0% found this document useful (0 votes)
136 views4 pages

Fencing

Bill of Quantities for Fencing

Uploaded by

bola.itsekor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
136 views4 pages

Fencing

Bill of Quantities for Fencing

Uploaded by

bola.itsekor
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 4

COST ESTIMATES FOR fencing of 20 polts of land

S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT

FENCING
General Description
This Cost Estimate will capture the fence work around the site of
20plots of land

EXCAVATION AND EARTHWORKS


Excavate trench for foundation start up starting from average
ground level.(3.6m/10ft per partition WITH ACUAL DEPT OF 300 Parts. 2,500 750,000.00
750mm)

Ditto, for column base 150 Nr 2,000 300,000.00

Level and compact bottom of trench to make good to receive


Sum 200,000.00
concrete for foundation footing.

FOUNDATION CONCRETE
Mix and place concrete 1:3:6-19mm aggregate as concrete for
foundation footing 100mm thick against trench
CEMENT (50 kg bags) 300 Bags 8,000 2,400,000.00

SAND (using 7ton tipper) 7 Trip 65,000 455,000.00

GRAVEL (using 20tons tipper - Mack Load) 4 Trip 550,000 2,200,000.00

LABOUR
For mixing of concrete 300 Bags 2,500 750,000.00

For tapping by mensons 30 Men 8,000 240,000.00

BLOCKWORK
Vibrated hollow sandcrete Block laid in stretcher bond and fix with
cement and sand (1:6) - 12 courses on top of foundation footing
inclusive of piers and insertions along fence work
9'' BLOCKS 28,550 Nr 550 15,702,500.00

CEMENT (50 kg bags) 400 Bags 8,000 3,200,000.00

SAND (using 7ton tipper) 40 Trip 65,000 2,600,000.00

For mixing & fixing (MENSON AND HELPER) 28,550 Nr 150 4,282,500.00

Reinforcement Work
12mm high yield bars for partial slabs 200 lengt. 11,200 2,240,000.00

12mm high yield bars for columns & bases 150 lengt. 11,200 1,680,000.00

8mm high yield bars as stirrups & reinforcement in concrete capping 100 lengt. 5,000 500,000.00

Labour for cutting, bending and fixing of reinforcements 0 Sum 0 1,000,000.00

CONCRETE WORK
Mix and place concrete 1:2:4-19mm aggregate as concrete for
partial slabs, columns and other associated concrete works
CEMENT (50 kg bags) 250 Bags 8,000 2,000,000.00

SAND (using 7ton tipper) 6 Trip 65,000 390,000.00

GRAVEL (using 30ton tipper - TRAILER Load) 3 Trip 800,000 2,400,000.00

Bolinkz AEC Consults NIG


Registered Quantity Surveyors $ Project Managers PAGE-1
COST ESTIMATES FOR fencing of 20 polts of land

S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT

LABOUR
For mixing of concrete 250 Bags 2,500 625,000.00

For tapping by mensons 25 Men 8,000 200,000.00

Formwork
Sawn treated softwood well fixed to meet required stability as
formwork for columns
1" x 12'' x 12'' plank 400 Nr 2,550 1,020,000.00

1” X 6” 12" PLANK 200 Nr 1,950 390,000.00

2” X 2” x 12" TIMBER AS RUNNERS 150 Nr 600 90,000.00

BAMBOO AS PROPS 100 Nr 700 70,000.00

2'', 3” NAIL 10 Bag 33,450 334,500.00


LABOUR
Labour for fixing and striping of formwork Sum 1,000,000.00

TOTAL FOR STRUCTURAL WORKS 47,019,500.00

Bolinkz AEC Consults NIG


Registered Quantity Surveyors $ Project Managers PAGE-2
COST ESTIMATES FOR fencing of 20 polts of land

S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT

FINISHES
M Surface Finishes
M20 PLASTERED/RENDERED/ROUGH CAST COATINGS
25mm thick cement and sand 1:4 rendering on walls both
externally and internally
CEMENT (using 50kg bag) 450 Bags 8,000 3,600,000.00

SHARP SAND ( using 7 ton tipper) 20 Trip 65,000 1,300,000.00

SOFT PLASTER SAND ( using 7 ton tipper) 10 Trip 70,000 700,000.00

Labour for manson and helper (10.8m2 per pertition)


550 Parts 7,500 4,125,000.00
plastering to walls

FINISHES TO FENCE 9,725,000.00

Bolinkz AEC Consults NIG


Registered Quantity Surveyors $ Project Managers PAGE-3
COST ESTIMATES FOR fencing of 20 polts of land

S/N DESCRIPTION OF ITEM QTY UNIT RATE AMOUNT

SUMMARY OF FENCING WORK

Structural Works 47,019,500.00

Finishes 9,725,000.00

Subtotal 1 56,744,500.00

5.00% 2,837,225.00
Allow a sum to cover for preliminary works and contingency

Subtotal 2 59,581,725.00

ALLOW 10% TO COVER FOR CONTRACTOR'S


10% 5,958,172.50
ENGINEERING FEE, PROFIT AND OVERHEAD

Allow a lumpsum to cover for construction of a self contained


Sum 15,000,000.00
storey building security house

TOTAL COST FOR CONSTRUCTION OF FENCE 80,539,897.50

Bolinkz AEC Consults NIG


Registered Quantity Surveyors $ Project Managers PAGE-4

You might also like