WALK-TXT-NW C-WATF-OTLN-DM C-WATF-OTLN-EX C-WATF-OTLN-NW C-WATF-TXT-DM C-WATF-TXT-EX C-WATF-TXT-NW C-WATR-HYDT-DM C-WATR-HYDT-EX C-WATR-HYDT-NW C-WATR-LINE-DM C-WATR-LINE-EX
- Stormwater text.
- Taxiway centerlines.
- Taxiway outlines.
- Taxiway text.
- Topographical Soil borings. - Topographical coordinates - Topographical grid tick marks - Topographical spot elevations
- Topographical text.
- Vegetation outline
- Vegetation text.
- Walkways.
- Walkway text.
- Water hydrants
- Water lines.
5-12
5-13
6.1 GENERAL 6.2 APPLICABLE PUBLICATIONS 6.2.1 ASTM Specifications 6.2.2 Government Technical Publications 6.3 PROJECT DEFINITION (10-15%) 6.4 SUBSURFACE INVESTIGATION AND GEOTECHNICAL REPORT 6.4.1 Subsurface Investigation 6.4.2 Geotechnical Report 6.4.3 Boring Logs 6.4.4 Boring Location Map 6.4.5 Laboratory Test Data 6.5 CONCEPT DESIGN (30-35%) 6.5.1 Design Analysis 6.5.2 Design Drawings 6.6 INTERIM DESIGN (50-60%) 6.7 FINAL DESIGN (UNREVIEWED 100%) 6.7.1 General 6.7.2 Design Analysis 6.7.3 Design Drawings 6.7.4 Specifications 6.8 READY-TO-ADVERTISE (100%) 6.9 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS EXHIBITS 6-1 Boring Log - General Notes 6-2 Boring Log - Soil Classification Legend 6-3 Boring Log - Rock Classification Legend 6-4 Boring Log - Abbreviations (1 of 2) 6-5 Boring Log - Abbreviations (2 of 2) 6-6 Boring Log - ENG Form 1836 6-7 Boring Log - ENG Form 1836A 6-8 Geotechnical Report Checklists 6-9 Plans and Specifications Submittal Checklist 6-10 CSV Files for Boring Log and Laboratory Test Data
6-1
CHAPTER 6 GEOTECHNICAL 6.l GENERAL This chapter outlines the content of subsurface investigations, geotechnical design reports, geotechnical design analyses, and geotechnical data for inclusion in design and contract documents. A geotechnical design report is typically identified as a Foundation Report for projects that include structures as primary features but may otherwise be identified as a Subsurface Investigation Report. The term Geotechnical Report is used synonymously for both types of reports hereinafter. The geotechnical report shall be provided to all designers for use in design and incorporated in the various submittal stages. As soon as possible after locations of the primary features of the project are identified, the Geotechnical and Dam Safety Section of the USACE Mobile District (CESAM-EN-GG) shall evaluate any existing subsurface data for the site and identify the need for subsurface investigation at the site. CESAM-EN-GG, or the designer if included in his statement of work, shall plan and perform such geotechnical subsurface investigation at the project site as required, and provide to the designer a comprehensive Geotechnical Report as early in the design as practicable and not later than the Interim Design (50-60%) submittal. This chapter also lists the specific requirements of the submittal stages for geotechnical design features. 6.2 APPLICABLE PUBLICATIONS 6.2.1 ASTM Specifications Many of the "Guide Specifications" reference ASTM specifications. Most of the ASTM specifications that are usually referenced by geotechnical specifications can be found in volume 04.08 of ASTM. Listed below are the most frequently used ASTM specifications. These specifications or their updated versions should be referenced. C 117-95 C 136-84 D 420-87 D 421-85 Test Method for Material Finer Than 75-um (No. 200) Sieve in Material Aggregates for Washing Method for Sieve Analysis of Fine and Coarse Aggregates Recommended Practice for Investigating and Sampling Soil and Rock for Engineering Purposes Practice for Dry Preparation of Soil Samples for Particle-Size Analysis and Determination of Soil Constants Method for Particle-Size Analysis of Soils Terminology relating to Soil, Rock and Contained Fluids Test Method for Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lb/ft3) (600kN-m-m/3)
6-2
D 1140-54 D 1241 D 1452-80 D 1556-90 D 1557-91 D 1586-84 D 1587-83 D 2113-83 D 2167-84 D 2216-90 D 2487-90 D 2488-90 D 2922-91 D 2937-83 D 3017-78 D 3740-88
Test Method for Amount of Material in Soils Finer than the No. 200 (75-um) Sieve Specification for Materials for Soil-Aggregate Subbase, Base, and Surface Courses Practice for Soil Investigation and Sampling by Auger Borings (1990) Test Method for Density and Unit Weight of Soil in Place by the Sand-Cone Method Test Method for Laboratory Compaction Characteristics of Soil Using Modified Effort Method For Penetration Test and Split-Barrel Sampling of Soils Method For Thin-Walled Tube Sampling of Soils Method for Diamond Core Drilling for Site Investigation (1987) Test Method for Density and Unit Weight of Soil InPlace by the Rubber Balloon Method (1990) Test Method for Laboratory Determination of Water (Moisture)Content of Soil and Rock Classification of Soils for Engineering Purposes Practice for Description and Identification of Soils (Visual-Manual Procedure) Test Methods for Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth) Test Method for Density of Soil in Place by the DriveCylinder. Test Method for Moisture Content of Soil and SoilAggregate in Place by Nuclear Methods (Shallow Depth) Practice for Evaluation of Agencies Engaged in Testing and/or Inspection of Soil and Rock as Used in Engineering Design Guide for Selection of Aquifer Test Method in Determining Hydraulic Properties by Well Techniques Test Method (Field Procedure) for Instantaneous Change in Head (Slug Test) for Determining Hydraulic Properties of Aquifers. Test Method for Liquid Limit, Plastic Limit, and Plasticity Index of Soils Test Method for Crosshole Seismic Testing
D 4318-84 D 4428/4428M-91
6-3
Practice for the Correction of Unit Weight and Water Content for Soils Containing Oversize Particles Test Method for Expansion Index of Soils Method for Field Measurement of Soil Resistivity Using the Wenner Four-Electrode Method Method for Field Measurement of Soil Resistivity Using the Wenner Four-Electrode Method (1984)
6.2.2 Government Technical Publications Government engineering and technical manuals should be used in conjunction with the ASTMS for accomplishing foundation design as applicable for the project features. The engineering manuals can be accessed at http://www.usace.army.mil/inet/usace-docs/eng-manuals/em.htm. The technical manuals can be accessed at http://www.usace.army.mil/inet/usace-docs/armytm/. Manuals to be used by the geotechnical discipline include but are not limited to the following: DM-1110-1-1 Engineering and Design Geotechnical Manual for Surface and Subsurface Investigations (USACE South Atlantic Division manual) EM 1110-1-1804 Geotechnical Investigations EM 1110-1-1-1904 EM 1110-1-1-1905 EM 1110-1-2908 EM 1110-2-1902 EM 1110-2-1906 EM 1110-2-1913 EM 1110-2-2906 TM 5-818-1 Settlement Analysis Bearing Capacity of Soils Rock Foundations Slope Stability Laboratory Testing Design and Construction of Levees Design of Pile Foundations Soils and Geology Procedures for Foundation Design of Buildings and Other Structures (Except Hydraulic Structures) Dewatering and Groundwater Control Foundations in Expansive Soils Engineering Uses of Geotextiles Design Criteria Design Build Instructions
See Chapter 4 SITE DEVELOPMENT and Chapter 11 STRUCTURAL for additional publications to be used in the design of roads and buildings.
6-4
6.3 PROJECT DEFINITION (10-15%) The Project Definition Submittal should have a geotechnical chapter that states the known general geology and physiology of the project site. The chapter should state the site's history and its status as a potential site of Hazardous and Toxic Waste (HTW) contamination. The chapter should identify any available and relevant existing subsurface data at the site and state whether additional subsurface investigation is required for the design of the project. The chapter should describe and state the status of any ongoing subsurface investigation. The chapter should identify the entities responsible for providing any required additional subsurface investigation, the Geotechnical Report, and for providing the geotechnical specifications. The entities typically should be either CESAM-EN-GG or the designer. 6.4 SUBSURFACE INVESTIGATION AND GEOTECHNICAL REPORT 6.4.1 Subsurface Investigation Planning for and implementation of the subsurface investigation shall be performed by the entity tasked to perform the subsurface investigation. 6.4.1.1 Planning The subsurface investigation should be planned considering the regional geology, existing subsurface information at the site or its vicinity, the site history, and locations of project features. The history of the site should be considered to assess whether subsurface conditions may have changed since existing subsurface information was obtained. A preliminary boring location plan showing proposed locations of borings, test pits, resistivity tests, etc. should be prepared. Drilling instructions detailing the type and required depths of borings should be prepared. The method of locating borings should be planned and coordinated. 6.4.1.2 Boring Locations and Elevations If the designer is tasked to perform the subsurface investigation, accurate determination of locations and elevations of borings including any required surveys shall be the designers responsibility unless specifically otherwise stated in his statement of work. Locations of borings at their as-drilled locations shall be documented both using coordinates on the drilling logs and showing the locations on the boring location map. Datum and units of location coordinates and elevations shall be indicated on the boring logs and boring location map. All changes to proposed boring locations at any stage should be documented. When topographic survey of site is conducted after preparation of preliminary boring location map and either before or concurrently with subsurface investigation, generally a copy of boring location map should be provided to surveyor and the surveyors statement of work should require placement of stakes marked with boring name and ground surface elevation at the proposed boring locations and that coordinates and ground surface elevations at the staked locations be provided. If borings on land are not staked out in advance by survey and if features, spot elevations, and elevation contours of sufficient detail and accuracy are shown on the boring location map, the proposed boring locations may be staked out based on offset distances from the boring
6-5
locations to other surveyed features shown on the boring location map and ground surface elevations may be estimated from the elevations shown on the map. Otherwise, a new survey should be conducted for the purpose of staking out the borings and determining the coordinates and elevations at these locations. For offshore borings in water too deep or rapid to stake out, location survey measurements shall be made while and after navigating to the required location. Ground surface elevations typically should be determined by correlation of water depth measurements at the boring locations and concurrent gage readings of the water levels. The water depth, date, and time of measurement should be recorded on the boring log for all such water depth measurements. A minimum of two water measurements should be made, one at the beginning of the boring and a second at the end. If the sampling platform is influenced by the tide or is unstable, additional measurements shall be made and recorded periodically as necessary to calculate the correct sampling depths. The method of locating borings shall be described in the Geotechnical Report. 6.4.1.3 Drilling and Sampling A copy of the preliminary boring location plan and drilling instructions containing specific requirements for drilling, sampling, backfilling of boreholes, disposition of samples, etc. should be provided to the CESAMEN-GG drilling inspector for drilling performed in-house by CESAMEN-GG or should be included in the drilling contractors or subcontractors statement of work. Right-of-entry and drilling permits shall be obtained where required. No drilling shall be performed prior to obtaining utility clearance. Drilling, sampling, and presentation of results should be in accordance with USACE South Atlantic Division DM1110-1-1. 6.4.1.4 Laboratory Testing Laboratory testing shall be performed on selected samples as needed to accurately characterize the subsurface conditions at the site and to determine parameters for design analysis. Tests shall be appropriate for the type of materials encountered in the borings. 6.4.2 Geotechnical Report The Geotechnical Report shall be prepared by or under the direction of the geotechnical engineer or geologist responsible for the subsurface investigation. The Geotechnical Report shall present the results of the subsurface investigation including laboratory testing and shall offer recommendations for the design of structure foundations, pavements, and other geotechnical features. Specialty field tests such as pH measurements, resistivity tests, and percolation tests shall be included for use in design, if appropriate. The designer shall be responsible for selecting the structure foundation type based on the recommendations offered in the Geotechnical Report. The Geotechnical Report shall contain all the required data to design the foundation, to include items such as construction and permanent dewatering, pile driving, slope stabilization, etc. The geotechnical investigation shall adequately characterize the site geology and hydrogeology and shall provide all geotechnical data required to complete the project design. The Geotechnical Report including logs of borings and laboratory test data shall be made a part of the Design Analysis and shall be reviewed by
6-6
CESAM-EN-GG if the Geotechnical Report was not prepared by CESAM-EN-GG. The Geotechnical Report may be submitted for review prior to the conventional submittal dates if time permits. The designer should contact CESAM-EN-GG if there are any questions about the content of the Geotechnical Report or the features required by the various submittal stages or if the project has been resited. The narrative portion of the Geotechnical Report and any sections or profiles containing interpretations of subsurface data should be included with design submittals, but should not be included in contract documents. The Geotechnical Report Checklist (Exhibit 6-8) should be used to verify that the report is complete regarding the items described in the checklist 6.4.2.1 Structures The Geotechnical Report shall recommend the type of foundation system to be used for each primary structure in the project. The designer shall prepare earthwork specification for the structures. See requirements for shallow foundations and deep foundations below and Chapter 11 titled STRUCTURAL for further design requirements. If shallow foundations are recommended, the Geotechnical Report shall recommend the allowable bearing pressure, the depth of placement and bearing elevations for the footings, minimum footing widths, and minimum footing embedment depths. Requirements for measures such as soil stabilization, removal and replacement of unsatisfactory materials, surcharge fills, and capillary water barriers shall be addressed in the Geotechnical report if these measures are needed. The designer shall size all footings, grade beams, slabs, etc., utilizing the recommendations and restrictions presented in the Geotechnical Report. The designer shall be responsible for obtaining all geotechnical data required for the design of each type of foundation during the subsurface investigation if tasked to perform the subsurface investigation. If deep foundations are recommended, the Geotechnical Report shall provide recommendations for the type of deep foundation system to be used (piling, caissons, etc.), elevation of top of sound rock if applicable, the size and length of the piling or caissons, required tip elevations, and the allowable bearing capacity. The designer shall determine the number of piles or caissons, actual spacing, and the pile cap design. The number and location of test piles and load tests to be specified in the construction contract should be recommended in the Geotechnical report. 6.4.2.2 Dewatering Systems Groundwater levels at borings, soil classifications, and sieve analysis of aquifer samples shall be routinely conducted and included in the Geotechnical Report and shall be used to determine routine requirements for temporary dewatering systems. More specialized investigation such as piezometer installation, field pumping tests, laboratory permeability tests may be used and are advisable if a large dewatering effort will be required. Based on the results of the geotechnical investigation, the designer shall determine project dewatering requirements. All the required information necessary for the design of the system (hydrogeologic data, geotechnical analyses of sediments, aquifer properties such as hydraulic conductivity, transmissivity, storage coefficient, etc.) shall be collected during the geotechnical investigation and presented in the Geotechnical report. The use of slug
6-7
tests to determine aquifer characteristics shall not be acceptable for dewatering designs. Short-term construction dewatering due to poor surface drainage, precipitation, or short duration work at or near the water table is generally considered a contractor responsibility. Using information from the Geotechnical Report, the designer should alert the contractor to any known conditions that shall require dewatering. When temporary construction dewatering shall be required due to a consistently high water table or the effects of underlying artesian aquifers, the designer shall design and present a dewatering plan in sufficient detail that the contractor can bid on and install the dewatering system. Design of long-term or permanent dewatering systems, including selection of well screen slot sizes, screen lengths, discharge pipe sizes, installation methods, etc. shall be the responsibility of the designer. 6.4.2.3 Earth Liners The geotechnical investigation and report should provide the designer with the overall geologic conditions, the in situ and constructed permeabilities that can be obtained using native materials and stabilizing agents, liner types and thickness, and slope stabilization requirements. The designer shall be required to apply for all necessary permits. As part of the permitting process he shall be required to determine the classification of the material to be contained, the permeability necessary to contain the material, and the size and functional configuration of the containment area. No earth liners shall be permitted when material to be retained has a pH below 5. 6.4.2.4 Cathodic Protection and Grounding Systems The geotechnical investigation and report should include all pH tests, salinity tests, resistivity measurements, etc., required to design corrosion control and grounding systems. The raw field data shall be provided in the Geotechnical Report without interpretation or recommendations. The designer shall design all corrosion control and grounding systems required for the project and shall advise MDO immediately if additional field data is required. 6.4.2.5 Permanent Water Well Design and Construction If required by his scope of work, the designer shall be required to determine the location of the well, verify the flow requirements, verify future demands based on facility estimates, and determine the pump size and type. The permanent well design shall be based on data collected from the installation and aquifer testing of a pilot well. Test well borings shall be continuously sampled and visually logged by a qualified geologist. Additionally, the borehole shall be geophysically logged to verify the visual log. Sediment samples from the anticipated production zone(s) shall be analyzed for grain size distribution and any other required parameters to assist in the design of the well. The completed design shall specify casing sizes and lengths, grouted intervals, well screen slot size(s), screen length, filter pack gradation, centralizer locations, and testing requirements to insure the straightness and plumbness of the borehole and completed well.
6-8
6.4.2.6 Pavements The Geotechnical Report shall recommend for pavement subgrades the allowable design CBR and modulus of subgrade reaction parameters with the required compaction effort. Guidance shall be offered on the types of base course materials available in the area and design strengths. The designer shall prepare all earthwork specifications for pavement subgrades. The designer shall prepare all pavement material specifications with consultation from the Geotechnical Branch. See Chapter 4 titled SITE DEVELOPMENT, for deviations or exceptions. 6.4.2.7 General Earthwork and Special Features The Geotechnical Report shall recommend undercutting requirements, fill and backfill placement procedures, types of compaction equipment to be used, and outline earthwork procedures for special features such as retaining walls, embankment construction, earth covering of structures, basements, buried and mounded tanks, utilities, etc. The designer shall consult with the geotechnical engineer or geologist responsible for the subsurface investigation, or his office in his absence, in the design and preparation of specifications for any special features with geotechnical aspects that are not included or adequately described in the Geotechnical Report. For projects requiring gabion or riprap slope protection, the designer shall also coordinate with CESAM-EN-GG for required materials investigations and/or specification requirements. Notification of the proposed slope protection should be given CESAM-ENGG as soon as possible so as to allow time for any needed sampling and testing. 6.4.3 Boring Logs Logs of borings shall be provided as an appendix to the Geotechnical Report, design analysis, and contract specifications. ENG Form 1836 and ENG Form 1836A, modified to 8.5 inch x 11 inch page size as shown in Exhibits 6-6 and 6-7, shall be used for the first page and for continuation pages respectively for boring logs unless otherwise approved by CESAM-EN-GG. Adobe Acrobat Portable Document Format (PDF) files named logs.pdf and tests.pdf shall be provided for the appendices. General Notes, Soil Classification Legend, Rock Classification Legend if applicable, and Abbreviations pages (Exhibits 6-1, 6-2, 6-3, 6-4 and 6-5 respectively) shall be included at the beginning of the logs.pdf file, followed by boring location map if applicable, followed by the boring logs. For subsurface investigations conducted by the designer, his subcontractor, or by a contractor under MDOs direction, the designer or contractor shall, in addition to the required PDF files, provide complete and accurate boring log data in comma-separated-values (CSV) files as described in Exhibit 6-10 not later than when the Geotechnical Report is required. Boring log data obtained for all subsurface investigations conducted for Mobile District projects, including Design-Build and A-E designed projects as well as in-house-designed projects, shall be stored and maintained by CESAM-EN-GG for future use. Digital file formats used by the Borlog application shall be used. Soon after receipt of CSV files containing boring log data from contractors, CESAM-EN-GG shall import the data to the Borlog digital formats using the Borlog application.
6-9
6.4.4 Boring Location Map Locations of borings, test pits, monitoring wells and piezometers shall be shown on boring location map(s) in the appendix with boring logs in file logs.pdf, on civil site plans, or in both the logs.pdf file and on civil site plans. Boring location maps shall be clearly legible when printed at 8.5 in. x 11-in. size if included in the logs.pdf file. 6.4.5 Laboratory Test Data Laboratory test data shall be provided as an appendix to the Geotechnical Report, design analysis, and contract specifications. Laboratory test data shall be provided in a PDF file named tests.pdf. The designer or contractor shall, in addition to the required PDF files, provide laboratory test data in comma-separated-values (CSV) files as described in Exhibit 6-10 not later than when the Geotechnical Report is required. Laboratory test data obtained for all subsurface investigations conducted for Mobile District projects shall be stored and maintained by CESAM-EN-GG for future use. Soon after receipt of the CSV files containing laboratory data, CESAM-EN-GG shall import the data to the Borlog digital formats using the Borlog application. 6.5 CONCEPT DESIGN (30-35%) 6.5.1 Design Analysis (a) Incorporate recommendations stated in the Geotechnical Report into the design. (b) Provide geotechnical design calculations using parameters outlined in the Report and include a copy of the Report in the design analysis. (c) Notify the Geotechnical branch of any conflicts between the Geotechnical Report and concept design. If the topographic surveys are to be performed by the designer, then an electronic file copy in a DGN format of the survey must be sent to the entity performing the geotechnical investigation, as soon as possible but no later than the date for the submittal of the 35% design. (d) Include boring logs and laboratory test data as an appendix. 6.5.2 Design Drawings (a) Locate soil borings, test pits, monitoring wells and piezometers on the civil site plan. Add the appropriate symbol to legend. (b) Add note to civil site plan: "For logs of borings and test data, see __." and reference the appendix that includes boring logs and test data. 6.6 INTERIM DESIGN (50-60%) (a) (b) Comply with the accepted comments on the concept design. Perform any Concept Design tasks that were not completed.
6-10
(c) Prepare list of specifications to be provided by the geotechnical discipline. List should include specifications for all earthwork operations and specialty items such as dewatering systems, piling operations, slope stabilization, etc. 6.7 FINAL DESIGN (UNREVIEWED 100%) 6.7.1 General (a) Comply with comments on the interim review. Perform any Concept Design or Interim Design tasks that were not completed. (b) Prepare specifications for final review. (c) Include boring logs and laboratory test data as an appendix of the specifications. CESAM-EN-GG personnel should email files logs.pdf and tests.pdf to the Specifications engineer, who should include them in the appendix. Show locations of borings, test pits, monitoring wells and piezometers either on a page in the appendix with boring logs (file logs.pdf) and/or on civil site plans. (d) Use the Plans and Specifications Submittal Checklist (Exhibit 6-9) to verify that the submittal is complete regarding the items described in the checklist. 6.7.2 Design Analysis (a) Incorporate recommendations stated in the Geotechnical Report into the design. (b) Provide foundation design calculations using parameters outlined in the Report, and include a copy of the Geotechnical Report in the design analysis. (c) Identify and resolve any conflicts between the Geotechnical Report and the design. Contact the author of the Geotechnical Report for assistance in resolving such conflicts if needed or if the Geotechnical Report needs to be modified. 6.7.3 Design Drawings (a) Locate soil borings, test pits, monitoring wells and piezometers on civil site plan. Add the appropriate symbol to legend. (b) Add note to civil site plan: "For logs of borings and test data, see __ and reference the appendix that includes boring logs and test data. 6.7.4 Specifications The designer for A-E designed projects or CESAM-EN-GG for in-house design shall provide specifications required for geotechnical aspects of the project. If applicable, specifications provided by the geotechnical entity should include, but not be limited to: 02300 Earthwork 02360 Soil Treatment For Subterranean Termite Control The following Mobile District guide specifications are available for use, when applicable:
6-11
02300 Earthwork 02315 Excavation, Filling and Backfilling For Buildings 02316 Excavation, Trenching, and Backfilling for Utilities Systems The Mobile District guide specifications sections 02300, 02315, and 02316 are preferred over the UFGS (Unified Facilities Guide Specification) Section 02300 and are recommended for use as applicable for earthwork for site work, at buildings, and for utilities respectively. If the UFGS Section 02300 is used as the only earthwork specification, it shall be edited and care shall be taken to ensure all applicable aspects of earthwork (for site work, at buildings, and for utilities) are covered. Other specifications related to geotechnical aspects of the project should be provided as applicable. 6.8 READY TO ADVERTISE (100%) (a) Comply with comments on the final design review. (b) Include, or verify that they are included, any drawings and specifications in the Index of Drawings and the Table of Contents for specifications. (c) Include boring logs and laboratory test data (PDF files named logs.pdf and tests.pdf) as appendix of the specifications. (d) Do not include the narrative portion of the Geotechnical Report or any sections or profiles containing interpretations of subsurface data in contract drawings or specifications. 6.9 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides the geotechnical requirements regardless of the level of RFP development. These are the minimum requirements for ALL RFP development. CESAM-EN-GG shall provide any existing geotechnical data at the project site and prepare the Geotechnical Design portion of specification Section 01010. If no historical geotechnical data exists for the site, CESAM-EN-GG will obtain several borings at the site for inclusion in the Design-Build documents. Minimum requirements for additional subsurface investigations and assumptions to be used by the designer for bidding purposes should be provided in Section 01010. These minimum requirements should be established so as to provide adequate data to perform the analysis required by paragraph 6.4.2 GEOTECHNICAL REPORT. Section 01010 should make it clear that the Design-Build contractor is responsible for the geotechnical design for the project and for providing adequate Geotechnical investigations for the conditions encountered at the site. If unforeseen subsurface conditions that will significantly impact the design and construction of the project are encountered and additional subsurface investigation is needed, the Design-Build contractor should notify the government and submit a plan for additional subsurface investigation for the Government's approval. If the plan is approved, cost should be negotiated and the contractor should be compensated for the cost of such additional subsurface investigations by change to the contract.
6-12
EXHIBIT 6-8 GEOTECHNICAL REPORT CHECKLIST 1. Describe general site access with respect to mobility or drilling or other test equipment. Field sketches of existing utilities, fences, walkways and pavements should be made to compare to the topography map. 2. Generally describe the site topography and note all the topographic features that effect the project. 3. Describe the slope of the ground surface and delineate all drainage channels and any previous cut and fill or erosion. 4. Describe existing structures, pavements, or other obstructions and the procedures for demolition. 5. Fully describe the results of the subsurface investigation and any laboratory testing and its impacts on constructing the project. 6. GENERAL SCOPE: a. Results of subsurface investigation & testing b. Recommendations based on (a) above. 7. DETAIL INFORMATION: a. Description of structure(s) (1) (2) (3) (4) (5) (6) (7) (a) problems (b) Condition or history of nearby buildings (c) Analyze whether dewatering would cause settlement of adjacent structures (d) Location of fills or dump areas near site, which may jeopardize foundation (e) Existing buried Utilities conflict with new foundations b. Specific recommendations for foundation design and/or construction based on site features. (1) (2) (3) (4) (5) (6) (7) Topography Surface Water Groundwater Subsurface soil conditions Availability of borrow materials Location & availability of spoil areas Permitting actions required. Written general description Type of construction contemplated. Size and Height Finished Floor elevation; Elevation of existing ground Type of Foundation recommended Approximate load (s) Special Features affecting Foundation Design Water table, or history of dewatering or seepage
EXH 6-8, pg 1
c. Results and/or Recommendations for: (1) (2) (3) (4) (5) (6) (7) structures (8) (9) Construction Dewatering Erosion control during and after construction Bearing capacity Piles (Type, length, capacity, type of installations) Retaining Walls or basement walls Mat Foundations Slope Stability Settlement Permanent ground water drainage around or under
d. Revisions, additions, and/or deletions to the standard guide specs resulting from the foundation analysis. (1) Include a copy of the specification as it is proposed to be used. (2) Mention the major changes in the write-up and the reason for making them. e. Design Calculations (1) Include applicable design calculations on settlement, bearing capacity, seepage, uplift, stability analysis, quantities, shrinkage, dewatering, etc. (2) Show formulas, assumptions and reference source f. Site Plan (1) Show building road locations (2) Contours (3) Boring, test pit, infiltrometer locations (4) Locations of temporary & permanent surface water diversion measures (5) Location of buried utility line (existing & to be installed) g. Logs of all boring and test pits in Adobe Acrobat Portable Document Format in file named logs.pdf. Make sure the logs have horizontal control to the nearest foot and vertical control to the nearest tenth of a foot shown for each log. h. Results of all laboratory test data in Adobe Acrobat Portable Document Format in file named tests.pdf. i. Results of all boring log and laboratory test data in CSV files as specified. j. Detailed Dewatering design, if it is to be a major foundation cost.
EXH 6-8, pg 2
EXHIBIT 6-9 PLANS AND SPECIFICATIONS SUBMITTAL CHECKLIST GENERAL 1. Coordinate index of drawings with the title of each sheet. 2. Coordinate the title of the drawings with the title of the specifications. 3. Coordinate drawings for scale and dimension. 4. Reference related views and details. 5. Orientate all drawings and plan views by north arrow. 6. Clearly define limits of the contractor and owner's responsibility, i.e. Owner furnished - contractor installed equipment or materials, Owner furnished - owner installed equipment or materials, Contractor furnished - Contractor installed equipment or materials. 7. Proofread applicable sections of the specifications after typing. 8. Coordinate technical provisions terminology of the specifications for compatibility against the drawings. 9. Provide written responses to comments on the previous submittal. that the accepted comments have been incorporated. Check
10. Show haul routes, disposal areas, borrow areas, benchmarks, and all general type contractor information. 11. Check that boring logs and test data have been properly included as Adobe Acrobat Portable Document Files logs.pdf and tests.pdf for Appendix A of the specifications. If provided by CESAM-EN-GG, verify that these files have been emailed to the specifications engineer for the project. TECHNICAL 1. Check if allowable soil or rocks bearing values are shown on structural sheet. 2. Check logs of borings and test result for accuracy with respect to location, elevation, classification, water level, etc. 3. Check that previous accepted comments have been incorporated into drawings and/or specifications.
EXH 6-9
EXHIBIT 6-10 CSV File Requirements for Boring Log and Laboratory Test Data 1. Data Format. Comma-separated-value (CSV) file format shall be used. CSV file format is used by many spreadsheet and database software applications and is used for importing and exporting to and from the Borlog and Bordbs MDL (Microstation Development Language) applications. In CSV format files, data fields for each spreadsheet row or database record are written to a ASCII file as a single line with text fields separated by commas. There may be subtle but important differences in the way double-quote characters and embedded comma characters in CSV files are used, interpreted, and displayed by various software. Boring log and laboratory test data shall be provided in CSV files with the following characteristics:: a) Text data fields including embedded comma character(s) must be enclosed with beginning and ending double-quote characters. b) Data fields not including embedded comma character(s) may optionally be enclosed with beginning and ending double-quote characters, but they are not required. c) Data fields including embedded double-quote character(s) must include a contiguous pair of double-quote characters for each double-quote character in the data field. d) Numerical data must not include embedded comma characters. For example the numerical value 100000 must appear as either ...,100000,... or as ...,"100000",... when viewed with Notepad. It must not appear as ...,"100,000",... . For example illustrating text with neither an embedded comma or an embedded double-quote, the text data "BROWN LEAN CLAY (CL)" must appear in the CSV file when viewed with Notepad as either ...,"BROWN LEAN CLAY (CL)",... or as ...,BROWN LEAN CLAY (CL),... . For example illustrating text with both an embedded comma and an embedded double-quote, the text data "TAN POORLY GRADED GRAVEL (GP), 2" MAX." must appear in the CSV file when viewed with Notepad as ...,"TAN POORLY GRADED GRAVEL (GP), 2"" MAX.",... . CSV files produced with the "Save As" command (specifying CSV as file type) in Microsoft Excel software are compatible with these requirements. Users producing CSV files for importing data into Borlog should verify that their software is capable of producing CSV files with meeting these requirements or should edit the CSV file data as required after producing it. CSV files for boring log and laboratory testing use keywords (as defined in following paragraphs) that describe the content of the data that follows the keyword. By convention if the keyword ends with a colon character, the data associated with that keyword follows in the next data field on the same line. If the keyword does not end with a colon character, the keyword is a column heading and data associated with that keyword follows in the same data field on the following lines. 2. File Name Conventions and Data Content for Boring Log Data. Six types of Borlog CSV files can be used to import boring log data into Borlog (.bor) format files. The files should be named according to the conventions described in paragraphs 2.1 to 2.6 so as to be able to easily identify the data content by the file name. The first line of
EXH 6-10, pg 1
each type of CSV files when viewed in Notepad (or first row in spreadsheet) must contain heading text that matches keywords that are defined in the Borlog application. Valid heading keywords are listed Table 2.1 to 2.6. The keywords are not case sensitive.For keywords with units of length (northing, easting, and various depths and elevations), the units of length can be specified by appending to the base keyword ",ft" or ",ft_s" for U.S. survey feet, ",ft_i" for international feet, or ",m" for meters (for example, ...,"Easting,m","Northing,m",...). The difference between U.S. survey feet and international feet is significant only for northing and easting boring location coordinates. Default units if units are not appended to the base keyword are U.S. survey feet. Data columns with invalid heading keywords are allowed but are not imported. The data corresponding to the keywords must be placed in columns if viewed with spreadsheet. Each line of data in CSV files (or a row in spreadsheet) is limited to a maximum of 511 characters. The first heading keyword of all .csv files (at cell A1 in spreadsheet) must be Boring. The second and third keywords (cells B1 and C1 in spreadsheet) of all .csv files except zzznnnnn-gen.csv must be "Top_D" and "Bot_D". All other keywords are optional and, with a few exceptions, may appear in any sequence, but generally should appear in the sequences indicated in the following in the interest of consistency. Data fields for which no data is available should be left blank except where otherwise stated. 2.1 File gen.csv (or zzznnnnn-gen.csv if Borlog project ID zzznnnnn has been defined, where zzz is a 3-character zone abbreviation and nnnnn is a zero-filled 5-digit sequential number for subsurface investigations in that zone) should contain data that is general; i.e., it contains information about the boring that is not specific to any particular depth, sample, or stratum. It should include the data with keyword headings listed in Table 1. If mm/dd/yy or mm-dd-yy formats are used for dates in the Date_Start and Date_Compl data fields, years between 50 and 99 inclusive are assumed by Borlog to be between 1950 and 1999 and years between 0 and 49 inclusive are assumed to be between 2000 and 2049. Use of mm/dd/yyyy format is recommended for dates to avoid any possibility of misinterpretation. Depth zero is usually assumed to be at ground surface level at the boring location; However, any depth datum may be used provided that the same datum is consistently used for all depths recorded for the boring. Levels below depth zero should be entered as positive depth values and levels above depth zero should be entered as negative depth values. Table 1: Borlog Heading Keywords, Descriptions and Variable Types for Gen.csv File: Boring - boring name, 12-character max. text Easting - easting coordinate at boring location, numeric Northing - northing coordinate at boring location, numeric GS_E - ground surface elevation at boring location, numeric GS_D - ground surface depth at boring location (usually zero), numeric BOH_D - bottom of hole depth, numeric GW_DI - initial groundwater depth, numeric (same as GW_DF if only one reading made) GW_DF - final groundwater depth, numeric TOR_D - top of rock depth, numeric Date_Start - start date, text in m/d/y format
EXH 6-10, pg 2
Date_Compl - completion date, text in m/d/y format No_Dist_Samp - number of disturbed soil samples No_Undist_Samp - number of undisturbed soil samples No_Core_Boxes - number of core boxes Driller - driller's name (first name, middle initial and last name, or portion thereof), 32-character max. text Inspector - drilling inspector's name (first name, middle initial and last name, or portion thereof), 32-character max. text Recov_Tot - total sample recovery percentage for boring, 5-character max. text Drilling_Org - drilling organization, 32-character max. text Installation - installation, 24-character max. text 2.2 File des.csv (or zzznnnnn-des.csv) should contain strata description data using heading keywords listed in Table 2. It should not contain any remarks related to drilling method or anything else that does not describe the materials that were encountered. An example is: Boring, Top_D, Bot_D, Classif, Description SS-1-99,0.0,1.5,SM,"BROWN SILTY SAND (SM), SOME ROOTS NEAR SURFACE" SS-1-99,1.5,6,SP,TAN POORLY GRADED FINE SAND (SP) SS-2-99,0.0,1.5,GP-GM,"TAN SILTY GRAVEL (GP-GM), 1-1/2"" MAX. SIZE" SS-2-99,1.5,10.0,LMS,"DARK GREY LIMESTONE, HARD" Table 2: Borlog Heading Keywords, Descriptions and Variable Types for Des.csv File: Boring - boring name, 12-character max. text Top_D - top depth of stratum, numeric Bot_D - bottom depth of stratum, numeric Classif - field classification abbreviation (cell name) of stratum, NS, NA or *, 12-character max. text. Description - field description of stratum, text, length controlled by max. line length of 511 characters The abbreviation in the Classif field of data, except for NS, NA and * entries described below, should be the Microstation cell names used for the symbology column on the boring log. These include all of the standard USCS 2-character soil classifications (GP, GW, GM, GC, SP, SW, SM, SC, ML, MH, CL, CH, OL, OH, and Pt), 3-character abbreviations for rock classifications (BST for basalt, CHT for chert, CLS for claystone, CNG for conglomerate, COL for coal, DLM for dolomite, GNS for gneiss, GRN for granite, LMS for limestone, PHY for phyllite, QTZ for quartzite, RHY for rhyolite, SCH for schist, SDS for sandstone, SHA for shale, SHC for cemented shale, STS for siltstone, and TUF for tuff and 3-character abbreviations for certain other materials (ASP for asphalt, CNC for concrete, SHL for shell, and WAT for water), and CAV for a cavity. Use of dual classifications made by combining two of the abbreviations listed above, separated with either a hyphen or an ampersand character, is allowed by the Borlog program (for example, SP-SM or GP&CL). However use of dual classifications, except those with specific procedures for identification defined in the Unified Soil Classification System (GP-GM, GW-GM, GP-GC, GM-GC, SW-SM, SW-SC, SP-SM, SP-SC, and CL-ML), is considered poor practice and is discouraged. "NS" may be used in the Classif column of data to indicate that the boring was not sampled at the depth interval indicated. Alternately, the line of data may be omitted at any depth intervals that were not sampled. "NA" should be used in the Classif column of data to indicate a material
EXH 6-10, pg 3
for which no classification abbreviation is defined. No symbol will be drawn on the boring log by Borlog in this case. An asterisk should be used in the Classif column of data to indicate that the data in that row is a detail note (having the same classification as the previous line of data) for which bracketed text or a leader line with or without text should be drawn. Bracketed description text will be drawn if the top and bottom depths are different, else a single leader line with description text will be drawn. A leader line without text connected to a bracket (typically used to indicate interior locations of more than two joints in rock with the same description at various depths) will be drawn if an asterisk is in the Classif column, top and bottom depths are the same, and the Description column is left blank. 2.3 File smp.csv (or zzznnnnn_smp.csv) should contain sample identification data for all samples and optionally may contain moisture content and Atterberg limits lab test data, laboratory classification, and laboratory descriptions. The sample identifcation data should be shown in column f of the boring log. The results of the index laboratory tests should be shown in the Remarks column of the boring log. Typically for subsurface investigations conducted by SAM-EN-GG, this data is initially input or imported before lab data is available. Later when lab data becomes available, the data is supplemented either by inputting the lab data from index testing or by importing a similar file that also contains lab data from index testing (file T01.csv, see paragraph 3.1) and imported again. Examples of both are shown. Boring,Top_D,Bot_D,Sample SS-1-99,0,1.5,JAR 1 SS-1-99,0,1.5,JAR 2 SS-2-99,0,1.5,JAR 1 SS-2-99,4.5,6.0,JAR 3 Boring,Top_D,Bot_D,Sample,LL,PL,MC,Lab_VC,Lab_Descr SS-1-99,0,1.5,JAR 1,,,12.3,SM,SILTY SAND SS-1-99,0,1.5,JAR 2,,,,, SS-2-99,0,1.5,JAR 1,65,25,30.3,CH, SS-2-99,4.5,6.0,JAR 3,NP,NP,27.4,ML, Table 3: Borlog Heading Keywords, Descriptions and Variable Types for Smp.csv File: Boring - boring name, 12-character max. text Top_D - top depth of sample, numeric Bot_D - bottom depth of sample, numeric Sample - sample name, 12-character max. text LL - liquid limit, text (NP for nonplastic or numeric text) PL - plastic limit, text (NP for nonplastic or numeric text) MC - moisture content, in percent, numeric Lab_VC - laboratory visual classification of sample, 12-character max. text Lab_Descr - laboratory description of sample, text, max. character controlled by max. line length of 511 characters 2.4 File spt.csv (or zzznnnnn-spt.csv) should contain Standard Penetration Test (SPT) data. If the computed N-value data is available for input but C1, C2 and C3 data is not available, use zero values for C1, C2 and C3, 0.5 values for P1, P2 and P3, and the N-values for SPT_Text. Otherwise, only use the SPT_Text column to input W.O.R. or W.O.H. values (abbreviations for weight of rods and weight of hammer
EXH 6-10, pg 4
respectively) for zero blow counts. The example file below includes an example of typical SPT data entry in the first line after the heading, an example for zero blow count in the second line, and examples for 100+ blow counts in the following 3 lines. Boring, Top_D, Bot_D,C1, C2, C3, P1, P2, P3, SPT_Text SS-1-99,0,1.5,8,12,18,.5,.5,.5, SS-1-99,1.5,3,0,0,0,.5,.5,.5,W.O.H. SS-2-99,15,16.3,17,35,50,.5,.5,.3, SS-2-99,16.5,17.2,32,50,0,.5,.2,0, SS-2-99,18.5,18.9,50,0,0,.4,0,0, Table 4: Borlog Heading Keywords, Descriptions and Variable Types for Spt.csv File: Boring - boring name, 12-character max. text Top_D - top depth of sample, numeric Bot_D - bottom depth of sample, numeric C1 - number of blows in first drive in SPT test, integer C2 - number of blows in second drive in SPT test, integer C3 - number of blows in third drive in SPT test, integer P1 - penetration in first drive in SPT test in feet, numeric P2 - penetration in second drive in SPT test in feet, numeric P3 - penetration in third drive in SPT test in feet, numeric SPT_Text - SPT N-value 15-character max. text (optional, overrides computed SPT N value if not field is not blank, should be W.O.R., W.O.H., 100+, or an integer SPT N value from 0 to 100) 2.5 File rem.csv (or zzznnnnn_rem.csv) should contain remarks data to be drawn in the "Remarks" column of the boring log. The top and bottom depth data is used only to determine the location for placement of the remark text, which will placed as close as possible to the average of the top and bottom depths without overlapping other remarks data. An example is: Boring, Top_D, Bot_D, Remark SS-1-99,0,1,BORING OFFSET 20 SOUTH TO AVOID POND Table 5: Borlog Heading Keywords, Descriptions and Variable Types for Rem.csv File: Boring - boring name, 12-character max. text Top_D - top depth of sample, numeric Bot_D - bottom depth of sample, numeric Remark - remark for Remarks column of boring log, text, max. character controlled by max. line length of 511 characters. The remark may contain tilde ~ characters which force a new line when the text is drawn. 2.6 File crc.csv (or zzznnnnn_crc.csv) should contain core recovery data for rock core samples. The Cor_Remark data may contain tilde (~) characters which force a new line when the text is drawn. The entire remark should be included in one field on the same line of data as the other data (the line is wrapped for display purposes in the example below). Boring, Top_D, Bot_D, Pull_Num, Corr_D, Recov, Cor_Remark SS-1-99,105.4,112.3,PULL-1,109.4,3.5,RAN: 6.9~W.L.: 30%~W.C.: BROWN~DRILL P.: 200 - 300~DRILL A.: LIGHT CHATTER~WATER RETURN: 70% Table 6: Borlog Heading Keywords, Descriptions and Variable Types for Crc.csv File:
EXH 6-10, pg 5
Boring - boring name, 12-character max. text Top_D - top depth of sample, numeric Bot_D - bottom depth of sample, numeric Pull_Num - pull number of core sample, 12-character max. text Corr_D - corrected depth of core sample, numeric Recov - recovered length of core sample, numeric Cor_Remark - remark for core sample, text, max. character controlled by max. line length of 511 characters 3. File Name Conventions and Data Content for Laboratory Test Data. Each CSV file for laboratory test data shall be named according to the established file name convention and shall include data at the beginning lines of the file that includes the keywords in Table 7 and the associated data for those keywords. Table 7: Heading Keywords, Descriptions and Variable Types for General Data: Laboratory: - laboratory performing test, 32-character max. text Client: - organization requesting test, 32-character max. text Project: - name of project site where sample was obtained, 32-character max. text Location: - location of project site where sample was obtained, 32character max. text Started: - date that first test in the file was started, m/d/y format Completed: - date that last test in the file was completed, m/d/y format Test_Type: - type of test, text If mm/dd/yy or mm-dd-yy formats are used for dates in the Started and Completed data fields, years between 50 and 99 inclusive are assumed to be between 1950 and 1999 and years between 0 and 49 inclusive are assumed to be between 2000 and 2049. Use of mm/dd/yyyy format is recommended for dates to avoid any possibility of misinterpretation. The text value for the Test_Type keyword shall be one of the following, which are not case sensitive: "Index Testing", "Grain Size Multiple", "Grain Size Single", "Consolidation", or "Consolidation Time Curve". Data for each type of test shall include the keywords in Table 8 with associated data to identify the sample that was tested. The keywords Top_D and Bot_D should be replaced with "Top_D,m" and "Bot_D,m" respectively if the depth values are entered in meter units; otherwise, depths should be entered in units of feet. Table 8: Heading Keywords, Descriptions and Variable Types for Sample Indentification Data: Boring - boring name, 12-character max. text Top_D - top depth of sample, numeric Bot_D - bottom depth of sample, numeric Sample - sample name, 12-character max. text 3.1 Index Testing. File T01.csv shall contain general and sample identification data using keywords defined in Tables 7 and 8 respectively, and moisture content and Atterberg limits lab test data, laboratory classification, and laboratory descriptions using the keywords defined in Table 9. A short example to illustrate the format follows: ; Example of T01.csv file for Index Testing Laboratory:,"Materials Testing Center, Vicksburg MS",,,,,,,,,,,,,,,,,, Client:,USACE Mobile District,,,,,,,,,,,,,,,,,,
EXH 6-10, pg 6
Project:,Dining Facility,,,,,,,,,,,,,,,,,, Location:,"Redstone Arsenal, Alabama",,,,,,,,,,,,,,,,,, Started: - 3/23/1999 Completed: - 3/24/1999 Test_Type:,Index Testing,,,,,,,,,,,,,,,,,, ,,,,,,,,,,,,,,,,,,, Boring,Top_D,Bot_D,Sample,LL,PL,MC,Lab_VC,Lab_Descr SS-1-99,0,1.5,JAR 1,,,12.3,SM,SILTY SAND SS-2-99,0,1.5,JAR 1,65,25,30.3,CH, SS-2-99,4.5,6.0,JAR 3,NP,NP,27.4,ML, Table 9: Heading Keywords, Descriptions and Variable Types for Index Testing T01.csv File: LL - liquid limit, text (NP for nonplastic or numeric text) PL - plastic limit, text (NP for nonplastic or numeric text) MC - moisture content, in percent, numeric Lab_VC - laboratory visual classification of sample, 12-character max. text Lab_Descr - laboratory description of sample, text, max. character controlled by max. line length of 511 characters 3.2 Grain Size Tests. File T02.csv shall contain general and sample identification data using keywords defined in Tables 7 and 8 respectively, and test data for grain size tests, including sieve analysis and/or hydrometer test data. Column heading keywords for sieve analysis may include any of following U.S. Standard sieve sizes: 3 in, 2-1/2 in, 2 in, 1-1/2 in, 1 in, 3/4 in, 1/2 in, 3/8 in, #3, #4, #6, #10, #16, #20, #30, #40, #50, #70, #100, #140, #170, #200, and #230. Column heading keywords Size,mm and Value shall be used for hydrometer analysis and if sieves other than the U.S. standard sieve sizes are used. An example file including both types of data is shown below: ;Example of CSV file for Grain Size Tests Organization:,"Materials Testing Center, Vicksburg MS",,,,,,,,,,,,,,,,,, Client:,USACE Mobile District,,,,,,,,,,,,,,,,, Project:,Dining Facility,,,,,,,,,,,,,,,,, Project Location:,"Redstone Arsenal, Alabama",,,,,,,,,,,,,,,,, Started:,9/25/2002,,,,,,,,,,,,,,,,, Completed:,10/3/2002,,,,,,,,,,,,,,,,, Test Type:,Grain Size Sieves,,,,,,,,,,,,,,,,, Table Value:,Percent Finer,,,,,,,,,,,,,,,,, Boring,Top_D,Bot_D,Sample,#1/2 in,#3/8 in,#3,#4,#6,#10,#16,#20,#30,#40,#50,#70,#100,#140,#200 DF-1-02,0,1.5,JAR 1,100,97,96.2, 96,95.8,94.8,93.1,91.5,89,86.8,84.6,82.8, 80.8,79.7,79.5 DF-2-02,6,7.5,JAR 5,100,100,100,100,100,98.9,97.6,96.9,96.4,95.8,94.8,93.2,90.8,88.3,86.1 ,,,,,,,,,,,,,,,,,,, Boring:,DF-1-02, Top_D:,0 Bot_D:,1.5 Sample:,JAR 1 Test Type:,Grain Size Single,,,,,,,,,,,,,,,,,, Table Value:,Percent Finer,,,,,,,,,,,,,,,,,, "Size,mm",Value,,,,,,,,,,, .0031,69.6,,,,,,,,,,,,,, .0043,38.4,,,,,,,,,,,,,,
EXH 6-10, pg 7
3.3 Consolidation Tests. File T03.csv shall contain general and sample identification data using keywords defined in Tables 7 and 8 respectively, and test data for consolidation tests. Keywords specifically for consolidation tests include Initial void ratio: and column heading keywords Load,tsf and Void Ratio. An example file that includes both loading and unloading is shown below: ;Example CSV file for Consolidation Test Organization:, USACE ERDC Client:,USACE Mobile District Project:,Fire Crash Station Project Location:,"MacDill AFB, Florida" Started:,11/07/2002 Completed:,11/21/2002 ,, Test Type:,Consolidation Boring:,DF-1-02 Top_D:, 16.5 Bot_D:, 18.8 Sample:,TUBE 1 Initial void ratio:,1.20 ,, Load,tsf, Void Ratio 0.1,1.150 0.25,1.124 0.5,1.072 1,0.990 2,0.910 4,0.826 8,0.740 16,0.656 32,0.578 60,0.499 16,0.516 4,0.560 1,0.616 0.25,0.67 0.1,0.684
EXH 6-10, pg 8
GENERAL 7.1.1 Scope APPLICABLE PUBLICATIONS 7.2.1 Corps of Engineers Unified Facilities Guide Specifications PROJECT DEFINITION (10-15%) CONCEPT DESIGN (30-35%) 7.4.1 Concept Design Analysis 7.4.2 Concept Design Drawings INTERM DESIGN (50-60%) 7.5.1 Interim Design Analysis 7.5.2 Interim Design Drawings FINAL DESIGN (100% UNREVIEWED) 7.6.l Specifications 7.6.2 Final Design Drawings READY-TO-ADVERTISE (100%) RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS 7.8.1. Mandatory Requirements 7.8.2 Specific Requirements
7.5
7.6
7.7 7.8
7.9
TECHNICAL REQUIREMENTS 7.9.l Design Criteria 7.9.2 Site Investigation 7.9.3 Coordination
7-1
7.1.1
Specific submittal and technical requirements for landscape planting and turfing are presented in this chapter as guidance for development of plans and specifications. The quality of planting design shall be comprehensive and shall be coordinated with pertinent aspects of the overall site development, the architecture of structures, and user requirements. 7.2 APPLICABLE PUBLICATIONS Unified Facilities Criteria (UFC): UFC 2-600 Design Manuals: TI 800-01 TI-800-03 7.2.1 Design Criteria Design Build Instructions Installation Design
Specifications are updated on a regular basis. Instructions on retrieving UFGS (Unified Facilities Guide Specifications) are covered in Chapter 3, SPECIFICATIONS. 7.3 PROJECT DEFINITION (10-15%)
The project definition shall verify the minimum design requirements for the work being performed in the landscape plan. Specific boundaries, limits of the work being performed, shall be delineated to anticipate the level of development of the landscape plan. The plan will in turn be used to determine a preliminary cost estimate for the project. Specific use areas shall be located to determine the proper landscape treatment for those areas, from both the standpoint of material selection and functional use e.g. screening, canopy, color, enclosure etc. and/or turf, it shall also be communicated in the project definition. 7.4 CONCEPT DESIGN (30-35%) Concept Design Analysis
7.4.1
The landscape planting design narrative shall describe the conditions of the existing site, including an indication of existing plant materials that are to remain on the site. Specific site problems related to proposed development and the rationale for proposed plant locations shall be indicated. The narrative shall also include a list of suggested types and sizes of plant materials, which are to be used, based upon the designated functional and visual criteria. The concept cost estimate shall be based on quantities derived from generalized locations and listed types and sizes of plant materials. 7.4.2 Concept Design Drawings
The overall design approach shall depict factors, which affect existing site features and influence subsequent design proposals. The concept drawings
7-2
shall be prepared at a scale, which corresponds with the site layout and grading plans, and shall include reference coordinates, north arrows, graphic scales, and appropriate legends. 7.5 INTERM DESIGN (50-60%) Interim Design Analysis
7.5.1
The descriptive narrative, list of materials and cost estimate shall be refined to correspond with the development of the preliminary planting plans. 7.5.2 Interim Design Drawings
The interim design submittal shall expand the concept design by development of an overall planting layout and shall include enlarged detail plans of specific areas, as needed, to clarify requirements. The proposed layout shall indicate shade trees, evergreen trees, flowering trees, shrub masses, etc., according to designated functional and visual locations of planting. A legend indicating sizes of plants recommended for each of the above categories shall be included. The preliminary design drawings and all subsequent plans shall indicate existing and proposed buildings, paved areas, signs, light standards, transformers, dumpster areas, storm drainage system, and other structures and utilities. If existing and proposed contours cannot be clearly indicated graphically on the plan, overlay of the drawings shall reveal that grades and elevations have been taken into account. Grassing limits, seeded or sodded, shall be clearly described in the contract documents. 7.6 FINAL REVIEW (100% UNREVIEWED) Specifications
7.6.l
Landscape planting specifications shall be based on the current specifications available in the UFGS Guide Specification Index. 7.6.2 Final Design Drawings
Final design drawings, indicating proposed plants by a (+) mark for the plant location and a circle which is scaled at approximately 2/3 the ultimate growth spread (diameter) of plants, shall include a complete schedule of plant materials indicating botanical and common names, plan symbols, quantities, sizes, condition furnished, and pertinent remarks. Final drawings shall also include the basic details for installation of tree, shrub, and ground cover planting, as well as any other applicable details for clarification of specific project requirements. Pertinent notes applicable to construction requirements, in addition to standard notes, shall be included. The design plan, plant schedule, details, notes, specifications, and subsequent cost estimates shall all correspond. 7.7 READY-TO-ADVERTISE (l00%)
All final design drawings, specifications, and cost estimates shall have incorporated comments from the preceding reviews before submittal as Ready-to-Advertise. 7.8 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS
TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria
7-3
development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs. 7.8.1 Mandatory Requirements a. 7.8.2 See TI 800-03 for mandatory requirements.
Specific Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria:
1. Preliminary Landscaping Plan (including kind, size and type trees, shrubs and ground covering). b. Partial Project Criteria: 1. 2. c. Same as Nominal requirements. Include an outline of the specifications to be edited.
Full Project Criteria: 1. 2. Final Plans (See description above under 7.6.2.) Final Specifications (See description above under 7.6.1.)
NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements. 7.9 TECHNICAL REQUIREMENTS Design Criteria (a) Designer Qualifications
7.9.1
The designer shall obtain and use the services of a qualified Landscape Architect who is registered, preferably in the State in which the work is to be done, and is experienced in site planning and planting design. The person performing this work shall be thoroughly familiar with the referenced Technical Manuals, and specifications. (b) Major Design Considerations
Design plans shall reflect user needs, simplicity of layout, proper scale and spacing of materials, low maintenance considerations, and compatibility with adjacent surrounding. Specified plant materials shall be readily available for purchase, require minimum maintenance, be suitable and tolerant to both the geographic locale and the specific site conditions, be the proper quantities selected for the surroundings, and be of sufficient size to give an immediate effect. The types and locations of plant materials shall be utilized, as appropriate to the function and prominence of specific facilities, to define the functional use areas and circulation systems of the site layout; to provide open space buffers between land uses
7-4
and within parking areas; to reinforce the orientation of buildings and the use of earthforms for energy conservation; to supplement erosion control; to provide screening; and to emphasize entrances to buildings. The aesthetic quality of planting design shall be supportive in providing visual continuity in the relationships between buildings, the site, and the surrounding environment. 7.9.2 Site Investigation
A visit to the project site is recommended as a necessary aspect of initial concept development. Visual observation of the surrounding environment of the Installation, determination, where applicable, of the continuity between new construction planning and existing development and ascertainment of the types of recommended materials and maintenance practices are influential factors in the analysis of site problems and the formulation of concept solutions. 7.9.3 Coordination (a) Interface with Applicable Construction Drawings
Landscape planting plans shall be coordinated with existing conditions and demolition plans, site layout, grading and drainage, utilities, architectural floor plans and elevations, and pertinent aspects of mechanical, plumbing, and electrical drawings for the locations of items such as compressors, fuel oil tanks, transformers, meters, light standards, and hose bibs. (b) User Requirements
Coordination of Corps of Engineers and Installation requirements shall be accomplished prior to initiation of design submittals. The designer shall consult with the local user and involved Installation personnel in order to substantiate the extent of design requirements and to provide planting proposals, which correspond with maintenance capabilities.
7-5
CHAPTER 8 WATER, WASTEWATER AND ENVIRONMENTAL PROTECTION INDEX 8.1 GENERAL 8.1.1 8.1.2
8.2
APPLICABLE PUBLICATIONS 8.2.1 Army/Air Force Basic References 8.2.2 Water Supply Systems 8.2.3 Water Supply for Fire Protection 8.2.4 Wastewater Systems PROJECT DEFINITION (10-15%) 8.3.1 Narrative 8.3.2 Water and Sanitary Site Plan CONCEPT DESIGN (30-35%) 8.4.1 Design Analysis 8.4.1.1 Water Supply Sources 8.4.1.2 Service Lines 8.4.1.3 Water Distribution Lines 8.4.1.4 Sanitary Sewers 8.4.1.5 Building Connections 8.4.1.6 Lift Station 8.4.1.7 Domestic and Industrial Wastewater Treatment 8.4.2 Concept Design Drawings 8.4.3 Environmental Permitting INTERIM DESIGN (50-60%) 8.5.1 Interim Design Analysis 8.5.2 Interim Design Drawings 8.5.2.1 Water Supply 8.5.2.2 Domestic and Industrial Water and Wastewater Treatment 8.5.2.3 Water Distribution and Wastewater Collection Systems FINAL DESIGN (UNREVIEWED 100%) 8.6.1 Final Design Analysis 8.6.2 Final Design Drawings 8.6.3 Draft Specifications 8.6.4 Environmental Protection READY TO ADVERTISE (100%) RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS 8.8.1 8.8.2 Mandatory Requirements Specific Requirements FINAL DESIGN (UNREVIEWED 100%)
8.3
8.4
8.5
8.6
8.7 8.8
8.9
TECHNICAL REQUIREMENTS 8.9.1 Standard Systems Criteria 8.9.1.1 Building Services 8.9.1.2 Fire Protection 8.9.1.3 Sewage Collection System 8.9.1.4 Treatment Plants 8.9.1.5 Seismic Provision
8-1
Fire Protection Using AFFF Systems Supplemental Design Criteria Water Supply/Water Distribution Wastewater Treatment and Disposal
8-2
This chapter presents general requirements for the preparation of plans, specifications, and design analyses for water supply and wastewater treatment systems. The general requirements for water and wastewater systems for US Army projects will generally follow the order of Unified Facilities Criteria (UFC), Military Handbooks (MIL-HDBK), Technical Instructions (TI), Engineering Instructions (EI), Technical Manuals (TM), industry organization standards as recognized in the listed documents for applicable publications, such as AWWA and WEF. US Air Force projects will generally follow the same criteria order as above, except after Military Handbooks and before the TI series, Air Force Instructions (AFI) will preceed the remaining list. The designer must always keep in mind that the listed publications and guidance above are minimum standards. Where local, state, and federal regulations (and sometimes Host Nation Standards) require a larger or more robust requirement, those regulations must be followed and supercedes the military requirements. Where details are left to the designer, standards dictated herein shall be applied. Specific design submittal requirements in this chapter supplement the requirements in Chapter 1,titled GENERAL INSTRUCTIONS. All required documents, including drawings and design analysis, shall be in accordance with Chapter 2, titled PRESENTATION OF DATA. 8.1.1 Water Supply Systems
Water supply systems include sources, pumping, treatment, storage, and distribution of water used for domestic, industrial, irrigation, and fire protection purposes. 8.1.2 Wastewater Systems
Wastewater systems include collection, pumping, treatment, and disposal of domestic and industrial wastes. 8.2 APPLICABLE PUBLICATIONS
Unified Facilities Criteria (UFC): UFC 3-600-01 Design: Fire Protection Engineering for Facilities
Military Handbook: MIL-HDBK-1005/7A MIL-HDBK 1005/16 Water Supply Systems Wastewater Treatment System Design Augmenting Handbook
MIL-HDBK 1005/17 Industrial Pretreatment Design and Nondomestic Wastewater Control Water System Design Documents-Military: TI 800-01 Design Criteria
8-3
TI 800-03 TI 814-01 TI 814-03 TI 814-10 TM 5-8l3-l TM 5-8l3-3 TM 5-8l3-4 TM 5-813-5 TM 5-8l3-7 TM 5-813-8 TM 5-8l3-9 TM 5-8l4-8 TM 5-814-9 ETL 1110-3-446 ETL 1110-3-465 ETL 1110-3-466 ETL 1110-3-484 ETL 1110-3-485 ETL 1110-3-481
Technical Requirements for Design-Build Water Supply Water Distribution Wastewater Collection Water Supply: Sources and General Considerations
Water Supply: Water Treatment Water Supply: Water Storage Water Supply: Water Distribution Water Supply for Special Projects Water Desalination Water Supply for Pumping Stations Evaluation Criteria Guide for Water Pollution Prevention, Control, and Abatement Programs Central Vehicle Wash Facilities Revision of Thrust Block Criteria in TM 5-813-5 - Appendix C Design and Construction of Water Meters and Their Appurtenances at New Army Facilities. Selection and Design of Oil/Water Separators at Army Facilities Aircraft Hangar Fire Protection Systems Fire Protection for Helicopter Hangars Containment and Disposal of Aqueous Film-Forming Foam (AFFF) Solution
Industry and Organizational Standards: IPC NFPA 20 NFPA 24 NFPA 291 NFPA 409 ETL 1110-3-466 International Plumbing Code, Latest Edition Centrifugal Fire Pumps Private Fire Service Mains and Their Appurtenances Recommended Practice for Fire Flow Testing and Marking of Hydrants Standard on Aircraft Hangars Selection and Design of Oil/Water Separators at Army Facilities
8-4
Standards for Sewage Works (Ten States' Standards), Latest Edition Design of Municipal Wastewater Treatment Plants (MOP 8), Latest Edition Water Treatment Plant Design (AWWA Pub., McGraw- Hill), Latest Edition Manual of Septic Tank Practice EPA 625/1-80-012 Disposal Systems Design Manual: Onsite Wastewater Treatment and
The project definition shall contain a narrative description and a water and sanitary site plan. Construction of new facilities and major expansions to existing water and wastewater systems must comply with the procedural requirements of the applicable permitting agency or agencies having approval authority. Each state also has a department for pollution control projects involving point discharges. All designs of water and wastewater systems should be coordinated with the appropriate regulatory agency at all stages of design. 8.3.1 Narrative
The narrative shall define the source of water for potable use and fire protection. The narrative shall also describe any pretreatment, treatment, and methods of wastewater disposal from the new facility. 8.3.2 Water and Sanitary Site Plan
The water and sanitary site plan shall show all existing water lines and sanitary sewers. The new water lines for building service and fire flow shall be shown from the point of connection to the existing water distribution system. All necessary valves, fire hydrants, ground storage tanks, pump stations, etc. shall be indicated. Building connections for wastewater shall be shown from the building to the existing sanitary sewer system or onsite treatment system. All necessary septic tanks, grease traps, oil/water separators, treatment plants, manholes, lift stations, force mains, etc. shall be shown. All pipe sizes shall be indicated. At this stage or earlier, the designer shall request a fire flow test(s) specifying exact hydrant locations required to flow and where residual pressure is to be measured. Request shall be furnished to COE project manager. 8.4 CONCEPT DESIGN (30-35%) Design Analysis
8.4.1
Base all new designs on the most economical plan consistent with the applicable criteria; i.e., Army Technical Manuals, Air Force Manuals, etc. Include in the design analysis any assumptions made or source of information if not included in manuals, guides, or instructions. The design analysis shall be sufficiently complete to clearly show project requirements and utility support capacity. Prepare outline specifications as directed in Chapter 3, SPECIFICATIONS.
