Structure Erection Work Method Statement
Structure Erection Work Method Statement
Structure Erection Work Method Statement
METHOD STATEMENT FOR RECEIPT, HANDLING AND UNLOADING AND ERECTION OF STRUCTURE
LOCATION of work (as specific as possible): Niacinamide EXPANSION
DESCRIPTION of work (as specific as possible): The method statement covers the guideline for receipt, storage, handling, unloading,
shifting and erection of structure (column, beam, bracing etc.) at Niacinamide Expansion at Unit-1, Jubilant Project.
This method statement describes the work procedure to be followed for unloading, Shifting & erection of column, beam etc
(structure) at UNIT-1, Jubilant Project.
2. SCOPE:
o Farana-15T
o Crane-40 /80/100 MT
o D-shackle-
o Web Sling -
o 25 mm Rope (PP)/12 mm Wire rope sling
o Personal safety equipment’s-safety helmets, safety shoes, safety, cotton hand gloves, leather hand Gloves & work
related PPEs also Other tools & tackles for finishing purpose,
o Spirit level/Water level
o Spanner /Hammers attached with rope
o Grinder
o Measuring Tape
o Welding Machine
o Grinding Machine for Buffing.
5. UNLOADING CREW:
o Site In charge -
o Safety Officer -
o Foreman-
o Fitter –
o Rigger/ Helper-
o Welder –
o Grinder –
Ground Preparation:
o Check all the material as per BOQ, Packing list
o Physically check the material for any damage
o Bring all the material at location By farina /manually using
/nylon rope/wire sling to be ensured that no damage, any dent, bend & distortion etc .and
using 40/80/100 Mt crane , 80 FT Boom lift for height works
o Bring the particular column as per drawing and part mark to the location where it
is to be erected.
o Attach clips for eaves strut and girt with the main columns at ground only.
o Tie one end of all erection bracings with the column top.
o Erect the column on pedestal. Take care about threads of Foundation bolts while
Inserting base plate in to foundation bolt. There should not be damage to threads.
plate and top of R.C.C Column place the M.S. shim plates in single piece as much as
o After checking the verticality retightens the nut and place the erection bracings in placed.
o Verticality shall be checked by plumb bob & tightening of Foundation bolt shall be
Checked.
Note: - The crane should be released slowly only after placing the erection column (Guy Ropes) and
tightening of bolts
STEP-2
o Same procedure as in step-1 has to be followed for erecting the second adjacent
Column.
o Once placed the tie beam it should be tightened by using Nut Bolt
o If complete the 12 mtr level erection using more than 40/80/100 mt cap crane
o Note: -Same procedure as in step 1 and 2 has to be followed in opposite side for erection of
columns
and bracing
STEP-3
o Connect all the segments of one frame as per drawing or part marks at the
o Ground itself.
o All connections are field bolted, all bolts are high tensile.
o Install and tighten the Primary frame connections bolts, fastener shall be tightened
as required torque according torque chart as each grid Primary frame is assembled.
o Torque tightening for primary frames shall be checked for bolts at ground
STEP-4
o Install all roof bracings. The bracings should be tightened. Align the braced
o No further erection is to proceed until the above mentioned 3rd and 4th steps are
Completed. Crane has to be released only after the completion of step 3 and 4.
Step – 5
4.
o After alignment proceed for further erection as per drawing and details.
o Wherever the braced bay comes, the erection of temporary bracing shall follow
o After completing the erection of one module in length wise erection will proceed
o Align the complete column After inspection of level, alignment grouting will be
Carried out.
o NOTE- After completion of alignment, the gap between top of RCC pedestal and
bottom of base plate (if any) should be grouted by others using G P -2 (High
o Weight of Crane = 40 T
o Weight of Accessories (Counterweight) = 2 T
o Weight of Load = 4 T
o Weight of Rigging equipment=0.6T +
o Total Weight = 46.6 T+
o Weight on out riggers =46.6/4 = 11.65 T / out trigger
P= Force / Area = 11.65 T /6.25 M 2 = 1.864 T / Meter square
10. LOAD CHART FOR FARANA AND CRANE :
Farana Crane
What services will need to be ISOLATED...? (Electricity, Compressed Air, Hydraulics, Gravity, Springs, Other stored energy)
SERVICES TO BE ISOLATED: Not Applicable
if
Safety Reflective Eye Face Ear Protective Respiratory Respiratory Personal fall Protective
required Helmet
footwear vest protection protection) protection gloves protection protection arrest system clothing
√ √ √ ✓ √ √ √
If using gloves or respiratory protection cotton mask or if any other, indicate type: Safety Harness
No unauthorized entry, close supervisor and ensure use of PPEs and barricading with Signage boards.
Prepared Approved By
By Review By
JUBLIANT
Signature
Name
Date