Project Scheduling-Aug 28
Project Scheduling-Aug 28
Time Management
Introduction
Any project involves planning, scheduling and controlling a
number of interrelated activities with use of limited resources,
namely, men, machines, materials, money and time.
4
Activity Lists and Attributes
5
Milestones/Events
• A milestone is a significant event that normally has no duration.
• Milestones are useful tools for setting schedule goals and monitoring
progress.
6
Activity Sequencing
7
Network Diagrams
8
Arrow Diagramming Method (ADM)
9
Network Diagramming Techniques
A convenient analytical and visual technique of PERT and
CPM prove extremely valuable in assisting the managers
in managing the projects.
Event: An event (or node) will always occur at the beginning and end of an
activity. The event has no resources and is represented by a circle. The ith
event and jth event are the tail event and head event respectively.
Merge and Burst Events
An imaginary activity which does not consume any resource and time is
called a dummy activity. Dummy activities are simply used to
represent a connection between events in order to maintain a logic in
the network. It is represented by a dotted line in a network.
ERRORS TO BE AVOIDED IN CONSTRUCTING A NETWORK
2. The event numbered 1 is the start event and an event with highest
number is the end event. Before an activity can be undertaken, all
activities preceding it must be completed. That is, the activities must
follow a logical sequence (or – interrelationship) between activities.
5. A network should have only one start event and one end event.
Some conventions of network diagram are shown in Figure (a),
(b), (c), (d) below:
Example1: Sequence of activities of a house building
project
Solution :
The network diagram shows the procedure
relationship between the activities. Activity A
(preparation of house plan), has a start event 1 as
well as an ending event 2. Activity B (Construction
of house) begins at event 2 and ends at event 3. The
activity B cannot start until activity A has been
completed. Activities C and D cannot begin until
activity B has been completed, but they can be
performed simultaneously. Similarly, activities E
and F can start only after completion of
activities C and D respectively. Both activities E
and F finish at the end of event 6.
Example 2: Consider the project given in Table
and construct a network diagram: Sequence
of Activities for Building Construction Project
Solution:
The activities C and D have a common predecessor A. The network
representation shown in Figure (a), (b) violates the rule that no two activities can
begin and end at the same events. It appears as if activity B is a predecessor of
activity C, which is not the case. To construct the network in a logical order, it is
necessary to introduce a dummy activity.
EXAMPLES OF THE USE OF DUMMYACTIVITY
Network concurrent activities
a
a 2
1 2 1 Dummy
b 3
b
WRONG!!! RIGHT ✓
a precedes d.
a and b precede e,
b and c precede f (a does not precede f)
WRONG!!! RIGHT!!!
a d a 1 d
1
b e b 2
2 4 e
c f c 3 f
3
a precedes d.
a and b precede e,
b and c precede f (a does not precede f)
The critical path for any network is the longest path through the entire
network.
If the project has to be completed ahead of the schedule, then the time
required for at least one of the critical activity must be reduced.
Further, any delay in completing the critical activities will increase the
project duration.
The activity, which does not lie on the critical path, is called
non-critical activity.
Activity
1
t = expected activity
time
7
4
1 6
Activity
2
LF = latest finish time
LS = latest start time
D[5,8] 5
2 3[7,10]
7
4
1 6
2
ES LS EF EF
5 8 9 12
LF-EF = 12 –9 =3
LS-ES = 8 – 5 = 3
LF-ES-t = 12-5-4 = 3
A - 23
Earliest Event Time
B - 8
C - 20
D A 16
E A 24
F B.D 18
G C 19
H B, D, G 4 E G(19) E
I F,G 10 2 5
L L H(4)
C(20)
D1
D2
0
B(8) E F(18) E
1 E I(10)
0 4 6 7
L L
L
A(23)
D(16)
E(24)
E
3
L
E G(19) E
2 L
5 L H(4)
C(20)
D1
D2
0 B(8) E F(18) E I(10) E
1 0 4 L 6 7 L
L
A(23)
D(16)
E(24)
E
3 L
Determination of Earliest Event Time of Event
Start from the 1st Event i.e. Start of the Project. The Earliest Event time for it = 0
Consider the next event 2.
Consider all activities terminating at that event i.e. C. C starts at event 1 and
requires 20 days. For event 2 occur activity C has to be completed. Hence event 2
can occur only after the time event 1 has occurred and after C is completed
i.e after 0 + 20 days = 20 days
Similarly event 3 will occur after event 1 has occurred and activity A is completed
i.e. after 0 +23 days = 23 days
For event 4 to occur we need to complete activities B and D. The earliest that
event 4 can occur is after the completion of activity B and D. i.e. Maximum of (0 +
8), (23 + 16) = 39 days
20 39, 39
20 G(19) 39
2 5
L L H(4)
C(20)
D1
8,39 D2
43, 67, 47
0 39, 57
B(8) F(18)
39 67
57 I(10)
1
0 4 6 7
L L
L
A(23)
D(16)
E(24)
23
23
3
L
Hence earliest completion of Project time
is 67 days