0% found this document useful (0 votes)
7 views13 pages

Example No 01

Detailed Estimation QSEV
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
7 views13 pages

Example No 01

Detailed Estimation QSEV
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 13

Example No 1

Figure shows a plan of building and section of wall.

Calculate the quantities of following given below and enter them in standard measurement sheet
1. Excavation for foundation
2. PCC bed in cement concrete 1:4:8 below foundation
3. UCR masonry in foundation and plinth in cement mortar 1:6
4. DPC in cement concrete 1:2:4
5. BBM in super structure in cement mortar 1:4
6. External plaster in cement mortar 1:6
7. RCC slab in cement concrete 1:2:4
8. Wood work in doors and window frames
9. Plinth filling materials
Assume horizontal wall as long wall and vertical wall as short wall.
L1= (0.15+3+0.15) + (0.15+3.2+0.15) = 6.8m…………. (No=2)
L2= (0.15+4.6+0.15) = 4.9m……………………………. (No=1)
S1= (0.15+3.3+0.15) = 3.6m……………………………. (No=5)
S.N PARTICULARS NO. LENGTH BREADTH DEPTH QUANTITY REMARK
Excavation in soft murum in
foundation lift , including
dewatering etc
For long wall

1
6.8+0.9=7.7 2 7.7 0.9 1 13.86
4.9+0.9=5.8 1 5.8 0.9 1 5.22
For short wall
3.6-0.9=2.7 5 2.7 0.9 1 12.15
TOTAL 31.23
PCC bed below foundation
15cm 1:4:8 with providing
and laying , compacting ,
curing etc complete

For long wall


2
6.8+0.9=7.7 2 7.7 0.9 0.2 2.772
4.9+0.9=5.8 1 5.8 0.9 0.2 1.044
For short wall
3.6-0.9=2.7 5 2.7 0.9 0.2 2.43
TOTAL 6.246
U.C.R masonry in
foundation and plinth in
C.M(1:6) with mixing ,
dressing , curing etc
complete

1st footing
For long wall
6.8+0.6=7.4 2 7.4 0.6 0.7 6.216
3
4.9+0.6=5.5 1 5.5 0.6 0.7 2.31
For short wall 0
3.6-0.6=3 5 3 0.6 0.7 6.3
nd
2 footing
For long wall
6.8+0.5=7.3 2 7.3 0.5 0.9 6.57
4.9+0.5=5.4 1 5.4 0.5 0.9 2.43
For short column 0
3.6-0.5=3.1 5 3.1 0.5 0.9 6.975
TOTAL 30.801
D.P.C in C.C 1:2:4 providing
and laying , compacting ,
curing etc
For long wall
6.8+0.5=7.3 2 7.3 0.5 7.3
4.9+0.5=5.4 1 5.4 0.5 2.7
4
For short wall
4

3.6-0.5=3.1 5 3.1 0.5 7.75


TOTAL 17.75
Deduction for Openings
Doors 3 1 0.5 1.55
NET QUANTITY 16.2
B.B.M in superstructure in
C.M 1:4 with formwork ,
curing etc
For long wall
= L1+0.3=7.1m 2 7.1 0.3 3.1 13.206
= L2+0.3=5.2m 1 5.2 0.3 3.1 4.836
For short wall
= S1-0.3=3.3m 5 3.3 0.3 3.1 15.345
5 TOTAL 33.387
Deduction for Openings
Doors 3 1 0.3 2.1 1.89
window 7 1.1 0.3 1.3 3.003
Deductions of Lintels
Over door 3 1.3 0.3 0.15 0.1755
Over window 7 1.4 0.3 0.15 0.441
Total Deductions 5.510
Net quantity 33.387-5.510=27.877
External plaster in C.M (1:6)
with mixing , placing ,
formwork , curing

L=(7.1+7.5)x2=29.2 1 29.2 _ 3.1 90.528 sq.m


6
Deductions for opening
6

doors 1.5 1 _ 2.1 3.15


windows 3.5 1.1 _ 1.3 5.005
Total Deductions 8.155
Net quantity 90.52-8.155=82.36
R.C.C slab in C.C 1:2:4 with
bending binding , mixing ,
placing , curing etc
7 A1=7.5x5.2=39
A2=1.9x3.9=7.41
Area=
A=A1+A2=46.41 1 0.15 6.962
46.41
Woodwork in doors and
window shutter

8
For Door L=1+2*2.1 3 5.2 0.1 0.08 0.1248
For Window
L=2*1.1+2*1.3=4.8
7 4.8 0.1 0.08 0.2688
Total 0.3936
Plinth filling material in
plinth for living room
L=4.6-2x Plinth offset=4.6-
2x0.1=4.4m 1 4.4 3.1 0.6 8.184
B=3.3-2x0.1=3.1m
For bedroom
9 L=3.2-2x0.1=3 1 3 3.1 0.6 5.58
B=3.3-2x0.1=3.1
For kitchen
L=3-2x0.1=2.8m 1 2.8 3.1 0.6 5.208
B=3.3-2x0.1=3.1m
Total 18.972
PLINTH OFFSET= (WIDTH OF PLINTH - WIDTH OF WALL)/2

Center Line Method


Total C/C length :T.L= (6.8x2)+(4.9x1)+(3.6x5)
36.5
Number of T Junction :n= 4
S.N PARTICULARS NO. LENGTH BREADTH DEPTH QUANTITY REMARK
Excavation in soft murum in
foundation lift , including
1 dewatering etc
L=T.L - 1/2x4x0.9
34.7 1 34.7 0.9 1 31.23 cu.m
PCC bed below foundation
15cm 1:4:8 with providing
2 and laying , compacting ,
curing etc complete
L=T.L - 1/2x4x0.9 = 34.7 1 34.7 0.9 0.2 6.246
U.C.R masonry in
foundation and plinth in
C.M(1:6) with mixing ,
dressing , curing etc
3 complete
L=36.5 - 1/2x4x0.6 = 35.3 1 35.3 0.6 0.7 14.826
Plinth footing
L=T.L - 1/2x4x0.5 = 35.5 1 35.5 0.5 0.9 15.975
total 30.801
D.P.C in C.C 1:2:4 providing
and laying , compacting ,
curing etc
4 L=36.5 - 1/2x4x0.5 = 35.5 1 35.5 0.5 0 17.75
Deduction for Openings
4

Doors 3 1 0.5 1.5


NET QUANTITY 17.75-1.5=16.25
B.B.M in superstructure in
C.M 1:4 with formwork ,
curing etc
L=T.L - 1/2x4x0.3 = 35.9 1 35.9 0.3 3.1 33.387
Deduction for Openings
Doors 3 1 0.3 2.1 1.89
5 window 7 1.1 0.3 1.3 3.003
Deductions of Lintels
Over door 3 1.3 0.3 0.15 0.1755
Over window 7 1.4 0.3 0.15 0.441
Total Deductions 5.510
Net quantity 33.387-5.510=27.877

Note 1. Quantity of other items can be calculated in similar way as it is calculated in L/W & S/W
2. center line method is used to calculate quantity of above 5 items