8-5
8.4.1.1
The source of the potable water supply for domestic and industrial use and fire flow demand shall be identified in this submittal. If lawn irrigation is required, the source of water for the irrigation system shall also be identified in this submittal. Provide calculations indicating available supply and pressure versus required supply and pressure. If a pump, water storage tank, or any other peripheral equipment is required, provide calculations to support the selected pump size, storage tank volume, and sizes of peripheral equipment. Individuals experienced in fire protection systems must accomplish design of fire pumping stations. The designer shall determine in this submittal whether a fire pump station with or without a ground storage reservoir is required. 8.4.1.2 Service Lines
Service lines are the water lines connecting building piping to water distribution lines. The analysis for service lines shall show service line size, domestic demand, velocity and pressure drop between the water distribution line and building. 8.4.1.3 Water Distribution Lines
The water distribution system comprises the network of piping throughout building areas and other areas of water use or fire demand, and includes hydrants, valves, and other appurtenances used to supply water for domestic, industrial, and fire fighting purposes. If new water distribution lines are required to meet fire flow demands, a Hardy Cross or similar analysis shall be provided in the Design Analysis. This shall consist of a flow analysis based on fire flow test results from the nearest fire hydrants to the points of connection to the existing distribution system and fire flow demands developed from criteria contained in UFC 3-600-01. The flow through all lines shall be balanced by use of a Stet Cross analysis or other approved means. If the existing system is proven to be inadequate to supply the fire demand, revisions to the existing distribution system may be required. This will be documented even though it may not be part of the project. The designer shall request fire flow tests results through the Project Manager if not provided earlier. 8.4.1.4 Sanitary Sewers
New gravity sanitary sewers will be sized in this submittal. The design analysis shall show wastewater flows, velocities, pipe sizes, elevations, and pipe capacities. Where new sewage collection systems are to be connected to the existing system, the existing sewage collection system shall be checked to determine whether it has adequate capacity for the additional flow. If the existing system does not have sufficient capacity, it shall be revised to handle the increased flow. The design analysis shall contain a narrative description with all necessary calculations for new wastewater lift stations and force mains showing flows, velocities, component capacities, head requirements, detention periods, etc. The design analysis shall be prepared in accordance with TI 814-10. A design analysis is required for onsite sewage treatment and disposal systems (e.g. septic tank and tile field). The feasibility of an onsite sewage treatment and disposal system where buildings are remotely located and it is not economically possible to
8-6
connect to an existing wastewater collection system shall be determined. Coordination shall be made with the appropriate county sanitarian to determine soil percolation rates to use for sizing the tile fields. Permits for septic tank and tile fields are not generally required for Federal projects, but the criteria established by the local sanitary authorities is typically employed unless an appropriate justification can be cited. 8.4.1.5 Building Connections
Building connections are the sanitary sewers connecting the building plumbing system to the wastewater collection system. A design analysis of gravity building connections is not required if the same slope for the building plumbing can be maintained to the street line. If that slope cannot be maintained an analysis shall be provided to determine pipe slope. The minimum diameter pipe shall not be less than 6 inches. 8.4.1.6 Lift Station
If a lift station and force main are required to transport the wastewater from the building, a design analysis is required to show rational for pump selection and size of force main. 8.4.1.7 Domestic and Industrial Wastewater Treatment
Calculate the average and peak loadings for individual unit processes including hydraulic, organic, solids, etc. Provide detailed descriptions of proposed unit processes including type, size, capacity, supporting data, and calculations showing the degree of treatment expected in each unit process, as well as the overall treatment efficiency. Provide narrative discussion of controls, instrumentation, and proposed operating sequences or methods. Include discussion of features for operator safety and comfort. Provide narrative indicating that the treatment facility was designed to simplify operation and minimize maintenance. Provide calculations to support selected equipment and pipe sizes. Provide pollution control authority design requirements. 8.4.2 Concept Design Drawings
The water and sanitary site plan shall be adequately detailed to show new work and connections to the existing water distribution system and wastewater collection system. The proposed designs shall include sufficient details to obtain adequate concept cost estimates for all items such as lift stations, septic tanks, oil separators, etc. The invert elevations of all new and existing sanitary sewer lines and the top and invert elevations of all new and existing manholes shall be shown on concept plans. The water and sanitary site plans shall be on a minimum scale of l" = 30'. The designer shall provide any additional drawings other than those listed above which he considers necessary to show the intent of design. 8.4.3 Environmental Permitting
A separate section shall be provided in the design analysis entitled Environmental Permits. A separate sheet for each environmental permit contact shall be provided in the design narrative. The sheet shall be in a block format and contain the following information: Subject; Type Permit Required; Approving Agency and Address; Point-of-Contract and
8-7
Telephone Number; Fee; Agency Processing Requirements; and any Special Requirements or Information. See Figure 8-1 for an example. 8.5 8.5.1 INTERIM DESIGN (50-60%) Interim Design Analysis
The Interim Design Analysis shall include all items in the Concept Design Analysis and any necessary updates or revisions. Provide catalogue cuts, pump curves, and any other manufacturers information on selected equipment. 8.5.2 Interim Design Drawings
The following specific items shall be submitted, when applicable. 8.5.2.1 Water Supply
Provide detailed floor plans and sections of treatment plants and pumping stations with equipment layout, piping, and sufficient dimensions and elevations to physically locate all items of equipment, piping, etc. Provide hydraulic profiles. 8.5.2.2 Domestic and Industrial Water and Wastewater Treatment Provide detailed floor plans and sections layout, piping, and sufficient dimensions locate all items of equipment, piping, etc. control schematics.
Provide hydraulic profiles. of structures with equipment and elevations to physically Provide instrumentation and 8.5.2.3
Provide a site plan showing all existing and new valves, fire hydrants, manholes, pumping stations, laterals, meters, etc. Include sizes of all water lines, sanitary sewers, and force mains. Invert and rim elevations are required for all manholes. Provide profiles of gravity sewers. Double lines are required for profile piping. Provide details for connecting new lines to existing systems. 8.6 FINAL DESIGN (UNREVIEWED 100%) Final Design Analysis
8.6.1
The Final Design Analysis shall be a refinement of the Interim Design Analysis. Design analysis shall include all references for design assumptions. Design analysis shall incorporate all accepted comments from the previous design submittal. All pipe-sizing computations shall be included in analysis. Piping analyses shall show design flows, pipe sizes, friction factors, slopes, lengths, elevations where applicable, conducted quantity, and velocity in each line. Provide flow diagrams in the analysis. Determination of pump heads shall be based on complete takeoff of friction losses and static heads. Systems head curves are required for all pumping systems. Pumping stations with multiple pumps shall be provided with pumping curves for the individual pumps and any combination of possible pump operation that will occur.
8-8
8.6.2
Final plans shall be the refinement and completion of the interim drawings. All comments relating to interim or concept design shall be incorporated in the final drawings. Where crowded conditions exist due to close proximity of other phases of the work, sufficient sections and elevations shall be shown to indicate clearly the exact location of new facilities. The number of elevations and details shall be sufficient to allow construction and installation of the work without additional design work by the contractor. Where equipment connection details are shown, indicate all required valves, trim, gages, and fittings required. Coordinate with the specification requirements and make sure that valves, fittings, etc., that are specified to be furnished with each piece of equipment are included in the detail. Final plans shall show all pipe sizes. Catwalks, ladders, platforms, access panels, and doors required for operation and maintenance of equipment, valves, and accessories shall be detailed on the drawings. Performance characteristics for all items of equipment shall be placed in carefully prepared equipment schedules. Equipment characteristics specified in "Note" fashion, or in random locations on the drawings are not acceptable. Equipment characteristics selected shall not be restrictive to any one manufacturer but must be competitive among at least three major manufacturers. Manufacturer's trade names shall not be shown on the drawings. Electrical characteristics, horsepower ratings, classification of NEMA type, if applicable, and except in special cases, rotation speeds shall not be included in equipment schedules. Location of equipment and piping shall be completely coordinated with other features of the project; architectural, plumbing, mechanical, structural, electrical, etc. Profiles shall be provided for all new sanitary sewers and force mains. These profiles shall indicate elevations, depth of bury, and interfering utilities which may be encountered. Profiles for building connections may not be required depending on length of run, topography and state permitting requirements. Complete construction details of water and sanitary sewer utilities as well as layouts shall be required on final plans. A legend shall be provided on drawings to clearly differentiate between existing and new construction. Existing construction is generally indicated by light symbols and new construction is indicated by heavy black symbols. Existing construction data such as pipe sizes, elevations, valves, and fire hydrant locations, etc., pertinent to new construction shall be included on the drawings. 8.6.3 Draft Specifications
Marked-up guide specifications shall be included in this submittal. Specifications shall not be restrictive. Generally, the description shall be such that at least three major manufacturers can meet the specified requirements. Do not use trade names in the specifications unless a sole source authorization has been approved. The subparagraphs on "Electrical Work" shall be carefully coordinated with the electrical section of the specifications. There shall be no conflicts as to which section covers starters, controls, or wiring; and no conflicts as to the type of starters required for the individual items of equipment. 8.6.4 Environmental Protection
The appropriate UFGS Guide Specification section for Environmental Protection, shall be included in this submittal. A list of all required construction permits, existing environmental permits, and new environmental permits shall be included in this specification section.
8-9
All permits obtained by the user or required to be obtained by the user or designer shall be listed by title, permit number or form number, permitting agency, effective date and expiration date. The list shall include but is not limited to the following: Federal Aviation Administration Construction General Permit for New Stormwater Discharge State Wetlands Dredge and Fill Permit Construction Permit for Water Line Extensions Construction Permit for Sanitary Sewer Work Air Pollution Construction Permit Consumptive Use Permit for Water (Florida - water wells) A separate list in the same format as above will also be prepared for all permits to be obtained by the contractor. Permits to be obtained by the contractor include but are not limited to the Well Drilling Permit. 8.7 READY-TO-ADVERTISE (100%)
All final design drawings, specifications, and cost estimates will have incorporated comments from the preceding reviews before submittal as Ready- To-Advertise. 8.8 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS
TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs. 8.8.1 Mandatory Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development: a. The water and wastewater systems shall be designed and specified to the latest industry standards, codes, and Government regulations. The RFP shall ensure high quality, energy efficient equipment and systems with minimum maintenance. Design documents shall be submitted and reviewed prior to commencing work on any treatment system. b. 8.8.2 See TI 800-03 for additional mandatory requirements.
Specific Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria:
1. Include a paragraph describing the collection, distribution, and treatment system(s), any major features such as pumping stations, treatment systems for drinking water, domestic and industrial wastewater. Process flow diagrams shall be
8-10
submitted including descriptions for proposal for any telemetry or remote monitoring requirements. A description of environmental permitting requirements shall also be submitted in accordance with the requirements herein. The information presented in Figure 8-1 shall be submitted at a minimum. For projects that have discharge or disposal requirements, a narrative or discussion shall be provided describing the final fate of such disposal and environmental regulatory impacts. Designer shall provide a commissioning and acceptance plan to demonstrate compliance with the approved technical requirements. b. Partial Project Criteria:
1. Include a paragraph describing the pumping stations, any major features such as process and instrumentation diagrams (P&ID), unit processes, unit operations, emergency power generation requirements, and any environmental regulations that apply to the project. For projects that require a final discharge disposal, a submittal fully describing the final fate of the discharge and coordination with regulatory officials shall be submitted. On treatment plants or systems, list estimated capacities of equipment, types of equipment and number of each type of equipment. Include a preliminary floor plan showing possible locations of major equipment and maintenance clearances. Discuss control of the plant or systems and provide a commissioning and acceptance plan to demonstrate that the system functions as required without shortcomings. 2. Describe the pumps and pipe materials, and required coatings to be used on all piping systems. 3. Include an outline of the specifications to be edited. For specifications that are not available in the UFGS listing, an appropriate specification shall be written prior to the final project submittal for review and approval. The approved and revised as necessary equipment specification or other specification shall be included in the final unreviewed specifications submittal. c. Full Project Criteria: Final Plans (See previous description under 8.6 FINAL
1. DESIGN.)
2. Final Specifications (See previous description under 8.6 FINAL DESIGN.) NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements. 8.9 TECHNICAL REQUIREMENTS Standard Systems Criteria Building Services
8.9.1
8.9.1.1
(a) Water Service Lines. Provide exterior water service line to all new buildings from existing and/or new water distribution systems. Size building water service line to meet the peak building demand as
8-11
required in the IPC. The pressure drop through the service line will not exceed l0 psi or a velocity of 8 feet per second at the peak building demand. Provide a gate valve or service stop near the connection point to the distribution system. The designer shall insure that all state and local cross connection requirements have been incorporated into the design. (b) Building Connections (Sanitary). Building connections will be of either the gravity type or the force main type as required by the building site conditions. Gravity type sanitary sewers are preferable, if feasible, and will be constructed of 6-inch minimum size pipe on an appropriate slope to achieve a velocity (or equivalent) cleansing velocity of two (2) feet per second. Where gravity type building connections to a sanitary collection system are not possible, provide pneumatic ejectors or sewage pumps in the building or a lift station outside the building. The selection of pumps or ejectors will be based on the economy of initial installation. A design analysis of gravity sanitary sewers for building connections is not required if the same slope for the building plumbing can be maintained to the street sewer. However, if the slope cannot be maintained an analysis demonstrating maximum achievable velocity during peak flow must be provided with the proposed slope. Pipe diameter and slope must be shown on the drawings. Duplex units will be provided where ejectors or pumps are required. The capacity of each unit will be sufficient to handle the peak rates of flow. Other design characteristics will conform to TI 814-10. 8.9.1.2 Fire Protection
(a) Distribution Lines and Fire Hydrants. Provide distribution lines and additional fire hydrants, as necessary, in the building area in accordance with the applicable portions of TI 814-03 and UFC 3-60001. The residual flow pressures at design flows at fire hydrants will not be less than 20 psi. Water lines shall be installed parallel to streets and roads, but not under roadway pavements, except for crossings. The sum of the fire flow, 50% of the average domestic demand rate, and any industrial demand that cannot be reduced during a fire period determine the fire demand. Provide fire hydrants in accordance with TM-5-813-5, NFPA 24, and UFC 3-600-01. Any point of the building should be within 350 feet of at least 2 hydrants. Fire hydrants shall be installed with not less than a 6-inch connection to a supply line and be valved at the connection. (b) Building Sprinkler Supply Lines. Sprinkler supply lines shall be at least the size required by the National Fire Protection Association. The adequacy of the existing or proposed distribution system and sprinkler lines to meet the sprinkler and hose stream demands as indicated in UFC 3-600-01,Fire Protection for Facilities-Engineering Design, and a fire flow analysis or other approved means of analysis must justify Construction. Where required, augment the existing distribution system to provide at least a 15-pound residual pressure at the highest sprinkler heads in the building at design fire demands. Provide cutoff valves on the supply lines. These shall be located not less than 25 feet nor more than 50 feet from the face of the building, which they are to serve. They may be of either the post indicator type, or the rising stem and yoke type installed in a pit, as dictated by the proposed construction provided for that area. Use post indicator valves generally in grassed areas, and use the rising outside stem and yoke type installed in underground pits in paved areas. Fire pumping stations shall comply with UFC 3-600-01 and NFPA Codes 20, 24, and 409, as appropriate, and shall be designed by persons experienced in design
8-12
of fire protection systems. The design of a fire pump or series of fire pumps shall not exceed 1500 GPM each without approval of the Corps of Engineers. Provide standby fire pumps where required by NFPA 409. 8.9.1.3 Sewage Collection System
(a) Gravity Sewers. Where more than one building is involved, use gravity sewers. Design is to conform to the applicable requirements of TI 814-10. Size gravity sewers to discharge the expected peak rate of flow. Design pipes to run not more than 80% full, except that regardless of the design quantities, the minimum size of gravity sewers is 8 inches. Gravity sewers shall normally be laid on a sufficient slope to provide a velocity of at least 2.5 feet per second when the pipe is flowing full and 2.0 feet per second at the average rate of flow. Locate gravity sewers by the topography of the site to minimize excavation. (b) Force Mains and Sewage Lift Stations. Where more than one building is involved, if gravity type sewers cannot be provided, sewage pumps shall be installed in a sewage lift station constructed on the lowest terrain in the vicinity. Since force mains do not require a specific grade for satisfactory operation, they shall be constructed as straight, short, and shallow as possible. Routings for force mains shall generally follow existing right-of ways, roads, or utility corridors. In the Mobile District, force mains are generally installed a minimum of 30 inches below final grade. Force mains and sewage lift stations shall conform to the applicable requirements of TI 814-10. The capacity of the lift station shall be sufficient to handle peak rates of sewage flow, determined in accordance with TI 814-10. Sewage pumps must be designed to meet actual head conditions of the force main provided for the lift station. The design point on the pump characteristic curve shall be justified by plotting this curve against the system head-capacity curve. The system head curve shall be obtained by plotting the static lift plus the friction head at various flow rates. Where pumps operate in parallel or series, combined curves shall be provided. Intersection of characteristic curve with system head curve shall be the design operating point. Where appropriate, grinder-type pumps shall be considered. (c) Septic Tank and Tile Field. Design septic tanks and tile fields in accordance with Manual of Septic Tank Practice and applicable state criteria. When state criteria is not relevant, then use design manual EPA 625/1-80-012. Prefabricated septic tanks approved by the state or local authority may be used providing the minimum wall thickness is 4 inches and calculations are provided for structural soundness. (d) Oil/Water Separators. Oil/water separators shall be provided for process wastewaters in accordance with ETL 1110-3-466 for Army projects and as required by state and local regulators for Air Force projects. Separators shall be of the prefabricated type or built in place. Oil/water separators shall be designed to meet the effluent requirements for pretreatment by the EPA and/or applicable State Agency. The effluent from the oil/water separator shall be routed to a sanitary sewer or an industrial sewer. Oil/water separators shall be designed so that large quantities of storm water are not processed through the separator. Separators shall be installed to meet installation requirements for containment of hazardous wastes as required by the applicable state agency, the storm water pollution prevention plan, and the spill prevention and control plan. Overall project designs should
8-13
be coordinated in order to minimize peak flow rates into separators and to prevent any extraneous flow into a separator. Before designing in a separator into a project permission must be obtained due to environmental constraints at some bases. 8.9.1.4 Treatment Plants
Specific instructions for water treatment plants and/or wastewater treatment plants are provided in the Statement of Work. 8.9.1.5 Seismic Provision
All projects shall include appropriate provision for protection of piping, equipment, and underground utilities against damage from seismic events in accordance with TM 5-809-10, Seismic Design for Buildings and Air Force projects using the latest recognized civilian standard, such as ASCE. 8.9.1.6 Fire Protection Using AFFF Systems
Fire protection using AFFF Systems shall comply with the requirements of ETL 1110-3-481. Provide a means for containment of and disposal of AFFF foam solution runoff through coordination with Government personnel and the local environmental regulatory authority. Containment and disposal must meet the requirements of the applicable State Agency, and shall be a part of permitting requirements. Other options that can be approved by the installation and state regulatory agencies should be presented as economic alternatives before the 30% design is finalized. 8.9.2 Supplemental Design Criteria Water Supply/Water Distribution
8.9.2.1
(a) Water wells shall conform to AWWA Standard A-100; TI 814-01 and applicable State Public Health Department criteria for public water supplies. Specification for water wells shall be based current UFGS specification provided. (b) The designer through the Mobile District geologist (CESAM-ENGG) shall coordinate design of water wells. (c) Vertical turbine pumps larger than 5 hp shall conform to AWWA E-101 and the appropriate UFGS. (d) Design of water treatment plants shall conform to TI 814-02 and Mil-Handbooks as appropriate and any applicable State criteria for public water supplies; and as a minimum the Recommended Standards for Water Works (Ten States' Standards). (e) Small isolated facilities shall utilize a hydro-pneumatic pressure tank and, if appropriate, a ground storage reservoir as discussed below. Small systems shall normally be located in a protective building. Where permitted by the State, pitless well adapters may be used. Use of well pits is prohibited. (f) Supply and distribution piping shall comply with TI 814-03 and appropriate UFCs and UFGS. Piping materials shall be based on UFGS unless technical considerations require other methods.
8-14
(g) Water storage designs shall comply with UFC 3-600-01, TI 81401, and AWWA D100. Specifications shall be based on the appropriate UFGS. (h) Hydraulic analyses shall normally be made using a value of C = 100 for the roughness co-efficient; however, consideration should be given to the use of coefficients greater than 100 when specifying concrete or plastic pipe. Changes in coefficients from new pipe to an aged pipe should be considered to insure that excessive velocities are not generated in new piping by using only coefficients for aged pipe. (i) Fire hydrant branches shall not be less than 6 inches in diameter, shall be as short in length as possible, and shall have a gate valve and box. (j) Locate water lines at least l0 feet horizontally from a sewer or drain line. When required, a minimum horizontal separation of 6 feet can be allowed, but the bottom of the water line must be at least 12 inches above the top of the sewer pipe, unless state regulations require a more strict limitation. (k) Where water lines must cross sewers they shall conform to the requirements of TM 5-813-5, UFGS Guide Specifications for water lines, and applicable state criteria. (l) Water lines crossing railroads shall be installed in protective casings conforming to the requirements of American Railway Engineering Association (AREA), Volume 1. Design should specify method of construction for each particular site (i.e., ut vs. jacking). The designer shall obtain permits from the railroad authority, as required. Permit application procedure and submittal should occur as soon as practicable. (m) Water lines located in airfield pavement shall conform to the requirements of TM 5-813-5. (n) Control valves shall be provided on distribution systems in accordance with TM 5-813-5. (o) Air release and vacuum relief valves shall be provided in accordance with the requirements of TM 5-813-5. (p) Fire hydrants shall be provided in accordance with the requirements of TM 5-813-5;; NFPA 24, Outside Piping; and UFC 3-600-01. Hydrants should not be located closer than 25 feet to a building and should be located not more than 7 feet nor less than 6 feet from the edge of a paved roadway surface. Residual pressures at fire hydrants shall not be less than 20 psi when flowing at the desired rate. (q) Thrust blocking shall be provided in accordance with TM 5-813-5; ETL 1110-3-446 Revision of Thrust Block Criteria in TM 5-813-5, Appendix C, and the UFGS water lines specification. (r) Where the base distribution system is unable to provide the fire flow demand at the required residual pressure, the designer shall analyze the existing distribution system and provide pumping equipment and ground storage tanks, if necessary. A complete design analysis is required, including fire flow test data. Pumping stations shall conform to the requirements of NFPA 20, UFC 3-600-01, and TM 5-813-9. Pumping
8-15
stations for aircraft and helicopter hangars shall conform to UFC 3-60001, TM 5-8l3-9, and NFPA 409, except that fire pumps shall be diesel engine driven. Provide post indicating cutoff valves in accordance with NFPA 24. (s) Water for domestic purposes and fire protection for special projects such as reserve centers shall be provided in accordance with the requirements of TM 5-813-7. (t) Service lines to new buildings shall be sized to meet peak building demands in accordance with TM 5-810-5. Pressure drop between the connection to the distribution line and the building shall not exceed l0 psi at peak rate. Provide control valves, in accordance with the appropriate UFGS Guide Specification. (u) All water lines, water wells, and storage tanks shall be effectively sterilized with chlorine solution and tested bacteriologically safe in accordance with AWWA Standards and as specifically required by state and local drinking water regulations before placing them in service. See current index listing of the UFGS Guide Specifications. (v) Storage reservoirs shall be provided with cathodic protection when required. Questions on cathodic protection should be addressed to the Mobile District Cathodic Protection Specialist. Coatings and paint shall conform to state and federally approved coatings as approved for health concerns. An AWWA coating systems shall be specificed if project is beyond the regulatory boundaries of the state and federal environmental regulators. (w) Hydropneumatic Pressure Systems:
(l) Use at small activities where the demand is not enough to justify any other type of storage. Design the tank to meet the appropriate pressure vessel requirements. Provide air compressors, safety valve, and sight glass, to show the air/water ratio when diaphragm-type tanks are not practical. Typically, the tank should be designed as a branch connection to prevent excessive air entrainment in the distribution system. (2) Generally, use 20-psi pressure differential between high water level and low water level. (3) Provide duplex high service pumps to meet the peak 4-hour demand of 2.5 times average flow. When water well source is inadequate to provide peak 4-hour demand, investigate the feasibility of providing ground storage or a pressure tank equal to 40 times the well pump. 4) Tank capacity. Conventional tank capacity shall be based upon a withdrawal, in gallons, of 2-l/2 times the GPM capacity of the pump and a low-water level of not less than l0 percent of total tank capacity or 3 inches above top of tank outlet, whichever is higher. Table l indicates high water levels and withdrawals for efficient operation of tanks with bottom outlets and a l0 percent residual. Using the table, the tank capacity may be determined as per Example l: Example l: Determine the tank capacity when pump capacity is 150 GPM and tank operating pressure range is 40-60 psi.
8-16
Referring to table 1, the withdrawal from the tank is 24 percent of the tank capacity. Total tank capacity = 2.5 X 150 GPM = 1,562 gallons 0.24 TABLE I HYDROPNEUMATIC TANK HIGH-WATER LEVELS AND WITHDRAWALS Pressure Range (PSI) Capacity 20-40 30-50 40-60 50-70 60-80 High-Water Level (% of Total Tank Capacity) 43 38 34 32 28 Withdrawal (% of Total Tank 33 28 24 22 18
(5) Compressed Air. Compressed air is supplied for tank operation according to the tank capacities. For tank capacities up to 500 gallons, provide l.5 CFM. Provide 2.0 CFM for capacities from 500-3,000 gallons and each additional 3,000 gallons or fraction thereof. Quantities are expressed in CFM free air at pressure equal to the high-pressure maintained within the hydropneumatic tank. (6) Controls. The controls of a hydropneumatic system shall maintain the predetermined pressures, water levels, and air-water ratio within the tank. When duplex pumps are provided, controls shall start only one pump at a time; pumps shall be operated alternately. Pumps shall operate simultaneously only when a single pump cannot maintain the predetermined low pressure. Controls shall admit compressed air into the tank only when tank pressure at high-water level is below normal. (7) If required by the user/owner, provide a water meter on the service line from the pressure tank. (8) Provide a chlorine disinfection system for water to be consumed by humans. Size to provide l mg/l chlorine residual when flowing at the peak 4-hour rate. Consider using a hypochlorite feeding machine for intermittent pumping rates up to 200 gpm or when maximum chlorine demand is less than 3 pounds per day. When hypochlorite feeders are not practical and chlorine gas is the only reasonable choice for disinfection, due consideration must be presented regarding local, state, and federal requirements concerning storage or hazardous materials. (9) Refer to the publication "Handbook of Chlorination" by George White (Van Nostrand Reinhold) and manufacturer's literature for details of design of chlorination systems. (10) Diaphragm-type tanks shall be designed and sized in accordance with the manufacturers instructions. (y) Asbestos-cement pipe shall not be specified for water lines.
8-17
8.9.2.2
(a) Design of on site treatment/disposal facilities shall conform to applicable criteria published by the appropriate state regulatory agency and MIL-HDBK 1005/16. When appropriate, a "mound" system shall be considered where high water tables or impervious layers of soil exist. Other alternative systems may be considered when approved by the installation facility and environmental regulators. (b) Where soil conditions at the site are such that a septic tank/tile field system cannot be used, consideration shall be given to use of a septic tank subsurface sand filter system. Design must conform to the above referenced documents for septic tanks. (c) Gravity Sewers (TM 5-814-1) (l) Provide a minimum of 24" to 30" of cover over pipe.
(2) Manholes are required at the end of laterals and at each change of direction or slope. (3) Distance between manholes shall not exceed the following: Diameters less than 18" Diameters 18" and larger 400' 600'
(4) Drop connections are required at manholes when the invert of the inlet pipe is more than 18 inches above the manhole floor. (5) diameter. Minimum size for building connections is 6 inches in
(6) Sewers shall be laid with sufficient slope to ensure cleansing velocities (2 fps when flowing full or half full). (7) Capacity of building connections shall be based on fixture units. (8) Minimum size sanitary sewers between manholes shall be 8 inches in diameter. (9) Use Mannings formula for computing gravity flows in sewers. Use n = 0.013 for pipes 12 inches or smaller and n = 0.014 for pipe larger than 12 inches. (10) Deep sewers shall be analyzed for excessive loads using the equations of TM 5-814-1, Paragraph 12. (11) Selection of pipe materials shall consider structural loads, soil conditions, and characteristics of transported wastes. (l2) Design analyses are required for sizing all 8 inch and larger sewers. (13) Asbestos-cement pipe shall not be specified for gravity sewers or force mains.
8-18
(d)
(l) Force mains shall be analyzed for water hammer conditions. (2) Minimum size force mains where nonclog pumps are used is 4 inches. Smaller pipe sizes can be considered when grinder pumps are used. (3) Small lift stations shall be of the wet-pit, submerged-pump type. (4) Capacity of pumping stations shall be sufficient to handle maximum rates of flow when the largest pump is out of service. See TI 814-10 for determining pumping rates. (5) (6) Overflows shall not be provided. A complete design analysis is required.
(7) Force mains shall be provided with a minimum of 24" to 30" cover. (8) systems. Systems head curves are required for all pumping
(e) Wastewater treatment plant designs shall conform to MIL-HDBK 1005/16; applicable State criteria; and Recommended Standards for Sewage Works (Ten States' Standards). Designs shall be based on meeting NPDES discharge permit limitations for the site, as provided by the State or EPA, depending on who has authority. (f) Treatment plants for industrial wastes shall conform to MILHDBK 1005/17 and TM 5-814-8. Designs shall be based on meeting NPDES discharge permit limitations for the site or meeting owner of the final treatment systems requirements. (g) Wastewaters containing oils shall be treated in accordance with the requirements of local environmental authorities. Oil-water separators shall be provided on effluent lines from aircraft and vehicular wash racks for pretreatment prior to discharge to a central sewage collection system. Where central sewage systems are non-existent, package, coalescing type oil/water separators meeting State discharge criteria are required. Grit separators are required ahead of separators serving vehicle wash racks. Prior to design of separators, permission of Base personnel is required because of environmental constraints. (h) Special Requirements for Fire Pump Stations/Fire Booster Stations. A comprehensive transient analysis shall be performed and submitted for pumping systems required to provide water pressure and flow for sprinkler systems and/or standpipes. The analysis shall be a computerized model of the pipe, control and relief fittings, and pumps required by the A-E to support the fire suppression system being designed. A report describing the analysis procedures, control methods, need for corrosion control, etc., shall be submitted with the design analysis. As a minimum requirement, the following shall be included in the analysis:
8-19
(1) Pump start and stop against a closed (no flow) system such as motor or engine exercising only. (2) Single pump running with other pumps coming on line to supplement the single pump. (3) Pump(s) trip in a single run mode and a multiple pump trip with all pumps tripping at the same instance. (4) Pump(s) start and stop at intermediate design flow; e.g., 35 to 50 percent. (5) Analysis of all pressure relief or reduction elements such as air chambers, surge relief valves, by-pass, etc. All assumptions used to model the system shall be clearly explained. In addition, any physical phenomenon anticipated to occur shall be described so that Base operations personnel can be made fully aware of these phenomenons and take any appropriate actions required.
8-20
SUBJECT: Wastewater Treatment Plant Construction Permit PERMIT REQUIRED: Permit to Construct APPROVING AGENCY: Central Florida District, FDER (P.O.C.) Denise Judy or alt. Lee Miller ADDRESS: Central Florida District Department of Environmental Regulation 3319 Maguire Blvd., Suite 232 Orlando, FL 32803 Attn: Office of Domestic Permitting (407) 894-7555 FEE: $5,000 (Includes cost of both applications.)
PROCESSING: Two Applications -- 1) App. To Const. Domestic Wastewater Facility 2) App. To Const. Reuse/Land Application System *30 days to review plus public notice period plus any time needed to incorporate FDER changes* SPECIAL REQUIREMENTS: Controls for this facility are TSS 20 mg/L, BOD 20 mg/L, and N-NO3 12 mg/L. Construction permit good for up to 6 months after construction is finished. Can be extended during construction if time expires for $50 per extension, up to 5 years. Systems operating manual is required (Note: FDER says these manuals are usually disappointing, because they are normally only O & M manuals and not process controlbut have allowed it to suffice). The systems manual is required to be ready within the 6-month period that the construction permit is used to operated plan.
EXHIBIT 8-1
8-21
9.1
9.2 9.3
APPLICABLE PUBLICATIONS PROJECT DEFINITION (10% - 15%) 9.3.1 General Considerations 9.3.2 Charrette Reference Information CONCEPT DESIGN (30% - 35%) 9.4.1 General Considerations 9.4.2 Concept Design Analysis Narrative 9.4.3 Concept Design Drawings 9.4.4 Specifications INTERIM DESIGN (50% - 60%) 9.5.1 Interim Design Analysis Narrative 9.5.2 Interim Design Drawings 9.5.3 Specifications FINAL DESIGN (UNREVIEWED 100%) 9.6.1 Final Design Analysis Narrative 9.6.2 Drawings 9.6.3 Coordination 9.6.4 Specifications 9.6.5 Mandatory Requirements 9.6.6 Specific Requirements 9.6.7 Specifications READY TO ADVERTISE (100%) REQUEST FOR PROPOSAL (RFP) DEVELOPMENT REQUIREMENTS 9.8.1 Mandatory Requirements 9.8.2 Specific Requirements TECHNICAL REQUIREMENTS 9.9.1 Site Work 9.9.2 Masonry 9.9.3 Miscellaneous Metals 9.9.4 Thermal and Moisture Protection 9.9.5 Doors 9.9.6 Finishes 9.9.7 Rooms and Spaces for Utilities 9.9.8 Floor Drains and Slopes
9.4
9.5
9.6
9.7 9.8
9.9
9-1
9.1.1
This chapter states criteria, requirements, and guidance for architectural design. Specific requirements in this chapter supplement the requirements of Chapter 1, titled GENERAL INSTRUCTIONS. All required documents, including the drawings and the design analysis, shall be prepared in accordance with Chapter 2, titled PRESENTATION OF DATA. 9.1.2 Architectural Quality
The objective of the Corps of Engineers is to obtain attractive costeffective buildings which are designed using sound technical knowledge and which are constructed using recognized, good commercial building industry practices. The design shall incorporate those characteristics which will provide buildings with present and continuing utility, durability, and desirability, provide a safe and healthy environment, and which will be economical to maintain for the life of the building. 9.2 APPLICABLE PUBLICATIONS
The following publications shall be used to provide a complete design and meet all requirements of applicable codes and governmental requirements. Lead Design Manual TI 800-01 Design Build Manual TI-800-03 International Building Codes International Building Code, 2000 (as modified by UFC 3-600-01, dated 20 August, 2003). International Residential Code, 2000 (as modified by UFC 3-60001, dated 20 August, 2003). Supplemental Air Force Design Manual MIL-HDBK-1190 Facility Design Guide latest edition. Design Build Instructions Design Criteria
National Fire Protection Association (NFPA) NFPA, latest edition, applicable portions. Life Safety Code, NFPA 101, latest edition.
9-2
UNIFIED FACILITY CRITERIA (UFC) (UFC) 3-110, Design: Architectural UNIFIED FACILITY GUIDE SPECIFICATIONS (UFGS) Specifications are updated once a month. Instructions on Retrieving UFGS are covered in Chapter 3 SPECIFICATIONS Department of Army or Air Force Technical Manuals as applicable. Installation Design Guide as applicable. Requirements established by the installation Department of Public Works office (Army projects), Base Civil Engineer's office (Air Force projects), or the using agency. Requirements of state and local governmental agencies (health department, environmental agency, etc.) that are applicable. 9.3 PROJECT DEFINITION (10% - 15%) General Considerations
9.3.1
This submittal consists of one or more single line schematic floor plans which effectively indicate to the using agency that the function, circulation, and life safety issues have been assessed and can be met by the proposed design. At least one major elevation (preferable the front elevation) for each submitted building is required. A site plan is required to indicate the building orientation and circulation to the building entrances. The site plan shall be coordinated with the requirements of Chapter 4, titled SITE DEVELOPMENT. 9.3.2 Charrettes
When called for in the Scope of Work (SOW), the design process known as the "Charrette" for obtaining a schematic design shall be used as described in "The U.S. Air Force Project Manager's Guide to Project Definition" published by USAF/CE September 1994. Additional information on this design process is also available through the Air Force publication "An Overview of Project Definition - Project Definition Tools" on an Audio Visual Program, in 35 MM slides, on disk in Microsoft Power Point, in overhead view graphs, and with a briefing script that can be modified or abbreviated depending on the briefing forum. 9.4 CONCEPT DESIGN (30% - 35%) General Considerations
9.4.1
The minimum requirements for this submittal consist of floor plan(s) drawn to appropriate scale, fire protection information as required by the paragraph 9.4.3.10 titled Life Safety Analysis Plan, exterior building elevations, typical wall sections to indicate material usage and structure, and a design narrative as described in the paragraph 9.4.2. titled Concept Design Analysis. Additional drawings may be required at this submittal due to the complexity of the project (i.e., hospitals research facilities, blast resistant structures, etc.) to adequately describe the proposed design.
9-3
9.4.2
The following specific items shall be included when applicable: 9.4.2.1 General Description of the Project
State the purpose, function, and capacities in sufficient detail to delineate and characterize functional features and the desired image or visual appearance of the project. The narrative shall reflect the regional architecture as well as the visual characteristics of the existing facilities around the site. 9.4.2.2 Basis of Design Summary
Provide a summary of the Basis of Design including, but not limited to, the following: (a) State the building construction type and occupancy classification appropriate to the model code(s) in use. (b) State the design wind speed and velocity pressure used in the design. (c) (d) (e) (f) List the functional areas and their relationships. List the space allocations. State the energy conservation measures used in the design. State the noise control criteria established for the design.
(g) State any requirements for exterior finish materials and color selection. Indicate that consultation has occurred with the Installations Engineering Office, and that the Installation's program of architectural compatibility and the finish materials and colors selected for the project are in accordance with the installation's approved standards. (h) List special requirements such as EM1/RF1 shielding, security requirements, raised flooring, blast resistance, and fallout protection. 9.4.2.3 Technical Criteria
List the technical criteria used to guide the design work. 9.4.2.4 Building Organization Analysis
Submit, as necessary, any graphic design aids such as affinity drawings, spatial organization and relationship matrices, and space layout sketches in a sequential order, with sufficient narrative to indicate the reasoning and justification for major design decisions. Any provisions for future expansion shall be indicated, including schedules for phasing. 9.4.2.5 General Design Statement
The designer shall state the assumptions and rationale behind all major facility design decisions including, but not limited to, discussions of the following:
9-4
(a)
(b) The relationship to any surrounding natural or manmade environment. (c) (d) area. (e) Justification for not orienting buildings on the site so that the long axis of the building is in the east-west plane as required by the Architect/Engineer Instructions (AEI), Design Criteria. 9.4.2.6 Building Systems Analysis (Applicable only where no specific base criteria exists.) Include any substantiating material to support the selection of architectural materials or systems. Selection shall be based on a comparison of several alternate systems, which shall be presented. Indicate the economic decision process (comparative cost analysis method, life-cycle analysis method, or other techniques used) and any other rationale utilized in the selection of the various systems. It must be evident that the designer has adequately conceived the project as a whole and that the systems selected represent the maximum value that can be obtained for the intended result. The following are some, but not necessarily all, of the systems that should be investigated: (a) (b) (c) (d) (e) (f) (g) (h) (i) (j) (k) (l) Exterior wall systems. Passive solar systems. Fenestration. Roof systems. Interior partition systems. Openings in interior partitions (doors, windows, etc.). Ceiling systems. Floor systems. Integrated building systems. Noise and/or acoustics control measures. Special equipment such as trash handling systems and dock levelers. Vertical transportation systems (elevators). The interface with any contiguous traffic circulation. The visual impact of the facility with regard to the overall
9-5
9.4.2.7
Design Calculations
Submit complete calculations for the following: (a) Criteria. Gross building areas in accordance with the AEI, Design
(b) "U" values for each exterior construction assembly (walls and roofs). (c) (d) Calculations for toilet fixture count. Roof Drainage (Roof drain sizes and quantities, gutters and Downspout sizes)based on rainfall intensity at the project location.
9.4.3
9.4.3.1
When the main floor plans must be drawn in segments in order to comply with the requirements for the proper scales, provide a composite floor plan for each floor level. These plans shall show the following: (a) The general building layout showing exterior walls, interior partitions, and circulation elements (stairs, elevators, corridors, etc.) drawn to scale. (b) The identification of major areas and their functional relationship. (c) (d) (e) (f) sections. (g) 9.4.3.2 Overall building dimensions, out to out. Planning grid or column lines where applicable. Match lines indicating larger scale floor plan segments. Cross-references for enlarged floor plans and building Gross area tabulations.
Floor Plans
Provide a floor plan or floor plan segments, 1/8-inch scale minimum, 1/4-inch scale for Health Care facilities, for each floor showing functional arrangement and circulation elements, drawn to scale. In addition, the following shall be shown: (a) (b) (c) (d) level. (e) Planning grid and/or column lines. All major overall dimensions. Type of occupancy in each area. Finish floor elevations for each floor or change in floor Openings in walls (doors, windows, etc.).
9-6
(f) (g)
All major equipment. Furnishings layouts for typical rooms where required. (Reference Chapter 10 INTERIOR DESIGN for additional furniture placement plan requirements). Gross floor area tabulations on the first floor plan sheet. Cross-references for sections and details. Provisions for the handicapped where required. Reflected ceiling plans.
Roof Plan
Provide a roof plan showing the following: (a) (b) (c) (d) (e) (f) (g) 9.4.3.4 Planning grid and/or column lines. Overall dimensions. Indication of roof slope and drainage. Roof accessories (skylights, roof scuttles, etc.). Major roof-mounted equipment. Gutters and Downspouts. Roof Details.
Demolition Plans
Floor plans showing demolition work in sufficient detail to indicate all existing building materials and finish conditions are required for renovation and modification projects. Drawings shall be of sufficient detail to indicate "existing to remain," "existing to be removed," and new work and materials. Contractors are not required to site verify correctness or completeness of renovation and modification contract drawings and specifications, therefore, the drawings shall be complete with adequate detail and descriptions of existing materials, assemblies, and systems (type, thickness, quantity spacing, length, width, height, etc.) to enable the contractor to bid on the project. 9.4.3.5 Building Elevations
Provide building elevations showing the exterior design of all major elevations. Each elevation shall show the following: (a) (b) (c) (d) (e) Planning grid and/or column lines. Building masses and fenestration. Identification of all major building materials. Roof accessories, when visible in elevations. Major roof-mounted equipment.
9-7
(f) 9.4.3.6
Building Sections
Provide building sections as necessary to demonstrate the coordination of the structural, mechanical, and electrical systems. In addition, the following shall be shown: (a) (b) (c) (d) (e) (f) (g) (h) 9.4.3.7 Planning grid and/or column lines. Structural system. Changes in floor levels. Finish ceilings. Floor-to-ceiling and floor-to-floor heights. Floor elevations. Spaces to be used by the lighting and HVAC systems Adjacent grades.
Provide at least one unbroken, typical wall section (3/4-inch scale preferred). All sections shall be fully noted. These sections shall show the following: (a) (b) (c) (d) (e) (f) (g) 9.4.3.8 Structural system. Exterior wall and roof assemblies. Ceiling systems. Floor-to-ceiling and floor-to-floor heights. Floor elevations. Spaces to be used by the lighting and HVAC systems. "U" values through roof, walls and floors.
Finish Schedules
Finish schedules requirements are included in Chapter 10, titled INTERIOR DESIGN. 9.4.3.9 Details
In addition to the above requirements, show details of any significant design features and any sections necessary to demonstrate the required coordination of the various building systems. 9.4.3.10 Life Safety Analysis Plan
Unless specifically deleted by the SOW, a Life Safety Analysis Plan shall be submitted for each floor at the Project Definition Phase and
9-8
the Concept Design phase. Life Safety Analysis Plan sheets shall be referenced as architectural sheets and placed after the other Architectural Drawing sheets in the contract drawing submittal set. Include the following data and provide a legend for symbols used on the drawings: (a) (b) (c) (d) (e) (f) (g) (h) details. (i) (j) (k) 9.4.3.11 Type of occupancy. Type of construction. Fire/smoke compartments. Exit width calculations and number of exits. Location and rating of walls (1 hr., 2 hr., etc.). Door labels. Door hold open devices. Fire extinguisher and/or fire hose cabinet locations and Egress distances from most distant point to exit. Smoke proof doors. Exit lights. Coordination
Preliminary coordination with work of other technical disciplines shall be implemented as outlined in the paragraph 9.6.3 titled Coordination. 9.4.4 Specifications
Provide a basic outline in accordance with Chapter 3, SPECIFICATIONS. 9.5 INTERIM DESIGN (50% - 60%)
9.5.1
The Interim Design Analysis narrative shall include all items in the Concept Design Analysis narrative and any revisions necessitated by comments about the Concept Design submittal. In addition the following specific items shall be included when applicable: 9.5.1.1 Safety and Accessibility Requirements
Assure compliance in all aspects with the latest requirements of the following where applicable: (a) (b) (c) 9.5.1.2 Occupational Safety and Health Agency (OSHA). Uniform Federal Accessibility Standards (UFAS). Americans with Disability Act (ADA).
Graphics
9-9
Verify the graphics requirements with the Army Corps of Engineers Interior Designer (Chapter 10 INTERIOR DESIGN) and coordinate the system selected. This shall include graphics for the building(s) and the site.
9.5.2
These drawings shall include updated versions of the Concept Design Drawings. In addition, they include, but are not limited to, the following items: 9.5.2.1 Implementation of Concept Design Review Comments
Implement Concept Design review comments into the drawings and provide annotated comments (responses) describing the action taken for each comment (changes or additions to the design, reasons for the design, directions received from the user, etc.). 9.5.2.2 Building Plans
Provide plans for each floor, roof, and ceiling showing dimensions, functional arrangement, and equipment for all areas, including corridors, exits, stairs, and utility spaces. The relationship of the building to exterior access, vehicle parking, service areas, etc., shall be indicated on site plans. Individual treatment shall be given to special design or items involving deviation from normally accepted standards. All column lines shall be designated to aid in locating project components and all fire rated construction shall be indicated. Show indications of phased construction if required. Thoroughly crossreference section cut symbols on plans and elevations to detail sheets. Identify fire walls and smoke partitions. Include door and window numbers, space names, section cuts, etc. Complete door and window details to minimum of 60%. Identify all interior wall and partition types on floor plans and reference them to detail sheets showing construction, heights, fire ratings, and acoustical ratings. 9.5.2.3 Schedules
The drawings shall include door, window, and equipment schedules. Schedules need not be complete at this point, however, they shall be sufficient to indicate the door and window sizes and major equipment items. 9.5.3 Specifications
Provide a basic outline in accordance with Chapter 3, SPECIFICATIONS. 9.6 FINAL DESIGN (UNREVIEWED 100%)
9.6.1
The Final Design analysis narrative shall include all items in the Interim Design analysis narrative and any revisions necessitated by comments about the Interim Design submittal. In addition the following specific items shall be included when applicable.
9-10
9.6.2
Drawings (a) Complete to the extent required for the Ready To Advertise Submittal. Drawings are to be complete, except for incorporation of comments about this submittal. (b) Implement Interim Design review comments into the drawings and provide annotated comments describing the action taken for each comment (changes or additions to the design, reasons for the design, directions from user, etc.). (c) Insure that all details, sections, etc., necessary for the final documents have been added to the drawings and are complete and thoroughly cross-referenced.
(d) Complete all schedules. Insure that hardware sets have been added to the door schedule and coordinated with the specifications. (e) Complete all title blocks including drawing and file numbers, specification numbers, dates, and drawing titles. Information required from the Corps of Engineers shall be requested from the Project Coordination and Specification Section. (f) Insure that the drawing index is complete, accurate, and coordinated with the drawings and all other disciplines. 9.6.3 Coordination
All architectural work shall be coordinated with work of other technical disciplines. (a) Insure adequate above-ceiling space for ductwork, piping, lighting, structural members, etc. (b) (c) (d) Coordinate reflected ceiling plans with lighting and HVAC plans. Coordinate light switches with door swings. Coordinate electrical and mechanical drawings with architectural plans to assure proper power, gas, water, etc. for drinking fountains, kitchen equipment, etc. Coordinate with other disciplines to insure no there are no conflicts in roof drain, exhaust fan, louvers, and other similar item locations. Insure that all door louvers are coordinated with mechanical drawings and that no louvers are located in fire or smoke doors. Insure complete coordination between site work, walks and landscaping, water supply, sewerage, architectural, and electrical. Coordinate structural with architectural to insure framing at all roof openings.
(e)
(f)
(g)
(h)
9-11
(i)
Coordinate electrical and instrumentation to ensure utilities are provided for power operated doors and doors requiring electrical or electronic controls. Insure all rated wall penetrations received fire stopping or receives fire rated sealant around penetrations. Specifications
(j) 9.6.4
Provide a basic outline in accordance with Chapter 3, SPECIFICATIONS. 9.7 READY TO ADVERTISE SUBMITTAL (a) (b) (c) (100%)
Implement Final Design review comments into the drawings. Verify consistency between plans and specifications. Verify that all drawings are complete.
9.8 REQUEST FOR PROPOSAL (RFP) DEVELOPMENT REQUIREMENTS TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03. 9.8.1 MANDATORY DESIGN CRITERIA AND STANDARDS Although not all-inclusive, this paragraph contains Federal requirements that are established by executive orders, public laws, local requirements, and other directives. These requirements and all other Federal requirements must be reviewed and included, as applicable, in the RFP for each new project. a. Occupational Safety and Health Act Considerations. The Occupational Safety and Health Act of 1970 requires that safety standards issued by the Secretary of Labor be followed in the work place. Section 19 of this Act requires Federal agencies to establish and maintain effective and comprehensive programs, consistent with the standards issued by the Secretary of Labor. Those standards issued by the Secretary of Labor that affect the design of buildings are principally found in the General Industry Standards, 20 CFR 1910, Occupational Safety and Health Administration, Department of Labor, 200 Constitution Avenue, N.W., Washington, D.C. 20210. The design of all Army facilities that serve as places of employment will conform to, or be consistent with, all applicable standards published under the Occupational Safety and Health Act (OSHA) of 1970. In the case of an apparent conflict between this document and OSHA Standards, the standard providing the greatest degree of safety will govern. b. Master Plan. Master plan development will consider the planning goals and objectives of the communities surrounding Army installations. Review and coordination will be in accordance with AR 210-70, Intergovernmental Coordination of DOD Federal Development Program and Activities, 31 December 1984. Master plans and proposed designs for individual projects on installations located within the National Capital Region (NCR) will be submitted in accordance with instructions contained herein as directed by AR 415-15, Army Military Construction Program Development and Execution to the National Capital Planning Commission
9-12
(NCPC) and The Commission of Fine Arts (CFA). The Management Team should review the Master Plan and provide guidance in the RFP so that offerors will be knowledgeable about how the Master Plan applies. c. Physical Disabilities Background. Design and construction of Department of Defense buildings and facilities must ensure that they will be readily accessible to individuals with physical disabilities. Design and Construction must conform to the Uniform Federal Accessibility Standards (UFAS) and the Americans With Disabilities Act (ADA) of 1990. The Americans With Disabilities Act (ADA) of 1990 provides comprehensive civil rights protection to individuals with physical disabilities in the area of public accommodations, employment, State and local government services, transportation, and telecommunications. d. Basic Criteria Conform building construction to the fire resistance requirements, allowable floor area, building height limitations and building separation requirements of the IBC 2000 edition, except as modified by UFC 3-600-01 (Unified Facilities Criteria) dated 20 August, 2003. The RFP must reference codes and standards the offeror shall comply with. e. Egress and Safety to Life Comply with NFPA 101 for building construction related to egress and safety to life. For conflicts between the IBC and NFPA 101 related to fire resistance rating, conform to NFPA 101 and applicable criteria contained in UFC. 9.8.2 Specific Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria: 1. b. Follow Appendix B plus C Architectural.
c.
9.8.2.1 Check individual contract scope of work for level of RFP development and for specific design level requirements. 9.9 TECHNICAL REQUIREMENTS
In addition to the criteria in the following paragraphs, the architectural design shall comply with UFC 3-600-01. Materials and construction methods shall comply with the instructional notes inserted in the applicable Guide Specifications.
9-13
9.9.1
9.9.1.1
The finish floor of concrete floor slabs on fill shall be a minimum of 6 inches above the finished grade. 9.9.1.2 Access to Entrances
All stoops, steps, or similar required access to entrances that will normally be built by a building contractor as differentiated from sidewalks, driveways, etc., which are normally constructed by a paving contractor, shall be shown and detailed on the architectural drawings. Ramps complying with the requirements of ADA and/or UFAS shall be provided where required to allow access by the physically impaired. 9.9.2 Masonry Interior Walls and Partitions
9.9.2.1
Concrete masonry units (CMU) for interior masonry walls and partitions shall be not less than 6 inches in nominal thickness. Where split face units are used, provide smooth face units where concrete paving or flashing occurs and where items are attached to wall surfaces. 9.9.2.2 Coursing
Concrete masonry unit coursing generally shall be coordinated with door heights to minimize the need for cutting block. 9.9.3 Miscellaneous Metals
All access panels required to service mechanical items normally furnished and installed by the non-mechanical trades shall be shown on the architectural drawings. Insure that access panels, when required, are specified and detailed. 9.8.4 Thermal and Moisture Protection Roof and Wall Insulation
9.8.4.1
Except when required for refrigerated spaces, roof and wall insulation shall be drawn at a nominal thickness consistent with the insulation requirements of the particular building or project. The thickness of roof or wall insulation shall not be dimensional nor the thickness indicated on the drawings. General standards for insulation, as indicated in the applicable guide specification, require insulation thickness as determined by the established "U" value for total roof or wall thickness, and the type of material utilized. Unless specifically directed, "U" values shall be provided as indicated in the AEI, Design Criteria. Details shall allow for possible differences in insulation thickness. The exterior envelope of all cooled facilities shall have a continuous, positive vapor barrier of at least .06 permeance. The vapor barrier shall be part of a building moisture control plan. 9.8.4.2 Standing Seam Metal Roofs
All standing seam metal roofs shall be installed over a 40 mil, selfsealing, secondary water barrier over rigid insulation board (if attic
9-14
is to be used as a return air plenum) over a structural metal deck (for diaphragm action). Roof panels shall be a minimum thickness of 24-gauge steel or 0.040 aluminum. Vented ridge caps are not desirable due to potential leaks. Use locking type seams (as opposed to snaplock type) for hurricane and high wind areas. Roof specifications shall require that an independent registered roofing consultant be present to monitor the entire roof application. 9.8.4.2.1 Other Roofs For other roof types comply with the National Roofing Contractors Association standards. 9.8.4.3 Roof Slope
The minimum roof slope for built-up roofs shall be 1/4-inch per foot, however, the use of a "flat" built-up roof is discouraged except for facilities of unusual building configuration or extremely large areas. In no case shall a built-up roof slope exceed 2 inches per foot. Roof slope for standing seam metal roofs shall be 1:12 minimum, however, individual Installation/Command policy will dictate required slope for a particular base. 9.8.4.4 Sheet Metal
In all cases sheet metal for various elements used throughout a building shall be of the same basic metal. Atmospheric conditions shall be considered in the selection of exposed sheet metal. Different types of sheet metal that can cause accelerated corrosion (galvanic action) of either one shall not be placed in direct contact. Sheet metal used on roofs with concrete roof tiles shall not react with nor corrode excessively due to the concrete. 9.8.4.5 Gutters and Downspouts
When downspouts are required they shall not drain directly onto a walk or platform. When downspouts must occur at walks or platforms they shall pass through or under into underground drains or toward open ground beyond. Downspouts draining onto open ground shall be diverted using precast concrete splash blocks to prevent erosion. Use of interior downspouts shall be avoided wherever design permits. The use of scuppers should be maximized. Avoid built-in gutters behind fascia or parapet due to expansion/contraction of metal and surrounding material unless dictated per the Installations requirements. All gutters shall have leaf screens at locations susceptible to collection of leaves and other wind blown debris. 9.8.5 Doors Pedestrian Doors
9.8.5.1
All pedestrian doors shall be 7 feet 0 inches or 7 feet 2 inches high, except in family housing where they may be 6 feet 8 inches high. Door openings shall, in general, be 3 feet 0 inches wide, except for special purpose doors, toilet rooms (except for handicap) or closet doors in family housing, for instance.
9-15
9.8.5.2
Doors to Rooms
Doors to rooms shall be of adequate size to accommodate the installation and removal of furniture and equipment installed therein. 9.8.5.3 Exterior Doors
Except in underground structures and floors above the first story of multi-story structures, doors to boiler or mechanical rooms, doors from power rooms, generator rooms, and doors from similar areas should be to the outside of the building only. Electrical closet and air handling room doors may open to the building interior. 9.8.5.4 Special-Purpose Doors
Special-purpose doors such as rolling and coiling doors shall be adequately designed to safely resist the design wind pressure. Rolling and coiling steel or aluminum doors shall be designed so as to permit operation of the doors at maximum wind velocities defined in the area where used. 9.8.5.5 Finish Hardware
When selecting finish hardware carefully read the "Notes to Specifier" for the hardware specification Section 08710, Door Hardware. Hardware shall then be selected from BHMA and ANSI standards. Except for items not listed by BHMA or ANSI manufacturer names and catalog numbers shall not be used in hardware schedules. All cylinders shall have 7 pins. As base and installation requirements regarding provision of cylinders and keying vary, provision of these items must conform to individual requirements of base or installation on which the project is located. 9.8.5.6 Hardware Set Designations
Hardware set designations shall be listed in the Door Schedule in preference to locating on the floor plans. Specification Section 08710, Door Hardware, shall provide the necessary hardware set designation numbers, plus description and function of each hardware item included in the Hardware Set. 9.8.5.7 Return Air Louvers
Overall size of return air louvers located in doors shall be included in the Door Schedule. Minimum bottom rail dimension shall be 10 inches and the minimum stile dimension shall be 5 inches. 9.8.5.8 Door and Window Schedules and Types
Door and window schedules and types shall be indicated on the contract drawings. 9.8.6 Finishes Acoustical Plaster and Acoustical Tile
9.8.6.1
The use of acoustical plaster is discouraged. In electronics and communications facilities in which avoidance of dust is a major consideration acoustical treatment shall be limited to acoustical tile or gypsum wallboard with non-dusting characteristics.
9-16
9.8.7
Rooms and spaces for utilities, including mechanical and electrical equipment rooms, shafts, chases, and chimneys, shall be indicated on the Concept Design drawings, even though their exact size and location is undeterminable at the Concept Design stage. At times the technical and servicing requirements of the required equipment necessitate increases in the areas allocated in the Concept Design drawings. A reasonable increase in area for utility spaces will be authorized and will specify the extent of increase allowed. If an increase in area cannot be authorized, information shall be furnished by the Corps of Engineers advising which interior areas cannot be authorized and which interior areas must be rearranged or reduced. 9.8.8 Floor Drains and Slopes
Floor drains and slopes, hose bibbs, and shower heads shall be shown on the architectural drawings as well as on mechanical drawings, and shall be closely coordinated. All floors in areas requiring drains shall be sloped toward the drains.
9-17
10.1
Scope Overview CID Procurement Criteria Review Reviews and Revisions of Interior Design Projects
10.2
SID/CID REQUIREMENTS AND INFORMATION 10.2.1 Hard Copy SID/CID Deliverable Format Requirements 10.2.2 Digital Copy SID/CID Deliverables 10.2.2.1 Digital CID File Structure 10.2.3 Computer Software Requirements SID SPECIFIC INSTRUCTIONS 10.3.1 SID Deliverable Matrixes 10.3.2 SID PPTO Projects 10.3.3 SID D-B RFP Projects 10.3.3.1 Instructions for Writing RFP Section 01010 Design Criteria 10.3.3.2 Unified Facility Guide Specifications for D-B RFP 10.3.3.3 Color Schedule 10.3.3.4 Room Finish Schedule 10.3.3.5 D-B RFP Color Boards 10.3.4 Instructions for Writing the SID/CID D-B RFP Section 01012 Design After Award CID SPECIFIC INSTRUCTIONS 10.4.1 CID Deliverables 10.4.2 Master CID MS Excel Folder 10.4.3 Editing the Master CID Ms Excel Folder 10.4.4 Editing MS Excel Workbooks and Worksheets 10.4.5 Editing the Table of Contents Link Worksheet 10.4.6 Editing the Section Title Page 10.4.7 Alphanumeric Location Codes 10.4.7.1 Workbook Alphanumeric Location Codes 10.4.8 Editing Illustrated Order Forms (IOF) Worksheets 10.4.8.1 Information Provided on the IOF Worksheets 10.4.9 Editing the Furniture Systems Worksheets 10.4.10 Editing the Project Title Page Worksheet 10.4.11 Editing the Table of Contents Worksheet 10.4.12 Editing the Best Value Statement Worksheet 10.4.13 Editing the UNICOR Waiver Worksheet 10.4.14 Editing the SID/CID Narrative Worksheet 10.4.15 Editing the Point of Contract Worksheet 10.4.16 Editing the Location Code and Cost Estimate Worksheet 10.4.17 Editing the Manufacturers List Worksheet
10.3
10.4
10-1
10.5
ASSEMBLING THE RECORD COPY CID 10.5.1 Add Bookmarks to Section Title Pages 10.5.2 Adding Bookmarks to Illustrated Order Forms 10.5.3 Electronic Signatures for the Record Copy 10.5.4 Default settings Adobe.PDF Record Copy ADOBE ACROBAT READ DRAWINGS AND DRAWING BOOKMARKS 10.6.1 Adding and Bookmarking Acrobat Read Drawings 10.6.2 Adding and Bookmarking Individual Room Placement Plans FURNITURE SYSTEMS 10.7.1 Furniture System Requirements During the Design Phase 10.7.2 Furniture Systems Requirements During the Construction Phase 10.7.3 Editing CID Ms Excel Furniture Systems Workbook 10.7.4 Workstation Finish Sample Boards 10.7.5 Workstation Location Codes 10.7.6 Editing the Ms Excel Manufacturer Worksheet 10.7.7 Editing Fabric and Finish Worksheet 10.7.8 Editing Typical Workstation Worksheets 10.7.9 Editing UFGS Section 12705 Furniture Systems CONSTRUCTION CONTRACTOR INSTRUCTIONS FOR D-B SUBMITTALS 10.8.1 Full D-B Project Criteria 10.8.2 Nominal and Partial D-B Project Criteria 10.8.3 Pre-Definition Conference 10.8.4 50%, 100% AND Final Design Submittals GLOSSARY OF TERM AND DEFINITIONS FURNITURE COST GUIDELINES U.S. ARMY SPACE UTILIZATION GUIDANCE
10.6
10.7
10.8
10-2
EXHIBITS 10-1a 10-1b 10-1c 10-2a 10-2b 10-2c 10-2d 10-2e 10-2f 10-3a 10-3b 10-3c 10-3d 10-3e 10-3f 10-3g Two Categories for Interior Design Services Project Delivery Process CID Procurement Criteria Review SID/CID Binder Labels SID/CID Binder Material, Finish & Color Sample Boards SID Digital Drawings and Specification Deliverables CID Digital Drawings and Specification Deliverables Final CID Electronic Binder Folder/File Structure Software Requirements Project Specific SID Matrixes SID PPTO Deliverable Matrix SID D-B RFP Section 01010 Design Criteria Matrix Color Schedule for D-B RFP Section 01010 Room Finish Schedule for the D-B RFP Section 01010 Example of a Finish Schedule I Drawing SID/CID D-B RFP Section 01012 Design After Award Matrix Project Specific C ID Matrixes CID PPTO Deliverable Matrix CID D-B RFP Section 01010 Design Criteria Matrix Master CID MS Excel Folder of Workbook Files Opened Workbook Section Title Page Illustrated Order Form (8-1/2 x 11) Location Codes and Cost Estimate Adobe.PDF Project Folder and Files Adobe Acrobat Digital CID Book Format Composite Furniture Placement Plans and Room Bookmarks Furniture Systems Workbook SID/CID D-B Contractor Deliverables After Award of the D-B Contract Not Used Furniture Cost Guidelines Space Utilization Guidelines GSA Best Value Determination Guidelines
10-4a 10-4b 10-4c 10-4d 10-4e 10-4f 10-4g 10-4h 10-5a 10-5b 10-6a 10-7a 10-8a
10-3
10-4
Two Categories for Interior Design Services Structural Interior Design (SID) is the selection, specification and sampling of all the buildings interior features exposed to view in the finished construction. The SID submittal will include SID material/finish samples, interior floor plans, and detail drawings showing finish placement, finish schedules, interior signage schedules and material specifications. The SID is purchased and installed by the General Construction Contractor using Military Construction (known as MILCON, MCP, MCA) Funds. Comprehensive Interior Design (CID) is the development and documentation of a very large consolidated procurement furniture package developed during the design phase of a project and implemented during the construction phase of a project. The CID is the selection and illustration of all furnishings (interior and in some cases exterior furnishings) required to outfit a facility. The CID includes market research narratives and best value determination statements, samples of furniture finishes, furniture placement plans, illustrated order forms and a comprehensive cost estimate. The CID is to be fully coordinated with the SID, architectural layout, and building engineered system designs to ensure a fully integrated SID/CID project is developed to meet User/project requirements. The CID design, like the SID design, is funded with MILCON funds when the CID is documented as part of the project requirements described in the DD 1391. However, procurement and installation of the CID package is funded with operations & maintenance (O&M) funding requested by the User Group and funded by their Command. Although packaged in a book set the SID and CID are two separate and distinct projects when executing them. Project Delivery Process Price Performance Trade Off(PPTO) When the PPTO project delivery process is used, 100% of the SID/CID will be developed by a single interior design source in the prescribed formats discussed herein. The single source may be either a government in-house interior design source or an Architecture-Engineering (A-E) interior design source. Design Build Request for Proposal (D-B RFP) When the D-B project delivery process is used, the SID/CID project becomes a "two-step" process and will require the services of two different interior design sources to develop the SID/CID in the prescribed format herein. Step 1: During the first step, either a government or A-E interior design source will provide nominal (10%-35%), partial (35%-50%) or full (100%)SID/CID design criteria. Two sections within the D-B RFP will require Interior Design criteria and instructions. The two sections are (1) Section 01010 Design Criteria and (2) Section 01012 Design After Award. Step 2: The second step occurs after award of the RFP D-B contract. During the design phase after award of the D-B contract, the D-B Contractor's interior design source will
CID
D-B RFP
10-5
respond to the D-B RFP SID/CID instructions provided in Sections 01010 and 01012. When the design phase of the project is complete, 100% SID/CID submittals will be completed as well. 10.1.3 CID Procurement Criteria Review As early as possible and before starting a PPTO or D-B RFP project, a CID procurement criteria discussion is to be held in conjunction with the facility design criteria review meeting. Answers to the following questions are to be used to develop the overall project solicitation instructions and possible bid options for development and installation of the CID. Exhibit 10-1c Review Questions CID Procurement Criteria Review Will a CID package be part of the project design? (See the DD 1391) Will the CID be government procured, contractor installed? Will the CID be installed after the building is complete? Which Contracting Group will buy the furniture? Will systems furniture be procured with the building and the remaining CID procured by the User under a different action? District Project Management District Project Architect/Engineer District Interior Designer A-E Interior Designer A-E Project Manager User Major Command Representative Installation Contracting Specialist if not using General Services Administration
Attendees
10.1.4 Reviews and Revisions Reviews of SID/CID projects are to be performed by the Government regardless of the project delivery process. Chapter 10 is to be used by the Government reviewer as the basis for the SID/CID technical review comments. Revisions and updates will require hard copy and digital copies of the SID/CID to be refreshed and resubmitted at the next formal submission unless otherwise required by the reviewer. It is the responsibility of the in-house interior designer or A-E interior designer to request the return of SID/CID binders for updating and revision. Revisions will incorporate accepted comments and provide updated information as the project proceeds to the next phase of design.
