2 - TNB Fuel Services SDN BHD V China National Coal Group Corp
2 - TNB Fuel Services SDN BHD V China National Coal Group Corp
2 - TNB Fuel Services SDN BHD V China National Coal Group Corp
The appellant had called for tenders for long term supply of coal. The
respondent submitted its bid which included: a duly completed bid form to
E supply coal for 15 years; a bid bond in the sum of RM500,000; and technical
proposals for the supply of the coal. The appellant accepted the respondent’s
bid and issued a letter of acceptance which laid out terms of award. The
respondent accepted the terms of the award and caused Standard Chartered
Bank to furnish a pre-commencement bond for the amount of RM1m in
F favour of the appellant. However, the respondent then failed to supply the coal
that it had promised the appellant for the said project citing changes in the
policy of the Government of China. The appellant’s response was to serve a
notice of arbitration on the respondent. This caused the respondent to apply by
way of originating summons (‘the first OS’) to the High Court for a declaration
G that no arbitration agreement existed between the parties. It also applied and
obtained an ex-parte injunction order restraining the appellant from
proceeding with the arbitration proceedings. The ex-parte order was then
confirmed inter-partes after arguments before the High Court judge. While the
appellant’s appeal to the Court of Appeal against the injunction order was
H pending, the first OS was struck off when the respondent failed to comply with
an order for security for costs. Following the dismissal of the first OS, the
arbitral tribunal was fully-constituted. The respondent then filed an identical
originating summons (‘the second OS’) in the High Court seeking similar
orders as in its previous action and also an injunction application to once again
I injunct the arbitration proceedings. On the other hand, the appellant filed a
stay application under s 10 of the Arbitration Act 2005 (‘the Act’) to stay the
respondent’s action in favour of arbitration. The appellant and the respondent
attended the preliminary meeting fixed by the arbitral tribunal (‘the Tribunal’).
The respondent informed the Tribunal that it was challenging the jurisdiction
858 Malayan Law Journal [2013] 4 MLJ
of the Tribunal to hear the dispute that was brought to arbitration by the A
appellant. The Tribunal agreed to hear the respondent’s jurisdictional challenge
as a preliminary issue. Directions were given by the Tribunal for parties to
exchange pleadings and witness statements on the preliminary issue. A hearing
date for the preliminary issue was fixed but the respondent obtained an
ad-interim injunction before the High Court judge pending the hearing of the B
respondent’s injunction application. As a result, the preliminary issue before
the Tribunal was never heard. The respondent’s injunction application was
granted and the stay application was dismissed. This appeal was against the
judgment of the Court in allowing the injunction and refusing stay.
C
Held, allowing the appeal with costs of RM15,000:
(1) Section 9 of the Act had introduced a significant change as regards the
existence of an arbitration agreement. This change was the result of the
expansion in the meaning of the words arbitration agreement between D
the Arbitration Act 1952 and the Act. Applying the new definition of
arbitration agreement to the facts of this case, the application for the
injunction in the second OS ought to have been determined based on an
examination of all the documents exchanged between the parties to
determine whether there was an agreement in writing and whether there E
was sufficient reference in this agreement to the document containing the
arbitration agreement so as to entitle the court to conclude that the
arbitration agreement formed part of the agreement between the parties.
The High Court judge considered the merits of the respondent’s
application for the injunction on the basis of the Arbitration Act 1952 F
and not the Act, which ought to have been the case (see paras 18–20).
(2) The trial judge erred in not considering the application for the injunction
on the basis of sub-s 9(5) of the Act. The fact of the matter was that the
exchange of documents between the parties which included the bid form
and supporting bid bond from the respondent, the letter of award by the G
appellant and the letter from the respondent confirming acceptance of
the terms in the letter of award constituted the requisite offer and
acceptance thereby creating a binding contract. This contract, in turn,
incorporated the terms of the unsigned coal purchase contract thereby
incorporating by reference the arbitration agreement in this document H
(see para 21).
