Overhead Analysis
Overhead Analysis
Overhead Analysis
Woventex Ltd operates a factory which consists of two production cost centres namely
Machining and Finishing. Within the factory is located two service cost centres, namely
Stores which is responsible for material procurement and maintenance which provide
machine maintenance facilities to the production cost centre.
Shown below are next year’s budgeted overhead costs for the company:
Production Total Machining Finishing Stores Maintenance
overheads Rs Rs Rs Rs Rs
Indirect wages 100,000 45,000 35,000 15,000 5,000
Indirect materials 30,000 10,000 8,000 7,000 5,000
Overhead Analysis 1 of 13
REQUIRED:
(a)
a) ) Prepare an overhead analysis sheet showing the allocation and apportionment of
overheads to each production cost centre clearly showing the bases of
apportionment used. (10 marks)
(ii) Calculate an appropriate overhead absorption rate for both Machining and
Finishing cost centre, explaining the relevance of the basis used. (4 marks)
(iv) On the assumption that actual activity during a particular period was:
Machining 50,000 machine hours
Finishing 30,000 labour hours
For the same period, actual overheads incurred by each cost centre was:
Machining Rs135,000
Finishing Rs75,000
CALCULATE:
(b) (i) Overheads absorbed by Machining and Finishing cost centres. (3 marks)
(c) What is Activity Based Costing and how it differs from Traditional
product costing methods? (6 marks)
(d) List the main differences between Financial Accounting and Cost and
Management Accounting. (4 marks)
Overhead Analysis 2 of 13
QUESTION 2: (30 MARKS)
Common costs:
Electricity 9,000
Supervision 3,000
Insurance of building 15,750
Insurance of plant 11,000
Depreciation of plant 5,500
National Pension Scheme 4,200
Building security 5,625
Other information:
Total Machining Assembly Stores Maintenance
Floor area (sq. Ft) 4,500 2,000 1,500 450 550
Plant Value (Rs’000) 220 100 80 15 25
No of employees 200 50 130 10 10
No. of requisitions 2,500 1,500 700 - 300
Maintenance hours 1,500 900 600 - -
Labour hours 8,000 2,000 6,000 - -
Machine hours 10,000 7,500 2,500 - -
Overhead Analysis 3 of 13
REQUIRED:
(a) Prepare a statement to show the total overheads for each production department
showing the basis of apportionment selected. (11 marks)
(b) Calculate an appropriate overhead absorption rate for Machining and Assembly
department, explaining the relevance of the basis used. (3 marks)
(c) Calculate the budgeted manufacturing overhead cost per unit of product A if it uses
4kgs of material at Rs5/kg, 3 labour hours at Rs2/hour and the estimated cost of
product A if 2 machine hours and 1.5 labour hours is required for processing.
(3 marks)
(d) The Machining department was in operation for 2,500 hours and the no. of direct
labour hours worked by the Assembly department was 1,200. For the same period,
overheads incurred were as follows:
Machining Rs 35,000 Assembly Rs20,000
CALCULATE:
(i) Overheads absorbed by Machining and Assembly departments
respectively. (3 marks)
(ii) Over/under absorbed overheads for each department. (6 marks)
Overhead Analysis 4 of 13
QUESTION 3: (40 MARKS)
The three production departments – A, B and C, and the two service departments – X
and Y, are housed in the new premises, the details of which, together with other statistics
and information, are given below:
Departments
A B C X Y
REQUIRED:
(a) Prepare a statement showing the overhead cost budgeted for each department,
showing the basis of apportionment used. Also calculate suitable overhead
absorption rates. (20 marks)
Overhead Analysis 5 of 13
(b) Two pieces of furniture are to be manufactured for customers. Direct costs are as
follows:
Job 123 Job 124
Calculate the total cost and selling price for Job 124, using a margin of 20%
(6 marks)
(c) Assume that the actual fixed overhead cost of the Department A totals Rs 30,000
and that the actual labour hours were 3,700.
Calculate any over-/under absorption for Department A. Explain briefly the
possible causes for your answer. (6 marks)
Overhead Analysis 6 of 13
QUESTION 4: (40 MARKS)
Sam Limited has three production departments, Forming, Machining and Assembly,
and two service departments, Maintenance and General. During the past years, the
following departmental overhead absorption rates have been in use:
Overheads are absorbed on the basis of direct labour hours for the forming and
assembly departments, and on machine hours for the machining department.