10-6
Some Air Force Major Commands require in-process updating to revise finishes that were disapproved at the formal submittal level. Their requests are to be met. 10.2 SID/CID REQUIREMENTS AND INFORMATION SID/CID projects shall always be "packaged" and delivered as a book set but are two distinct products and shall not be cross-referenced. Both SID and CID packages shall use a hard copy and digital format. Ninety percent (90%) of the SID/CID project will be developed and reviewed electronically. The remaining ten percent (10%) will be hard copy. The hard copy products are the SID/CID binders and Color Boards. 10.2.1 Hard Copy SID/CID Deliverable Format Requirements
Hard copy deliverables for both SID/CID projects will use the same presentation format for binders and color boards. The SID/CID binders become the book set envelope. The binders will hold the hard copy SID/CID color Boards and the digital project data (CD-ROM). Do not merge the SID and CID color samples together on the same board. Building related finishes are packaged separately and stand alone from furniture related finishes. Requirements for SID/CID binders and color boards are shown in Exhibits 10-2a and 10-2b. Exhibit 10-2a Size Features SID/CID Binder and Labels Three Ring Binders to be 8-1/2" x 11"(210 x 280 mm) Inside pocket inserts for CD-ROM submittals and review comments Clear outside cover and spine for project label inserts Outside Cover and Spine % Design Phase, Volume Number (i.e. Vol.1 of 3) "Structural" or "Comprehensive" Interior Design title Project Title Project Location Date Design Agents or A-E Firm and Design Build Contractor Typical side mark distributions are (EN-DR), (BCE), (Resident Office)(User) etc. The project specific distribution list may be obtained from the Project Manager.
Project Identification
10-7
Photos of Samples
SID/CID "Material, Finish & Color" Sample Boards Color Boards shall be an 8-1/2" x 11" module Fold out color boards should have a maximum spread of 640 mm (25-1/2). Room/Area Color Scheme or Furniture Category Project name, Project Location, no dates Actual samples only Duplications of samples are not required. Label samples consistent with drawings, specifications and illustrated order forms (IFO) codes Photos are not allowed on any project including MILCON medical projects.
10.2.2 Digital Deliverables for SID/CID Projects This paragraph provides a general list of SID/CID Deliverables and general guidance for developing these deliverables. Digital deliverables for SID projects are shown in Exhibit 10-2c. The CID digital deliverables are shown in Exhibits 10-2d. Computer software requirements are discussed in paragraph 10.2.3. Furniture Systems drawings and specifications requirements are discussed in paragraph 10.7. Exhibit 10-2c SID Drawings SID Digital Drawings and Specification Deliverables Building related floor plans, floor patterns plans Building related elevations and details Finish Schedules Interior signage plans and schedules Based on DoD Tri-Services CADD Standards SID Sheet Letter I UFGS 09915 Color Schedule (exterior and interior) Carpet, Resilient Floor Coverings, Ceramic Tile, Terrazzo, industrial floor coatings Wall base (all kinds) Wall paint, wall coverings (all kinds) Ceiling Tiles, Grid, Ceiling treatments Plastic Laminates, solid surfacing Auditorium Seating (Fixed) Blinds or attached Widow Treatments Stage Curtains and Hardware Visual Communication Boards Trim, Signage, Operable Doors, Toilet Partitions, Lockers Built-in Casework Elevator Cab interior finishes Based on DoD Tri Services Standards Unified Facility Guide Specifications (UFGS) are used. Contact EN-DW for specification software. Use UFGS Section 09915 Color Schedule to list all SID
Specifications Standards
10-8
finishes, colors and manufacturers in lieu of putting this information on the I or A drawings. Jewel Box & *EN-DW will provide the title block CD-ROM Labels *EN-DW will consolidate all building related drawings *EN-DW will press the CD-ROM and add the labels The Ready To Advertise (RTA) CD-ROM (building related contract (drawings & specifications) may be requested from *EN-DW and submitted in the inside pocket of the SID binder. * EN-DW= Mobile District Engineering Divisions Project Support Section
10-9
Exhibit 10-2d
CID Digital Drawings and Specification Deliverables Based on DoD Tri-Services CADD Standards, I Drawings. Composite Furniture Placement Plans (FPP) are working drawings showing all furniture systems and freestanding furniture and equipment specified in the CID package. FPP validates the building layout ensuring the furniture and equipment within the room functions to meet User requirements. All furniture items and furniture systems will be identified with a location code that is fully coordinated with the CID package discussed in paragraph 10.7 Room numbers are to appear on the FPP drawings. The FPP drawings, showing the proposed furniture layouts are to be at a scale of 1:100 (1/4 inch = 1 foot), (1/4 inch = 1 foot,) unless otherwise specified. Coordination notes referencing the electrical plans are to be added to FPPs to locate Power, Voice and Data (PVD) connections/junction box locations as they relate to CID items. See UFGS Section 12705 Furniture Systems for shop drawings submittal requirements detailing furniture systems designs and installations. Artwork Placement Plans are to show typical elevation drawings dimensioning the vertical and horizontal location of the artwork. If large quantities of artwork are specified such as for medical projects, provide these drawings in a separate stand-alone electronic folder and name the folder Artwork drawings. Provide working drawings and Adobe.PDF drawings in the 100% CID. Other Drawings: Provide detailed drawings related to items that require cutting and fitting and are not being installed during the building's construction. Provide any necessary instructions on the Illustrated Order Form (IOF) for that item(s). Provide working drawings and Adobe.PDF drawings on the 100% CID CD-ROM. See Paragraph 10.4 for developing FPP drawings into the required Adobe.PDF files and inserts.
Use UFGS Section 12705 Furniture Systems when specifying and bidding Furniture Systems is required. Illustrated Order Forms (IFO) are used to specify freestanding furniture and equipment. IFO formats are discussed in paragraph 10.4. Label the CID CD jewel box and CD with the project information used on the hard copy SID/CID binders. Unlike the RTA SID CD-ROM, the Ready to Procure (RTP) CID CDROM (furniture related contract) is consolidated and pressed by the projects Interior Designer of Record will be submitted in the inside pocket of the CID binder. EN-DW will not be
CID Specifications
10-10
10.2.2.1
The digital CID data used to create the "electronic CID binder" shall be organized in a file structure to differentiate between Portable Document Files (Adobe.PDF), CADD files, and MS Excel files. The Master Adobe.PDF Folders can be linked together to facilitate easy viewing between Adobe.PDF SID electronic data submitted and coordinated through EN-DW and will not appear in the CID CD-ROM. The CID file structure shall be as follows: Exhibit 10-2e Final Electronic CID Binder Folder/File Structure
PROJECT FOLDER
#1 SUB-FOLDER
CID PROCUREMENT FORMS (RECORD COPY) Adobe.PDF Read Only submittal of the comprehensive CID MS Excel files. Submitted @ 35%,50%,100% & Final Design
#2 SUB-FOLDER
Adobe.PDF Read Only Drawings of the .dwg or .dgn files. Submitted @ 35,50 100% & Final Design Do not merge Ms Excel Files in this folder.
Provide sub-folders for Artwork drawings And Interior Signage drawings when part of the CID.
#3 SUB-FOLDER
Adobe.PDF Read Only Image of the Hard Copy Color Boards. Submitted @ Final Design
#4 SUB-FOLDER
CID MS Excel Folder Working files of all the CID MS Excel files (00-Project Title Page.xls thru 17-Window Treatments.xls) Submitted @ Final Design
#5 SUB-FOLDER
CID CADD Drawings Folder All FPP Working files Submitted @ Final Design
10-11
10.2.3
SID and CID digital deliverables are to be developed and viewed using five (5) computer software programs with no exceptions. The five software programs relate to: (1) CADD drawings, (2) Unified Facility Guide Specifications (UFGS), (3) CID procurement data (other than drawings), (4) viewing the SID/CID Record Copy and (5) writing the digital data to CDs. All digital data files shall be delivered in a format that is directly readable and compatible with the CADD, MS Excel and Adobe Acrobat software and platforms without conversions. Exhibit 10-2f 1. CADD Working Drawings Software Requirements SID/CID working CADD drawings shall be developed in the latest version of AutoCAD (.dwg) or Microstation (.dgn). Customer requirements will dictate which software version to use. AutoCAD is the preferred CADD program for developing CID (furniture related) drawings. SID specifications will be edited using SpecsIntact software. Contact the office of EN-DW to obtain project specific software programs available for downloading. CID Procurement Ordering data shall be developed in the latest version of MS Excel (.xls). The required 18 editable working files are ready for copy and downloading on the Mobile District Public FTP web site. The Website address is ftp://ftp.sam.usace.army.mil/pub. Open the folder marked "INTERIOR DESIGN" for the editable CID .xls files and copy to your hard drive. The SID/CID digital record copy shall be developed and viewed in the latest version of Adobe Acrobat Read/Write portable document format (Adobe.PDF). Working CADD drawings are to be "printed" in black and white (no color output) Adobe.PDF format. CID MS Excel.xls files are to be "printed" in the Adobe.PDF format. Write CDs using Easy CD Writer written in "Data/Data CD" platform. Don't use Direct CD with DVD driver to write the CD. Write to CD-Recordable discs. Do not write digital data information using DIRECT CD with .udf or .ulf extensions". No additional drivers or programs shall be installed on the hard drives of reviewers. Projects submitted in .udf or .ulf extensions will automatically be disapproved. All submittals are to be directly opened and viewed through AutoCAD or Microstation, MS Excel and Adobe Acrobat Read software programs.
2. Unified Facility Guide Specifications (UFGS) 3. CID Procurement Ordering data (Other than drawings)
5. CD's and Jewel Box General Notes For CID Digital Files
10-12
10.3 SID SPECIFIC INSTRUCTIONS This paragraph gives instructions for developing SID criteria and assembling sequence of the SID package for the PPTO and the D-B RFP project delivery process. A matrix is provided for each project delivery process to summarize submittal deliverables. Carefully read and follow the instructions before beginning a project. SID submittals will run concurrent with the architectural submittal regardless of the design delivery process. 10.3.1 SID Deliverable Matrixes There are four matrixes to use for SID projects. The project delivery process used for the project solicitation will determine which SID matrix to use. The Exhibit 10.3a list the project specific SID Matrixes.
Exhibit 10.3a Project Delivery Process Project Specific SID Matrixes Matrix Description SID PPTO Deliverable Matrix Gives the sequence of assembly Gives Format requirements and Project Phase specific submittal requirements. Not all projects will have a formal 65% design review phase. If that is the case, those items may move to the 100% submittal phase. MILCON Medical Projects will follow this matrix.
SID D-B RFP Section 01010 Design Criteria" Matrix Gives the sequence of assembly Gives Narrative requirements It is important that the User be involved in the development of the interior design criteria to ensure their project requirements are fully integrated into the D-B RFP solicitation. The D-B Contractor will only provide what is required of him/her after the award of the contract SID & CID D-B RFP Section 01012 Design After Award" Matrix Gives the standard clause to cut and paste into D-B RFP "Section 01012 Design After Award". The standard clause may require modification to meet project specific requirements. A project specific requirement may include the purchase and installation of the CID.
PPTO
Exhibit 10.3b
D-B RFP
Exhibit 10.3c
D-B RFP
Exhibit 10.3g
It is important to reference paragraph 10.4 for CID PPTO and D-B RFP project specific criteria to ensure coordination of SID and CID products.
10-13
10.3.2 SID PPTO Projects SID PPTO projects will require 100% of the SID to be developed by one interior design source. During the project development process, the project interior designer will be required to write the SID CD-ROM. The CD will be submitted in the front pocket of the SID binder at each submittal phase. These preliminary contract documents will be submitted in the Adobe.PDF Read Only format. When the project is complete and Ready to Advertise (RTA) all the contract drawings and specifications, including SID drawings and specification, will be sent to the Mobile District. The Districts project support section, EN-DW, will write the final RTA Project CD-ROM. The project interior designer will be required to obtain copies of the RTA CD-ROM from EN-DW and include it in the front pocket of the SID Binder before the final SID binders are distributed. EXHIBIT 10.3b
SID-PPTO Deliverable Matrix This applies to MILCON Medical Projects * Hard Copy Presentation ** Digital Data Presentation
10%15% S-2 30%35% S-3 50%60% S-4 100% S-5 RTA S-6
ITEM
DESCRIPTION
1. 2.
* COVER SHEET/SPINE LABEL * TABLE OF CONTENTS (SID) Include the CID table of contents if part of the "packaged book set". ** NARRATIVE of SID OBJECTIVES (printed to a Adobe.PDF file) *INTERIOR FINISHES-COLOR BOARDS * INTERIOR SIGNAGE-COLOR BOARDS
X X
X X
X X
X X
3. 4. 5. 6.
X X X
X X X X
X X X X
X X X X
**DRAWINGS- Floor plans, Room Finish Schedule, etc. (Black and White out put Adobe.PDF format) **INTERIOR SIGNAGE ILLUSTRATIONS PLANS AND SCHEDULES (Black and White out put Adobe.PDF format) ** UFGS SPECIFICATIONS (printed to the Adobe.PDF format) ** Ready to Advertise (RTA) CD with all drawings and specifications. Obtain from EN-DW.
7.
8.
9.
10-14
10.3.3 SID D-B RFP Projects The SID D-B interior designer two sections are: RFP Section RFP Section RFP project delivery process requires the project to edit two sections of the D-B RFP solicitation. 01010 Design Criteria 01012 Design after Award
The
Coordination of interior design information with architectural and engineering narratives is critical and necessary to ensure no overlapping or conflicting criteria occurs in the D-B RFP. 10.3.3.1 Instructions for Writing D-B RFP SECTION 01010 DESIGN CRITERIA" When developing the SID design criteria in a D-B RFP title the paragraph Structural Interior Design. Narratives within this paragraph should discuss the following objectives: SID objectives for health safety and welfare SID Color Scheme objectives and aesthetic goals Project specific criteria The Color Schedule (Exhibit 10.3d) Preliminary Room Finish Schedule (Exhibit 10.3e) Interior Signage Requirements Exhibit 10-3c provides guidance the sequence of the paragraphs and relate only to Structural Interior Design. The project interior designer, project architect and other engineering disciplines that address finishes are to fully coordinate the SID selections and placement of materials, color, textures and patterns with the customer to ensure complete customer satisfaction. Compare and coordinate all SID information with the architectural and engineering design criteria to eliminate conflicts and/or redundant design criteria. Ensure that all exposed building related materials and fixtures requiring finishes are addressed. 10.3.3.2 Unified Facility Guide Specifications (UFGS) for D-B RFPs When edited UFGS are part of the D-B RFP solicitation the interior designer is to complete to the fullest extend possible UFGS Section 09915 Color Schedule and supporting UFGS. When UFGS are NOT provided in the D-B RFP to establish minimum quality and performance characteristics, add quality minimums to the a modified Color Schedule and included it in the Structural Interior Design criteria D-B RFP Section 01010 Design Criteria. For example, add the minimum face weight, yarn type and carpet construction method in the Carpet paragraph to establish a basis for quality such as (CPT-1: 32 oz, tufted, graphic pattern, 100% solution dyed nylon; Manufacturer Shaw, Style number 6087, Color 800 Blue). When UFGS are NOT provided in the D-B RFP, list the UFGS by Section number and title and require the D-B Contractor to edit them during the design phase after award.
10-15
For example:
x.x.x Unified Guide Specification Requirements
The Contractor shall edit and submit the following specifications as defined in D-B RFP Section 01012 Design After Award: UFGS UFGS UFGS UFGS UFGS UFGS UFGS UFGS UFGS Section Section Section Section Section Section Section Section Section 06580a 09310a 09510a 09650a 09680a 09915a 10100a 10260a 10440a Solid Polymer Fabrication Ceramic Tile Acoustical Ceilings Resilient Flooring Carpet Color Schedule Visual Communication Boards Wall and Corner Protection Interior Signage
10.3.3.3 Color Schedule SID materials, finishes and colors not discussed or required in the D-B RFP Section 01010 Structural Interior Design criteria may not be provided by the Construction Contractor during the construction phase of the project without additional funds and a "change order". Therefore, it is important that a edited version of the UFGS Section "09915 Color Schedule" and UFGS list be included in the RFP design criteria to ensure as much information about the quality, material, finish and color of interior finishes is provided in the solicitation. A modified "cut and paste" version of the UFGS Section 09915 Color Schedule is provided in Exhibit 10.3d. Project interior designers are to edit this schedule fully to ensure the SID is fully integrated in the D-B RFP solicitation. 10.3.3.4 Room Finish Schedule A preliminary Room Finish Schedule is be provided in the D-B RFP Section 01010 Structural Interior Design criteria and used in combination with the Color Schedule to further define the SID in the D-B RFP. Providing a preliminary Room Finish Schedule in a graphic form is more efficient than using narrative. The Room Finish Schedule shall be edited to establish minimum finishes for each room type within the facility. The Room Finish Schedule may be a table like the cut and paste one provided in Exhibit 10.3e or it may be a drawing as illustrated in Exhibit 10-3f. If a drawing is used, verify that other drawings are part of the D-B RFP solicitation. To establish minimum finish requirements indicate floor, wall base, walls and ceiling finishes if a table is used. The Color Schedule may be used include specific details needed to establish additional minimum finishes for casework, interior signage, crown moldings, tile patterns and other details. 10.3.3.5 D-B RFP Color Boards
SID color boards are only required on D-B RFP project using 100% project criteria. The interior designer will not need to develop SID color Boards when only nominal or partial criteria is used in the D-B RFP.
10-16
EXHIBIT 10-3c
SID-D-B RFP Section 01010 Design Criteria Matrix * Hard Copy Presentation ** Digital Data Presentation NOMINAL PROJECT CRITERIA 10%-30% PARTIAL PROJECT CRITERIA 35%-50% FULL PROJECT CRITERIA 100% X
ITEM
Description/sequence of information included in the RFP "Section 01010 Design Criteria See Exhibit 10-3b when Full SID Project Criteria is used in the D-B RFP. Full project criteria will include 100% SID Color boards and SID binders, drawings and specifications. Interior Design Narrative. Provide D-B RFP SID narratives that address the following objectives in this sequence: x.1 The SID objectives and general description/parameters of the interior color scheme.
1. * **
1. **
1.a **
X 1.b ** x.2 Discussion of special spaces and finish requirements of these spaces; discussion of details of finishes required such as crown molding, chair rails, flush mounted corner guards etc. to further explain the Color Schedule and Room Finish Schedule. x.3 Discussion of interior signage plan that addresses the major signage categories (building directories, floor directories, room/office identification, safety signs, graphic symbols, visual communication and display boards, corridor numbering and other project specific interior sign requirements. x.4 Color Schedule. Completed UFGS 09915A Color Schedule if specifications are included in the RFP. Reference this specification in the RFP "01010" to coordinate SID criteria. -Orx.4 "Cut/paste" and edit Exhibit 10-3d Color Schedule and include it after the discussion of the interior signage. (ITEM 1.c-above) x.5 Room Finish Schedule. To fullest extent possible complete a Room Finish Schedule to indicate the level of finishes for all rooms in the project. The Room Finish Schedule can be placed as a table in "Section 01010 Design Criteria" after the Color Schedule or it can be a developed as a drawing. Insert the Standard CID Clauses directly after the Room Finish Schedule Table. (See Exhibit 10-3a).
1.c **
2. **
3. **
4. **
10-17
Exhibit 10-3d Color Schedule for D-B RFP Section 01010 --------------Cut and paste into the Section 01010 -----------------------remove the gray shading------x.x.1 COLOR SCHEDULE This section covers only the color of the exterior and interior materials and products that areas exposed to view in the finished construction. The word color as used herein includes surface color, pattern and texture. Requirement for quality and method of installation are covered in other appropriate sections of the specifications. Specific locations where the various materials are required or items not designated for color in this RFP shall be determined after the award of the Design-Build Contract. The color schedule lists the colors, patterns, and textures required for exterior and interior finishes, including both factory applied and field applied colors. x.x.2 REFERENCE TO MANUFACTURERS COLOR Where color is shown as being specific to one manufacturer, an equivalent color by another manufacturer may be submitted as a deviation and acceptance is required. Manufacturers and materials specified are not intended to limit the selection of equal color from other manufacturers. x.x.3 Exterior Walls Exterior wall colors shall apply to exterior wall surfaces including recesses at entrances and projecting vestibules. Conduit shall be painted to closely match the adjacent surfaces color. Wall color shall be provided to match the colors listed as follows: a. b. c. d. e. f. g. h. Brick: [___] Mortar: [____] Paint: [____] Concrete Masonry Units (Integrally Colored): [____] Metal Wall Panels, Hardware, and Associated Trim: [_] Insulation and Finish System: [____] Precast Concrete: [____] Glass and Glazing: [_____]
x.x.4 Exterior Trim and Miscellaneous Finishes Exterior trim shall be provided to match the colors listed below. a. b. c. d. e. f. g. h. i. j. k. Doors and Door Frames: [___] Windows (million, sash. Trim, and sill): [____] Wood Stain: [____] Fascia: [____] Downspouts, Gutter, Louvers, and Flashings: [____] Handrails: [___] Soffits and Ceilings: [______] Signage: [____] Overhangs: [______] Caulking and Sealants: [______] Stamped Concrete:[ ]
10-18
x.x.5 Exterior Roof Roof color shall apply to exterior roof surfaces including sheet metal flashings and coping, mechanical units, roof trim, pipes, conduits, electrical appurtenances, and similar items. Roof color shall be provided to match the colors listed below. a. b. c. d. e. Metal: [____] Shingles: [____] EPDM: [____] Terra Cotta Tiles [% of colors] Roof Penetrations [Match roof color]
x.x.6 Interior Floor Finishes Flooring materials shall be provided to match the colors listed below. a. b. c. d. e. f. g. h. i. j. k. l. m. n. o. Carpet: [____] Carpet Tile: [_____] Vinyl Composition Tile: [____] Sheet Vinyl: [___] Raised Pattern Rubber Tile: [____] Stair Treads, Kick Strips, and Risers: [____] Quarry Tile: [____] Ceramic Tile: [_____] Porcelain Tile: [_____] Terrazzo Tile: [_____] Grout: [_____] Plastic Laminate: [______] Static [Dissipative] [Conductive] tile: Concrete: [____] Raised Floor Manufacturer: [_____]
x.x.7 Interior Base Finishes Base materials shall be provided to match the colors listed below: a. b. c. d. e. f. g. h. i. j. k. l. Resilient Base And Edge Strips: [____] Quarry Tile: [____] Ceramic Tile: [___] Porcelain Tile: [____] Grout: [____] Coved Sheet Vinyl: [_____] Glazed Structural Units: [______] Prefaced Concrete Masonry Units: [_____] Brick: [____] Mortar: [____] Painted: [____] Wood: [____]
10-19
x.x.8 Interior Wall Finishes Interior Wall color shall apply to the entire wall surface, including reveals, vertical furred spaces, grilles, diffusers, electrical and access panels, and piping and conduit adjacent to wall surfaces unless other wise specified. Items not specified in other paragraphs shall be painted to match adjacent wall surface. Wall materials shall be provided to match the color listed below. a. b. c. d. e. f. g. h. i. j. k. l. x.x.9 Paint: [_____] Vinyl Wall Covering: [____] Fabric Wall Covering: [_____] Ceramic Tile: [____] Ceramic Tile Grout: [____] Acoustical Wall Covering: [_____] Brick: [____] Metal Liner Panels: [_____] Glazed Structural Units: [____] Prefaced Concrete Masonry Units: [_____] Mortar: [_____] Columns: [_____] Interior Ceiling Finishes
Ceiling color shall apply to ceiling surfaces including soffits, furred down areas, grilles, diffusers, registers, and access panels. Ceiling color shall also apply to joist, underside of roof deck, and conduit and piping where joists and deck are exposed and required to be painted. Ceiling Materials shall be provided to match the colors listed below. a. b. c. d. Acoustical Tile and Grid: [___] Paint: [_____] Structural Framing: [_____] Metal Deck: [______]
x.x.10 Interior Trim Interior trim shall be provided to match the colors listed below. a. b. c. d. e. f. g. h. i. j. Doors: [_____] Door Frames: [_____] Windows (mullion, sash, trim and stool): [____] Window Sills: [_____] Fire Extinguisher Cabinets: [____] Handrails: [_____] Ladders: [______] Metal Stairs: [______] Wood Stain: [______] Wood Base, Wood Chair rails, Wood Crown Molding:
[_____]
10-20
x.x.11 Interior Window Treatments Window treatments shall be provided to match the color listed below. a. b. c. d. e. x.x.12 Horizontal Blinds: [Wood/Metal] Vertical Blinds: [____] Drapery Hardware: [_____] Roller Shades: [_____] Electric Shades: [______]
Interior Miscellaneous
Miscellaneous items shall be provided to match the colors listed below. a. b. c. d. e. f. g. h. i. j. k. l. Toilet partitions and Urinal Screen: [_____] Casework: [____] Reception Counter Tops and Base: [_____] Interior Signage Message Color: Interior Signage Background Color: Lockers: [____] Corner Guards: [_____] Operable Partitions: [____] Electrical Device Cover Plates and Panels: [____] Casework: [______] Shower Curtain: [______] Auditorium Seating: [_____________]
Exhibit 10-e Room Finish Schedule for D-B RFP Section 01010 ------cut and paste into Section 01010 ------------------------------x.x.x Preliminary Room Finish Schedule.
NOTE: This preliminary Room Finish Schedule provides a basis for material, finish and color placement. Further development of this schedule is required after the award of the contract. This Room Finish Schedule is to be used in conjunction with other design criteria and schedules in this contract. ROOM NAME FLOOR BASE WALLS CEILINGS REMARKS
10-21
10-22
10.3.4.
Instructions for Writing the SID/CID D-B RFP SECTION 01012 DESIGN AFTER AWARD"
The standard clause used in the D-B RFP Section 01012 Design After Award is in Exhibit 10-3g. This standard clause is a "bridge" clause because is involves both the SID and CID instructions to the D-B Construction Contractor. Some modification to this clause may be needed to meet project specific requirements. For example, if a CID is not required, then revise the standard clause by deleting the CID submittal requirements. EXHIBIT 10-3g SID/CID-RFP Section 01012 Design After Award Matrix ** Digital Data Presentation -------Cut and Paste-------The standard clause to use in the RFP "Section 01012- Design After Award. x.1 The Contractor shall provide the SID and CID in accordance with 2002 Chapter 10 Interior Design of the Mobile District Design Manual. Instructions to the Contractor are provided in paragraph 10.8 and Exhibit 10.8a
ITEM
10-23
10.4
This paragraph gives information and instructions for developing CID criteria and assembling sequence of the CID package for the PPTO and D-B RFP project delivery processes. A matrix is provided for each project delivery process to summarize submittal deliverables. Carefully read and follow the instructions before beginning a project. Exhibit 104a provides a summary of the CID matrixes to use. When a CID is part of the D-B RFP design process and the D-B RFP Sections 01010 Design Criteria and Section 01012 Design After Award requires CID information and standards clauses previously discussed. Paragraph 10.4.2 thru 10.4.17 gives specific step-by-step instructions and development sequence of the digital CID package. The electronic CID package will begin with the documenting the procurement information in MS Excel workbooks and end with the MS Excel workbooks transposed into a Adobe.PDF files and which are then assembled into an Adobe.PDF folder that is opened and viewed through Adobe Reader. Carefully read and follow the instructions before beginning a CID project. CID submittals will run concurrent with the architectural submittals regardless of the project delivery process. 10.4.1 CID Deliverables There are four matrixes to use when a CID is part of the overall project delivery process. The project delivery process used for project development will determine which CID matrix to use. Exhibit 10.4a list the project delivery process and corresponding CID Matrix to use.
10-24
Project Specific CID Matrixes Matrix Description CID PPTO Deliverable Matrix Gives the sequence of assembly of the CID CD-ROM Tells what information is to be provided and the format the information is to be provided. Not all projects will have a formal 65% design review phase. If that is the case, those items may move to the 100% submittal phase. Use this matrix for MILCON Medical projects. CID D-B RFP Section 01010 Design Criteria" Matrix Gives the sequence of assembly of CID narratives Gives the level of information that is to be provided when writing the D-B RFP Section 01010 Design Criteria". It is important that the User be involved in the development of this criteria to ensure their project requirements for "outfitting" the building are included in the D-B RFP solicitation. Based on the CID Criteria Review comments, the D-B RFP Design Criteria shall also provide requirements for the procurement and installation of the CID package. SID & CID D-B RFP "Section 01012 Design After Award" Matrix Gives the standard clause to use when writing the D-B RFP Section 01012 Design After Award". This is a "bridge clause and combines SID/CID requirements into one standard clause that gives instructions to the D-B Contractor. This standard clause may have to be modified to meet project specific requirements if a CID is not part of the project. SID-CID "D-B Contractor Response to the RFP" Matrix Gives the sequence of assembly of the CID presentations and package Tells what information is to be provided and when it is to be provided during the design phase after award of the D-B Contract. This Matrix also tells what format the information is to be provided in after award of the D-B contract. If the client/User Group is installing the CID package, including furniture systems (prewired) workstations, all furniture system related drawings should be indicated in the SID contract drawings with the note "FOR INFORMATION ONLY". Reference 10.7 for furniture system drawing and specification requirements. If the D-B contractor is installing the CID project specific clauses require the Construction Contractor to supply the installation of the CID, it is the responsibility of the project interior designer to ensure Government/Contractor obligations are clearly stated in the D-b RFP and Bid Options and Costs are defined in the D-B RFP.
10-25
EXHIBT 10-4b
ITEM
CID BINDER (Hardcopy) Note: Insert CD into inside front pocket of the binder. * BINDER COVER SHEET AND SPINE LABEL * TABLE OF CONTENTS (SID/CID) * PRELIMINARY FURNITURE MATERIAL, FINISH AND COLOR SAMPLE BOARDS * FINAL FURNITURE SAMPLE BOARDS Sub-Folder #1 Record Copy CID Procurement Information Ms Excel files transposed to Adobe.PDF format PROJECT TITLE PAGE TABLE OF CONTENTS CID BEST VALUE STATEMENT UNICOR WAIVER SID/CID NARRATIVES POC LIST CODES & COST ESTIMATE MANUFACTURERS LIST ACCESSORIES SECTION TITLE PAGE PRELIMINARY ACCESSORIES ILLUSTRATED ORDER FORMS (IOF)(one IOF) ACCESSORIES IOF (All items specified) AV SECTION TITLE PAGE AV IOF CHAIRS SECTION TITLE PAGE PRELIMINARY CHAIRS IOF (one IOF) CHAIRS IOF (all chairs used on the project) DESK SECTION TITLE PAGE PRELIMINARY DESK IOF (one IOF) DESK IOF FILES & STORAGE SECTION TITLE PAGE PRELIMINARY FILES & STORAGE IOF (one IOF) FILES & STORAGE IOF TABLES SECTION TITLE PAGE PRELIMINARY TABLE IOF (one IOF) TABLES IOF FURNITURE SYSTEMS SECTION TITLE PAGE FURNITURE SYSTEMS IOF EQUIPMENT SECTION TITLE PAGE PRELIMINARY EQUIPMENT IOF(one IOF) EQUIPMENT IOF BEDDING SECTION TITLE PAGE BEDDING IOF WINDOW TREATMENT SECTION TITLE PAGE WINDOW TREATMENT IOF X X X X X X X x X X X
1. 2. 3. 3A. **
4. 5. 6. 7. 8. 9. 10. 11. 12. 13. 13A. 14. 15. 16. 17. 17A. 18. 19. 19A. 20. 21. 21A. 22. 23. 23A. 24. 25. 26. 27. 27A. 28. 29. 30. 31.
X X X X X X X
X X X X X X
X X X X X X X X X
X X X X X X X X X
X X X
X X X X
X X X X X X X X X X X X X X X X X X X
X X X X X X X X X X X X X X X X X X X
X X X
X X X X X X X X X X X X X
X X X X X
10-26
Sub Folder #2 Record Copy CID Composite FPP Drawings Adobe.PDF To be viewed using Adobe Acrobat Read Furniture Placement Plans Furniture Systems Plans Furniture Systems Product/PVD List Sub-Folder #3 Record Copy MASTER CID SAMPLE BOARDS Adobe.PDF To be viewed using Adobe Acrobat Read
10%15% S-2
30%-S-3 35%-S-4 X X
50%65% S-5 X X X
100% S-6 X X X
RTP
X X X
**
35%-S-4 S-6 Title Section Page-MARKED FOR INFORMATION ONLY-NOT FOR SHOP DRAWING APPROVAL 36. SID Material, Finish and Color Boards Adobe.PDF 37. CID Fabric and Finish Color Boards Adobe.PDF * Note if Artworks and Interior Signage are part of the CID provide record copy and working drawings in digital separate folders. 35. ** Sub-Folder #4 Working Files Ms Excel Folder of all the CID WORKBOOKS To be viewed using MS Excel 00-Project Title Page.xls 01-Table of Contents.xls 02-Best Value Statement.xls 03-UNIOCR Waiver.xls 04-SIDCID Narrative.xls 05-POC List.xls 06-Codes&Cost.xls 07-Manufacturer's.xls 08-Accessories.xls 09-AV.xls 10-Chairs.xls 11-Desks.xls 12-Files&Storage.xls 13-Tables.xls 14-Furniture Sys.xls 15-Equipment.xls 16-Bedding.xls 17-Window Treatments.xls Sub-Folder #5 Working Files Composite FPP Drawings To be viewed using AutoCAD or Microstation All CID CADD drawings
10%15% S-2
30%-S-3
50%65% S-5
100%
RTP
X X X
10%15% S-2
30%-S-3 35%-S-4
50%65% S-5
100% S-6
RTP
38. 39. 40. 41. 42. 43. 44. 45. 46. 47. 48. 49. 50. 51. 52. 53. 54. 55. **
X X X X X X X X X X X X X X X X X X
10%15% S-2
30%-S-3 35%-S-4
50%65% S-5
100% S-6
RTP
56.
10-27
EXHIBIT 10-4c
CID-RFP Section 01010 Design Criteria Matrix Summary ** Digital Data Presentation -----CUT AND PASTE--Standard clauses to use in the RFP "Section 01010- Design Criteria x.1 The CID has been fully developed and ready for procurement. The Contractor is to coordinate building changes with the USER and the CID package. All changes must be coordinated with the User. The User will be responsible for updating the CID based on building related changes. X.1 The Contractor shall be responsible for the CID requirement analysis survey to determine the furniture needs of the User. The Contractor will develop the CID package in accordance with the Mobile District's Design Manual 2002 Chapter 10 Interior Design. The Government will provide the brand(s)names of furniture to use in the CID package after award of the Design Build contract. Furniture selected and specified shall have a current GSA contract or be from UNICOR. Typical CID items to be specified are: Accessories, Artwork, Planters, Plants Audio Visual support, carts, project screens Chairs(all kinds) Desk (all kinds) Files & Storage (all kinds) Furniture Systems Tables (all kinds) Equipment, TV. Refrigerators, Washer/Dryers Bedding, all Dormitory Room furniture, Sheets, Bedspreads Window Treatments, cubicle curtains, shower curtains NOMINAL PROJECT CRITERIA 10%-30% PARTIAL PROJECT CRITERIA 35%-50% FULL PROJECT CRITERIA 100%
ITEM
STANDARD CLAUSE **
STANDARD CLAUSE **
10-28
10.4.2 Master CID MS Excel Folder The following paragraphs describe the sequence for developing and assembling the digital CID data. The process begins with CID procurement information developed in MS Excel Workbooks. Exhibit 10.4d illustrates all the MS Excel workbooks within the Master CID MS Excel Folder. FPP Drawings will be developed using the DoD Tri-Services standards. Master CID MS Excel Files and Project Folder (Sub-Folder #4) The CID project folder could be comprised of as many as of eighteen (18) separate Ms Excel files called workbooks. The number of workbooks used in a CID project will depend on project specific requirements. Exhibit 10-4d illustrates the comprehensive list of all possible CID workbook files. Workbook file names 00-Project Title.xls through 07-Manufacturers List.xls are related to documenting the design analysis, market research analysis, project specific personnel, and the final cost estimate. Workbook file names 08-Accessories through 17 Window Treatments.xls are related to the ten-(10) furniture/equipment item categories. No new furniture categories or workbooks shall to be created. Each of the 10 furniture categories has its own unique, stand-alone workbook with its own unique alpha code. All 18 workbooks are have a prescribed file name and are stacked in a prescribed order. Workbooks shall not be merged or renamed or the CID project will be disapproved. Ready-to-Edit CID Ms Excel Workbooks The required "ready to edit" CID MS Excel workbooks which are the working files needed to create the CID can be obtain upon request. Request files from the Mobile Districts EN-DR (Interior Design) or copy them from the Mobile District's public web site: ftp://ftp.sam.army.mil/pub in the folder labeled "INTERIOR DESIGN". 10.4.3 Editing the Master CID Ms Excel Folder (Sub-Folder #4)
The Master CID MS Excel Folder will require editing if certain categories of furniture/equipment are not used for a project. For example, not all CID packages will require bedding, dormitory furniture and window treatments like draperies. These workbook files would be deleted from the Master Project Folder to reflect only the furniture categories required for the project. Although workbooks files are removed from the master list, the prescribed order of the list shown in Exhibit 10-4d is to remain. Do not add, merge, rename or reorganize the structure of files in the prescribed Master Ms Excel Folder files.
10-29
10.4.4
Editing the Ms Excel Workbooks and Worksheets will begin with instructions for editing files 08-Accessories.xls through 17-Window Treatments.xls and end with instructions for editing files 00-Project Title Page.xls through 07-Manufacturer List.xls. Default Page Set-up and hyperlinks for all Ms Excel Worksheets are follows: A "portrait"-down and over orientation Letter size 8-1/2 x 11 No gridlines All 18 workbooks are hyperlinked in two places. The first link is found in the workbook file 01-Table of Contents.xls. A second hyperlink is found within each of the 18 workbooks on a worksheet tab marked Table of Contents Link. Exhibit 10-4e illustrates a workbook opened to the Table of Contents Link worksheet. The hyperlinks are ordered and listed in column B with corresponding digital file names in column C. Column C is not hyperlinked.
10-30
10.4.5
Editing The Table of Contents Link Worksheet The first worksheet tab within each workbook file shall always be the hyperlinked Table of Contents Link. This hyperlink feature will facilitate easy access and navigation to all other workbook files within the master project folder during the development of the CID. The integrity of these hyperlinks is to remain at all times. When workbook files are deleted from the master project Folder, edit all Table of Contents Links worksheets, the corresponding digital file names and the 01-Table of Contents workbook to reflect project specific requirements. The Link worksheets shall never be part of the Adobe Acrobat Master CID Submittal. The Link worksheets will remain a unique worksheet within the Master CID MS Excel Folder.
10-31
10.4.6
The second worksheet tab within each workbook file shall always be the Section Title Page. Exhibit 10-4f illustrates the "Section Title Page". Edit the footer on all "Section Tile Page" worksheets to indicate the Project Name and Location. Verify the correct "Section Title" is in the header. Do not put dates or location codes in the "headers and footers". Edit the Section Title Page to provide a generic list of items specified in each section. For example the list under the general category of "Section 8-Accessories" may read: Artwork, Artificial Plants, Clocks, Coat Racks and Wastebaskets. Edit the "Section Title Page" for the range of location codes used within this section. For example if 32 accessory type items are being specified in Section 8-Accessories then the range of location codes would read: A-1 thru A-32.
Exhibit 10-4f
10-32
10.4.7
Alphanumeric Location Codes The third worksheet tab within a workbook shall always start the Illustrated Order Forms (IOF). Each IFO is identified on a worksheet tab with the new simplified alphanumeric Location Code. Exhibit 10-4g illustrates the Location Codes tabs and stacked horizontally for easy navigation. There are only 10 "alpha codes" that can be used in developing the CID. However there are infinite "number codes" to use. Before assigning an alphanumeric location code to an item, determine the CID category workbook the item is to be in. When the category and workbook is determined, using the workbook's unique alpha code, assign the item an "alphanumeric" location code. Location Codes are not in alphabetical order. Codes are selected, ordered and stacked for easy editing of the Master MS Excel Director. Workbook Alpha Location Codes
10.4.7.1
A= V= C= D= F= T= S= E= B= W=
Accessories Audio Visual and Presentation support furnishings Seating (All Kinds) Desks (All Kinds of free standing units) Files and Storage (All Kinds) Tables (All Kinds) Furniture Systems (Panels, components, & worksurfaces) Equipment Bedding, dormitory room furniture, Sheets, Mattress Window Treatments not included in the SID such as draperies.
10-33
10.4.8
Editing the IOF worksheet is a two-step process. The first step is the page set-up. The second step is the actual development of the item specific ordering information. The following instructions will provide general guidance developing IOF worksheets and page set-ups: Only one location code per worksheet tab. Specify only one CID item per worksheet tab. Worksheets also known, as IOFs shall not be merged. For example, if 32 different types of accessories are specified for a project, there shall be 32 worksheets tabs labeled A1, A-2, A-3 etc. The new simplified Location Codes are provided in the editable MS excel files obtained from the Mobile District. Use only the alphanumeric codes provided in the 10 Furniture/Equipment workbooks. Do not create any new locations codes or workbooks. Alpha Codes used other than those provided will be disapproved. Exceptions are for Medical Projects. The Location Code used on the worksheet tab is also to be placed in the worksheet on line 1, column B. Do not place the Location Code in the "header or footer". Edit the header/footer of each IOF with the Section Number and Name and the Project Name and Project Location. Dates are not required. If hyperlinks are used during the design development process, delete the hyperlinks in the in the Ready-To-Purchase (RTP) working files to. Hyperlinks are to be only in the "Table of Contents Link" Worksheets and the file 01-Table of Contents workbook at the RTP submittal. Formulas for adding and multiplying cost and quantities can be used for quick calculations within a IFO worksheet only and can remain in individual IOFs at RTP. Do not hyperlink formulas to any other IOF worksheets or workbooks. Do not link the Cost Estimate workbook to any of the IOF worksheets. All 100% workbooks and worksheet are "stand alone" documents.
10-34
10.4.8.1 Information Provided on IOF Worksheets The designer is to edit the IOF by completing all sections. The goal is the use of only one page, 8-1/2 x 11 with portrait orientation and shown in Exhibit 10-4g. An exception is allowed if additional sheets are needed for detail specifications. The additional pages are to be ordered down then over in the page set. Each IOF worksheet is a stand-alone document and provides comprehensive ordering information including the following: Items Location Code GSA FSC Group and Schedule Name Contractor's GSA Contract Number/Expiration Date Contractor's Name and Address information Ordering Address Catalog Item Name Catalog Number Catalog Description Dimensions Finishes An image of the item to be purchased. It is suggested that furniture images be inserted into the Ms Excel page using a .bmp format. Do not provide an image of the finishes. Finishes shall only be placed on the Hard Copy CID Color Boards. Provide all the ordering information and specification data need for the item illustrated. Listing of the room numbers where the item is used. Quantity count per room. Total quantity count for the project. Unit cost of the item. Extend cost of all units specified Freight cost if applicable.
10-35
Exhibit 10-4g Illustrated Order Form (8-1/2 x 11) 10.4.9 Editing the Furniture Systems Worksheets
File 14-Furniture Systems.xls workbook will not follow the format of the other furniture item and equipment workbooks. Paragraphs 10.4.5 Furniture Systems and 10.4 SID/CID Drawing and Specification Requirements will discuss in detail developing projects that include Furniture Systems. 10.4.10 Editing the Project Title Page Workbook
The Project Title Page is found in the file 00-Project Title.xls Edit the project specific information as indicated in Exhibit 10-2a and 10-2b. This worksheet will also be printed and used as the CID binder cover insert as well as the digital title page for the Master CID Adobe.PDF Folder, which will be discussed later. Editing the header and footer in this workbook is not required. Design Firms may insert their companies logo in the title page as well as project specific User and command logos.
10-36
10.4.11
The Table of Contents is found in the file 01-Table of Contents.xls. Provide a comprehensive table of contents based on project specific requirements. Ensure this information is coordinated with the "Table of Contents Links" in each workbook. 10.4.12 Editing The Best Value Statement Workbook
10.4.12.1 Purpose. The purpose of the Best Value Statement is to provide a Contracting Official with the proper documentation to assist them in determining that the CID package meets Federal Acquisition Regulations (FAR). A complete and well-written Best Value Statement is the first step in ensuring the CID package will be purchased as designed. 10.4.12.2 File Name. The Best Value Statement is found in the file named 02-Best Value Statement.xls. This workbook contains an editable, GSA approved Best Value Statement form (Reference Exhibit 10-12 for the form) and an example of a completed Best Value Statement. The completed Best Value Statement example contains (1) the best value market research narratives and (2) completed pricing documentations forms required by Contracting Officials to make their determination that the CID items in the whole package meets the FAR. The approved GSA best value criteria form can be expanded to add additional criteria and is a valid form that can be used by Contracting Officials other than GSA. 10.4.12.3 CID Resources. The CID package is simply a large volume, consolidated procurement package of commercial items. To simplify and streamline the procurement process and obtain the volume of commercial items specified in the CID, the Mobile District requires designers to use the resources and follow rules and requirements found in FAR 8, Subpart 8.4 Federal Supply Schedules (FSS). The FAR 8, Subpart 8.4Federal Supply Schedules are actually indefinite delivery contracts established with commercial furniture manufacturers to provide furniture and services for a given contract period of time. The FSS program, directed and managed by the General Services Administration (GSA), mirrors commercial buying practices more than any other procurement process in the federal government today. The GSA FSS program provides Federal agencies with a simplified process for obtaining commonly used commercial furniture and services at prices associated with volume buying typical of a CID package. The GSA FSS schedule contracting office issues publications, entitled Federal Supply schedules, containing the contracting information necessary for placing delivery orders with schedule contractors. When a CID package is ready to implement, ordering offices issue delivery orders directly to the schedule contractors for the required furniture and service. All GSA FSS contractors have been extensively evaluated and their products tested to ensure Federal agencies large or small, even those in remote locations, are provided with the same services, convenience and pricing. GSA FSS provide a variety of contractors supplying comparable items and services at varying prices to provide the designer and User with the flexibility to select the best value items that meets the needs of the CID project.
10-37
Below are typical GSA FSS numbers and schedule titles to be used by the interior designer to develop the CID package. All the GSA schedules are found on the GSA web site in their e-library.
Number 71-I 71-II 71-II-H 71-II-K 71-III 71-III-E 72-I-A 72-II Office Furniture Household and Quarters Furniture Packaged Furniture Comprehensive Furniture Management Services Special Use Furniture Miscellaneous Furniture Floor Coverings Furnishings Title
10.4.12.4
The FAR mandates that all commercial items (furniture and related services) acquisitions use and document two separate and distinct criteria to reach a best value determination before commercial items can be purchased. The two criteria are: (1) market research and (2) price reasonableness. Though these two determinations may both consider the same information obtained during market research, they are separate and distinct from each other. The documentation of price reasonableness is required for all contract awards. The Best Value Statement for all CID packages will document both criteria. In addition, the CID Best Value Statement will also document the market research and price reasonableness of UNICORs products as well. Although the Department of Defense is not mandated to obtain a UNICOR waiver or required to buy from UNICOR, it is a requirement that UNICOR products be considered when developing a CID package. The Best Value Statement is to list the Location Code, then the three required vendors considered for the item, the price of the three considered and a brief statement why the selected item was the best value to the government. For Example: C-1 Manufacturer #1 Chair $300.00 Manufacture #2Chair $350.00 Manufacturer #3 Chair $400.00 Chair #3 was found to be the best value to Government because it was ergonomically designed, easy to operate, and received the most favorable comments by the User when given the opportunity to test the three chairs.
10-38
The Interior Designer of record sign the approved GSA form electronically as follows: /signed by/ Mary Doe, Interior of Record, Such and Such Firm, dated. 10.4.12.5 CID Scope of Work for Additional Services
The Best Value Statement workbook may also be expanded to include any Scope of Work documents required to procure from the FSS 71-II-H Packaged Furniture or FSS 71-II-K Comprehensive Furniture Management Services contracts.
10.4.13
The UNICOR Waiver statement is found in the file 03-UNICOR Waiver.xls. Department of Defense (DoD) activities are not mandated to obtain a waiver from UNICOR. The UNICOR Workbook has been completed. It contains all the statements and DoD documentation required by a Contracting Official to determination that the CID meets the FAR. No additional editing is needed. If the CID is being developed for another Federal Agency or Department other than the DoD, a paper copy of the UNICOR wavier is to be scanned and inserted as an image into this workbook. Edit the UNICOR Waiver Worksheet to document: If a UNICOR waiver is required. Provide the .bmp image of the required waiver.
10.4.14
The CID Narrative worksheets are found in the file 04-CID Narrative. The CID narrative will provide a comprehensive discussion and design analysis as to how CID items are integrated and function with the SID. Edit the CID narrative worksheet using: A "portrait"-down and over orientation Letter size 8-1/2 x 11 No gridlines Do not import any other word document programs into this Workbook. The CID Narrative is to: Discuss the design decisions made to fully coordinate the SID and CID. Discuss Function, Safety, and Ergonomic Considerations Discuss Durability, Aesthetics Discuss how the CID met project specific design requirements or Buildings systems(power voice and data) requirements.
10-39
10.4.15
The POC List is found in file 05-POC List.xls is a comprehensive list of POCs needed to implement this CID project. The POC workbook is to list: Name Address Phone/Fax E-mail Job Function of those associated with the CID project.
10.4.16
The comprehensive cost estimate if found in file 06-Codes & Cost.xls. The comprehensive cost estimate shall be organized and grouped by the General Service Administration (GSA) Contracting Sources Contract Number. Because GSA has consolidated many of their schedules, it is possible to have several different types of furniture items listed under one Contractor's Contract Number. Reference Exhibit 10-3h for an example of the Cost Estimate. Do not organize the cost estimate by location codes. The Cost Estimate is organized according to GSA FSS Schedule Numbers and Titles then by individual contractors and their unique contract numbers under that GSA FSS multiple award schedule. After furniture and equipment costs have been sub-totaled add the following line item costs to determine the final total cost of the CID package. Add: Freight charges 7-10% CONUS ONLY or 34% for CONUS/OCONUS 14% Installation fees 5-6% GSA FSS Project Management Fees 6.5% Area Office fees (If the project acceptance is accomplished by the Districts Resident Office) Lead Vendor Management fees other than the ordering an installation fees. (% may vary and are to be based on the CID Procurement Plan discussed in 10.1.3)
10-40
10.4.17
The Manufacturer Lists are found in file 07-Manufacturer List.xls. The Manufacturer's list is a comprehensive, summary list with addresses of all the contractors and sources used on the CID project. IOF will provide other specific information required for ordering purposes in addition to the addresses shown on the Manufacturers List. The Manufacturer's List is to show: Name of the Source Address Phone/Fax E-Mail address
10-41
Exhibit 10-4h "Location Codes and Cost Estimate" 10.5 ASSEMBLING THE RECORD COPY CID (Sub-Folder #1)
After the MS Excel CID workbooks are edited to meet project and submittal level requirements, each workbook is to be "printed" in an Adobe Acrobat portable document format (Adobe.PDF) and compiled into Sub-Folder #1 which is the Record Copy CID. The creation of the Record Copy CID is a two-step process. The first step is to print or transposed all the Ms Excel working files into Adobe.PDF files. Exhibit 10-5a illustrates the files names and stacking order. Creating the CID Adobe.PDF files is quick and easy. To print the Ms Excel CID working files into the Adobe.PDF file, print one entire workbook at a time by simply highlighting the required worksheet tabs then print in a .PDF output. The file name will be the same with one exception. The file extension will be .PDF. Not all the worksheets in a workbook will be printed. Do not print to the .PDF file the Table of Contents Link worksheet tab. The Link worksheet tab is used only in the CID working files within the MS Excel Master Sub-Folder #4 for navigation purposes. Typical tabs titles printed in files 08 through 17 are: Section Title Page tab Illustrated Order Forms tabs.
10-42
Workbooks with the digital file names 00-Project Title Page.xls through 07-Manufacturer List.xls will require the workbook specific tabs to be printed. Do not print the Table of Contents Link in these workbooks.
The second step is to insert the Adobe.PDF files into the Sub-Folder #1- which will become the CID Record Copy is created. Adobe.PDF files inserted into the CID Record Copy using Adobe Acrobat Writer program. The CID Record Copy is the comprehensive CID procurement data other than drawings and actual sample boards. 10.5.1 Adding Bookmarks to Section Title Pages
After the digital workbook pages have been inserted into the SubFolder #1 using Adobe Acrobat Writer program, begin adding bookmarks to identify each "Section Title Page" and provide the number of pages within each Section. Exhibit 10-5b illustrates this requirement. For example, in Exhibit 10-5b the Section Title page "SID CID Narratives has (2) pages within that section. The page numbers within the each section are noted in parentathes ( #).
10-43
10.5.2
Add IOF bookmarks as a sub-tile under the Section Title bookmarks. Edit the bookmarks using the simple alphanumeric location code used to identify the furniture item. If two or more sheets are required for an IOF add the number of sheets in (#) like the Section Title pages. 10.5.3 Electronic Signatures for the Record Copy
When all the information required for a submittal is inserted into the CID Record Copy, add a digital signature with a protective password for authenticity of the Record Copy. This signature action notes if any changes have been made to the document after the digital signature has been added.
10.5.4
Default settings Adobe.PDF Record Copy Set the default settings in the Record Copy CID as:
Open with page and bookmarks Magnification shall be set to "fit width".
10-44
10.6
Working drawings of the "Composite Furniture Placement Plans" (FPP) shall be printed to Adobe.PDF files and placed in Sub-Folder #2. The FPP drawings are not to be included in the same folder as the IOFs. Drawings are to be stacked in a drawings folder as illustrated in Exhibit 10-2e. 10.6.1 Adding and Bookmarking Acrobat Read Drawings
Working files of AutoCAD or Microstation drawings are to be printed in the Adobe.PDF format using black and white output. Color output is not acceptable. When inserted into the Adobe Drawings Folder, "Bookmark" a full view of the each composite furniture placement. Use the sheet name in the drawings title block for the Bookmark title. 10.6.2 Adding and Bookmarking Individual Room Placement Plans After all the FPP drawings have been set for full view, bookmarked and titled, create individual room placement views under each Sheet title. This is done by "zooming-in" on the individual furnished rooms and inserting a bookmark for that one room. Edit Room Placement Plan bookmarks with the room number only. If the customer requires a hard copy of the room plan, instruct them to use the crop and print feature in the Acrobat program to obtain the hard copy. Exhibit 10-6a illustrates the Composite FPP with individual room bookmarks.
10-45
10.7
FURNITURE SYSTEMS
Furniture systems workstations, either desk based, panel based or a frame and tile system are actually a building within a building because of their intended use and the requirement to fully coordinate them with the buildings finishes, architectural layout, structural, electrical and mechanical systems. Furniture system workstations are intended to function as hard walled offices providing some degree of acoustical and visual privacy in addition to having power, voice and data (PVD) network distribution outlets like one would find in a hard walled office. Workstation designs and layouts are required to fully coordinate with the life safety plan, audio and visual alarms and the fire suppression system to ensure the building within the building supports life safety. Workstation solutions for projects are not only to be designed for project specific requirements but are required to address the inevitable office reconfiguration. Workstations need to be selected for their best value features, durability, flexibility, and ease of reconfiguration. Workstations are to offer limited interruption of the PVD when reconfiguration occurs and are to be easily adaptable to incorporate new technology. Workstations are to provide ergonomic features such as adjustable height work surfaces, fully articulating keyboards with parallel and changeable mouse pads, and paper management and storage tools to support tasking. All computer hard drives are to be mounted under the worksurfaces. A suitable, ergonomically designed task chair is to be selected and specified for each workstation. To the fullest extent possible, avoid placing an occupied workstation next to common use area such as semi-private conference spaces, copy areas or food preparation areas. When considering the scope of work involved developing a furniture systems design and cost estimate and when considering the project delivery process of fast track- Design Build, new design requirements have been developed to ensure furniture systems designs and installation efforts are reasonably distributed throughout the design and construction process. These new requirements shall be applied to PPTO and D-B RFP projects alike to ensure the SID/CID submittal process for all projects are consistent. 10.7.1 Furniture System Requirements During the Design Phase
During the Design Phase of an PPTO or D-B RFP project provide the following design and procurement information: Workstation finishes, Coded workstation layouts plans Workstation product lists PVD requirements per typical workstation Cost estimates Edited UFGS Section 12705 FURNITURE SYSTEMS
10-46
10.7.2
During the construction phase of the project furniture systems vendors and the construction contractor is to provide as a single shop drawing the following submittal information: Detailed drawings, panel plans, PVD plans, Bill of materials Elevations or isometrics of typical workstations
Note: These requirements are based on submittal requirements listed in the UFGS 12705 Furniture Systems.
10.7.3
The following instructions will provide guidance for the development of the CID MS Excel file 14-Furniture Systems.xls to meet Design Phase requirements. The MS Excel File 14-Furniture Systems.xls is different from all other IOF files. Isometrics are not required during the design phase of the project unless a unique workstation design needs to be shown. When an isometric is needed, the isometric is to be shown on the furniture systems I drawings. Editing the Table of Contents Link and the Section Title page is the same as the other 17 files. 10.7.4 Workstation Finish Sample Boards
Provide a hard copy sample color board(s) illustrating all workstation finishes. On the sample board identify the furniture systems manufacturers name, and product line Identify each finish with the manufacturers color name and number. Workstation Location Codes
10.7.5
A simplified workstation alphanumeric location code is to be used. The letter S followed by a number is all that is required. The intent of the location code is to identify the workstation type. The location code is not to be used as a room number. If a combination of a desk based and frame and tile or panel based systems are used the S location code may be modified as follows: SD-# for the desk based systems SP-# for the panel based systems ST-# for the frame and tile systems
10-47
10.7.6
Block 1 Locations Codes: List all the location codes used. If only one manufacturer is supplying two or three types of systems, the location codes should be keyed to the ordering information make the distinction. Block 2 thru 6: Edit to include all the required ordering information and GSA contracting information. Block 7: Special Instructions. Block 8: List the types by Location Code and in [brackets] list the room numbers where they are used. Block 9: Indicate the total quantity of a each typical. Block 10: Indicate the cost of a single workstation type. Block 11: Indicate the extended cost. Block 12: Indicate the total cost for all types. Block 13: Add additional costs for design, installation etc. Blocks 14-16: Cost may vary depending on the CID procurement strategy agreed to during the Criteria Review meeting. Block 17: Indicate the Grand Total for Workstation design and installation.
NOTE: If UNICOR is designing and supplying the furniture systems a design fee of $225.00 per workstation for design and or design verification must be added to the project costs. If the CID WILL NOT be installed by the General Construction Contractor, fees associated with the installation of the PVD networks and distribution systems must be added to the cost estimate. 10.7.7 Editing Fabric and Finish Worksheet
Edit the fabric and finish worksheet by listing the manufacturers fabric and finishes according to typicals. For example: Fabrics and finishes in open office areas may be different from fabrics and finishes used for private offices. Avoid Custom or Customers Own Material. COMs will be disapproved. Editing Typical Workstation Worksheets
10.7.8
Worksheet Tabs: Edit the sheet tabs using the typicals location code. Block 1: Indicate the Location Code. Block 2: Workstation dimensions/square footage requirements. Block 3: List of product and PVD requirements.
NOTE: A go-by product list has been provided in worksheet S-1. If the designer chooses, the product and PVD requirements lists may be scheduled on an I drawing and included in the composite furniture placement plan drawings. The schedule may also be added to UFGS Section 12705 Furniture Systems in Part 3 Execution.
10-48
10.7.9
The UFGS 12705 Furniture Systems specification provides paragraphs describing the three types of systems discussed in paragraphs 10.3. Ensure only the systems types specified for the projects are included in the final specification. Ensure furniture system types that are not used in the project are edited out. A schedule of workstation products per type may be added under Part 3 Execution in lieu of using the drawings for scheduling workstation type product list.
Note: When the UFGS 12705 is used but not included in the set of building related contract drawings and specifications published by the Districts EN-DW, submit the specification as part of the Master CID Adobe Acrobat file. Print the SpectsInTact file to a Adobe.PDF file and insert into the Master CID Binder directly behind the last typical location code for furniture systems. Provide a Bookmark indicating it is the Furniture Systems Specification.
10-49
10.8 CONSTRUCTION CONTRACTOR INSTRUCTIONS FOR D-B SUBMITTALS The D-B Construction Contractor is to respond to the D-B RFP by completing a 100% SID and CID if required by the D-B RFP. 10.8.1 Full D-B Project Criteria When full project criteria is provided in the D-B RFP the D-B Contract, the Prime Contractor will provide a 100% SID based the 100% plans and specifications provided in the RFP. If 100% of the CID packages has been developed during the RFP phase of the project, The Prime Contractor is to coordinate any changes made during construction with the User and the 100% SID/CID. Revisions to the SID are the responsibility of the Construction Contractor. Revisions to the CID are the responsibility of the User Group. 10.8.2 Nominal and Partial D-B Project Criteria When Nominal or Partial Project criteria is provided in the D-B RFP, the D-B contractor will be required to make submissions for Government acceptance of the SID and CID during the Predefinition Conference, 50% design phase, 100% un-reviewed design phase and final design phase after award of the D-B contract. The 100% CID is to be completed by the D-B Contractor's Design Team and ready for government procurement at the time building construction begins. The CID needs to be fully coordinated with the other engineering disciplines to ensure PVD connection requirements are met as well as the architectural layout and building related finishes. The level of Contractor response is directly related to the level of criteria and submittal requirements provided in the D-B RFP. Contractor responses are provided during the following phases: 10.8.3 D-B D-B D-B D-B Pre-Definition Conference 50% Design Phase 95% Design Phase Final Design Phase.
Pre-Definition Conference
The Contractor shall lead a predefinition conference at the User's office or at a site agreed upon by the Mobile District Project Manager, 30 days before the 50% design submittal is due. Government personnel responsible for the interior design of this project shall attend this meeting. The purpose of the predefinition conference is to present and discuss the SID color scheme for the project and to present any Contractor initiated deviations from the D-B RFP. Any SID deviations accepted are to fully integrate and coordinate with the SID materials, finishes, colors, textures, and patterns indicated in Section 01010 Design Criteria or related UFGS.