(3) If the trial judge had applied s 9(5) of the Act to these facts, she would
have come to the conclusion that the arbitration agreement was binding
on the parties. In any event, the trial judge entertained any doubts I
concerning the existence of the arbitration agreement, she ought to have
leaned in favour of refusing the injunction so as to enable this
jurisdictional issue to be determined by the arbitral tribunal (see para 21).
(4) The trial judge erred in failing to appreciate that the balance of
TNB Fuel Services Sdn Bhd v China National Coal Group
[2013] 4 MLJ Corp (Anantham Kasinather JCA) 859
A convenience was also in favour of the appellant. At the time of the hearing
of the injunction application, the arbitral tribunal was fully-constituted
and ready to hear the respondent’s jurisdictional challenge. The tribunal
already held the meeting to discuss the issue of the respondent’s objection
to the tribunal’s jurisdiction and a preliminary meeting already having
B been directed on this issue for hearing. This hearing did not proceed
because of the respondent having obtained the ad interim injunction (see
para 22).
(5) The order of the High Court granting the injunction restraining the
C appellant from proceeding with the arbitration proceedings was set aside.
The order of the High Court refusing a stay of the pending arbitration
proceedings was also set aside. The court ordered further proceedings in
the second OS be stayed pursuant to s 10 of the Act (see para 24).
Notes
F For cases on grant of stay of proceedings, see 1(1) Mallal’s Digest (4th Ed, 2012
Reissue) paras 1963–1964.
Cases referred to
Albilt Resources Sdn Bhd v Casaria Construction Sdn Bhd [2010] 3 MLJ 656;
G [2010] 7 CLJ 785, CA (refd)
CMS Energy Sdn Bhd v Poscon Corp [2008] 6 MLJ 561, HC (folld)
Dell Computer Corporation v Union des consommateurs [2007] 2 SCR 801;
2007 SCC 34, CA (refd)
Tjong Very Sumito and others v Antig Investments Ptd Ltd [2009] 4 SLR 732, CA
H
(refd)
Legislation referred to
Arbitration Act 2005 ss 6, 8, 9, 9(5), 10, 10(1), 18, 18(1)
I
Appeal from: Originating Summons No 24–1925 of 2011 (High Court, Shah
Alam)
Mohan Kanagasabai (Sheena Babu with him) (Mohanadass Partnership) for the
appellant.
862 Malayan Law Journal [2013] 4 MLJ
Wong Kah Hui (Chan Yee Chong and Kuah Jiun Yin with him) (Jeff Leong, Poon A
& Wong) for the respondent.
BACKGROUND FACTS
[1] In 2002, the appellant called for tenders for the long term supply of coal C
for its Tanjung Bin Power Project. The tender documentation provided to the
respondent included the proforma coal purchase contract, bid form, and form
of bid bond.
[2] On or about 4 December 2012, the respondent submitted its bid which D
included:
(a) a duly completed bid form to supply coal for 15 years. This form was
signed by the respondent’s deputy managing director, Mr Pan Wanze;
(b) a bid bond dated 2 December 2002, issued jointly by Standard Chartered E
Bank (M) Bhd and the respondent in the sum of RM500,000; and
(c) technical proposals for the supply of the coal.
[3] The joint bid bond submitted by the respondent was signed by one F
William Randall who was the lawful attorney of the respondent, pursuant to a
power of attorney issued by the respondent on 26 November 2002 duly
notarised in Hong Kong. This power of attorney authorised Randall to
negotiate a contract on behalf of the respondent to supply coal to the appellant.
G
[4] The appellant accepted the respondent’s bid and issued a letter of
acceptance dated 18 November 2003 which included, inter alia, the following
terms:
H
(a) that the terms and conditions of the supply shall be in accordance with
the proforma coal purchase contract;
(b) the respondent to provide a bond for the due and proper performance of
the contract;
I
(c) the respondent to appoint a local agent; and
(d) the respondent to acknowledge acceptance of the terms and conditions in
the letter of acceptance within 14 days of the receipt of the letter of
acceptance.