Rs. Rs
Rent and Rates 16,000
Power 15,000
Repairs and maintenance
Forming 1,600
Machining 3,600
Assembly 600
Maintenance 400
General 200 6,400
Departmental expense
Forming 3,000
Machining 4,600
Assembly 2,200
Maintenance 1,800
General 3,000 14,600
Depreciation
Plant 10,000
Fixtures 15,750
Insurance-Plant 4,000
81,750
Overhead Analysis 7 of 13
Other data is available as follows:
Forming Machining Assembly Maintenance General Total
Floor Area (sq
Ft) 2,000 4,000 3,000 500 500 10,000
Plant Value 25,000 60,000 7,500 7,500 - 100,000
Fixtures and
fittings 1,000 500 2,000 1,000 500 5,000
Power 40 90 15 5 - 150
Budgeted
direct labour
hours - -
10,000 18,000 20,000 48,000
Budgeted
machine - -
hours 5,000 25,000 2,000 32,000
Actual direct
labour hours 10,500 20,000 19,500 50,000
Actual
machine
hours 6,000 23,000 1,800 30,800
REQUIRED:
Required:
Calculate the overhead absorption rates for each machine hour and each direct
labour hour for the three production units. You should use bases of apportionment
and absorption which you consider most appropriate, and the bases used should be
clearly indicated in your statement. (15 marks)
Overhead Analysis 9 of 13
QUESTION 6: (40 MARKS)
Water-mount Ltd is a textile company which operates two production cost centres
Assembly and finishing and two service cost centres namely maintenance and
canteen. Budgeted data is provided below:
Further information:
The maintenance service centre provides 3,000 hours to the Assembly Department
and 5,000 hours to Finishing Department.
Required:
Overhead Analysis 10 of 13
(c) Suppose that the company used 65,000 machine hours incurring Rs850,000
of overheads in the Assembly department and consumed 43,000 labour
hours in the Finishing department incurring Rs720,000 of overheads.
(d) A special order known as job number 21BX will incur the
following costs:
(e) Briefly explain two differences between Absorption costing and Activity based
costing. (4 marks)
(f) Discuss the difficulties that businesses may face in implementing ABC.
(6 marks)
Overhead Analysis 11 of 13
QUESTION 7: (40 MARKS)
PART A: (30 MARKS)
Steel manufacturer’s Ltd operates a factory which consists of three production departments, namely
Machining, Finishing and Assembly. Within the factory is located two service departments, namely
Stores and Machine maintenance which provide support facilities to the production departments.
Shown below are next year’s budgeted overhead costs for the company:
Rs Rs Rs Rs Rs Rs
Floor area (sq. Ft) 25,000 5,000 6,000 8,000 2,000 4,000
Value of Plant (Rs 000) 150 60 45 15 6 24
Horse power 100 50 30 15 - 5
No. of employees 100 40 30 15 10 5
No. of requisitions 17,500 6,000 9,000 2,000 - 500
Maintenance hours 1,200 500 400 300 -
Labour hours 55,000 20,000 10,000 25,000 -
Machine hours 85,000 40,000 45,000 - -
Overhead Analysis 12 of 13
Required:
(a) Prepare an overhead analysis sheet showing the allocation and apportionment of overhead
to the five cost centres and apportion the service cost centres’ overheads to the three
production cost centres, clearly indicating the basis of apportionment. You should rewrite
the format of the table in your answer booklet. (17 marks)
(b) Calculate suitable overhead absorption rates for Machining, Finishing and Assembly
department, explaining the relevance of the basis used. (3 marks)
(c) Calculate the overhead to be absorbed by product PK, with cost sheets showing the
following times spent in different production departments:
(d) Calculate the full production cost of product PK if costs incurred were as following: Direct
material Rs15 and Direct labour Rs10. (2 marks)
(e) The Machining department was in operation for 7,000 hours and the number of direct labour
hours worked by the Finishing and Assembly departments were 3,000 and 5,000 hours
respectively. For the same period, overheads incurred were as follows: Machining
Rs95,000, Finishing Rs30,000 and Assembly Rs50,000.
Calculate the extent of any over/(under) overheads absorbed by the production cost centres.
(3 marks)
(a) Explain briefly two differences between financial and cost/management accounting
(4 marks)
(b) Briefly explain why ABC costing is preferred to traditional absorption costing in
assessing management performance (6 marks)
Overhead Analysis 13 of 13