10-50
Actual exterior and interior materials, finishes and colors are to be provided for review and comment. The format for this presentation shall be on 24 inch by 36-inch (600 by 900 mm) presentation board(s). The Contractor shall provide colored elevations or perspectives of both the SID exterior and interior color schemes to assist in the discussion and presentation. At the end of the predefinition conference the Government will decide the final SID finishes that will be accepted for incorporation into the construction and ensure that installation guide standards are met. SID finishes accepted throughout the predefinition and design phase process shall be installed during the construction phase process. Discontinued items will be the only justification for changing a accepted SID finish during the construction process. Therefore if is critical that accepted SID finishes will be available at the time of installation. The Government shall provide specific guidance as to the types and manufacturers to be used to develop the CID package during the Pre-definition conference. 10.8.4 50%, 100% AND Final Design Submittals
After the Pre-Definition Conference, the D-B Contractor will submit the formal 50%, 100% Un-reviewed and Final Design Package. The Contractor shall submit 5 complete sets of the 100% SID/CID package in accordance with this Chapter 10 of the Mobile District's Design Manual
EXHIBIT 10-8a SID/CID D-B Contractor Deliverables After Award of the D-B Contract * Hard Copy Presentation ** Digital Data Presentation 100% 50% PreDescription of the D-B UnDesign definition contractor SID deliverables Reviewed Phase Conference after the award of the D-B Final Contract. Design Phase Start of SID Submittals The D-B Contractor shall provide 2 sets of 100% SID color boards, 120 days after the Contractor is given Notice to proceed, complying with the requirements of Full Project Criteria. The Color Boards are to be submitted in an 81/2 x 11 format as indicated in the Mobile District Design Manual Chapter 10. Side mark each set with "USER" and "COE Resident Engineer". Provide large SID presentation color boards organized logically according to color X placement and use. Deviations or alternatives samples can be provided for further development of the Design. Provide preliminary review of X exterior materials etc. X Colored rendering may be used as visual aid. SID binders (see 10.3)
ITEM
Final Design
1. * **
2. *
3. *
4.
10-51
5. 6. 7.
8. ** 9. ** 10. **
SID binders will be returned to the D-B contractor for updating. Drawings (10.3) Specifications (10.3) Interior Signage Design, and placement plans (10.3) Start of CID Submittals Preliminary layout of the furniture and equipment plans to validate the space supports the furniture requirements. (10.4) 100% layout and scheduling of the furniture and equipment plans. (10.4) Preliminary CID selections and Illustrated Order Forms for one area of the facility. Preliminary discussions manufactures to use in the development of the CID. (10.4) Preliminary digital CID. PDF files only. (10.4) 100% digital CID. PDF files only. (10.1 & 10.4) Final CID Adobe.PDF and MS Excel working files. (10.1 & 10.4) CD-ROM with entire Contract drawings and specification
X X X
X X X
X X X X
10.9
The following commonly used terms and definitions are associated with SID/CID design development process. The terms may not be used in this Chapter but are helpful when planning or implementing an interior design package. There are many terms used in the Federal Government and many may be defined differently by other Department of Defense activities, other Federal Agencies and private sector professional societies and organizations. This Glossary provides Departments of the Air Force and Army specific acronyms related to the SID/CID packages and related contracting actions. The Glossary is divided into three sections: (1) Army and Air Force Terms, (2) Procurement Terms and (3) Space Planning Terms Army and Air Force A-E - ARCHITECT-ENGINEER A term generally used informally to identify a non-government designer, design team or design service contractor. AR-405-70- Army Regulation for Utilization of Real Property- Army space allocation guidance. Exhibit 10-8a provides a summary of space allocation guidelines for administrative space. BCE - BASE CIVIL ENGINEER The Air Force term for the centralized engineering management staff. The BCE is responsible for the coordination of all MILCON and O&M design and construction projects; is the principle coordinator between the designer, users and Major Commands. See also DPW.
10-52
CID - COMPREHENSIVE INTERIOR DESIGN The selection and illustration of all furniture necessary to complete the interior environment; The submittal is O&M funded and includes furniture illustrations, fabric and finish samples, plans, and ordering information. The CID may include the furniture systems plans and purchase orders if they are not included in the SID. See also SID. DD 1391 - DEPARTMENT OF DEFENSE FORM 1391 A programming document initiated by the installation and submitted to Congress through the Major Command for funding. It includes an outline of basic needs for a proposed facility and an estimated cost to fulfill the needs.
DPW - DIRECTORATE OF PUBLIC WORKS The Army term for the centralized engineering management staff. The DPW is responsible for the coordination of all MILCON and O&M design and construction projects; is the principle coordinator between the designer, users and Major Commands. See also BCE. DoD Tri-Service Standards CADD and Specification standard used by the three services branches that make up the Department of Defense (DoDDepartment of Army, Air Force and Navy. EN-DR- Mobile District Engineering Design and Review Section responsible for SID/CID criteria development, in-house design development and project review during design and construction. EN-DW- Mobile District Engineering Project Support Section responsible for compiling and publishing the Contract Solicitations. FSN 595B - FEDERAL STANDARD NUMBER 595B A collection of standard colors used by the various departments or agencies. The first number in the five digit series indicates a specific finish: (1)full gloss, (2) semigloss and (3)flat. The remaining 4 digits indicate a specific hue and tint/shade range. FSN 595B COLOR FAN DECK Federal Standard colors are available in a "fan deck" booklet for under $10.50. Use Order number # NSN 7690-01-162-2210 and mail your request and check to: GSA Specification Unit (3F-BP-W) Seventh and D Sts SW Washington, DC 20407
FY - FISCAL YEAR (a) October 1 of a calendar year through September 30 of the following calendar year; (b)"FY-...." at the beginning of a project title identifies the year Congress will fund the construction c contract. IMA - Installation Management Agency The Department of Armys regionalized management activities responsible for but not limited to Army Standard Design Program.
10-53
JOC - (JOB ORDER CONTRACT) OR SABER (SIMPLIFIED ACQUISITION OF BASE ENGINEERING REQUIREMENTS) The JOC (Army) and SABER (Air Force) are methods the installation uses to contract for repair work. The Contracting Officer and the contractor agreed upon unit prices for work, then individual job orders are negotiated for specific scopes of repair work. Mobile District Design Manual- The Mobile District Design Manual prescribes standard procedures and instructions for the preparation of design documents for Military and Civil Construction projects the direction of the US Army Corps of Engineers, Mobile District. Chapter 10 of the engineering design manual covers specific project directions and instructions for SID/CID designs. The web site for the complete design manual is: http://www.sam.usace.army.mil/en MILCON - MILITARY CONSTRUCTION Funds that are appropriated by Congress for new military construction. Also known as MCA or MCP. OMA-O&M - OPERATION AND MAINTENANCE Funds provided to each installation by the Major Command and used for the day to day operations of the installation. These funds may be used for the renovation of existing buildings or for the purchase of furniture. Funds not spent to award a contract disappear at the end of the FY and cannot be recovered. PD- Project Definition-Air Force term-The requirement validation and schematic design phase of the design process. It satisfies the requirements for early preliminary design (35%). Select Program- A UNICOR program allowing purchasing activities to select the projects that will be purchased from UNICOR. SID - STRUCTURAL INTERIOR DESIGN (a) The selection and sampling of building related finishes; (b) A submittal with samples of proposed building materials a for a particular project; (c) Materials and finishes purchased and installed by the General Contractor; (d) Projects that are funded with the MILCON funds. The SID may also include the O&M funded furniture systems workstations. Sustainable Design- Designs that consider the use of re-cycled products and designs conditions that score rating points such with the as LEEDs program. Building Related and Furniture Related Procurement Terms BEST VALUE- The best value provision in the FAR gives an ordering agency the authority to consider non-price-related factors in making a purchasing decision. Some non-price-related factors are: special features of a product not offered by other vendors that will enhance the agencys performance product trade-in considerations advantageous warranty product maintenance availability
10-54
When non-price related factors are used, these factors are documented as market research. In making a best value determination, the Contracting Official uses price and market research assessments. COM- CUSTOMERS OWN MATERIAL- Manufacturers have standard fabric offerings that meet testing standards, aesthetics qualities and color trends. A custom or special order fabric which is not part of a the standard offering is called Customers Own Material (COM). Typical COM adds extra cost and coordination issues to the order. COM is discouraged. DESIGN BUILD-The term Design-Build has many meaning. For the purposes of this chapter of the Design Manual the term Design Build will be a method of contracting in which a single entity takes responsibility for both design and construction of a facility. Performance requirements are outlined using the RFP format. See also RFP. ENVIRONMENTAL PRODUCTS GUIDE- A GSA catalog for supply items. can be obtained by contacting: GSA CENTRALIZED MAILING LIST SERVICE (7CAFL) P.O. BOX 6477 FT. WORTH, TX 76115 (817) 334-5215 This guide
FAR - FEDERAL ACQUISITION REGULATIONS The Federal laws governing how the Federal Government buys products and services. FAR 8.4 indicates the process for ordering from Federal Supply Schedules. FSS - FEDERAL SUPPLY SCHEDULES Contracts that provide indefinite quantity contracts for commercial items at established prices for direct ordering use by Government agencies. For copies, mail requests to: Furniture Commodity Center (3FN-CO) Crystal Mall 4, RM 403 Washington DC 20406 (703) 305-5056.
GSA FSC - GENERAL SERVICES ADMINISTRATION FEDERAL SUPPLY CLASSES FEDERAL SUPPLY GROUPS Government contracts with private manufacturers that have a fixed price, MOL, and expiration date. This publication can be ordered from the following address: GSA CENTRALIZED MAILING LIST SERVICE (7CAFL) P.O. BOX 6477 FT. WORTH, TX 76115 (817) 334-5215 The Web site is: www.gsa.gov visit the GSA e-Library for a list of all the FSS schedules. MO - MAXIMUM ORDER- Maximum Order replaces the old Maximum Order Limit (MOL). Under the new Maximum Order provision (MO), any size order may be placed against a Federal Supply Schedule. The MO does not require the customer or the vendor to engage in a requote process. Under FAR 8.404, the new MO suggests the customer many want to seek a reduced price from the contractor. Under the MO principle, the customer may contract a preferred vendor(s), or dealer, and negotiate a better price directly with them. The ordering agency is not required to use the formal requote process. Depending on the specific circumstances, the vendor and dealer
10-55
may order a better price than the contract. reductions on to all Federal agencies.
OPEN MARKET - Designation for products that are not on a GSA or UNICOR contract. PPTO PRICE PERFORMANCE TRADE-OFF One of the ways the Government solicits for construction. The PPTO is a standard 100% design contract with clearly defined requirements, specifications, and terms that are not negotiated. Any proposal prepared in response to an PPTO must strictly adhered to the terms. The award is based on a best value bases and the past performance of the construction contractor on similar type projects. RFP - REQUEST FOR PROPOSAL One of the ways the Government solicits for construction. An RFP usually defines a design problem and allows those who respond to the RFP to suggest a solution. The RFP is much more flexible than the PPTO. A solicitation document used in lieu of a sealed bid procurement. When and RFP so states, the Government reserves the right to award a contract based on initial offers received without any written or oral discussion with the Offerors. RFQ - REQUEST FOR QUOTES item. An informal request for a price for a standard
UNICOR- The trade name for the Federal Prison Industries (FPI)Inc., a wholly owned government corporation established in 1934. UNICOR provides a variety of products and services to the Federal Government. All furniture systems workstations and conventional furniture requires a waiver. All waivers are to be requested at 35% design. Web site for FPI is www.unicor.gov. The waiver requests are sent to FPI on this web site. Space Programming and Planning Factors AR-405-70 Utilization of Real Property- The Department of Armys programming requirements for space utilization of administrative areas. See Exhibit for the table of allowances for personnel. Assignment Drawings- Single-line architectural drawings, which incorporate graphic and statistical information broken down by tenant or organization. Base Building Drawings- Scaled architectural drawings indicating the building shell and accurately representing all architectural and structural elements. They shall include but not be limited to exterior building elements, and permanent interior partitions, core areas, columns and convectors. Numerical identification of all columns, stairwells and elevators, toilets, doors, etc., shall be included. Bay- The space in a building bounded by four columns. 20,25 and 30 foot bays are common. Blocking, Stacking and Zoning- The first step in space planning. Arranging all organizational units by floor and within a floor to fit in the building. Determined by adjacency requirements, square footage and special space needs. Zoning diagrams show public, semi-private and secure spaces by floor or within the facility.
10-56
Building Core- Includes elevators, stairs, restrooms, mechanical rooms, shafts, and electrical closets. Circulation & Layout factors: In accordance with the AR-405-70, the circulation factor is a percentage of the net square footage allocation per person. The AR-405-70 space allocations for open offices include both the net square footage for an assigned workstation footprint and the net square footage of circulation required to access the assigned workstation. Net square footage allocations for private offices do not include the necessary square footage allowance to move Color Boards- Boards displaying samples of the materials to be used in the project. There are color boards for SID building related materials and color boards for CID furniture related materials. Design Charrette Phase-The second part of the on-site effort is to produce a responsive schematic project solution based on the documentation of the Requirement Analysis Charrette. See Requirement Analysis Charrette. Ergonomic- The science or study of human proportions and actions as related to the immediate human environment such as a employees workstation. Footprints & Typical- The footprint is an outline of the space required for a workstation and a typical is an example type of workstation that is used repeatedly throughout the project with no variation. FPP- Furniture Placement Plans Drawings usually provided in the CID package that show all the furniture and equipment needed to outfit the facility. FURNITURE SYSTEMS Furniture systems refer to workstations cubicles that are either desk based, panel based or frame and tile based. All types are under the same GSA Contract Furniture Systems Workstations are O&M funded only and never MILCON. If included in the construction contract and funded with O&M dollars, the workstations may be purchased and installed in the construction contract. The interior designer will coordinate the workstation plans with the building and building systems and provide the plans and specifications in the contact documents for bids if the General Contractor will purchase and install the workstations and connect the workstations to the building's electrical, data, voice, and LAN systems. Reference UFGS Section 12705 Furniture systems workstations. Layout plans for workstations purchased and installed by the User are to fully coordinated with the building's systems and workstation layouts are included in the contract plans for "information only." PVD- Power, Voice and Data- Electrical and Electronic systems that must be coordinated with the FPP. Each workstation must be assessed for the type of equipment that will be used and ensure the correct number of electrical and data outlet devices and circuits are specified. These requirements are to be coordinated with the Electrical Drawings. Requirement Analysis Charrette Phase- The first part of the on-site effort to systematically collect and analyze the customer and project requirements. Information is typically gathered through the use of project
10-57
specific questionnaires typically alphanumeric and proceeds to the schematic design such as a bubble diagram and the blocking and stacking plans. Turnkey- Specific to Mobile District- When the a single contractor is hired to provide all services related to implement the SID and CID packages. Typically the CID is procured by the Government and installed by the General Construction Contractor. The coordination and installation of furniture deliveries and placement efforts are typically and option to the building related contract. Workstation Standard-Development of a personal workspace, which includes all necessary storage, and furnishings for a specific job function. 10.10 FURNITURE PROGRAMMING GUIDELINES
In projects where the furniture budgets have not been established, furniture programming guidelines are provided to establish preliminary targets for CID packages. Furniture programming costs have been developed based on the number of personnel who will occupy the facility and the facility type being occupied. Exhibit 10-10a Furniture Cost Guidelines Facility Type Administrative Space Programming figures allow for Workstation Cost Task Seating Installation Air Force Quarters and Army Barracks
10-58
10.11.1
The Department of Army programming requirements for space utilization OF administrative areas is found in AR-405-70. Net square footage allowances include internal circulation within workstations. For example, a 200 net square foot office for a Division Head is the total square footage allowed for furniture and circulation within the office.
Exhibit 10-11a Space Utilization Guidelines SPACE ALLOCATION P-1 Commanders and Deputy Commanders Heads and Deputies of Directorates, Offices, Bureau, and Agencies GRADE NET SQUARE FOOTAGE ALLOWANCE 400
P-2 Command and Deputy/Assist Heads and Deputies of Directories P-3 Commands and Deputy Commanders Commanders Division Heads Branch Heads Professional/Admin. Personnel Command Sergeants Major of Positions in P-1 and P-2 Categories P-4 Commanders Division Heads, LT. Col Branch Heads Command Sergeants Major of Positions in P-3 Category P-5 Commanders Branch Heads Professional/Admin. Personnel Staff Sergeants Major Unit First Sergeant
010 & 09 010, 109 and GS/GM 18 Comparable positions 08 & 07, SES, GS-15 06 05 GS 15-14 Colonel GS 15-14 Colonel GS 16
300 200
04 GS13 GS 15-13
150
03 GS 12, Major GS 13, LT. Col. & below who require office E-8 GS-9, E-8 WO, 01 or above W/6 Employees GS-7, E-8 WO, 01 and above GS-8, E-7 and above GS-07-GS-14 GS-07-GM-14 GS-12 GS-12 GS-13 GS-14
110
CIVILIAN PERSONNEL /CIVILIAN SPECIFIC CATEGORIES 0-1 Unit Supervisors 0-2 Professional Administrative Personnel Unit Supervisors 0-3 Clerical * Employees (Non-Supervisory) Administrative Officers (NonSupervisory) Employee (Special assignment) Supervisor Supervisor * NOTE: Add five (5) square feet for computer terminals, fax machines printers, typewriters etc.
110
100
150 200
10-59
Exhibit 10.12
NATIONAL FURNITURE CENTER (NFC) MULTIPLE AWARD SCHEDULE BEST VALUE DETERMINATION GUIDELINES as of 1/23/04
Schedule purchases are subject to FAR 8.001 (See following page) FAR 8.4 requires that you make a best value determination before placing Multiple Award Schedule orders above the Mico-Purchase Threshold (MPT). Follow the guidelines below to make a best value determination. Orders under the MPT, currently $2,500-place with any schedule contractor: this form is not required. Orders over the MPT, but under the Maximum Order (MO)-Review GSA Advantage or at least 3 GSA vendors price lists Orders over the MO, review additional price lists/use GSA Advantage and seek a price reduction. REQUISITION OR MIPR NUMBER______________________________________________________ Review at least three sources under the Federal Supply Schedule and list the contractors names and prices below. Submit justification if fewer than three sources were considered. You may attach the pricing or contractors quotes. It is important to have installation, design and other services pricing included as separate line items in each quote. Please indicate the selected contractor by placeing a check or X by the Contractor Name. Location Code 1. Contractor Product $ Installation$ Design $ Other Services$ Total$ 2. Contractor Product $ Installation$ Design $ Other Services$ Total$ 3. Contractor Product $ Installation$ Design $ Other Services$ Total$ Yes or No (circle one) Was the requirement in excess of the MO? If yes, reiveiw additional sources/GSA Advantage! Under the Federal Supply Schedule and list below (attach if desired) Location Code 1. Contractor 2. Contractor
Product $ Product $
Installation$ Installation$
Design $ Design $
Total$ Total$
Indicate the factors, other than price, considered in your best value decision: __Special Features __Warranty Consideration ___Delivery Time __Past Performance/Experience __Comfort/suitability of the item __Technical Qualifications __Trade-In Considerations __Compatibility with existing furniture __Probable life of the item selected compared with that of a comparable item __Environmental considerations-ie. Recycled content, naturally renewable ingredients, bio based content, energy efficiency, (See Executive Order 13101) __Other (specify)
When ordering through the NFC, please include this checksheet with your order. Please ensure that all the information is complete. Fax order to 703-305-6032 or call 703-305-7003 for more information. Please include all the information, requested below in case additional information is required. Orders over $100,000.00 require a written Acquisition Plan, which will require extra information and time for the NFC to complete the order issuance. Signature: Title Date
Phone Number Email Note: This form does not apply to services.
10-60
8.001 Priorities for use of Government supply sources. (a) Except as required by 8.002, or as otherwise provided by law, agencies shall satisfy requirements for supplies and services from or through the sources and publications listed below in descending order of priority (1) Supplies. (i) Agency inventories; (ii) Excess from other agencies (see Subpart 8.1); (iii) Federal Prison Industries, Inc. (see Subpart 8.6); (iv) Products available from the Committee for Purchase From People Who Are Blind or Severely Disabled (see Subpart 8.7); (v) Wholesale supply sources, such as stock programs of the General Services Administration (GSA) (see 41 CFR 101-26.3), the Defense Logistics Agency (see 41 CFR 101-26.6), the Department of Veterans Affairs (see 41 CFR 101-26.704), and military inventory control points; (vi) Mandatory Federal Supply Schedules (see Subpart 8.4); (vii) Optional use Federal Supply Schedules (see Subpart 8.4); and (viii) Commercial sources (including educational and nonprofit institutions). (2) Services. (i) Services available from the Committee for Purchase From People Who Are Blind or Severely Disabled (see Subpart 8.7); (ii) Mandatory Federal Supply Schedules (see Subpart 8.4); (iii) Optional use Federal Supply Schedules (see Subpart 8.4); and (iv) Federal Prison Industries, Inc. (see Subpart 8.6), or commercial sources (including educational and nonprofit institutions). (b) Sources other than those listed in paragraph (a) of this section may be used as prescribed in 41CFR 101-26.301 and in an unusual and compelling urgency as prescribed in 6.302-2 and in 41 CFR 101-25.101-5. (c) The statutory obligation for Government agencies to satisfy their requirements for supplies available from the Committee for Purchase From People Who Are Blind or Severely Disabled also applies when contractors purchase the supplies or services for Government use. NOTE: Department of Defense procedural requirements when purchasing Federal Prison Industry products changed with passage of FY 2002 and 2003 DoD Appropriations Acts. Section 811 of the 2002 Act, as amended by Section 819 of the 2003 Act, follows in part: (For the full language of Sections 811 and 819, go to http://www.wifcon.com/dod811.htm and http://www.wifcon.com/hasc819.htm ) SEC. 811. APPLICABILITY OF COMPETITION REQUIREMENTS TO PURCHASES FROM A REQUIRED SOURCE. Conditions for Competition. -- (1) Chapter 141 of title 10, United States Code, is amended by adding at the end the following: ``Sec. 2410n. Products of Federal Prison Industries: procedural requirements (a) MARKET RESEARCH.--Before purchasing a product listed Prison Industries catalog under section 4124(d) of title conduct market research to determine whether the Federal comparable to products available from the private sector needs in terms of price, quality, and time of delivery in the latest edition of the Federal 18, the Secretary of Defense shall Prison Industries product is that best meet the Department's
(b) COMPETITION REQUIREMENT- If the Secretary determines that a Federal Prison Industries product is not comparable in price, quality, or time of delivery to products available from the private sector that best meet the Department's needs in terms of price, quality, and time of delivery, the Secretary shall use competitive procedures for the procurement of the product or shall make an individual purchase under a multiple award contract. In conducting such a competition or making such a purchase, the Secretary shall consider a timely offer from Federal Prison Industries.'; and (c) IMPLEMENTATION BY SECRETARY OF DEFENSE- The Secretary of Defense shall ensure that-(1) the Department of Defense does not purchase a Federal Prison Industries product or service unless a contracting officer of the Department determines that the product or service is comparable to products or services available from the private sector that best meet the Department's needs in terms of price, quality, and time of delivery; and (2) Federal Prison Industries performs its contractual obligations to the same extent as any other contractor for the Department of Defense.
10-61
(d) MARKET RESEARCH DETERMINATION NOT SUBJECT TO REVIEW- A determination by a contracting officer regarding whether a product or service offered by Federal Prison Industries is comparable to products or services available from the private sector that best meet the Department's needs in terms of price, quality, and time of delivery shall not be subject to review pursuant to section 4124(b) of title 18.
10-62
CHAPTER
11
STRUCTURAL INDEX
GENERAL 11.1.1
Scope
APPLICABLE PUBLICATIONS PROJECT DEFINITION (10-15%) CONCEPT DESIGN (30-35%) 11.4.1 Structural System Selection Analysis 11.4.2 Concept Design Analysis 11.4.3 Concept Drawings INTERIM DESIGN (50-60%) 11.5.1 Interim Design Analysis 11.5.2 Interim Specifications 11.5.3 Interim Drawings FINAL DESIGN (Unreviewed 100%) 11.6.1 Design Analysis 11.6.2 Final Specifications 11.6.3 Final Drawings READY TO ADVERTISE (100)% 11.7.1 Design Analysis 11.7.2 Ready-To-Advertise Specifications 11.7.3 Drawings RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS 11.8.1 Mandatory Requirements 11.8.2 Specific Requirements TECHNICAL REQUIREMENTS 11.9.1 General 11.9.2 Design Loads 11.9.3 Foundations 11.9.4 Structural Steel 11.9.5 Steel Joists 11.9.6 Pre-engineered Metal Buildings 11.9.7 Cold-Formed Steel 11.9.8 Steel Roof and Floor Deck 11.9.9 Concrete 11.9.10 Precast Architectural Concrete 11.9.11 Masonry Construction 11.9.12 Antiterrorism/Force Protection 11.9.13 Required Standard Details
11.5
11.6
11.7
11.8
11.9
11-1
11.1.1
This chapter states criteria, requirements, and guidance for structural design. Specific submittal requirements in this chapter supplement the requirements of Chapter 1, titled GENERAL INSTRUCTIONS. All required documents, including drawings and the design analyses, shall be prepared in accordance with Chapter 2, titled PRESENTATION OF DATA. 11.2 APPLICABLE PUBLICATIONS
The issue of the publications listed below form a part of this Manual to the extent indicated by the references thereto. Publications will be referred to hereinafter by basic designation only. Design Manuals: TI-800-03 TI 809-04 TM 5-809-12 Technical Requirements for Design-Build, 01 July 1998 Seismic Design for Buildings, 31 December 1998 Concrete Floor Slabs on Grade Subjected to Heavy Loads, 25 August 1987
Industry Standards: AASHTO Std Spec American Association of State Highway Traffic Officials, Standard Specifications for Highway Bridges, 17th Edition, 2002 Building Code Requirements for Structural Concrete and Commentary, 2002 American Society of Civil Engineers, Minimum Design Loads For Buildings and Other Structures, 2002 International Code Council, International Building Code, 2003 International Code Council, International Residential Code, 2003 Metal Building Manufacturers Association, Metal Building Systems Manual, 2002 Manual for Quality Control for Plants and Production of Architectural Precast Concrete Products, 1996 Architectural Precast Concrete, 1989
PCI Mnl-122
SDI Diaphragm Mnl Steel Deck Institute, Diaphragm Design Manual, 1987 11-2
SSTD 10-99
Southern Building Code Congress International Standard for Hurricane Resistant Residential Construction, 1999
Unified Facilities Criteria (UFC): UFC 1-200-01 Design: General Building Requirements, 31 July 2002
11.3
At the Project Definition phase, the designer must define the specific project requirements and confirm that they can be met within the project constraints. This is normally done through a charrette or other data gathering process. The structural engineer shall also coordinate with the architect at this phase to insure that the architectural floor plan and other architectural features of the project can be framed and constructed economically. The Project Definition submittal will consist of a narrative describing the structural loads, general design criteria and references and any unusual design conditions. The narrative shall include a brief description of the intended structural system or if the size of the project warrants, a description of the structural systems to be used for the comparative analysis. 11.4 CONCEPT DESIGN (30-35%) Structural System Selection Analysis
11.4.1
An economical structural system will be selected to meet the requirements of the design. For projects with a construction value of $10,000,000 or greater, a comparative analysis of two or more competitive structural systems will be required unless indicated otherwise in the Statement of Work (SOW). A portion of each facility large enough to be representative of the entire structure shall be designed in enough detail to provide for an estimate that will be the basis of the structural system selection. The portion of the structure selected for comparing alternate system costs shall include framing for at least one typical bay of the roof, floor, and foundation systems. Additional costs of nonstructural systems attributable to a structural alternative shall be included in the comparative cost estimate for that alternative. Determination of these additional costs must be based upon a concept of the complete building configuration, including architectural, mechanical, electrical, and other systems; hence, the main structural members must be sized to check for compatibility with ceiling, duct, lighting, and all other space demands. The method of providing the required degree of fire-resistance shall be determined for each alternative and the cost must be included. The submittal shall include the following items: a. A complete description, with sketches, of each structural system considered. b. Design calculations supporting the member sizes used for the cost estimate. c. A comparative cost for each system, clearly showing all costs and quantities used. 11-3
d. An analysis of the study results with justification for the system selected. For projects with a construction value of less than $10,000,000, a brief rational justification of the proposed structural system will be presented. 11.4.2 Concept Design Analysis
List all references used in the Concept design including Government design documents, industry standards, and criteria given to designer at the charrette or pre-design meeting. 11.4.2.2 Live Loads
Live load values to be used in the design shall be identified, including roof and floor loads, wind loads, lateral earth pressure loads, seismic loads, etc., as applicable. 11.4.2.3 Lateral Stability Analysis
The method of providing lateral stability for the proposed structural system to meet seismic and wind load requirements shall be described. The analysis shall include sufficient calculations to verify the adequacy of the proposed method of support. 11.4.2.4 Fire Resistance
Materials selected must be in consonance with the fire rating requirements of the structure. 11.4.2.5 Structural Calculations
Calculations for typical roof, floor, and foundation members as applicable for the structural system proposed to be used are required. 11.4.3 Concept Drawings
Sufficient framing plans are required for roof, floors, and foundations, as applicable, to indicate layout of principal members. Typical sections shall be furnished through roof, floors, and foundations indicating materials and type of construction proposed. Drawings will contain a set of general notes indicating design live, wind, and seismic loading, references used in the structural design, and applicable material strengths. 11.5 INTERIM DESIGN (50-60%) Interim Design Analysis
11.5.1
The interim design analysis shall include all items in the concept design analysis and any revisions necessitated by comments on the Concept Submittal. Calculations shall be included for all principal members, including the foundations.
11-4
11.5.2
Interim Specifications
The interim submittal shall include a list of all specification sections to be provided in the final design submittal. Certain projects may, at the users request, require the submittal of redlined specification sections at the interim submittal stage. The specific requirements for a project will be clarified during negotiations. 11.5.3 Interim Drawings
Drawings for this submittal will include roof and floor framing plans, as applicable. All principal members will be shown on the plans. A foundation plan will also be furnished showing main footings and grade beams where applicable. Where beam, column, and footing schedules are used, they will be filled in sufficiently to indicate principal member sizes to be used. Typical bar bending diagrams shall be included if applicable. Typical sections will be furnished for principal roof, floor, and foundation conditions. Slab-on-grade crack control joint locations shall be indicated on plans and appropriate joint details shall be provided. Formed concrete slab crack control joint locations shall be indicated on plans and appropriate joint details shall be provided. Masonry wall control joint locations shall be shown on the structural and architectural plans. Wall joints shall be carefully coordinated between the structural and architectural plans. Masonry walls supported directly by thickened slabs shall insure that the slab crack control joints are located directly below the wall crack control joint. Typical applicable masonry construction details shall be provided. Comments made on the Concept Submittal shall be incorporated into the drawings for this submittal. The general notes will be developed to reflect the interim level of design. 11.6 FINAL DESIGN (Unreviewed 100%) Design Analysis Any
11.6.1
Complete calculations for all structural members shall be included. changes required by comments on the Interim and Concept Design Submittals must be incorporated. 11.6.2 Final Specifications
A set of all redlined specification sections shall be included in the final design submittal. 11.6.3 Final Drawings
Complete final plans and details of all structural elements are required. Structural drawings shall be carefully checked to insure coordination with architectural, site, mechanical, and electrical drawings. Drawings will contain a complete set of general notes indicating design live, wind, and seismic loading, and all references used in the structural design. All applicable material strengths will also be indicated. All roof and floor openings, with details, will be shown on the structural drawings. 11.7 READY-TO-ADVERTISE Design Analysis 11-5 (100)%
11.7.1
A final complete set of structural calculations will be furnished, incorporating all changes made during the process of design. Calculations will be checked and verified by an engineer other than the original designer. 11.7.2 Ready-To-Advertise Specifications
Specification sections will incorporate all comments from previous submittals. All redlines will be removed from the specification sections and the specifications shall be checked for brackets, section references, and publication references. 11.7.3 Drawings All
Drawings will incorporate all comments from previous submittals. drawings shall be verified, finalized, and consistent with the specifications. 11.8 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS
TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs. 11.8.1 Mandatory Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development: a. List all structural references, codes, and standards to be used in the design, including Government design documents, industry standards, and criteria given to the designer at the design charrette or predesign meeting. b. List the wind speed, building classification category, and exposure category. c. List the seismic short period spectral acceleration value (Ss) and the one second period spectral acceleration value (S1) for a 2% probability of exceedance in 50 years, the building classification category and the seismic use group. Provide the seismic site classification or address the appropriate method to derive the seismic site classification. d. List any specific live loads such as vehicular loads, cranes, special equipment loads, hanging loads, etc. State locations, weights, and special support requirements. e. List any special structural requirements such as floor tolerances or deflection criteria, which deviates from IBC 2003. f. g. 11.8.2 List any restrictions on types of structural systems. See TI 800-03 for additional mandatory requirements.
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria:
1. Include specific technical criteria to include minimum material strengths. 2. Include specific quality control items such as sample panels and inspection requirements. b. Partial Project Criteria:
1. The Partial Project Criteria shall include all of the information required in the Nominal Project Criteria. 2. Include desired column locations on the architectural drawings. 2. 3. c. Include list of recommended structural systems. Include guide specifications.
Full Project Criteria: Final Drawings (See description above under 11.6.3 FINAL
1. DESIGN.)
2. Final Specifications (See description above under 11.6.2 FINAL DESIGN.) NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements. 11.9 TECHNICAL REQUIREMENTS General
11.9.1
a. Structural design shall be in accordance with the criteria, requirements, and guidance provided in IBC 2003 as modified by UFC 1200-01 and the following requirements. Local building codes shall not be used. b. The designer's Structural Engineer is responsible for insuring that all mechanical and electrical equipment and other auxiliary building features such as sprinkler piping, etc. are properly supported and that all architectural features are adequately framed and connected. The structural engineer is also responsible for the design of all lesser structures such as utility vaults, pits, retaining walls, etc., although they may be shown on other disciplines drawings. c. When future expansion of buildings or facilities is planned, it is especially important that the provisions made for the expansion are carefully developed and shown on the drawings. d. Building structural details will be shown on the structural drawings and not intermixed with architectural plans and details. 11-7
11.9.2
Design Loads
Load assumptions shall be in accordance with IBC 2003 and UFC 1-200-01 with the following modifications. 11.9.2.1 Wind Load Criteria
The design requirements of ASCE 7-02 will be used, except for one and two family housing. Local building code requirements do not apply and will not be used. Wind-load criteria to be used for one and two family housing shall be as set forth in IRC 2003. Family housing projects located near coastal areas of the Gulf of Mexico and the Atlantic Ocean shall comply with the design requirements of SSTD 10-99. 11.9.2.2 Seismic Load Criteria
a. Family Housing. Seismic criteria used for one and two family housing shall be in accordance with IRC 2003. b. Bridges. Seismic criteria used for bridges shall be as set forth in the AASHTO Std Spec. c. All Other Structures. Seismic criteria used for structures other than family housing and bridges shall be in accordance with IBC 2003, as modified by UFC 1-200-01. UFC 1-200-01 requires the use of TI 809-04 for buildings classified as Seismic Use Group III as defined in IBC 2003, Table 1604.5 and within Seismic Design Category D, E or F as defined by IBC 2003, paragraph 1616.3. 11.9.3 Foundations
A minimum safety factor of 1.5 shall be provided against uplift, sliding, overturning, or flotation. All below grade column base plates and anchor bolts shall be completely encased in concrete. All below grade steel columns shall be completely encased in concrete or coated with coal tar epoxy. 11.9.4 Structural Steel
Steel structures shall be designed in accordance with IBC 2003. Shop connections for structural steel will be welded, and field connections will generally be made with high-strength bolts, ASTM A325 bearing-type connections. Connection angles shall be a minimum 5/16 inch thick and bolts shall be a minimum inch in diameter. All connections other than standard AISC beam connections will be designed by the structural engineer and detailed on the final plans. When standard AISC beam connections are used, beam end reactions will be provided on the drawings. Design responsibility for all connections remains with the designer's Engineer of Record. Unless the structure involves very minor structural steel fabrication, the structural steel specification will be edited to include the requirement that the steel fabricator shall be certified by the AISC Quality Certification Program for the appropriate category. For steel framed floor systems, design calculations shall be submitted demonstrating that the floor system is acceptable in accordance with the AISC Steel Design Guide Series #11: Floor Vibrations Due to Human Activity. 11.9.5 Steel Joists
11-8
Steel joist construction will be in accordance with IBC 2003. Joists will be anchored to steel supports by bolting or field welding. Steel insert plates will be provided in concrete work as required. Maximum joist spacing will be 2.5 feet for floors and, generally, 4.0 feet for roofs. Where top chords are extended, the required section modulus of extensions will be shown on the drawings. Where equipment is hung from joists, details of joist reinforcement at hangar locations shall be provided on the drawings. Floors shall be designed to prevent excessive vibration. For steel framed floor systems, design calculations shall be submitted demonstrating that the floor system is acceptable in accordance with the AISC Steel Design Guide Series #11: Floor Vibrations Due to Human Activity. 11.9.6 Pre-engineered Metal Buildings
Pre-engineered metal buildings shall be designed in accordance with the 2002 edition of the MBMA MBSM, except seismic loads shall be in accordance with IBC 2003 and all other loads shall be in accordance with the ASCE 7-02, except as noted. The metal building system shall be provided by a single manufacturer and shall include all components and assemblies that form the building including the standing seam metal roof system. The metal building system shall be required to be the product of a recognized steel building systems manufacturer who has been chiefly engaged in the practice of designing and fabricating metal building systems for a period of not less than 5 years. The erector shall be required to have specialized experience in the erection of steel building systems for a period of at least 3 years. When pre-engineered buildings are used in conjunction with masonry, deflection of the building frame shall be limited to H/600 to prevent cracking of the masonry. 11.9.7 Cold-Formed Steel
a. Roof Trusses. Generally, cold-formed steel trusses shall be pre-engineered and pre-fabricated in the manufacturers plant from system components specifically manufactured for trusses. Trusses designed and fabricated from standard light gauge framing members and field fabricated trusses shall be limited to only minor trusses. The designer shall provide proper truss load diagrams on the drawings. The diagrams shall show the design span length and all appropriate load components. Details showing required bearing conditions and connections shall be shown on the contract drawings. A special specification section shall be prepared for the cold-formed steel roof trusses. The truss fabricator shall be required to have a minimum of three years experience in the production of steel roof trusses. Complete shop drawings showing erection plan, bracing, truss configurations, and truss joint connections shall be required to be submitted for approval. b. Generally, cold-formed steel framing is not allowed for axial load bearing systems or floor framing. Cold-formed steel framing is allowed for exterior walls not supporting axial loads, bracing, ceiling, soffit and fascia framing. Cold-formed steel framing shall be designed in accordance with IBC 2003. All cold-formed steel framing shall be formed from steel that conforms to the requirements of ASTM A-653, Grade 33 or higher, having a minimum yield of 33 ksi. Minimum uncoated steel thickness (design thickness times 0.95) shall be 0.0329 inches (20 gage). All cold-formed steel framing, connectors, etc. shall receive a G60 galvanized coating. Deflection of exterior wall studs supporting masonry shall be limited to l/600.
11-9
11.9.8
Where steel roof and floor deck is used, the required section modulus and moments of inertia shall be shown on the drawings. The type and quantity of decking connectors to be used to resist computed wind uplift and shear diaphragm forces shall be clearly detailed on the final plans. Steel deck diaphragms shall be designed in accordance with the SDI Diaphragm Mnl. All decking shall have a minimum galvanized coating conforming to ASTM A653, G60. Steel roof deck material shall have a minimum thickness of 0.0295 inch (22 gage); non-composite steel form decking shall have a minimum thickness of 0.0179 inch (26 gage); composite steel form deck shall have a minimum thickness of 0.0295 inch (22 gage). When the underside surface of large areas of steel decking is exposed to view and indicated to be finish painted, the underside surface of the steel decking will be specified to be factory cleaned and factory primed with a finish paint compatible primer. 11.9.9 Concrete
Concrete design and detailing shall be in accordance with IBC 2003 except as indicated below: a. All edge or spandrel beams shall have continuous reinforcing top and bottom. As a minimum, 2 #5 bars, top and bottom shall be used. Beams shall have continuous ties at a maximum spacing of 16 inches. b. Floor slabs-on-grade shall be a minimum of 4 inches thick and reinforced with a minimum of 0.15 percent welded wire fabric, provided in flat sheets, or deformed bars. Reinforcement shall be placed approximately 1-1/2 inches from top of slab. Floor slabs-on-grade subject to heavy loads shall be designed in accordance with TM 5-809-12. Floor slabs-on-grade shall be divided by crack control joints spaced a maximum of 25 feet on center. Slab areas created by crack control joints shall be as near as square as possible; slab area lengths shall not be greater than twice the width. In addition, reentrant corners in slabs and discontinuous joints shall be reinforced with two #4 bars, 4 feet long. Slabs-on-grade to receive moisture sensitive finishes shall be placed on a minimum 15 mil vapor barrier. c. Reinforcing of concrete walls, continuous footings, and tie and bond beams shall be continuous and, therefore, typical details showing the arrangement of reinforcing at corners and intersections of these members shall be shown on the drawings. 11.9.10 Precast Architectural Concrete
Precast architectural concrete panels shall be configured to prevent notches or excessive cutouts along the perimeter of the panels. Additional reinforcing shall be provided at corners, notches, and cutouts to prevent cracks in the panels. Precast concrete panels shall be waterproofed. Precast concrete panels shall be designed and fabricated by an experienced and acceptable precast concrete manufacturer certified under either the Precast/Prestressed Concrete Institute or the National Precast Concrete Association Plant Certification Program. Precast design shall conform to ACI 318/318R and PCI Mnl-122. Precast concrete panels shall be manufactured and cured in accordance with the applicable provisions of PCI Mnl-117. Units shall be set true to alignment and level, with joints properly spaced and aligned both vertically and horizontally. Erection tolerances shall be in accordance with the requirements of PCI Mnl-117 and PCI Mnl-122. 11-10
11.9.11
Masonry Construction
Masonry construction shall be designed in accordance with IBC 2003. All structural masonry walls (load bearing walls, shear walls, or exterior walls) shall be designed as reinforced masonry, neglecting the tensile strength of masonry. Nonstructural masonry walls may be designed as unreinforced masonry. However, the minimum reinforcement in bond beams and around openings given for structural walls shall be incorporated. a. Minimum thickness of structural masonry walls shall be 8 inches. Minimum bar size shall be #4. Minimum reinforcement for structural masonry walls shall be as follows: one vertical reinforcing bar provided continuously from support to support at each wall corner, at each side of each opening, at each side of control joints, at ends of walls, and elsewhere in the wall panels at a maximum spacing of 48 inches. This minimum reinforcement shall be the same size as the minimum vertical reinforcement provided for flexural stresses. b. Horizontal reinforcement in continuous masonry bond beams shall be provided continuously at floor and roof levels and at the tops of all walls. Horizontal reinforcement shall also be provided above and below all wall openings. These bars shall extend a minimum of 40 bar diameters, but not less than 24 inches, past the edges of the opening. For masonry laid in running bond, the minimum horizontal reinforcement shall be two #5 bars per bond beam. Lintel units shall not be used in lieu of bond beam units. c. Exterior and interior masonry walls shall have vertical control joints as follows: at 24 feet maximum, at changes in wall height or thickness, near wall intersections, at points of stress concentration, at control joints in foundation walls and control joints in floors that support masonry walls, and as otherwise noted in UFC 1200-01. d. Particular attention will be given to details for the reinforcement of masonry construction. The horizontal and vertical wall reinforcement and reinforcement around openings and at all lintels shall be clearly shown on the structural drawings and coordinated with the sections and details on the architectural drawings. Masonry control joint and expansion joint locations shall be shown on the drawings. Joint locations and location of and details between bond beams and reinforcing may be shown on the architectural plans and sections, but will be checked by the designer's Structural Engineer for structural adequacy. 11.9.12 Antiterrorism/Force Protection
Antiterrorism/Force Protection design shall be in accordance with Chapter 19,titled ANTITERRORISM/FORCE PROTECTION. 11.9.13 Required Standard Details
Certain standard structural details are required, as applicable, on all projects. Typical masonry details shall be furnished showing details of horizontal and vertical wall reinforcement, reinforcement around openings and at lintels, and masonry control joints and brick expansion joints.
11-11
12.1
GENERAL 12.1.1
Scope
12.2 12.3
APPLICABLE PUBLICATIONS PROJECT DEFINITION (10-15%) 12.3.1 General Considerations 12.3.2 Project Definition Narrative CONCEPT DESIGN (30-35%) 12.4.1 General Considerations 12.4.2 Concept Design Analysis 12.4.3 Specifications 12.4.4 Concept Drawings INTERIM DESIGN (50-60%) 12.5.1 Interim Design Analysis 12.5.2 Specifications 12.5.3 Interim Drawings FINAL DESIGN (Unreviewed 100%) 12.6.1 Final Design Analysis 12.6.2 Specifications 12.6.3 Final Drawings READY-TO-ADVERTISE (100%) RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS 12.8.1 12.8.2 Mandatory Requirements Specific Requirements
12.4
12.5
12.6
12.7 12.8
12.9
TECHNICAL REQUIREMENTS 12.9.1 General Considerations 12.9.2 Plumbing Considerations 12.9.3 Seismic Protection
12-1
CHAPTER 12 PLUMBING
12.1
GENERAL Scope
12.1.1
This chapter provides guidance for preparation and development of plumbing (including compressed air, fuel gas, and medical gas systems). Specific design submittal requirements in this chapter supplement the requirements in Chapter 1, titled GENERAL INSTRUCTIONS. All required documents, including drawings and design analysis, shall be in accordance with Chapter 2, titled PRESENTATION OF DATA.
12.2
APPLICABLE PUBLICATIONS
The publications listed below, but referred to thereafter by basic designation only, form a part of this Manual. These publications are supplemented by the UFGS Guide Specifications to form design criteria. Lead Design Manual: TI-800-01 Design Build Manual: TI-800-03 Design Build Instructions Design Criteria
International Plumbing Code: Latest Edition at time of Project Solicitation Issue Date (Advertise Date). Unified Facilities Criteria (UFC): UFC 3-420-01FA Design: Plumbing
Supplemental Air Force Design Manuals: MIL-HDBK-1190 MIL-HDBK-1191 Facility Design Guide Facility Design Guide Medical
Department of the Army Technical Manuals (TM): TM 5-810-5 TM 5-810-4 Plumbing Compressed Air
UFGS Guide Specifications/ Mobile District Guide Specifications: Specifications are updated on a regular basis. Instructions on Retrieving UFGS Specifications are covered in Chapter 3, SPECIFICATIONS.
12-2
12.3
12.3.1
At the Project Definition phase the designer shall define the customer's requirements and confirm that they can be met within the project's constraints. To that end, a comprehensive interface with the customer is required generally through a Charrette or other previously approved data gathering process. The primary purpose of the design process at this stage is to gather any information from the customer that would be necessary in the design of the facility. Also, the design preferences of the customer should be obtained for compliance if possible. The general plumbing system type and purpose along with an order- ofmagnitude estimate of major equipment sizes will be provided at the Project Definition phase for use in preparing the cost estimate and sizing the required mechanical spaces. 12.3.2 Project Definition Narrative
The Project Definition narrative shall include, but not be limited to, the following items as applicable: (a) List all references used in the Project Definition design including Government design documents, industry standards, safety manuals, and criteria given to designer at the charrette or predesign meeting. (b) Explain proposed type of the plumbing system.
(c) List the major equipment and give the sizes in general orderof- magnitude. (d) Describe any demolition required.
(e) List any environmental concerns and actions to be taken to address them. 12.4 CONCEPT DESIGN (30-35%) General Considerations
12.4.1
At the Concept design stage of project development, it is recognized that all calculations are preliminary for analysis purposes and only indicate approximate capacities of equipment. Any dimensions and sizes required are order-of-magnitude figures, conversationally stated, to insure adequate space for installation and maintenance of equipment and utility elements such as piping, etc., in congested areas. Equipment shown in plans and sections need not be shown in great detail but is shown merely as simple geometric forms with approximately correct dimensions. Piping layouts shown are simple main pipe runs showing general location, routing and, when applicable, approximate order-of-magnitude sizes. 12-3
Schematic diagrams are simplified. The purpose of the schematic is only to show system design intent and the basic principle of system operation. 12.4.1.1 Drawings and sketches. Scale of concept drawings will generally be smaller than the working drawings. Plans and sections need be only large enough to properly show pertinent information. Sketches, neatly drawn, will be acceptable when sufficient to show pertinent information or to convey basic system concepts. Quantity of concept drawings is to be kept to the minimum number required to convey basic systems information. Some mechanical information required in the Concept submission may logically be included on other discipline drawings or in sketch form in the design analyses and need not be completed on formal drawings. 12.4.2 Concept Design Analysis
The Concept Design Analysis shall include but not be limited to the following items as applicable: (a) List all references used in the Concept design including Government design documents, industry standards, criteria given to designer at pre-design meeting, etc. (b) Provide justification and a brief description of the types of plumbing fixtures, piping materials, and equipment proposed for use. (c) Prepare basic preliminary calculations for systems such as sizing of domestic hot water heater and piping, compressed air piping, compressors and receivers, vacuum piping, vacuum pumps and receivers, natural gas piping, and container gas piping and tanks. (d) 12.4.3 Describe any demolition required.
Specifications
Provide a basic outline in accordance with Chapter 3, SPECIFICATIONS. 12.4.4 Concept Drawings
The Concept design drawings should include, but not be limited to, the following items as applicable: (a) Indicate locations and general arrangement of plumbing fixtures and major equipment. (b) Indicate location and extent of any demolition that will be required concerning the plumbing system.
12.5
In addition to the following items, the designer shall incorporate or answer all comments received from the COE and customer concerning the Concept submittal.
12-4
12.5.1
The Interim Design Analysis shall include all items in the Concept design analysis and any necessary revisions. In addition, the following specific items shall be included when applicable: Provide detailed calculations for the sizing of the following systems: domestic hot water, domestic cold water, waste and vent, natural and LP gases, vacuum, compressed air, distilled or deionized water, medical gases, and other specialty systems. Identify and address any security requirements. 12.5.2 Specifications
The outline specifications previously submitted for concept phase shall be revised, updated, further developed and resubmitted in accordance with Chapter 3, titled SPECIFICATIONS. 12.5.3 Interim Drawings
The Interim drawings should show all information given on the concept drawings but in greater detail. In addition, the Interim drawings should include, but not be limited to, the following items as applicable: (a) Include plan and isometric riser diagrams of all areas including hot water, cold water, waste, and vent piping. Piping layouts and risers should also include natural gas (and meter as required), LP gas, vacuum systems, compressed air systems, distilled or deionized water, medical gases, and other specialty systems as applicable. (b) Include equipment and fixture schedules with descriptions, capacities, locations, connection sizes, and other information as required. 12.6 FINAL DESIGN (Unreviewed 100%)
In addition to the following items, the designer shall incorporate or answer all comments received from the COE and the customer concerning Interim submittal. 12.6.1 Final Design Analysis
The Final Design Analysis shall include all of the information required in the Interim submittal in its final form and Incorporate or answer all comments received from the COE or the customer. 12.6.2 Specifications
Marked-up draft specifications shall be submitted in accordance with Chapter 3, titled SPECIFICATIONS. Specifications used shall be those acquired subsequent to the Interim submittal.
12-5
12.6.3
Final Drawings
The Final drawings for plumbing systems should be in a Ready-toAdvertise state which should include, but not be limited to, the following items as applicable. (a) Plans, sections, details and riser diagrams in final condition. (b) Complete all legends and schedules.
(c) Complete all narratives, notes, and title blocks as necessary. 12.7 READY-TO-ADVERTISE (100%)
The comments generated concerning the Final submittal shall be incorporated in the design documents before they are submitted as "Ready-to-Advertise." 12.8 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS
TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs. 12.8.1 Mandatory Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development: a. Mandatory energy and water conservation criteria. Title 10 CFR, Subpart A, Part 435, Energy Conservation Voluntary Performance Standards for New Commercial and Multi-family High Rise Residential Buildings, Mandatory For New Federal Buildings Published January 30, 1989; Public Law 100-615, Federal Energy Management Improvement Act of 1988, November 5, 1988; Public Law 102-486, Energy Policy Act of 1992; Executive Order 12902, Energy Efficiency and Water Conservation at Federal Facilities, dated March 8, 1994; and Department of Defense energy goal requirements. b. Codes and Standards. Water supply, backflow prevention, and drainage at Army installations will comply with the International Plumbing Code. c. Special Plumbing Requirements (handicap requirements, low flow requirements, maximum hot water requirements, dilution basins, grease separators, sewage ejection, etc.). d. See TI 800-03 for additional mandatory requirements.
12-6
12.8.2
Specific Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria:
1. Include a paragraph describing the plumbing system, any major features such as pressure booster pumps, well requirements, etc. and any special plumbing requirements such as handicap requirements, low flow requirements, maximum hot water requirements, dilution basins, grease separators, sewage ejection, etc. b. Partial Project Criteria:
1. Include a paragraph describing the plumbing system, any major features such as pressure booster pumps, well requirements, etc. and any special plumbing requirements such as handicap requirements, low flow requirements, maximum hot water requirements, dilution basins, grease separators, sewage ejection, etc. 2. systems. 3. c. Describe the pipe materials to be used on all plumbing
1. Final Plumbing Plans (See description above under 12.6.2 FINAL DESIGN.) 2. Final Specifications (See description above under 12.6.1.1 FINAL DESIGN.) NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements. 12.9 TECHNICAL REQUIREMENTS General Considerations
12.9.1
Coordinate space requirements, foundations, supports, pipe routing, electrical service, and the like for mechanical items with architectural, structural, and electrical design elements. Coordinate exterior mechanical distribution systems with design elements handling other exterior utility designs and site work. Standard or "packaged" equipment shall be used to the greatest extent possible to simplify specifying, purchasing, installation, and maintenance of equipment. TI 800-01, Design Criteria, is the prime design manual. For Army and Air Force projects, UFC 3-420-01FA supplements it. UFC 3-420-01FA 12-7
references the International Plumbing Code. For Air Force projects, MIL-HDBK-1190 and MIL-HDBK-1191 supplements it. For Army projects various manuals in the TM 5-810 series supplement it. In case of conflict, TI 800-01, Design Criteria governs. The requirements listed hereinafter are Mobile District requirements and take precedence over referenced criteria. 12.9.2 Plumbing Considerations
(a) Piping System Piping materials and sizes shall comply with the recommendations in the International Plumbing Code and TM 5-810-5. Flow velocities in water pipe shall not exceed 10 feet per second. All piping shall be sloped to permit complete drainage and shall be properly supported with allowances for expansion and contraction. Expansion loops or expansion joints and anchor points shall be shown on plumbing drawings. Piping subject to freezing shall be suitably protected. (b) Wall Hydrants and Lawn Faucets The maximum spacing between wall hydrants or between lawn faucets around the perimeter of a building is 200 feet. Add 5 gpm for each hydrant or faucet to building load for sizing water main. (c) Floor Drains Floor drains shall be provided in all boiler and mechanical equipment rooms and adjacent to each emergency deluge shower. Provide trap primers for all floor drains unless specified otherwise. (d) Backflow Prevention The water distribution system shall be protected against the flow of water or other liquids into the distributing pipes from any unintended source or sources. Refer to the International Plumbing Code for requirements on all systems. (e) Domestic Hot Water In the design of any buildings in which water closets and showers are installed, the designer shall exercise the necessary precautions to prevent personnel from being scalded while taking showers due to simultaneous operation of water closets equipped with flush valves. (1) Domestic Hot Water Temperature Domestic hot water supply maximum temperatures at the point of use will be as follows for the indicated facilities or areas unless higher temperatures are required for sanitizing or special processes: (a) In all latrines, heads, and toilet facilities without showers or tubs, the actual measured temperature of hot water delivered to the user shall not exceed 130 F. (b) In all latrines, heads, and toilet facilities with showers or tubs, the actual measured temperature of hot water delivered to the user shall not exceed 120 F. (c) In buildings such as BOQ's and BEQ's where there may be toilet facilities both with and without showers or tubs, where there is both heavy and frequent use of the bathing facilities, where
12-8
there is a common hot water supply system, the delivered temperature of 120 F may be used for all facilities. (d) In buildings such as administrative, where showers are provided only in a few special cases, such as for the commanding officer and duty officer, the delivered water temperature shall exceed 120 F. The same condition shall prevail in laboratory and special buildings where showers are provided for emergency or exceptional use, or where the number of users or frequency of use is low. (2) It is recognized that in some older buildings or in some unusual cases it may be necessary to do more than reset existing temperature controllers. In some cases, added storage tanks, temperature blending equipment, or separate lines might be required. (3) Domestic hot water requirements for medical facilities will be as specified in Mil Handbook 1191. (f) Compressed Air Unless requirements are stated in specific instructions, compressed air system and compressor sizes will be determined by the designer from analysis of equipment layout and/or coordination with the customer's requirements. Design shall be in accordance with TM 5-810-4. (g) Fixture Selection All specifications and references to outfit numbers and figure numbers shall be as defined in Federal Specification WW-P-541D. Unless they are an integral part of the fixture, bathroom and toilet accessories, such as prefabricated shower stalls, towel bars, mirrors, etc., shall be included in other specifications. (l) Equipment Schedules
(a) Plumbing Fixtures Each set of drawings for a project or building shall include one or more fixture schedules that will designate the symbols, P numbers, outfit numbers, description, and sizes of connections. (b) Other Equipment The equipment information indicated in "Equipment Notes" in TM 5-810-5 will be supplemented, expanded as required and put on drawings as Equipment Schedules. (k) Plumbing shall not traverse over or under electrical panels or switchboards. 12.9.3 Seismic Protection
All piping, equipment, and utilities shall be protected in accordance with TM 5-809-04.
12-9
13.1
GENERAL 13.1.1
Scope
APPLICABLE PUBLICATIONS ENERGY BUDGET AND ECONOMIC STUDIES PROJECT DEFINITION (10-15%) 13.4.1 General Considerations 13.4.2 Project Definition Narrative CONCEPT DESIGN (30-35%) 13.5.1 General Considerations 13.5.2 Concept Design Analysis 13.5.3 Concept Drawings INTERIM DESIGN (50-60%) 13.6.1 Interim Design Analysis 13.6.2 Interim Drawings FINAL DESIGN (Unreviewed 100%) 13.7.1 Specifications 13.7.2 Final Design Analysis 13.7.3 Final Drawings READY-TO-ADVERTISE (100%) 13.8.1 Specifications RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS 13.9.1 13.9.2 Mandatory Requirements Specific Requirements
13.5
13.6
13.7
13.8
13.9
13.10
TECHNICAL REQUIREMENTS 13.10.1 General Considerations 13.10.2 HVAC Design Considerations l3.10.3 Seismic Protection
13-1
13.1
GENERAL Scope
13.1.1
This part of the chapter provides guidance for preparation and development of the following design aspects: heating, ventilating, air conditioning (including chilled water and dual temperature water distribution systems). Specific design submittal requirements in this chapter supplement the requirements in Chapter 1, titled GENERAL INSTRUCTIONS. All required documents, including drawings and design analysis, shall be in accordance with Chapter 2, titled PRESENTATION OF DATA.
13.2
APPLICABLE PUBLICATIONS
The issue of the publications listed below, but referred to thereafter by basic designation only, form a part of this Manual. These are supplemented by the Corps of Engineers Guide Specifications (CEGS) to form design criteria. Design Manuals: TI 800-01 TI-800-03 TI-809-04 Design Criteria Design Build Instructions Seismic Design for Bldgs.
Unified Facilities Criteria (UFC): UFC 3-410-01FA Design: Heating, Ventilating, and Air Conditioning Design: Energy Conservation
UFC 3-400-01
American Society of Heating, Refrigeration, and Air Conditioning Engineers (ASHRAE) Inc. Standards: Latest Editions at time of Project Solicitation Issue Date (Advertise Date). Sheet Metal and Air Conditioning Contractors' National Association (SMACNA) Inc.:
13-2
Latest Editions at time of Project Solicitation Issue Date (Advertise Date). and Balancing UFGS Guide Specifications/ Mobile District Guide Specifications: Specifications are updated on a regular basis. Instructions on Retrieving UFGS Specifications are covered in Chapter 3, SPECIFICATIONS.
13.3
ENERGY CONSERVATION
The building HVAC systems shall be designed in accordance with UFC 3400-01. The criteria provides manditory and prescriptive criteria that must be followed in order to provide an energy efficient facility. 13.4 PROJECT DEFINITION (10-15%) General Considerations
13.4.1
At the Project Definition phase the designer must define the customer's requirements and confirm that they can be met within the project's constraints. To that end, a comprehensive interface with the customer is required generally through a charrette or other previously approved data gathering process. The primary purpose of the design process at this stage is to gather any information from the customer that would be necessary in the design of the facility. Also, the design preferences of the customer should be obtained for compliance if possible. The general HVAC system type and purpose along with an order-ofmagnitude estimate of major equipment sizes will be provided at the Project Definition phase for use in preparing the cost estimate and sizing the required mechanical spaces. 13.4.2 Project Definition Narrative
The Project Definition narrative shall include, but not be limited to, the following items as applicable: (a) List all references used in the Project Definition design including Government design documents, industry standards, safety manuals, and criteria given to designer at the Charrette or predesign meeting. (b) Explain purpose and proposed type of the environmental system (i.e., personnel comfort, process or computer cooling, freeze protection or otherwise). (c) List manditory and prescriptive HVAC features to be included in the design as required by UFC 3-400-01 in order to provide an energy efficient facility. (d) State the design conditions including indoor and outdoor temperatures, relative humidities for summer and winter conditions, filtration and ventilation requirements, personnel loads, special equipment loads, etc.
13-3
(e) State the proposed building characteristics including 'U' Factors of walls, floors, roofs, windows, etc., orientation of the building, latitude and longitude of location, and any special conditions that would have an impact on HVAC design. (f) List the major equipment and give the sizes in general orderof- magnitude. (g) Briefly describe the proposed control system type. Specific Base Criteria. See
(h) Discuss requirements for natural gas, fuel oil, and water flow meters. (i) Describe any demolition required.
(j) List Force Protection, Sustainable Design, or Seismic Protection concerns. 13.5 CONCEPT DESIGN (30-35%) General Considerations
13.5.1
At the Concept design stage of project development, it is recognized that all calculations are preliminary for analysis purposes and only indicate approximate capacities of equipment. Any dimensions and sizes required are order-of-magnitude figures, conversationally stated, to assure adequate space for installation and maintenance of equipment and utility elements such as piping, ductwork, etc., in congested areas. Equipment shown in plans and sections is not shown in great detail but is shown merely as simple geometric forms with approximately correct dimensions. Piping layouts shown are simple main pipe runs showing general location, routing and, when applicable, approximate order-of-magnitude sizes. Control valves, check valves, etc., are shown only as required to indicate function of the system. Only routing of main headers feeding batteries of water coils are shown, not individual lines to coils unless required for clarity of the system. Schematic diagrams are simplified. System flow diagrams, layouts, and one of each type of take-off, branch, or feed must be shown but not all individual branches. The purpose of the schematic is only to show system design intent and the basic principle of system operation. Drawings and sketches. Scale of concept drawings may be smaller than the working drawings. Plans and sections need be only large enough to properly show pertinent information. Sketches, neatly drawn, will be acceptable when sufficient to show pertinent information or convey basic system concepts. Quantity of concept drawings are to be kept to the minimum number required to convey basic systems information. Some mechanical information required in the Concept submission may logically be included on other discipline drawings or in sketch form in the design analyses and need not be completed on formal drawings.
13-4
Throughout the design submittals and on the Ready-to-Advertise drawings, abbreviations used on drawings shall conform to ASHRAE Fundamentals and shall be indicated in the mechanical drawing legend. 13.5.2 Concept Design Analysis
The Concept Design Analysis shall include, but not be limited to, the following items as applicable: (a) List all references used in the Concept design including Government design documents, industry standards, safety manuals, criteria given to Designer at predesign meeting, etc. (b) Explain purpose of the environmental system (i.e., personnel comfort, process or computer cooling, freeze protection or otherwise). (c) List manditory and prescriptive HVAC features to be included in the design as required by UFC 3-400-01 in order to provide an energy efficient facility. (d) State the design conditions including indoor and outdoor temperatures, relative humidities for summer and winter conditions, filtration and ventilation requirements, personnel loads, special equipment loads, etc. (e) State building characteristics including 'U' Factors of walls, floors, roofs, windows, etc., orientation of the building, latitude and longitude of location, and any special conditions that would have an impact on HVAC design. (f) Prepare basic calculations such as typical room loads, block loads for heating and cooling systems, approximate CFM, GPM (or applicable units) quantities, and a balance flow diagram showing quantities of air handled and circulated throughout each building as a whole (including quantities for outside and exhaust air). (g) Briefly describe the proposed sequence of control for temperature, humidity, ventilation, etc. (h) Discuss requirements for natural gas, fuel oil and water flowmeters. (i) (j) Describe any demolition required. Provide a basic outline specification in accordance with Chapter 3, titled SPECIFICATIONS.