TNB Fuel Services Sdn Bhd v China National Coal Group
[2013] 4 MLJ Corp (Anantham Kasinather JCA) 863
A [5] By its letter of 18 December 2003 signed by one Zhou Dongzhou, the
respondent accepted the terms of the award and at the same time appointed a
company known as Fasa Galian Sdn Bhd, represented by its attorney William
Randall and one PC Yong, as its local agent. After accepting the award of the
contract, the respondent caused Standard Chartered Bank to furnish a
B pre-commencement bond dated 15 March 2004 for the amount of RM1m in
favour of the appellant. Standard Chartered Bank confirms on the face of this
bond that it was issued ‘on behalf of and at the request of our client, China
National Coal Group Corp’ ie the respondent. This pre-commencement bond
was extended twice by the respondent. Both extensions included reference to
C the extensions having been effected at the request of the respondent.
[7] The ex parte order was then confirmed inter partes after arguments
F before YA Dato’ Zaleha bt Yusof on 29 July 2010. While the appellant’s appeal
to the Court of Appeal against the injunction order was pending, the first OS
was struck off when the respondent failed to comply with an order for security
for costs. Following the dismissal of the first OS, the arbitral tribunal was fully
constituted on 12 July 2011. The respondent then filed a virtually identical
G originating summons in the High Court of Shah Alam on 27 July 2011 (OS
24–1925 of 2011 — ‘the second OS’) seeking similar orders as in its previous
action and also an injunction application (encl 3) to once again injunct the
arbitration proceedings. The appellant on the other hand filed a stay
application (encl 13) under s 10 of the Act to stay the respondent’s action in
H favour of arbitration.
[8] The appellant and the respondent attended the preliminary meeting
fixed by the arbitral tribunal on 24 August 2011. The respondent informed the
Tribunal that it was challenging the jurisdiction of the tribunal to hear the
I dispute that was brought to arbitration by the appellant. The tribunal agreed to
hear the respondent’s jurisdictional challenge as a preliminary issue. Directions
were given by the tribunal for parties to exchange pleadings and witness
statements on the preliminary issue. A hearing date for the preliminary issue
was fixed from 12–16 December 2011. However, on 25 August 2011, the
864 Malayan Law Journal [2013] 4 MLJ
[10] In connection with the appellant’s tender for the long term supply of
coal, the following documents were exchanged between the appellant and the
respondent. The tender notice, bid form, the supporting bid bond from the
D
respondent, the letter of award of the appellant and the letter from the
respondent confirming acceptance of the terms in the letter of award. The
tender notice included amongst its documents the proforma coal purchase
contract. The arbitration clause or the ‘arbitration agreement’ in turn was
included in the unsigned proforma coal purchase contract. Learned counsel for
E
the appellant submitted that notwithstanding that the proforma coal purchase
contract was unsigned, a binding contract had come into existence and the
arbitration clause or agreement binding on the parties by virtue of the
operation of s 9(5) of the Arbitration Act 2005 (‘the Act’).
F
[11] In support of learned counsel’s reliance on s 9(5) of the Arbitration Act
2005 (‘the Act’), we were referred to the passage in the judgment of this court
in Albilt Resources Sdn Bhd v Casaria Construction Sdn Bhd [2010] 3 MLJ 656;
[2010] 7 CLJ 785 that:
Section 9(5) of the Arbitration Act 2005 (‘the Act’) provides for the incorporation of G
an arbitration clause in a document into an agreement to constitute the latter as an
arbitration agreement to which the Act shall apply. This is known as incorporation
by reference. … It is clear from a reading of the above provision that the agreement
itself need not have arbitration clause in it as long as the agreement refers to an
arbitration clause in another document and the agreement is in writing and the H
reference incorporates the said clause into the agreement, (at p 674(MLJ); pp
805–806 (CLJ)).
[12] Learned counsel for the appellant then proceeded to refute the
allegation of the respondent contained in the affidavit of one Zhou Li that the I
respondent had no knowledge of this transaction with the appellant and that
the signature of Zhou Dongzhou on its letter of 18 December 2003 was a
forgery. In this respect, learned counsel for the appellant highlighted that
notwithstanding that the respondent had lodged a report on 2 February 2010,
TNB Fuel Services Sdn Bhd v China National Coal Group
[2013] 4 MLJ Corp (Anantham Kasinather JCA) 865
[13] On the law, learned counsel for the appellant submitted that the courts
have leaned in favour of arbitration even when the ‘arbitration agreement’ was
D disputed. The rational for this being the availability of challenge to the
jurisdiction of the tribunal prior to the commencement of the proceedings.
