CONSTRUCTION PROJECT GANTT CHART
PROJECT NAME PROJECT LOCATION START DATE
Project Beta 10/01/27
PROJECT MANAGER 423 Main St, Springfield, CA 90210 END DATE
Josh K. 06/01/28
TIMELINE
START END DURATION
TASK NAME 09/20/27 11/09/27 12/29/27 02/17/28 04/07/28 05/27/28
DATE DATE in days
Demolition 10/06/27 10/24/27 19 Demolition
Roof 11/19/27 12/10/27 22 Roof
Plumbing 10/29/27 12/09/27 42 Plumbing
Windows 11/22/27 12/15/27 24 Windows
Electrical 12/10/27 12/22/27 13 Electrical
House wrap 12/27/27 12/30/27 4 House wrap
Plumbing -hang sinks 02/16/28 02/23/28 8 Plumbing -hang sinks
Interior painting 02/28/28 04/14/28 47 Interior painting
FINAL Inspections 05/02/28 05/02/28 1 FINAL Inspections
Wrap up 05/09/28 05/29/28 21 Wrap up
House Cleaning 05/27/28 05/30/28 4 House Cleaning
Complete 06/01/28 06/01/28 1 Complete