(k) Describe actions to be taken to address Force Protection, Sustainable Design, or Seismic Protection concerns.
13.5.3
Concept Drawings
The Concept design drawings should include, but not be limited to, single-line layouts of heating and air conditioning systems showing equipment and contemplated zoning for each building. Drawings shall indentify rooms and be sufficiently complete to show the location,
13-5
arrangement, approximate capacities of all major items of equipment, and space allocated for servicing and maintenance. Include the following items: (a) Single-line layouts of HVAC systems with preliminary representative duct sizes of main runs and air quantities. This includes exhaust systems and makeup air systems. Representative sections of ducts in congested areas should be shown double line. (b) Component parts of air handling equipment should be indicated (e.g, fan, coils, filters, etc.). (c) Show required maintenance space for all major equipment, preferably with dashed lines. (d) Show major piping single line with approximate size.
(e) Indicate preliminary approximate capacities of all major equipment, including horsepower of motors, KW of major electric heating elements, cfm of major air handlers, cooling and heating capacities, etc. (f) Indicate location and extent of any demolition that will be required concerning the HVAC system.
13.6
In addition to the following items, the designer shall incorporate or answer all comments received from the COE and the customer concerning the Concept submittal. 13.6.1 Interim Design Analysis
The Interim Design Analysis shall include all items in the Concept design analysis and any necessary revisions. In addition, the following specific items shall be included when applicable: (a) Provide detailed calculations for the following: heating loads, cooling loads, piping, ductwork, equipment sizing,etc. Computer calculations shall include print out of input data as well as output. (b) Equipment selection: Equipment selection shall be based on not less than three manufacturers whose equipment meets project requirements for each item. The design analysis shall include catalog cuts of all major equipment (e.g., air handlers, coils, chillers, condensing units, boilers, pumps, fans, unit heaters, heat exchangers, etc.) used as the basis of the design indicating manufacturer, model number, dimensions, capacities, and electrical requirements. The project design is not complete until the designer is assured that there is sufficient physical space in areas where equipment is to be located to install and to maintain the selected equipment. (c) Include any other information or calculations to verify that the design complies with applicable criteria codes or standards and is satisfactory for intended purposes.
13-6
(d) Major unforeseen costs and any changes from Concept submittal shall be referenced and the impact on energy efficiency shall be indicated. Justification for departures, if any, from the original design recommendations shall be provided. (e) covering engineer controls those in Explanatory notes shall be included in the design analysis all rationale for design which would not be obvious to an reviewing the analysis. Methods of air conditioning and for air conditioning systems shall generally be confined to common use in the industry.
(f) Specifications: The outline specifications previously submitted for concept phase shall be revised, updated, further developed and resubmitted in accordance with Chapter 3, titled SPECIFICATIONS. 13.6.2 Interim Drawings
The Interim drawings should show all information given on the concept drawings but in greater detail. In addition, the Interim drawings should include, but not be limited to, the following items as applicable: (a) Show all duct work and piping, with sizes and flow rates, where necessary for balancing purposes. Indicate the duct work pressures in accordance with SMACNA standards. Include all accessories and appurtenances. (b) Show elementary ladder diagrams and temperature control schematics indicating remote sensors, panel mounted controllers, and thermostats. (c) Show layout and details of the final version of all HVAC systems. The location, arrangement, capacity, and space requirements of all equipment shall be indicated. Selected zones of air distribution shall be sufficiently completed to indicate the solution of the design for the remainder of the system and the precautions taken to coordinate the design with the architectural, structural, and electrical phases of construction. Equipment room layouts shall be sufficiently complete to show piping and duct layouts and access for maintenance. Since equipment rooms represent the most congested areas for both equipment and piping, the following guidelines should be followed when drawings are being prepared. (1) Pipe fittings and accessory details shall be shown.
(2) All duct and fittings in congested areas and mechanical rooms shall be drawn to scale using double-line layouts. In a VAV system, ducts between the AHU and VAV boxes shall be double-lined and ducts downstream of the VAV boxes may be single lined. (3) All equipment shall be outlined to scale, and maintenance or removal space shall be indicated by dashed lines. (4) Removal and replacement space must be considered for the largest and heaviest equipment when a drawing is made.
13-7
(5) In other HVAC plans, sections, and details, these same guidelines shall apply. (d) Show new exterior chilled water, dual temperature water, or steam distribution systems from central energy plants in plan and profile. Show all other exterior piping in plan. (e) The final form of all equipment schedules shall be shown with preliminary equipment data filled in (see the equipment schedules in (Exhibit 13-1). 13.7 FINAL DESIGN (Unreviewed 100%)
In addition to the following items, the designer shall incorporate or answer all comments received from COE and customer concerning Interim submittal. 13.7.1 Specifications
The designer shall provide complete edited draft specifications. The specifications shall be edited and tailored by the designer to meet the requirements of the project under design. The Contractor Submittal Register must be edited and included. The UFGS are GUIDE specifications only. The Designer is to delete what is not needed and add what is needed. Specifications shall be in accordance with Chapter 3, titled SPECIFICATIONS. 13.7.2 Final Design Analysis
The Final Design Analysis shall include all of the information required in the Interim submittal in its final form and the information listed below when applicable: (a) Include flow diagrams with all quantities for both air and water sides of complex HVAC systems for balancing purposes (including all kitchens with commercial hoo systems.) (b) Major unforeseen costs and any changes from Interim or Concept submittals shall be referenced and impact on energy and economic studies shall be indicated. Justification for departures, if any, shall be provided. (c) The designer shall review the prepared plans and specifications and determine that they are in accordance with this Manual and all other criteria and instructions furnished by the COE. It will be the responsibility of the designer to coordinate the HVAC systems with the other trades involved in the building design and to eliminate interference between HVAC equipment and other components of the building. 13.7.3 Final Drawings
The Final drawings should be in a Ready-to-Advertise state which should include, but not be limited to, the following items as applicable: (a) Include all plans, sections, and details in final condition.
13-8
Include all completed legends and schedules. Show all necessary piping schematics in final form. Complete narratives, notes, and title blocks as necessary. Show all temperature control systems as follows: (1) Location of sensors, thermostats, and control panels.
(2) Schematics. diagrams, layouts, legends, narratives, sequences, etc. of the Direct Digital Control System. The narratives and diagrams shall be based on those shown in TM-5-815-3. (3) NOTE: Compatibility with any existing basewide control systems must be insured. 13.8 READY-TO-ADVERTISE (100%)
The comments generated during the Final submittal shall be incorporated in the documents before they are submitted as "Ready-to- Advertise." 13.8.1 Specifications
The Designer shall prepare the final detailed Technical Provisions of the specifications in accordance with Chapter 3, titled SPECIFICATIONS. 13.9 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS
TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs. 13.9.1 Mandatory Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development:
a. The HVAC systems shall be designed and specified to the latest industry standards, codes, and Government regulations. The RFP shall ensure high quality, energy efficient HVAC equipment and systems with minimum maintenance. Design documents shall be submitted and reviewed prior to commencing work on the HVAC system.
b. 13.9.2 See TI 800-03 for additional mandatory requirements.
Specific Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP
13-9
development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria:
1. Include a paragraph describing the HVAC system, any major features such as central equipment and any special HVAC requirements such as clean rooms, kitchens, humidity control, DDC Control System type, etc. b. Partial Project Criteria:
1. Include a paragraph describing the HVAC system, any major features such as central equipment and any special HVAC requirements such as clean rooms, kitchens, humidity control, DDC Control System type, etc. 2. Describe the duct and pipe materials, and insulation to be used on all plumbing systems. 3. c. Include an outline of the specifications to be edited.
1. Final Plumbing Plans (See description above under 13.7.3 FINAL DESIGN.) 2. Final Specifications (See description above under 13.7.1 FINAL DESIGN.) NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements.
13.10
13.10.1
(a) Coordinate space requirements, foundations, supports, duct and pipe routing, electrical service, etc., for mechanical items with architectural, structural, and electrical design elements. Coordinate exterior mechanical distribution systems with design elements handling other exterior utility designs and site work. (b) Standard or "packaged" equipment shall be used to the greatest extent possible to simplify specifying, purchasing, installation, and maintenance of equipment. (c) For all projects, the UFC 3-410-01FA, Design: Heating, Ventilating, and Air Conditioning is the prime design manual. 13.10.2 (a) HVAC Design Considerations Design Temperatures Indoor design temperatures shall be in accordance with
13-10
(2) TM 5-785.
(3) Manual cooling and heating load calculations shall be submitted on forms in accordance with ASHRAE Fundamentals. Computer printouts (program input data as well as output results) shall be submitted for calculations performed by automated procedures. (b) Noise Control All noise control design work shall be in accordance with TM 5-805-4. The sound levels for various applications for both propeller and centrifugal type fans shall be as set forth in the ASHRAE Guide and Data Books. (c) Selection of HVAC Systems UFC 3-400-01 shall be used in the selection and efficiencies of the HVAC system. Mandatory and Prescriptive requirements must be met unless an energy budget analysis is performed to prove the selected system is the most efficient and cost effective over the life of the facility. The Users request for a specific type of equipment shall be honored if at all possible or feasible. (d) Energy Saving Controls and Heat Recovery Devices 3-400-01 compliance. (e) Water Chillers Insure UFC
(1) Chillers greater than 200 tons shall be centrifugal, helical rotary screw or absorption type. Centrifugal or absorption machines of less than 200 tons capacity may be used at the discretion of the designer or at the request of the user. Insure UFC 3-400-01 compliance. When packaged water chillers, packaged air conditioning units, or packaged air-cooled air conditioning units are equipped with reciprocating compressors, the total capacity of any one packaged unit shall not exceed 200 tons. A single packaged unit of any type shall not contain more than eight compressors. (2) For loads greater than 400 tons, an Energy Cost Budget Study in accordance with UFC 3-400-01 and a life-cycle cost study shall be made to determine whether two or three machines may be more economical than a single machine. In no case, where only personnel comfort is involved, shall consideration be given to a standby machine. Similarly, standby chilled water and condensing water pumps are not authorized for personnel comfort applications. Exception to this policy may be granted in accordance with UFC 3-410-01FA. (3) Water Cooled When specifying a water cooled chiller system, a complete description of the cooling water treatment, automatic blowdown control, and cooling tower construction will be included. (4) Humid Areas The following criteria shall also be applied to humid areas as defined in UFC 3-410-01FA. The cooling capacity of chilled water systems of 100 tons and over shall be divided between two chillers to insure reliability and constant chilled water supply without temperature fluctuations, to prevent short cycling, and to minimize hot gas bypass. The combined capacity of the two chillers
13-11
shall not exceed the total requirement, including diversity. Selection of chiller capacity should be based on the analysis of part load operating hours for extended periods at low load conditions. (f) Air Handling Systems
(1) Central station type package air handling units complete with filters, coils, and fan sections will be utilized where commercially available. Size and number of package units will be dependent upon availability and design considerations. (2) Central station built-up systems comprised of filters, coils, and fan will be installed where system requirements cannot be satisfied with the factory-assembled package equipment. Maximum capacity for the built-up systems will be limited to 60,000 cfm. Total system demands in excess of 60,000 cfm will utilize multiple systems. (3) Package air handling units will normally be located at floor level with adequate clearance for maintenance, test procedures, and equipment removal. Locations above ceilings, above mechanical equipment, and suspended 6 feet or more above the floor, are undesirable and should be avoided where possible. Adequate height shall be provided in the form of base rails and service pads for proper trap installation. (4) Humid Areas Reference the UFC 3-410-01FA for additional requirements for humid areas. (g) Water Coils Water cooling coils shall be certified in accordance with ARI STD 410-64. In lieu of ARI certification, the manufacturer shall submit a written certification from a nationallyrecognized independent testing firm to verify coil performance when tested according to ARI STD 410-64 testing procedures. (h) Fire Protection
(1) The current requirements of NFPA 90A and 90B will be incorporated in all heating and air conditioning system designs. Corridors shall not be used as supply, return or exhaust air plenums. (i) Duct Work Duct work shall be designed in accordance with applicable SMACNA standards and ASHRAE recommendations. Fibrous glass ductwork shall not be used. (j) Ventilation
(1) Equipment Rooms Mechanical ventilation shall be provided to limit air temperature rise to 10 F in unoccupied equipment rooms. Normally occupied areas shall be spot cooled as required. Control rooms, etc., shall be air conditioned. Some air conditioned equipment rooms such as control, electrical switchgear, or computer rooms, even though they are unoccupied, will require 100 percent backup where economically justified or required by design criteria. (k) Heating
13-12
(1) Outside Design Conditions Outside heating design conditions for Army and Air Force installations are listed in TM 5-785. (2) Inside Design Conditions Unless stated otherwise the inside design temperatures shall be determined as follows: 70 degrees F employment) 55-65 degrees F 40 degrees F Living and administrative areas (inactive
(3) Boilers Boilers shall be designed, constructed, tested, and installed in accordance with the ASME Boiler and Pressure Vessel Code, Section IV. Design pressures shall be 15 psig or less for steam boilers and 50 psig or less for hot water boilers. Boiler trim shall include safety valves, stop valves, water column, blow-off valves, piping and tank, low water cutoff, flame safety system, and control panel. (4) Fuel Oil Burning Equipment and Fuel Oil Storage Tanks This equipment and tanks shall be in accordance with NFPA Pamphlets 31 and 54, respectively. All underground fuel oil tanks shall be double wall with leak detection system. A monitoring well system shall be provided if the fuel oil tank is in ground water. (5) Gas-firing Equipment accordance with NFPA Pamphlet 54. This equipment shall be in
(6) Electric Resistance Heating For space heating or reheat for personnel comfort applications is prohibited, except for situations as listed in UFC 3-410-01FA. (l) Piping, Valves, and Fittings (1) Refrigerant piping
This shall be designed in accordance with the ASHRAE Handbooks. Special care in designing suction lines shall be taken to ensureoil return and to prevent liquid carry-over to the compressor. Where an optional refrigeration piping is allowed, design of piping for all options shall be provided. Hot gas discharge lines shall be designed to ensure oil return. Oil separators shall be provided as required. (2) Water distribution piping
a. Balancing At every point where balancing is required, a flow sensor plus a balancing valve (or a combination unit) shall be specified and shown on the plans. The required length of straight pipe before and after the flow sensor shall be clearly shown on the plans. b. Water velocity in medium and small diameter water piping generally shall not exceed 8 feet per second and shall be sized for friction loss not to exceed 4 feet per 100 feet.
13-13
c. An air separator and an expansion tank shall be installed in the main line of all systems. d. Multiduty valves and fittings, such as combination shutoff/check/balancing valves at pump discharges and combination suction diffuser/strainers at pump inlets, shall be used where they can simplify piping and reduce costs. e. For maintenance purposes, isolation valves and unions shall always be used for isolating equipment from the system. (m) Chilled and Dual Temperature Water Distribution Systems The contract drawings shall show the general arrangement of piping, sizes, grades, thrust block, and other details. Analyses shall be made to determine the most economical thickness of insulation for the supply and return lines. The systems will generally be composed of factory fabricated preinsulated conduit sections. (1) Thermal expansion Thermal expansion must be considered and accounted for in straight runs of high temperature piping. All lines above ambient temperature must be considered, and calculations for lines above 160 degrees F must be included in the design analysis. Allowable stress ranges are given in ANSI B31.1. (2) Anchors Anchors shall be required where there is a change in direction, diameter, or wall thickness of a pipeline that may cause undesired movement, loads, or stress and whenever buckling of the pipe may occur. For buried piping, no credit may be taken for resisting friction between the pipe and the soil since the full development of this force does not occur when line movement is prevented. Anchors may be concrete or piling type. (n) Mechanical Equipment Spaces Mechanical equipment sized from three manufacturers, piping, and accessories in boiler and equipment rooms will be drawn to scale in both plan and elevations. Adequate space will be provided for maintenance, operation, and replacement of equipment, piping, and accessories. Catwalks, ladders, platforms, access panels and doors required for operation and maintenance of equipment, valves, and accessories will also be indicated and detailed on the drawings. (n) Other Systems Other systems are required for special projects such as medical and industrial facilities. These will be designed in accordance with the SOW for each project of this type. (o) Equipment Schedules Equipment schedules are required for all HVAC equipment. The schedule shall be presented in tabular form. (p) Insulation water piping. Use only cellular glass insulation on chilled
(q) Controls Most bases have in place Direct Digital Control (DDC) systems. The designer shall contact the base to insure the new controls are equal to or can seamlessly interface with the existing system.
13-14
13.10.3
Seismic Protection
All piping, equipment, and utilities shall be protected in accordance with TM 5-809-04.
13-15
GENERAL 14.1.1
Scope
APPLICABLE PUBLICATIONS PROJECT DEFINITION (10-15%) 14.3.1 General Considerations 14.3.2 Project Definition Narrative CONCEPT DESIGN (30-35%) 14.4.1 General Considerations 14.4.2 Concept Design Analysis 14.4.3 Specifications 14.4.4 Concept Drawings INTERIM DESIGN (50-60%) 14.5.1 Interim Design Analysis 14.5.2 Specifications 14.5.3 Interim Drawings FINAL DESIGN (Unreviewed 100%) 14.6.1 Final Design Analysis 14.6.2 Specifications 14.6.3 Final Drawings READY-TO-ADVERTISE (100%) RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS 14.8.1 14.8.2 Mandatory Requirements Specific Requirements
14.4
14.5
14.6
14.7 14.8
14.9
TECHNICAL REQUIREMENTS 14.9.1 General Considerations 14.9.2 Fire Suppresion System l4.9.3 Seismic Protection
14-1
14.1.1
This Chapter provides guidance for preparation and development of the fire suppression systems. Specific design submittal requirements in this chapter supplement the requirements in Chapter 1,titled GENERAL INSTRUCTIONS. All required documents, including drawings and design analysis, shall be in accordance with Chapter 2, titled PRESENTATION OF DATA. 14.2 APPLICABLE PUBLICATIONS.
The publications listed below, but referred to thereafter by basic designation only, form a part of this Manual. These publications are supplemented by the Corps of Engineers Guide Specifications (CEGS) to form design criteria. Design Manuals: TI 800-01 TI-800-03 Unified Facilities Criteria: UFC 3-600-01 Facilities Fire Protection Engineering for Design Criteria Design Build Instructions
National Fire Protection Association (NFPA) Standards: Latest Edition Guide Specifications: Specifications are updated on a regular basis. Instructions on retrieving UFGS Specifications are covered in Chapter 3, SPECIFICATIONS. 14.3 PROJECT DEFINITION (10-15%) General Considerations National Fire Codes
14.3.1
At the Project Definition phase the designer must define the customer's requirements and confirm that they can be met within the project's constraints. To that end, a comprehensive interface with the customer is required generally through a charrette or other previously approved data gathering process. The primary purpose of the design process at this stage is to gather any information from the customer that would be necessary in the design of the facility.
14-2
The general fire suppression system type and purpose along with an order-of-magnitude estimate of major equipment sizes will be provided at the Project Definition phase for use in preparing of cost estimate and sizing the required mechanical spaces. 14.3.2 Project Definition Narrative
The Project Definition narrative shall include, but not be limited to, the following items as applicable: (a) List all references used in the Project Definition design including Government design documents, industry standards, safety manuals, criteria given to designer at the Charrette or predesign meeting. (b) (c) Explain proposed type of the fire suppression system. Describe any demolition required.
(d) List any environmental concerns and actions to be taken to address them. 14.4 CONCEPT DESIGN (30-35%) General Considerations
14.4.1
At the Concept design stage of project development, it is recognized that all calculations are preliminary for analysis purposes and only indicate approximate capacities of equipment; however, calculations must be adequate to determine whether fire pumps and/or storage tanks are required. Any dimensions and sizes required are order-of-magnitude figures, conversationally stated, to assure adequate space for installation and maintenance of equipment and utility elements such as piping in congested areas. Equipment shown in plans and sections is not shown in great detail but is shown merely as simple geometric forms with approximately correct dimensions. Piping layouts shown are simple main pipe runs showing general location, routing and, when applicable, approximate order-of-magnitude sizes. Schematic diagrams are simplified. System flow diagrams, layouts, and one of each type of take-off, branch, or feed must be shown but not all individual branches. The purpose of the schematic is only to show system design intent and the basic principle of system operation. 14.4.1.1 Drawings and sketches
Scale of concept drawings will generally be smaller than the working drawings. Plans and sections need be only large enough to properly show pertinent information. Sketches, neatly drawn, will be acceptable when sufficient to show pertinent information or to convey basic system concepts. Quantity of concept drawings are to be kept to the minimum number required to convey basic systems information. Some mechanical information required in the Concept submission may logically be included on other discipline drawings or in sketch form in the design analyses and need not be completed on formal drawings. 14-3
14.4.2
The Concept Design Analysis shall include, but not be limited to, the following items as applicable: (a) List all references used in the Concept design including Government design documents, industry standards, criteria given designer at predesign meeting, etc. (b) Classify each building in accordance with the following: (1) (2) (3) Fire zone Building floor areas Height and number of stories
(c) Discuss and provide description of required fire protection including extinguishing equipment, detection equipment, alarm equipment, and water supply. (d) If water sprinkler systems are to be provided, preliminary hydraulic calculations shall be prepared for the most hydraulically demanding area to insure that flow and pressure requirements can be met with current water supply. Information on water supply available for fire protection will generally be provided by installation personnel through "Fire Flow Test" data. See Chapter 8, titled WATER, WASTEWATER, AND ENVIRONMENTAL PROTECTION. (e) 14.4.3 Identify any special security requirements.
Specifications
Provide a basic outline in accordance with Chapter 3, SPECIFICATIONS. 14.4.4 Concept Drawings
The Concept design drawings should include, but not be limited to, the following items as applicable: (a) The location and rating of any fire-resistive construction such as occupancy separations, area separations, exterior walls, shaft enclosures, corridors, stair enclosures, exit passageways, etc. (b) The location and coverage of any fire detection systems.
(c) The location and coverage of any fire suppression systems (e.g., sprinkler risers, standpipes, etc.). (d) (e) The location of any other major fire protection equipment. Indicate any hazardous areas and their classification.
(f) Provide description of type sprinkler system to be provided (e.g., dry pipe, preaction, wet pipe, AFFF, etc.). (g) Address security requirements (e.g., dielectric couplings, grounding, etc.).
14-4
14.5
In addition to the following items, the designer shall incorporate or answer all comments received from Corps of Engineers and Using Agency personnel concerning Concept submittal. 14.5.1 Interim Design Analysis
Provide a detailed description of the system and its controls such as activation of system, interlocks with HVAC system and connection to detection and alarm systems. 14.5.2 Specifications
The outline specifications previously submitted for the Concept design shall be edited, updated, further developed and resubmitted in accordance with Chapter 3, titled SPECIFICATIONS. 14.5.3 Interim Drawings
The Interim drawings should show all information given on the concept drawings but in greater detail. In addition, the Interim drawings should include, but not be limited to, the following items as applicable: (a) Include items shown on the concept drawings and any necessary revisions. (b) Prepare a schedule describing the system with the following information: fire hazard and occupancy classifications, building construction type, GPM/square foot sprinkler density, area of operation, hose stream allowances and other as required. (c) Provide detail of suppression system interface with HVAC, detection, or alarm systems. (d) Provide one set of black line drawings showing a rough layout of the main piping involved in the sprinkler system. All piping, with the exception of branch lines, should be indicated and roughly sized. These drawings are for estimating purposes only. Do not indicate piping on the actual drawings. 14.6 FINAL DESIGN (Unreviewed 100%)
In addition to the following items, the designer shall incorporate or answer all comments received from the COE and customer concerning Interm submittal. 14.6.1 Final Design Analysis
The Final Design Analysis shall include all of the information required in the Interim submittal in its final form and the information listed below when applicable: (a) Incorporate or answer all comments received from the COE or the customer. (b) Verify water supply through fire flow tests or otherwise. 14-5 See
(a) Edited specifications shall be submitted in accordance with Chapter 3, titled SPECIFICATIONS. Specifications used shall be those acquired subsequent to the Interim submittal. (b) Specifications for fire suppression systems shall be performance type, except when aircraft hangars require specificallydesigned sprinkler systems, listing hazards, minimum water densities, miminum area of operation, waterflow test data and any other data necessary for the construction contractor to design the system. 14.6.3 Final Drawings
The Final drawings for sprinkler systems should be in a Ready-to-Advertise state which should include, but not be limited to, the following items as applicable. (a) (b) (c) Include plans in final condition. Complete all legends and schedules. Complete all narratives, notes and title blocks as necessary.
(d) Provide one set of black line drawings for estimating purposes as described in the Interim submittal requirements. 14.7 READY-TO-ADVERTISE (100%)
The comments generated concerning the Final submittal shall be incorporated in the design documents before they are submitted as Ready-to-Advertise. 14.8 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS
TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs. 14.8.1 Mandatory Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development: (a) The mandatory design criteria are those contained in Unified Facilities Criteria; Fire Protection Engineering for Facilities, UFC 3-600-01. UFC 3-600-01 contains fire protection and life safety requirements in the following areas: (1) (2) (3) (4) (5) (6) Type of construction. Height and area limitation. Building separation. Fire resistive construction. Flame-spread and smoke-developed ratings. Means of egress. 14-6
(7) Special hazard protection. (8) Automatic sprinkler and fire suppression systems. (9) Water supplies for fire protection. (10) Standpipe systems and fire extinguishers. (11) Fire alarm and detection systems, (12) Connection to the base fire reporting system. (b) UFC 3-600-01 may not include all the latest Federal requirements, established by executive orders, public laws, local requirements, and other directives that relate to fire protection and life safety. These requirements must be reviewed and included in the RFP as required for each project. (c) See TI 800-03 for additional mandatory requirements. 14.8.2 Specific Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria:
1. List areas Requiring Fire Protection or require the Design-Build Contractor to make selection of area fire protection requirements based upon applicable codes and standards for the use of the area. If fire protection system is preferred, indicate the type. b. Partial Project Criteria:
1. List areas Requiring Fire Protection or require the Design-Build Contractor to make selection of area fire protection requirements based upon applicable codes and standards for the use of the area. If fire protection system is preferred, indicate the type. 2. systems. 3. c. Describe the pipe materials to be used on all sprinkler Include an outline of the specifications to be edited.
1. Final Fire Suppression Plans (See description above under 14.6.3 FINAL DESIGN.) 2. Final Specifications (See description above under 14.6.2 FINAL DESIGN.) NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements. 14.9 14.9.1 TECHNICAL REQUIREMENTS General Considerations
(a) Coordinate space requirements, foundations, supports, pipe routing, electrical service, and the like for mechanical items with 14-7
architectural, structural, and electrical design elements. Coordinate exterior mechanical distribution systems with design elements handling other exterior utility designs and site work. (b) Standard or "packaged" equipment shall be used to the greatest extent possible to simplify specifying, purchasing, installation, and maintenance of equipment. (c) UFC 3-600-01, Fire Protection Engineering for Facilities, is the prime design manual. This criteria is supplimented by the technical provisions listed hereinafter. In case of conflict, this document governs. 14.9.2 Fire Suppression System
(a) Criteria The use of fire suppression systems shall be governed by the requirements of the UFC 3-600-01, Fire Protection Engineering for Facilities. Where systems are required they shall be designed in accordance with the applicable NFPA standards. (b) Fire Protection Fire protection that is cost-effective, yet provides maximum degree of protection consistent with the type and degree of fire exposure, shall neither be diminished in an effort to reduce project costs nor shall it be set aside for security or other considerations. (c) Automatic Systems Automatic fire protection systems shall be employed where suitable and cost-effective. Suffocating extinguishers should not be considered in conjunction with munitions or materials that contain their own oxygen supply. (d) Low Maintenance Automatic fire suppression systems, smoke evacuation systems, and other fire protection systems shall be designed so that their proper operation does not depend upon a high degree of sophisticated maintenance. (e) Sprinkler Systems Sprinkler systems will be performance-specified by the designer in compliance with UFC 3-600-01, Fire Protection Engineering for Facilities, NFPA 13, and the this document using the more stringent of the two in case of discrepancy. Preliminary hydraulic calculations shall be provided to insure that system demand does not exceed available supply. Plans developed shall indicate water densities, hazards, area of operation, waterflow test data, and any other data necessary for the construction contractor to design the system. The construction contractor will use the plans and specifications as a guide for subsequent preparation of detailed drawings which will be coordinated with requirements and options of the work of other trades required for construction of the facility. A note to this effect shall be placed on the plan. Riser locations shall also be shown on the plans. (f) Accessibility Check Designers shall check each system and its equipment to assure ready accessibility and operability of all maintenance points, gages, valves, controls, and signals. Devices whose operations are critical during emergency conditions shall be prominently located and singularly identified. (g) Coordination Check A cross-check shall be made by designers of the structural, process piping, Fire Suppression, conveyor, and packaged equipment systems in order to detect and correct interferences 14-8
with illumination levels, electrical raceways, fire detection, alarm and suppression systems, toxic or explosive detection systems, personnel, fire doors and shutters, and material and equipment traffic or other degradations of personnel or property safety. A check shall be made to ensure that no piping crosses over or under electrical panels or switchboards (i.e., the "dedicated electrical space"). See the National Electric Code for definition of "dedicated electrical space." The dedicated electrical space shall be clearly marked on the mechanical drawings. 14.9.3 Seismic Protection
All piping, equipment, and utilities shall be protected in accordance with TM 5-809-04.
14-9
GENERAL APPLICABLE PUBLICATIONS PROJECT DEFINITION (10-15%) 15.3.1 General Considerations 15.3.2 Project Definition Narrative CONCEPT DESIGN (30-35%) 15.4.1 Concept Design Analysis 15.4.2 Concept Design Drawings 15.4.3 Specifications INTERIM DESIGN (50-60%) 15.5.l Interim Design Analysis 15.5.2 Interim Design Drawings 15.5.3 Specifications FINAL DESIGN (Unreviewed 100%) READY-TO-ADVERTISE (l00%) RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS 15.8.1 Mandatory Requirements 15.8.2 Specific Requirements TECHNICAL REQUIREMENTS 15.9.1 15.9.2 15.9.3 15.9.4 15.9.5 15.9.6 15.9.7 POL Facilities Engine-Generators Cranes and Hoists Storage Tanks For Petroleum, Oils, and Lubricants Central Energy Plants and Energy Distribution Elevators Other Mechanical Systems
15.4
15.5
15.9
15-1
CHAPTER 15
15.1
GENERAL
Specific submittal requirements contained in this chapter supplement the requirements of Chapter 1, titled GENERAL INSTRUCTIONS. All required documents including drawings and design analysis shall be in accordance with Chapter 2, titled PRESENTATION OF DATA. Requirements of this chapter pertain to the following mechanical systems and equipment.
1. 2. 3. 4. 5. 6. 7. 15.2
Petroleum, Oils and Lubricant (POL) Facilities/Automotive and Aircraft Fueling Systems Diesel Engines For Generators and Fire Pumps Cranes and Hoists Storage Tanks Central Energy Plants and Distribution System Elevators Other Mechanical Systems
APPLICABLE PUBLICATIONS
The following publications shall be used when preparing plans and specifications for special mechanical systems and equipment included in this chapter: (The current edition of all publications shall be used.) Design Manuals: TI 800-01 TI-800-03 TI-809-04 International Building Code: Latest Edition at time of Project Solicitation Issue Date (Advertise Date). Unified Facilities Criteria (UFC): UFC 3-400-01 UFC 3-430 series General Criteria: ASME Engineers American Society of Mechanical -Codes and Standards. Design: Energy Conservation Design: Central Energy Plants and Distribution Systems Design Criteria Design Build Instructions Seismic Design for Bldgs.
15-2
ANSI Institute
American Welding Society - Codes Standards. American Petroleum Institute Standards and Publications. National Fire Protection Codes.
NFPA AssociationCranes and Hoists CMAA No. 70 Traveling CMAA No. 74 Girder Cranes. Elevators ASME A17.1 Storage Tanks TM 5-848-2 MIL-HDBK-1022
Crane Manufacturers Association of America Specification for Electric Overhead Cranes. Crane Manufacturers Association of America Specification for Top Running Single Electric Overhead Traveling
API Standard 620 Recommended Rules for Design and Construction of Large, Welded, Low-Pressure Storage Tanks. API Standard 650 API Publication 1505 Storage NFPA-30 API Standard 653 Welded Steel Tanks for Oil Storage. Installation of Underground Petroleum Systems. Flammable and Combustible Liquid Code. Tank Inspection, Repair, Alteration, and Reconstruction.
Automotive and Aircraft Fueling Systems/Petroleum, Oils and Lubricant (POL) Facilities TM 5-848-2 FM 10-68 MIL-HDBK-1022 Handling of Aircraft and Automotive Fuels. Aircraft Refueling. Petroleum Fuel Facilities.
15-3
Specifications Specifications are updated on a regular basis. Instructions for retrieving UFGS Specifications are covered in Chapter 3, SPECIFICATIONS.
15.3
PROJECT DEFINITION
(10-15%)
15.3.1
General Considerations
At the Project Definition phase the designer must define the customer's requirements and confirm that they can be met within the project's constraints. To that end, a comprehensive interface with the customer is required generally through a charrette or other previously approved data gathering process. The primary purpose of the design process at this stage is to gather any information from the customer that would be necessary in the design of the facility. Also, the design preferences of the customer should be obtained for compliance if possible. The general mechanical system types and purpose along with an order-ofmagnitude of major equipment sizes will be estimated at the Project Definition phase for the purpose parametric cost estimate and required mechanical spaces. 15.3.2 Project Definition Narrative
The Project Definition narrative shall include, but not be limited to, the following items as applicable: (a) List all references used in the Project Definition design including Government design documents, industry standards, safety manuals, criteria given to designer at the charrette, predesign meeting, etc. (b) (c) (d) Describe proposed type of the mechanical system. Describe any demolition required. List any environmental concerns and actions to be taken to address them.
(e) Describe proposed construction planning of mechanical system for alteration/modification project. 15.4 CONCEPT DESIGN (30-35%) Concept Design Analysis
15.4.1
The following specific items shall be included where applicable. (a) A list of all special mechanical systems and equipment in the
15-4
project. (b) A list of criteria, codes, documents, and design conditions used. Reference to any authorized waiver of these criteria or codes. (c) Logic establishing the need for the system. If necessary, a life-cycle cost estimate for all systems considered and a statement of justification for selection of the final system. (d) Preliminary sizes of equipment, piping, and space required for the equipment and distribution methods selected. (e) A description of the proposed control system.
(f) Description, approximate capacity, and location of any special mechanical equipment such as elevators, cranes, lifts, etc. (g) Description of the various types and quantities (supported by calculations as applicable) of POL products and their associated unloading, storage, and dispensing systems. (h) 15.4.2 Phasing.
The following specific items shall be shown where applicable. (a) Flow diagrams of all systems proposed. These diagrams shall be an accurate schematic representation of the system, showing all proposed equipment, piping, control valves, and primary control loops. In addition, the drawings shall indicate approximate capacities of equipment, flow rates in mains, branches, and outlets, direction of slope for pipe, and shall identify the location of equipment by building and room. (b) Plans that are sufficiently complete to show the location and general arrangement of mechanical equipment and major piping. Piping may be shown with single lines. 15.4.3 Specifications
15.5 15.5.1
The Interim Design Analysis shall include all items in the Concept Design Analysis and any necessary revisions. In addition, the following specific items shall be included when applicable: (a) (b) (c) Detailed calculations for sizing equipment. Detailed logic diagrams for control schemes used. Any other information or computation required to verify that
15-5
the design complies with the design criteria, codes, and standards, and is satisfactory for the intended purposes. 15.5.2 Interim Design Drawings
The following specific items shall be shown when applicable: 15.5.2.1 Flow Diagrams of Systems (where applicable)
These diagrams shall show all of the information given on the Concept drawings, but in greater detail. The diagrams shall include equipment capacities and power requirements, all piping sizes with flow rates indicated, all valves, piping specialties, instrumentation, and control devices. 15.5.2.2 Plans and Sections
Layouts and details of the final version of the proposed system showing location, arrangement, capacity and space requirements of all equipment plus size, elevations, supports, product identification and direction of flow for all piping. 15.5.2.3 Equipment
The drawings shall include space for rating data in tabular form for all items of equipment, with space reserved for designating the manufacturer and the model number, in anticipation of as-built drawings. Preliminary rating data shall be inserted in the equipment schedules at this stage. Equipment schedules shall be completed when final rating data are established but not later than the Final Review submission. 15.5.3 Specifications
The outline specifications previously submitted for concept phase shall be edited, updated, further developed and resubmitted in accordance with Chapter 3, titled SPECIFICATIONS.
15.6
The design analysis and the drawings submitted shall be complete. A technical specification is required for each mechanical system or piece of equipment covered in this chapter. 15.7 READY-TO-ADVERTISE (l00%)
The comments generated concerning the Final design submittal and all previous submittals shall be answered and incorporated in the design documents before they are submitted as Ready-to-Advertise. 15.8 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS
TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and
15-6
specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs. 15.8.1 Mandatory Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development: The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development:
a. The mechanical systems shall be designed and specified to the latest industry standards, codes, and Government regulations. The RFP shall ensure high quality, energy efficient mechanical equipment and systems with minimum maintenance. Design documents shall be submitted, reviewed and approved prior to commencing work on the mechanical system.
b. 15.8.2 See TI 800-03 for additional mandatory requirements.
Specific Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria: 1. Include a paragraph describing the mechanical systems and support utilities that will be needed. 2. On central energy plants, list estimated capacities of equipment, types of equipment and number of each type of equipment. b. Partial Project Criteria: 1. Include a paragraph describing the mechanical systems listing possible manufacturers and model numbers for unusual systems. 2. On central energy plants, list estimated capacities of equipment, types of equipment and number of each type of equipment. Include a preliminary floor plan showing possible locations of major equipment and maintenance clearances. Discuss control of the plant. Discuss any environmental concerns. 3. c. Include an outline of the specifications to be editted.
15-7
1. 2.
Final Plans (See description above under 15.6) Final Specifications (See description above under 15.5.3)
NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements. 15.9 TECHNICAL REQUIREMENTS POL Facilities
15.9.l
POL facilities shall be designed in accordance with AEI, Design Criteria, TM 5-848-2, and MIL-HDBK-1022. Fuel oil supply shall be from an independent source for diesel driven emergency generators and fire pumps. 15.9.2 Engine-Generators
Diesel engine-generators shall be designed in accordance with instructions given in applicable Guide Specification and the applicable portions of this text. 15.9.2.1 Facilities for Engine-Generators
Engine-generator buildings or rooms designed for engine-generator installation shall be designed to support the unit with the following: (a). Sufficient cooling and combustion air supply and exhaust.
(b). Correct air flow patterns to optimize cooling of both generator and engine. (c). sets. Door width and height to allow installation and removal of
(d). Floor space for starting batteries, charger, and working space around the set, fuel oil supply and return piping trenches, day tank, electrical equipment, etc. (e). Height of building to accommodate diesel engine, exhaust pipe, muffler and insulation. Materials should be selected for exterior piping to resist rusting, corrosion to prevent discoloration of the building exterior. (f). Size of building roof framing to accommodate suspension or installation of engine exhaust system. Materials should be selected for exterior piping to resist rusting, corrosion, to prevent discoloration of the building exterior. (g). Sufficient inside building temperature for engine to be maintained with jacket water heaters at required starting temperature. A scaled drawing is required for all diesel-generator sets and shall show each set and the above-mentioned appurtenances. 15.9.3 Cranes and Hoists
15-8
15.9.3.1
Hoists The
Hoists shall be shown on the drawings in both plan and elevation. following items shall be shown to scale and dimensioned on the drawings: 1. 2. 3. Length, size and location of monorail. Location, degree and radius of all monorail curves. Location of all monorail track switches.
4. Minimum acceptable hook height; i.e., distance from finished floor to saddle of hoist hook in raised position. These items can be shown on architectural, structural or on a separate mechanical drawing. If additional specifications are required, recognized standards, HM1-100 and MMA Specifications, for example, shall be used. 15.9.3.2 Overhead Traveling Cranes
A crane clearance diagram is required for all overhead traveling cranes. The required limits of crane hook travel in both plan and elevation and the dimensions of an envelope reserved for installation of the crane shall be shown on the drawing. For envelope dimensions, an overhead clearance of 3 inches above the high point of the crane is satisfactory. Between the crane and the side walls of the building, a clearance of 4 to 6 inches is adequate. Details of special features, such as pickup beams, control outriggers, special hooks, trolleys, hoist, end trucks, etc., shall also be shown on this drawing. 15.9.3.3 Special Hoists and Cranes
Special hoists and cranes that are not monorail or overhead traveling type shall be treated as special designs. Design requirements for these special cranes shall be requested through Project Management to the appropriate technical section at or before the predesign conference. 15.9.4 Storage Tanks for Petroleum, Oils, and Lubricants
Tanks shall be vertical or horizontal and either aboveground or underground. For tanks with a volume of 40,000 gallons or less, preference shall be given to tanks of the shop-fabricated horizontal type. Tanks with volumes larger than 40,000 gallons shall be aboveground, vertical, fixed-roof with floating pan, as required by project criteria. 15.9.4.1 Aboveground Tanks (Army)
Tanks shall be designed in accordance with TM5-848-2, the latest editions of API-650 and NFPA-30. Tanks to be rehabilitated or modified shall be in accordance with API-653. All aboveground tanks shall have spillage containment dikes. 15.9.4.2 Aboveground Tanks (Air Force)
15-9
Tanks shall be designed in accordance with MIL-HDBK-1022, and the latest editions of API-650 and NFPA-30. All aboveground tanks shall have spillage containment dikes. 15.9.4.3 Underground Tanks (Army)
Tanks shall be designed in accordance with TM-5-848-2, Standard Drawings and NFPA-30. Tanks with volumes of 40,000 gallons or less shall be double-wall, horizontal and suitable for underground installation. Tanks shall be either of fiberglass reinforced plastic construction or of steel construction. Steel tanks shall be coal tar or epoxy coated and provided with a cathodic protection system or coated with glass fiber-reinforced polyester resin coating. All storage tanks shall be monitored by a leak detection system. The leak detection system shall indicate, by an audible alarm and indicator lights, the occurrence of a leak in any part of either tank shell. The system shall be of the electronic monitoring, pressure monitoring, vacuum monitoring, or liquid monitoring type. Observation wells shall be provided in areas of seasonal high groundwater where the tank is anchored in the groundwater during normal operation. The wells may employ any of the types of leak detectors mentioned above to provide continuous monitoring. All observation wells shall be clearly identified and provided with locking devices. Tanks with volumes of more than 40,000 gallons shall be vertical, and field erected unless otherwise authorized. 15.9.4.4 Underground Tanks (Air Force)
Tanks shall be designed in accordance with MIL-HDBK-1022 and NFPA-30. Tanks with volumes of 40,000 gallons or less shall be double-wall, horizontal and suitable for underground installation. Tanks shall be either of fiberglass reinforced plastic construction or of steel construction. Steel tanks shall be coal tar or epoxy coated and provided with a cathodic protection system or coated with glass Fiber-reinforced polyester resin coating. All storage tanks shall be monitored by a leak detection system. The leak detection system shall indicate, by an audible alarm and indicator lights, the occurrence of a leak in any part of either tank shell. The system shall be of the electronic monitoring, pressure monitoring, vacuum monitoring, or liquid monitoring type. Observation wells shall be provided in areas of seasonal high groundwater where the tank is anchored in the groundwater during normal operation. The wells may employ any of the types of leak detectors mentioned above to provide continuous monitoring. All observation wells shall be clearly identified and provided with locking devices. For tanks with volumes of more than 40,000 gallons, preference shall be given to vertical aboveground field erected unless otherwise authorized. 15.9.5 Central Energy Plants and Energy Distribution Systems
Central energy plants and energy distribution systems shall be designed in accordance with the UFC 3-430 series of criteria. 15.9.6 Elevators
15-10
Building Code and ASME A17.1, Safety Code for Elevators. 15.9.7 Other Mechanical Systems
All other mechanical systems shall be designed in accordance with the latest and most stringent design criteria as listed in the contract scope of work.
15-11
CHAPTER 16 ELECTRICAL AND ELECTRONIC SYSTEMS INDEX 16.1 GENERAL 16.1.1 16.1.2 16.2 Scope Design Submittals
APPLICABLE PUBLICATIONS 16.2.1 16.2.2 16.2.3 16.2.4 16.2.5 16.2.6 16.2.7 16.2.8 16.2.9 16.2.10 16.2.11 16.2.12 American National Standard Institute (ANSI) Institute of Electrical and Electronic Engineers Instrument Society of America (ISA) National Fire Protection Association (NFPA) National Electrical Manufacturers Association (NEMA) Military Handbooks Technical Manuals Unified Facilities Criteria (UFC) Technical Instructions (TI) Miscellaneous References Other Publications and Code Compliance Guide Specifications
16.3
PROJECT DEFINITION (10%-15%) 16.3.1 16.3.2 16.3.3 16.3.4 Interior Electrical System Design Analysis Narrative Interior Electronic Systems Design Analysis Narrative Exterior Electrical Distribution System Design Analysis Narrative Exterior Electronic System Design Analysis Narrative
16.4
CONCEPT DESIGN (30%-35%) 16.4.1 Interior Electrical System Design Analysis Narrative 16.4.2 16.4.3 16.4.4 16.4.5 Interior Electronic Systems Design Analysis Narrative Exterior Electrical Distribution System Design Analysis Narrative Exterior Electronic System Design Analysis Narrative Concept Design Drawings (30%-35%) 16-1
INTERIM DESIGN (50%-60%) 16.5.1 Interim Design Analysis 16.5.2 Interim Design Drawings (50%-60%) 16.5.3 Additional Criteria
16.6
FINAL DESIGN (Unreviewed 100%) 16.6.1 16.6.2 16.6.3 Final Design Analysis Final Design Drawings Specifications
16.7 16.8
READY-TO-ADVERTISE (100%) RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS 16.8.1 16.8.2 Mandatory Requirements Specific Requirements
16.9
TECHNICAL REQUIREMENTS 16.9.1 16.9.2 16.9.3 16.9.4 16.9.5 16.9.6 16.9.7 16.9.8 16.9.9 16.9.10 16.9.11 16.9.12 16.9.13 16.9.14 16.9.15 Metering Salvageable Material Special Items Design Criteria for Nonlinear Loads Telecommunication/Data Systems Fire Detection and Alarm System Special Grounding Systems Public Address Systems Intrusion Detection Systems Leak Detection for Underground Storage Tanks Lightning Protection System Local Area Networks (LAN) Hospital Systems Cable Television Systems (CATV) Closed Circuit Television Security (CCTV) System
16-2
EXHIBITS 16-1 16-2 16-3 16-4 16-5 16-6 16-7 PANEL SCHEDULE LIGHTING FIXTURE SCHEDULE INTRUSION DETECTION SYSTEM RISER DIAGRAM TYPICAL TELEPHONE SYSTEM RISER DIAGRAM FIRE ALARM RISER DIAGRAM TYPICAL PUBLIC ADDRESS SYSTEM RISER DIAGRAM DESIGN REVIEW CHECKLIST
16-3
16.1.1
This chapter gives general guidelines for the preparation of drawings, specifications, and design analysis as related to power, lighting, grounding, and electronic systems. Specific submittal requirements in this chapter supplement the requirements of Chapter 1, GENERAL INSTRUCTIONS. All required documents, including drawings and design analysis, shall be in accordance with Chapter 2, PRESENTATION OF DATA. 16.1.2 Design Submittals
The following submittal guidelines have been developed for the most common projects such as a building or buildings and minor exterior electrical design. Projects which require extensive exterior electrical work and projects with complicated or highly-technical interior electrical work will have special submittal requirements developed for that project. The requirements shall be defined, developed and agreed upon at the predesign conference and will become part of the contract. Design submittals will be reviewed for general compliance with criteria. Some detailed checks will be made. Complete and independent checking of the design should be accomplished by the designer. The designer is fully responsible for the design. The design should be complete and accurate. It should be thoroughly checked for errors, conflicts (both within and between disciplines), and proprietary requirements. No proprietary restrictions may be included in the contract unless specifically authorized. 16.2 APPLICABLE PUBLICATIONS American National Standard Institute (ANSI) National Electrical Safety Code
16.2.1
Institute of Electrical and Electronic Engineers Recommended Practice for Grounding of Industrial Commercial Power Systems.
IEEE 142
Instrument Society of America (ISA) Instrumentation Symbols and Identification Binary Logic Diagrams for Process Operations
National Fire Protection Association (NFPA) National Electrical Code (Latest Issue) Electrical Safety Requirements for Employee 16-4
Workplaces NFPA 72 NFPA 90A NFPA 101 Structures NFPS 160 16.2.5 National Fire Alarm Code (Latest Issue) Installation of Air Conditioning and Ventilating Systems Safety to Life from Fire in Buildings and Fire Safety Symbols
National Electrical Manufacturers Association (NEMA) Pulse Initiators for Watthour and Other Meters
Military Handbooks Military Handbook Grounding, Bonding and Electronic Equipments and facilities Military Handbook for Facility Planning and Guide
MIL HDBK 1191 Military Handbook for Medical and Dental Treatment Facilities, Design and Construction Criteria Guide
16.2.7
Technical Manuals (TM) Electric Power Supply and Distribution Electrical Design: Lightning and Static Protection
Unified Facilities Criteria (UFC) Design: General Building Requirements Design and O&M: Mass Notification Interior Electrical Systems Design: Fire Protection Engineering for DOD Minimum Antiterrorism Standards for
UFC 1-200-01 UFC 4-021-01 UFC 3-520-01 UFC 3-600-01 Facilities UFC 4-010-01 Buildings 16.2.9
Technical Instructions (TI) Design Guide Design Build Instructions Lighting Design
16-5
16.2.10
Miscellaneous References Design Analyses, Chapter 1 Electrical Power Systems for Non-Linear Loads Prewiring fire Protection Criteria - New Aircraft
STD 40-06-04 Lighting Fixtures, Standard Detail No. 40-06-04 available at http://www.hnd.usace.army.mil/techinfo/fixtdwg.htm. STD 40-06-05 Army Aviation Lighting Fixtures, Standard Detail No. 40-06-05
16.2.11
In addition to the codes and standards listed above, all electrical work shall comply with the applicable requirements of the latest edition of the standards of the National Electrical Manufacturer's Association (NEMA); Insulated Power Cable Engineer's Association (IPCEA); and all applicable federal, state, city, and local codes, regulations, ordinances, publications and manuals. All new manufactured equipment shall be listed by the Underwriter's Laboratory (UL) or a similar testing laboratory acceptable to COE. When codes conflict, the more stringent standard shall govern. 16.2.12 Guide Specifications.
Specifications are updated on a regular basis. Instructions on retrieving UFGS Specifications are covered in Chapter 3, SPECIFICATIONS. 16.3 PROJECT DEFINITION (10%-15%)
The Preconcept Design Analysis shall include the requirements stated below and shall include all data and any calculations(if required) to support design decisions and estimates at this stage of design. The analysis shall incorporate specific criteria furnished and conference minutes of all systems considered. The analysis shall include the following: 16.3.1 Interior Electrical System Design Analysis Narrative
(1) Provide brief description of the Electrical Characteristics (phase voltage and number of wires) for electrical system(s). Justification for the type of system proposed (Economical or Special Condition). (2) Provide brief description of the lighting system(s) to be used for major areas. (3) State type of wiring system, such as rigid or intermediate conduit, electrical metallic tubing, nonmetallic sheathed cable, etc., that will be use. (4) Provide a paragraph describing special items of design, such as equipment, handicapped and seismic requirements, etc.; include 16-6
description and location. (5) Clearly define and completely indicate any and all hazardous areas with the applicable class, group, division, and suitable operating temperature as defined in the National Electrical Code. Do not attempt to design around the hazardous areas in lieu of designating the areas. State source of criteria, such as Safety Officer or some other recognized official. Include documentation of the source of the criteria. (6) Indicate if a lightning protection system will be required; if none, so state. (Reference TM 5-811-3 and NFPA 780). (7) Provide brief description of the grounding system to be installed. If a counterpoise, grid, EMI shielding requirements, etc., is to be utilized, state standards to be used. (8) List Unified Facilities Guide Specifications that will be used. The designer shall obtain the appropriate guide specifications and use them for design guidance. (9) Provide a firm statement that no brand names or proprietary items will be used in final plans and specifications. (10) Provide a statement identifying the sustainable design features to be incorporated. See Chapter 20, Sustainable Design and Development (SDD) for specifics. 16.3.2 Interior Electronic Systems Design Analysis Narrative
(1) Where additions or alterations to existing systems are to be made, verify that the systems are expandable and can accommodate the additions or alterations. Provide a description of all proposed additions and alterations to each system. (2) Provide a descriptive narrative of all electronic systems that are required for project. A list of some of the possible electronic components and/or systems that may be required on a given project are as follows: (a) (b) (c) (d) (e) (f) Telecommunication/Data Systems Fire Detection and Alarm System Special Grounding Systems Public Address Systems Security Systems Mass Notification System
(3) Define any hazardous areas (as defined in the National Electrical Code) and indicate the type of equipment proposed for use in such areas. (4) 16.3.3 List the specifications that will be used.
Narrative (1) Make a statement, with documentation, that the primary supply is adequate to support the added load. If the primary source is inadequate, state measures proposed to correct the deficiency in the design. (2) Provide brief description of the electrical characteristics of power supply from the service point to the main service equipment (voltage, phase, number, and size of conductors). (3) Provide brief description of the conductor type(s), such as copper or aluminum, and the proposed areas of use and a justification for the choice made. (4) Provide brief description of the standards of design, such as physical characteristics of overhead and/or underground circuits. If underground, state the basis for the selection. Reference applicable conclusions and/or calculations(if necessary). State short circuit current available at project site and state the source of this data. (5) A statement will be included describing all exterior lighting, with handicapped features if required. (6) List Specifications that will be used. The designer shall obtain the specifications listed and use them as design criteria. (7) Include a statement that no brand names or proprietary items will be used in the final plans and specifications. 16.3.4 Exterior Electronic System Design Analysis Narrative
(1) Provide a statement describing the extent of any exterior work such as telephone lines, duct banks, etc., outside of 5 feet from the building line. Provide brief description of the standards of design. (2) 16.4 List the specifications that will be used.
The Concept Design Analysis shall include the requirements stated below and shall include all data and calculations to support design decisions and estimates at this stage of design. The analysis shall incorporate specific criteria furnished and conference minutes of all systems considered. The analysis shall include the following: 16.4.1 Interior Electrical System Design Analysis Narrative
(1) Indicate Electrical Characteristics (phase voltage and number of wires) for electrical system. Justification for the type of system proposed (Economical or Special Condition). (2) Provide brief description of the lighting system(s) to be used for major areas and referencing calculations. Also include tabulation, showing the following: a. b. such as Room, name, and number. Lighting intensity for each room. (State design basis I.E.S., Definitive Drawings, etc.) 16-8
Type of fixture, either by Standard Drawing Number 40-06-04 or, if not applicable, include three (3) manufacturers' catalog cut sheets of each fixture type. (3) State type of wiring system, such as rigid or intermediate conduit, electrical metallic tubing, nonmetallic sheathed cable, etc., and location of proposed use. (4) Provide a paragraph describing special items of design, such as equipment, receptacles, handicapped and seismic requirements, etc.; include description and location. Reference pertinent NEMA or any recognized standards to identify type receptacles selected. (5) Clearly define and completely indicate any and all hazardous areas with the applicable class, group, division, zone, and suitable operating temperature as defined in the National Electrical Code. Do not attempt to design around the hazardous areas in lieu of designating the areas. State source of criteria, such as Safety Officer or some other recognized official. Include documentation of the source of the criteria. (6) Describe lightning protection system; if none, so state. (Reference TM 5-811-3 and NFPA 780). (7) Describe grounding system to be installed. If a counterpoise, grid, EMI shielding requirements, etc., is to be used, state standards to be used in design calculations. (8) Describe basic characteristics of panelboards, protective devices, switchgear, motor control centers or other major equipment to be provided. Short circuit and voltage drop calculations must be included to the service. Indicate equipment interrupting rating and short circuit withstand current, and include the source of this information. Evidence shall be included to support that the equipment is manufactured or can be manufactured and supplied by at least three reliable manufacturers and that the space is adequate for the equipment having the greatest dimensions. (9) List Unified Facilities Guide Specifications that will be used. Use Mobile Guide Specifications where available. The designer shall obtain the appropriate guide specifications and use them for design guidance. (10) Provide a firm statement that no brand names or proprietary items will be used in final plans and specifications. (11) Describe electrical metering equipment to be provided.
c.
(12) Provide a statement identifying the sustainable design features to be incorporated. See Chapter 20, Sustainable Design and Development (SDD) for specifics. (13) Provide a statement identifying compliance with AT/FP requirements. See chapter 19 for specifics. 16.4.2 (1) Interior Electronic Systems Design Analysis Narrative Where additions or alterations to existing systems are to be 16-9
made, verify that the systems are expandable and can accommodate the additions or alterations. Provide a description of all proposed additions and alterations to each system. (2) Provide a descriptive narrative of all electronic systems that are required for project. A list of some of the possible electronic components and/or systems that may be required on a given project are as follows: (a) (b) (c) (d) (e) (f) Telecommunication/Data Systems Fire Detection and Alarm System Mass Notification System Special Grounding Systems Public Address Systems Security Systems
(3) Telephone layout information should be furnished from the Using Service on "marked-up" 30%-35% drawings. (4) Clearly define and completely indicate any and all hazardous areas with the applicable class, group, division, zone and suitable operating temperature as defined in the National Electrical Code. Do not attempt to design around the hazardous areas in lieu of designating the areas. State source of criteria, such as Safety Officer or some other recognized official. Include documentation of the source of the criteria. (5) List the specifications that will be used.
16.4.3 Exterior Electrical Distribution System Design Analysis Narrative (1) Make a statement, with documentation, that the primary supply is adequate to support the added load. If the primary source is inadequate, state measures proposed to correct the deficiency in the design. Reference photographs of existing substations, pole line structures, or other exterior components. The photographs shall be included in the design analysis of all affected equipment and structures. (2) Provide electrical characteristics of power supply from the service point to the main service equipment (voltage, phase, number, and size of conductors). (3) Indicate type, number, kVA capacity and impedance of transformer installation proposed and state method of sizing. State primary and secondary connections of transformers (i.e., 12470 to 480Y/277 volts, Delta-wye) in accordance with ANSI C57.12.00. (4) State type of conductor, such as copper or aluminum, and where proposed to use and a justification for the choice made. (5) A statement will be included describing standards of design, 16-10
such as primary and secondary voltage drop, and physical characteristics of overhead or underground circuits. If underground, state the basis for the selection. Reference applicable conclusions and/or calculations. State short circuit current available at project site and state the source of this data. (6) A statement will be included describing all exterior lighting, with handicapped features if required. IES point-to-point calculations shall be submitted to support the selection for the aforementioned lighting system. (7) List Specifications that will be used. The designer shall obtain the specifications listed and use them as design criteria. (8) Include a statement that no brand names or proprietary items will be used in the final plans and specifications. 16.4.4 Exterior Electronic System Design Analysis Narrative
(1) Provide a statement describing the extent of any exterior work such as telephone lines, duct banks, etc., outside of 5 feet from the building line. (2) 16.4.5 List the specifications that will be used. Concept Design Drawings (30%-35%) Interior Electrical Show typical room lighting and receptacle layouts on floor plan.
16.4.5.1 (1)
(2) Show the service and the main electrical service and size same.
equipment
(3) Show the location of all major pieces of electrical equipment, including panelboards. (4) Show the proposed riser diagram. Sizes of all conduit, wires, cables, panels, etc., need not be included, except for the main service feeder. Where the electrical configuration cannot be adequately explained on a power riser diagram, a complete one-line diagram will be provided. (5) Provide samples of panelboard, switchboard, motor control and fixture schedules. (See EXHIBIT 16-1 and 16-2.) (6) Clearly define and completely indicate any and all hazardous areas with the applicable class, group, division, and suitable operating temperature as defined in the National Electrical Code. Do not attempt to design around the hazardous areas in lieu of designating the areas. State source of criteria, such as Safety Officer or some other recognized official. Include documentation of the source of the criteria. 16.4.5.2 (1) Interior Electronic Systems Show the location of all electronic system panels, etc., on 16-11
floor plans. (2) Show the proposed riser diagrams for all systems. Sizes of conduit, wires, cables, panels, etc., need not be included at the 30%35% design. (See EXHIBIT 16-3, 16-4, 16-5, and 16-6) (3) Provide a complete symbol legend for all devices or equipment shown on the plans. (4) It may be necessary for the designer to provide a recommended layout for telephone, LAN, mass notification and CATV on floor plan. 16.4.5.3 Exterior Electrical
(1) Existing and new electrical primary lines both overhead and underground shall be properly identified. (2) Show removals and relocations, if any. separate drawing(s). If extensive, provide
(3) Indicate electrical characteristics of all items shown; include voltage, phase, conductor size, and kVA. (4) Show new construction and location of transformers.
(5) Indicate the secondary service to the facility and whether it is overhead or underground. (6) Show guy leads and guy strengths on the plans. Guying calculations shall be submitted verifying the guying design shown. 16.4.5.4 Exterior Electronic Systems
(1) Exterior work to be shown on electrical site plan or separate Electronic systems site plan. (a) and (b) 16.4.6 Existing and new communications service lines, both overhead underground, shall be properly identified. Show removals and relocations, if any.
16.4.7
Any additional criteria, deviations concerning criteria, questions or problems will be listed. 16.5 INTERIM DESIGN (50%-60%) Interim Design Analysis
16.5.1
(not amendments to concept submittal) to permit verification that the design complies with the criteria furnished and the approved Concept Design. Short circuit and voltage drop calculations shall be included to all panelboards. 16.5.1.1 Interior Electrical System Design Analysis Narrative
(1) Indicate Electrical Characteristics (phase voltage and number of wires for the electrical system. Justification for the type of system proposed (Economical or Special Condition). A life cycle analysis is required on 120/208 volt system above 300 kVA. (2) Provide description of lighting system(s) to be used for all areas, referencing calculations and economic analysis. Also include tabulation, showing the following: (a) Room name and number (b) Lighting intensity for each room. (State design basis such I.E.S., Definitive Drawings, etc.) (c) Type of fixture, either by Standard Drawing Number 40-06-04 or, if not applicable, provide three (3) manufacturers' catalog cut sheets of each fixture not in the 40-06-04. (3) State type of wiring system, such as rigid or intermediate conduit, electrical metallic tubing, nonmetallic sheathed cable, etc., and location of proposed use. (4) Provide a paragraph describing special items of design, such as equipment, receptacles, handicapped and seismic requirements, etc.; include description and location. Reference pertinent NEMA or any recognized standards to identify type receptacles selected. (5) Clearly define and completely indicate any and all hazardous areas with the applicable class, group, division, zone, and suitable operating temperature as defined in the National Electrical Code. Do not attempt to design around the hazardous areas in lieu of designating the areas. State source of criteria, such as Safety Officer or some other recognized official. Include documentation of the source of the criteria. Insure that all devices installed in hazardous classified locations are shown and/or specified as suitable for the location in which they are installed. (6) Describe lightning protection system; if none, so state. (Reference TM 5-8ll-3 and NFPA 780.) (7) Describe grounding system to be installed. If a counterpoise, grid, etc., is to be used, state standards to be used in design calculations. (8) Describe basic characteristics of panelboards, protective devices, switchgear, motor control centers or other major equipment to be provided. Short circuit and voltage drop calculations must be included to all panelboards. Indicate equipment interrupting rating and short circuit withstand current, and include the source of this information. Evidence shall be included to support that the equipment is manufactured and/or can be manufactured and supplied by at least three reliable manufacturers and that the space is adequate for the 16-13
equipment having the greatest dimensions. (9) used. (10) Provide a firm statement that no brand names or proprietary items will be used in final plans and specifications. (11) Describe electrical metering equipment to be provided. If facility has an UMCS (EMCS) System, address method to provide signals to master station. (12) Include a statement certifying that the designer has implemented the 30%-35% annotated comments. List Unified Facilities Guide Specifications that will be
(13) Provide a statement identifying the sustainable design features to be incorporated. See Chapter 20, Sustainable Design and Development (SDD) for specifics. (14) Provide a statement identifying compliance with AT/FP requirements. See chapter 19 for specifics. 16.5.1.2 Exterior Electrical Distribution System Design Analysis Narrative
(1) Make a statement, with documentation, that the primary supply is adequate to support the added load. If the primary source is inadequate, state measures proposed to correct the deficiency in the design. Reference photographs of existing substations, pole line structures, or other exterior components. The photographs shall be included in the design analysis of all affected equipment and structures. Properly label all photographs indicating pole location, pole designation and view orientation of picture. (2) Provide electrical characteristics of power supply from the service point to the main service equipment (voltage, phase, number, and size of conductors). (3) Indicate type, number, kVA capacity and impedance of transformer installation proposed. State primary and secondary connections of transformers (i.e., 12470 to 480Y/277 volts, Delta-wye), in accordance with ANSI C57.12.00. (4) State type of conductor, such as copper or aluminum, and location of proposed use and a justification for the choice made.
