Project Presentation
Project Presentation
PROJECT PRESENTATION
AFNOR AUDIT
A. Organisation of the joint venture
Consulting Engineer :
Control : SYSTRA
Joint Venture :
Project duration:
67 months including 3 months at the beginning of the contract to decide on alternatives and 2 months for the EWP (Experimented Working
Period).
NAT
Consulting Engineer
G1 G2 G3 G4 G5 G6
Signalling,
telecommunication and
Civil Works, TBM, Power Supply -
Control Track works Rolling Stock Toll Equipment
Coordination Electromechanical
B. CAIRO METRO LINES
C. LINE 3 PHASE 3: GENERAL DESCRIPTION
Line 3 Phase 3
15 Stations:
8 Underground Stations
5 Elevated Stations
2 At grade Stations
A Diverting Box
7 Annexed Structures
Phase 3A CW 2 TBM Shafts
2 Cut & Cover structures
3 Ramps
C. LINE 3 PHASE 3: GENERAL DESCRIPTION
Line 3 Phase 3
Main quantities:
Phase 3A CW
C. LINE 3 PHASE 3: GENERAL DESCRIPTION
Warracq
Underground
Management Office
C. LINE 3 PHASE 3: GENERAL DESCRIPTION
3a 2b
4
Warracq
3b
2a
1 Cut & Bent area
4 Segment Storage
D. Phase 3 : Viaduct Section
D. Phase 3 : Viaduct Section
Concrete viaduct inside Elevated Stations (Example of El Bohy Station)
Benefits
• Erections of viaduct and station are independant
• No stop in the progress of launching girders through
stations
Constraints
• Marginal modifications of stations internal
arrangements
Merits
•Stations architectural signature maintained
• Functional areas maintained
• Reduced risk in construction time schedu
E. Phase 3 : Underground Station
Underground station : TOP DOWN Method
E. Phase 3 : Underground Station
Undergournd station phasing
E. Phase 3 : Underground Station
Undergournd station phasing
E. Phase 3 : Underground Station
Undergournd station phasing
E. Phase 3 : Underground Station
Undergournd station phasing
F. Phase 3 : Annexed Structure & bored Tunnel
D wall Box 1 &2 Planned Progress =100 % D wall Box 3 Planned Progress =100 % D wall Box 4 Planned Progress = 100 %
D Wall Box 1 & 2 Actual Progress = 0 % D Wall Box 3 Actual Progress =50% D Wall Box 4 Actual Progress = 95 %
G. Nasser Station - UG Station – Works Progress
G. Nasser Station - UG Station – Works Progress
G. Maspero Station - UG Station – Works Progress
G. Maspero Station - UG Station – Works Progress
G. Maspero Station - UG Station – Works Progress
G. Zamalek Station - UG Station – Works Progress