Section 18 provides for jurisdictional challenge by allowing the arbitral
tribunal to decide on the ‘existence or validity of the arbitration agreement’. A
passage in the commentary of the Malaysian Arbitration Act 2005 by Sundra
E Rajoo and WSW Davidson to the following effect:
Section 18 deals with the issue of who is to decide on the arbitral tribunal’s
jurisdiction and corresponds with article 16 of the Model Law. It is one of the key
pillars of the Model Law. Like article 16, Section 18 sets out two general principles,
F namely the doctrines of Kompetenz-Kompetenz and separability. The remaining
parts of the section deal with the prescribed procedures for raising a plea of the
arbitral tribunal’s lack of jurisdiction, including the relevant time limits for raising it.
The last part of the section provides however, a plea is dealt with -initially by the
arbitral tribunal and later by the High Court which has the last word on the issue of
an arbitral tribunal’s jurisdiction.
G
was cited to us in support of this proposition.
[14] According to learned counsel for the appellant, Abdul Aziz J (as His
Lordship then was) in CMS Energy Sdn Bhd v Poscon Corp [2008] 6 MLJ 561
H made pronouncements to similar effect when His Lordship said:
Clearly therefore in this case one of the issues is the existence of the JV and whether
the defendant did execute the purported JV agreement … In my view these
questions may be posed to the arbitrator and the arbitrator is competent to answer
I them.
In my view the language used in ( Section 18(1) of the 2005 Act) confers on the
arbitration a broad and wide powers to decide on issues raised before it — not only
the substantive issues but also on the point of preliminary objections as to its
jurisdiction.
866 Malayan Law Journal [2013] 4 MLJ
[15] On the issue of stay, learned counsel for the appellant submitted that B
since our legislation on arbitration is pari materia with Canadian legislation,
our courts should have regard to precedents originating from that jurisdiction.
Pursuant thereto, we were referred by counsel to the case of Dell Computer Corp
v Union des consommateurs [2007] 2 SCR 801; 2007 SCC 34 ; [2007] SCJ No
34 where the court laid down the following principles and guidelines: C
[17] Learned counsel for the respondent then submitted that the pertinent
issue: ‘whether there was a signed and executed CPC’? has actually been
TNB Fuel Services Sdn Bhd v China National Coal Group
[2013] 4 MLJ Corp (Anantham Kasinather JCA) 867
A determined by Justice Dato’ Zaleha bt Yusof in ‘the first OS’, before the
identical issue was determined for the second time by Justice Hadariah bt Syed
Ismail in ‘the second OS’. Justice Zaleha had ruled that:
there is no proof that the parties have entered into a valid arbitration agreement.
B
Hadariah J adopted this reasoning in allowing the injunction application.
C Injunction application
In the 2005 Act, the same term has been defined in s 9 as follows:
9(1) In this Act, ‘arbitration agreement’ means an agreement by the parties to submit
to arbitration all or certain disputes which have arisen or which may arise between
F them in respect of a defined legal relationship, whether contractual or not.
(2) An arbitration agreement may be in the form of an arbitration clause in an
agreement or in the form of a separate agreement.
(3) An arbitration agreement shall be in writing;
G (4) An arbitration agreement is in writing where it is contained in —
(a) a document signed by the parties;
(b) an exchange of letters, telex, facsimile or other means of communication
which provide a record of the agreement; or
H (c) an exchange of statement of claim and defence in which the existence of an
agreement is alleged by one party and not denied by the other.