(5) A statement will be included describing standards of design, such as primary and secondary voltage drop, and physical characteristics of overhead or underground circuits. If underground, state the basis for the selection. Reference applicable conclusions and/or calculations. State short circuit current available at project site and state the source of this data. (6) A statement will be included describing all exterior lighting, with handicapped features if required. Types of fixtures, pole heights, and proposed intensities are to be included. IES pointto-point calculations shall be submitted to support the selection for the aforementioned lighting system. 16-14
(7)
(8) Include a statement that no brand names or proprietary items will be used in the final plans and specifications.
16.5.2
16.5.2.1
(1) All removals must be shown. If removals are extensive, separate demolition plans are required. The designer shall display the information in such a manner that it would not be necessary to visit the site to prepare a bid. (2) A complete legend shall be provided for all devices and equipment shown on the plans. Mounting heights shall be included as applicable. 16.5.2.2 Interior Electrical
(1) Power riser or one-line diagram shall be essentially complete except for finalization of conduit and wire sizes. (2) Panelboards, motor control centers, switchgear equipment and all utilization equipment shall be located with schedules and physical layout arrangement completed. Provide front elevations for freestanding equipment. (3) Branch circuits, lighting fixtures with switches, receptacles, and motors shall be shown with number of conductors indicated. (4) drawings. A completed fixture schedule shall be included on the
(5) Before submittal, drawings shall be thoroughly checked by the designer for discrepancies and conflicts, particularly as related between disciplines and various systems above dropped ceiling. 16.5.2.3 (1) Electronic Systems All exterior plans should be completed.
(2) Thoroughly check for discrepancies and conflicts, particularly between disciplines. (3) Any removals required must be shown. If removals are extensive, demolition plans are required.
(4) Provide riser diagrams for fire detection and alarm system, intrusion detection system, public address system, telephone system, mass notification system, etc. Risers should show the location of the 16-15
various components and interconnections with other systems such as HVAC panel connections to fire alarm panels, etc. (See EXHIBIT 16-3, 16-4, 16-5 and 16-6) (5) Show location of all devices and equipment for electronic systems on the floor plans. Show location of devices to be interconnected; e.g., show duct-mounted smoke detectors, hood firesuppression system contacts for fire alarm system input, etc. Location of all devices shall conform to NFPA 72 and UFC 3-600-01, ADA and/or UFAS. (6) Provide details of telephone outlets, telephone backboard arrangement, and other items required by criteria or comment. (7) 16.5.2.4 Provide data for special ground system. Exterior Electrical
All exterior electrical shall be completed in plan with poles and other pertinent components detailed. Details shall include transformer's location, type of construction, kVA, impedance, voltage, phase, and type, size and number of conductors. If manholes or handholes are required for underground, utilize typical manhole from TM 5-811-1. Manholes and/or handholes shall be detailed on final drawings. 16.5.3 Additional Criteria
Any additional criteria, deviations concerning criteria, questions or problems should be listed. 16.6 FINAL DESIGN (Unreviewed 100%) Final Design Analysis
16.6.1
This analysis is an extension of the approved 50%-60% design analysis and supports and verifies that the design complies with the requirements of the project. A coordination analysis of the electrical system shall be provided as stated herein below. This requirement depends on the complexity of the project. It shall not be provided for projects having nonadjustable protective devices for which coordination is not possible (e.g. standard molded case breakers). Projects that are served by a transformer 750 kVA or less do not require a study. All other systems shall have a coordination study provided. 16.6.2 Final Design Drawings.
The final drawings are an extension of the approved 50%-60% drawings and shall incorporate the 50%-60% comments. (1) All details for final package shall be on the drawings (pole details, fixture details, etc.). Congested areas where there can be interference with various electrical systems, cable trays, piping, ducts, etc., shall be thoroughly detailed by expanded scale drawings. (2) Thoroughly check the drawings for discrepancies, for compatibility between drawings and specifications, and for compatibility between disciplines. Check the following, as a minimum, but DO NOT 16-16
LIMIT CHECKING TO THESE ITEMS: (a) Verify compatibility between electrical, electronic systems, and other disciplines (equipment locations, reflected ceiling plans, motor voltage and across the line as reduced voltage starters and horsepower, NEMA enclosures, plans and specifications for systems furnished in other specification sections, etc.), to ascertain that there are no conflicts on the drawings. (b) Panelboards, motor control centers, switchboard and switchgear schedules, home runs, and floor plans. (c) Power riser or one-line diagram configuration agrees with floor plans. (d) drawings. (e) Fixture types indicated on the drawings agree with fixture schedule. (f) criteria. (g) Adequacy of details and control diagrams. Assure design complies with design analysis and Legend and/or symbols complete and compatible with
(h) Proper and practical circuitry with number of conductors and conduit sizes indicated correctly. (i) Clearly define and completely indicate any and all hazardous areas with the applicable class, group, division, and suitable operating temperature as defined in the National Electrical Code. Do not attempt to design around the hazardous areas in lieu of designating the areas. State source of criteria, such as Safety Officer or some other recognized official. Include documentation of the source of the criteria. Insure that all devices installed in hazardous classified locations are shown and/or specified as suitable for the location in which they are installed. (j) Ensure that all Electronic Systems are provided with power.
(k) Ensure that the proper receptacle types(s) are provided for the specific special purpose equipment that will be used in the facility. Obtain equipment list and requirements from user. 16.6.3 Specifications
(1) Read thoroughly and comply with the instructions in each set of guide specifications, including notes to specification writer. The SPECINTACT specification writing system shall be used for specification preparation. (2) Cross out nonapplicable index items, publications, paragraphs, phrases, words, and sentences. Fill in blanks as applicable.
16-17
(3) Add publication references, paragraphs, phrases, words, and sentences for items not adequately covered by specifications. (4) Do not specify proprietary items.
(5) Ascertain that major or special types of equipment are available commercially. (6) The specifications shall require the contractor to provide a system short circuit study and coordination curves for the equipment to be furnished. The study and curves shall be approved prior to approval of shop drawings for the equipment. The study shall not be provided for projects having nonadjustable protective devices for which coordination is not possible (e.g. standard molded case breakers). Projects that are served by a transformer 750 kVA or less do not require a study. Certain facilities where the loss or power would be critical shall also require the study. (7) If the design is predominately exterior overhead or underground with a small amount of information required that is contained in the interior electrical specification, the design specifications may include excerpts from the interior specifications in either the overhead or underground specifications and the title changes to "Electrical". This procedure must have prior approval. 16.7 READY-TO-ADVERTISE (100%)
The comments generated during the Final Review shall be incorporated into the completed design analysis (not amended sheets), specifications, and drawings before they are submitted as Ready-to-Advertise. The analysis shall be complete and shall support the requirements of the project. The drawings and specifications shall be complete and thoroughly checked. Where additions to existing electronic systems are made, the designer shall have verified that the existing system is expandable and can accommodate the additions. This verification shall include an onsite survey of the system and contacts with the manufacturer to ensure that the expansion modules, etc., are available. Information on manufacturer, model number, etc., of the existing electronic equipment shall be included in the plans and specifications. This is typical of expansions made to fire alarm and public address systems. 17.8 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS
TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs. 16.8.1 Mandatory Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development: 16-18
a. All criteria that is not listed in the RFP will not normally be a part of the RFP. Any specific TI, UFC, etc. that is required to be used shall be referenced as mandatory. A link to a web site where the specific criteria can be obtained shall be provided. b. 16.8.2 See TI 800-03 for additional mandatory requirements. Specific Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria:
1. Include all the information included in paragraph 16.4 CONCEPT DESIGN (30%-35%) b. Partial Project Criteria:
1. Include all the information included in paragraph 16.5 INTERIM DESIGN (50%-60%) except that branch circuit wiring need not be shown unless deemed necessary for the specific project. Completed panel schedules are also not necessary unless deemed appropriate. c. Full Project Criteria:
1. Final Plumbing Plans (See description above under 16.6 FINAL DESIGN.) 2. Final Specifications (See description above under 16.6 FINAL DESIGN.) NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements. 16.9 TECHNICAL REQUIREMENTS.
16.9.1 Metering. Metering shall be provided for both Army and Air Force projects as required by UFC 3-520-01. 16.9.2 Salvageable Material
The salvageable material resulting from a demolition design and not reincorporated in the design remains property of the U.S. Government. The debris will be disposed of as directed by the Contracting Officers Representative. Typical removal paragraphs are listed below. 16.9.2.1 Removals
Where indicated, existing equipment and material shall be removed and shall remain the property of the Government. Salvageable equipment and materials shall be delivered to the Contracting Officers Representative for storage on the premises as directed. Materials and debris considered unsalvageable by the Contracting Officers Representative 16-19
Removed materials with the exception of poles shall be reused if they are in good condition and they meet the requirements of this section of the specifications. Removed wood poles shall not be reinstalled. (Removed materials not incorporated in the new work shall be delivered to storage and disposed of as directed by the Contracting Officers Representative.) 16.9.3 Special Items
The following items will be included in each submittal, where applicable: (1) Unified Facilities Guide Specifications must be used in preparing contract specifications for diesel-electric generators. Unless application requires otherwise, provide brushless type generators. (2) Egress lighting must comply with life safety code NFPA 101. In the concept and design analysis, write up reference paragraph and chapter that the design is based upon. (3) Facilities requiring design for the handicapped shall comply with the Uniform Federal Accessibility Standards (UFAS)as outlined in 41-CFR-101-19.6, as well as the American with Disability Act (ADA), and all state and local laws and standards for buildings and facilities requiring accessibility and usability for physically handicapped people. These instructions cover such items as switch heights, adequate lighting at ramps, exit lights, etc. The most stringent of these codes shall be applicable. (4) In areas where the probability of hurricanes are high, distribution systems and equipment outside of buildings are to be adequately anchored, braced, or guyed to withstand hurricane winds. Details with supporting design analysis and specifications will be provided to verify conformance with the applicable codes and regulations for the specific project location. (5) Provide both green grounding conductors and driven electrodes for exterior lighting poles. (6) Seismic design, when required, shall be in accordance with UFC 1-200-01. (7) Dedicated electrical space shall be provided around and above panelboards, switchboards, transformers, transfer switches, motor control centers and similar major items of electrical equipment. This space shall be defined in accordance with UFC 3-520-01. (8) Fire Resistant Ceilings. When the false ceiling is used as the fire resistant ceiling, then the lighting fixtures shall be installed in accordance with Underwriters Laboratories Fire Resistance Directory. The lighting fixtures specified shall be classified for fire resistance and will be so noted in the lighting fixture schedule. (9) All air-cooled chillers shall be served by a fused disconnect 16-20
switch. The fuse size shall be as indicated by the name plate on the equipment installed. (10) Electrically-driven fire pumps. The designer will insure that the requirements of NFPA 20 are met in all designs that include fire pumps. In particular, a letter from the installation confirming reliability of the utility service in accordance with UFC 3-600-01 and calculations that substantiate the starting voltage drop requirements must be submitted by the designer. (11) Interior Lighting Systems. Interior lighting accounts for a significant portion of electrical energy consumed in a building. Energy is saved and electric demand reduced by improving lighting system efficiency and using daylighting. The lighting design shall incorporate the latest techniques of energy savings applied to lighting systems. Lighting designs shall incorporate high efficiency fluorescent tubes. Designs for work within existing buildings shall be compatible with the existing system. When designing new lighting systems the designer shall consider incorporating the following features into the lighting design: high efficiency electronic ballasts, the use of automated dimmers sensitive to the amount of natural light in the space, the use of motion detectors and/or other devices to automatically turn off lights in unoccupied rooms. Employ sustainable design features to the greatest extent possible. (12) Nonmetallic sheathed cable will be included in all Army designs, and in Air Force where allowed by MIL HDBK 1190, as allowed by the National Electric Code. In CMU block construction, a detail will be included to indicate how the cable shall traverse through the block and bond beams. (13) Electrical Service to Army Reserve Centers shall be underground as required in the "Design Guide" furnished to all designer's designing ARC's. The primary will be extended UG from the property line to a padmounted transformer near the mechanical room, and then an UG secondary will be extended into the building. A letter must be furnished (as part of the 30%-35% design analysis) from the power company giving the costs and all their requirements for the complete installation of the UG service. Where an exact cost cannot be furnished, an estimate will be adequate for the 30%-35%. An exact cost, however, must be obtained before the Final (unreviewed 100%) submittal for inclusion in the specifications as a separate bid item. (15) The thickness of long runs of grounding bus bar shall be 3 X if shown to be supported at 5 ft. intervals. If thinner bus bar (1/4) is used, supportive intervals shall be at 2-ft. (15) Insure that the Impedance for the main transformer(s) are shown on the drawings and/or covered in the specifications. (16) Low-pressure sodium light fixtures shall be utilized for installations where use of other types of HID fixtures present environment concerns (e.g. impact on marine life such as sea turtles). See also, installation site specific criteria. (17) Where applicable, provide lighting controls on stage in classrooms and assembly rooms where instructions take place. 16.9.4 Design Criteria for Nonlinear Loads
16-21
The design of the electrical distribution (both normal and emergency power) shall consider the effects that harmonics from non-linear loads can produce on the system. Harmonics from non-linear loads can affect the sizes of the neutral conductor, panelboards, phase conductors and emergency generators. Design for facilities having nonlinear loads shall be in accordance with ETL 1110-3-403 dated June 1989. Per the requirements of paragraphs 4c and 4g, the use of 75 degree C. (minimum) conductors is required and must be shown as such on the drawings. Eight-wire branch circuits within the building which serve nonlinear loads shall be 3#12, 3#10 N., 1#12 GND., and 1#12 Isolated GND. Feeders serving panelboards with nonlinear loads shall have the neutral conductor ampacity based on at least 1.73 the ampacity of the phase conductors. The simplest way to accomplish this is a double ampacity neutral or parallel neutrals in sizes allowed by the National Electrical Code. "K" rated transformers shall be used where the associated panelboards are feeding a large quantity of non-linear loads. Special attention shall be given to the harmonics produced by variable speed and variable frequency drive units for control of HVAC equipment.
16.9.4.1 The following sentence shall be included in the general wiring paragraph of SECTION 16415A (ELECTRICAL WORK, INTERIOR): (1) "Conductor sizes for nonlinear loads (as shown on the drawings) are based on the use of 75 degree C. (minimum) insulated conductors for the branch circuits and feeders." 16.9.5 Telecommunication/Data Systems
Telephone service entrance cables will be provided by the telephone company to the site. The designer shall design a raceway system from a point on site designated by the telephone company or using agency into the main telephone room in the facility. All conduit shall be concrete encased when run underground. Spare conduit(s) shall be included in the service entrance run. While the telephone service may be provided by the Telephone Company, the designer shall verify all telephone/data requirements. 16.9.5.1 General Design
Design shall include the provision of required electrical components and a complete raceway system and cabling for the telecommunications system. Sufficient details for cabling, conduits, raceways, wiring ducts, and similar delivery means for telecommunications services shall be provided to guide the Contractor in their installation. The incoming telephone service raceways and primary communications room shall be kept separate from the electrical service raceways and main electrical equipment room. These services must remain separate through to the final point of delivery in user areas. 16.9.5.2 Additional Design Guidance
The following additional design guidance must be practiced: (1) The designer shall incorporate into the design a telephone system in accordance with all pertinent regulations and guidelines and with criteria provided. This may include a complete and operational 16-22
telephone system or prewire the building such that the telephone equipment may be installed by others. The designer must specify all cable, modular outlets, etc. (2) Telephone outlet locations should be provided to the designer by the Using Agency. Coordinate with the Project Manager for requirements. Show location of telephone outlets on the plans. Include notation or symbol definition to indicate height above finished floor (A.F.F.). (3) Show Telephone Conduit System Riser Diagram on the plans. Size conduit on Riser Diagram. Do not show conduit runs between the telephone closet backboards and outlets on the floor plans. (4) Underground telephone entrance conduit shall be shown on the electrical site plan or separate electronic systems site plan. If installation to an existing pole, manhole, etc., is not required and if an entrance conduit termination location is not designated by the local telephone company as indicated above, the conduits must extend 5 feet, as a minimum, outside building and should be clear of any decorative wall, sidewalks, parking areas, etc., with a clear, planned route to the service connection point (pole, manhole, etc.). Outside of the building, the conduit should be capped and the location marked for future installation of cable by telephone company. All underground conduits should be a minimum of thirty (30) inches below grade and concrete encased. (5) When involved with a large complex or building (i.e., multibuilding complex, etc.), make a determination as early as possible if a private automatic branch exchange (PABX) is or will be planned. PABX installations require special considerations (e.g., space, additional HVAC, vented exhaust systems for batteries, rated walls, hazardous area, etc.). Often, the plans for a PABX may not be stated in the specific project document. State any requirement or anticipated plans for a PABX in the concept design analysis along with all data justifying this need. (6) When telephone outlets are installed in prewired workstations, the cable shall be a continuous run from the outlet to the connector block at the backboard. (7) The designer shall insure that the telephone system design complies with the Uniform Federal Accessibility Standards (UFAS) and/or the American with Disability Act (ADA), and all state and local laws and standards for buildings and facilities requiring accessibility and usability for physically handicapped people. These instructions cover such items as the height of payphones, These requirements may require that power outlets be provided next to telephones for TDD devices. (8) Provide show telephone jack in each Elevator Equipment Room. Add a note on title drawing stating g that The Contractor shall obtain the elevator response telephone number from the base via the Contracting Officers Representative. (9) Check with the base Communications Officer for requirements associated with providing a LAN (Local Area Network) connections to the mechanical HVAC DDC Controls. Coordinate with the Mechanical designer. (10) Include provisions for under floor routing of microphone and other types or cables in courtrooms and similar areas. 16-23
16.9.6
The fire detection and alarm system shall comply with the following design guidance where applicable. (1) System shall conform to the NFPA Codes and ADA and/or UFAS Requirements. (2) Do not show wire or conduit size, or the quantity of conductors in the circuits, as they will vary with different manufacturers and shall be required by the specifications to be included in the shop drawings. One exception to this requirement is the AC power circuit to the fire alarm equipment. (3) Show location of all system components on the floor plans. Use NFPA 160 standard symbols. (4) Provide a riser diagram showing the control panel, annunciator panel (if required), all zones, radio transmitter (if required), battery cabinet and interfaces to other systems (HVAC, sprinkler, hood dry chemical, etc.). (5) Primary power shall be provided from a lockable breaker in electrical panel nearest to the originating point of the power and lighting service (208Y/120 Volts). Backup power shall be provided by batteries and charger. (6) The fire alarm system must report to a Central Station. if required, (which will send an alarm signal to the local fire station) via transceiver, transmitter connected to telephone lines or existing fire reporting system. Conduit and wire in building to be included in design. The Contractor does not normally supply the central station receiver module; however, any equipment supplied must be fully compatible with the central station equipment. The make and model number of control station equipment must be determined for inclusion in the specifications. (7) The specific project Criteria shall be followed for specific requirements. All ambiguities or conflicts should be clarified early in the design. 16.9.7 Special Grounding Systems General
16.9.7.1
Special grounding systems, such as for computer and electronic equipment; for lightning protection of sensitive electronics equipment, such as radios and communication equipment shall be designed in accordance with the specific project POR document. A common grounding system can be utilized, when practical, for all grounding needs. When separate grounding systems are provided, all grounding systems shall be tied together below grade, unless otherwise directed. The surface area and lateral extent of the ground electrode in the earth, and resistivity of the earth are major factors in determining the effective resistance of the combination, known as the electrode groundresistance. Frequently, a single electrode of even the maximum practical dimensions will not provide acceptable electrode ground resistance. In such cases, additional electrodes must be added, all 16-24
For certain special grounding systems, a design specialist will be required by the designer contract. When so indicated, field work, analysis and design must be accomplished by or under the direct supervision of an Engineer having at least 10 years experience in the design of special-type grounding systems and shall have successfully completed at least 10 projects of similar nature. Proof demonstrating the above shall be provided the Contracting Officers Representative. The expert may be a consultant hired especially for the particular project or may be a regular employee of the designer, but his credentials must be acceptable in the judgment of the Contracting Officers Representative. 16.9.7.3 Description of Analysis Work
(1) The designer will conduct measurements in a number of areas to determine the location, number and length of ground rods to provide the required ground resistance. (2) The designer shall clearly define areas that could create corrosion problems and necessitate the need for cathodic protection, due to installation of the grounding system. 16.9.7.4 Design of a Ground System
(1) The specifications and drawings shall completely reflect all of the design requirements. The specifications shall require field tests (in the construction phase), witnessed by the Contracting Officers Representative, to determine the effectiveness of the grounding system. (2) The design must include drawings showing existing construction. Verification of the validity of any existing drawings and/or any other data furnished by the Government shall be the responsibility of the engineering services firm. (3) The designer shall provide a cost estimate for the grounding system. This will include all construction and testing cost reflected to installation of the grounding system. The estimate shall be a detailed estimate, showing equipment, labor, excavation, etc. (4) 16.9.8 Use IEEE 142 for additional design guidance.
Public address systems encompass many applications of amplified voice and music used for entertainment and distribution of voice messages. They run the gamut from a speech reinforcement system in a conference room, to a frequency equalized voice and music system for an auditorium, and on to a complex multi-zone system used for both background music and selective paging by zone with multi-media selectable inputs and area level control with paging capability. Most systems involve amplifiers, loudspeakers, and a program input. Inputs include microphones, AM/FM tuners, tape decks, phonographs, and compact disk players. Many configurations can be developed using standard equipment to fit any desired operational requirement. Each system is to be designed to meet the user's criteria requirements. 16-25
In many cases, space limitations dictate the use of wall-mounted amplifiers. Dual voice coil speakers should be used for background music systems that require voice paging to override the music levels. The use of miniature relays at zone volume controls to override volume control settings for paging should be avoided. In small systems employing relatively-short runs of audio bus cable and low power requirements, a 25-volt distribution system should be used. Where long runs with high power requirements are levied on the distribution network, a 70-volt system should be used. The choice of all system components should be based on design calculations. These calculations should begin with the desired sound pressure level to be achieved in each area and be developed through the system to establish component power capacity and wire sizes. Specifications shall include sufficient technical data to establish minimum equipment quality levels. This data shall include frequency response, distortion, RMS power capacity, and minimum number and types of controls. Public address systems shall be designed in accordance with the specifications and EIA standards for sound systems. All-channel paging, consisting of paging microphone, push-to-talk switch paging amplifier, and one or more paging relays, shall be provided. All accessories, material and other equipment for a complete public address system shall be furnished. The system shall be accessed via the telephone system and may be located in the main telephone equipment room for convenience of interfacing. The design of Public Address System must be coordinated with the telephone system and the user. The system must be sized to be audible at all points throughout the facility. The system can be accessed through individual telephone handsets as well as through PBX switch. The system shall provide hands free talk back capabilities in lab areas. At a minimum, separate paging zones shall be provided for the following areas: Administrative offices, Chemical labs, Biological labs, General office areas, Hazardous storage areas, Parking lots, and Exterior secured areas. In multi-floor facilities, further zoning will be required. Controls for individual speaker units shall be wall mounted and include volume control and on/off switching. The system shall comply with the Uniform Federal Accessibility Standards as well as the American with Disability Act (ADA), and all state and local laws and standards for buildings and facilities requiring accessibility and usability for physically handicapped people. These instructions may require additional amplification devices. 16.9.9 Intrusion Detection Systems
(1) The designer shall design a complete intrusion detection system, as required by user comments and criteria. The designer shall have a minimum of 3 years experience in similar installations. The intrusion detection system shall protect all grade level doors, operable windows and openings leading into the facility as well as roof hatches and roof access doors. Operable windows shall be lockable and accessible windows shall be alarmed. Roof access doors or hatches shall be secured with heavy duty hardware and alarmed. In addition to perimeter protection, alarm a minimum of the interior doors as designated by the user. Door switches shall be of the balanced magnetic type.
16-26
(2) drawings.
(3) A lockable circuit breaker shall be reserved for the Intrusion Detection System primary power connection in the 120V power panel located nearest the service entrance. (4) All signal conductors outside component enclosures must be enclosed in rigid, heavy wall conduit or intermediate metal conduit (IMC). Power cable from the Control Unit and the Monitor Cabinet to their respective junction boxes may be in electrical metal tubing (EMT). 16.9.10 Leak Detection for Underground Storage Tanks General
16.9.10.1
Leak detection must be provided for underground storage tanks and piping which will contain petroleum products or the hazardous materials as required by local, state, or federal regulation. The leak detection provisions shall comply with all requirements established by EPA, State or local regulatory authorization. 16.9.10.2 Guidance
Specifications for the leak detection system shall be included in the specification section containing the tank and piping. Locations of control panels, cables, conduits, alarms, and all other electrical details associated with the leak detection system shall be shown on the Electrical drawings. 16.9.11 Lightning Protection System Minimum Scope
16.9.11.1
A lightning protection system shall be provided for all facilities containing laboratory modules, as well as for facilities containing radioactive or explosive materials. 16.9.11.2 Additional Scope
For building types not in the above description, a risk assessment shall be performed using the guides in TM 5-8ll-3 and NFPA 780 to determine the risk of loss due to lightning. 16.9.11.3 Master Label
For buildings and facilities with a strong risk potential, furnish and install equipment, accessories, and material necessary for a complete "Master" labeled lightning protection system to protect all building components. The system shall comply with all the requirements of TM 5-8ll-3 and AMC-R 385-100, as well as the National Fire Protection Association (NFPA 780), the Underwriter's Laboratories, Inc., (UL 96A), and the Lightning Protection Institute (LPI 165). All cables, air terminals, and accessories shall be copper. All connections and splices shall be exothermic weld type. 16.9.11.4 Minimum Requirements
conductors built into the building during construction to conceal all conductors, and it shall be properly flashed and watertight. Installation shall be made in conformance with shop drawings prepared by supplier and approved by the Government. 16.9.11.5 Certification Delivery
Before the lightning protection system is accepted, the contractor shall obtain and deliver to the supervising architect, the "Master Label" of the Underwriters Laboratories, Inc., or an equivalent certification. 16.9.12 Local Area Networks (LAN)
Local Area Networks shall be included for all projects, as required. The basic criteria will be obtained by the user and provided to the designer for inclusion in the project. All LAN outlets installed in prewired work stations shall be wired continuous from the outlet to the backboard, multitap, etc., depending on type system installed. 16.9.13 Hospital Systems
Hospital systems are very special designs, and specific requirements should be provided for each project. Hospital systems include Nurse Call, Central Dictation, Patient Monitoring, Radio and Public Address, CATV or MATV, Radio Paging Telephone, etc. 16.9.14 Cable Television Systems (CATV)
The CATV shall be a prewired system or a conduit system only for projects according to the criteria given. A two-inch (2") empty entrance conduit shall be installed for all projects for future installation of service cable by Using Agency. Provide a 3/4-inch plywood backboard with sufficient space for the distribution cable terminations, amplifiers, and splitters. The systems shall include cables from the backboard to each outlet, connectors on outlet plates and sufficient spare cable at backboard for future connection to splitters. All empty conduits shall have pull wires. Specifications will be included in Section ELECTRICAL WORK, INTERIOR. 16.9.15 Closed Circuit Television Security (CCTV) System
The video security system, where required, shall be integrated into the overall function of the facility. The designer shall design a complete closed circuit television security (CCTV) system and shall have a minimum of 3 years experience in similar installations. Placement of cameras must be carefully considered in order to avoid dead zones. Conduit and wiring shall be installed for the system and a camera shall be installed at all entrance and exit areas. The location of the camera shall be suitable for monitoring people movement when entering or leaving the building and an emergency circuit shall provide power for each camera location. Conduit, wiring, cameras, etc., shall also be installed in all parking lots, loading docks, and computer areas to provide monitoring. (1) Cameras shall be of the fixed or pan-tilt-zoom type as required for each specific location. Camera components shall include cameras, lenses, fixed and remote-control camera accessories, camera housing, and environmental options. Cameras shall be housed in proper enclosures for the environment in which they are to operate (e.g., defrosters, heaters, weatherproof enclosures, corrosion resistant or 16-28
vandalproof enclosures, etc.). (2) All cameras shall be monitored/controlled at the facilities central control station. Monitors shall be event driven. Monitor components shall include monitors and monitor mounts. A VCR shall be provided where required, to record unauthorized access (control by guard). A 120 volt single duplex receptacle (emergency power) shall be provided immediately adjacent to all CCTV camera locations. (3) CCTV cameras shall be provided to monitor entry and exiting from the loading dock areas. CCTV monitors (in addition to that at the central console for the loading dock areas), shall be provided in the loading dock office to provide identification of delivery vehicles prior to opening the loading dock doors.
16-29
EXHIBIT 16-1
16-30
EXHIBIT 16-2
16-31
EXHIBIT 16-4
16-33
EXHIBIT 16-5
16-34
EXHIBIT 16-6
16-35
Obtain a copy of the project scope. This may be in the form of the charrette report, RAMP, 1391 or other similar document. Major items of electrical equipment (e.g. generators, etc.) and special utilities (e.g. underground power lines) must be line items in the 1391 or they are not allowed. Insure that the following criteria, where appropriate has been incorporated in the design: MIL HDBK 1190 Military Handbook for Facility Planning and Design Guide MIL HDBK 1191 Military Handbook for Medical and Dental Treatment Facilities, Design and Construction Criteria Guide TM 5-8ll-l Electric Power Supply and Distribution TM 5-8ll-3 Electrical Design: Lightning and Static Electricity Protection UFC 4-021-01 Design and O&M: Mass Notification UFC 3-520-01 Interior Electrical Systems UFC 3-600-01 Design: Fire Protection Engineering for Facilities UFC 4-010-01 DOD Minimum Antiterrorism Standards for Buildings TI 800-01 Design Guide TI 800-01 Design Build Instructions TI 811-16 Lighting Design Check the power riser diagram. o Main transformer Check to insure that the primary and secondary voltages/connections are shown. Check to see if the impedance is shown or covered in the specifications. Primary Insure that the size and voltage rating of the cable is shown. Insure that the size is adequate for the transformer size. Insure that fused cutouts or fused primary switch is shown. Service Insure that the service entrance conductors are sized for the demand load or the transformer secondary current as a maximum. Insure that the grounding electrode conductor is in accordance with NEC Article 250. Service Equipment Insure that the main breaker and interrupting ratings are shown (verify interrupting rating with short circuit calculations; verify the continuous current rating with demand load calculations). Insure that the main bus rating is shown (size should agree with the demand load calculations as a minimum).
16-36
Insure that Ground Fault Protection is shown if required be the National Electrical Code. See also additional requirements from UFC 3-520-01. Insure that 15%-25% spare breakers are shown. EXHIBIT 16-7 page 1 Subpanels Insure that the feeders are sized per the demand load calculations (as a minimum; can be sized to match the rating of the panel) Insure that the panel main breaker (if not MLO) is sized for the panel rating. Insure that the interrupting rating is shown and verified by short circuit calculations. Insure that the panel trim (flush vs. surface) is shown. Insure that a oversized neutral is shown when required for nonlinear loads (ETL 1110-3-403) Insure that 15%-25% spare breakers are shown. o 208Y/120 Volt Panels Insure that the required main breaker is shown. Check to insure that it is sized at the demand load as a minimum or the panel rating as a maximum. Insure that the interrupting rating is shown and verified by short circuit calculations. Insure that an oversized neutral is show when required for nonlinear loads (ETL 1110-3-403). Insure that 15%-25% spare breakers are shown. o 480Y/277 Volt dry type transformers Insure that these are sized by demand load calculations. Indicate the K-Factor ratings on the drawings and in the specifications. Insure that the grounding electrode conductor is shown in accordance with Article 250of the National Electrical Code. Insure that the primary and secondary connections are shown. Insure that the impedance is shown. Floor Plans o Compare the electrical plans (lighting, power, and systems) with the architectural to insure that these agree. o Compare these plans with the mechanical plans to insure that power is provided to mechanical equipment and it its the correct size as shown in the mechanical equipment schedule(s). Lighting Plans o Coordinate the lighting fixture layout with the HVAC plans to insure that fixtures and registers do not conflict in location. o Insure that lighting switches are shown on the correct side of the door swing and that they are not located in sidelights or other glass. o Insure that a fixture schedule is included. Use the new 4006-06 for details and EI 16E500 for the schedule. 16-37 o
Insure that fixtures chosen are compatible with ceiling types specified on the architectural plans. o Insure that boundaries of any hazardous classified location and identification of this location(s) are shown clearly. o If dimming ballasts are required, insure that they are shown in the details and/or schedule. Power Plans o Verify that there is power to each piece of HVAC equipment (size for the sizes shown in mechanical equipment schedules. o Insure that GFI is provided where required by the National Electrical Code o Insure that the chiller circuit is sized in accordance with manufacturers data and that the data is included in the design analysis. EXHIBIT 16-7 page 2 o o o Insure that receptacles are located at the TBB, LAN backboard and at DDC controls. Insure that there is at least one outlet on every wall. Panel Schedules: Panel name MLO or Main Breaker AIC rating shown Size of branch breaker and description shown Oversize neutral shown where required Surface or flush trim shown Voltage rating and main bus rating is shown Spare breakers shown Insure that standard sizes are shown (100 Amps < use 30 poles; 225 Amps < use 42 poles) Indicate any 2 section panels (state if they are feedthrough or double lugs) Insure that boundaries of any hazardous classified location and identification of this location(s) are shown clearly.
Fire Alarm Plans o Initiating devices Manual pull stations Every egress Every level 200 foot maximum travel distance. Area detection Protect all areas including area above ceiling if needed. Place all detection devices at least 12-18 inches from lights and 3 feet from HVAC registers. Heat detectors Reduce spacing for ceilings above 10 feet Reduce spacing for other that smooth ceiling (joist, beams, etc.) All points on ceiling shall be within .7 of the listed spacing after adjustments made Smoke detectors
16-38
Use 30 foot spacing as a guide Adjust spacing for other than smooth ceilings (joist, beams, etc.) All points on ceiling shall be within .7 of the listed spacing after adjustments made Consider the effects of stratification. Special Applications Use smoke detectors under raised floors and above ceilings if this area is a return air plenum. Use detectors rated for the air velocity present. See NFPA 72-5.7.5.3 for areas of high air movement. See NFPA 72-5.7.5.2 for high rack storage areas. See NFPA 72-6.15.5.2 for smoke door release. See NFPA 72-6.15.3 for elevator recall. EXHIBIT 16-7 page 3
Duct detectors Coordinate with the mechanical engineer Over 2000 CFM, provide on supply. Over 15000 CFM and multistory building, provide on return. Provide remote test station as required by NFPA 72. Show detectors on floor plans and in the riser. o Notification Appliances Audible Appliances Locate to provide sufficient sound level o 15 dB above ambient o 5 dB above maximum 60 second sound level o Double the distance loses 6 dB o Lose 25 dB through walls o Lose 10 dB through doors o UFGS states that bells/horns have 85 dBA at 10 feet o Provide devices on every floor o Provide devices in noisy areas (e.g. mechanical rooms, etc.) o Devices shall have a temporal sound pattern in accordance with NFPA 72 Visual Appliances o Space in accordance with Chapter 7 of NFPA 72 and ADA. Control Panel Where connecting to an existing system, insure that the existing and new systems are compatible. For conventional systems, use the following zones: Fire suppression system Hazardous areas Flow switches
16-39
Tamper switches Other supervisory devices Firemans elevator service Attic detectors Pull station Kitchen equipment Notification appliances Automatic door release Power shutdown to data processing equipment AHU shutdown Provide manual override for AHU shutdown testing NFPA 72 lists maximum number if devices fir a zone. Annunciator: use a graphic annunciator if one is required. Specify transceiver to be compatible with the base/post system
Riser Power
Diagram Show FACP Show power supply Show signaling method Show annunciator Show all zones supply Provide primary source from light and power system (208Y/120 volts) per NFPA 72. Secondary source is primarily batteries. Size per NFPA 72 requirements. PROVIDE A SEPARATE BATTERY CABINET. Power all devices from the FACP Wiring All wiring is to be Class A, Style D When connecting to an existing system, insure compatibility, Do not connect a 4-wire system to a 2-wire system. Sprinkler System Supervision Coordinate with the Mechanical/fire protection engineer. Flow switches Tamper switches Pressure switches (on all systems) Telephone o Coordinate that receptacles are located at the TBB o Verify that phone outlets are located as desired by the user o Provide telephone outlets at the DDC panel location o Verify that the telephone room complies with EIA/TIA standards
16-40
Insure that CAT 5 circuits have not exceeded the 90-meter limit in length.
Mass Notification System o Insure that audible and visual devices are shown o Insure that the system is shown interconnected with the FACP Site Plan o Verify that the electrical site plan agrees with the civil site plan o Coordinate with the landscaping plans to avoid conflicts between electrical equipment (transformers, lighting fixtures, etc.) and planting materials o Coordinate with the mechanical plans to avoid conflicts in location between transformers and chillers, etc. o Verify the lighting layout meets design lighting level prescribed in IES and the TI; support with calculations o Verify that required details are shown; these include pole details, pad details, manhole/handhole details, duct bank sections, etc. o Coordinate with other utilities (water, sewer, gas, storm sewer, etc.) to identify any conflicts and to insure that required code (IEEE C2 and NFPA 70) clearances are obtained
o o o o o
EXHIBIT 16-7 page 5 Verify that manholes/handholes have been located in accordance with pulling calculations Verify that overhead line clearances meet IEEE C2 (verified with sag calculations where required) Verify that guy leads and guy sizes are shown and supported by calculations. Verify that cathodic protection is provided where required and that all appropriate details are shown and that the current specifications have been used. Insure that all circuits that are intended to remain and be reconnected to new circuits are properly shown and all necessary work is identified.
Miscellaneous Drawings o Verify that all symbols are included in the legend (use Triservice standard symbols) o Verify that enlarged plans of electrical and/or mechanical rooms are included if necessary o Insure that the size of large items of equipment can be provided by at least three manufacturers o Verify that NFPA 70 clearances have been obtained Miscellaneous o Insure that Customer Specific Criteria has been incorporated o Insure that all design techniques for nonlinear loads have been incorporated Design Analysis o Calculations included Demand load analysis Lighting Calculations Zonal cavity for interior
16-41
o o o o Lessons o
Exterior Short circuit calculations Voltage drop calculations Coordination study provided (as required in the design manual) Design narrative Interior, exterior narratives Catalog cuts Learned Verify that all applicable lessons learned from the district database have been incorporated (at each design/review submittal). Lesson Learned certification is required before RTA.
16-42
CHAPTER 17 CORROSION CONTROL AND CATHODIC PROTECTION SYSTEMS INDEX 17.1 GENERAL 17.1.1 17.1.2 17.2 Scope Design Submittals
APPLICABLE PUBLICATIONS 17.2.1 17.2.2 17.2.3 17.2.4 17.2.5 17.2.6 17.2.7 17.2.8 National Fire Protection Association (NFPA): National Association of Corrosion Engineers: Unified Facilities Criteria (UFC): Military Handbooks: Technical Manuals: Miscellaneous References: Other Publications and Code Compliance: Guide Specifications:
17.3
17.4
CONCEPT DESIGN (30%-35%) 17.4.1 17.4.2 17.4.3 17.4.4 17.4.5 Design Analysis Narrative Concept Design Drawings (30%-35%) Concept Removal or Demolition Specifications Concept Additional Criteria/Information
17.5
INTERIM DESIGN (50%-60%) 17.5.1 17.5.2 17.5.3 17.5.4 Interim Design Analysis Interim Design Drawings (50%-60%) Specifications Additional Criteria
17.6
FINAL DESIGN (UNREVIEWED 100%) 17.6.1 17.6.2 17.6.3 Final Design Analysis Final Design Drawings Final Design Specifications
17.7 17.8
READY-TO-ADVERTISE (100%). RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS. 17.8.1 17.8.2 Mandatory Requirements Specific Requirements.
17.9
TECHNICAL REQUIREMENTS 17.9.1 17.9.2 17.9.3 17.9.4 Salvageable Material Special Items Corrosion Control and Cathodic Protection Other Electronic Systems
17-1
17.1
GENERAL Scope
17.1.1
This chapter gives general guidelines for the preparation of drawings, specifications, and design analysis as related to corrosion control and cathodic protection systems. A cathodic protection (CP) system shall be provided where applicable; project design and construction without considering CP are not acceptable. CP is a functional requirement for virtually all projects involving new aboveground water tanks, direct buried or submerged metallic structures (including metallic components of non-metallic pipelines), or the repair or replacement of similar existing structures. New buildings requiring fire sprinkler systems are one example of projects requiring CP. Although new fire lines supplying new buildings may be constructed of non-metallic materials such as PVC, fire lines will contain some or all of the following buried metallic components: PIVs, fire hydrants, pressurized metallic piping under floor slabs, change of direction devices, valves, and other buried metallic components. Buried metallic components of fire lines require cathodic protection under this chapter. Specific submittal requirements in this chapter supplement the requirements of Chapter 1, GENERAL INSTRUCTIONS. All required documents, including drawings and design analysis, shall be in accordance with Chapter 2, PRESENTATION OF DATA. For additional information and guidance relating to Corrosion Control and Cathodic Protection Systems, see the Corrosion Control and Cathodic Protection Systems DX website at http://www.sam.usace.army.mil/en/cp.
17.1.2
Design Submittals
The following submittal guidelines have been developed for the most common projects such as cathodic protection design for the protection of new buried metallic piping to building or buildings and utility facilities that might be constructed in support of those new buildings such as water tanks, fuel tanks, sewage lift stations, etc. Projects, which require extensive, unusual, or complicated cathodic protection work, will have special submittal requirements developed for that project. The requirements shall be defined, developed and agreed upon at the pre-design conference and will become part of the contract. Design submittals will be reviewed for general compliance with criteria. Some detailed checks will be made. The designer should accomplish complete and independent checking of the design. The designer is fully responsible for the design. The design should be complete and accurate. It should be thoroughly checked for errors, conflicts (both within and between disciplines), and proprietary requirements. No proprietary restrictions may be included in the
17-2
17.2
APPLICABLE PUBLICATIONS
The publications listed below, but referred to thereafter by basic designation only, form a part of this Manual. These publications are supplemented by the UFGS Guide Specifications to form design criteria. 17.2.1 National Fire Protection Association (NFPA): National Electrical Code (Latest Issue)
NFPA 70
17.2.2
National Association of Corrosion Engineers (Latest Issue) Control of External Corrosion on Underground or Submerged Metallic Piping Systems (Latest Issue) Mitigation of Alternating Current and Lightning Effects on Metallic Piping Systems (Latest Issue) Design Considerations for Corrosion Control of Reinforcing Steel in Concrete (Latest Issue) Discontinuity (Holiday) Testing of Protective Coatings (Latest Issue) External Protective Coatings for Joints, Fittings, and Valves on Metallic Underground or Submerged Pipelines and Piping Systems (Latest Issue) External Cathodic Protection of On-Grade Metallic Storage Tank Bottoms (Latest Issue) High-Voltage Electrical Inspection of Pipeline Coatings (Latest Issue) Corrosion Control of Underground Storage Tank Systems by Cathodic Protection (Latest Issue) The Electrical Isolation of Cathodically Protected Pipelines (Latest Issue) Impressed Current Cathodic Protection of Internal Submerged Surfaces of Carbon Steel Water Storage Tanks (Latest Issue) Design, Installation, Operation, and Maintenance of Impressed Current Deep Groundbeds
NACE RP0193 NACE RP0274 NACE RP0285 NACE RP0286 NACE RP0388
NACE RP0572
17.2.3
UFC 3-570-06
17-3
17.2.4
Military Handbooks: Military Handbook for Facility Planning and Guide Electrical Engineering Cathodic Protection
17.2.5
TM 5-811-7
17.2.6
Miscellaneous References: Design Criteria Technical Requirements for Design-Build Corrosion Control Design Analyses, Chapter 1 Safety Manual Engineering and Design Cathodic Protection Technical Standards and Corrective Action Requirements for Owners and Operators of Underground Fuel Storage Tanks (UST) Transportation of Natural and other Gas by Pipeline: Minimum Federal Safety Standards Transportation of Hazardous Liquids by Pipeline
TI 800-01 TI 800-03 AFI 32-1054 ER 1110-345-700 AMCR 385-100 ETL 1110-3-474 CFR 40 Part 280
17.2.7
In addition to the codes and standards listed above, all electrical work associated with cathodic protection work shall comply with the applicable requirements of the latest edition of the standards of the National Electrical Manufacturer's Association (NEMA); and all applicable federal, state, city, and local codes, regulations, ordinances, publications and manuals. The Underwriters Laboratory (UL) or a similar testing laboratory acceptable to COE shall list all new manufactured equipment. When codes conflict, the more stringent standard shall govern.
17.2.8
Guide Specifications
17-4
Specifications are updated on a regular basis. Instructions on retrieving UFGS Specifications are covered in Chapter 3, SPECIFICATIONS. For cathodic protection design, the following guide specifications shall be utilized, as applicable: UFGS 13110A UFGS 13111A UFGS 13112A Cathodic Protection System (Sacrificial Anode) Cathodic Protection System (Steel Water Tanks) Cathodic Protection System (Impressed Current)
17.3
The Pre-concept Design Analysis shall include the requirements stated below and shall include all data and calculations to support design decisions and estimates at this stage of design. The analysis shall incorporate specific criteria furnished and conference minutes of all systems considered. The analysis shall include the following:
17.3.1
(1) Provide the name of the licensed Corrosion Engineer, certified NACE Cathodic Protection Specialist, or certified NACE Corrosion Specialist. (2) New or supplemental CP shall be compatible to the existing CP systems (if operational) and other adjacent structures or components. It is the responsibility of the Corrosion Expert, as defined in this chapter, to verify, during the pre-design cathodic protection survey, the operability of existing cathodic protection systems located adjacent to or in the vicinity of the new metallic structures requiring cathodic protection. All variables that may compromise the operation of the new cathodic protection system, such as interference and grounding to existing structures, etc., must be considered in the design. The design shall require remedial actions that will mitigate all interference, grounding, and other undesirable effects to enable the new CP system to afford the required potentials. New systems will be compatible with installation wide systems to allow ease of repair and maintenance. New metallic pipelines or other metallic structures which are to be connected to existing metallic pipelines or other existing structures shall be electrically isolated by the installation of isolation flanges between the new and old metallic structures, regardless if the existing metallic structure is cathodically protected or not. That is, new cathodic protection systems must be independent and isolated from existing cathodic protection systems and designed such that the new CP system provides the specified protective potentials to the new metallic structure. Any variations from the installation of isolation flanges between new and old pipelines such as expansions of existing cathodic protection systems to accommodate new pipe extensions, must be submitted to and approved by the COE, Mobile District, Engineering Division CP Specialist. Expansions of existing CP systems to cathodically protect new pipelines or other metallic structures must be supported by CP field survey data, including potential surveys of existing pipelines under cathodic protection, existing isolation flange tests, existing coating integrity tests, etc. All these tests, as well as other tests that might be necessary in order to support the design, must be conducted by
17-5
the Corrosion Expert and results and procedures included in the Design Analysis. Where additions or alterations to existing CP systems are to be recommended, verification and substantiation that the systems are operational, expandable, and can accommodate the additions or alterations are mandatory. Provide a description of all proposed additions and alterations to each system. Information on manufacturer, model number, etc., of the existing cathodic protection equipment shall be included in the plans and specifications. (3) Provide a descriptive narrative of all cathodic protection systems and other corrosion control measures that are required for project. The narrative shall describe the extent of the corrosion control and cathodic protection work both inside and outside of the 5 foot from the building perimeter line. Provide brief description of the standards of design. Any project that includes buried or submerged metallic surfaces must be evaluated for corrosion control requirements in accordance with this chapter and with the guidance of all other referenced documents included in this chapter. (4) Provide the following for cathodic protection systems: (a) (b) Clearly define areas of structures or components in soil or water to be protected. Type system recommended (i.e., sacrificial or impressed current), comparison of systems, and cost estimate showing all equipment alternatives.
(5) Define any hazardous areas (as defined in the National Electrical Code) and indicate the type of any cathodic protection equipment proposed for use in such areas. (6) List the specifications that will be used.
17.4
The Concept Design Analysis shall include the requirements stated below and shall include all data and calculations to support design decisions and estimates at this stage of design. The analysis shall incorporate specific criteria furnished and conference minutes of all systems considered. The analysis shall include the following:
17.4.1
(1) Provide the name of the licensed Corrosion Engineer, certified NACE Cathodic Protection Specialist, or certified NACE Corrosion Specialist. (2) New or supplemental CP shall be compatible to the existing CP systems (if operational) and other adjacent structures or components. It is the responsibility of the Corrosion Expert, as defined in this chapter, to verify, during the pre-design cathodic protection survey, the operability of existing cathodic protection systems located adjacent to or in the vicinity of the new metallic structures requiring cathodic protection. All variables that may compromise the operation of the new cathodic protection system, such as interference and grounding to existing structures, etc., must be considered in the design. The design
17-6
shall require remedial actions that will mitigate all interference, grounding, and other undesirable effects to enable the new CP system to afford the required potentials. New systems will be compatible with installation wide systems to allow ease of repair and maintenance. New metallic pipelines or other metallic structures which are to be connected to existing metallic pipelines or other existing structures shall be electrically isolated by the installation of isolation flanges between the new and old metallic structures, regardless if the existing metallic structure is cathodically protected or not. That is, new cathodic protection systems must be independent and isolated from existing cathodic protection systems and designed such that the new CP system provides the specified protective potentials to the new metallic structure. Any variations from the installation of isolation flanges between new and old pipelines such as expansions of existing cathodic protection systems to accommodate new pipe extensions, must be submitted to and approved by the COE, Mobile District, Engineering Division CP Specialist. Expansions of existing CP systems to cathodically protect new pipelines or other metallic structures must be supported by CP field survey data, including potential surveys of existing pipelines under cathodic protection, existing isolation flange tests, existing coating integrity tests, etc. All these tests, as well as other tests that might be necessary in order to support the design, must be conducted by the Corrosion Expert and results and procedures included in the Design Analysis. Where additions or alterations to existing CP systems are to be recommended, verification and substantiation that the systems are operational, expandable, and can accommodate the additions or alterations are mandatory. Provide a description of all proposed additions and alterations to each system. Information on manufacturer, model number, etc., of the existing cathodic protection equipment shall be included in the plans and specifications. (3) Provide a descriptive narrative of all cathodic protection systems and other corrosion control measures that are required for project. The narrative shall describe the extent of the corrosion control and cathodic protection work both inside and outside of the 5 foot from the building perimeter line. Provide brief description of the standards of design. Any project that includes buried or submerged metallic surfaces must be evaluated for corrosion control requirements in accordance with this chapter and with the guidance of all other referenced documents included in this chapter. (4) Provide the following for cathodic protection systems: (a) (b) Clearly define areas of structures or components in soil or water to be protected. Type system recommended (i.e., sacrificial or impressed current), comparison of systems, and cost estimate showing all equipment alternatives. Calculations on all systems that are considered, showing all information and descriptions. Estimate showing materials and cost.
(c) (d)
(5) Define any hazardous areas (as defined in the National Electrical Code) and indicate the type of any cathodic protection equipment proposed for use in such areas. (6) List the specifications that will be used.
17-7
17.4.2
(1) Cathodic Protection work to be shown on Utilities Site plan or separate Cathodic Protection Systems site plan. (a) Identify any gas lines, water lines, fire protection lines, fuel lines, force main lines, and all other structures that are to be protected by the Cathodic Protection System as required by this chapter, as well as applicable laws and regulations. Show removals and relocations, if any.
(b)
17.4.3
17.4.4
Specifications
17.4.5
Any additional criteria, deviations concerning criteria, questions or problems will be listed.
17.5
17.5.1
This stage of Design Analysis shall be an entirely updated analysis (not amendments to concept submittal) to permit verification that the design complies with the criteria furnished and the approved Concept Design.
17.5.2
17.5.2.1
(1) All removals must be shown. If removals are extensive, separate demolition plans are required. The designer shall display the information in such a manner that it would not be necessary to visit the site to prepare a bid. (2) A complete legend shall be provided for all devices and equipment shown on the plans. Mounting heights shall be included as applicable.
17-8
17.5.2.2 (1)
(2) Thoroughly check for discrepancies and conflicts, particularly between disciplines. (3) Cathodic protection system should be complete, including analysis, narrative description of system, and drawings. The submittal shall include drawings showing all structures or components to be protected and all cathodic protection components in relation to the protected structure. This includes showing sacrificial and impressed current anodes, rectifiers, isolation (dielectric), bonding, and any other data needed to define the scope and area of the cathodic protection system. (4) Show location of all devices and equipment for cathodic protection system on the floor plans if any components, such as rectifiers, are to be mounted inside of the building. Show location of devices to be interconnected. Include all CP rectifier circuits in electrical panel schedules.
17.5.3
Specifications
The outline specifications previously submitted for concept phase shall be revised, updated, further developed and resubmitted in accordance with Chapter 3, SPECIFICATIONS. 17.5.4 Additional Criteria
Any additional criteria, deviations concerning criteria, questions or problems should be listed.
17.6
17.6.1
This analysis is an extension of the approved 50%-60% design analysis and supports and verifies that the design complies with the requirements of the project.
17.6.2
The final drawings are an extension of the approved 50%-60% drawings and shall incorporate the 50%-60% comments. (1) All details for final package shall be on the drawings.
(2) Thoroughly check the drawings for discrepancies, for compatibility between drawings and specifications, and for compatibility between disciplines. Check the following, as a minimum, but DO NOT LIMIT CHECKING TO THESE ITEMS: (a) Verify compatibility between civil/site utilities, environmental, mechanical, electrical, CP systems, and
17-9
other disciplines (equipment locations, NEMA enclosures, plans and specifications for systems furnished in other specification sections, etc.), to ascertain that there are no conflicts on the drawings relating to the installation of all new CP systems. (b) (c) (d) (e) drawings. (f) criteria. (g) (h) conductors and (i) Adequacy of details and diagrams. Proper and practical circuitry with number of conduit sizes indicated correctly. Ensure that all hazardous areas are clearly defined where rectifiers and other electrical equipment are to be located. Ensure that all cathodic protection rectifiers are provided with power. Assure design complies with design analysis and Panelboard locations and home runs to rectifiers. Terminal cabinet and test station locations. Rectifier locations. Legend and/or symbols complete and compatible with
(j)
17.6.3
Marked-up specifications shall be submitted in accordance with Chapter 3, SPECIFICATIONS. Specifications used shall be those acquired subsequent to the Interim submittal. (1) Read thoroughly and comply with the instructions in front of each set of guide specifications and with all other notes to the specification writer. The SPECINTACT specification writing system shall be used for specification preparation. (2) Cross out non-applicable index items, publications, paragraphs, phrases, words, and sentences. Fill in blanks as applicable. (3) Add publication references, paragraphs, phrases, words, and sentences for items not adequately covered by specifications. (4) Do not specify proprietary items.
(5) Ascertain that major or special types of equipment are available commercially.
17.7
READY-TO-ADVERTISE (100%).
The comments generated during the Final Review shall be incorporated into the completed design analysis (not amended sheets),
17-10
specifications, and drawings before they are submitted as Ready-toAdvertise. The analysis shall be complete and shall support the requirements of the project. The drawings and specifications shall be complete and thoroughly checked. Where additions to existing cathodic protection systems are made, the designer must follow the guidance included in previous submittals described in this chapter.
17.8
TI 800-03 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs.
17.8.1
Mandatory Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development: a. Engineering and design of Cathodic Protection and coatings are required as indicated in accordance with Army Engineer Technical Letter (ETL) No. 1110-3-474. Include requirements in the RFP. Requirements should not be included by reference to the ETL. b. Cathodic Protection and protective coatings shall be provided for the following buried or submerged ferrous metallic structures regardless of soil or water resistivity: (1) (2) (3) (4) (5) (6) (7) (8) (9) Natural gas and propane piping Liquid fuel piping Underground storage tanks Fire protection piping Steel, Ductile, or cast iron pressurized piping under floor (slab on grade) in soil Underground heat distribution and chilled water piping in ferrous metallic conduit in soils with resistivity of 30,000 ohm-cm or less Other structures with hazardous products Steel casing for underground hydraulic elevator jack Oxygen piping
Metallic components of non-metallic piping systems and other nonmetallic systems listed in this paragraph shall also be coated and cathodically protected. Some, but not to be limited to, examples of such components are: fire hydrants, post indicator valves (PIVs), change of direction devices, etc. c. Require the D-B contractor to have all pre-design surveys, cathodic protection designs, and acceptance surveys performed by a person that is accredited or certified by NACE International [formerly National Association of Corrosion Engineers (NACE)] as a NACE Accredited
17-11
Corrosion Specialist or a NACE certified CP Specialist or be a registered professional engineer who has certification or licensing that includes education and experience in corrosion control of buried or submerged metallic piping and tank systems. d. Require in the RFP, the Design-Build contractor provide training for each cathodic protection system. e. Codes and Standards. In addition to ETL 1110-3-474, referenced above, the RFP must require the Design-Build contractor to comply with all other relative corrosion control and cathodic protection system requirements as contained in all of the criteria documents referenced in this Chapter, as well as Codes and Standards, which may not be included in this Chapter, but are relative to the locality. f. Require in the RFP, that all new metallic components that are connected to existing metallic piping systems or other existing metallic structures shall be electrically isolated from those existing structures by the installation of an isolation flange, dielectric union, or isolation valve. This requirement is mandatory regardless if the existing piping system or other structure that is being connected to currently has a cathodic protection system in place, even if the existing system is operational. g. Special Cathodic Protection Requirements (conflicts with grounding systems; structure interference considerations; structure isolation considerations; coating requirements; special installation problems, such as location of ground beds in conjunction with rock formations; etc.). h. Require in the RFP, that only the latest Army edition of the UFGS cathodic protection system specifications be utilized in the contractors cathodic protection design. That is, cathodic protection system specifications with an A suffix. These specifications must be utilized even if other portions of the RFP design documents allow the use of specifications other than UFGS specifications. i. See TI 800-03 for additional mandatory requirements.
17.8.2
Specific Requirements.
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria:
1. Include a paragraph describing the cathodic protection systems and structures that they are to protect, any major features such as rectifiers, test stations, anode types and locations (i.e., type of anodes; type of system, distributed or remote ground bed), terminal cabinets, cabling, etc., and any special corrosion related requirements such as conflicts with grounding systems; structure interference considerations; structure isolation considerations; coating requirements; special installation problems, such as location of ground beds in conjunction with rock formations; etc. Include a paragraph on
17-12
required Corrosion Expert qualifications. required criteria of protection. b. Partial Project Criteria:
Include a paragraph on
1. Include a paragraph describing the cathodic protection systems and structures that they are to protect, any major features such as rectifiers, test stations, anode types and locations (i.e., type of anodes; type of system, distributed or remote ground bed), terminal cabinets, cabling, etc., and any special corrosion related requirements such as conflicts with grounding systems; structure interference considerations; structure isolation considerations; coating requirements; special installation problems, such as location of ground beds in conjunction with rock formations; etc. Include a paragraph on required Corrosion Expert qualifications. Include a paragraph on required criteria of protection. 2. Describe the cathodic protection equipment and materials to be used on all cathodic protection systems. Describe the type of cathodic protection system that is to be utilized, i.e., impressed current or galvanic type. 3. Describe all the structures that are to be cathodically protected. Include the type of construction materials that are to be utilized for the structures, a description of the coating systems that are to be employed on those structures, etc. 4. Describe any other cathodic protection systems in the area of the new systems, which may conflict with the new systems. 5. If known, provide data and information relating to the corrosivity of the electrolytes (i.e., water or soil) in which the anodes and the structures to be protected are to be installed. The data should include such information as resistivity, pH, chloride content, etc. 6. c. Include an outline of the specifications to be edited.
1. Final Corrosion Control and Cathodic Protection Systems Plans (See description above under 17.6.2, Final Design Drawings.) 2. Final Specifications (See description above under 17.6.3, Final Design Specifications.) 3. Design Narrative and other requirements not specifically included in above paragraph under this section [See description above under 17.6 FINAL DESIGN (Unreviewed 100%).] NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements.
17.9
17.9.1
17-13
The salvageable material resulting from a demolition design and not reincorporated in the design remains property of the U.S. Government. The debris will be disposed of as directed by the Contracting Officers representative. Typical removal paragraphs are listed below. 17.9.1.1 Removals.
Where indicated, existing equipment and material shall be removed and shall remain the property of the Government. Salvageable equipment and materials shall be delivered to the Contracting Officers representative for storage on the premises as directed. Materials and debris considered unsalvageable by the Contracting Officers representative shall be disposed of as directed. 17.9.1.2 Reuse of Removed Materials
Removed materials shall be reused if they are in good condition and they meet the requirements of this section of the specifications. (Removed materials not incorporated in the new work shall be delivered to storage and disposed of as directed by the Contracting Officers representative.)
17.9.2
Special Items
The following items will be included in each submittal, where applicable: (1) Unified Facility Guide Specifications [UFGS, Corps of Engineers version only, currently with A suffix] must be used in preparing all contract specifications for cathodic protection work.
17.9.3
For all metal facilities located in the atmosphere, soil, or water electrolytes, corrosion control shall be provided. In all instances, cathodic protection, or approval to omit it, shall be provided for metals in soils or water. Coatings are normally provided as corrosion protection in the atmosphere. A cathodic protection system shall be provided where applicable; project design and construction without considering cathodic protection are not acceptable. As a minimum, cathodic protection and protective coatings shall both be provided for the following buried or submerged ferrous metallic structures, regardless of soil or water resistivity: Natural gas and propane piping, including metallic components of non-metallic lines Liquid fuel piping Oxygen piping Bottom of on-grade fuel and water storage tanks Interior of water tanks and elevated tank risers Underground metal storage tanks, piping, and ancillary items
17-14
Metallic components of force mains Metallic components of backflow preventors Fire protection lines or water lines utilized for fire protection, including metallic components of non-metallic lines (i.e., PIVs, fire hydrants, change or direction devices, valves, metallic sections under building slab and elsewhere, etc.) Steel, ductile iron, and cast iron pressurized piping under floor (slab on grade) in soil Underground heat distribution and chilled water piping in ferrous metallic conduit Oil/Water separators and all associated metallic fittings in contact with soil Sewage lift stations (all metallic components in contact with soil or liquids) Other structures with hazardous products as identified by the user of the facility These are some of the systems and components requiring cathodic protection by technical instructions and other military criteria, regulations, and/or law but are not all-inclusive. The results of an economic analysis and recommendations by a corrosion expert shall govern the application of CP and protective coatings on gravity sewer lines, regardless of soil resistivity, and for potable water lines in resistivities above 10000 ohm-centimeters (unless the CP is a requirement on the potable water line due to other reasons, such as pressurized steel piping under floor slab, as listed above). The Corrosion Expert shall identify special areas of concern that could create a need for corrosion mitigation. For example, the installation of grounding systems could create special corrosion problems such as the introduction of dissimilar metal corrosion cells (i.e., copper ground rods interconnected to other metal piping, etc.). Resolution of these type of special problems must be incorporated into the cathodic protection design or some other part of the total corrosion mitigation plan. 17.9.3.1 Coating Requirements
(1) In addition to cathodic protection requirements, a minimum coating thickness of 40 mils is required on all underground metal. (2) The only coating types that are allowed to be utilized on metallic components, structures, and pipelines that are cathodically protected are listed in the applicable cathodic protection specification section. These coating types shall have precedence over all other specification sections that may specify or allow other coating types for metallic components and structures that are to be cathodically protected. (3) Unbonded coatings, such as polyethylene encasement, shall not be allowed on pipelines or components requiring cathodic protection as
17-15
defined in this chapter and in referenced documents and criteria. Additionally, the use of unbonded coatings such as loose polyethylene wraps are prohibited for all buried metallic components and pipelines installed for Air Force projects, regardless if cathodic protection is also applied or not. 17.9.3.2 Qualifications for Cathodic Protection Work
Cathodic protection field work (pre-design surveys), analysis, and design must be accomplished by or under direct supervision of a corrosion expert. Corrosion expert refers to a person, who by thorough knowledge of the physical sciences and the principles of engineering and mathematics, acquired by professional education and related experience, is qualified to engage in the practice of corrosion control of buried or submerged metallic surfaces. Such a person must be accredited or certified by NACE International [formerly the National Association of Corrosion Engineers (NACE)] as a NACE Accredited Corrosion Specialist or a NACE certified Cathodic Protection (CP) Specialist or be a registered professional engineer who has certification or licensing that includes education and experience in corrosion control of buried or submerged metallic piping and tank systems, if such certification or licensing includes 5 years experience in corrosion control on underground metallic surfaces of the type under this contract. The corrosion experts name and qualifications shall be certified prior to start of design. He must be available to answer questions relating to his work. 17.9.3.3 Description of Analysis Work
(1) The Corrosion Expert is responsible for assuring that all necessary field data such as resistivity measurements, etc., is obtained for the cathodic protection design. He must assure that resistivity measurements are taken along the pipeline and/or other buried metallic structure that will be cathodically protected and also in areas of proposed anode ground beds. The geotechnical engineer may conduct measurements in the necessary locations or areas as designated by the Corrosion Expert in order to provide the designer the data necessary to determine Interim size and type cathodic protection for structures protection. The resistivity, soil borings, and other soils data should be provided in the Foundation Report. The designer is required to obtain the necessary resistivity and other design data if the geotechnical engineer does not obtain this information in the appropriate locations. (2) The preliminary design submittal shall include economic justification for selection of type of cathodic protection system (sacrificial or impressed current), soil corrosiveness (resistivity, pH, etc.) data, current requirement test (if applicable), potential survey data (if applicable to existing structures), and all design calculations for cathodic protection in the basis of design. (3) The design shall provide sufficiently detailed calculations and one line diagrams at the early preliminary design stage to show the magnitude and layout of the cathodic protection system. The designer must clearly define areas that will be protected and the areas that could be affected by interference, and steps to be taken to ensure other structures (pipes, tanks, etc.) are protected from interference. (4) Provide sufficient and properly located electrical bonds, electrical insulating devices, and corrosion control test stations to
17-16
ensure adequate allowance for periodic inspection, review, testing, and examination of the system. 17.9.3.4 Design of Cathodic Protection
(1) Regardless if other sections of the contract documents allow the use of specifications other than the UFGS (Unified Facilities Guide Specifications) for other portions of the design of this facility; ONLY the latest Corps of Engineers edition of UFGS specifications will be allowed and shall be utilized in the cathodic protection design for the specification of cathodic protection systems. These specifications are listed in this chapter under guide specifications and are available through the Techinfo homepage of Huntsville Division, Corps of Engineers (which currently points to the following web address in order to obtain the applicable specification sections: http://www.ccb.org/docs/ufgshome/UFGSToc.htm), or can be obtained from the Mobile District, Corps of Engineers. With regards to Cathodic Protection, this requirement applies also to Design-Build and RFP type contracts, which sometimes may allow the use of specifications other than UFGS specifications for other disciplines. (2) The cathodic protection systems provided on the metallic structures listed in this chapter shall be either impressed current or galvanic type systems as determined by the following requirements: 1) the pertinent design data as gathered by the "corrosion expert" (as defined in this chapter), including but not limited to soil resistivity, material selection, coating selection, current requirements, anode selection, ability to isolate from foreign structures, etc. as necessary to meet the defined minimum potential criteria; and 2) as required by the applicable guide specification(s). For nonmetallic pipelines with metallic components and metallic components of other described structures requiring cathodic protection, the cathodic protection designer shall, as a minimum, submit specification section UFGS 13110A and comply with all the requirements of that section (unless gathered data requires the use of an impressed current system). For pipelines or structures constructed of all metallic materials in their entirety or for those that require more voltage and current than can be supplied from galvanic systems, the cathodic protection designer shall, as a minimum, submit specification section UFGS 13112A and comply with all requirements of that section. For example, section 13112A must be submitted for cathodic protection of on-grade storage tank bottoms in contact with an electrolyte. For water storage tanks interiors, the cathodic protection designer must submit specification section UFGS 13111A and comply with all requirements of that section. (3) The design of the cathodic protection system shall be completed prior to construction contract advertisement except for Design-Construct and pre-approved underground heat distribution systems. That is, submission of an all performance type design rather than a complete design, ready for construction, is not acceptable. (4) In addition to the soil and water resistivity surveys, current requirement tests and design, the designer shall provide recommended tests, formats, required methodology, etc., for the final acceptance of the cathodic protection system based upon the USACE cathodic protection acceptance criteria. (5) This design shall clearly provide thorough and comprehensive specifications and drawings. The design must meet the requirements of Army ETL 1110-3-474 and shall incorporate guidance from all referenced
17-17
documents and other applicable criteria, such as NACE RP0169, NACE RP0177, NACE RP0187, NACE RP0188, NACE RP0190, NACE RP0193, NACE RP0285, NACE RP0286, NACE RP0388, NACE RP0572, applicable Code of Federal Regulations (CFR), etc. The expected results shall be provided by field test (in the construction phase) witnessed by the Contracting Officers representative. (6) The design must include applicable drawings, as available, showing existing construction. Verification of the validity of these drawings and/or any other data furnished by the Government shall be the responsibility of the engineering services firm. (7) The designer shall provide an updated cost estimate of the cathodic protection system. This will include all construction and testing costs related to installation of cathodic protection. The estimate shall be a detailed estimate showing equipment, labor, excavation, etc. (8) The design shall identify all locations for interference testing (all pipe that passes within 1000 feet of an impressed current anode bed and then crosses the cathodically protected line). (9) The design plans and specifications will show extent of the facilities to be protected; location and type of anodes; location of test points; locations of rectifiers, test stations, junction boxes, wiring, etc.; installation details; insulators; bond connections; and details for sectionalizing an underground piping system. Coordinate with mechanical, site, environmental, and other disciplines. This design shall be complete enough to purchase equipment and build, without design changes, to meet criteria of protection. (10) For non-metallic pipelines with buried metallic components, each buried or submerged metallic component shall have design calculations, a drawing detail of that component showing cathodic protection with at least one test station. Each component shall have a minimum of one test station, two anodes, and one permanent reference electrode. Each location shall be shown on drawings. Header cables shall not be used for connection of anodes. Each anode shall be connected to a test station via an individual lead conductor and bonded to the structure being protected inside the test station. The test station shall be connected to the structure being protected via two conductors. (11) Each new metallic pipeline connecting to an existing metallic pipeline shall be electrically isolated from the existing pipeline by the installation of an insulating flange. New metallic pipeline passing through concrete slabs, walls, and floors shall have an insulating material (such as a PVC sleeve) between the pipe and concrete in order to provide isolation. Insulating flanges shall also be installed in new metallic pipelines extending above grade or where they extend above floor slabs; the flanges are to be located above grade. (12) The cathodic protection designer shall coordinate his design with any existing cathodic protection systems in the area of the new facility. As necessary, the contractor shall relocate any existing cathodic protection system test stations or other cathodic protection equipment located in areas conflicting with construction of the new
17-18
facility. Any existing cathodic protection system equipment that has to be moved shall be relocated to areas approved by the Contracting Officers representative. (13) All potential tests shall be made at 2.5 ft. intervals witnessed by the Contracting Officer's Representative. Design shall require that submittals identify test locations on a separate drawing showing all metal to be protected and all cathodic protection equipment. However, a minimum of 3 tests shall be made at each metallic component in the piping system. Test points, equipment, and protected metal shall be easily distinguished and identified on the drawings. 17.9.3.5 Criteria of Protection
Criteria for determining the adequacy of protection on a buried structure are defined in NACE International Publication NACE RP0169, NACE RP0193, or NACE RP0285, as applicable. Criteria for determining the adequacy of protection on internal submerged surfaces of carbon steel water storage tanks are defined in NACE RP0388. For buried metallic components, the cathodic protection system shall meet the minimum criteria for steel, ductile iron, and cast-iron structures defined in the first subparagraph below (criteria indicated in the second subparagraph may be utilized as an alternative procedure if the first criteria procedure fails and if submitted to and approved by the Contracting Officers representative prior to testing): (1) A negative voltage of at least minus 850 millivolts as measured between the structure or specified underground metallic component and a saturated copper-copper sulfate reference electrode contacting the earth (electrolyte) directly over the structure. Determination of this voltage shall be made with the cathodic protection system in operation and after it has been in operation for a minimum of 72 hours. Voltage drops shall be considered for valid interpretation of this voltage measurement. A minimum of minus 850 millivolts instant off potential between the structure being tested and the reference cell shall be achieved over 95 percent of the area of the structure. A close interval survey shall be conducted on all cathodically protected pipelines and components. The design shall be accomplished so that the protective current can be interrupted in order to obtain the instant off potential readings. Adequate number of measurements shall be obtained over the entire structure, pipe, or other metallic component to verify and record achievement of minus 850 millivolts instant off. This potential shall be obtained over 95 percent of the total metallic area without the instant off potential exceeding 1100 millivolts. (2) A minimum polarization voltage shift of 100 millivolts as measured between the structure and a saturated copper-copper sulfate reference electrode contacting the earth directly over the structure. This polarization voltage shift shall be determined by interrupting the protective current and measuring the polarization decay. When the protective current is interrupted, an immediate voltage shift shall occur. The voltage reading, after the immediate shift (this reading shall be defined herein as being the same reading as the instant off reading described in the immediate paragraph above and this term will be utilized below), shall be used as the base reading from which to measure polarization decay. Measurements achieving 100 millivolts decay shall be made over 95 percent of the metallic surface. Alternatively, the instant off measurements can be compared to the native readings taken prior to energizing of the cathodic protection system and in the exact
17-19
same locations. For comparison of instant off to native readings, the same number of measurements in corresponding locations must be taken. If the instant off reading is compared to the corresponding native reading in the same location, it must be a minimum of 100 mV more negative with respect to the copper/copper-sulfate reference cell than the native reading. The Corrosion Expert must assure that a complete set of native readings are taken prior to energizing the cathodic protection system at all of the same locations as the on and instant off measurements are taken (i.e., close interval survey), as is required by the referenced guide specifications. The instant off measurements shall be made after the system has been in operation for a minimum of 72 hours.
17.9.4
17.9.4.1
Leak detection must be provided for underground storage tanks and piping which will contain petroleum products or the hazardous materials as required by local, state, or federal regulation. The leak detection requirements are discussed in chapter entitled, ELECTRICAL AND ELECTRONIC SYSTEMS, of this manual. 17.9.4.2 Grounding Systems
Grounding systems can cause special corrosion problems that must be properly resolved in the corrosion control and cathodic protection design. Extreme care must be exercised in order to avoid the interconnection of dissimilar metallic materials and in order to avoid interference problems and/or the compromising of the cathodic protection system. Refer to chapter in this manual entitled, ELECTRICAL AND ELECTRONIC SYSTEMS, for guidance on electrical grounding systems.
17-20
GENERAL APPLICABLE PUBLICATIONS GENERAL INSTRUCTIONS DELIVERABLES ESTIMATOR QUALIFICATIONS METHODS OF ESTIMATING 18.6.1 General 18.6.2 TRACES (AF TRACES Parametric Bldg. Models) 18.6.3 MCACES GOLD 18.6.4 MCACES 2nd Generation (MII) 18.6.5 18.6.6 Manual Excel Spreadsheet REQUIREMENTS General Cost Control Format Cost Breakdown Resubmittal and/or Support Bid Exceeds Estimate REQUIREMENTS General Quantity Survey Material Pricing Labor Construction Equipment Subcontract Work Mobilization and Demobilization Costs Indirect Costs Profit Bond Contract Modification Estimates Current Working Estimate (CWE) Quality Assurance Supplemental Information Clarification DD Form 1391
18.7
SUBMITTAL 18.7.1 18.7.2 18.7.3 18.7.4 18.7.5 18.7.6 TECHNICAL 18.8.1 18.8.2 18.8.3 18.8.4 18.8.5 18.8.6 18.8.7 18.8.8 18.8.9 18.8.10 18.8.11 18.8.12 18.8.13 18.8.14 18.8.15 18.8.16 SCOPE
18.8
18.9 18.10
SPECIFIC INSTRUCTIONS (MCACES GOLD) 18.10.1 MCACES GOLD User Manual 18.10.2 MCACES GOLD Software
18-1
18.10.3 18.10.4 18.10.5 18.10.6 18.10.7 18.10.8 18.11 TECHNICAL 18.11.1 18.11.2 18.11.3 18.11.4 18.11.5 18.11.6 18.11.7 18.11.8 18.11.9 18.11.10 18.11.11 18.11.12
Labor Rates Database Sample Projects Templates Work Breakdown Structure Training Unit Price Book Database INSTRUCTIONS FOR MCACES GOLD COST ESTIMATES Estimate Format MCACES GOLD Software and Databases Military Estimate Hierarchy MCACES GOLD Common Errors Quantity Take-Off Design Stage Identification Wage Rates Subcontractors Prime Contractor Field Overhead Profit Major MCACES GOLD Menu Screens Required Services
STARTING THE MCACES GOLD PROJECT PRINT SELECTED REPORTS SAVE TO COMPRESSED
EXHIBITS 18-1 18-2 18-3 18-4 18-5 18-6 18-7 18-8 Field Indirect Costs Weighted Guideline Method for Derivation of Profit Factor Technical Quality Control Checklist Major Menu Screens Merging Multiple Projects Databases Checklist Creating a New Project Checklist Print Submittal Reports Checklist Contingencies and Supervision & Administration
18-2
18.l
GENERAL
The purpose of this chapter is to provide specific guidance for the preparation of cost estimates for military construction projects. Estimates are made for programming, cost control during design, evaluation of bids, control of negotiations, and to serve as a guide in establishing a schedule of payments. Often these estimates are also used to evaluate the reasonableness of the contractor's proposal for negotiated procurement contracts. As such, they must be consistent with the best estimating practice of the construction industry and be current, accurate, and complete. They must reflect the expected cost to the Government to perform the work by contract and include all reasonable costs which a prudent, experienced, and well-equipped contractor might anticipate and include in his bid. 18.2 APPLICABLE PUBLICATIONS TI-800-03, Design Build Instructions Unified Facilities Criteria (UFC) UFC 3-700 series, Cost Engineering Air Force Parametric Cost Engineering System User Guidebook (PACES) Civil Works Work Breakdown Structure EI01D010, Engineering Instructions - Construction Cost Estimates EP 1110-1-8, Volume 3, Current Edition - Construction Equipment Ownership and Operating Expense Schedule - Region III ER 1110-1-1300, Engineering and Design Cost Engineering Policy and Requirements ER 1110-2-1302, Engineering and Design Civil Works Cost Engineering ER 1110-3-1300, Engineering and Design Military Programs Cost Engineering ER 1110-3-1301, Engineering and Design Environmental Restoration Cost Engineering Hazardous, Toxic, Radioactive Waste Work Breakdown Structure Historical Air Force Construction Cost Handbook MCACES GOLD User Manual, Volume I - Function and Capabilities & Volume II - Advanced Options Military Work Breakdown Structure National Unit Price Book, Region III, Current Edition
18-3
18.3
GENERAL INSTRUCTIONS
The Cost Engineer is responsible for obtaining the current version of all software and applicable user manuals. Micro-Computer Aided Cost Estimating System (MCACES) GOLD Version 5.31 software can be obtained through the U.S. Army Engineering and Support Center, Huntsville, AL at www.hnd.usace.army.mil/traces. Note: Support for MCACES GOLD Version 5.31 will be discontinued in the near future, as this software will be replaced by MCACES 2nd Generation (MII) software. MCACES 2nd Generation (MII) software is currently unavailable, but in the future can be obtained from the U.S. Army Engineering and Support Center, Huntsville, AL as permitted by the Mobile District Cost Engineering Branch. MCACES GOLD Databases and/or MCACES 2nd Generation (MII) Libraries can also be obtained through the Mobile District Cost Engineering Branch. Air Force Parametric Cost Estimating System (PACES) software can be obtained from Earth Tech, 9100 E. Panorama Drive, Suite 200, Englewood, CO, 80112 at 303-771-3103 or www.talpart.com/products/paces. The following supplemental cost estimating information required to complete the cost estimate is available on the Internet. The address for the Mobile District home page is http://www.sam.usace.army.mil/en/cost/encost.html The following items can be downloaded off the Internet: AF Form 1178 (Blank Form) Cost Estimate Submittal Checklist (Blank Form) Cost Growth Factors - Army Air Force Civil Works MCACES Databases: Assemblies Crews Construction Equipment Labor Rates Models Project Templates Unit Price Book Guide for Estimating Latin American Projects Panama, El Salvador and Honduras Guide for Estimating Payroll Taxes & Insurance and Sales Tax Costs (Stateside Projects Only) HAG Data Sheet Work Breakdown Structure: Civil HTRW Military
Projects will be designed in U.S. measurements or Metric measurements. When the project is a metric design, all units of measure and cost data referenced in this and other referenced documents for this project shall be changed to Metric Units of Measure and Metric Cost Data.
18-4
18.4
DELIVERABLES
The following items are to be included in estimate submittals which are to be reviewed by the Mobile District: Cost Estimate Submittal Checklist (Required for all submittals). The checklist shall be filled in and used as a cover sheet for each cost estimate submittal. The Checklist can be downloaded off the Internet (See Paragraph 18.3 above). Access to each cost estimate and its contents shall be limited to those persons whose duties require knowledge of the cost estimate. Estimate (Required for all submittals, number of copies specified in Appendix A, A-E Design Contracts). For manually-prepared, the complete detail and required summaries; for MCACES GOLD, all material printed out in accordance with the print settings in the Project Template, in reduced size (8-1/2x11), landscape, and suitably-bound. MCACES 2nd Generation guidance can be obtained from the Mobile District Cost Engineering Branch. All electronically prepared cost estimates can be e-mailed or ftped to the Mobile District Cost Engineering Branch. The RTA cost estimate that is submitted to the Government shall be accompanied by a letter of transmittal which includes the following statement: To the best of my knowledge the confidential nature of this estimate has been maintained. This statement should be signed, dated and maintained until the official markings have been removed. AF Form 1178 (Required for all submittals on Air Force Projects only), properly filled out in accordance with the instructions below. A blank AF Form 1178 can be downloaded off the Internet (See Paragraph 18.3 above). (1) completed. Blocks 1 through 59, excluding 14 and 46, are to be If a block is not applicable, so state as N/A.
(2) Blocks 48 and 50 (Area Cost factor and Size Adjustment Factor) should be listed as N/A if actual area costs are used. If unit costs for common DOD facilities are used, the appropriate factors listed in the latest Tri-service report should be used. (3) Compute Items 55 and 57 (Construction Contingency and SIOH) based on the appropriate percentage of Item 54f, Subtotal. (4) Reference Block 52:
(a) The desired midpoint of construction (month/year) is to be calculated from Block 19, Construction Start, and Block 20, Months of Construction. (b) The midpoint of available estimate (month/year) is the date the cost estimate is prepared. (c) Both raw inflation indexes are to be obtained from the latest AF Cost Growth Factors via the Cost Engineering Branch Internet address. (5) The SIOH in Block 57 is to 5.7%.
Supporting Data (Required for all submittals). A suitably-bound, ordered and legible presentation of all cost estimate backup. Backup consists of Quantity Survey, Quantity Derivations and Quotations. ALL
18-5
BACKUP MUST BE TRACEABLE TO THE LINE ITEM TASK IN THE COST ESTIMATE THAT THE BACKUP SUPPORTS. HAG Data Sheet (Required with RTA submittal only). The HAG Data Sheet can be downloaded off the Internet (See Paragraph 18.3 above). Annotated Comments, as appropriate. NOTE: THE VARIOUS CUSTOMERS SPECIFIED IN APPENDIX A, A-E DESIGN CONTRACTS WILL RECEIVE THE COST ESTIMATE PLUS AF FORM 1178, IF APPLICABLE ALL THE OTHER ITEMS LISTED PLUS 1 EACH COST ESTIMATE (BOUND) AND 1 EACH COST ESTIMATE (UNBOUND) WILL BE PROVIDED TO THE MOBILE DISTRICT COST ENGINEERING BRANCH ONLY. 18.5 ESTIMATOR QUALIFICATIONS
The designers cost estimating staff shall consist of dedicated full-time cost engineering specialist(s) for each required design discipline, such as architectural, structural, civil, mechanical, and electrical. It is imperative that estimates be prepared by, and reviewed under the supervision of, personnel who are competent in construction cost estimating. Estimators must possess a working knowledge of construction and be capable of making professional determinations based on experience. If the designer determines his staff does not possess all these qualifications, he shall obtain assistance from a qualified firm whose specialty is cost estimating. In making this determination, the designer shall consider the complexity of the project and the number and qualifications of his full-time estimators. In consideration and selection of a consultant firm for cost estimating, the designer shall consider, in addition to the foregoing, the firm's specialties, its ability to coordinate the estimates with the designer, and its previous experience in preparing cost estimates for the Government. Estimates prepared by a consultant must be reviewed by the designer before submittal to insure coordination and compliance with contract requirements. 18.6 METHODS OF ESTIMATING General
18.6.1
The method(s) used to prepare estimates for the various required submittals shall be as specified in the Statement of Work-Cost Estimating Criteria. Method specified may be the Micro-Computer Aided Cost Engineering System (MCACES GOLD Edition); Micro-Computer Aided Cost Engineering System (MCACES 2nd Generation (MII); Tri-Service Automated Cost Engineering System (AF TRACES Parametric Building Models - PACES); Manual Method or Excel Spreadsheet Method as described below, or a combination of the above software systems. REGARDLESS OF THE METHOD USED, THE DESIGNER SHALL MAKE ALL NECESSARY INVESTIGATIONS, EVALUATIONS, CALCULATIONS, AND ADJUSTMENTS TO INSURE THAT ESTIMATES FIT THE SPECIFIC PROJECT SCOPE AND CONDITIONS AND ARE CURRENT, ACCURATE AND COMPLETE. ABSOLUTELY, NO OTHER METHODS (COMPUTERIZED SOFTWARE, SPREADSHEET, TYPED, ETC.) WILL BE ALLOWED WITHOUT SPECIFIC APPROVAL IN ADVANCE PER PROJECT FROM THE MOBILE DISTRICT COST ENGINEERING BRANCH (251-690-2626). 18.6.2 TRACES (AF TRACES Parametric Building Models)
When the TRACES (AF TRACES Parametric Building Models) system is specified, the estimate shall be prepared as explained in the Statement
18-6
of Work-Cost Estimating Criteria and the TRACES User Manual and Site Work Model Report. Further detailed instructions and specific information will be provided separately as necessary by the Mobile District Cost Engineering Branch. 18.6.3 MCACES GOLD
Under the MCACES GOLD procedure, the estimate shall be prepared as explained in the Statement of Work-Cost Estimating Criteria and the MCACES Gold User Manual. Further detailed instructions and specific information will be provided separately as necessary by the Mobile District Cost Engineering Branch. 18.6.4 MCACES 2nd Generation (MII)
Under the MCACES 2nd Generation (MII) procedure, the estimate shall be prepared as explained in the Statement of Work-Cost Estimating Criteria. Further detailed instructions and specific information will be provided separately as necessary by the Mobile District Cost Engineering Branch. 18.6.5 Manual
When the manual procedure is directed or elected for a specific submittal, the estimate shall be prepared similarly to the sample final estimate which will be furnished if applicable. At the Ready-ToAdvertise submittal, the estimate forwarded to the Mobile District shall be the original, prepared in pencil, in order that any necessary revisions by the Government may be readily made. 18.6.6 Excel Spreadsheet
When the Excel Spreadsheet method is directed, the estimate shall be prepared on the Excel Spreadsheet blank forms and similarly to the sample Excel Spreadsheet final estimate which will be furnished if applicable. Further detailed instructions and specific information will also be provided separately as necessary by the Mobile District Cost Engineering Branch. 18.7 SUBMITTAL REQUIREMENTS General
18.7.1
The designer shall prepare (or have prepared by an estimating consultant) a professional quality construction cost estimate at each of the various stages of project design. Estimates must accurately reflect the scope and features of work shown on the design documents actually submitted. The degree of detail must be commensurate with that represented by the submitted plans, specifications, design analyses, etc. Where the design is not sufficiently complete to enable accurate definition of any portion of the work, appropriate allowances, based on good estimating experience and judgement, must be made to cover work not yet fully defined. 18.7.2 Cost Control construction are usually programmed based on the the project definition or concept design stage. Based amount, which frequently cannot be increased, a Limitation (CCL) is determined. The designer is
18-7
responsible for making every reasonable effort to design a project that can be built within the CCL, specified in the Statement of Work (SOW). Throughout the entire design period, close coordination between the designer and cost engineer must be exercised to achieve accurate cost control. 18.7.2.1 Cost Estimate Overruns
It is the designers responsibility to design the project so that the current construction costs including project escalation costs are within the construction cost limitation specified in the SOW. However, if for some reason beyond the designer's control the project should exceed the construction cost limitation, the designer shall submit the following: (1) the cost estimate showing a base bid that is equal to or less than the construction cost limitation; (2) identify a list of additives alternates/options to bring the total bid package to no more than the construction cost limitation specified, that have been coordinated through the Mobile District Corps of Engineers Project Manager (PM); and (3) a written narrative explaining the reasons why the current construction costs including project escalation exceeds the construction cost limitation specified. A written narrative shall also be submitted whenever the current cost estimate has changed more than 5% (plus or minus) from the previous cost estimate. In the case of the project definition or concept cost estimate, variations from the DD Form 1391 shall be explained in narrative form. 18.7.2.2 Failure to Comply with Procedures
Failure of the designer to conform to the procedures outlined within this or referenced manuals will result in the estimate being rejected and resubmitted with deficiencies corrected and the designer may be required to come to the Mobile District office within 48 hours for a face-to-face meeting for the purpose of preparing a corrected cost estimate. 18.7.3 Format General
18.7.3.1
When TRACES, MCACES GOLD or MCACES 2nd Generation (MII) is specified, the format will be as outlined in the Statement of Work-Cost Estimating Criteria. The Cost Estimate shall also follow the Tri-Services Work Breakdown Structure (WBS). In addition, a Work Breakdown Structure hierarchy (Normal, Full, Partial or Special) has been established for all M-CACES Gold and MCACES 2nd Generation (MII) projects. Project information shall be input so that the estimate output will present costs for the building (or primary facility), broken down according to its various features, and costs for all support items. Any bid schedule, money allocations, etc. requirements shall also be considered. The TRACES system, after project/facility data has been established, models selected, project parameters defined, quantities and direct costs calculated, modifiers (overhead, profit, escalation, contingency, and SIOH) added, the system will generate various construction cost reports. The MCACES and MCACES 2nd Generation (MII) system, after project unit prices, assemblies, models, labor rates, construction equipment rates and crew data is input, will compute costs and produce the estimate. When an estimate is manually prepared, its format shall conform to the example provided, with similar breakdown of features and bid items. When an estimate is prepared using the Excel Spreadsheet method, its
18-8
format shall also conform to the example provided, with similar breakdown of features and bid items. 18.7.3.1.1 Military Projects
The Military WBS as specified in Section 18.11 will normally be used on all Military Construction Projects. 18.7.3.1.2 Civil Works Projects
At the Reconnaissance Study or alternative evaluation phase of Feasibility Studies, rough-order-of-magnitude estimates based on historical costs can be prepared manually or using an Excel spreadsheet. Once a selected plan is determined a detailed MCACES GOLD or MCACES 2nd Generation (MII) estimate must be prepared using the appropriate Civil Works Work Breakdown Structure (WBS) format. After which a Total Project Summary of Costs must be prepared using an Excel spreadsheet. This summary must be arranged by Code of Accounts format and include all project costs (e.g. Real Estate, Design, Engineering During Construction, etc.) and show the appropriate escalation. At the Plans and Specifications (P&S) stage all estimates must be prepared using MCACES or MCACES 2nd Generation (MII) and detailed equal to the level of design. The MCACES or MCACES 2nd Generation (MII) estimate should be arranged according to the project Bid Schedule included in the specifications and be formatted in the Civil Works WBS. The Total Project Summary of Costs must also be updated at this stage to reflect the current estimates. At the RTA stage, the Government Estimate must be arranged according to the Bid schedule shown in the solicitation specifications. The Government Estimate must be prepared using MCACES or MCACES 2nd Generation (MII) to a level of detail commensurate with the solicitation drawings. The Government Estimate does not include Prime Contractor Profit. For Civil Works Projects involving dredging, the cost estimate should be prepared using the appropriate CEDEP spreadsheet program in lieu of MCACES for the Dredging Account only. 18.7.3.1.3 HTRW Projects
HTRW Environmental Restoration Projects shall use the HTRW WBS. The HTRW WBS provides the framework for preparing cost estimates, modeling development, and collecting historical data for all remediation projects. The WBS consists of a numbering and title system that details the work to four levels of the WBS to organize the HTRW estimate. As a minimum, all estimates shall be prepared to the fourth level followed by detail. The quantity take-off shall be prepared following the WBS to the same level. In no case shall the WBS title descriptions be changed for levels one through four. Levels five and six are optional. New titles for work not covered in the WBS may be added under numbers 90 through 99. Maintaining this rigid structure for the first four levels will allow systematic collection of historical HTRW costs. Any vertical building construction required within the HTRW project shall be a separate estimate from the environmental work and shall follow the Military WBS. HTRW projects will likely have two distinct phase; construction of a treatment facility and operation and maintenance of the facility over a period of time that may range from months to years. Construction and operating wage rates, escalation rates, and other cost
18-9
may be different for construction vs. long-term plant operation. Therefore, construction costs will be prepared in a separate estimate from the after construction operations cost. Depending on the project scope, it is possible the designer will be required to prepare three (3) separate estimates for each submittal. One for the vertical building construction, one for the HTRW construction, and one for plant operations. 18.7.3.2 Bid Schedule
For Project Definition submittals, estimated contract costs shall conform to a bid schedule similar to that expected to be developed later, with a minimum of at least one bid item for work within any building and at least one to cover exterior work. For later than concept submittals, estimates shall conform to an acceptable bid schedule proposed by the designer. Generally, each different building or building type must be covered under a separate bid item. Within a building, selected features or work items may be required to be covered under separate bid items for cost accounting or other reason. Exterior work may be required to be broken into separate bid items where quantities of work are significant and highly variable or where useful historical cost data can be derived from analysis of bids received. The estimate shall present a total amount for each bid item to include direct labor, material and construction equipment costs, indirect costs and profit. The final bid schedule will be as directed or approved by the Government. If the estimated cost of the total project, including cost growth allowance, would exceed the CCL, it may be necessary that the bid schedule include items under a base bid and additive alternates /options. Where additional bid item breakdown beyond that proposed by the designer is considered necessary, it shall be provided by the designer at no additional cost to the Government. Guidance regarding bid item breakdown may be obtained by contacting the Mobile District Military Cost Engineering Unit. Estimates for modifications under an existing construction contract must conform to the contract pay item schedule. When the Statement of Work requires multiple Bid Schedules, preparation of separate detailed cost estimates and associated summaries is mandatory. 18.7.3.3 Contractor Type
The estimate shall be structured according to the type contractor considered most likely to bid as prime. For example, if the job is so heavy in mechanical work that most bidders would likely be mechanical contractors, the estimate should reflect a mechanical prime contractor. 18.7.4 Cost Breakdown General
18.7.4.1
Costs must be broken down into priceable elements. All cost and quantities in the estimate must be supported. Unsupported lump sum pricing is not acceptable at any stage of design. The level of breakdown must be commensurate with detail available from the design documents. 18.7.4.2 Project Definition (10-15%)
The Project Definition Cost Estimate should be as detailed as the level of design will permit. Unit pricing which includes all direct labor,
18-10
material and construction equipment costs and any subcontractor markups is permitted, provided appropriate support is included. Prime contractor indirect costs and allowance for profit must be excluded from such unit prices and added separately. 18.7.4.3 Concept Design (30-35%)
The Project Definition Cost Estimate should be as detailed as the level of design will permit. Unit pricing which includes all direct labor, material and equipment costs and any subcontractor markups will be permitted up through the concept submittal, provided appropriate support is included. Prime contractor indirect costs and allowance for profit must be excluded from such unit prices and added separately. 18.7.4.4 Interim Design (50-60%)
The Interim Design Submittal Cost Estimate shall be prepared in task-bytask detail to accurately reflect the scope of work shown in the submittal. This cost estimate provides good cost control prior to final design. 18.7.4.5 Final Design (Unreviewed 100%)
The Final Design Cost Estimate shall be prepared in task-by-task detail to accurately reflect the scope of work shown in the submitted documents. At the Final submittal, since design is complete, the scope of work is defined sufficiently well to permit accurate and complete determination of all project costs. 18.7.4.6 Ready-to-Advertise (100%)
At the Ready-To-Advertise submittal, a final update of the Final submittal, the estimate will be comprised entirely of work tasks for which basic costs are detailed. The designer is responsible for the complete cost estimate including amendments that might occur during the advertising period. This cost estimate should be submitted to the Mobile District Cost Engineering Branch 4 days prior to the final bid/proposal opening date. 18.7.5 Resubmittal and/or Support
If upon review, any submitted estimate is found to not be in compliance with any of the requirements stated or referenced in these instructions, it will be rejected. The designer shall, promptly upon request, revise and resubmit the estimate in the time specified in the resubmittal notice, with deficiencies corrected, at no additional cost to the Government. If cost, quantity, etc., of any item in the estimate appears questionable, the designer shall promptly provide sufficient and satisfactory explanation and/or supporting data. 18.7.6 Bid Exceeds Estimate
After all bids are received and they are significantly higher than the Government Estimate to be determined unreasonable, there is a possibility that one or more bidders will protest the reasonableness of the Government Estimate. In addition, the designer/cost consultant Final Bid Price Estimate may not be within 15 percent of the low responsive bid at bid opening time. If this occurs, the designer has a major role in reviewing the Government Estimate and evaluating the Government's position. The designer/cost consultant will promptly
18-11
conduct an independent review of the Government estimate at no additional cost to the Government. The responsible cost engineer would review the Government Estimate to be sure that it does not contain any omissions, discrepancies (errors in calculation, etc.), quantity takeoff errors, or errors in cost/pricing data. In addition, the reviewer should further analyze any unusual conditions or circumstances that may affect or complicate the work. If the reasonableness of the Government Estimate is protested, the analysis will consist of an in-depth, pointby-point response to all issues raised by the protestor or contractor. The review/analysis will consist of the Government Estimate, including all backup and supporting data, complete explanations about assumptions made and, if available, historical data from previous similar projects which support the estimate. The Government Estimate should be revised immediately if an error is found, and an explanation of the error should accompany the revised estimate. If the revised estimate brings an offeror's price within range of a fair and reasonable price, the Contracting Officer will review the situation and determine final contracting action. The designer is required to accomplish the design to permit the award of a contract at a price that does not exceed the construction cost limitation specified. When bids for the construction contract exceed this amount, the Mobile District may enforce the contract clause requiring the designer to perform such redesign necessary to permit award within funding limitations. These services shall be performed at no increase in the cost to the Government. 18.8 TECHNICAL REQUIREMENTS General
18.8.1
Estimates must accurately reflect the project scope and conditions, local labor situation and prices of material, labor, and construction equipment anticipated or forecast to prevail in the project vicinity at the time of construction, based on a practicable construction schedule. The estimate should consider delivery dates for materials and equipment to be installed. Estimates will not be accepted as meeting contract requirements if data used in their preparation is substantially different from that shown on the submitted drawings or other design data. Very close coordination and clear communication among the designers and estimators is required because reliable, accurate estimates cannot otherwise be produced. 18.8.2 Quantity Survey
Accuracy and completeness of the quantity survey (takeoff) is essential as it directly and critically affects the accuracy of the estimate. The takeoff shall be comprehensively and accurately prepared to cover all work for the project. It shall be based on all facts that can be gathered from the available engineering and design data. Assumptions as to detail which is beyond the level available at the current stage of design is often necessary to insure that total cost of the overall project work is covered. In such cases, statements and explanations of necessary assumptions shall be included so that, when design details become available, quantities can be reconciled. Quantity surveys must be planned to fit the pricing for the work involved, conform to the bid schedule, and be consistent with the payment provisions of the specifications. Surveys must be documented in such manner that computations can be later followed and verified by others. Tabulation and computation sheets shall be dated and contain appropriate references
18-12
to plans, specifications, or design analyses. Relevant sketches shall be included. Quantity survey documentation must be furnished as a part of the estimate submittal to be reviewed by the Mobile District Cost Engineering Branch. The importance of accurate and concise quantity take-off to the cost estimate cannot be overstressed. The following procedures and exhibits must be followed in order for the designer to have an acceptable cost estimate. If a spot check of quantities by the District reveal inaccuracies or the required format has not been used in the preparation of the cost estimate, the estimate will be rejected and must be resubmitted with the deficiencies corrected. The quantity take-off is required to follow the applicable WBS. The quantity take-off and cost estimate shall be treated in a confidential manner and only those personnel concerned with the preparation and/or review of the project shall have access to it. The cost estimate will be utilized in preparing government estimates for evaluating bids and shall be classified FOR OFFICIAL USE ONLY. Such material cannot be divulged to other than accredited Government personnel with a need to know. Information contained within estimates shall not be divulged to prospective bidders. Parametric measurement(s) such as lump sums, building costs by square foot of area, etc. for all estimates are not permissible and estimates utilizing such will be rejected. Prepare a quantity take-off in accordance with appropriate WBS showing all quantities used in the cost estimate. The estimator shall show all assumptions as to scope and design used in preparation of the cost estimate. These assumptions shall include WBS systems contained within the project. Proper allowances shall be made for WBS system and subsystems not completely determined in the plans, specifications and design analysis. The quantity take-off and cost estimate shall be an accurate representation of the complete design submitted. Quantity take-offs shall not be written on the drawings themselves. The quantity take-off shall be prepared in a manner that is clearly legible, indicating the calculations involved in determining the quantity and any assumptions the estimator has made in determining the quantity. The take-off shall contain backup and supporting sheets showing breakdown for all quantities of all materials contained within the design drawings and/or specifications. The top of each quantity take-off sheet shall contain the following information: (1) project information; (2) the design stage; (3) the drawing file number and/or specification section & paragraph number from which the quantity was derived; (4) facility name, quantity, and Unit of Measure (UOM); (5) WBS code where the quantity is located in the cost estimate; and (6) the date and initials of the estimator who prepared them as well as the initials of the estimator who checked them. ALL QUANTITIES AND QUANTITY CALCULATIONS MUST BE CLEARLY TRACEABLE TO THE COST ESTIMATE ITEM THAT THEY SUPPORT. 18.8.3 Material Pricing
When an item of material is relatively minor or not yet fully defined, as at concept or earlier stage, it may be satisfactory to base pricing on data in estimating handbooks (including the MCACES Database). In these cases, appropriate adjustments must be made to account for project conditions. For later stages or for significant items, material costs will be based on verbal or written quotations obtained from
18-13
manufacturers and suppliers, price lists appropriately discounted, and previous recent quotations. Specific current price quotations (at least two, if practicable) should be obtained for major items of permanent equipment and for significant, unusual or nonstandard material items. Where quantities or unit costs will have only moderate impact, recent reliable quotations from other projects for comparable items are considered acceptable. Freight costs to the project site must be covered. Sales and other applicable taxes must be included in the estimate by applying, in a separate calculation, appropriate percentage markups of material cost. Guide for Estimating sales Taxes can be downloaded off the Internet (See Paragraph 18.3 above). Each submittal for which quotations are appropriate shall include a list showing principal items of material, equipment and supplies (such as concrete, structural steel, siding, pumps, chillers, uninterrupted power system, etc.), and indicating the manufacturer/supplier, location, person contacted, telephone number, date, pricing, etc., along with all other pertinent information collected or prepared for the estimate. A record of the pricing data utilized must be maintained and submitted as backup data with the estimate to be reviewed by the Mobile District Military Cost Engineering Unit. 18.8.4 Labor Wages
18.8.4.1
Labor costs in the estimate must be based on rates that include basic wages, overtime and holiday premium payments, and Contractor's contributions for fringe benefits such as health and welfare, holiday and vacation pay, pension fund, apprentice training, etc. Estimated rates should be those which the contractor will be expected to pay when the project is actually constructed and must consider prevailing rates actually being paid in the project area as well as minimum rates which will be included in the contract in accordance with the requirements of the Davis-Bacon Act. Information on wages may be available from various sources, such as Corps field offices, Mobile District Cost Engineering Branch, contractors in the project area, etc. Ultimately, the designer is responsible for all wage rates used in the cost estimate. 18.8.4.2 Unit Costs General
18.8.4.2.1
Labor unit costs should be based on estimated productivity and cost of wages, fringe benefits, etc. for the labor involved. Productivity estimates are based on experienced rates, tempered by estimators' judgement and must consider project conditions, labor availability, market conditions, and the like. Useful information can be obtained from vendors, subcontractors, and other pertinent sources. 18.8.4.2.2 TRACES
TRACES does not use specific project location wage rates to develop unit costs, but uses location modifiers to adjust material, labor, and construction equipment costs based on the location of the project. However, TRACES scope and cost can be exported to MCACES GOLD where specify line items can be adjusted.
18-14
18.8.4.2.3
MCACES GOLD
For MCACES GOLD estimates, labor unit cost is a function of the crew unit cost and the value for crew daily output included for each task. The productivity rates in the MCACES GOLD Database must be adjusted for project conditions as appropriate. 18.8.4.2.4 Manual or Excel Spreadsheet
Productivity must also be carefully evaluated for Manual or Excel Spreadsheet estimates. For mechanical and electrical work, labor cost must be estimated by assigning unit manhours to each task, then applying an appropriate prevailing wage rate to the summarized manhours. For work other than mechanical and electrical, labor may generally be estimated by applying to each task a realistic unit cost (based on a reasonable task productivity and current prevailing wage rates), unit manhours, unit crewhours, or as directed. Where the labor cost for a specific task in a manually-prepared or Excel Spreadsheet prepared estimate is significant, or the task has unique requirements, the submittal should include a detailed estimate based on productivity and cost of an appropriate crew similar to the example provided. 18.8.4.2.5 Social Benefits Cost
The contractor's cost for Social Security taxes (FICA), Federal and State Unemployment Insurance, Workmen's Compensation and Employer's Liability Insurance and any other social benefits must be included in the estimate as a percentage of the labor costs. Guide for Estimating Payroll Taxes & Insurance can be downloaded off the Internet (See Paragraph 18.3 above). 18.8.5 Construction Equipment
TRACES does not use specific project location construction equipment costs, but uses location modifiers to adjust material, labor, and construction equipment costs based on the location of the project. For MCACES GOLD estimates, costs for construction equipment and small tools costs are included in the equipment rates database. These costs are thereby included by the system for each task, as appropriate. For manually-prepared or Excel Spreadsheet estimates, costs shall be computed similarly to the crew method of MCACES GOLD and included in the detail for the work item to which it pertains. EP 1110-1-8 is the basis for MCACES GOLD construction equipment unit costs and shall be used as well for estimating construction equipment costs for manual or Excel Spreadsheet cost estimates. Sometimes extraordinarily large numbers, or highly specialized, unusual or unique items of construction equipment may be required to construct a project. In any instance where it is considered likely that the Contractor would have to rent certain construction equipment, rental rates should be determined for those items and appropriate adjustments included in the cost estimate to cover any additional cost. 18.8.6 Subcontract Work
Estimates shall be prepared for subcontract work using the same methodology and degree of detail for direct costs as outlined for work by the prime contractor. All Subcontractor work must be detailed. Subcontractor quotations in lieu of detail is unacceptable. The subcontract estimate shall include costs for direct labor, materials, equipment, and second-tier subcontracts, as well as subcontractor
18-15
mobilization and other indirect costs and profit. A subcontractor's overhead usually bears a fairly stable relationship to the subcontractor's portion of the work and can be estimated on a percentage basis. Overhead rates typically range from 10 to 15 % and profit rates from 7 to 10 %, depending on complexity, risk, etc., and judgement must be exercised in selecting appropriate rates. For second-tier subcontract work, overhead and profit markups must be covered for second-tier as well as first-tier. A detailed derivation of subcontractor's overhead costs will be required where his work has unique requirements or where the cost impact of the subcontracted work is significant. When reliable subcontractor quotations are obtained, they may be used to verify the reasonableness of the estimate for the subcontract work. 18.8.7 Mobilization and Demobilization Costs
These costs must be estimated by detailed analysis considering equipment requirements, distance to move to project site, transportation methods, effort required to prepare, service, load, unload, etc., and the detail included in the submittal. For most building-type projects, mobilization and demobilization for the prime Contractor may be included in the estimate of indirect costs. Subcontractor mobilization and demobilization cost should be included in the estimated subcontract total. Where costs apply primarily to certain work items, e.g., for specialized equipment, they should be appropriately distributed to applicable items. 18.8.8 Indirect Costs General
18.8.8.1
For concept or earlier estimates where direct cost items may be estimated by experienced unit prices, use of empirical markups for prime contractor is acceptable. For later-than-concept estimates, all field indirect costs for the project must be estimated in detail and then distributed logically to the various items in the bid schedule. Home office expense will normally be prorated to all bid schedule items. 18.8.8.2 Field Indirect Costs
These include such costs as those for field supervisory, administrative, and technical personnel, offices, shops, yards, utilities, communications, office and engineering supplies and equipment, etc. expected to be incurred at the project site but not chargeable to a specific work item. Exhibit 18-1 lists some items of field indirect cost. The list is not all-inclusive but is indicative of the type costs which are to be considered. 18.8.8.3 Home Office Expense
These costs will typically be included in estimates by applying an estimated percentage to the expected total field (direct plus indirect) cost amount. A contractor's home office expense rate is not fixed but varies from period to period. It is considered a function of his total general and administrative expense for a specific period divided by his total field costs for that same period. A reasonable average range of rates is estimated to be from 2% for larger to 7% for smaller contractors.
18-16
18.8.9
Profit
The estimate shall include appropriate allowances for profit. For the prime Contractor and for subcontractors whose work is a significant portion of the project, rates for profit allowance will be determined by the Weighted Guideline method (Exhibit 18-2). For less significant subcontract work, experienced percentage rates may be used. 18.8.10 Bond
Costs for performance and payment bonds shall be included in the estimate. Specific rates are dependent on factors such as the type of work to be performed, the contract amount, and the time allowed for completion. 18.8.11 Contract Modification Estimates
In certain instances, the designer will be tasked to prepare estimates for a modification to an ongoing construction contract. Such estimates are used as a basis of negotiations with contractors for additions to or deletions from a project, or both, and shall be carefully prepared in accordance with the applicable instructions in this chapter, as well as any supplemental information or instructions to be furnished by the Mobile District Military Cost Engineering Unit. Discussions with the Mobile District Military Cost Engineering Unit prior to preparation of the contract modification cost estimate is mandatory. 18.8.12 Current Working Estimate (CWE)
The CWE is defined as the latest available cost estimate for a particular project and should represent, as closely as possible, the total expected cost to construct the project. It must include the estimated contract cost as of the date of preparation, an allowance for cost growth (Current Cost Growth Factors can be downloaded off the Internet - See Paragraph 18.3 above), as applicable, an amount for contingency reserve to cover unforeseen developments during the actual construction which will result in additional costs, and an allowance for Government supervision and administration (S&A). To account for any cost increases which are anticipated to occur between the estimate preparation date and the actual construction period, an allowance for cost growth must be made. This will ordinarily be accomplished by the use of a percentage factor developed from a cost escalation index. Guidance for construction contingency allowance and S&A costs are outlined in the Statement of Work-Cost Estimating Criteria. 18.8.13 Quality Assurance
See Exhibit 18-3 Technical Quality Control Checklist. This checklist may be used by the cost engineer to ensure the cost estimate submittal is complete. 18.8.14 Supplemental Information
Additional specific information and guidance will be furnished as appropriate for projects which are unique or unusual or for projects outside the Continental United States.
18-17
18.8.15
Clarification
Should any question arise concerning the requirements, instructions, procedures, etc., described herein, the Mobile District Cost Engineering Branch (334-690-2626) should be contacted for explanation and clarification. 18.8.16 DD Form 1391
Estimates shall be based on the most recent and complete design information available and shall follow the format of the appropriate Work Breakdown Structure (WBS). There are three (3) separate Work Breakdown Structures: Military, Environmental Restoration, and Civil Works. The Military WBS shall be used for all vertical building construction whether Military, Environmental or Civil Works funded. Environmental Restoration projects shall use the Hazardous, Toxic, Radioactive (HTRW) WBS (funded by DERO, Superfund, DOE, etc.). The Civil Works WBS shall be used for large earth moving/dredging projects normally funded with non-military funds. 18.10 SPECIFIC INSTRUCTIONS (MCACES GOLD).
The designer will be provided the following information. 18.10.1 MCACES GOLD User Manual, Volume I - Functions and Capabilities; Volume II - Advanced Options. See Paragraph 18.3 above. 18.10.2 above. MCACES GOLD Software, Current Version. General See Paragraph 18.3
18.10.2.1
The designers computer will have to be configured properly and have sufficient disk space available (see MCACES GOLD User Manual, Volume I, Appendix A) before installing the software. The MCACES GOLD software shall be installed as provided following all instructions. The designer shall work through the MCACES GOLD User Manual and become familiar with the program. The designer shall use the installation instructions provided in the manual. Some of the databases may be in a Protected Mode and the user cannot edit these databases. Once items from these databases are brought into the project, they may be edited to reflect conditions for that project. Specific Project Templates are provided via the Cost Engineering Branch Internet address, and shall be used to create the project. The Project Templates provided already have the structure set. Working Appendix A, Learning GOLD, will help in getting familiar with the software. THE DESIGNER MUST USE THE MCACES GOLD SOFTWARE SPECIFIED FOR USE BY THE MOBILE DISTRICT FOR THIS PROJECT, AND NO OTHER MCACES GOLD SOFTWARE. All databases provided are FOR OFFICIAL USE ONLY and shall be protected accordingly. ASM94A - 17 Building Assemblies Library CWSA95 - Civil Works Smart Assemblies HTWASL - HTRW Assemblies Library
18-18
HTRW Estimate Example - Bid Form HTRW Template - Bid Form 1994 Civil Works Work Breakdown Structure 1994 Civil Works Checklist Job Office Overhead Model HTRW Remedial Action Work Breakdown Structure HTRW Remedial Action Work Breakdown Structure TRACES Work Breakdown Structure 44 Building Model Library Unit Price Book (Current Edition) Labor Rates (Note: Specific Locations Listed) Crews Database (Current Edition) Equipment Database (Current Edition)
Explanation can be found in the MCACES GOLD User Manual. Both the Assembly and Models databases contain similar information, which are a few generic type assemblies. Some of these assemblies may be close to your requirements and may be copied to a new assembly ID and edited to create a new assembly to be used in your project. The ASSEMBLY DATABASE ID is ASM94A, and the MODELS DATABASE ID is MDL92A. Note: Assemblies and Model Databases may not be used for Later-ThanConcept submittals. However, they may be used for Design-Build projects. 18.10.3 Labor Rates Database
If available, current wage rates to be used in preparing the construction cost estimate will be provided to the designer. The furnished wage rates will be generic and will normally reflect the Davis-Bacon minimum wage rate determination. The designer is responsible for addressing any abnormal circumstances required by the project and making corrections to the database wage rates provided. If no current wage rates are available, it is the designers responsibility to fully investigate and determine proper wage rates. Using the localized LABOR RATES DATABASE, will put the correct labor and unit cost into the project. As the units of work are brought into the PROJECT DATABASE they are repriced with the currently selected LABOR, EQUIPMENT and UPB (material only) DATABASES. The labor and unit cost shown in the UPB, CREW and ASSEMBLY DATABASES will not show the same cost when brought into the project because these databases have not been repriced to the localized LABOR RATES DATABASE. See Guide for Estimating Payroll Taxes & Insurance and Sales Tax Costs (Stateside Projects Only) Reference Paragraph 18.3 above.. 18.10.4 Sample Projects
Sample Projects are provided for review of the required format for the Civil, HTRW and Military type of estimates prepared by the U.S. Army Corps of Engineers. All databases are compressed and can be loaded from within the MCACES software using LOAD FROM COMPRESSED on the SERVICE Menu. All Sample Projects may be loaded into the \GOLD\PROJECT\ directories. The following Sample Projects are available via the Cost Engineering Branch Internet (See Paragraph 18.3 above) address: CIVEXM DEMAIR HTWEXM MILEXM Buffalo Bayou Sample Estimate Air Terminal Reconstruction HTRW Example Estimate Storage Building Example Estimate
18-19
18.10.5
Templates
Templates shown below are used to start the respective project. For Military Estimates the MILTM2,MILEX1 or MILEX2 Template (depending on the WBS specified) is to be used to create the estimate format. For Civil Estimates use the CIVTMP template, and for HTRW Estimates use the HTWTMP template. Use LOAD FROM COMPRESSED on the SERVICES Menu to load the required template into the \GOLD\PROJECT\ directory. Use COPY A DATABASE from the SERVICES Menu to copy this project template into a unique six-character project ID. The templates are not to be used for entering data. The templates contain the proper format for creating the cost estimate, along with the WBS Titles. CIVTMP HTWTMP MILTM2 MILEX1 MILEX2 18.10.6 Civil Works Template HTRW Template Military Template - Normal WBS Military Template - Full WBS Military Template - Partial WBS
The Work Breakdown Structure will be used as a guide in structuring the cost estimate and quantity survey sheets. The WBS should be reproduced and provided to each Cost Engineer working on the project. The WBS should be closely coordinated with the project Bid Schedule. If any problems arise in coordinating the Bid schedule and the WBS - the Mobile District Cost Engineering Branch should be contacted for resolution. 18.10.7 Training
MCACES GOLD training is no longer available through Building System Design, Inc., Atlanta, GA (404-876-4700), as this software is being phased out. 18.10.8 Unit Price Book Database
A hard copy of the Unit Price Book is not provided by the U.S. Army Corps of Engineers, Mobile District. However, if desired, it can be printed after downloading from the Internet and instructions obtained from the MCACES GOLD User Manual. 18.11 TECHNICAL INSTRUCTIONS FOR MCACES GOLD COST ESTIMATES
Note: The following instructions are based on a Military Project. Civil and HTRW would be similar. 18.11.1 Estimate Format
The Military Work Breakdown Structure (WBS) as provided by the Mobile district, and as specified above, shall be used on all Military Construction Projects (MCP). The Military WBS provides a common TriService framework for preparing cost estimates, model development, and collecting historical data for all conventional MCP. This Military WBS is a hierarchical structure comprised of a total of eight levels: (0) Project, (1) Primary/Supporting/Additive Alternate/Option, (2) Facility (Bid Item), (3) System (WBS), (4) Subsystem, (5) Assembly Category, (6) Assembly, and followed by line item (7) Detail. Each system is divided into one or more subsystems which are further divided into assembly categories, then assemblies. Assemblies are made up of construction
18-20
line items. The System, Subsystem and Assembly Category Titles are rigidly defined and shall not be changed. An Assembly is a collection of individual cost items that function together as a single building/construction unit. For example, a 12-inch storm drainage line consists of excavation, backfill, compaction, layer of drainage gravel, 12-inch concrete pipe, etc. One unit of an assembly contains a specified quantity and unit of measure of each included item. The Assembly has its own unit of measure. When the Assembly is linked and the assembly quantity is changed all included quantities are changed proportionately. Assemblies shall be created for building/construction systems as required by the project. In no case shall the WBS title descriptions be changed for levels (0) through (5). New titles for Subsystems or Assembly Categories shall be entered under the Other category. See the Military WBS. Note that the 01 through 15 Systems are for the interior of the building (5-foot line outside the building) and system 16 Selective Building Demolition fall under Primary Facilities. System 17 through 20 are exterior systems and fall under Support Facilities. 18.11.2 MCACES GOLD SOFTWARE AND DATABASES
ALL LABOR, CONSTRUCTION AND MATERIAL COSTS PROVIDED IN THESE DATABASES ARE A PRICING GUIDE ONLY. IT IS THE DESIGNERS RESPONSIBILITY TO CHECK AND VERIFY PRICING USED IN HIS COST ESTIMATE. All Databases are compressed and can be loaded from within the MCACES GOLD software using LOAD FROM COMPRESSED on the SERVICE Menu. All databases shall be loaded into the \GOLD\DATA\ directories. All databases provided are FOR OFFICIAL USE ONLY and shall be protected accordingly. NOTE: LOAD FROM COMPRESSED - When using this command you are presented with a list of available databases to load for the Directory/Path you indicated. To select a database use the Up/Down Arrow keys to highlight the database you want to load and press the [Space Bar]. This will place a check mark to the left of the database. This can be repeated for any or all databases. After marking the databases you want loaded press the [Enter] key to start the process. 18.11.3 Military Estimate Hierarchy
When creating a MCACES GOLD cost estimate it is important to recognize that the construction project consists of the following hierarchical levels: (1) NORMAL WORK BREAKDOWN STRUCTURE (WBS) LEVEL 0 (Top Most Level) LEVEL 1 LEVEL 2 LEVEL LEVEL LEVEL LEVEL LEVEL NOTE: 3 4 5 6 7 PROJECT SCOPE - PRIMARY/ SUPPORT/ ADDITIVE ALTERNATE/ OPTION BID ITEM - BOTH PRIMARY AND SUPPORTING FACILITIES SYSTEMS (WBS) SUBSYSTEM OPTIONAL OPTIONAL OPTIONAL
(a) Project Level (LEVEL 0). All cost of the Primary and Support Facilities are accumulated to obtain a total project cost. This
18-21
shall include all construction cost as well as Government-Furnished materials and items furnished through other than construction funds, i.e. information systems. Escalation, Construction Contingency and Supervision & Administration (S&A) or Supervision, Inspection & Overhead (SIOH) Costs are added at this level. (b) Scope - Primary/Support/Additive Alternate/Options (LEVEL 1). Divides the project into Primary Facilities, Support Facilities, Category E Equipment and Government-Furnished Equipment based on DD Form 1391 format for the project. Additive Alternates or Options shall also be located at this level if required. (c) Bid Items - Primary Facilities (LEVEL 2). Individual Facilities under Primary Facilities will be all individual building/major construction features. Individual Facilities under the Support Facilities shall be eight categories under Support Facilities of the DD Form 1391. (d) System (LEVEL 3). Under Primary Facilities the interior Military WBS System 01 through 15 and System 16 are titled at this level. If there are multiple Primary Facilities, each one shall be broken down by the 01 through 16 Systems. Under Support Facilities the Military WBS Systems 17 through 20 are broken down under the appropriate eight categories defined by DD Form 1391. (e) SubSystem (LEVEL 4). This level contains the Subsystem titles from the Military WBS for the above Systems. If there are subsystems in the project not identified by the Military WBS, they shall be identified using 90 through 99 under the appropriate System. (f) Optional (LEVEL 5), (LEVEL 6) OR (LEVEL 7). These levels could be used to further define the project features. Detail can be at level 5, 6 or 7. Individual Cost Items are located at this lowest level in the cost estimate and reports at this level are referred to as Detail Reports. These are the basic work tasks consisting of labor, construction equipment and material cost and is the same level of detail as that found in the Unit Price Book Database. Some of the basic work tasks can be modified by Modifiers from the UPB. (g) Modifiers are identified in the UPB Database and provide a method of adding or reducing, for optional quality or scope to the work task costs. Each modifier acts solely on the basic cost item it is assigned. (2) FULL WORK BREAKDOWN STRUCTURE (WBS) PROJECT SCOPE - PRIMARY/ SUPPORT/ ADDITIVE ALTERNATE/OPTION BID ITEM - PRIMARY FACILITIES SYSTEM (WBS) SUBSYSTEM ASSEMBLY CATEGORIES, BID ITEM SUPPORTING FACILITIES ASSEMBLY DETAIL
LEVEL 6 LEVEL 7
(a) Project Level (LEVEL 0). All cost of the Primary and Support Facilities are accumulated to obtain a total project cost. This shall include all construction cost as well as Government-Furnished
18-22
materials and items furnished through other than construction funds, i.e. information systems. Escalation, Construction contingency and Supervision & Administration (S&A) or Supervision, Inspection & Overhead (SIOH) Costs are added at this level. (b) Scope - Primary/Support/Additive Alternate/Options (LEVEL 1). Divides the project into Primary Facilities, Support Facilities, Category E Equipment and Government-Furnished Equipment based on DD Form 1391 format for the project. Additive Alternates or Options shall also be located at this level if required. (c) Bid Items - Primary Facilities (LEVEL 2). Individual Facilities under Primary Facilities will be all individual building/major construction features. Individual Facilities under the Support Facilities shall be eight categories under Support Facilities of the DD Form 1391. (d) System (LEVEL 3). Under Primary Facilities the interior Military WBS System 01 through 15 and System 16 are titled at this level. If there are multiple Primary Facilities, each one shall be broken down by the 01 through 16 Systems. Under Support Facilities the Military WBS Systems 17 through 20 are broken down under the appropriate eight categories defined by DD Form 1391. (e) SubSystem (LEVEL 4). This level contains the Subsystem titles from the Military WBS for the above Systems. If there are subsystems in the project not identified by the Military WBS, they shall be identified using 90 through 99 under the appropriate System. (f) Assembly Category, Bid Item - Supporting Facilities (LEVEL 5). This level contains the Assembly Category titles from the Military WBS for the Subsystems above. If there are Assembly Categories in the project not identified by the Military WBS, they shall be identified using 90 through 99 under the appropriate subsystem. In addition, this level contains the Bid Items for the Supporting Facilities. (g) Assemblies (LEVEL 6). Assembly Titles shall be created at this level following the definitions contained in the WBS. (h) Detail (LEVEL 7). Individual Cost Items are located at this lowest level in the cost estimate and reports at this level are referred to as Detail Reports. These are the basic work tasks consisting of labor, construction equipment and material cost and is the same level of detail as that found in the Unit Price Book Database. Some of the basic work tasks can be modified by Modifiers from the UPB. (I) Modifiers are identified in the UPB Database and provide a method of adding or reducing, for optional quality or scope to the work task costs. Each modifier acts solely on the basic cost item it is assigned. (3) PARTIAL WORK BREAKDOWN STRUCTURE (WBS) PROJECT SCOPE - PRIMARY/ SUPPORT/ ADDITIVE ALTERNATE/OPTION BID ITEM - BOTH PRIMARY AND SUPPORTING FACILITIES
18-23
3 4 5 6 7
(a) Project Level (LEVEL 0). All cost of the Primary and Support Facilities are accumulated to obtain a total project cost. This shall include all construction cost as well as Government-Furnished materials and items furnished through other than construction funds, i.e. information systems. Escalation, Construction contingency and Supervision & Administration (S&A) or Supervision, Inspection & Overhead (SIOH) Costs are added at this level. (b) Scope - Primary/Support/Additive Alternate/Options (LEVEL 1). Divides the project into Primary Facilities, Support Facilities, Category E Equipment and Government-Furnished Equipment based on DD Form 1391 format for the project. Additive Alternates or Options shall also be located at this level if required. (c) Bid Item - Both Primary & Supporting Facilities (LEVEL 2). Individual Facilities under Primary Facilities will be all individual building/major construction features. Individual Facilities under the Support Facilities shall be items such as: Exterior Electrical Distribution, Water Supply System, Sanitary Sewer System, Site Improvements, Parking Lot, Landscaping, etc. (d) System (LEVEL 3). Under this title show the Construction Specification Index (CSI) items, such as: Concrete Moisture Protection, Finishes, Specialties, etc. or Trades, such as Asbestos removal, Plumbing, Insulation, Controls, Test & Balance, etc. or a combination of both. The major features of the project should be shown at this level. (e) Optional (LEVEL 4), (LEVEL 5), (LEVEL 6) OR (LEVEL 7). These levels could be used to further define the project features. Detail can be at level 4, 5, 6 or 7. 18.11.4 MCACES GOLD Common Errors
A listing of common GOLD error messages, with explanations of the source of the error, are provided for your information in the MCACES GOLD User Manual. 18.11.5 Design Stage Identification
All sheets of the cost estimate and quantity take-off shall be clearly marked as to the design stage (concept, preliminary, final, etc.) the cost estimate represents. The design stage identity shall be entered in the REPORT TITLE field of the PRINT SELECTED REPORTS entry screen from the Report Menu of the MCACES GOLD software. 18.11.6 Wage Rates
If the project requires the designer to make changes to the Labor Database provided, the designer shall use the copy command from the SERVICES menu to copy the Labor Databases provided to a new Labor Database. The identification of the new Labor Database shall match the
18-24
six-character code of the project ID. The new Labor Database shall be edited to reflect required changes to wage rates. If a new Labor Database is created, it shall be saved when saving the project database to compress. 18.11.7 Subcontractors
The list of subcontractors shown in the MILTM2,MILEX1 or MILEX2 template are for illustration only. The Mobile district acknowledges the fact that there can be more or fewer subcontractors than those indicated, depending on the size and/or type project being designed. There can also be several different subcontractors within a system, such as carpeting contractors and painting contractors within WBS System 06 Interior Finishes. These subcontractors shall be broken out and defined in the Project Information Record within the MCACES GOLD cost estimate. 18.11.8 Prime Contractor Field Overhead
Itemized field overhead items for the Prime contractor shall be estimated in detail for all projects based on working knowledge of the project and the anticipated construction period. A generic itemized overhead (contained in the project template) will be provided by the Mobile District, Cost Engineering Branch as a starting place for the designer. The designer shall edit this itemized overhead to fit the specific project conditions. Items not applicable to this project shall be deleted and new items added as required. 18.11.9 Profit
The designer shall use the Weighted Guideline Method in determining profit for the prime contractor and major subcontractors 18.11.10 Major MCACES GOLD Menu Screens
The Major MCACES GOLD Menu Screens are shown in Exhibit 18-4. The PROJECT DATABASE EDIT, NAME DATABASE COLUMNS, SET BREAKDOWN STRUCTURE, SELECT 2ND VIEW COLUMNS, EDIT DETAIL REPORT FORMATTING, EDIT OTHER REPORT FORMATTING, EDIT REPORT TITLE PAGE, PROJECT NOTES, SELECT REPORTS TO PRINT, PRINT SELECTED REPORTS, EDIT PERMISSION SETTINGS, EDIT BOND AND PROFIT TABLE, EDIT OWNER, AND PRIME CONTRACTOR OVERHEAD & PROFIT SCREEN should be edited as shown and as appropriate. 18.11.11 Required Services
The designer shall supply the following Cost Engineering services: (1) The overall project shall be analyzed by all disciplines involved in preparing the cost estimate to consider the following procedure before making the detailed quantity take-off. This shall be done before preparing the concept estimate as it will dictate the final estimate format needed in the preparation of the quantity take-off. (2) Review the drawings and DD Form 1391 for the project to determine the number of Primary Facilities required in the project. Should the DD Form 1391 contain vertical buildings that can be identified by AR-415-28 Category Codes (no matter how small) in Support Facilities, the designer shall put these buildings under Primary Facilities in the estimate.