(5) A reference in an agreement to a document containing an arbitration clause shall
constitute an arbitration agreement, provided that the agreement is in writing and
I the reference is such as to make that clause part of the agreement.
that clause part of the agreement. The inclusion of the clause providing for A
arbitration to form part of the agreement can be said to be under the doctrine
of ‘incorporation by reference’. There are presently authorities originating from
Hong Kong, England and Canada where a clause providing for arbitration has
been held to give rise to an ‘arbitration agreement’ notwithstanding that the
document containing the clause was not signed by either party. In other words, B
the courts in these jurisdictions recognise that parties may enter into a valid
‘arbitration agreement’ by entering into a contract that incorporates by
reference to another document that provides for arbitration.
[21] With respect, in our judgment, the learned trial judge erred in not G
considering the application for the injunction on the basis of sub-s 9(5) of the
Arbitration Act 2005. The fact of the matter is that the exchange of documents
between the parties which included: the bid form and supporting bid bond
from the respondent, the letter of award by the appellant and the letter from the
respondent confirming acceptance of the terms in the letter of award H
constitutes the requisite offer and acceptance thereby creating a binding
contract. This contract, in turn, incorporated the terms of the unsigned coal
purchase contract thereby incorporating by reference the ‘arbitration
agreement’ in this document. Against these background facts, in our judgment,
if the learned trial judge had applied s 9(5) of the Act to these facts, we are of the I
considered opinion that Her Ladyship would have come to the conclusion that
the ‘arbitration agreement’ was binding on the parties. In any event, in our
opinion, even if Her Ladyship entertained any doubts concerning the existence
of the ‘arbitration agreement’, Her Ladyship ought to have leaned in favour of
TNB Fuel Services Sdn Bhd v China National Coal Group
[2013] 4 MLJ Corp (Anantham Kasinather JCA) 869
Stay application
10(1) A Court before which proceedings are brought in respect of a matter which is
the subject of an arbitration agreement shall, where a party makes an application
before taking any other steps in the proceedings, stay those proceedings and refer the
parties to arbitration unless it finds that the agreement is null and void, inoperative
or incapable of being performed. D
[24] The present form of s 10 of the Arbitration Act 2005 is the result of the
amendment to that section which came into force on 1 July 2011 (Act A1395).
It is generally accepted that the effect of the amendment is to render a stay E
mandatory unless the agreement is null and void or impossible of performance.
The court is no longer required to delve into the facts of the dispute when
considering an application for stay. Indeed, following the decision of the court
in CMS Energy Sdn Bhd v Poscon Corp, a court of law should lean towards
compelling the parties to honour the ‘arbitration agreement’ even if the court is F
in some doubt about the validity of the ‘arbitration agreement’. This is
consistent with the ‘competence principle’ that the arbitral tribunal is capable
of determining its jurisdiction, always bearing in mind that recourse can be had
to the High Court following the decision of the arbitral tribunal. In this
respect, we pause to observe that even the Singapore Court of Appeal in a very G
recent decision opined as follows on the question of stay:
… Woo J was quick to add this important caveat that if it was at least arguable that
the matter is the subject of the arbitration agreement, then a stay of proceedings
should be ordered. We agree with the measured approach taken by Woo J since the
question of whether a matter is the subject of an arbitration agreement is the very H
threshold to the application of s 6 of the IAA itself. However, it is only in the clearest
of cases that the court ought to make a ruling on the inapplicability of an arbitration
agreement.
(see the case of Tjong Very Sumito and others v Antig Investments Ptd Ltd [2009] I
4 SLR 732).
For the reasons contained herein and the provisions of s 8 of the 2005 Act
which states that ‘No court shall intervene in matters governed by this Act,
except where so provided in this Act’, we allowed both appeals. The order of the
TNB Fuel Services Sdn Bhd v China National Coal Group
[2013] 4 MLJ Corp (Anantham Kasinather JCA) 871
A High Court granting the injunction restraining the appellant from proceeding
with the arbitration proceedings is hereby set aside. The order of the High
Court refusing a stay of the pending arbitration proceedings is hereby set aside.
We hereby order further proceedings in Originating Summons No 24–1925 of
2011 be stayed pursuant to s 10 of the Arbitration Act 2005. The respondent
B is hereby ordered to pay costs of RM15,000 as costs here and below to the
appellant in respect of both appeals. The deposit is hereby refunded to the
appellant.