18-25
When multiple buildings are involved make each building as a separate Facility under the Primary Facilities. (Example: Tactical Equipment Shop which has POL, Storage and Sentry Buildings). When multiple buildings are being constructed at different sites the designer shall prepare a separate facility for each building in the Primary Facility and separate Supporting Facilities for each building site. The designer shall prepare a proposed Bidding schedule based on the Facility (LEVEL 2) of the Primary facility and the Support Facilities (LEVEL 5) for Site Work. (3) When the number of buildings have been defined in the Primary Facility, each of the buildings shall follow the WBS of defined Systems, Subsystems, Assembly Categories, and Assemblies. The Site Work shall follow the DD Form 1391 and WBS format. The detail Quantity takeoff shall follow this same format. (4) When projects are funded by more than one funding source, all work related to each funding source shall be segregated respectively. Funding sources shall be identified separately at Level 1 in the MCACES estimate and shall be identified separately on the Proposed Bidding Schedule. (5) If the cost estimate is to be prepared by more than one person on more than one computer and then merged into one Prime Estimate, follow the steps in Exhibit 18-5, MERGING MULTIPLE PROJECT DATABASES CHECKLIST. Failing to follow these steps may result may result in cost data having to be re-entered to correct the corrupted database. IT IS VERY IMPORTANT TO UNDERSTAND THAT THE MERGE AND EXTRACT ONLY WORK CORRECTLY WHEN THE FORMAT OF THE DATABASES ARE EXACTLY THE SAME. 18.12 STARTING THE MCACES GOLD PROJECT.
All program software and databases should be installed as described above. Activate the MCACES software following instructions from the MCACES GOLD User Manual. Before starting the project ensure that the appropriate Project Templates and Databases are selected in the Database Window. See Exhibit 18-6 CREATE A NEW PROJECT CHECKLIST. (1) For Military WBS Projects the MILEX1 or MILEX@ Template shall be selected and shown in the Database Window. If it is not currently selected, use [F8] SELECT and highlight with the cursor and select. The Models, Assemblies, Unit Prices, Crews and Equipment Databases shall be selected in like manner. The Labor Database shall be the database for the project location. The below procedure is based on the MILEX1 template. (a) With the proper project template selected and highlighted use COPY A DATABASE from the SERVICES menu and copy this database to a unique six-character identification code assigned by the designer. This will duplicate the information in MILEX1 or MILEX2 to your new project. Select the new project using [F8] SELECT. The new project ID shall now be in the DATABASE WINDOW. (b) With the new project highlighted press [F4] EDIT and enter the official descriptive project title. Press [F10] to save. (c) From the REPORTS menu choose Edit Report Title Page. Enter the appropriate information as shown on the screen. Use Project
18-26
Notes [F7] to describe the overall general scope of the project. Present [F10] to save. (2) Work on Project. Highlight the new project and press [Enter] to work on the project. The first item listed is the Project Information record. With the Project Information record highlighted press [F4] EDIT and enter the category code for the project from the DD Form 1391. Press [F4] to toggle out of EDIT and save the record. (3) Prime Contractor. Choose to work on Project Information Records by highlighting the item and pressing [enter]. The Prime Contractor record is displayed. Edit the Prime contractor by pressing [F4] EDIT. The Field Overhead shall be set to C to calculate. Home Office shall be set to P (Percent), Profit set to C and Bond shall be set to C. (a) OTHER Screen - The last line on the screen (the Status Line) indicates that an Other Screen is attached to this screen by the prompt OTHER. Choose the OTHER screen by pressing [Shift][F7] or using the [F9] MENU ADD/EDIT. This brings forward the attached Prime Contractor Window. The Profit Weighted Guideline Method of determining profit shall be used for the Prime contractor and all subcontractors. Each Risk factor field is HELP [F1] sensitive. By pressing [f1] HELP a description of the appropriate weight to apply to the project will be presented. Each Risk Factor shall be filled in based on the project cost, duration, complexity, and Contractor risks. Also see these instructions elsewhere. (b) The Bond Class Field shall be set to B. This will cause the software to automatically calculate the Bond percentage used in the estimate. Press [F10] twice to save the information on the Prime Contractor. With the Prime Contractor Record highlighted press [Enter] to work on the Prime Contractor. (c) Escalation, Construction Contingency and SIOH are entered on the EDIT OWNER entry screen located from the TITLE LEVEL where owner cost is set. Escalation Factors are found on the Cost Engineering Branch Internet homepage, and Construction Contingency & SIOH are shown in Exhibit 18-8. (d) A list screen appears showing record 0 as the Itemized Overhead followed by a long list of typical subcontractors. Choose the Contractors Overhead by pressing [Enter] to get a list of typical Field Overhead for the Prime Contractor. This list is provided only as a guide. The designer shall add/delete items, edit quantities and adjust cost to represent a detailed itemized Field Overhead for this project. Pressing [F10] upon completion will save the data. (4) Subcontractors. Now highlight the subcontractors and [F4] EDIT them. Any subcontractors not used in the estimate shall be deleted. In order for Contractors to be used in the estimate they must be assigned at the appropriate level within the Primary/Support facilities. [F10] EXIT until you are back at the Project Information Record. (5) Primary Facilities Title. Highlight the primary Facility Title and [f4] EDIT. On the Primary Facility Edit Screen the quantity shall be 1 LS (Lump Sum). Usually the Prime contractor ID AA is entered on this screen as he is usually the prime on all Facilities under Primary Facilities. The Contractor Override Field shall be set to
18-27
NO and the Project Category Code (from DD Form 1391) is typed into the Category Code Field. (6) Facility Titles. Highlight the primary Facility and press [Enter] to the default FACILITY Building One. Create the number of Primary Facilities that has been determined. To create another Facility highlight FACILITY Building One. MARK this item by pressing [Shift][F9] or using the [F9] FUNCTION Menu - MARK. This places a check mark to the left of the title. Exit up a level [F10] and choose COPY from the FUNCTION Menu - MARK or press [Shift][F4]. This brings up a window allowing you to copy AA.01 Building One to a new location. Change the default AA.01 to AA.02 and press [Enter] to complete the copy. Now there are two identical Facilities under the Primary Facilities. Continue this process for all Primary Facilities in the project. After creating all of the Facilities, [F4] EDIT each FACILITY TITLE and type in the name of the Facility, and Gross Square Feet of the Building as the Facility Quantity and UOM. If the Prime Contractor was defined on the PRIMARY FACILITIES TITLE leave the Contractor Field blank. After editing the first facility pressing [PgDn] takes you to the next facility to edit. (7) System Titles. With the FACILITY TITLE highlighted press [Enter] to go to Systems. The 01 to 15 System Titles and selective Demolition System 16 are predefined and the titles shall not be changed. Each title shall be edited to enter the appropriate quantity as defined in the WBS. Any SYSTEM TITLE not used in the project shall be deleted. Sometimes subcontractors can be identified at the Systems Title level as all work performed in the system is normally accomplished by one Contractor. For Example System 11 - Electric Power & Lighting is normally installed by the electrical Contractor EL. (8) Subsystem Titles. With the SYSTEM TITLE highlighted press [Enter] to go to subsystems. The Subsystem Titles are predefined and the titles shall not be changed. Each title shall be edited to enter the appropriate quantity as defined in the WBS. When there are Subsystems in the project which are not defined in the WBS, the designer shall create them using 90 to 99 Identification Code. Any SUBSYSTEM TITLE not used in the project shall be deleted. Subcontractors can be identified at the Subsystem Title level if all work performed in the subsystem is normally accomplished by one Contractor. (9) Assembly Category Titles. With the SUBSYSTEM TITLE highlighted press [Enter] to go to the Assembly Categories. The Assembly Category Titles are predefined and the titles shall not be changed. Each title shall be edited to enter the appropriate quantity as defined in the WBS. When there are Assembly categories in the project which are not defined in the WBS, the designer shall create them using 90 to 99 Identification Code. Any ASSEMBLY CATEGORY TITLE not used in this project shall be deleted. Sometimes subcontractors can not be identified at the Assembly Category title as all work performed in the category is normally not accomplished by one Contractor. For Example System 06 - Interior Finishes; Subsystem 01 - Wall Finishes; Assembly Category 03 - Gypsum Wallboard Finishes is normally installed by the GW Contractor and Assembly Category 04 - Tile & Terrazzo Wall Finishes is normally installed by the TE Contractor. (a) When Assemblies can be used multiple times within the project it is beneficial to the estimator to create the Assembly in the MODELs DATABASE rather than in the project. Assemblies from the MODELs DATABASE can be copied into the project as often as required.
18-28
The designer shall copy the Generic Models Database using Copy A Database from the SERVICES Menu to the same six characters as was used to name the project. Select this new Models Database and use it to create new assemblies. This new Models Database shall be submitted along with the project and labor rates database with each submittal. (10) Assembly Titles. The project template contains no Assembly Titles. The designer shall create the Assembly Titles based on the requirements of the project. The WBS provides a description of detailed items found in the assemblies. (a) CREATE an ASSEMBLY TITLE. Highlight the appropriate ASSEMBLY CATEGORY and from the FUNCTION MENU ADD/EDIT choose Add Subtitle or press [Shift][F3]. This will put you in the Add Subtitle Mode where you must enter a two character Assembly ID. This ID will normally be 01-99 but alpha characters may be used if required. You are now ready to look for an existing assembly or create a new assembly. (b) LOOKUP an ASSEMBLY. Press [F6] LOOKUP and choose Models to look into the Models Database for available Assemblies that may exist. If an appropriate Assembly is located in the Models Database, it can be copied into the project by highlighting the Assembly Title and pressing [F6] LOOKUP. You will be prompted to Confirm Lookup and by pressing [Enter] will accept what was looked up. You will then be prompted to OMIT Detail (Y/N)? N. with No being the default. Press [Enter] to receive detail. With Lookup completed you will have the Assembly title and detail items making up the Assembly in your project. Press [F10] to exit Add and press [Enter] to select the Assembly and view the Detail List screen. If the detail items have the letter P to the left of the quantity in the Quantity Field, the detail items have been linked to the Parent Quantity, the Assembly Title in this case. You will not be able to edit the Assembly Title and enter the correct assembly quantity which will then adjust the detail quantities. Note: Some of the assemblies are not linked and the assembly quantity will not adjust the detail. This is the case when there is not a direct correlation between assembly quantity and detail quantity. When this is the case there will not be a P in the detail quantity field and the detail quantity has to be entered at detail. Each Detail quantity will require editing. (c) CREATING an ASSEMBLY. If there is not an assembly already created that reflects the assembly needed for the project, then the designer shall create the assembly from detail items in the Unit Price Database. Locate the correct ASSEMBLY CATEGORY TITLE and Add Subtitle [Shift][F3]. This puts you in the Assembly Add Screen where you enter the Assembly ID, Title, Quantity and Assembly UOM. Reference WBS for UOMs. Press [f10] to save. Choose to work on the newly created Assembly Title by pressing [Shift][F5] ADD DETAIL. On the Cost Item Entry Screen the first two fields of the Project Sequence/Database ID requires no entry. Position the cursor to the third and press [F6] LOOKUP and choose to lookup into the Unit price Database [Shift][F6]. The software will place you at the top of the Unit Price Database. After selecting or marking the detail items needed in the assembly press [F6] and then confirm lookup. This will return all detailed items marked to your project. Press [F10] to exit Add Detail and save the items. Now check that all detail quantities are correct for your project by editing each item or, if appropriate, you can link the detail items to the Assembly quantity. Paragraph
18-29
18.12.(10) shall be repeated for all Facilities under Primary Facilities. Note: One must be located at DETAIL in the UPB when copying multiple detail items into the project, e.g. pressing [F6] to complete lookup. If [F6] is pressed while located at a title level, only the last marked item will be copied into the project. (11) Support Facilities Title. in most projects there is only one set of Support Facilities (all primary Facilities are constructed on the same site). When there is only one set of Support Facilities this title record needs only to be edited to identify the Prime Contractor. (12) Adding Additional Support Facilities. Occasionally there are projects that contain multiple Primary Facilities on more than one site. When this happens the Support Facilities Titles shall be duplicated by using [F2] ADD to create a second Support Facilities Title. Exit to save the title. Arrow to the original Support Facilities and press [Enter] to reach Facility level. Use the [shift][F9] to mark each Facility Title, [F10] up a level and arrow to the New Support Facilities Title. Now use [Shift] [F4] COPY to copy the facility titles. The second Support Facilities Title description shall be edited and the Prime Contractor shall be identified. This shall be repeated for each separate site location. 18.13 PRINT SELECTED REPORTS
The following procedures shall be required by the designer when creating the required printed reports for all submittals. See Exhibit 18-7 PRINT SUBMITTAL REPORTS CHECKLIST. (1) PACK A DATABASE. When making an estimate submittal to the Mobile District, the Project Database shall be packed to permanently erase deleted records from the project. From the SERVICES Menu choose Pack A Database while the project is highlighted in the Database Window. (2) SELECT REQUIRED REPORTS. The Mobile District Required Report settings shall be selected before executing the print command. From the REPORTS Menu choose Save/Load Report Settings. The first prompt asks if you want to Save Current Settings and the correct response is N for no. The second prompt asks if you want to Load Different Report Settings and the correct response is Y for yes. The Keyword Search Window now prompts for a Match ID. Type in the word SUBMITTAL and press [Enter] twice to activate the search. SUBMITTAL Mobile District Required Reports will be one of the choices presented. Select this choice by highlighting the cursor and pressing [Enter]. This will load the required reports settings. (3) Printer Setup. The printer shall be set up to print in Landscape Mode with 172 characters per line and 66 lines per page. (4) Activate Reports Generator. From the REPORTS Menu choose Print Selected Reports. Type in the estimate design status (Conceptual, Final, etc.) in the Report Title Field. (a) Send Reports to Printer. When sending the Reports directly to the printer as they are created enter PRN in the Printer device Field and press [OgDn] to activate writing the reports.
18-30
(b) Send Reports to File. If you want to send the Reports to a file and print at a later time or view the reports before printing, type in a filename.txt in the Printer Device Field and press [PgDn]. This writes the report to the file and the file can be printed later using the DOS Print command. (c) Viewing a Reports File. If the reports were written to a file, the file may be viewed using View Reports with Viewer from the REPORTS Menu. 18.14 SAVE TO COMPRESSED
After generating and printing the required submittal reports the database shall be SAVED TO COMPRESSED to diskette. (1) Compress Project Database. The project database shall always be SAVED TO COMPRESSED. A formatted diskette is required to complete the process. Highlight the project in the Database Window. From the SERVICES Menu choose SAVE TO COMPRESSED and enter the Project ID. When prompted to Save Related Databases along with Project? respond N for No. When the compression process is complete, save to the diskette. (2) Compress Assembly and/or Models Databases. If new items were created in the Models or Assembly Databases, those databases shall be Saved to Compressed along with the project. To Save to Compressed the Assembly or Models Database highlight either and use Save to Compressed. When prompted with the path of the databases press [Enter] and a list of available databases will be presented. Use the Up/Down arrow to locate the database(s) you want to compress and press the [Space Bar] to put a Check Mark by that database. When all databases have been marked press [Enter] to start the compression process. With the compression process complete save to diskette. The compressed Project is displayed with a check mark to the left of the ID in the Keep Database Window. Press [Enter] to keep the project and also save the compressed Assembly or Models to the same diskette. The next prompt will be Diskette is NOT BLANK, Delete ALL Non-Database Files?. Respond Y for yes. This will save both the project and other databases to, compressed diskette. (3) Compress Labor Database. compress along with the project. Labor rates shall be saved to
(4) Diskette Labels. The following information shall be recorded on all diskettes submitted to the Mobile District: Project Title: Location: Project Identification Code (6 Character Code) Design Status, e.g. (95% Cost Estimate Submittal Load from Compressed 1 of ?
18-31
FIELD INDIRECT COSTS 1. Supervisory and Administrative Personnel Field Project Manager General Superintendent Assistant Superintendents Construction Trade Superintendents Equipment Superintendent 2. Engineering Personnel Project Engineer Office Engineer Quality Control Engineers Surveyor and Surveymen Draftsmen 3. Office Staff Office Manager Payroll Clerk Clerk-Typists Purchasing Agent Janitor 4. Miscellaneous Staff Safety Engineer, Nurse, First-Aid Attendant Warehousemen Clerks Security Personnel 5. Job Expenses Office Facilities Shops, Warehouses, and Yards Laboratory and Testing Expense and Facilities Night Lighting Work Area Construction and Maintenance of Access and Haul Roads Office and Engineering Supplies and Equipment Water, Power, Telephone, Radios, Sanitary Facilities Project Sign and Bulletin Board Vehicles and Transportation Expenses Travel, Subsistence, Housing, etc. for Key Personnel Permits, Easements and Rights-of-Way Builders Risk Insurance Environmental Protection, Dust Control, and Restoration Progress Schedules and Reports Job Cleanup
EXHIBIT 18-1 1 OF 1
18-32
PROCEDURES: Based on specific project circumstances and considering the explanation of weights below, select appropriate weight values from the following table. For M-CACES GOLD estimates, enter the weights via Contractors' Overhead and Profit Entry Screens and the system will calculate profit. For manual estimates, multiply rates by weights. Add resulting values and round to the nearest tenth to obtain profit factor. FACTOR Degree of Risk Relative Difficulty of Work Size of Job Period of Performance Contractor's Investment Assistance by Government Subcontracting RATE 20 x 15 x 15 x 15 x 5 x 5 x 25 x WEIGHT(.03-.12) = = = = = = = TOTAL = VALUE _____ _____ _ _____ _____ _____ _____ _____
EXPLANATION OF WEIGHTS: Degree of Risk. Weight within range of .03 for slight risk to .12 for highest risk. Consider lump sum items riskier than unit price items. Also, consider nature and location of work, amount subcontracted, ratio of labor to total cost and whether work has already been accomplished. Relative Difficulty. Weight within range of .12 for most difficult and complex to .03 for simplest work. Size of Job. Size of Job $ 0 100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000 900,000 1,000,000 100,000 200,000 Select appropriate weight below. Factor $100,000 200,000 300,000 400,000 500,000 600,000 700,000 800.000 900,000 1,000,000 100,000 200,000 300,000 0.120 0.119 0.117 0.116 0.114 0.113 0.111 0.110 0.109 0.107 0.106 0.104 0.103 Size of Job 600,000 700,000 800,000 900,000 3,000,000 100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000 Factor 700,000 800,000 900,000 3,000,000 100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000 900,000 0.083 0.081 0.080 0.079 0.077 0.076 0.074 0.073 0.071 0.070 0.069 0.067 0.066
EXHIBIT 18-2 1 OF 2
18-33
Size of Job 300,000 400,000 500,000 600,000 700,000 800,000 900,000 2,000,000 100,000 200,000 300,000 400,000 500,000 400,000 500,000 600,000 700,000 800,000 900,000 2,000,000 100,000 200,000 300,000 400,000 500,000 600,000
Factor 0.101 0.100 0.099 0.097 0.096 0.094 0.093 0.091 0.090 0.089 0.087 0.086 0.084
Size of Job 900,000 4,000,000 100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000 900,000 5,000,000 OVER 4,000,000 100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000 900,000 5,000,000 10,000,000 10,000,000
Factor 0.064 0.063 0.061 0.060 0.059 0.057 0.056 0.054 0.053 0.051 0.050 0.040 0.030
Period of Performance. Factor OVER 23 TO 22 TO 21 TO 20 TO 19 TO 18 TO 17 TO 16 TO 15 TO 14 TO 13 TO 24 24 23 22 21 20 19 18 17 16 15 14 MONTHS MONTHS MONTHS MONTHS MONTHS MONTHS MONTHS MONTHS MONTHS MONTHS MONTHS MONTHS 0.120 0.116 0.112 0.109 0.105 0.101 0.098 0.094 0.090 0.086 0.082 0.079
Select appropriate weight below. Factor 12 11 10 9 8 7 6 5 4 3 2 1 TO TO TO TO TO TO TO TO TO TO TO TO 13 MONTHS 12 MONTHS 11 MONTHS 10 MONTHS 9 MONTHS 8 MONTHS 7 MONTHS 6 MONTHS 5 MONTHS 4 MONTHS 3 MONTHS 2 MONTHS UNDER 30 DAYS 0.075 0.071 0.068 0.064 0.060 0.056 0.052 0.049 0.045 0.041 0.037 0.034 0.030
Note: extension.
Contractor's Investment. Weight from .03 to .12 for below average to above average. Consider amount subcontracted, frequency of progress payments, whether there is pay item for mobilization, etc. Assistance by Government. Weight from .12 to .03 for average to above average. Consider use of Government facilities, expediting assistance, etc. Subcontracting. subcontracted. SUB Select weight below, based on % of work Factor 80% 70% 60% 50% 40% 30% 20% 10% 0% OR MORE 0.030 TO 80% 0.042 TO 70% 0.055 TO 60% 0.068 TO 50% 0.080 TO 40% 0.092 TO 30% 0.105 TO 20% 0.118 -- -0.120 EXHIBIT 18-2 2 OF 2
18-34
TECHNICAL QUALITY CONTROL CHECKLIST This checklist should serve as a tool to ensure that all areas of the cost estimate are properly prepared and adequately reviewed. GENERAL [ ] Has the reviewer been provided: [ [ [ [ ] ] ] ] A complete detailed cost estimate? All supporting backup? All applicable design documents (plans, specifications, design analysis, etc.)? Annotated Comments?
[ ] Has cost estimate been approved by the Chief, Cost Engineering Branch? [ ] Does the reviewer have a clear Definition of Scope? [ ] Has the estimator(s) visited the project site? [ ] Is the Sign-thru Cover Sheet for the Government Estimate that discloses the overall project cost estimate stamped FOR OFFICIAL USE ONLY? [ ] Has the Project Manager been notified of the estimated price verses the available funds? CONTRACT REQUIREMENTS (A-E/COST CONSULTANT ONLY) [ ] Has the Cost Estimate Submittal Checklist been provided? [ ] Has the Cost Estimate been submitted in the required number of copies, suitablybound, in landscape? [ ] Was AF Form 1178 provided (AF Projects Only)? [ ] Were the specified diskette(s) provided? [ ] Was all cost estimate supporting data provided?
EXHIBIT 18-3 1 OF 8
18-35
BID SCHEDULE [ ] Does the Bidding Schedule contain Bid items for the following work features, if applicable? [ ] Each Building to the 5 ft line? [ ] Major site features (e.g. Sanitary Sewer System, Exterior Electrical Distribution, Parking Lot, etc.)? [ ] Design Costs? [ ] Asbestos Abatement? [ ] Unit Cost Items (e.g. Rock Excavation, Unclassified Excavation, etc.)? [ ] Pre-Wired Work Stations? [ ] Project Manager/Customer Requested Items? [ ] Separately Funded Items (e.g. OMAR Equipment, etc.)? [ ] Additive Alternates? [ ] Options? FORMAT [ ] Has all required summaries been furnished? [ ] Has the required detail been furnished? [ ] Has the correct software been used? [ ] Were the correct Databases used in preparing the cost estimate? [ ] Has the MCACES Backup Reports for Wage rates and Construction Equipment been furnished? [ ] Were the MCACES Project and Contractor Settings furnished? [ ] Has all MCACES errors been cleared? [ ] Is the cost estimate in the required Work Breakdown Structure (WBS) to Level 4 (Subsystem)? [ ] Is the cost estimate structured according to the type contractor most likely to bid as prime?
EXHIBIT 18-3 2 OF 8
18-36
[ ] Has a sufficient number of subcontractors been developed for the project? [ ] Is a majority of the work selected to be done by the prime contractor or subcontractor(s) according to normal construction practice? [ ] Does the cost estimate include escalation, construction contingency and SIOH? [ ] Is the cost estimate so structured to be directly comparable to the project Bid Schedule? [ ] Is the Scope-Of-Work adequately defined in the Project Notes? [ ] Can the cost estimate be compared to the 1391? [ ] Is the cost estimate within the Construction Cost Limitation (CCL)? [ ] If the cost estimate is more than the CCL, have Additive Alternates or Options been identified that bring the Base Bid within the CCL? [ ] Have all amendments been acknowledged in the cost estimate? [ ] Has the cost estimate been compared to the previous cost estimate? [ ] If the cost estimate has changed more than 5% (+ or -) from the previous cost estimate, has reasons why been documented? [ ] Have all assumptions been documented in the cost estimate? [ ] Are all detail tasks in the cost estimate sufficiently described? [ ] Have specialty construction tasks (e.g. scaffolding, noise & dust control, phasing, etc.) been included in the cost estimate? [ ] Are Units of Measure proper? MAGNITUDE OF DETAIL [ ] Is the Level of detail commensurate with detail available from the design documents? [ ] Does the cost estimate include all design amendments?
EXHIBIT 18-3 3 OF 8
18-37
[ ] Have MCACES task overrides been sufficiently utilized? [ ] Does the cost estimate contain any unsupported lump sums? BACKUP [ ] Has all Backup (Quantity Takeoff, Quantity Derivations and Quotations) been furnished? [ ] Is all Backup traceable to the line item task in the cost estimate that it supports? [ ] Is Backup clear and understandable? [ ] Was sufficient quotations furnished? [ ] Was Backup current? [ ] Do quantities appear to be reasonable? [ ] Is Quantity Takeoff sufficient? [ ] Are Quantity Derivations clear and properly prepared? [ ] Did the reviewer spot check critical cost items and quantities? DIRECT COSTS - MATERIAL [ ] Are all major material items supported by a current quotation? [ ] Does quotation used include all applicable costs (e.g. manufacturer/supplier, location, person contacted, telephone number, date, freight to job site, etc.)? [ ] Is Sales Tax in the cost estimate? [ ] Is Sales tax shown correctly for project area?
EXHIBIT 18-3 4 OF 8
18-38
DIRECT COST - LABOR [ ] Have the wage rates been compared to the Davis-Bacon minimum wage rates? [ ] Does the wage rates reflect the local prevailing wage rates? [ ] Does the total wage rate shown include basic wage rate, fringes, OT, payroll taxes & insurance, etc.? [ ] Do the labor productivities used consider project conditions, labor availability, market conditions, etc.? DIRECT COST - CONSTRUCTION EQUIPMENT [ ] Has Construction Equipment Cost for major items been included in the cost estimate? [ ] Has small tools cost been included in the cost estimate? [ ] Has any construction equipment been included using rental rates? SUBCONTRACTED WORK [ ] Has subcontractor work been included in the cost estimate? [ ] Is all major subcontractor work detailed? Note: Minor work maybe unit priced. [ ] Does the project contain any work that is normally done by a 2nd Tier Subcontractor Work (e.g. Controls, Test & Balance, Insulation, etc.)? [ ] Were subcontractor quotes obtained to verify the reasonableness of the of the estimate for the subcontractor work? [ ] Were subcontractor markups reasonable?
EXHIBIT 18-3 5 OF 8
18-39
PRIME CONTRACTOR OVERHEAD [ ] Is all Prime Contractor Field Overhead detailed? [ ] Has the Prime Contractor Field overhead been prorated to all Bid Items proportionally to the direct costs? [ ] Have those items in the specification Special Clauses that are normally considered Field Overhead Items been incorporated into the cost estimate? [ ] Is the Prime Contractor Field Overhead reasonable? [ ] Has Mobilization/Demobilization costs been included in the cost estimate? [ ] Do overhead salaries shown include an allowance for payroll taxes & insurance? [ ] Are all overhead fixed costs included in the Base bid? [ ] Is Prime Contractor Home Office Expense included in the cost estimate? [ ] Is the Prime Contractor Home Office Expense reasonable? PROFIT [ ] Was Prime Contractor Profit included in the cost estimate? [ ] Was Profit for the Prime Contractor determined using the Weighted Guideline Method? [ ] Were the fixed cost (Size of Job, Period of Performance, Amount of Subcontracting) portion of the Weighted Guideline Method done correctly? [ ] Were the judgmental factors (Degree of risk, Relative Difficulty of Work, Contractors Investment, Assistance by Government) reasonable? BONDS [ ] Has Bond been included on the entire contract amount? [ ] Has Bond cost been calculated? [ ] Is Bond cost reasonable?
EXHIBIT 18-3 6 OF 8
18-40
COST ESCALATION [ ] Was Cost Escalation included in the cost estimate? [ ] Were all construction costs escalated to the Midpoint of Construction? Note: Army - Escalate from Midpoint of Estimate to Midpoint of Construction, AF - Escalate from Date of Submittal to Midpoint of Construction. [ ] Have indices and dates been shown? CONSTRUCTION CONTINGENCY [ ] Was a Construction Contingency percentage shown in the cost estimate? [ ] Is the percentage correct? SUPERVISION & ADMINISTRATION COST [ ] Was a SIOH or S&A percentage shown in the cost estimate? [ ] Is the percentage correct? MODIFICATIONS [ ] Has field office/cost estimator discussion been held? [ ] Has adequate information been received to reflect actual contractor rates? [ ] Has the original scope and changed scope been clearly defined? [ ] Is the net change in scope presented clearly? [ ] Does the estimate include costs and time for the impact on the unchanged work? [ ] Were current, actual labor rates utilized? [ ] Is backup and support for the estimate pricing available?
EXHIBIT 18-3 7 OF 8
18-41
DREDGING [ ] Was CEDEP used to prepare the cost estimate? [ ] Does the narrative document the decisions and selections made within CEDEP? [ ] Has effective working time been calculated considering lost time, weather delays, etc.? [ ] Have estimate results been compared against historic information and reconciled if necessary? [ ] Has the estimate been compared against data from similar projects? [ ] Have production rates been calculated considering pumping rate, travel time, line size, navigational delays, etc.? [ ] Have environmental requirements (beach and offshore) been included? [ ] Does the estimate reflect correct environmental windows for the project area?
EXHIBIT 18-3 8 OF 8
18-42
FUNCTION HELP ADD TITLES EDIT DETAIL LOOKUP NOTES SELECT MENU EXIT
Name : (32 Characters) LAST REPRICE REFERENCES Unit Price Database : (6 Characters) Crew Database : (6 Characters) Labor Database : (6 Characters) Equipment Database : (6 Characters) Measurement System : Original Currency Symbol : $ Currency Description : Dollars Units for Store/Display : O-Ones Units per U.S. Dollar : 1.0000
COMPUTATION CURRENCY
Note: The (Database ID) will show up on the 2nd line of the title on every page of the cost estimate. The (Name) will show up on the 1st line [Project : (Name - Proj Database Edit Screen)] on the REPORT TITLE PAGE.
EXHIBIT 18-4 1 OF 9
18-43
PROJECT COLUMNS
Estimate Type : A-Crews with Auto Reprice
FUNCTION HELP ADD TITLES EDIT DETAIL LOOKUP NOTES SELECT MENU EXIT
PROJECT DIRECT COST COLUMNS Col Type H L E M X Rep Width 8 10 10 10 0 Title MANHOURS LABOR EQUIPMENT MATERIAL (Unused) PROJECT INDIRECT COST COLUMNS Col Type O U P B X Rep Width 12 12 12 12 0 Title FIELD OH HOME OFC PROFIT BOND (Unused) PROJECT OWNER COST COLUMNS Col Type E C U X X Rep Width 12 12 12 0 0 Title ESCALATN CONTGENCY SIOH (Unused) (Unused)
PROJECT BREAKDOWN
FUNCTION HELP ADD TITLES EDIT DETAIL LOOKUP NOTES SELECT MENU EXIT
ID Level Level Level Level Level Level 1 2 3 4 5 6 ID ID ID ID ID ID Length 2 2 2 2 2 2 Trail Sep . . . . . . Level 2nd View Title Order Scope Bid Item System Subsystem Assm Cat Assembly 0 0 0 0 0 0
EXHIBIT 18-4 2 OF 9
18-44
FUNCTION HELP ADD TITLES EDIT DETAIL LOOKUP NOTES SELECT MENU EXIT
Col Type D C P X X Rep Width 12 12 12 0 0 Title DIRECT CONTRACT PROJECT (Unused) (Unused) Shadow x x x x x
FUNCTION HELP ADD TITLES EDIT DETAIL LOOKUP NOTES SELECT MENU EXIT
Page Break Levels : 2 Table of Contents Levels : 3 0 1 2 3 4 5 6 7 ROW OPTIONS Print Titles at Levels : Y Y Y Y Y Y Print Totals at Levels : Y Y Y N N N Print Notes at Levels : Y Y Y Y Y Y Y Y Print Unit Cost Row : Y Print Page Footer : Y Show Cost Codes : Y COLUMN OPTIONS Print Crew ID : Y Crew Output : Y Unit Cost : Y UPB TITLES No. of Levels to Print : 0 Bracket Titles With : N N Include Title Notes : N
EXHIBIT 18-4 3 OF 9
18-45
EXHIBIT 18-4 4 OF 9
18-46
PROJECT NOTES
FUNCTION HELP ADD TITLES EDIT DETAIL LOOKUP NOTES SELECT MENU EXIT
(Scope-of-Work of the Project) Note: At the RTA Stage, the Scope-of-Work should be obtained from Section 00100 of the Specifications
EXHIBIT 18-4 5 OF 9
18-47
FUNCTION HELP ADD TITLES EDIT DETAIL LOOKUP NOTES SELECT MENU EXIT
Report Title : (48 Characters) (% Design Status or Sol No w/Amend Print Device : (48 Characters) Printer Setup : (26 Characters)
Note: The Report Title will show up on the 3rd line of the title on every page of the cost estimate. EDIT PERMISSION SETTINGS ADMIN
ADMINISTRATOR SETTINGS
DATABASE EDIT-ACCESS
FUNCTION HELP ADD TITLES EDIT DETAIL LOOKUP NOTES SELECT MENU EXIT
PROJECT PERMISSIONS
Models Database : No Assemblies Database : No Unit Price Database : No Crews Database : No Labor Rates Database : Yes Equipment Rates Database : No Project Structure Access : No Allow Cost Overrides : Yes Allow Report Format Edit : No
AUXILIARY PROGRAMS Users File Viewer : C:\GOLD\CG_VIEWR.COM Communications : DIGITIZER SELECTION : A-None
EXHIBIT 18-4 6 OF 9
18-48
EXHIBIT 18-4 7 OF 9
18-49
EDIT OWNER
FUNCTION HELP ADD TITLES EDIT DETAIL LOOKUP NOTES SELECT MENU EXIT
Escalation Start Date/Index : 00/00 Escalation End Date/Index : 00/00 Contingency Note(s) No. :
0.000 0.000
This function is used to add or change Owner Cost information for a Project Database. The Edit Owner option is only available from title entry screens at the lowest title level and at the default Owner Cost Level designated on the Set Breakdown Structure Screen. Cost Method: This code specifies the method of figuring the indicated Owner Cost. Valid codes are: 0 - Set at Owner Level. Automatically entered by the program if the Owner Cost is set at a higher title level. P - GOLD calculates the cost by multiplying the percentage entered in the field below times the running total. The running total is the total of field below times the running total. The running total is the total of Project Direct and Indirect Costs plus the Owner Costs in any columns to the left of the present column. D - GOLD calculates the cost by multiplying the percentage entered in the field below times the total of the Project Direct and Indirect Costs only. Other Owner Costs are excluded. A - GOLD adds the amount you enter below as this Owner Cost. Code A can only be used at the default Owner Cost Level. C - GOLD computes the cost based on an escalation factor as defined in the Escalation fields below. Used only for the predefined Escalation column type.
EXHIBIT 18-4 8 OF 9
18-50
PRIME CONTRACTOR
FUNCTION HELP ADD TITLES EDIT DETAIL LOOKUP NOTES SELECT MENU EXIT
PROFIT WEIGHTED GUIDELINES Risk : 0.000 x 20 = 0.00% Diff : 0.000 x 15 = 0.00% Size : 0.000 x 15 = 0.00% Period : 0.000 x 15 = 0.00% Invest : 0.000 x 5 = 0.00% Assist : 0.000 x 5 = 0.00% Subcon : 0.000 x 5 = 0.00% TOTAL 100 0.00%
OVERHEAD 0.00% 0
PROFIT 0.00% 0
Bond Class : B
EXHIBIT 18-4 9 OF 9
18-51
[ ] Project Databases must have the identical layout to Merge Correctly. [ ] The Prime Cost Engineer created the agreed upon total project layout as determined in the MCACES GOLD user Manual. [ ] Copy this newly created project layout to Project databases for each of the Cost Engineering disciplines that will be preparing their cost data separately. Each of these Project Databases are exactly the same at this point. [ ] Each Cost Engineering discipline (including the Prime) shall edit their individual project Database and DELETE and PACK all System, Titles that are not applicable to their discipline. [ ] Each Cost Engineering discipline (including the Prime) shall complete the quantity take-off following the same format that is in their Project Database. [ ] After each discipline has completed their project and BEFORE merging, each project should be printed. Choose Print Selected Reports from the REPORTS Menu and print the individual project to be sure no database is corrupted and all errors have been corrected. You can send these reports to a file instead of the printer. [ ] PACK the Project Database one final time before Merging. [ ] The Prime Cost Engineer will collect the individual projects for merging into the Prime project. Make sure there is adequate hard disk space for EXTRACTING and MERGING project. [ ] MAKE DUPLICATE COPIES of all Project Databases before beginning the EXTRACTING/MERGING process. [ ] Carefully read the Merge and Extract functions in the MCACES GOLD User Manual. [ ] Practice Extracting and Merging on small project databases to insure you understand the complete process. [ ] Select the project Database to be Extracted and press (Enter) to open up the project.
EXHIBIT 18-5 1 OF 2
18-52
[ ] Using (Shift) (F9) or Mark from the MARK Menu to mark Titles to be Extracted. Titles should be marked at the highest level applicable for the information to be Extracted. [ ] From the MARKS Menu select Extract To....... or press (Alt) (X) to begin the Extract function. This will create an identical database of the marked items in a unique filename. Write down the filename for later use. [ ] Now select the Project Database where the extracted data is to be merged. Press (Enter) to open the database and choose Merge From...... on the MARK Menu or press (Alt)(E). You will now be prompted to enter the path and filename you Extracted To above. [ ] Examine the project to confirm that everything was merged properly.
EXHIBIT 18-5 2 OF 2
18-53
[ ] The correct databases (Models, Assemblies, Unit Prices, Crews, Labor Rates, Equipment Rates) are present in the Database Window. [ ] The correct WBS Project Template has been selected. [ ] The Project Template has been copied to new six character ID for this project. [ ] The New Project has now been selected, and name of project edited. [ ] The Report Title Page has been edited for this project. [ ] The Project Information Record has been edited. [ ] Prime and subcontractors have been edited. [ ] The correct number of Facilities have been created. [ ] The required Assembly Titles for all Primary and Support Facilities have been created and detailed items entered into the Assemblies. [ ] All System, Subsystem, and Assembly Category Titles not required in this project have been deleted and the Project has been Packed. [ ] All subcontractors not required in this project have been deleted and the Project has been Packed.
EXHIBIT 18-6 1 OF 1
18-54
[ ] All cost and pricing is entered based on the Current Design Status. [ ] Costs for Systems and Subsystems not shown in the design have been accounted for in the estimate. [ ] Titles (Facility, System, Subsystem, etc.) at all levels not applicable to this project have been deleted. [ ] Prime Contractors Field Overhead has been itemized to reflect project requirements. [ ] Prime contractors Bond has been set to calculate a Class B Bond. [ ] Prime Profit has been calculated by the Weighted guideline Method and each factor assigned has been explained in the NOTES (F7) for the Prime Contractor. [ ] Subcontractors Overhead has been set as a percentage. [ ] Subcontractors Profit has been set as a percentage. [ ] Prime and Subcontractors have been assigned at the appropriate locations within the project. [ ] Any Subcontractors not applicable to this project have been deleted. [ ] Sales Tax has been entered. [ ] Escalations, Construction Contingency and SIOH have been set. [ ] The project has been packed using Pack a Database from the SERVICES Menu. [ ] The Mobile District Required Reports settings have been selected using Save/Load Report Settings from the REPORTS Menu, paragraph 6.b. [ ] The printer has been set to print Landscape with 172 characters per line and 66 lines per page. [ ] Estimate Status (35%, 60%, etc.) has been entered in the Report Title field or the Print Selected Reports Window.
EXHIBIT 18-7 1 OF 2
18-55
[ ] Two hard copies of the Submittal Estimate have been made. [ ] The Project Database & Labor Rates Database and any other database that the A-E added information to (Models, Assemblies, Crews, Equipment, etc.) have been Saved to Compressed to diskette from the SERVICES Menu.
EXHIBIT 18-7 2 OF 2
18-56
CONTINGENCIES AND SUPERVISION & ADMINISTRATION (USE THESE VALUES UNLESS DIRECTED OTHERWISE) ARMY CONTINGENCIES NEW WORK ALTERATIONS & MODERNIZATION ADDITIONS/ALTERATIONS AND 10% IF ALTERATION IS LARGEST S&A (SIOH) NEW WORK ALTERATIONS & MODERNIZATION INSTALLATION SUPPORT 6.0% (CONUS) 6.0% 6.5% (OCONUS) 6.0% (CONUS) 6.0% 6.5% (OCONUS) 8.0% (CONUS) N/A 8.5% (OCONUS) 5% 10% 10% 5% 10% 5% - IF ADD IS LARGEST AIR FORCE
EXHIBIT 18-8 1 OF 1
18-57
19.1
GENERAL 19.1.1
Scope
19.2 19.3
APPLICABLE PUBLICATIONS PROJECT DEFINITION (10-15%) 19.3.1 General Considerations 19.3.2 Project Definition Narrative CONCEPT DESIGN (30-35%) 19.4.1 General Considerations 19.4.2 Concept Design Analysis INTERIM DESIGN (50-60%) 19.5.1 Interim Design Analysis FINAL DESIGN (Unreviewed 100%) 19.6.1 Final Design Analysis 19.6.2 Specifications READY-TO-ADVERTISE (100%) RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS 19.8.1 19.8.2 Mandatory Requirements Specific Requirements
19.4
19.5
19.6
19.7 19.8
19.9
TECHNICAL REQUIREMENTS 19.9.1 General Considerations 19.9.2 Site 19.9.3 Architectural 19.9.4 Structural 19.9.5 Mechanical 19.9.6 Electrical
19-1
19.1
GENERAL Scope
19.1.1
This chapter provides guidance for preparation and development of projects in accordance with the Department of Defense Antiterrorism/Force Protection requirements. Specific design submittal requirements in this chapter supplement the requirements in Chapter 1, titled GENERAL INSTRUCTIONS. All required documents, including drawings and design analysis, shall be in accordance with Chapter 2, titled PRESENTATION OF DATA. 19.2 APPLICABLE PUBLICATIONS
The publications listed below, but referred to thereafter by basic designation only, form a part of this Manual. These publications are supplemented by the UFGS Guide Specifications to form design criteria. Unified Facilities Criteria (UFC): UFC 1-200-01 02 UFC 4-010-01 DoD Minimum Antiterrorism Standards for Buildings, 08 Oct 03 DoD Minimum Antiterrorism Standoff Distances for Buildings; (For Official Use Only (FOUO)), 08 Oct 03 Design: General Building Requirements, 31 Jul
UFC 4-010-02
UFGS Guide Specifications/ Mobile District Guide Specifications: Specifications are updated on a regular basis. Instructions on Retrieving UFGS Specifications are covered in Chapter 3, SPECIFICATIONS. 19.3 PROJECT DEFINITION (10-15%) General Considerations
19.3.1
Antiterrorism/force protection design shall be integrated into the overall facility design from the beginning of the project. At the Project Definition phase the designer shall investigate the antiterrorism/force protection measures required for the project. Designer shall determine if the setback distances required for conventional construction can be provided within the project constraints or if further analysis and building hardening is likely to be required. In addition, any building elements requiring special design, such as mail rooms, equipment enclosures, progressive collapse, etc. shall be noted for use in preparing the cost estimate.
19-2
19.3.2
The Project Definition narrative shall include, but not be limited to, the following items as applicable: a. List all antiterrorism/force protection references used in the Project Definition design including Government design documents, industry standards, and criteria given to the designer at the charrette or predesign meeting. b. List the building category, the location of the facility within a controlled perimeter, and the level of protection required. c. Note the setback distances to be provided and describe the proposed construction to meet antiterrorism/force protection requirements. d. Describe any progressive collapse requirements and their impact on the structural system provided. Discuss how continuity, redundancy, or energy dissipating capacity will be provided in the structural system. e. List any building elements such as mail rooms, equipment enclosures, etc. requiring special design to meet antiterrorism/force protection requirements and describe the proposed design solution. These items shall be noted for use in preparing the cost estimate. 19.4 CONCEPT DESIGN (30-35%) General Considerations
19.4.1
The antiterrorism/force protection design shall be included in the drawings, calculations, and design analysis of each discipline involved. Antiterrorism/force protection design shall be to the concept design level required by the applicable design discipline, as stated in this document. 19.4.2 Concept Design Analysis
The Concept Design analysis shall include a separate section on antiterrorism/force protection design. This section shall include but not be limited to the following items as applicable: a. List all antiterrorism/force protection references used in the Project Definition design including Government design documents, industry standards, and criteria given to the designer at the charrette or predesign meeting. b. List the building category, the location of the facility within a controlled perimeter, and the level of protection required. c. Note the setback distances to be provided and describe the proposed construction to meet antiterrorism/force protection requirements. d. Describe any progressive collapse requirements and their impact on the structural system provided. Discuss how continuity,
19-3
redundancy, or energy dissipating capacity will be provided in the structural system. The discussion of the design solution shall reflect the level of a concept design, as described in this document for the structural discipline. e. List any building elements such as mail rooms, equipment enclosures, etc. requiring special design to meet antiterrorism/force protection requirements and describe the proposed design solution. The proposed design solution shall be developed to the level of a concept design, as described in this document for the discipline involved. 19.5 INTERIM DESIGN (50-60%)
The antiterrorism/force protection design shall be included in the drawings, calculations, and design analysis of each discipline involved. Antiterrorism/force protection design shall be to the interim design level required by the applicable design discipline, as stated in this document. In addition, the designer shall incorporate or answer all comments received from the COE and customer concerning the Concept submittal. 19.5.1 Interim Design Analysis
The Interim Design Analysis shall include a separate section on antiterrorism/force protection design. The Interim Design Analysis shall include all of the information required in the Concept submittal in its interim form and incorporate or answer all comments received from the COE or the customer. 19.6 FINAL DESIGN (Unreviewed 100%)
The antiterrorism/force protection design shall be included in the drawings, calculations, and design analysis of each discipline involved. Antiterrorism/force protection design shall be to the final design level required by the applicable design discipline, as stated in this document. In addition, the designer shall incorporate or answer all comments received from the COE and the customer concerning Interim submittal. 19.6.1 Final Design Analysis
The Final Design Analysis shall include a separate section on antiterrorism/force protection design. The Final Design analysis shall include all of the information required in the Interim submittal in its final form and incorporate or answer all comments received from the COE or the customer. 19.6.2 Specifications
Marked-up draft specifications shall be submitted in accordance with Chapter 3, titled SPECIFICATIONS. Specifications used shall be those acquired subsequent to the Interim submittal. Specifications shall include all antiterrorism/force protection requirements such as loadings for window and door frames and special glazing.
19-4
19.7
READY-TO-ADVERTISE (100%)
The comments generated concerning the Final submittal shall be incorporated in the design documents before they are submitted as "Ready-to-Advertise." 19.8 RFP (REQUEST FOR PROPOSAL) DEVELOPMENT REQUIREMENTS
TI 800-3 includes guidance to allow for three different levels of RFP development. These are Nominal, Partial, and Full project criteria development. This section provides both mandatory and specific criteria requirements that shall be used, in conjunction with TI 800-03 in the development of Mobile District RFPs. 19.8.1 Mandatory Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project regardless of the level of RFP development: a. List all Antiterrorism/force protection references to be used in the design including Government design documents, industry standards, and criteria given to the designer at the charrette or predesign meeting. b. List the building category, the location of the facility within a controlled perimeter, and the level of protection required. c. d. Note the setback distances to be provided. Describe any progressive collapse requirements.
e. List any building elements such as mail rooms, equipment enclosures, etc. requiring special design to meet antiterrorism/force protection requirements. 19.8.2 Specific Requirements
The following are requirements and criteria that shall be included (as applicable) in the RFP for every project for the indicated level of RFP development. Where the requirements stated in this document differ from the ones in TI 800-03, this document will take precedence: a. Nominal Project Criteria:
1. The design-build contractor will be responsible for developing a design proposal that may be impacted by antiterrorism/ force protection standards. Sufficient information must be provided to support the proposal without providing information from UFC 4-010-02 (FOUO). Provide specific design loads or specify the required standoff distance and provide candidate structural systems that allow for mitigation of the applicable explosive if the standoff is less than the minimum. If the standoff distances will allow the use of conventional construction without analysis of blast effects, this shall be stated.
19-5
b.
1. The Partial Project Criteria shall include all of the information required in the Nominal Project Criteria. c. Full Project Criteria:
1. Final drawings, calculations, and design analysis (See description above under 19.6. FINAL DESIGN.) 2. Final Specifications (See description above under 19.6.2 FINAL DESIGN.) NOTE: Check individual contract scope of work for level of RFP development and for specific design level requirements. 19.9 TECHNICAL REQUIREMENTS General Considerations
19.9.1
Project design shall incorporate mandatory DoD standards for new buildings and for existing inhabited buildings, when triggered, in accordance with UFC 4-010-01. To the extent possible within the project constraints, the Recommended Additional Antiterrorism Measures for New and Existing Buildings UFC 4-010-01, Appendix C, shall also be incorporated. Antiterrorism/force protection design shall be integrated into the overall facility design from the beginning of the project through coordination of all disciplines. Antiterrorism/force protection requirements shall be met in the most effective and economical method. These methods include maximizing standoff distances, preventing building collapse, minimizing hazardous flying debris, providing effective building layout, limiting airborne contamination, providing mass notification, and facilitating future upgrades. Antiterrorism/force protection requirements shall be coordinated with all other applicable DoD building and design criteria and policies. Where other criteria mandates more stringent requirements, the provisions of those criteria will be followed. 19.9.2 Site
a. The civil/site design shall incorporate applicable requirements for minimum standards for force protection from UFC 4-01001. Specific instructions for the minimum setback distances that apply to all new and existing (when triggered) facilities are shown in Appendix "B", Table B-1 and Figure B-1 in the UFC. b. Additional antiterrorism measures that significantly enhance site security listed in Appendix "C" shall be incorporated into the site design for every new and existing (when triggered) facility to the maximum extent possible. 19.9.3 Architectural
The following are requirements that shall be included in the architectural design for every new and existing, when triggered, inhabited building:
19-6
a. Glazing and window, skylight, and glazed door frames shall be designed in accordance with the special provisions of UFC 4-010-10, Appendix B, paragraph 3.1. b. The main entrance to a new inhabited building shall not face an installation perimeter of other uncontrolled vantage point with direct line of sight to the entrance. If the main entrance to an existing inhabited building faces the installation perimeter, the main entrance shall be moved or screened to block the line of sight. c. All exterior doors into inhabited areas shall open outwards.
d. Rooms to which mail is delivered or in which mail is handled in inhabited buildings shall be located on the perimeter of the building. Mailroom shall be as far as possible from heavily populated areas of the building and critical infrastructure, and shall be sealed to limit migration into building of airborne chemical, biological and radiological agents. e. External roof access shall not be used on new buildings. External roof access for existing buildings, shall be eliminated or secured with locked cages or similar mechanisms. 19.9.4 Structural
a. The structural design shall incorporate applicable requirements for minimum standards for force protection from UFC 4-01001. Conventional construction may be used for the buildings without a specific analysis of blast effects, if the specified minimum setback distances are provided. If the setback distances are not provided, an engineer experienced in blast-resistant design shall analyze the building and apply building hardening as necessary to provide an equivalent level of protection from the effects of the applicable explosives weights at the achievable standoff distances. b. For all buildings with three stories or more, progressive collapse shall be evaluated in accordance with UFC 4-010-01 using the guidance found in the Draft Department of Defense Minimum Antiterrorism Standards for Buildings, Guidance on Structural Requirements, dated 30 September 2003, and the latest Response Limits Summary Sheet. c. All building additions shall be designed to be structurally isolated from the existing building. All uninhabited areas of buildings shall be designed to be structurally independent from the inhabited areas or verify through analysis that collapse of the uninhabited portions of the building will not cause collapse of the inhabited areas of the building. As an alternative, design the uninhabited areas of the building to meet the requirements for an inhabited building. d. Building overhangs with inhabited space above them shall not be used. e. All exterior masonry walls shall provide a minimum of 0.05 percent vertical reinforcement with a maximum spacing of 48 inches on center.
19-7
f. Window and skylight frames, and glazed door frames shall be designed in accordance with the special provisions of UFC 4-010-10, Appendix B, paragraph 3.1. g. Supports for all overhead mounted architectural features and utilities or other fixtures weighing 31 pounds or more shall be designed for a minimum of 0.5 times the component weight in any direction and 1.5 times the component weight in the downward direction. 19.9.5 Mechanical
a. Outdoor air intakes must be at least 10 feet above the ground for new buildings and as close as possible to 10 feet above the ground for existing buildings. b. There must be an emergency shutoff switch in the HVAC control system that can immediately shut down air distribution throughout the building. c. Chillers (and all major mechanical equipment) should be located outside the unobstructed space, at least 33 feet from the building. If they are located within the unobstructed spaces and have an enclosure with more than 2 sides, the equipment shall be enclosed on all four sides and the top and shall be lockable. The top surface of the enclosure shall be visible to the casual observer. 19.9.6 Electrical
a. The electrical design shall incorporate applicable requirements for minimum standards for force protection from UFC 4-01001. Specific instructions for the location and protection of electrical equipment are shown in Appendix "B" to the UFC. It is not recommended that electrical equipment be located on the roof as allowed in Appendix "B".
19-8
20.1
20.2 20.3
SUBMITTAL REQUIREMENTS OFFICIAL WEB SITES FOR SDD 20.3.1 20.3.2 U.S. Army SDD Official Site U.S. Air Force SDD Official Site
20-1
20.1
GENERAL Scope
20.1.1
The objective of this chapter is to provide the most current web sites that link to Sustainable Design and Development (SDD)instructions. These web sites contain links to SDD rating systems, and rating tool (checklists). The official web sites for SDD are listed below. The project specific Scope of Work (SOW) issued by Mobile District and project specific design criteria will specify the rating system to use for the project and the level of SDD required. 20.2 Submittal Requirements
Submit the appropriate SDD rating tool (checklist) and narrative as part of the Design Analysis when SDD is required in the project specific SOW. The SDD checklist is to be completed to correspond to the design phase. For the RTA submittal, submit the completed SDD checklist and all supporting backup documentation along with the final plans and specifications. The SDD documentation may be submitted in either MS Excel or MS Word or a combination thereof. 20.3 OFFICIAL WEB SITE FOR SUSTAINABLE DESIGN AND DEVELOPMENT
20.3.1 Department of Army Office of Assistant Chief of Staff for Installation Management (OACSIM) http://www.hqda.army.mil/acsimweb/fd/linksSDD.htm
20.3.2 Under the Heading Documentation/References is the link to the SPiRiT rating Tool.
20.3.2 U. S. Air Force Center for Environmental Excellence (AFCEE) Sustainable Resource Menu http://www.afcee.brooks.af.mil/eq/programs/progpage.asp?PID=27
20.3.3 Under the Heading Sustainable Design Resource Menu is the link to the Auditing Checklist LEED Rating System Use this link to Register LEED projects.
20-2
21.1
21.2
DELIVERY OF ENGINEERED PRODUCTS 21.2.1 In-House Quality Management Process 21.2.2 A-E Quality Management Process QUALITY CONTROL PLAN QUALITY ASSURANCE PROCESS
21.3 21.4
21-1
21.1 GENERAL 21.1.1 Applicable Publications ER 1110-1-12 QUALITY MANAGEMENT 21.1.2 Goal The goal is to deliver quality engineering and design products in accordance with the applicable design standards and criteria, on schedule, and within the negotiated budget that meet all the prescribed requirements and expectations of our sponsors and customers. 21.1.3 Methods to obtain Goal This goal is obtained by implementing a Quality Management Process for each product. The Quality Management Process contains two major parts: Quality Control and Quality Assurance. 21.1.3.1 Quality Control Quality Control is the process used during development of products to ensure technical adequacy and conformance with applicable requirements and criteria. 21.1.3.2 Quality Assurance Quality Assurance is oversight of the Quality Control process to ensure its effectiveness in the preparation of required products. 21.2 DELIVERY OF ENGINEERED PRODUCTS Engineering Division delivers engineering and design products with inhouse technical personnel or by contracted private industry Architect Engineering firms. Each delivery method requires a different Quality Management Process. 21.2.1 In-House Quality Management Process The Government is responsible for both Quality Control and Quality Assurance of engineering and design products for In-House projects. 21.2.2 A-E Quality Management Process For A-E projects, the A-E is responsible for Quality Control and the Government is responsible for Quality Assurance. 21.3 QUALITY CONTROL PLAN
Quality Control begins with a Quality Control Plan. All engineering products require a Quality Control Plan whether done by In-House
21-2
Brief description of the project Criteria and references Critical design considerations and risks Management philosophy and approach Design team members, including design checkers and members of the Independent Technical Review Team Budget, schedule and milestones Verification of Government furnished information Coordination of plans and specs Design checklists Lesson learned checklists Independent technical review process Certification
A Quality Control Plan shall be prepared specifically for each product prior to beginning of product development and maintained as part of the product file. Sample Quality Control Plan (Appendix A) follows at the end of this Chapter. 21.4 QUALITY ASSURANCE PROCESSES Engineering Division puts into place processes that ensure the A-E is effectively developing a product that will give the customer the end product that meets the customers needs. The processes include technical review to ensure contract compliance, regular coordination with the A-E and conferences at scheduled milestones (35%, 60% and Final); Biddability, Constructability, Operating and Environmental (BCOE) review; Value Engineering review; and consultation with centers of expertise. 21.5 IMPLEMENTATION OF QUALITY MANAGEMENT PROCESSES Implementation of the Quality Management Process is the responsibility of the Government and when contracted, the A-E Firm. Engineering Division has Standard Operating procedures (SOPs) for implementing their own Quality Management Processes. The A-E firm is responsible for implementing their own processes to ensure the development of products that conform to applicable requirements and criteria. The Government will provide Quality Assurance or oversight of the A-Es Quality Control processes to ensure effectiveness of the A-E in preparation of required products.
21-3
APPENDIX A SAMPLE QUALITY CONTROL PLAN In-House Design Quality Control Plan
1. Purpose: The purpose of this document is to establish a Quality Control Plan (QCP) for accomplishing in-house engineering and design work for the subject facility. 2. Project Information: a. Project: (INPUT OFFICIAL PROJECT TITLE) b. Location: (INPUT PROJECT LOCATION) c. CADD ID: (INPUT CADD ID) d. Programmed amount: (INPUT PROGRAMMED AMOUNT) e. Design budget: (INPUT DESIGN BUDGET) 3. References: a. SAD Quality Management Plan. b. Mobile Plan. District Engineering and Design Quality Management
a. Design Team: The designers are responsible for the quality of their work and for the proper coordination of their work with the other disciplines. The design team is as follows: Project Manager: (INPUT NAMES/email) Project Engineer: Architect: Electrical: Electronics: Cathodic Prot: Interior Design: Mechanical: Utilities: Site: Landscaping Geotechnical Structural: Cost Estimator: (251) (251) (251) (251) (251) (251) (251) (251) (251) (251) (251) (251) (251) (251) 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX 69X-XXXX
b. Project Manager (PM): The PM is responsible for providing funds for adequate quality control and for including this Quality Control Plan (QCP) in the Project Management Plan (PMP) for the project.
21-4
c. Project Architect/Engineer (PAE): The PAE is responsible for writing the QCP, scheduling and documenting quality control milestones, and for insuring these events follow established procedures. The PAE will also lead QA conferences and insure design team and review teams comply with the QC Plan. d. Design Review Team (Senior Technical Leaders) (DRT): The DRT is responsible for providing the Independent Technical Review (ITR) and is comprised of the Senior Technical Leaders in each discipline of Engineering Division. The Senior Technical Leaders are as follows: (REVIEW AND EDIT AS REQUIRED) Bill Thomas (251) Don Smith (251) Billy Knapp (251) Larry Covert (251) Randy Goff (251) Joe Findley (251)
(1) Computer Aided Drafting and Design Software (CADD): This project will be designed utilizing AutoCADD 2002 Software. (2) Specification Software: This project will be designed utilizing Specsintact specification software. b. Estimating Tools:
Cost Estimating Software: This project will be estimated utilizing Micro Computer Aided Cost Estimating System (MCACES) Gold software. c. Management Tools:
(1) Dr Checks review comment management system. Dr. Checks software will be utilized on each project to track the comments and responses. (2) Engineering Divisions Project Design Schedules System (DSS). DSS software will be utilized on the project to track the schedule. (3) Engineering Divisions Project Design Budget and Preparation and Tracking System (BPTS): BPTS software will be utilized on the project to track the design budget. (4) Document Management Software: Projectwise will be utilized on this project to accurately manage the design drawing. Specintact will be needed to develop and manage the project specifications.
21-5
6.
Procedures:
a. Submittal Review: Each project is submitted to the User, the Installations Engineering Organization and the Major Command (MAJCOM) or Regional Installation Management Agency (IMA) at each submittal stage for formal review. Reviewer's comments are annotated and returned. This project will have the following submittals: 35%, 100% Un-reviewed Final and Ready-to-Advertise (RTA). Review comments from all reviewers will be input, annotated and managed using Dr. Checks software through a database maintained on the internet. All reviewers including the customer will utilize Dr. Checks for all submittals. b. Schedules: A schedule for the project will be input, maintained and tracked using Engineering Division's Project Design Schedule System software. Schedules will be monitored and discussed on a weekly basis in Engineering Division's Monday Morning Meetings. Refer to the attached Project Design Schedule. c. Design Budget: A budget for the project will be input, maintained and tracked using Engineering Division's Project Design Budget and Preparation and Tracking System (BPTS) software. Budgets will be monitored and discussed in the Districts Engineering Division's weekly management meeting. d. Document Management: Projectwise and Specintact will be utilized on this project to insure that the official working files for the plans and specifications are not duplicated. This insures that the latest version of the plans and specifications are edited and published. e. Mobile District Engineering Division Standard Operating Procedures (SOP): This project will utilize all of latest Engineering Division's SOP's. The SOP's will be discussed at the design kickoff meeting and at all major design review meetings. f. Quality Control Conference (QC): There will be a minimum of two QC Conferences held for each project. Each QC conference will include a formal, detailed drawing and specification review by the design team. g. Lessons Learned: Each discipline will check for compliance with the Mobile District's Lessons Learned database. Once in compliance, the Lessons Learned documentation will be signed by the PAE and presented to Construction Division along with the BCOE Certification for approval. h. Biddability, Constructability, Operability, and Environmental (BCOE) Certification: A BCOE review will be made at the 100% unreviewed final design stage by Construction Division. Comments will be input under a separate heading in Dr. Checks for accuracy of tracking. The BCOE certification of the design will be signed by both Engineering Division and Construction Division prior to contract bid opening. i. Customer Interaction: The customer (User, BCE and MAJOM) will be contacted on a weekly basis to make sure that there are no new developments in the project that effect the scope of work. Any changes
21-6
in the scope of work will be formally documented and routed through the PM to Engineering Division. Refer below for additional design funds request. j. Request for Additional Funds: In the event that the project increases in scope, a budget for the increased scope with cover letter will be sent to PM for approval. Approval and additional design funds will be obtained from PM before any additional work is performed. k. Lost Effort: In the event that the project has a change in scope that creates lost effort, an estimate of the lost effort with cover letter will be sent to PM for approval. Approval and additional design funds will be obtained from PM before any additional work is performed. Copy of revised Design Budget and Lost Effort report will be provided to Engineering Division.
21-7